IR 05000285-14-404, 03/20/2014, Fort Calhoun Station, Security Baseline
ML14122A355
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 05/02/2014
From: Haire M S
Plant Support Branch-1
To: Cortopassi L
Omaha Public Power District
D. Holman
References
IR-14-404
Download: ML14122A355 (3)


Text

- SECURITY-RELATED INFORMATIO N " " May 2, 2014 Lou Cortopassi, Vice President

and Chief Nuclear Officer Omaha Public Power District

Fort Calhoun Station FC-2-4 P.O. Box 550 Fort Calhoun, NE 68023-0550

SUBJECT: FORT CALHOUN STATION - NRC SECURITY BASELINE INSPECTION REPORT 05000285/2014404

Dear Mr. Cortopassi:

On March 20, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at the Fort Calhoun Station. The NRC inspectors discussed the results of this inspection with Mr. Mike Prospero, Plant Manager, and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection report.

NRC inspectors documented five findings of very low safety significance (Green) in this report. All of these findings involved violations of NRC requirements.

If you contest the significance of these non-cited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspectors at the Fort Calhoun Station.

If you disagree with a cross-cutting assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region IV; and the NRC resident inspectors at Fort Calhoun Station.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD

. However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information - Withhold from Public Disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1).

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for

your response.

Sincerely,/RA/

Mark S. Haire, Chief Plant Support Branch 1 Division of Reactor Safety

Docket: 50-285 License: DPR-40

Nonpublic

Enclosure:

NRC Inspection Report FCS 05000285/2014404

w/Attachment:

Supplemental Information cc w/enclosure:

Mr. Dennis A. Bakalar

Manager, Site Security Omaha Public Power District

Fort Calhoun Station Mail Stop FC-2-1 9610 Power Lane

Blair, NE 68008

cc w/o enclosure: Electronic Distribution for Fort Calhoun Station