ML18054A910

From kanterella
Revision as of 06:08, 14 December 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Responds to NRC 890628 Ltr Re Violations Noted in Insp Rept 50-255/89-07.Corrective Actions:Design Engineers & QA Personnel Provided W/Training on Structural & Welding Codes & Code Application to Weld Installation & Exam
ML18054A910
Person / Time
Site: Palisades Entergy icon.png
Issue date: 08/10/1989
From: BERRY K W
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8908180078
Download: ML18054A910 (50)


See also: IR 05000255/1989007

Text

. "' * G11neral 1946 West Parn11ll Road, Jackson, Ml 49201 * (6171 788-1638 ** -----August 10, 1989 Nuclear Regulatory

Commission

Document Control Desk Washington, DC 20555 DOCKET 50-255 -LICENSE DPR-20 -PALISADES

PLANT -RESPONSE TO INSPECTION

REPORT 89007 NOTICE OF VIOLATION

Kenneth W Berry Director Nuclear Licensing

Nuclear Regulatory

Commission

Inspection

Report 255/89007, dated June 28, 1989, identified

strengths

in inservice

testing programs and weaknesses

relative to design control. These weaknesses

resulted in three violations

supported

by numerous examples.

None of these examples were safety cant, but collectively

they indicated

a need for programmatic

refinements

and additional

communication

of management's

expectations.

The NRC required a written response to be provided within 30 days, however, discussion

between respective

members of our staffs extended the due date to August 10, 1989. This letter. summarizes

the actions to be taken. Details pertaining

to the specific items are provided in the Attachments.

Since 1986 significant

efforts have been undertaken

by Consumers

Power Company to provide for effective

control of Plant design change activities.

These efforts have resulted from evaluation

of performance

by Plant Engineering

and Corporate

Engineering

personnel, Quality Assurance

personnel, NRC and the Institute

of Nuclear Power Operations.

In achieving

an effective

design control process; procedures

governing

modification

control activities

have been revised, a single design authority

has been established, changes to the facility are. being effected through a single unified approach and expectations

and standards

have been communicated

to Design Engineering

personnel.

Procedural

upgrades have focused on translation

of design input to the desired output, controlling

and implementing

the design change in the field and providing

close coordination

of the design with the needs of the Plant. In the past, the design authority

for "minor" modifications

has resided at the Plant while offsite engineering

organizations

retained the design

for "major" modifications.

Establishing

the Plant as the design authority

for all changes to the facility has been effected by Plant sponsorship

of all design control procedures, Plant approval for assignment

of design individuals

and Plant review of all work completed

by non-Plant

organizations.

Further, OC0889-0167-NL04

8908180078

890810 PDR ADOCK 05000255 G PNU .*.-.*-. :; .--.* , .. -,,.. ** _,. "':;. '* *.;*;,***"'

  • .*

...... :,=o-*r-<*

*** *., ** , ... _ *--

  • * * Nuclear Regulatory

Commission

Palisades

Plant Response to IR 89007 August 10, 1989 semi-annual

design seminars and monthly design supervisor

meetings which include Engineering, Construction

and Testing and Quality Assurance

personnel

are being conducted

to facilitate

communication

of procedural

changes, standards

and expectations.

2 Consumers

Power Company believes, and as recognized

within the Inspection

Report, these efforts have resulted in programmatic

strengths.such

as; good design procedures, improved equipment

performance

and competent, knowledgeable

personnel.

However, Consumers

Power Company also recognizes

that as industry performance

standards

are increased, weaknesses

in established

programs may develop which require additional

effort. NRC violation

255/89007-01

presented

19 examples of inadequate

design control related to design changes implemented

at the Plant. The first seven of these examples were related to the failure to correctly

translate

design bases into drawings, procedures

and instructions.

Five of the examples are acknowledged

as presented

and are attributed

to the failure to; 1) follow established

procedures, 2) provide adequate justification

and documentation

within cation packages or 3) provide for adequate technical

reviews of installation

efforts. Also, certain areas were identified

where procedural

enhancements

and improved design guidance would preclude recurrences. er, the remaining

two examples, 255/89007-0ld

and Olg, are not acknowledged

as* presented

within the Inspection

Report. For these two* examples we believe the design intent of the modification

was preserved

and verified by testing and that record drawings utilized reflect the as-built condition

of the Plant. The

nine examples were related to the failure to adequately

verify and check design. Eight of the examples are attributed

to the failure to; 1) follow established

procedures, 2) document engineering

decisions

or 3) provide for adequate technical

reviews. Also, certain areas were fied where procedural

enhancements

would preclude recurrence.

However, Consumers

Power Company does not acknowledge

the remaining

example 255/89007-011.

For this example, the Inspection

Report noted that a setpoint change was implemented

without assuring the design intent of the system had not been compromised.

In review of the documentation

supporting

the design change, it was verified that design intent of the system was considered

and documented

within the modification

package and had not been compromised.

The remaining

three examples were identified

as non-compliances

for the

to adequately

delineate

acceptance

criteria.

Two of these examples are attributed

to a lack of procedural

guidance within modification

procedures.

Consumers

Power Company does not believe example 255/89007-0lq

is valid as presented

in that appropriate

equipment

selection

criterion

were applied during design and documented

within the modification

package * OC0889-0167-NL04

... *****-*' .... -.***.*****:*

.,--._., .. _ ....

...... *.*-****-***._*-.**.*.,,,,_._._,_

.. _,., ... **-*....-*******.-

..

  • Nuclear Regulatory

Commission

  • Palisades

Plant Response to IR 89007 August 10, 1989 3 In an effort to ensure the accuracy of the existing plant design basis is maintained, discrepancies

identified

within analyses supporting

the cited design changes have been or will be dispositioned

and documented.

As an effort to collectively

utilize auditing agencies appraisals

of our past performances, the identified

deficiencies

were presented

to Design Change Engineers

with emphasis placed on strict adherence

to established

procedures

and the concept of Plant based modification

engineering.

Enhancements

being made to design change procedures

regarding

documentation

of engineering

judgement, substantiating

input assumptions

and* thorough technical

reviews will be presented

to design change engineers

via personal letters, performance

seminars and continuing

training programs.

Enhanced design guidance is being developed

for weld engineering.

Specifically, code training for weld neers is being conducted

as well as design change procedure

revision to "prompt" the use of existing weld engineering

guidelines

for proper code selection

and specification.

In addition, as part of the Configuration

Control Project, additional

engineering

guidance regarding

cable sizing and raceway fill, designing

fire barriers and fire stops, evaluating

station and emergency

power* system.component

loads and cable routing including

the effects of cable submergence, is being developed.

Additionally, more engineering

guidance in the form of an engineering

specification

will be developed

for the civil/structural

discipline.

This specification

will be developed

by July 1990. . NRC violation

255/89007-02

presented

two examples where socket fillet welds were not-verified

to be in conformance

with weld size requirements

provided in welding specifications.

These examples are attributed

to a failure to meet current expectations

for the control of design change implementation.

To . avoid further non-compliance, design change procedures

are being revised to present welding specifications

input checklists

and implementation

drawings, and to provide for technical

reviews of weld requirement

inputs by Maintenance

Planners.

Additionally, Design, Engineers

and Quality Assurance

personnel

are.being

provided with training on structural

and welding codes and their application

to weld installation

and examination.

NRC violation

255/89007-03

was issued for a failure to implement

and maintain Technical

Specification

low temperature

overpressure (LTOP) setpoints

which were changed through the specification

change process. The violation

is attributed

to poor

within the Technical

Specification

Change Request development

process. When the LTOP setpoints

were derived, Plant personnel

failed to identify that the value included in the Technical cation did not account for calibration

tolerance.

A letter of interpretation

has been submitted

to the NRR which documents

ou"' '1-'osition

and commits to revising the setpoints

in a forthcoming

Technical

Specification

Change quest. In the interim, surveillance

procedures

which provide for setting and verifying

the LTOP setpoints.have

been revised to remove the positive tion tolerance.

An evaluation

will be conducted

to determine

where ments in the Technical

Specification

Change Request process can be made to preclude recurrence.

OC0889-0167-NL04 . t -. * ..... :*. : . *:: ... '*, ,;**.*:.r

., *. . .. * *. -. . . . ,: ::' .. ** , l *.. .. ....... :*'.'* *. -:.::. **-.:--..

.. ;.,;:**: ... *. -.. --. -.... . *.:*.:'.-.**: .. ':;:"'::::-*-:-*.*.

  • * Nuclear Regulatory

Commission

Pal:isades

Plant Response to IR 89007 August 10, 1989 4 The Inspection

Report additionally

requested

a written response be provided for certain, specific examples of programmatic

weaknesses.

The first weakness cited involved the addition of zener diodes in the safety injection

tank pressure transmitter

power supply without analyzing

potential

failure modes and without checking diode input voltage after installation.

The failure to fully analyze potential

failure modes is attributed

to personnel

error. Administrative

Procedures

currently

require that .a failure modes and effects analysis (FMEAs) be performed

as part of the safety evaluation

process. The periodic*

refresher

training program for design engineers

will include emphasis on FMEAs. The next weakness cited pertained

to the backup nitrogen supply modification.

Specifically, an unauthorized

design change was implemented

when field nel implemented

their own weld requirements

after identifying

that an priate weld was specified

by the design engineer.

The condition

is attributable

to the fact that welding maintenance

procedures

are not. ly integrated

with design control procedures, thus assuring that changes. in the field will be approved by engineering

before they are undertaken.

The welding maintenance

procedures

will be better integrated

with the design control procedures.

The third weakness pertained

to utilization

of different

editions of the ASME Code relative to stress intensification

factors utilized in analyses.

In summary, usage of the later addition of the ASME Code, as currently

described

in the Palisades.

Final Safety Analysis Report (FSAR), was discussed

in an April 1980 meeting between Consumers

Power Company and the NRC and found to be acceptable.

Our interpretation

of the results of this meeting was submitted

to the NRC in the draft form, revised FSAR pages in our Final Response to IE Bulletin 79-14 dated September

26, 1980. As indicated

in our submittal

to the NRC dated October 24, 1980, the use of different

code editions was found to be acceptable, reviewed in accordance

with 10CFR50.59

and placed in the Palisades

FSAR. Therefore, usage of different

code editions as presented

in the FSAR currently

represents

our position and is believed to be acceptable.

The last weakness cited pertains specifically

to the Engineering

Design Change (EDC) form utilized to revise facility changes not listing calculations

which may be affected by the particular

EDC. Therefore, it was unclear whether technical

reviewers

had considered

the effects of the EDC on the original analyses.

Consumers

Power Company believes that existing procedural ments direct the EDC initiator

to "reflect" the change in all affected tailed design documents;

the engineering

analysis was clearly identified

in the procedure

as being a detailed design document.

However, "engineering

analyses" will be specifically

added to the EDC form to ensure that technical

reviewers

consider effects on engineering

analyses and provide documentation

of this consideration

  • OC0889-0167-NL04

I

  • * Nuclear Regulatory

Commission

    • **Palisades

Plant Response to IR 89007 August 10, * 1989 5 The Inspection

Report also requested

that specific discussion

be provided regarding

unresolved

items pertaining

to welding. This discussion

is ed on page 41 of Attachment

1. In summary, we acknowledge

that no corrective

actions have yet been directed towards reviewing

previously

made socket fillet welds for compliance

with code requirements.

Consumers

Power Company plans, however, to select an appropriate

sample.of

as-built welds and inspect the * welds during the 1989 maintenance

outage. The sample will be chosen to include a range of weld types. The purpose of the inspection

will.be to verify that the weld characteristics (type and size) conform to requirements

set forth in the repair inspection

checklist

and/or applicable

welding code. Kenneth W Berry Director, . Nuclear Licensing-

CC Administrator, Region III, USNRC NRC Resident Inspector

-Palisades

Attachments

OC0889-0167-NL04

'" *'.*. -1 --* * ** *. '.<. ; *.** -, .. ' ** *-::. _. '.

  • * * .*_.* *; ATT0889-0167-NL04

ATTACHMENT

1 Consumers

Power Company Palisades

Plant Docket 50-255 DETAILED RESPONSES

TO INSPECTION

REPORT 89007 August 10, 1989 45 Pages . ' . * ,. . ..* *. , .. *** .. * *. ** ** .. *---"""--'---'----'-'-'""'"--=...;.......*

....._ . .._. ;...;,* .;....;...;.;.-""*--*

..:...* *.;_* _...;,_..;__:-......;.----.;_*

  • . .;...' *..:...* .._c*..:...*
  • ....;.....;.,.;.;.,___;__.___.;.;.,....;,.;,...;...___;_,;__.....;.._.;..:.;.;.;..;.;._
  • Violation

(255/89007-0!A-S)

1. lOCFRSO, Appendix B, Criterion

III, as implemented

by the Palisades

Operations

Quality Assurance

Program requires, in part, that the design bases be correctly

translated

into

drawings, procedures, and instructions;

that the design control measures provide for verifying

or checking.the

adequacy of the design; and that design control measures be applied to the delineation

of acceptance

criteria for inspections

and tests. Contrary to the above, the following

instances

of inadequate

design control were identified:

This is a Severity Level IV Violation.

This violation

is sustained

by 19 examples.

