ML061520375
| ML061520375 | |
| Person / Time | |
|---|---|
| Site: | Byron, Braidwood |
| Issue date: | 06/13/2006 |
| From: | Kuntz R F Plant Licensing Branch III-2 |
| To: | Exelon Generation Co |
| Kuntz, Robert , NRR/DLPM, 415-3733 | |
| References | |
| GL-04-002 | |
| Download: ML061520375 (6) | |
Text
June 13, 2006LICENSEE:Exelon Generation Company, LLC FACILITY:Braidwood Station, Unit No. 2 and Byron Station, Unit No. 1
SUBJECT:
SUMMARY
OF MAY 16, 2006, MEETING WITH EXELON GENERATIONCOMPANY, LLC, TO DISCUSS GENERIC LETTER 2004-02, "POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY RECIRCULATION DURING DESIGN-BASIS ACCIDENTS AT PRESSURIZED-WATERREACTORS"On May 16, 2006, a Category 1 public meeting was held between the Nuclear RegulatoryCommission (NRC) staff and representatives of Exelon Generation Company, LLC (thelicensee), at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville,Maryland. The purpose of the meeting was to discuss the licensee's proposal to delay two modifications identified as part of their response to Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors". A list of attendees is provided as Enclosure 1. The licensee presented information (Agencywide Documents Access and Management SystemAccession No. ML061390034) on planned modifications as they pertain to GL 2004-02, as well as a time line that the modifications are scheduled to be completed for Bryon Station, Unit Nos. 1 and 2, and Braidwood Station, Unit Nos. 1 and 2. GL 2004-02, Requested Information section, request 2.(b) states in part that, "All actions should be completed by December 31, 2007." In the licensee's presentation it was stated that all modifications would becompleted as per the guidelines in GL 2004-02 for Braidwood Station, Unit No. 1, and Byron Station, Unit No. 2. However, the licensee stated that due to on-going testing and evaluationthat two of the modifications planned could not be completed for Braidwood Station, Unit No. 2,and Byron Station, Unit No. 1 until the spring 2008 planned outages for each unit. Therefore, the licensee is planning to submit a request for an extension to the requirements of GL 2004-02.The NRC staff queried the licensee about several issues. The NRC staff asked the licensee if itwere at all feasible to complete all of the modifications at the four units in accordance with the guidance given in GL 2004-02. The licensee stated that it was possible, but would not bepreferable because the modifications would have to be complete without the desired analyses completed. The NRC staff also asked the licensee when they would be submitting their requestfor extension, and when they need a response from the NRC. The licensee state that theywould submit their request within 2 weeks of the meeting, and that they would like the NRC torespond as quickly as possible so they can procure the necessary parts, and begin the required testing. Members of the public were not in attendance and no public feedback was received. Please direct any inquiries to Robert Kuntz at 301-415-3733 or rfk@nrc.gov
. /RA/Robert F. Kuntz, Project ManagerPlant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. STN 50-457 and STN 50-454
Enclosure:
List of Attendeescc w/encl: See next page Please direct any inquiries to Robert Kuntz at 301-415-3733 or rfk@nrc.gov
. /RA/Robert F. Kuntz, Project ManagerPlant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. STN 50-457 and STN 50-454
Enclosure:
List of Attendeescc w/encl: See next pageDistribution
- PUBLICLPL3-2 R/F RidsNrrDorlLpl3-2 RidsNrrPMRKuntzRidsNrrLADClarkeRidsOgcRp RidsAcrsAcnwMailCenterR. Jasinski, NRRJ.Dixon-Herrity, EDO RIII RidsRgn3MailCenterRidsNrrDssRidsNrrPMMChawlaL. Whitney, NRRT. Hafera, NRRJ. Hopkins, NRR R. McNally, NRRS. Unikewicz, NRRADAMS Accession Number: ML061520375OFFICELPL3-2/PMLPL3-2/LALPL3-2/BC NAMERKuntz:mwDClarkeDCollins DATE6/12/066/12/066/13/06OFFICIAL RECORD COPY Byron/Braidwood Stations cc:
Dwain W. Alexander, Project ManagerWestinghouse Electric Corporation Energy Systems Business Unit Post Office Box 355 Pittsburgh, PA 15230-0355Joseph Gallo Gallo & Ross 1025 Connecticut Ave., NW, Suite 1014 Washington, DC 20036Howard A. LearnerEnvironmental Law and Policy Center of the Midwest 35 East Wacker Dr., Suite 1300 Chicago, IL 60601-2110U.S. Nuclear Regulatory CommissionByron Resident Inspectors Office 4448 N. German Church Road Byron, IL 61010-9750Regional Administrator, Region IIIU.S. Nuclear Regulatory Commission Suite 210 2443 Warrenville RoadLisle, IL 60532-4351Ms. Lorraine CreekRR 1, Box 182 Manteno, IL 60950Chairman, Ogle County BoardPost Office Box 357 Oregon, IL 61061Mrs. Phillip B. Johnson1907 Stratford Lane Rockford, IL 61107George L. EdgarMorgan, Lewis and Bockius 1800 M Street, NW Washington, DC 20036-5869Attorney General500 S. Second Street Springfield, IL 62701Illinois Emergency Management Agency Division of Disaster Assistance &
Preparedness 110 East Adams Street Springfield, IL 62701-1109Byron Station Plant ManagerExelon Generation Company, LLC 4450 N. German Church Road Byron, IL 61010-9794Site Vice President - ByronExelon Generation Company, LLC 4450 N. German Church Road Byron, IL 61010-9794U.S. Nuclear Regulatory CommissionBraidwood Resident Inspectors Office 35100 S. Rt. 53, Suite 79 Braceville, IL 60407County Executive Will County Office Building 302 N. Chicago Street Joliet, IL 60432Braidwood Station Plant ManagerExelon Generation Company, LLC 35100 S. Rt. 53, Suite 84 Braceville, IL 60407-9619Ms. Bridget Little RoremAppleseed Coordinator 117 N. Linden Street Essex, IL 60935 Byron/Braidwood Stations Document Control Desk - LicensingExelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555Site Vice President - BraidwoodExelon Generation Company, LLC 35100 S. Rt. 53, Suite 84 Braceville, IL 60407-9619Senior Vice President of OperationsExelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555Director - Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555Regulatory Assurance Manager - BraidwoodExelon Generation Company, LLC 35100 S. Rt. 53, Suite 84 Braceville, IL 60407-9619Regulatory Assurance Manager - ByronExelon Generation Company, LLC 4450 N. German Church Road Byron, IL 61010-9794Assistant General CounselExelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348Vice President - Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555Manager Licensing - Braidwood, Byron and LaSalle Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 EnclosureLIST OF ATTENDEESMEETING WITH EXELON GENERATION COMPANY, LLCTO DISCUSS GENERIC LETTER 2004-02MAY 16, 2006 NRCExelonT. MartinB. Rash D. CollinsJ. B auerR. KuntzB. Davenport M. ChawlaD. Walker L. WhitneyJ. Panici T. HaferaD. Brush J. Hopkins*
R. McNallySargent & LundyS. UnikewiczI. Garza* Attended only part of the meeting.