ML15299A084

From kanterella
Revision as of 14:18, 2 February 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search

PBAPS MELLLA License Amendment Request - Supplement 7 Revision Regarding Proposed Technical Specifications
ML15299A084
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 10/26/2015
From: Borton K F
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML15299A084 (5)


Text

U.S. Nuclear Regulatory Commission MELLLA+ License Amendment Request -Supplement 7 October 26, 2015 Page 2 Therefore, the requested deletion of SR 3.3.1.1.8 from the OPRM Upscale function 2f is withdrawn, and the SR will be retained in the Unit 2 and Unit 3 TS following MELLLA+ implementation.

Attachment 1 of this letter provides the affected markup Unit 2 and Unit 3 TS Page 3.3-7. There are no regulatory commitments contained in this letter. Should you have any questions concerning this letter, please call me at (610) 765-5528.

Respectfully, Kevin F. Borton Manager, Power Uprate Licensing Exelon Generation Company, LLC

Attachment:

1. Markup of Proposed Unit 2 and Unit 3 Technical Specifications Page 3.3-7 cc: USNRC Region I, Regional Administrator USNRC Senior Resident Inspector, PBAPS USNRC Project Manager, PBAPS R. R. Janati, Commonwealth of Pennsylvania S. T. Gray, State of Maryland w/attachment w/attachment w/attachment w/attachment w/attachment

U.S. Nuclear Regulatory Commission MELLLA+ License Amendment Request -Supplement 7 October 26, 2015 Page 2 Therefore, the requested deletion of SR 3.3.1.1.8 from the OPRM Upscale function 2f is withdrawn, and the SR will be retained in the Unit 2 and Unit 3 TS following MELLLA+ implementation.

Attachment 1 of this letter provides the affected markup Unit 2 and Unit 3 TS Page 3.3-7. There are no regulatory commitments contained in this letter. Should you have any questions concerning this letter, please call me at (610) 765-5528.

Respectfully, Kevin F. Borton Manager, Power Uprate Licensing Exelon Generation Company, LLC

Attachment:

1. Markup of Proposed Unit 2 and Unit 3 Technical Specifications Page 3.3-7 cc: USNRC Region I, Regional Administrator USNRC Senior Resident Inspector, PBAPS USNRC Project Manager, PBAPS R. R. Janati, Commonwealth of Pennsylvania S. T. Gray, State of Maryland w/attachment w/attachment w/attachment w/attachment w/attachment