Though Consumers

Power Company believes four of these are not supportive

examples.

We do acknowledge

the violation.

Our detailed response to each example follows: MI0789-1683A-TC01-NL02

1 ... . -::* -* .. ........ * -....... ,. .. *. .... *... ,.,_

"'":"."' .. * .. :_*:.-

_ ___:__*__'._._

.. _.* _-.. : *-* .

NRG Violation

255/89007-0la:

EA-FC-789-07, "Seismic Analysis of Auxiliary

Feedw'ater

Control ESSR 88714, 11 Revision l, August 24, 1988. [Refer to page 9 of NRG Report 50-255/89007 (DRS).] Example FC-789 contained

multiple dimensional

differences

between the analysis model and the installation

drawings.

The following

examples are provided:

-The location of new support 8224 was analyzed at 6 11 from the 45° elbow. The piping drawing (M-101 Sheet 5113) *used to install the support specified

a dimension

of l'-7 1/2" from the elbow. This difference

was not noted in the calculation.

-The length of pipe between Model Nodes 6276 and 6282 was analyzed as 5'-10" long. The installation

drawing specifies

S'-6" long. This difference

was not noted in-the calculation.

Several additional -dimensional .discrepancies

on the. new. bypass piping were . also noted between the analysis and installation

drawing. These discrepancies

ranged from 1 11 to 2-1/4" and were considered

minor by the inspector.

none of these discrepancies

were noted in the calculation.

Reason for Violation

During the evaluation*

of the design of the bypass piping system numerous changes in design dimensions

were encountered

due--to pipe, support and valve operator-interferences.

At a certain point in the analysis process, it was decided to build* the design *to. the drawing and* effect the final analysis reconciliation*when

the as-built data were recorded on a marked-up

drawing. The analysis reconciliation

with the as-built was never made. This violation

was due' to inadequate

documentation

of the* justification

for analytical

input and failure to follow established

procedures.

Corrective

Action Taken, and** Results Achieved-All engineering

groups have been briefed as to the results of this inspection.

These briefings

were completed

on August 2, 1989. The above noted

cies have been satisfactorily

dispositioned

and the finite element piping analysis model has been updated. Corrective

Actions to be Taken to Avoid Further Non Compliance

Interim All design change engineers

will be briefed as to the reported violations

by personal letter. These letters will require that all engineers

involved in design changes scheduled

for installation

in 1989 review existing design ages for similar problems and correct any identified

problems.

MI0789-1683A-TC01-NL02

2

... * ... *. -*. : .r;. : ...

I

.-:*** , .. ,,. .. Long-Term

Enhancements

will be made to plant administrative

design control procedures

to further clarify the requirements

that strict alignment

between engineering

analyses, associated/accompanying

drawings, and as-built condition

must be verified and documented

prior to declaring

modified systems/equipment

operable.

In additionf

a program will be developed

to provide periodic refresher

training to all design change engineers

on design change-related

administrative dures. Date When Full Compliance

Will be Achieved The personal briefings

by letter will be issued by September

1, 1989. dural enhancements

will be completed

by January 1 1 1990. The program for periodic training will be in place by March 1, 1990. NRC Violation

255/89007-0lb:

EA-FC-789-07, "Seismic Analysis of Auxiliary

Feedwater

Control ESSR 88714" Example b.l -For the south bypass loop, the Young's Modulus was specified

as 27.4 E6 psi instead of 27.9 E6 psi. This is equivalent

to analyzing

this portion of pipe with properties

at 300° instead of 70°. This discrepancy

was not noted in the analysis.

Reason for Violation

The use of the.27.4 E6 psi value for the Young's Modulus represents

a 1.8 cent error with *regard* to the correct value of 27 .9 E6* psi value. The impact of such an error is expected to be an underprediction

of thermal expansion

stress of no more than 1.8 percent. This resulted from inadequate

tion of technical

review and failure to follow existing procedures.

Corrective

Action Taken. and. Results= Achieved*

All engineering

groups have been* briefed as to the results of the inspection.

These briefings

were completed

on August 2, 1989. Corrective

Actions to be Taken to Avoid Further Non Compliance

Interim All design change engineers

will be briefed as to the reported violations

by personal letter. These letters will require that all engineers

involved in design changes scheduled

for installation

in 1989 review existing design ages for similar problems and correct the problems.

MI0789-1683A-TC01-NL02

3 .-.. ... ,. * ... * .. ** ... -

  • ** Long-Term

to plant administrative

design control procedures

will be made tog -Provide the technical

reviewer a review checklist

with a "prompt" to justify the numerical

values of all constants

and variables

utilized as inputs to the analysis (the checklist

will provide a comprehensive

set of "prompts" to ensure an overall accurate, thorough and auditable

analysis). -A mechanism

for the reviewer to note minor errors which would not necessitate

a reanalysis.

In addition, a program will be developed

to provide periodic refresher

training to all design change engineers

on design change-related

administrative dures. Date When Full Compliance

Will be Achieved The personal briefings

by letter will be issued by September

1, 1989e The procedural

enhancements

and training on the enhancements

will be completed

by January 1, 1990. The program for periodic training will be in place by March 1990. Example b.2 The location of the center of gravity (CG) for the new bypass valves was analyzed at 19 11 from the pipe centerline.

The location specified

on the vendor-drawing

was 22 11* This represents

a 15% increase in the moment arm which was not noted in the calculationo

Reason for Violation

The piping analysis was set up from preliminary

data. The valve assembly weight was included in the model. However, the weight placement

was not sistent with-*the

final drawing received.from

the vendor. The existing mentation

does not indicate whether or not the analyst reviewed the center of gravity data from the vendor drawing. The analysis certainly

was not run to accommodate This violation

occurred due to failure to account for vendor information

as analytical

input and failure to follow established

procedures.

Corrective

Action Taken and Results Achieved All engineering

groups have been briefed as to the results of the inspection.

These briefings

were completed

on.August

2, 1989. The calculation

was revised to incorporate

the correct vendor data and was found to be acceptable.

Corrective

Actions to be Taken to Avoid Further Non Compliance

Interim Same as that required for Violation

l.a. MI0789-1683A-TC01-NL02

4 ...... ... \*::..:***** . . . . *,_ . . .*. . . . .:::*-

. . * Long-Term

Enhancements

to plant procedures

will be made Ensure that vendor information/recolillllendations

are accounted

for ical input and that justification

be provided for departure

from information/recommendations, as such Provide the technical

reviewer a review checklist

with a 11 prompt" to assure that vendor information/recommendations

are appropriately

accounted

for. A program will be developed

to provide periodic refresher

training to all design engineers

on design change-related

plant administrative

procedures.

A 11 punch 11 list or equivalent

will be developed

to track items requiring

verification

when data becomes available.

Date When Full Compliance

Will be Achieved The personal briefings

by letter will be issued by September

1, 1989. These procedural

enhancements

will be in-place by January 1, 1990 as will required training on these enhancements.

The program to provide refresher

training will be in place by March 1, 1990. Example b.3 In addition to the above noted discrepancies

for modeling the bypass piping, other dis.crepancies

were noted in the model of the original auxiliary

feedwater

piping. The inspector

could not determine

whether these discrepancies

were inherent in the original data or whether they occurred during the transcription

of the original model into the current piping analysis.

However, notes in the piping model stated the following: "Bechtel analysis is a bit off from ISO here." -"Bechtel has modeled elbows only with SIFs. Elbows are used here." -"Review ISO for pipe schedule change." These notes led the inspector

to question the validity of the assumption

made in the calculation

concerning

the correctness

of the original input data. CPCo Response The three notes recorded by the inspector

do not necessarily

imply errors in the original input analysis.

The notes reflect free text written into the ADLPIPE computer model by the translator

of the ME101 Bechtel model for the review by the piping analyst. The specific analysis model/ISO

discrepancy

was small. However, the note advised the analyst that a choice needed to be made for analysis record runs. MI0789-1683A-TC01-NL02

5 . :.'.-.** -

  • There is nothing wrong with modeling elbows with SIFs and flexibility

characteristics.

However, the note merely advises the analyst that comparing

ADLPIPE elbows and ME101 elbows for counting of elbows for model benchmarking

will not yield consistent

results and that the MElOl model will require more review to ensure model consistency.

The note with respect to pipe schedule change is again for the benefit of the analyst. No error is implied. No corrective

action is required.

Example b.4 The additional

discrepancies

in the mod*el of the auxiliary

feedwater

piping were as follows: -For flow element FE-0736, the weight of 192 lbs was modeled at node 211 instead of node 205 *. Although this was only a 4-1/2" error on a 6 11 pipe, the flange pair was analytically

modeled with the weight concentrated

at one edge instead of at the middle of the flanges. For Valve M0-0754, the 460 lb weight was modeled at the centerline

of the pipe at node 267. The weight should have been specified

at the valve CG at node 268, 18" out from the pipe centerline.

The horizontal

response spectra used in the analysis was inconsistent

with the spectra given in Specification

C-175. The spectra used was lower and not as broad as those given in the Specification.

-Piping .between the nodes 252 and 253 was modeled as 4", schedule 40, instead of 6 11 , schedule 80. The above discrepancies

are further examples of violation

of 10 CFR 50, Appendix B, Criterion

III in that the licensee failed to correctly

translate

the design into the drawing (255/89007-0lb).

Reason for Violation

The placement

of the flow element weight, the placement

of the valve operator weight and the pipe schedule discrepancy

constitute

discrepancies

which should be picked up in the review process. The reason for the violation

has been attributed

to an inadequate

technical

review and failure to follow established

procedures.

The horizontal

response spectra employed in the original IE Bulletin 79-14 analysis of the Palisades

piping systems were based upon the Taft 1952 record. The digit,ized

data and a straight-edged

set of plots from those data were

.. to Consumers

Power Company by Bechtel in 1976. The horizontal

response spectra used in the piping analysis were derived from these digitized

data. The straight-edged

plots were used for building and equipment

tion seismic work * MI0789-1683A-TC01-NL02

6

..... .* ,.*

.. . . , *. **:. -------------------


Because the straight-edged

plots were very difficult

to read and because it was desired to incorporate

building and equipment

spectra in a single seismic ification

specification, the straight-edged

plots were redrawn and incorporated

into Specification

C-175. It is expected that the horizontal

spectra of C-175 could be slightly higher and broader than the straight-edged

spectra. However, that was not the purpose for drawing them. Although the C-175 horizontal tra should be very similar to the straight-edged

horizontal

they should be used for building analysis and equipment

qualification

only. They should not be used for piping analysis.

The correct horizontal

response spectra for safety related piping systems at Palisades

which use the initial plant seismic design basis are those included in the stress packages as developed

from the digitized

spectra._

New piping systems or modifications

involving

substantial

changes to existing systems will employ the spectra and procedures

in Specification

M-195. Corrective

Action Taken and Results Achieved All engineering

groups have been briefed as to the results of the inspection.

These briefings

were completed

on August 2, 1989. Corrective

Actions to be Taken to Avoid Further Non Compliance

Interim Same as for Violation

Item l.a. Long-Term

Enhancements

to plant procedures

will be made to: -Provid*e the technical

reviewer a checklist

with a comprehensive

set of "prompts" to ensure an overall accurate, thorough and auditable

analysis.

These "prompts" will specifically

require that the reviewer check the validity of all analytical

input and assumptions.

-Provide. the basis for the selection

of design

as governing, and -Provide a technical

review checklist

with.a prompt to concur that governing

design criteria (input) have been justifiably

selected.

-Identify applications

in which C-175 or M-195 would be used. Furthermore, a program witl be developed

to provide periodic refresher

training to engineering

personnel

on design change related plant administrative dures. Date When Full Compliance

Will be Achieved The personal briefings

by letter will be issued by September

1, 1989. dural enhancements

will be made by January 1, 1990 as will all required training on the enhancements.

MI0789-1683A-TC01-NL02

7 ::*:-";**

..... *\ .. * ::* r* '.*.

.! * NRC Violation

255/89007.0lc:

Consumers

Power Company Drawing M-101 Sheet 5113, Revision O, "Piping Isometric, Auxiliary

Feedwater

Control Valve CV-0736A and CV-0737A Bypass Piping." [Refer to page 12 of NRC Report 50-255/89007 (DRS)o] Example -The size of the fillet weld was determined

by the requirements

of Welding Specification

WPS-11.21, Revision 2; however, for the socket welded fittings, the size of the fillet weld was not specified

on this drawingo In reviewing

the Repair Inspection

Checklist (RIC) for the welds in question, the weld size specified

is 1 1/2 11* This is misleading

in that this is the size of the pipe and not the size of the fillet weld. In order for the welder to determine

the size of the fillet weld, the pipe wall thickness

must be obtained and a calculation

of 1.09 times the wall thickness

must be per-. formed. Although this is a relatively

simple calculation, it is a design function and* as such must be controlled.

There is no documentation

to demonstrate

that this design activity was performed.

In addition, there are *no controls in place to check and verify this design activity.

Reason for Violation

Specifying

welding requirements (such as applicable

code, weld material, weld type and weld size) is an engineering

function.

