August 14, 2007Mr. Dennis R. MadisonVice President - Hatch Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2 - NRC RECEIPT OFLICENSEE RESPONSE TO GENERIC LETTER 2006-03, "POTENTIALLY NONCONFORMING HEMYC AND MT FIRE BARRIER CONFIGURATIONS" (TAC NOS. MD1586, MD1587)
Dear Mr. Madison:
The Nuclear Regulatory Commission (NRC) acknowledges the receipt of your response toGeneric Letter 2006-03, "Potentially Nonconforming Hemyc and MT Fire Barrier Configurations," in letters dated July 24, 2007, November 28 and June 9, 2006, (ML072060088, ML063330230, ML061600376, respectively). Under oath or affirmation, you have stated that your nuclear power plant does not rely on either the Hemyc or MT fire barrier system. You have submitted documentation under oath or affirmation that other 1 or 3-hour fire barriers that separate redundant safe shutdown trains located within the same fire area have been designed and installed in accordance with current NRC guidance. Based on your response, the basis for stating that this other fire barrier has been designed and installed in accordance with NRC guidance should be maintained on site and will be subject to inspection during the normal NRC inspection process.If you have any questions regarding this response, please contact me at 301-415-1493.Sincerely,/RA/Robert E. Martin, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-321 and 50-366 cc: See next page
ML072180188OFFICENRR/LPL2-1/PMNRR/LPL2-1/LANRR/AFPB/BCNRR/LPL2-1/BCNAMERMartin:ncMO'BrienAKleinEMarinos DATE08/9/0708/9/0708/10/0708/14/07 Edwin I. Hatch Nuclear Plant, Units 1 & 2 cc:
Laurence BergenOglethorpe Power Corporation 2100 E. Exchange Place P.O. Box 1349 Tucker, GA 30085-1349Mr. R. D. BakerManager - Licensing Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295Resident InspectorPlant Hatch 11030 Hatch Parkway N.
Baxley, GA 31531Harold Reheis, DirectorDepartment of Natural Resources 205 Butler Street, SE., Suite 1252 Atlanta, GA 30334Steven M. JacksonSenior Engineer - Power Supply Municipal Electric Authority of Georgia 1470 Riveredge Parkway, NW Atlanta, GA 30328-4684Mr. Reece McAlisterExecutive Secretary Georgia Public Service Commission 244 Washington St., SW Atlanta, GA 30334Arthur H. Domby, Esq.Troutman Sanders Nations Bank Plaza 600 Peachtree St, NE, Suite 5200 Atlanta, GA 30308-2216ChairmanAppling County Commissioners County Courthouse Baxley, GA 31513Mr. Jeffrey T. GasserExecutive Vice President Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295General ManagerEdwin I. Hatch Nuclear Plant Southern Nuclear Operating Company, Inc.
U.S. Highway 1 North P.O. Box 2010 Baxley, GA 31515Mr. K. RosanskiResident Manager Oglethorpe Power Corporation Edwin I. Hatch Nuclear Plant P.O. Box 2010 Baxley, GA 31515