August 23, 2006MEMORANDUM TO:James E. Lyons, DirectorDivision of Risk Assessment
Office of Nuclear Reactor RegulationTHRU:Sunil D. Weerakkody, Chief
/RA/Fire Protection Branch Division of Risk Assessment
Office of Nuclear Reactor RegulationFROM:Paul W. Lain, Team Leader NFPA 805 Transition Pilot Program
Fire Protection Branch Division of Risk Assessment
Office of Nuclear Reactor Regulation
SUBJECT:
NFPA 805 SECOND PILOT OBSERVATION VISIT TRIP REPORT, MARCH, 2006 We have enclosed the trip report on the second observation visit of pilot plants transitioning to the risk-informed, performance-based fire protection licensing basis in Title 10 of the Code of Federal Regulations (10 CFR) 50.48(c), (the NFPA 805 Rule). The trip occurred March 27 to 30, 2006 at Progress Energy headquarters in Raleigh, NC. The two Utilities with transitioning
pilot plants; Duke Power for Oconee Nuclear Station and Progress Energy for the Shearon
Harris Nuclear Plant provided briefings. We have included the trip report, the agenda, "parking
lot issues," and Issue Summary Sheets as enclosures to this memo. The handouts from the
meeting are available in a separate file. This tr ip report will be publically available to provide lessons learned to those non-pilot plants transitioning NFPA 805.
Enclosure:
As statedCONTACT:Paul Lain, NRR/DRA/AFPB 301-415-2346 MEMORANDUM TO:James E. Lyons, DirectorDivision of Risk Assessment
Office of Nuclear Reactor RegulationTHRU:Sunil D. Weerakkody, Chief Fire Protection Branch Division of Risk Assessment
Office of Nuclear Reactor RegulationFROM:Paul W. Lain, Team Leader NFPA 805 Transition Pilot Program
Fire Protection Branch Division of Risk Assessment
Office of Nuclear Reactor Regulation
SUBJECT:
NFPA 805 SECOND PILOT OBSERVATION VISIT TRIP REPORT, MARCH, 2006 We have enclosed the trip report on the second observation visit of pilot plants transitioning to the risk-informed, performance-based fire protection licensing basis in Title 10 of the Code of Federal Regulations (10 CFR) 50.48(c), (the NFPA 805 Rule). The trip occurred March 27 to 30, 2006 at Progress Energy headquarters in Raleigh, NC. The two Utilities with transitioning
pilot plants; Duke Power for Oconee Nuclear Station and Progress Energy for the Shearon
Harris Nuclear Plant provided briefings. We have included the trip report, the agenda, "parking
lot issues," and Issue Summary Sheets as enclosures to this memo. The handouts from the
meeting are available in a separate file. This tr ip report will be publically available to provide lessons learned to those non-pilot plants transitioning NFPA 805.
Enclosure:
As stated DISTRIBUTION:
ADAMS RidsNrrAdra (GHolahan)
RidsNrrDra (JLyons)
TQuay MTschiltz RidsNrrDraAfpb
RidsNrrDirsIrib AFPB R/F SDinsmore PKoltay DSolorio. OE DStarkey, OE MSalley, RES JS Hyslop, RES AFPB PFillon, RII
JBradey, RII
RidsRgn1MailCenter
RidsRgn2MailCenter
RidsRgn3MailCenter
RidsRgn4MailCenterADAMS Accession # (Package): ML061530462ADAMS Accession # (Memo): ML061520285 ADAMS Accession # (Trip Report): ML061500468 ADAMS Accession # (Handouts): ML061530193OFFICEDRA:AFPBC:DRA:AFPB NAMEPLainSDinsmoreSWeerakkody DATE08/17/0608/12/0608 /23/06 OFFICIAL RECORD COPY