If properly administered

by procedure, the maintenance

planner can (and has) effectively

prescribe

welding details* for the field provided that adequate input from engineering

exists as a basis. In the past, engineering

input has been limited to welding

tion and/-0r structural

analysis engineering

sketches.

which have lacked size dimensions

for the welds *. As a result, the planner has failed to provide the proper size on the Repair Inspection

Checklist (RIC) thereby requiring

the field welder to determine

and install the proper weld size. This practice fails to meet current expectations

for control of design change implementation.

The plant administrative

design control procedures

required and currently

require that the design change project engineer determine

code requirements

for assigned projects (Reference

4), and plant maintenance

procedures

required and currently

require that the maintenance

planner specify applicable

code and weld parameters

after consultation

with the Engineering

Department (Reference

3). These procedures

have not been effectively

integrated

to support one another to ensure that weld specifications

from engineering

were accurately

translated

into installation

planning, installation, and post-installation

The following

actions have been/will

be taken to ensure the administrative dures relating to weld specifications

are properly integrated

with the Maintenance

Department.

Prior to actions taken as a

of recent self-identified

failures to verify weld size (Reference

7), no specific requirements

existed to verify characteristics (weld, type, size contour) of installed

welds. Although Nuclear Operations

Department

Standards

suggest inspection

hold points for weld installation

verification, working level administrative

procedures

did not specify a hold point requirement

except for fit up. MI0789-1683A-TC01-NL02

8 .. '. **. _.\**.**.*.:

  • ... . *.* ... _;**-::* .
  • .* -.,:* * .*.... -*. *;.-* .
  • * ---------Corrective

Action Taken and Results Achieved -All engineering

groups have been briefed as to the results of this inspectiono

The briefings

were completed

on August 2, 1989. The Inservice

Inspection (ISI) Section of the Plant Projects Engineering

Department

has effected the role of Design Authority

for weld engineering

by revising the RIC to identify critical weld parameters

and require ISI cal review of the maintenance

planner's

specifications.

The purpose of the review is to ensure that appropriate

welding codes are complied with in the areas of weld installation

and post-installation

examination.

Revision to the RIC was completed

as part of the revision to the plant administrative

procedure

for control of special processes (Reference

3). -The ISI Section (as well as planners, welders and welding supervisors)

has received specific training with respect to welding codes and technology

to augment their existing collective

knowledge.

-In addition, the RIC .. was revised to issue. the. weld minimum leg length to the field. This will eliminate

the need for the field welder to calculate

the length. The aforemenqoned

ISI review will assure that this specification

is provided.

-Finally, the RIC has been revised to require verification

of weld size * (RIC now requires that weld is inspected

for size, porosity, undercut,-etc.)

Training materials

for the welder tra1n1ng progression

course have been revised-to emphasize

fillet weld terminology

and conformance

of the completed

weld to the.design

specification.

Corrective

Actions to be Taken to Avoid Further Non Compliance

Interim -* Same as that required for Violation

Item l.a. Long-Term

-Enhancements

to plant design control and maintenance

procedures

will be made to more effectively

integrate

engineering

into weld specification

and mately into weld planning and verification:

Appropriate

welding codes will be included in the Design Input Checklist (Reference

2) to "prompt" the design engineer to specify appropriate

weld requirements (for installation

and examination)

in the facility change package as part of both conceptual

and detailed engineering.

In addition, a generic guideline

will be developed

to support the design engineer throughout

the weld design process. MI0789-1683A-TC01-NL02

9 . :*.-...

....... :. .\ :*_ .. *** '!: *-..... : .: . ' ,\ .. ,.' **::.**.*:-:

...

  • * Design control procedures

related to engineering

analyses (Reference

1) will explicitly

require that all drawings accompanying

structural/seismic

analyses provide detailed weld information (type, size, material)

for input to the planner. The procedures

will also require that sizing calculations

be* performed

as part of the analysis.

Finally, a technical

review checklist

will be provided to require that the reviewer ensures that weld information

be accurately

represented

on the analysis drawings.

-Plant maintenance

procedures (Reference

3) will require that the maintenance

planner utilize the contents of the facility change package to complete the RIC in specifying

for the field weld installation

and examination ments. The procedure

will require that the planner consult the Design Input Checklist

and structural/seismic

engineering

analyses.

Relative to weld verification, the design control program and related welding program will be evaluated

and enhancements

developed

as necessary

to ensure that administrative

and quality verification

controls exist to consistently

verify that field installation

satisfies

design requirements (ie, input vs output). Interim actions related to changes to the RIC and !SI group review of the RIC (as described

above) will remain in effect * Design and quality assurance

engineers

will be trained on the appropriate

structural

and piping weld codes and their application

to weld installation

and examination.

The engineers

will also be trained on the above procedural

enhancements.

Finally, a program will be developed

to periodically

train design and quality assurance

engineers

on the aforementioned

codes and their application, and on the weld-related

design control and maintenance

procedures.

In summary, it is expected that these actions will ensure that proper welding requirements (type, material, size) are specified

by engineering, planned by maintenance (with a check on planning by engineering), and in turn, verified by quality control. Date When Full Compliance

Will be Achieved The engineering

group briefing has been

The personal briefings

by letter will be issued by September

1, 1989. Procedure

enhancements

and required training on the enhancements

will be completed

by January 1, 1990. The program for periodic refresher

training will be developed

by March 1, 1990. NRC Violation

255/89007-0ld:

EA-T-FC-722-501-01 "Calculation

of Acceptance

Criteria for Modification

Test Procedure

T-FC-722-501," January 13, 1987. [Refer to page 16 of NRC Report 50-255/89007(DRS).]

MI0789-1683A-TC01-NL02

10 *:**.

.* ..

.*. .. . ; . .

  • * Example The calc.ulation

on page 2 of the engineering

analysis states that the total volume of gas contained

in the nitrogen bottles at 2000 psig is 209 scf. This value is incorrect

in that it is the usable cylinder volume as given in lation EA-FC-722-02.

The actual volume is approximately

228 scf. By using the incorrect

value, the calculated

acceptance

criteria for pressure drops were higher and, therefore, were nonconservative.

CPCo Response CPCo does not acknowledge

this example as a of violation

of 10CFR50, Appendix B, Criterion

III for the following

reasons. 1. As indicated

by EA-FC-722-02, the design intent of this modification

is to supply a nitr.ogen

header pressure from an initial minimum bottle pressure of 2,000 psig down to 150 psig to ensure that the associated

control valves would be brought to their safety-related

position and maintained

in that position for the -required

time period. * 2. In accordance

with the design intent of this modification, the usable volume of nitrogen is that volume contained

in the bottle from 2,000 psig to 150 psig or 209 scf as calculated

by EA-FC-722-02, Sheet 10 of 13. The usable volume of 209 scf is utilized as a conservative

value to establish

the number of nitrogen bottles required for each station to meet system design requirement.

3. Although not specifically

stated in *the body of EA-T-FC-722-501-01, the value of the "usable" volume of nitrogen (209 scf) was utilized in lishing test acceptance

criteria rather than the "total" volume of nitrogen (228 scf) to confirm the design intent, verify estimated

leakage rates, and confirm system margins. The test procedure

clearly tests the design intent of this modification.

Based up_on the above, we feel that this example does not support a violation

of lOCFRSO, Appendix B, Criterion

III has occurred.

However, certain actions will be undertaken

to remedy this minor deficiency

and prevent its recurrence:

Interim -All design change engineers

will be briefed as to the reported violation

by personal letter and by engineering

group presentation.

The letter briefings

will be completed

by September

1, 1989. The group presentations

were pleted on August 2, 1989. -EA-T-FC-722-Ji

will be revised to clearly indicate that "useable" volume has been utilized to calculate

the acceptance

criteria rather than "total" volume. MI0789-1683A-TC01-NL02

11 . **-.*****:*:

--:*;*-: ... :**:*,'. ... . . .. :-. ... ;-: . .;. :: ;*.* .. ...... _ ...... . ':. :*;*.-**

Long-Term

The actions identified

as being taken in the interim are considered

complete and effective

in responding

to this identified

condition;

no further action is required.

Date When Full Compliance

Will be Achieved The engineering

analysis will be revised by September

1, 1989. NRC Violation

255/89007-0le:

FC-756 11 HPSI Pump Miniflow Bypass Modification.

19 [Refer to page 18 of NRC Report 50-255/89007 (DRS).] Example Input into the AOLPIPE, Inc (AOL) piping stress analysis, contained

in FC-756, contained

multiple dimensional

differences

from the as-built dimensions.

Bechtel's

stress.isolmetric

drawing 03378, sheet 4 of 5, Revision 1, and drawing

Revision 4, showed a dimension

of 29 7/8 inches between pump 66A and the elbow. The as-built dimension

is 13 1/2 inches. Both (ADLPIPE, Inc.) AOL's and B.echtel's

stress analyses used 27 7/B inches. This dimensional

discrepancy

was not documented

during the NRC IEB 79-14 program, nor was it corrected

in Bechtel's

and AOL's stress analyses.

Further, this discrepancy

is in conflict with the assumptions

contained

in analysis No CS-ESSR 87-144 that purportedly

demonstrated

that the Bechtel drawings are correct. The inspector

also noted that the input data used in the modification

portion of the piping system was inconsistent

with as-built drawing No 03378, Sheet 4 of 5, Revision 2. The licensee reviewer was not aware of the above dimensional

discrepancies.

Failure to correctly

translate

the design into the drawings is considered

an example of violation

of 10CFR50, Criterion

III. Reason for Violation

The dimensional

discrepancy

associated

with the 27 7/8 versus 13-1/2 inch lengths was a result of the analyst relying on data being transmitted

from the field and not checking the installation

personally.

The smaller discrepancies

between the ADL and as-built drawing records were recognized

by the analyst when he was provided a marked-up

drawing of the as-built configuration.

The analyst acknowledged

receipt of the as-builts

via memo and stated that the as-built configuration

was acceptable

and no reanalysis

was required.

The reason for the violation

was inadequate

analytical

assumption

resulting

from a failure to perform a system walkdown and failure to follow established dures. Corrective

Action Taken and Results Achieved All engineering

groups were briefed on the results of this inspection.

The briefings

were completed

on August 2, 1989. The dimensional

discrepancies

noted have been satisfactoril*y

dispositioned

and documented.

MI0789-1683A-TC01-NL02

12 *::**. -.* ...... .

... :* ..... **', ..

  • Corrective

Actions to be Taken to Avoid Further Non Compliance

The following

corrective

actions will be taken to prevent

Interim Same as that required for Violation

Item 1.a. Long Term Procedural

enhancements

will be made to ensure

-The analyst "walks down" the area of interest *to confirm all as-built (or intended as-built)

data is utilized in the analysis.

This confirmation

must be made prior to declaring

modified structures

or equipment

operable.

-By approval of the facility change "Responsible

Engineer, 11 the above bility for as-built data confirmation

may be delegated

to field construction

by controlled

procedure

or work order instruction.

-In the event the analyst concludes

that no further "analysis" is necessary, the reconciliation

of such shall be documented

as part of a controlled

analysis revision which ensures technical

review. A program will be developed

  • to provide refresher

training on design change related prQcedures.

This training will be directed towards all design change engineers.

_ Finally, a portion of the Configuration

Control Projec.t involves the walkdown and field verification

of piping as-built dimensions

to confirm the accuracy of our stress isometric

drawings.

Verification

of the stress isometric ings for a sample system is planned for 1990 to assess theneed and extent of further verification

activities.

CPCo will perform any required walkdowns

by no later than the 1990 refueling

outage. Date When Full Compliance

Will be Achieved Personal briefings

by letter will be issued* by September

1, 1989. Procedural

enhancements

and required training on the enhancements

will be completed

by January 1, 1990. The periodic training program will be in place by March 1, 1990. Walkdown and field verification

of stress isometric

drawings requiring

verification

will be completed

by the 1990 refueling

outage. ' NRC Vio*lation

255/89007-0lf:

FC-756 "HPSI Pump Miniflow Bypass Modification." [Refer to page 19 of NRC Report 50-255/89007 (DRS).] Example The as-built sketch used in the analysis for FC-756 contained

a nine inch dimensional

error. MI0789-1683A-TC01-NL02.

13 *:.:*:: ** . *' ... . i.: .*

_ .. * . ,, .. *-* :-*._:: ... ; . . ' . : :: ... :. ' ........

The as-built sketch for the modification

near pump 66A was sent from the site to the engineering

office for review. The inspector

noted that this sketch contained.a

dimensional

error. the 2 1-6 1/2" dimension

was incorrectly

marked on the sketch. This dimension

was off by nine inches. Failure to correctly

translate

the design into the drawing is considered

an example of violation

of lOCFRSOP Appendix B, Criterion

III. Reason for Violation

As a result of required piping changes for this modification, a seismic analysis and Stress Package 03378 update were requested

by the site. Included with the request were M-107 Sh 2247/2248

which indicated

the existing configuration, and proposed modification.

Using the drawings as input 1 the system was modeled on ADLPIPE to generate the system stresses after the modification.

The existing drawings (sent as part of the request) were marked "Issued As-Built per NRC IE Bulletin 79-14.11 After the analysis was performed, a pre-installation

walkdown was performed.

During the walkdown the referenced

dimensional

discrepancy

was noted. The seismic analyst was contacted

to evaluate the change. As a resultp the analyst issued a letter stating *that since stresses in the area were low, based on his judgement, the change was acceptable.

When the construction

was complete, the seismic analyst compared the as-built to the dimensions

used in the preliminary

analysis.

It was determined

the analysis was acceptable

with the dimensional

variance .... Stress Package 03378 was annotated

to reflect this information.

The above-information

describes*

the circumstances

surrounding.the

modification

however does not indicate a root cause. The discrepancy

is not directly related to the modification

except that the modification

brought a previous error to light. That is, the drawings used were certified

as being dimensionally

correct per Bulletin 79-14, when in reality there was an error. Corrective

Action Taken and Results Achieved The engineering

groups were briefed as to the inspection

results. These ings were completed

on August 2, 1989. The above noted discrepancy

has been satisfactorily

  • dispositioned

by analysis.

Corrective

Actions to be Taken to Avoid Further Non Compliance

The. following

corrective

actions will be taken to prevent recurrence:

Interim Same as that required for Violation

Icem l.a. Long-Term

  • The "long-term" actions prescribed

for Violation

Item l .e will prevent rence. MI0789-1683A-TC01-NL02

14 .

..... ,, --.

  • . -
  • Date When Full Compliance

Will be Achieved The dates established

for.actions

related to Violation

Item l.e apply here as well. NRC Violation

255/89007-0lg:

FC-756 "HPSI Pump Miniflow Bypass Modification.eu

[Refer to page 19 of NRC Report 50-255/89007 (DRS).] Example Pipe support drawings in p1p1ng support Calculation

No 03378 of FC-756 did not adequately

describe the required weld sizes. Pipe support drawings DCl-8198.1

and DC1-Hl96.2

contained

in support tion No 03378 were reviewed.

The inspector

found that one drawing showed fillet welds at the structural

joints but no weld sizes were specified.

The other drawing showed a 3/16 inch fillet weld with a note "assumed." As a result, the design bases of the welds were not adequately

translated

into the drawings.

CPCo Response As part of the evaluation

of this example, M-107 Sh 2254/2255

were reviewed which are detail drawings for the subject hangers. The two ports *cited were not modified or installed

as part of FC-756. The supports were only evalua.ted

regarding

stresses in relation to the modification.

In both cases, the_drawings

are Rev 0 and are issued as-built per IE Bulletin 79-14. It appear-s that this is a situation

where documentation

from the 79-14 effort may not be completely

However, when past discrepancies

were identified, there was no signficant

impact on analytical

conclusion.

Neither drawing DC1-H198.l

nor DC2-Hl96.2

were utilized as design input to FC-756. After further discussion

on this issue with NRC Region III via telecon on July 26, 1989 and review of the drawings referenced

by the inspector, it was determined

that these drawings were initial IEB 79-14 calculation

file ings of preliminary

status. These drawings do not represent

the final hanger detail drawings referenced

above. Since these calculation

file drawings are not "record" drawings reflecting

as-built condition, and are not referenced (by intent) in our Facility Change Design Document Checklist, they are not input to our facility change process. No further action is required since neither a design change control deficiency

nor inaccurate

record (as-built)

document exists. Therefore, CPCo does not acknowledge

this example. However, reference

example e. for actions to be taken to ensure accurate dimensions

are utilized as* analysis inputs. NRC Violation

255/87007-0lh:

FC-731 "Regulatory

Guide 1.97 Transmitter

Replacement." [Refer to pages 19 and 20 of NRC Report 50-255/89007 (DRS).] Example The seismic stress calculation

assumed an incorrect

center of gravity which was not identified

during the checking process.

15 . *.*:.,*-*

-.-.:*-**

  • .** '* .:: *:_.: '! ... ,' . _..,,-. '* .* .*.,** .:*::.'.-
  • The analysis criteria shown on page 3 required the center of gravity (CG) of the instruments/equipment

to be considered

in the seismic stress calculationso

A review of the rack support bent plate on page 27 found that the CG of the instruments

was not considered

in the seismic stress calculations.

As a

the forces and moments at the rack support attachment

were inadequately lated. Reason for Violation

The analysis addresses

the adequacy of instrument

racks inside the containment

building.

For the GWO 7906, FC-731 job, the work involved modifying

all four instrument

racks. Three of the racks are tied together while the fourth one is by itself. The racks are made out of Unistrut attaching

to the containment

liner plate using bent plates. The instruments

are mounted on the mounting plate which in turn is* bolted to the Unistrut.

Analytical

error based on the failure to consider the center of gravity is acknowledged.

The reason for this

is an error made by the analyst, inadequate

technical

review and.failure

to follow established

procedures.

Corrective

Action Taken and Results Achieved and the The analysis has been revised to include the center of gravity analytical

results represent

an acceptable

as-built condition.

groups have been briefed as to the results of this* inspection.

were completed

on August 2, 1989. All engineering

These briefings

Corrective,Actions

to be Taken to Avoid.Further

Non Compliance

To prevent recurrence

of this or similar discrepancies, the following

corrective

actions will be taken: Interim Same* as* that required for Violation

Item* La. Long-Term

The Plant Administrative

Procedure

will be enhanced by the incorporation

of a technical

review checklist

consisting

of a comprehensive

set of review "prompts." One of the "prompts" will require that the reviewer ensure that all analysis objectives

be carried through to completion.

' In addition, a program will be developed

to provide periodic refresher

training to all design engineers

on design change-related

administrative

procedures.

Date When Full Compliance

Will be Achieved The personal briefings

letter will be issued by September

1, 1989. Procedural

enhancements, as well as required training on the enhancements, will be pleted by January 1, 1990. The program for periodic refresher

training will be in place by March 1, 1990. MI0789-1683A-TC01-NL02

16 *.:.

  • NRC Violation

255 /89007-0li:

FC-731 "Regulatory

Guide 1. 97 Transmitter

Replacement." [Refer to page 20 of NRC Report 50-255/89007 (DRS).] Example The calculated

bending stress "fbx" shown on page 27 of the analysis was in error. The 5,645 psi should be 5,976 psi. The checker did not identify this calculational

error. Reason for Violation

Analytical

error based on the inaccurate

bending stress is acknowledged.

The analysis has been revised to incorporate

the accurate "fbx" value and the analytical

results represent

an acceptable

as-built condition.

Corrective

Action Taken and Results Achieved All engineering

groups have been briefed as to the results of this inspection.

These briefings

were completed

on August 2, 1989. Corrective

Actions to be Taken to Avoid Further Non Compliance

To prevent recurrence

of this or similar discrepancies, the following

corrective

actions will be taken: Interim Same as that required for Violation

Item La. Long-Term*

Same as that required for Violation

Item l.h with the exception

that a "prompt" will be included on the technical

review checklist

to require that the reviewer verify the accuracy of all analysis calculations.

Date When Full Compliance

Will be Achieved The dates specified

for Violation

Item l.h apply to this item also. NRC Violation

255/89007-0lj:

FC-567 "Core Cooling Instrumentation

Modification." [Refer to page 22 of NRC Report 50-255/89007 (DRS).] Example FC-567 did not address the impact of the increased

load on the inverters, bypass regulators

on the battery chargers.

The inspector

observed that the licensee performed

calculations

to analyze the impact of the increased

loading on the preferred

AC bus supply breakers, cabling to the preferred

busses from their respective

inverters

and on the DC batteries.

However, no calculations

or analyses were evident which addressed

MI0789-1683A-TC01-NL02

17 . . :_ . =** *; ..... ... : . . .. **. ::: :.

. :.' ..... -. the impact on the inverters, bypass regulator

or the DC system battery chargers.

This resulted in a concern for the capability

and capacity of these Class lE systems to perform their safety-related

functions.

The inspector

concluded

that the licensee had failed to employ adequate design controls during the design stage of the facility change in that the full impact of the increased

loading was not analyzed.

In response to the inspector's cern, the licensee verified the present loading on the respective

inverters

and battery chargers which includes the increase resulting

from the instrumentation

additions.

The inspector

concurs that based on the licensee's

reported inverter and battery charger outputs, plus the anticipated

emergency

loading, per the Design Basis document, the inverters, bypass regulator

and battery chargers will not be overloaded.

However, the licensee failed to employ adequate design controls which would have included analyses of all impacted components.

Reason for Violation

Facility Change FC-567 (Core Cooling Instrumentation)

added a Reactor Vessel Level Monitoring

System (RVLMS) to the plant design. Addition of this system resulted in an increased

load of 600VA on each of preferred

busses, YlO and Y20, the associated

DC to AC inverters, bypass regulator

and DC system. In reviewing

this design change, the inspector

identified

that, although the effect of the increased

load on the batteries

was determined, the facility change did .not. address the impact of the increased

load on the inverters, bypass regulator

or the battery chargers * . * . The apparent failure to adequately

verify and check design resulted from inadequate

documentation

of assumptions

and engineering

judgement

utilized to determine

the impact of the load additions

to the preferred

busses. The effect of the load increase on the batteries

was determined

based on the undocumented

assumption

that the batteries

were the limiting component.

In order to mine the effect of the increased

load on the batteries, the new loading on each of the preferred

buses and thus the loading on each of the inverters

was determined.

No documentation

was provided, however, comparing

the revised load on the invertors

against their design. rating. A similar situation

existed for the battery chargers.

The new battery load profile was determined

based on the increased

loads, however, no documentation

of the effect of the new load profile on the battery charges was provided.

Subsequent

evaluations

have been performed

to document that the load additions

to the preferred

buses performed

by FC-567 did not result in overloading inverter, battery charger or bypass regulator.

The results of these evaluations

are summarized

below: 1. The maximum loadings on the YlO and Y20 buses during emergency

conditions

are 4378VA and 5456VA respectively.

This includes the loads added by FC-567. The design rating of the invertors

is 6000VA and thus the tors are not overloaded.

MI0789-1683A-TC01-NL02

18 ., .... .._: .*

  • *. * .....

.. *.-.,: .. *;-*: **.***.***

.. ** .. *. *.".: '*':.':-__ ._ .. _* . ....... *\ '.: .. ;.*-o*.** . ,, . : .... **_ cl I .!

. ' * -* _._ .. _. . ... ..... * ... 2. The steady state constant DC current requirements

during emergency tions is 253 amps for the most heavily loaded battery (Battery No 2) after approximately

ten minutes. This is less than the 400 amp combined rating of the two battery chargers connected

to each DC bus. The battery chargers thus have sufficient

capacity to provide the DC steady state load with capacity remaining

for restoration

of the batteries

following

the discharge

during the first ten minutes. 3. The bypass regulator

is utilized to provide temporary

power to a preferred

bus from a non-class

lE source to allow maintenance

to be performed

on an inverter.

The initial response made to the inspector

regarding

operation

of the bypass regulator

was incorrect.

The bypass regulator

is not shed during accident conditions

and could be subject to the emergency

load. Operation

with the bypass regulator

energizing

the preferred

buses is, however, restricted

by Administrative

Procedures

to less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> (eight hours for some buses). This restriction

minimizes

the amount of time that the bypass regulator

would be subject to providing

power to a preferred

bus during accident conditions.

The limiting component

of the bypass regulator

is the isolation

transformer*

This transformer

is rated at 5000VA. As discussed

earlier, the maximum loading on

bus Y20 is 5456VA. Thus the load on the bypass regulator

could be exceeded if it were connected

to bus Y20 during an emergency

condition.

This discrepancy

had been previously

identified

by the Configuration

Control Project and Discrepancy

Report F-CG-88-002

was initiated.

This discrepancy

was quently closed out by assuring that the output voltage of the bypass regulator

will be maintained

at acceptable

levels at up to 150% of the nameplate

rating of the tr...an*sformer.

Corrective

Action Taken and Results Achieved All engineering

groups havebeen briefed on the results of this inspection.

These briefings

were completed

on August 2, 1989. -An engineering

analysis was per.formed

documenting

that the inverter and * battery charger were not overloaded

as a result of this modification.

-The Configuration

Control Project had.previously

identified

the concern with the bypass regulator

and has subseq'uently

resolved and closed out the crepancy.

Corrective

Actions to be Taken to Avoid Further Non Compliance

To prevent recurrence

of this or similar discrepancies, *the following

corrective

actions have or will be taken: Interim Same as that required for Violation

Item l.a * MI0789-1683A-TC01-NL02

19 *.*:-: * .. " .-* *,::: >*'. -:-,,. .. ........ **. *'* ----

  • * Long Term Upgrades have been initiated

to our station load analysis program to account for full aystem impact of load additions.

In the

the load carry1ng

ability of load carrying components

will be assessed in addition to assessing

power supplies.

Specifically, the load carrying capability

of the battery chargers and preferred

power inverters

will be assessed, along with battery capacity whenever load is added to the 120V preferred

AC system. Periodic training as proposed for Violation

Item l.a will feature the ities of modifications

support groups such as: Power Resources

and Systems Planning (for load addition

and -Systems Protection

and Planning (for breaker

and -Energy Supply Services Civil Section (for structural

analyses).

It is expected that this training wil-1 maintain the design engineer's

awareness

as to what must be taken into account when adding electrical

or mechanical

load to plant systems. Date When Full Compliance

Will be Achieved Personal briefings

letter will be issued by September

1, 1989. The station load analysis program upgrades will be completed

by September

1, 1989. A gram for the periodic training on the capabilities

of support groups will be in place by -March 1, 1990. NRC Violation

25S/89007-0lk:

FC-760-02 "Control Room Emergency

Lighting." [Refer to pages 23.and 24 of NRC Report 50-255/89007 (DRS).] Example This FCcontained

an unverified

assumption

in that the assumption

that emergency

lighting fixtures were rigit was never proven. Engineering

Analysis EA-FC-760-2-001

was performed

to analyze the mounting of the lighting fixtures to be installed.

Section V of this document, referring

to the DC lighting fixtures, states in part "Assume the lighting fixture is rigid **** " This assumption

is not justified

in the analysis document and, in fact, the fixture (McMasters-Carr

Lampholder, Catalog No 1700Kl2) employs a swivel joint. The lighting fixtures are not safety-related, but mounting is considered

critical since they are in the control room and failure could endanger personnel

or safety-related

devices * MI0789-1683A-TC01-NL02

20 : * .. *:-. -**-. . .. .

-*. ' **:*:.-:***

Reason for Violation

The McMasters-Carr

Lampholder, Catalog No 1700Kl2 fixture has been used for the control room emergency

lighting design associated

with

The fixture employs a swivel joint for adjusting

only. The adjustment

is made in one plane only. The mechanism

used is a bolted connection

and the lamp tion is fixed in place by the friction from tightening

the bolt. Tightening

the bolt keeps the joint tight in service and keeps it from swiveling.

The assumption

of rigidity of the fixture service was based upon the analyst's

interpretation

of catalog data. That assumption

is considered

appropriate.

Plant administrative

design control procedures

required, and currently

that all analytical

assumptions

be documented, acknowledged

in terms of icance and technically

reviewed (Reference

1). The identified

discrepancy

results from failure to implement

this procedural

requirement.

Corrective

Action Taken and Results Achieved All e.ngineering

groups have .. been briefed as to the results of this inspection.

The briefings

were completed

on August 2, 1989. Corrective-Actions

to be Taken to Avoid Further Non Compliance

Interim * Same* as that required for Violation

Item 1.a. * Long-Terni-

-Develop a program to provide periodic refresher

training on "the requirements

of plant administrative

design change procedures

related to engineering

analyses.

Date When Full Compliance

Will be Achieved The personal briefings

letter will be issued by September

1, 1989. The program for periodic refresher

training will be in place by March 1, 1990. NRC Violation

255/89007-011:

SC-87-090

Water Leak Detection

Set Point. [Refer to page 27 of NRC Report 50-255/89007 (DRS).] Example Specification

Change No 87-090 changed the Service Water (SW) leak detection

set point from 75 gpm to 300 gpm

verifying

what size of SW piping break in the containment

air coolers would result in a 300 gpm delta-flow

alarm * MI0789-1683A-TC01-NL02

21 -.... * *** *i,.. :. * .. *:. -... . -.

  • CPCo Response The containment

SW leak detection

system monitors SW flow into and out of the reactor building and provides an alarm in the control room when a preset differential

flow is exceeded.

SC-87-090

changed the differential

flow alarm set point from 75 gpm to 300 gpm. The instrumentation

loops for the leak detection

system consist of flow elements 1 differential

pressure transmitters

with square root output and a differential

flow switch with a time delay output. A time delay of approximately

15 seconds is incorporated

to eliminate

nuisance alarms due to flow noise spikes and still allow timely indication

of leakage. The SW leak detection

system is utilized as a post accident monitor. During accident conditions, without all control rods

water leaking inside the containment

building can dilute the containment

building sump water to a boron concentration

low enough to allow the reactor to return to a power state. As noted in Engineering

Analysis EA-SC-87-090-1, the basis for the original alarm set point of 75 gpm was engineering

judgement.

Further, the new 300 gpm set.point.was

selected based on the total inaccuracies

of the instrumentation

loop, times the full scale flow of the transmitters.

Use of instrument acies within the engineering

analysis provides a conservative

determination

based on instrument

capabilities.

As noted in the inspection

report, the engineering

analysis did not provide justification

that the set point meets the design intent of the SW leak tion systeqi..

However, the adequacy of the set point with respect to the tion system.design

intent was presented

and evaluated

as part of the written l0CFR50.5-9

.. (Safety Evaluation)

analysis for the SC. The safety evaluation

is part of the SC package and was reviewed with other supporting

documentation

comprising

the SC package by the Plant Review Committee (PRC) on March 2, 1987. Therefore, Consumers

Power Company does not acknowledge

this example as a lation of 10CFR50, Appendix B, Criterion

III. NRC Violation

255/89007-0lm:

SC-87-163 "Upgrade Feedwater

Flow Transmitters." [Refer to pages 27 and 28 of NRC Report 50-255/89007 (DRS).] Example Specification

Change No 87-163 added a series voltage

zener diode to the feedwater

flow transmitter

instrument

loop for Transmitter

Nos FT-0701 and FT-0703 without specifying

the required zener diode design parameters.

Reason for Violation

upgraded FW flow transmitters

FT-0701 and FT-0703 to Rosemount

units. The supply voltage requirements

for an 1151 DP transmitter

is 12 Vdc to 45 Vdc (4 mA to 20 mA current loop). The transmitter

will operate within this voltage range as a function of load resistance.

The load resistance

for the FW flow transmitters

is approximately

300 ohms. The nominal supply voltage requirements

for the transmitter

as determined

from the Rosemount

functional

specifications

was approximately

19 Vdc. MI0789-1683A-TC01-NL02

22 *__:_-.*-:-

    • .. ,._ *. ,. : o:. *..*.. * .. **:
  • .* , ..... *. :, .. ,._ *,*

c* * ., .-.

  • * As part of the SC, a zener diode was installed -in the series current loop to lower the power supply output voltage to the operating

voltage of the Rosemount

flow transmitter.

During development

of the SC, the design criteria for the zener diode, that is the required voltage was determined

to be 11 Vdc. This design criteria is shown on Drawing F-69 Sh 1, Rev 22 of SC-87-163.

As a result of this criterion

being stated within the SC package, the proper zener diode was installed

and as stat-ed in the inspection "the zeners were performing

their function." Therefore, Consumers

Power Company does not specifically

acknowledge-this

example as stated. While the design criterion

was detailed sufficiently

within the SC to provide for installation

of the proper zener diode, Consumers

Power Company acknowledges

the need for design packages to contain documentation

which provides the bases for engineered

changes. The failure to include the required enigneering

analysis which served as the basis for the design criterion

presented

within SC-87-163

has been attributed

to a weakness within the SC process regarding

documentation

of engineered

decisions.

Corrective

Actions Taken and Results Achieved In that the proper zener diode was prescribed

and installed, and resulted in the equipment

affected by the modification

being capable of performing

their design function, no immediate

corrective

actions have been undertaken.

All engineering

groups were briefed on the results of this inspection.

The briefings

were completed

on August 2, 1989. Correctiv.e .Actions to be Taken to Avoid Further Non Compliance

Interim Same as that required for Violation

Item 1.a. Long-Term

To ensure that adequate bases are developed

to justify the change and that these bases are technically

reviewed and documented

within the specification

change package, plant *administrative

procedures (Reference

5) will be revised either to require that a formal engineering

analysis (per Reference

1) or a new SC change justification

form be utilized for the following:

To provide a reason for the change (in part by describing

why the existing condition

is less than desired and why the change will improve as-built dition), ., *:ra describe the design basis function of the system within which this change is being made and justification

that this function will be maintained, -To identify the full impact

change will have on the system within which this change is being made and on potential

interfacing

systems, MI0789-1683A-TC01-NL02

23 ;---* . *:..:.::--.**

.*--... :. .. :.

,, .. ,, .. -....... ;:., :*. * .. **.:::;1-'* . :"'.*

  • .. * *.*. .... :. -To identify critical functional

or physical features that must be met by the change to achieve the desired as-built condition (this may require formal engineering

analysis per Administrative

Procedure

9.11), and -To describe how these critical features will be verified (eg, inspection

or test). Date When Full Compliance

Will Be Achieved The personal briefings

letter will be issued by September

1, 1989. The revision to administrative

procedures

will be completed

by January 1, 1990. In addition, a program will be developed

by March 1, 1990 to provide engineers

with periodic refresher

training on SC-related

administrative

procedures.

NRC Violation

255/89007-0ln:

SC-88-069 "Upgrade Safety Injection

Tank Pressure Transmitters." [Refer to pages 29 and 30 of NRC Report 50-255/89007 (DRC).] Example Specification

Change No 88-069 added a series voltage regulating

zener diode to the safety injection

tank. pressure transmitter

instrument

loops for Transmitter

Nos PT-0361, 0367 , 0369, and 0371 without specifying

the required zener diode design parameters.

Reason for_Violation

SC-88-069

safety injection (SI) tank pressure transmitters, PT-0363, PT-0367, ..PT-0369

and PT-0371 to Rosemount

units. This modification, like SC-87-163, introduces

a zener diode in series current loop to lower the power supply output voltage to the operating

voltage of the Rosemount

pressure mitter. During development

of the SC package for this modification, engineering

analyses.

were performed

to* determine

the design criterion

for the zener diode. However, as evidenced

by the transmitter

voltage measurements

taken during the inspection, an error was made .in the analysis.

This error was not identified

during design reviews of the modification

package due to the lack of a mented engineering

analysis within the SC package. Further, after modification

installation, no preoperational

testing specific to transmitter

operating age was conducted.

Therefore, the failure to attain a completed

modification

with all equipment

operating

within manufacturer

prescribed

operating

ranges has been attributed

to weaknesses

within the Specification

Change process regarding

documentation

of engineered

options and adequate preoperational

testing. Corrective

Action Taken and Results Achieved The power supply output voltage, zener diode vuic:age and transmitter

voltage for all the upgraded Rosemount

transmitters

associated

with SC-88-069

were measured.

As indicated

within the inspection

report, the transmitters

were found to be operating

outside their nominal operating

of 14 Vdc to 45 Vdc by.up MI0789-1683A-TC01-NL02

24 .. * '* .,. **:*

    • to 12.62 Vdc. As a result of this finding, all other installed

transmitters

having zener diodes in their circuit had power supply, zener diode and mitter voltages measured.

From these measurements, two additional

non-safety

related transmitters (PT-5117 and PT-0927) were identified

to be operating

outside their prescribed

nominal* operating

range. Due to these findings, SC-89-162

was generated

to replace the improper zener diodes. As part of this modification

package, an engineering

analysis was completed

and technically

reviewed to assure proper zener diode selection

and to provide documentation

of design criterion.

The analysis was completed

on August 1, 1989. Additionally, work orders were generated

on June 5, 1989 to inspect the transmitters

that were operating

outside their nominal operating

range. Presentations

to all engineering

groups have been conducted

to. brief engineers

as to the NRC engineering

team inspection

results. These presentations

were completed

on August 2, 1989. Corrective

Actions to be*Taken to Avoid Further Non*Compliance

Interim Personal letters will be sent to all engineers

by September

1, 1989 describing

the NRC observed weaknesses

and requiring

that the engineer look at SC's rently being engineered

for similar problems.

Long Term -The plant administraive

procedure (Reference

5) revisions

described

for tion l.m apply as do the following:

-Revise plant administrative

procedures (Reference

1) to provide the technical

reviewer of an engineering

analysis a checklist

to assure a thorough, accurate and auditable

analysis.

The checklist

would feature a set of "prompts" in part to verifyall

analytical

input, assumptions

and calculation.

-Revise administrative

procedures (Reference

5) to require that pre-operational

testing be specified

as part of SC engineering

either in a work request or test procedure

prior to technical

review of the SC engineering

package. In addition, require that the test specification

align with the critical features identified

as part of the documented

change basis (see procedure

changes identified

for Violation

Item l.m). Date When Full Compliance

Will be Achieved Administrative

procedures

will be revised by January 1, 1990. Training on the procedure

revisions

will also be complete on January 1, 1990. In addition, a program will be in place by March 1, 1990 to provide periodic refresher

training on SC-rela.ted

procedures.

SC-89-162

will be performed

by November 15, 1989. The work orders to inspect the affected transmitters

will be completed

by December 1, 1989. MI0789-1683A-TC01-NL02

25 ; .....

NRC Violation

255/89007-0lo:

SC-88-069 "Upgrade Safety Injection

Tank Pressure Transmitters." [Refer to pages 29 and 30 of NRC Report 50-255/89007 (DRS).] Example Specification

Change No 88-069 did not consider the effect of instrument

loop loading on the power supply; as a result, the load adjustment

resistor setting which matches impedance

for maximum power transfer was not specified

or adjusted.

Reason for Violation

SC-88-069

upgraded safety inJection (SI) tank pressure transmitters, PT-0363, PT-0367, PT-0369 and PT-0371 to Rosemount

units. This modification, like SC-87-163, introduces

a zener diode in series current loop to lower the power supply output voltage to the operating

voltage of the Rosemount

pressure mitter. While reviewing

this SC the inspector

reviewed the SI tank pressure loop power supply manual. As-stated

intheinspectionreport; "the Foxboro Model 610A power supply is designed to furnish power to a single electronic

transmitter.

The nominal DC output voltage is 80 volts. The manual also states that the output load resistance

must be 600 ohms +10; -20 percent. The SC package did not determine

the load resistance.

The manual provided detailed instructions

to sum the input resistances

of all the receivers

in the loop (excluding

the

and to adjust the load adjustment

dial on the power supply to the difference,,between

the loop resistance

and 600 ohms. Subsequentcto

the inspection

on July 25, 1989, plant engineering

personnel

contacted

the power supply vendor to discuss the inspector's

concern regarding

the affects of increased

load resistance

on the power supply. During this conversation

the vendor noted that the specific requirement

for a load tance of 600 ohms applies only to Foxboro transmitters

connected

to Foxboro power supplies and that applied power supply load resistance

is based on the voltage requirements

of the associated

transmitter.

The voltage requirements

of the Rosemount

transmitters

installed

under SC-88-069

are addressed

in the modification

package, however, documentation

was not provided regarding

resultant.

power supply l6ad resistance.

Failure to include applicable

documentation

within the modification

package has been attributed

to a lack of guidance being provided within Administrative

Procedure

9.04, fication Changes." Corrective

Action Taken and Results Achieved Presentations

of the inspection

results were made to all affected engineering

groups. These presentatioris

were completed

on August 2, 1989. Corrective

Actions to be Taken to Avoid Further Non Compliance

Personal letters will be sent to all engineers

describing

the NRC engineering

inspection

results by September

1, 1989. The letters will require that neers review SC packages currently

being engineered

for similar problems.

MI0789-1683A-TC01-NL02

26 -:* : .. \_._ .:: ;*'.. ,. -** :=. * .. : ** _.-:-: .*

  • . '. *--.*. -* .""; . . *.* .. '<' * .* , *' . ** ...

.. *. . '*

  • -The plant administrative

procedure

revisions (and training)

described

for lation Items l.m and l.n effectively

respond to this item also. Date When Full Compliance

Will be Achieved Administrative

procedures

will be revised by January 1990. Training in the procedure

revisions

will also be complete on January 1, 1990. In addition, a program will be in place by March 1, 1990 to provide periodic refresher ing on SC-related

procedures.

NRC Violation

255/89007.0lp:

SC-88-102 "Upgrade Containment

Pressure Transmitter

PT-1812." [Refer-to

pages 31 and 32 of NRC Report 50-255/89007 (DRS).] Example Specification

Change No 88-102 installed

a different

model containment

pressure transmitter

for Transmitter

No PT-1812 without performing

a seismic analysis to determine

the acceptability

of installing

the new transmitter

on the old mounting.

Reason for-Violation

SC-88-102

upgraded containment

building pressure transmitter, PT-1812 to a Rosemount

pressure transmitter.

The pressure loop affected by the modification

provides indication

only and is not required to be operable for any analyzed event. The pressure transmitter

is mounted off piping associated

with

ment Penetrcation

MZ-17 and is physically

located between the manual instrument

isolation

valve and the manual containment

isolation

valves. The manual instrument

isolation

valve is maintained

open to allow pressure transmitter

operation.

Therefore, the primary containment

boundary includes PT-1812. While processing

SC-88-102, engineering

personnel

  • failed to identify that the pressure transmitter

constituted

part of the containment

boundary.

This ure is attributed

to the following

factor: The administrative

procedure

for Specification

Changes (Reference

5) requires that the engineer consult the Equipment

Data Base (EDB). The EDB-Q-Listing

identifies

the pressure retaining

and structural (seismic)

requirements

to be met by the equipment.

The existing Q-Listing

in the EDB for PT-1812 indicates

that the transmitter

function is not safety-related, there are no pressure retaining

requirements, and that the structural

mounting is not safety-related.

This specific Q-Listing

needs to be reviewed and revised as necessary.

Given accurate EDB information, the existing_

SC checklist "prompts" which also existed at the time this deficiency

occurred, are sufficient

to identify the governing

design codes, standards

and regulatory

guides to be complied with. Corrective

Actions Taken and Results Achieved A formal seismic engineering

analysis has been initiated

to document the adequacy of the existing transmitter

mounting and the associated

tubing. MI0789-1683A-TC01-NL02

27 ;..&.. ',' :*,* : .:*:

  • . ..... , .* *:: :.:;.: *;* .. .. . , .. :" : .

--;_,.

The results of the inspection

have been presented

to all engineering

groups. These presentations

were completed

on August 2, 1989. Corrective

Actions to be Taken to Avoid Further Non Compliance

The existing Q-List interpretation

for PT-1812 will be reviewed for accuracy and revised as necessary.

In addition, if it is determined

that the tation is in error, other interpretations

will also be reviewed to identify the breadth of the discrepancy.

These additonal

reviews will cover, as a minimum, interpretation

for other instrumentation

serving pressure retaining

functions.

If additional

reviews indicate the need, additional

clarification

in

tive P.rocedures

related to Q-List interpretation (Reference

6) will be provided and engineers

will be trained. Further, a review will be conducted

to ensure the seismic qualification

of other similar configurations.

In addition, a program to provide periodic refresher

training on procedures

related to Q-Listing

will be developed.

Finally, a portion of the Configuration

Control Project involves the tion of the Q classification

for approximately

16,000 components

in the Plant's equipment

data base. This activity is currently

scheduled

to be completed

by the end of-1990 and will provide a sound technical

basis for future tions. Date When F.ull Compliance

Will Be Achieved The existing Q-List interpretation

for PT-1812 will be reviewed for accuracy and revised necessary)

by September

15, 1989. If it is concluded

that the PT-1812 interpretation

is in error, interpretation

for other similar tions will be completed

by November 1; 1989. If these additional

reviews tate the need for procedural

clarification, the procedures

will be enhanced by January 1, 1990 and all engineers*

will be trained on the enhancements

by this date. The program for periodic refresher

training on Q-Listing

will be in place by March 1, 1990. The additional

seismic review will be completed

by October 1, 1989. NRC Violation

255/89007-0lg:

EA-FC-722-10 "N2 Backup Test Evaluation

for Station 5," February*21, 1987. [Refer to page 15 of NRC Report 50-255/89007 (DRS).] Example The

stated that the nitrogen usage rate was 32.5 psig AP/hour based on the test results from Functional

Test T-FC-722-501-01.

However, the test results failed to account for the post test calibration

shift of 5 psig for of the pressure gauges. By incorporating

this additional

factor, the usage rate is increased

to 33.75 psig AP/hour. MI0789-1683A-TC01-NL02

28 . *. . -:* ** '7. *. ,-'* .. .*,* . ,* ' *.*.:* ... * *,'* *. **-:*** ."'-*,' .. * .** .... *.,_ ..

.; .....

. ' * * Using the above rate in the calculation

reduces the "actual operating

period" from 10.3 days to 9.93 days. This is below the assumed acceptance

limit given in the original calculationo

No safety significance

was attributed

to this occurrence;

however, the instrument

accuracy requirements

specified

in the test procedure

were inadequate

as noted belowo -Procedure

No T-FC-722-0501, "CV Air Supply -N2 Backup Performance

Test," Revision O, February 6, 1987. Under Special Tools/Equipment, a 0-3000 psig pressure gauge is called for. The accuracy specified

is +/- 2% minimum. This equates to a +/- 60 psig accuracyo

The acceptance

criteria for three of the four nitrogen stations ranged from 24 psig to 68 psig over the four hour span of the performance

test. CPCo Response CPCo does not acknowledge

this example as a violation

of

Appendix Criterion

III Design Control," based upon the following.

1. Page 6 of 32 of "Palisades

Nuclear Plant Modification

Procedure

No T-FC-722-501," and "Temporary

Change to a

Change No FFC-87-006, specified

calibrated

analog pressure gauges, 0-3000 psig, +/- 2% minimum accuracy and that these gauges shall be calibrated

in accordance

with 2.4, reference

paragraph

6.1.5. 2. The intent of specifying

a minimum accuracy of the test gauges was to allow qualified

test personnel

the. flexibility

to utilize test gauges of a higher degree"of

accuracy if available.

3. The intent of Reference

2.4 (Palisades

Nuclear Plant Administrative dure S.07, "Control of Measuring

of and Test Equipment"), paragraph

6.1.5, is to require performance

of pre-and post-calibrations

of the test gauges. These calibrations

were performed

as

Pre-and Post-Calibrations

of the gauges are utilized to determine/verify

the actual gauge accuracy as utilized during the test. 4. As stated in paragraph

1 of page 16 of NRC Report No 50-255/89007 (DRS), "Additional

reviews by the inspector

disclosed

that the pressure gauges actually used has a specified

accuracy of +/- 1%. In addition, pre-test and post-test

calibration

data indicated

that the actual accuracy was closer to +/- 0.1%." This statement

reinforces

the intent of specifying

and the requirement

to perform pre-and post-calibrations (reference

Item 83) of the gauges. 5. Acceptance

criteria for Palisades

Nuclear Plant Modification

Procedure

No T-FC-722-501

are established

via calculation

and are not affected by gauge inaccuracies

which are linear and constant throughout

the test range *

29 ... .: . ' . . ...... *--*

  • * Based upon the above the specification

of test gauges, 0-3000 psig, +/- 2% accuracy was appropriate

and in accordance

with Palisades

Nuclear Plant Administrative

Procedures--.

Plant administrative

design control procedures (Reference

2) required, and currently

require, that modification

test procedures

feature requirement

-The use of calibrated

test equipment

of the proper range and accuracy to determine

conformance

to specified

acceptance

criteria, -Test equipment

be identified

along with its calibration

status, and -Acceptance

criteria (with appropriate

tolerances)

be specified

to effectively

determine

whether critical design requirements

have been satisfied.

Thus, no corrective

action is deemed necessary.

NRC Violation

255/89007-0lr:

SC-87-163 "Upgrade Feedwater

Flow Transmitters." [Refer to pages 27 and 28 of NRC Report 50-255/89007 (DRS).] Example Specification

Change No 87-163 added a series voltage regulating

zener diode to the FW flow transmitter

loop for Transmitter

Nos FT-0701 and FT-0703 without specifying

__ the measurement .of. the power supply, zener, and transmitter

voltage as acceptance*

criteria to determine

if the transmitter

loop was operating

within its-design

limits. Reason for Violation

SC-87-163

upgraded FW flow transmitters

FT-0701 and FT-0703 to Rosemount

units. The supply voltage requirements-

for a 1151 DP transmitter

is 12 VDC to 45 VDC (4 mA to 20 mA current loop). The transmitter

will operate within this voltage range as a function of load resistance.

The load resistance

for the FW flow transmitters

is approximately

300 ohms. The nominal supply voltage requirement

for the transmitter

as determined

from the Rosemount

functional

specifications

was approximately

19 Vdc. As part of the SC a zener diode was installed

in the series current loop to lower the power supply output voltage to the operating

voltage of the Rosemount

flow transmitter.

During the inspection, the NRC inspector

identified

that the SC package did not contain post installation

power supply output voltage urements.

Further, it did not contain zener diode and transmitter

operating

voltages following

modification.

The failure to adequately

specify necessary

preoperational

testing requirements

on the work orders which implemented

the SC has been attributed

to weaknesses

within Administrative

Procedure

9.04. Currently, no guidance exists as to the type of

which may be appropriate, nor does the procedure

specify the need to document testing performed

on implementing

work orders or within the SC package.

30 . *** ..............

  • .*:***:_-

.. *. . .. ., .. ... ......

Corrective

Actions Taken and Results Achieved As noted within the inspection

reportp the power supply output voltage, and the zener diode and transmitter

operating

voltages were measured.

From these urements it was determined

that all components

were performing

their design function within manufacturer

specifications.

Presentations

have been made to engineers

discussing

the results of the recent NRC engineering

inspection.

These presentations

were completed

on August 2, 1989. Corrective

Action to be Taken to Avoid Further Non Compliance

Personal letters will be sent to all engineers

on or before September

lp 1989 describing

the results of the NRC inspection

and requiring

that SC's currently

being managed be reviewed for similar problems.

Date When Full Compliance

Will be Achieved The procedure

revisions

for Violation

Items l.m and l.n will effectively

respond to this item. NRC Violation

255/89007-0ls:

SC-88-069 "Upgrade Safety Injection

Tank Pressure Transmitters." [Refer to pages 29 and 30 of NRC Report 50-255/89007 (DRS).] NRC Identi£ied

Discrepancy

Specificai:ion

Change No 88-069 added a series voltage regulating

zener diode to the safety injection

tank pressure transmitter

loops for Transmitter

Nos PT-0363, 0367, 0379, and 0371 without specifying

the measurement

of the power supply, zener, and the transmitter

voltage as acceptance

criteria to determine

if the transmitter

loop was operating

within its design limits; and also did not specify acceptance

criteria for determining

the acceptability

of changing the load adjustment

resistor in the power supply. Reason for Violation

Consumers

Power Company's

response regarding

the failure to specify acceptance

criteria to determine

if the transmitter

loop was operating

within its design limits in the preoperational

stage is provided in our response to Violation

Item l.m. In regard to the post modification

stage of this SC, the failure to establish

a program to periodically

measure the pressure transmitter

loop voltages has been attributed

to plant personnel

not considering

all potential

failure modes and effects in the circuit design. Acceptance

criterion

for determining

the acceptability

of changing the load adjustment

resistor in the power supply were not specified

in the SC package. The manual for the Foxboro 610A power supply stated that the output load resistance

for the power supply must be 600 ohms + 10; -20 percent. In matory conversations

with the vendor on July 25, 1989, the requirement

for load resistance

was said to be based on transmitter

limitations, not power supply limitations.

The new Rosemount

transmitters

installed

per SC-88-069

do MI0789-1683A-TC01-NL02

31 . . : ' :* -. . : -. *-: ... ... , .... ....

not have this load restriction

and hence do not have acceptance

criteria as delineated

in the manual. Therefore

this item by itself is not a violation

of 10CFR50-, Appendix B, Criterion

III. It is noted however that the new Rosemount

transmitters

have voltage limitations

and this is discussed

in our response to Violation

Item l.n. Corrective

Actions Taken and Results Achieved Same as that taken for Violation

Item l.n. Corrective

Actions to be Taken to Avoid Further Non Compliance

Procedural

revisions

and tra1n1ng described

for Violation

Item l.n will ively respond to this item. Additionally, preplanned

and periodic control sheets (preventive

maintenance

activities)

will be established

to provide for periodic measurements

of loop voltages.

Date When Full Compliance

Will be Achieved The control sheet program will be established

by October 1, 1989. Violation

'255/87007-02a-b)

lOCFRSO, Appendix B, Criterion

X as implemented

by the Palisades

Operations

Quality Assurance

Program requires, in part, that a program for inspection

of activities-,affecting

quality be established

and executed by or for the zation performing

the activity to verify conformance

with the documented

instructions, procedures, and drawings for accomplishing

the activity and that examinations, measurements, or tests of materials

or products processed

be performed

for each work operation

where necessary

to assure quality. Contrary to the above: This is a Severity Level IV Violation.

NRC Violation

255/89007-02a:

CPCo Drawing M-101 Sheet 5113, Revision O, "Piping Isometric, Auxiliary

Feedwater

Control Valve CV-0736A and CV-0737A Bypass Piping." [Refer to pages 12 and. 13 of NRC Report 50-255/89007(DRS).]

Example A secondary

aspect, associated

with the socket welds, pertains to the quality control (QC) inspection

of the completed

fillet welds. The RIC forms have a column for "QC verification" but for the socket welds in question, the size of the fillet welds was not inspected

by QC. Line No 16 of the RIC form, which specifies

the weld, size, gap, and type of joint was marked "NA" (not applicable)

for all the welds in question under the QC Verification

column. Although all of the welds received a Nondestructive

Testing (NDT) Visual Examination (VT), it is not clear if the size of the welds was verified during these examinations.

Since the size of the socket fillet welds was not specified

on the drawing, nor noted on the RIC form, the NDT examiner would MI0789-1683A-TC01-NL02

32 ** : * '."'!'* *.* :: * .. * ..... ' ..... : ..... '.'-:_: ....... *.** -:-*:**.**

    • . ,
  • .-*.'* .. * ;, ..... * ::* : : .. *: .* ***.* ....... * .. : ........ .
  • have had to determine

the required size in the same manner as previously

described

for the welder. No notation of size nor record of the size calculation

was

in the documentation

provided with the NDT-VT data. In addition, the VT report did not list fillet weld gauges under "Visual Aids Used" giving further indication

that the size of the welds was not checked. As a point of clarification, it should be noted that the VT performed

on the socket fillet welds was in accordance

with American Welding Society (AWS) Dl.l requirements.

This is a structural

welding code and allows portions of fillet welds to be undersized

by 1/16". This is inconsistent

with the requirement

of ANSI 831.1, Power Piping Code which specifies

minimum fillet weld sizes. If the size of the-socket fillet welds was verified by the stated VT examinationp

it cannot be assured that the weld meets the ANSI 831.1 Code requirements.

Reason for Violation

The failure to merit conformance

of the size of the socket fillet welds has been attributed

to a lack of engineering

input to and technical

review of the maintenance

planning for the welding process. Prior to actions taken as a result of recent self-identified

failures to verify weld size (Reference

7), no specific requirements

existed to verify characteristics (weld, type, size contour) of installed

welds. Although Nuclear Operations

Department

Standards

suggest inspection

hold points for weld installation

verification, working level administrative

procedures

did not specify:a

hold point requirement

except for fit up. Corrective'"Action-Taken

and Results Achieved Presentations

to all engineering

groups have been conductep

to review the results of this inspection.

These presentations

were completed

on August 2, 1989. -The Inservice

Inspection (ISI) Section oP the Projects Engineering

Department

has assumed the role of Design Authority

for weld engineering

by revising the RIC to technically

review the maintenance

planner's

specifications.

The purpose of the review is to ensure that appropriate

welding codes are complied with in the areas of weld installation

and post-installation

examination.

-The RIC has been revised to issue the-weld minimum leg length to the field. This will eliminate

the need for the field welder to calculate

the length. The aforementioned

ISI review will assure that this specification

is provided.

-Reference

Violation

255/89007-0lc

for other applicable

actions being taken. Corrective

Actions to be Taken to Avoid Further Non Compliance

Specifying

welding requirements (such as applicable

code, weld material, weld type and weld size) is an engineering

function.

If properly administered

by procedure, the maintenance

planner can (and has) effectively

prescribe

welding MI0789-1683A-TC01-NL02

33 :. . . ' . : . -; : . ':* *:-. . . ': . *. *: **.::-. ,._ *. ,*,_ ... , ..

details for the field provided that adequate input from engineering

exists as a basis. In the past, engineering

input has been limited to welding

tion and/or structural

analysis engineering

sketches which have lacked size dimensions

for the welds. As a result 11 the planner has failed to provide the proper size on the Repair Inspection

Checklist (RIC) thereby requiring

the field welder to determine

and install the proper weld size. This practice fails to meet current expectations

for control of design change implementation.

Although plant administrative

design control procedures

required and currently

require that the design change project engineer determine

code requirements

for assigned projects (Reference

4), and plant maintenance

procedures

required and currently

require that the maintenance

planner specify applicable

code and weld parameters

after consultation

with the Engineering

Department (Reference

3), these procedures

had not been effectively

integrated

to support one another to ensure that weld specifications

from engineering

were accurately

translated

into installation

planning, installation, and post-installation

verification.

As a result, the following

actions have been/will

be taken to prevent rence: Interim Same as that required for.Violation

Item.l.a.

Long-Term

-Enhancements

to .plant design.control

and maintenance

procedures

will be made to more effectively

integrate

engineering

into weld specification

and mately -into weld planning and verification:

Appropriate

welding codes will be included in the Design Input Checklist (Reference

2) to prompt the design engineer to specify appropriate

weld requirements (for installation

and examination)

in the facility change package as part of both conceptual

and detailed engineering.

-Design control procedures

related to engineering

analyses (Reference

1) will explicitly

require that all drawings accompanying

structural/seismic

analyses provide detailed weld information (type, size, material)

for input to the planner. In addition, the procedures

will require that sizing culations

be performed

as part of the analysis.

Finally, a technical

review checklist

will be provided to require that the reviewer ensure that weld information

be accurately

represented

on the analysis drawings.

Plant maintenance

procedures (Reference

3) will require that the maintenance

planner utilize the contents of the facility change package to complete the RIC in specifying

for the field weld installation

and examination ments. The procedure

will require that the planner consult the Design Input Checklist

and structural/seismic

engineering

analyses.

Interim actions related to changes to the RIC and ISI group review of the RIC (as described

above) will remain in effect. MI0789-1683A-TC01-NL02

34 *. *, -;.*; .. *:. ' ....... .. *' .... -. . *.::*****

,: .... . :*

.. ;*,

.. .a.* ' *-**.*. :-*: -.

  • -Design and quality assurance

engineers

will be trained on the appropriate

structural

and piping weld codes and their application

to weld installation

and examination.

The engineers

will also be trained on the above procedural

enhancements.

A program will be developed

to periodically

train design and quality assurance

engineers

on the aforementioned

codes and their application, and on the related design control and maintenance

procedures.

In summary, it is expected that these actions will ensure that proper welding requirements (type, material, size) are specified

by engineeringp

planned by maintenance (with a check on planning by engineering)p

and in turn verified by quality control. Date When Full Compliance

Will be Achieved The personal briefings

by letter will be issued prior to September

lp 1989. Procedure

enhancements

and required training on the enhancements

will be pleted by January 1, 1990. The program for periodic refresher

training will be developed

by March lp 1990. NRC Violation

255/89007-02b:

SC-89-072 (Deviation

Report D-PAL-89-043).

[Refer to page 32 of NRC Report 50-255/89007 (DRS).] Example This

report documented

the undersized

fillet welds on socket welded fittings -for SC-89-072.

This specification

change was necessary

to provide an interim solution to primary coolant system leakage from cold leg drain valves. The change required the

of a new length of two inch schedule 160 pipe with a socket welded cap on each of the four loop drains. Inspection

of all eight socket fillet welds indicated

that none of them met the Code required size of 3/8 inch. During the inspector's

review* of the deviation

report, there were several concerns that apparently

were not addressed.

First, although the corrective

actions appear to recognize

that the current RIC form does not give the welder sufficient

information (specifically

the size of the fillet weld), there was no recognition

that QC did not and was not required to verify the size of the fillet weld. The.undersized

condition

was not discovered

until the authorized

inspector (AI) pointed it out to the licensee.

All of the welds had been reviewed and

by the licensee's

program and yet the size had never been verified.

This is considered

another example of violation

of 10CFR50, Appendix 8p Criterion

X, in that the size of the socket fillet welds was not verified (255/89007-02b).

Reason for Violation

Specifying

welding requirements (such as applicable

code, weld material,

type and weld size) is an engineering

function.

If properly administered

by procedure, the maintenance

planner can (and has) effectively

prescribe

welding MI0789-1683A-TC01-NL02

35 . *.".,'T:'

  • .*. ': .. *: ***-._ .. ___
    • .,. . ... . * .. *.:* *. '. . .. --. _.,*.
  • details for the field provided that adequate input from engineering

exists as a basis. In the past, engineering

input has been limited to welding

tion and/or structural

analysis engineering

sketches which have lacked size dimensions

for the welds. As a result, the planner has failed to provide the proper size on the Repair Inspection

Checklist (RIC) thereby requiring

the field welder to determine

and install the proper weld size. This practice fails to meet current expectations

for control of design change implementationo

Corrective

Action Taken and Results Achieved -Presentations

to all engineering

groups were conducted

to brief engineers

as to the results of this inspection.

The presentations

were completed

on August 2, 1989. -The Inservice

Inspection (ISI) Section of the Projects Engineering

Department

has assumed the role of Design Authority

for weld engineering

by revising the RIC to technically

review the maintenance

planner's

specifications.

The purpose of the review is to ensure that appropriate

welding codes are complied .with in the areas of weld installation

and post-installation

examinationm

-The RIC has been revised to issue the weld minimum leg length to the fieldo This will eliminate

the need for the field welder to calculate

the length. The aforementioned

ISI review will assure that this specification

is provided.

Corrective

Actions to be Taken to Avoid Further Non Compliance

Although .plant administrative

design control procedures

required and currently

require that the design change project engineer determine

code requirements

for assigned projects (Reference

4), and plant maintenance

procedures

required and currently

require that the maintenance

planner specify applicable

code and weld parameters

after consultation

with the Engineering

Department (Reference these procedures

had not been effectively

integrated

to support one another to ensure that weld specifications

from engineering

were accurately

translated

into installation

planning,.

installation, and post-installation

verification.

As a result, the following

actions have been/will

be taken to prevent rence: Interim Same as that required for Violation

Item l.a. Long-Term

-Enhancements

to plant design control and maintenance

procedures, and to ESS Departmental

guidelines

will be ***ade by January 1, 1990 to more effectively

integrate

engineering

into weld specification

and ultimately

into weld ning and verification:

-Appropriate

welding codes will be included in the Design Input Checklist (Reference

2) to prompt the design engineer to specify appropriate

weld requirements (for installation

and examination)

in the facility change package as part of both conceptual

and detailed engineering.

MI0789-1683A-TC01-NL02

36 . , ... 'i--: ' .. . .. ' ....... ;** _. **:*: I

. '* ,. ' .. Design control procedures

related to engineering

analyses (Reference

1) will explicitly

require that all drawings accompanying

structural/seismic

analyses provide detailed weld information (type, size, material)

for input to the planner. In addition, the procedures

will require that sizing culations

be performed

as part of the analysis.

Finally, a technical

review checklist

will be provided to require that the reviewer ensure that weld information

be accurately

represented

on the analysis drawings.

-Plant maintenance

procedures (Reference

3) will require that the maintenance

planner utilize the contents of the facility change package to complete the RIC in specifying

for the field weld installation

and examination ments. The procedure

will require that the planner consult the Design Input Checklist

and structural/seismic

engineering

analyses.

-Interim actions related to changes to the RIC and ISI group review of the RIC (as described

above) will remain in effect. -Design and quality assurance

engineers

will be trained on the appropriate

structural

and piping weld codes-and

their application

to weld installation

and examination.

The engineers

will also be trained on the above procedural

enhancements.

A program will be developed

to periodically

train design and quality assurance

engineers

on the aforementioned

codes and their application, and on the related design control and maintenance

procedures.

In

is expected that these actions will ensure that proper welding requirement-s (t-ype, material, size) are specified

by engineering, planned by maintenance (with a check on planning by engineering), and in turn verified by quality control *. Date When Full Compliance

Will be Achieved *The personal briefings

by letter will be issued prior to September

1, 1989. Procedure

enhancements

and required training on the enhancements

will be pleted by January 1, 1990. The program for periodic refresher

training will be developed

by March 1, 1990. NRC Violation

255/89007-03:

SC-87-344

Low Temperature

Over Pressure Set Points. [Refer to page 28 of NRC Report 50-255/89007 (DRS).] Technical

Specification (TS) No 3.1.8.1.a

requires a low temperature sure (LTOP) power operated relief valve (PORV) lift setting of < 310 psia for Tc < 300°F and TS 3.1.8.1.b

requires a LTOP PORV lift setting 575 psia for Tc < 430°F. Contrary to the above, between August 9, 1988 and February 27, 1989, the PORV as-left setting exceeded the TS requirement

on 17 occasions.

This is a Severity Level IV violation.

MI0789-1683A-TC01-NL02

37 *.-* ***-**-;* . * '* .* .. *.** ...... :* :,-* ;;;. ..... : .. :* .. , .

., I .. * * :* .. * .. Reason for Violation

changed the LTQP protection

system set points for temperature

switches TS-0115 and TS-0125. The LTOP system provides primary coolant system {PCS) overpressure

relief capability

to protect the reactor vessel from the potential

for brittle fracture.

The Palisades

LTOP system is a two channel system which relieves PCS pressure through either of two PORV's. Channel A relieves through PRV-1042B

and channel B relieves through

The system is enabled at two settings.

When the PCS cold leg temperature

is less than or equal to 300°F, the lift set point for the PORV is less than or equal to 310 psia. When the PCS cold leg temperature

is greater than 300°F but less than 430°F, the set point for PORV opening is less than or equal to 575 psia. Above 430°F the LTOP system is not required to be enabled. The LTOP system set points are derived from plant heatup and cooldown limits specified

in Plant Technical

Specifications.

The set points reflect the ature and pressure limits calculated

according

to the requirements

of Appendix G to 10CFR50, using the methodology

provided in Regulatory

Guide 1.99, Revision 2. These set points were enacted with the issuance of Amendment

117 to the Palisades

operating

license on November 14, 1988. At the time the 310 and 575 psia LTOP PORV set points were proposed on the Technical

Specification

change request which resulted in the issuance of Amendment

117, existing Technical

Specifications

did not recognize

the need for LTOP above_300°F.

Instrumentation

existing at this time did not operate above 600 psia had a recognized

accuracy of +/- 22 psia. Therefore, the 310 and 575 psia points were selected to provide the maximum practical

operating

window allawed by exi.sting

plant components

while remaining

bound by 10CFR50 Appendix G limits. The proximate

cause of this condition

is that the set point value which results from the addition of instrument

inaccuracies

is not conservative

with the lift point specified

in Technical

Specifications.

This condition

has been attributed

to poor documentation

within the Technical

Specifications

regarding

the fic lift point value. When the technical

specification

value was derived, Engineering

personnel

subtracted

instrument

inaccuracies

from the 10CFR50 Appendix G limit and arrived at the 310 and 575 psia set points found in Technical

Specifications.

The intent of the Technical

Specification

lift point value is to ensure compliance

with Appendix G. The typical set point methodology, if applied to this situation, would be to provide the applicable

Appendix G limit in TS and then control the actual set point, adjusted for instrument

inaccuracies, through Technical

Specification

Surveillance

dures. As noted in the inspection

report, the issue was identified

in parallel by both the and plant personnel.

At the plant, the issue was identified

during a review of the set point methodology

process utilized at Palisades.

Plant Engineering

personnel

identified

that the PORV lift point had been set at the technical

specification

values of 310 and 575 psia. Setting the lift points at the technical

specification

value, neglecting

instrument

accuracies, could result in the actual lift points being 332 and 597 psia when maximum instrument

inaccuracies

are accounted

for. A review of past performances

of MI0789-1683A-TC01-NL02

38 * '

  • .. * * ,.. .-I -* <.. . / * r * ;:: ** **,: *. . "' .._<:*

. : , ........ ,-:*. Technical

Specification

Surveillance

Procedures

M0-27A through D which provide for functional

testing of the LTOP system, revealed that 29 of the 31 times lift set points (310 or 575 psia) were checked, the set point was greater than the technical

specification

limitc While the lift point did exceed the technical

specification

limit, it was within the acceptance

values provided by 10CFR50 Appendix Ge Corrective

Actions Taken and Results Achieved Plant Engineering

personnel

reviewed the basis for Technical

Specification

3.1.8.1 and Technical

Specification

Surveillance

Procedures

which set the PORV lift points and verified that even if the largest positive instrument

inaccuracy

was added to the technical

specification

lift point, the 10CFR50 Appendix G limit would not be exceeded.

Upon further review it was additionally

identified

that the curve utilized in defining the Appendix G limit has incorporated

a 30 psia measurement

inaccuracy.

In that a Technical

Specification

change request is being prepared for submittal

in support of LTOP protection

system modifications

to be performed

during an upcoming maintenance

outage, a letter of interpretation

was submitted

to the NRC on July 12, 1989 which presented

Consumers

Power Company's

position regarding

continued

compliance

with 10CFR50 Appendix G. Technical

Specification

Surveillance

Procedures

M0-27C and M0-27D 9 which provide setting and

the PORV lift set points were revised on May 11, 1989 to remove the + 22 psia tolerance.

Corrective_Actions

to be Taken to Avoid Further Non Compliance A Technical

Specification

change request will be submitted

which delineates

the requi.red

PORV lift set points to assure continued

compliance

with 10CFR50 Appendix G limits following

LTOP protection

system modifications.

  • An tion of the Technical

Specification

change request development

process is being undertaken

to determine

where enhancements

in the review process are required to preclude future occurrences.

Date When Full Compliance

Will be Achieved Continued

compliance

with the lift set point value specified

in the Technical

Specifications

has been assured by submittal

of Consumers

Power Company's

letter dated July 12, 1989 and the rev1s1ons

to M0-27C and M0-27D. The cal Specification

change request supporting

the planned LTOP protection

system modifications

will be submitted

by October 1, 1989. The evaluation

of the Technical

Specification

change request development

process will be completed

by November 1, 1989. NRC Open Item 255/89007-04:

Consumers

Power Company Drawing M-101 Sheet 5113, Revision O, "Piping Isometric, Auxiliary

Feedwater

Control Valve CV-0736A and CV-0737A Bypass Piping, 11 [Refer to page 13 of NRC Report %-255/89007

(.DRS).] Example 'An additional

aspect was associated

with the size of socket fillet welds: The inspector

noted that the current design practice used by the licensee is sistent with the original Code of construction.

The current practice utilizes MI0789-1683A-TC01-NL02

39 '* ... ; .... "' ,****:::. *:;* .... -,, . ' . "*;. :.-: .. ..;.-.: ,;.* ... -.. . ..... .. .. .... :*"'* '/' --

  • later editions of 831.1 Code which specify the lo09 times the nominal p1p1ng wall thickness.

The original Code of construction

required 1.25 times the nominal wall thickness. -From a technical

standpoint

the current practice is acceptable;

however, this inconsistency

has not been delineated

by the licensee in the FSAR. Pending revision of the

this item is considered

open (255/89007-04).

Reason for Violation

Construction

codes related to 831.1 have not been reconciled

1n a document useable to the modifications

engineer.

Corrective

Action Taken and Results Achieved Presentations

have been made to all engineering

groups on the results of this inspection.

These presentations

were completed

on August 2, 1989. Corrective

Actions to be Taken to Avoid Further Non Compliance

Interim Same as that required for Violation

l.a. Long-Term

Palisades

&taff will complete a reconciliation

of all construction

codes to the latest edit:,.ion

of 831.1. This. action would provide for standardization

of code usage-and

simplify the determination

of code requirements.

This effort will also address the structural

welding code AWS Dl.l. Such reconciliation

will be documented

in plant administrative

design control procedures ence 4). In addition, a periodic training program covering procedural

welding requirements

will be developed.

Upon completion

of the reconciliation

the FSAR will be updated to* identify applicable

codes and standards

and their application.

Date When Full Compliance

Will be Achieved The personal briefings

letter will be issued by September

1, 1989. The ciliation

of construction

codes will be completed

and implemented

into plant. design control procedures

by January 1, 1990. Training on these procedural

revisions

will also be complete by January 1, 1990. The periodic training program will be in place by March 1, 1990. The FSAR will be updated in the next revision following

January 1, 1990. NRC Unresolved

Item 255/89007-06:

SC-89-072 (Deviation

Report D-PAL-89-043).

[Refer to page 32 of NRC Report 50-255/89007 (DRS).] MI0789-1683A-TC01-NL02

40 .--' ...

.. '.* .:-.. --*<.

Example The second concern pertains to the generic aspect of the problem. The licensee appeared to recognize

the programmatic

weakness which contributed

to the problem by revising the RIC form to include the specific weld size. However, there appeared to be no corrective

actions directed toward reviewing

previously

made socket fillet welds for compliance

with Code requirements.

Based on the added complication

that the sizes of fillet welds in general apparently

have not been verified under the licensee's

program, reviews of past work may not be sarily limited to socket welded fittings.

Pending a review of the licensee's

justification

as to why additional

inspection

of previous fillet welds is not required, this is considered

an Unresolved

Item (255/89007-06).

CPCo Response CPCo acknowledges

that no corrective

actions have yet been directed towards reviewing

previously

made socket fillet welds for compliance

with code ments. CPCo plans, however, to select an appropriate

sample of as-built welds and inspect the-welds

during the 1989 maintenance

outage. The sample will be chosen to include a range of weld types. The purpose of the inspection

will be to verify that the weld characteristics (type and size) conform to requirements

set forth in the Repair Inspection

Checklist

and/or applicable

welding code. These field verifications

and resulting

report will be completed

by December 1, 1989. NRC Unresolved

Item 5: Consumers

Power Company Drawing M-101 Sheet 5113, Revision O,. "Piping Isometric, Auxiliary

Feedwater

Control Valve CV-0736A and CV-07-3JA

Bypass Piping." [Refer to page 14 of NRC Report 50-255/89007 (DRS).] NRC Identified

Discrepancy

A further concern associated

with the p1p1ng installation

drawing pertains to the attachment

weld for a bypass piping fitting onto the existing run pipe. For this situation, the drawing did not specify the type of joint nor the weld reinforcement

required.

However, the specified

fitting is a "Weldolet" and as such has an exisitng weld prep on it and requires no additional

design work. Also, the size of the fillet weld cover is specified

in the welding procedure

for this type of full penetration

branch line connection.

The problem arose during the review of the RIC forms for the four branch connection

welds. Although these are full penetration

single bevel groove welds, with fillet weld reinforcement, the RIC form labels these welds as "F.W." indicating

a fillet weld. For Gap Thickness, the RIC form specifies "NA" which would be appropriate

for a fillet weld but not for a full penetration

weld. Since this attachment

must be a full penetration

weld, there was no documentation able to assure that the proper penetration

has been achieved using the fied fillet weld. Additional

review by the inspector

of the NDT Examination

Reports revealed another deficiency.

According

to liquid penetrant (PT) examination

report sheet No MKV-01, welds No 2 and No 13 on line

1/2 did not receive a PT examination

as required by

Specification

M-152(Q) "Field Fabrication

and Installation

of ASME Section Xi Piping fication in a Nuclear Power Plant," Revision 14, September

30, 1986, paragraph

MI0789-1683A-TC01-NL02

41 .... ,.. .,.. . .... '* .. -. . --.. *.**-:**.'... . **.* .. -.

.. *. :*'. "*. -* ,c;, ' *.** '"' ,' * -' ' --

9.1.1. Pending verification

that all four branch attachment

welds are full penetration

welds and resolution

of the PT

this is considered

an Unresolved

Item (255/89007-05).

CPCo Response Reference

NRC Violation

255/89007-02a.

MI0789-1683A-TC01-NL02

42 . -=--***_µ_*

      • ..:___*
  • '*' -... --

. -* ATT0889-0167-NL04

ATTACHMENT

2 Consumers

Power Company Palisades

Plant Docket 50-255 LIST OF REFERENCES

August 10, 1989 1 Page ' ... *.* .. *.* .. ' .: ... :***_-..

References

.. lo Plant Administrative

Procedure (AP) 9.11 "Engineering

Analyses" --i I 2. AP 9.03 "Facility

Change" 3. AP 5.06 "Control of Special Processesn

4. AP 9.06 "Code Requirements

for Maintenance

and Modifications" 5. AP 9.04 "Specification

Changes" 6. AP 9.30 "Q-List" 7. Deviation

Report D-PAL-89-43

-..*. MI0789-1683A-TC01-NL02

1 .... '* : .. : . *. ,: .. ' .... -. . ..... . . .. ' *,*.1 . .-.: :'