ML15236A007
| ML15236A007 | |
| Person / Time | |
|---|---|
| Site: | FitzPatrick |
| Issue date: | 08/21/2015 |
| From: | Chereskin A N Plant Licensing Branch 1 |
| To: | Azulay-Chasnoff J Alliance for a Green Economy |
| References | |
| Download: ML15236A007 (3) | |
Text
1 NRR-PMDAPEm Resource From: Chereskin, Alexander Sent: Friday, August 21, 2015 12:49 PM To: jessica@allianceforagreeneconomy.org
Subject:
RE: RE: GUNTER ET AL. 2.206 PETITIO N REQUESTING ENFORCEMENT ACTION AGAINST JAMES A. FITZPATRICK PLANTJessica, The meeting summary is located in ADAMS at accession number ML15197A333. The instructions for requesting the audio is located in ADAMS at accession number ML15197A327.
Thank you,
Alex Chereskin
From: jessica@allianceforagreeneconomy.org [1] Sent: Friday, August 21, 2015 12:44 PM To: Chereskin, Alexander <Alexander.Chereskin@nrc.gov>
Subject:
[External_Sender] RE: GUNTER ET AL. 2.206 PETITION REQUESTING ENFORCEMENT ACTION AGAINST JAMES A. FITZPATRICK PLANT
Alexander,
Thanks for checking in. I do not believe that I received the meeting summary or the instructions for requesting the audio. Could you please send those to me again?
Jessica
From: Chereskin, Alexander [mailto:Alexander.Chereskin@nrc.gov
] Sent: Friday, August 21, 2015 11:08 AM To: 'jessica@allianceforagreeneconomy.org' <jessica@allianceforagreeneconomy.org
>
Subject:
GUNTER ET AL. 2.206 PETITION REQUESTING ENFORCEMENT ACTION AGAINST JAMES A. FITZPATRICK PLANT Ms. Azulay, It has been almost 60 days since we have last been in contact and Nuclear Regulatory Commission (NRC) Management Directive (MD) 8.11, which governs the 10 CFR 2.206 Petitions, requires that the Petition Manager contact the petitioner(s), every 60 days regarding the status of the Petition. I want to check-in to ensure that you received a copy of the meeting summary of the June 29, 2015, meeting where the petitioners addressed the PRB. In addition, I want to ensure that you received a copy of the instructions on how to request the audio recording from the 6/29/15 meeting. You were listed on the CC list for both the meeting summary, and instructions to request the audio.
The PRB is currently reviewing the information provided during the 6/29/15 meeting in order to make a final recommendation on the petition.
Thank you, Alex Chereskin 2Project Manager NRR/DORL/LPL1-1 O-08 H18 Alexander.Chereskin@nrc.gov Office: (301) 415-2549 Cell: (631) 748-1726
Hearing Identifier: NRR_PMDA Email Number: 2329 Mail Envelope Properties (Alexander.Chereskin@nrc.gov20150821124900)
Subject:
RE: RE: GUNTER ET AL. 2.206 PETITION REQUESTING ENFORCEMENT ACTION AGAINST JAMES A. FITZPATRICK PLANT Sent Date: 8/21/2015 12:49:12 PM Received Date: 8/21/2015 12:49:00 PM From: Chereskin, Alexander Created By: Alexander.Chereskin@nrc.gov Recipients: "jessica@allianceforagreeneconomy.org" <jessica@allianceforagreeneconomy.org> Tracking Status: None
Post Office: Files Size Date & Time MESSAGE 2196 8/21/2015 12:49:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: