NRC INSPECTION MANUAL IRGB INSPECTION MANUAL CHAPTER 1245, APPENDIX C7 FIRE PROTECTION INSPECTOR TECHNICAL PROFICIENCY TRAINING AND QUALIFICATION JOURNAL Effective Date: 07/30/2018 Issue Date: 07/30/18 i 1245 Appendix C7 Table of Contents Introduction ................................................................................................................................ 1 Required Training Courses ........................................................................................................ 1 Fire Protection (FP) Inspector Individual Study Activities (ISA) .................................................. 2 (ISA-FP-1) Deterministic Fire Protection Regulations .................................................... 3 (ISA-FP-2) Fire Modeling ................................................................................................ 5 (ISA-FP-3) NFPA 805 Fire Protection Risk-Informed, Performance-Based Regulations .................................................................................................................... 7 (ISA-FP-4) Mitigation Measures for Loss of a Large Area ............................................... 9 Fire Protection Inspector On-the-Job (OJT) Activity ..................................................................11 (OJT-FP-1) Participate in Regional Fire Protection Inspection ......................................12 Fire Protection Inspector Technical Proficiency-Level Signature Card and Certification ............13 Form 1 Fire Protection Inspector Technical Proficiency Level Equivalency Justification ...........14 Attachment 1 - Revision History Sheet for IMC 1245 Appendix C7 ..................................... Att1-1 Issue Date: 07/30/18 1 1245 Appendix C7 Introduction This appendix establishes the program for initial qualification of fire protection inspectors through formal training courses, individual study activities (ISAs), and on-the-job training (OJT). In the future, one member of the inspection team for all fire protection triennial inspections will be required to be qualified to this standard. Before imposing this requirement, there will be a phase-in period to allow inspectors time to complete this training. Individual inspectors should be given credit for previous experience and training when completing the requirements outlined in this appendix. Section 05.02 of IMC1245 provides additional information on alternate methods for meeting a program requirement. Required Training Courses 1. Fire Protection for Power Plants (Nuclear Power Plant option) This is an external course, available through the Professional Loss Control Division of the Hartford Steam Boiler Inspection and Insurance Company. Details on the course and registration are (http://www.hsbplc.com/FireProtectionCourses.aspx). 2. IMC 0609 Appendix F Fire Protection Significance Determination Process (SDP) Training (available in iLearn as P-108) 3. Post Fire Safe Shut Down Analysis* 4. Circuit Analysis* *This course material is currently under development. Until it is available, a suitable alternative is the completion of two modules from the EPRI/NRC Fire Probabilistic Risk Assessment Course, one of which must be attendance at or self-(ML14226B017). The Chief of the Fire Protection Branch within NRR is available to be consulted on the acceptability of other alternatives for these two courses. NOTE: Appendix D3, Fire Protection Advanced-Level Training provides a list of additional courses and on the job training that inspectors may wish to consider in order to gain more skills in specific areas of fire protection.
Issue Date: 07/30/18 2 1245 Appendix C7 Fire Protection (FP) Inspector Individual Study Activities (ISA)
Issue Date: 07/30/18 3 1245 Appendix C7 Fire Protection Individual Study Activity TOPIC: (ISA-FP-1) Deterministic Fire Protection Regulations PURPOSE: The purpose of this activity is to become familiar with the most -risk-fire protection regulations and the NRC generic communications that have been issued to help clarify regulatory expectations and positions on deterministic fire protection regulations. COMPETENCY AREA: TECHNICAL AREA EXPERTISE LEVEL OF EFFORT: 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />
REFERENCES:
Contact the chief of the Fire Protection Branch in NRR if you encounter difficulty locating references. 1. 10 CFR Part 50, Appendix A, General Design Criterion for Nuclear Power Plants, Criterion 3, ire protection 2. 1ire protection 3. 10 CFR Part ire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979" 4. Branch Technical Position (BTP) Auxiliary and Power Conversion System Branch (APCSB) 9.5-, ADAMS Accession No. ML070660461 5. Appendix A to BTP (APCSB) 9.5-, ADAMS Accession No. 070660458 6. BTP Auxiliary System Branch (ASB), Guidelines for Fire Protection ML070660450 7. BTP Chemical Engineering Branch (CMEB) 9.5-Fire Protection for Nuclear Power Plants, Revision 3, July 1981, ADAMS Accession No. ML070660454 8. GL 77-02, Nuclear Plant Fire Protection Functional Responsibilities, Administrative Controls and Quality Assurance, August 4, 1977, ADAMS Accession No. ML031280293 9. NUREG-Analysis Reports for Nuclear Power Plants, LWR Edition, Section 9.5.1.1, Fire Protection Program, Revision 0, March 2009, ADAMS Accession No. ML090510170 10. GL 86-24, 1986, ADAMS Accession No. ML031150322 Issue Date: 07/30/18 4 1245 Appendix C7 11. Regulatory Guide 1.189, "Fire Protection for Nuclear Power Plants" Revision 2, October 2009 ADAMS Accession No. 092580550 12. Power Plants During Decommission and Permanent Shutdown, May 2001, ADAMS Accession No. ML011500010 13. Thhttp://www.nrc.gov/about-nrc/fire-protection/related-info.html) 14. Attachment 71111.05AQ, Fire Protection (Annual/Quarterly) 15. Attachment 71111.05T, Fire Protection (Triennial) EVALUATION CRITERIA: At the completion of this activity, you should have a clear understanding of the regulatory history of deterministic nuclear power plant fire protection as well as the relationship among the various key documents by which the NRC has clarified their deterministic expectations and positions. Specifically, you should be able to do the following: 1. Describe the concept of defense-in-depth as it relates to fire protection. 2. fire protection program must do. 3. Describe what a lic. 4. system, or component of a facility. 5. Determine which Branch Technical Position/Regulation is used . TASKS: The activities listed below shall be performed under the guidance of a qualified Fire Protection Inspector (C-7). 1. Review the references and develop an understanding sufficient to meet the evaluation criteria. 2. Discuss the evaluation criteria with a qualified Fire Protection Inspector (C-7). 3. which Branch Technical Position/Regulation applies to the plants fire protection program. DOCUMENTATION: Fire Protection Inspector Technical Proficiency-Level Signature Card Item ISA-FP-1.
Issue Date: 07/30/18 5 1245 Appendix C7 Fire Protection Individual Study Activity TOPIC: (ISA-FP-2) Fire Modeling PURPOSE: The purpose of this activity is to become familiar with the fire modeling techniques used in fire protection. COMPETENCY AREA: TECHNICAL AREA EXPERTISE LEVEL OF EFFORT: 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br />
REFERENCES:
Contact the chief of the Fire Protection Branch in NRR if an inspector encounters difficulty locating references. 1. NUREG- ADAMS Accession No. ML043290075 and NUREG-1805, Supplement 1, July 2013, ADAMS Accession Nos. ML13211A097 and ML13211A098). 2. NUREG-2012, ADAMS Accession No. ML12314A165 EVALUATION CRITERIA: At the completion of this activity, you should have a clear understanding of the fire modeling techniques used in fire protection. Specifically, you should be able to do the following: 1. Describe the difference between an algebraic, zone and a CFD or field model. 2. Describe the general limitations of the five fire models described in NUREG-1934, Section 4.1. 3. Describe how a fire model can be used in a fire hazard analyses. TASKS: The activities listed below shall be performed under the guidance of a qualified Fire Protection Inspector (C-7). 1. Review the references and develop an understanding sufficient to meet the evaluation criteria. 2. Discuss the evaluation criteria with a qualified Fire Protection Inspector (C-7). 3. Develop a scenario on your own, or use an example that is part of the fire model documentation, change the input parameters to see how these changes affect the output from the model. For example, changing the heat release rate of the fire, the geometry, or changing the ventilation from natural to forced ventilation.
Issue Date: 07/30/18 6 1245 Appendix C7 DOCUMENTATION: Fire Protection Inspector Technical Proficiency-Level Signature Card Item ISA-FP-2.
Issue Date: 07/30/18 7 1245 Appendix C7 Fire Protection Individual Study Activity TOPIC: (ISA-FP-3) NFPA 805 Fire Protection Risk Informed, Performance-Based Regulations PURPOSE: The purpose of this activity is to become familiar with the risk-informed, performance--Based Standard for licensees must meet to demonstrate if adopting or maintaining a risk-informed performance-based Fire Protection Program under 10 CFR COMPETENCY AREA: TECHNICAL AREA EXPERTISE LEVEL OF EFFORT: 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />
REFERENCES:
Contact the chief of the Fire Protection Branch in NRR if you encounter difficulty locating references. 1. National Fire Protection Association Standard NFPA 2. -Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, ADAMS Accession No. ML010800360 3. NUREG-Analysis Reports for Nuclear Power Plants: LWR Edition, Section 9.5.1.2, Risk-Informed (RI), Performance-Based (PB) Fire Protection Program, Revision 0, December 2009, ADAMS Accession No. ML092590527 4. Regulatory -Informed, Performance-Based Fire Protection for Existing Light-Revision 2, December 2009, ADAMS Accession No. ML092730314 5. NEI 04-a Risk-Informed, Performance-Based Fire Protection Program Under 10 CFR 50.48(c), Revision 2, April 2008, ADAMS Accession No. ML081130188 6. NEI 00-2, June 2009, ADAMS Accession No. ML091770265 7. Shearon Harris Nuclear Power Plant, Unit 1 - Issuance of Amendment Regarding Adoption of National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating, ADAMS Accession No. ML101130535- Un-Redacted Version) 8. Attachment 71111.05XT, Fire Protection NFPA 805 (Triennial)
Issue Date: 07/30/18 8 1245 Appendix C7 EVALUATION CRITERIA: At the completion of this activity, you should have a clear understanding of the NR role in evaluating the adequacy with which a licensee adopts and maintains compliance with 10 CFR 50.48(c) through adherence to NFPA 805. TASKS: The activities listed below shall be performed under the guidance of a qualified Fire Protection Inspector (C-7). 1. Review the references and develop an understanding sufficient to meet the evaluation criteria. 2. Discuss the evaluation criteria with a qualified Fire Protection Inspector (C-7). 3. Outline the process by which a licensee converts their fire protection program from a traditional/deterministic program to one based on NFPA 805. Note: Additional insights into different fire protection programs can be gained by inspecting an NFPA 805 plant as well as a pre-1979 and post 1979 plant. DOCUMENTATION: Fire Protection Inspector Technical Proficiency-Level Signature Card Item ISA-FP-3 Issue Date: 07/30/18 9 1245 Appendix C7 Fire Protection Individual Study Activity TOPIC: (ISA-FP-4) Mitigation Measures for Loss of a Large Area PURPOSE: The purpose of this activity is to become familiar with mitigation measures that licensees were required to develop and implement in response to the Section B.5.b of the Interim Countermeasures (ICM) Order EA-02-026 of February 25, 2002, subsequently imposed License Conditions, and 10 CFR 50.54(hh)(2). COMPETENCY AREA: TECHNICAL AREA EXPERTISE LEVEL OF EFFORT: 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />
REFERENCES:
Contact the chief of the Beyond Design Basis Management Branch (NRR/DLP/PBMB) to resolve B.5.b issues or if you encounter difficulty locating references. 1. 2. B.5.b inspections Community of Practice (CoP) 3. NEI 06-December 2006, available on B.5.b inspections CoP (ML070090060) 4. 5. IMC 0609, Appendix L, B.5.b Significance Determination Process 6. Temporary Instruction 2515/171, Rev. 1, Verification of Site Specific Implementation of B.5.b Phase 2 & 3 Mitigating Strategies (ML081340110) 7. IP 71111.05T, Fire Protection (Triennial) 8. IP 71111.05XT, Fire Protection - NFPA 805 (Triennial) EVALUATION CRITERIA: At the completion of this activity, you should have a clear understanding of the maintains compliance with the requirements of Section B.5.b of the ICM Order, the subsequent License Conditions and 10 CFR 50.54(hh)(2). TASKS: The activities listed below shall be performed under the guidance of a qualified Fire Protection Inspector (C-7). 1. Be sure you are familiar with the requirements to properly handle security related information. If needed, consider taking the Information Security (INFOSEC) Awareness Training (see IMC 1245 Appendix A, ISA-25, Task 1) as a refresher.
Issue Date: 07/30/18 10 1245 Appendix C7 2. Review the information in IMC 1245 Appendix A, ISA-2, Task 1.l. Under the NRC Web Applications link, locate the NRC Knowledge Center (NKC). Become a member of the B.5.b Inspection CoP so you can view the information there. Membership is required since many of the documents and discussions on this site are Official Use Only Security Related Information. After joining the CoP, review the posted documents and the past questions and answers. 3. Review the references and develop an understanding sufficient to meet the evaluation criteria. 4. Discuss the evaluation criteria with a qualified Fire Protection Inspector (C-7). 5. commitments were proposed and evaluated. 6. Discuss the basis for enforcement of License Conditions or 10 CFR 50.54(hh)(2) with a qualified Fire Protection Inspector (C-7). DOCUMENTATION: Fire Protection Inspector Technical Proficiency-Level Signature Card Item ISA-FP-4 Issue Date: 07/30/18 11 1245 Appendix C7 Fire Protection Inspector On-the-Job (OJT) Activity Issue Date: 07/30/18 12 1245 Appendix C7 Fire Protection Inspector On-the-Job Activity TOPIC: (OJT-FP-1) Participate in Regional Fire Protection Inspection PURPOSE: The purpose of this activity is to acquaint you with the fire protection inspection process. COMPETENCY AREAS: TECHNICAL AREA EXPERTISE LEVEL OF EFFORT: 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> EVALUATION CRITERIA: At the completion of this activity, you should understand the regional fire protection inspection process. Specifically, you should be able to do the following: 1. Discuss the objectives of the triennial fire protection Inspection. 2. Discuss the criteria used in choosing the fire areas or zones for inspection. 3. Discuss the regulatory requirements and licensing basis against which post fire safe shutdown capability is assessed. TASKS: The activities listed below shall be performed under the guidance of a qualified Fire Protection Inspector (C-7) while accompanying a team of regional Inspectors during a fire protection inspection 1. Discuss the evaluation criteria with a qualified Fire Protection Inspector (C-7). 2. Prior to the inspection obtain any documents the team leader deems necessary. See Section 71111.05-06 of the triennial inspection procedure. 3. Participate with the inspection team leader and the Regional SRA in the selection process of determining which fire areas or zones are to be inspected in this particular inspection. 4. Any other task given by the inspection team leader. DOCUMENTATION: Fire Protection Inspector Technical Proficiency-Level Signature Card Item OJT-FP-1.
Issue Date: 07/30/18 13 1245 Appendix C7 Fire Protection Inspector Technical Proficiency-Level Signature Card and Certification Inspector Name:___________________________________ Employee Initials/ Date Signature/ Date Training Courses for Fire Protection Inspector Qualification Fire Protection for Power Plants MC 0609 Appendix F Fire Protection Significance Determination Process (SDP) Training (P-108) Circuit Analysis Post Fire Safe Shut Down Analysis Individual Study Activities ISA-1 Fire Protection Inspector: Deterministic Fire Protection Regulations/Generic Communications ISA-2 Fire Protection Inspector: Fire Modeling ISA-3 Fire Protection Inspector: NFPA 805 Fire Protection Risk-Informed, Performance-Based Regulations ISA-FP-4 Mitigation Measures for Loss of a Large Area On-the-Job Training Activity OJT-1 Fire protection Inspector: Participate in Regional Fire Protection Inspection listed in this training standard. dividual has not previously completed an oral board.
Issue Date: 07/30/18 14 1245 Appendix C7 Form 1: Fire Protection Inspector Technical Proficiency Level Equivalency Justification Inspector Name:___________________________________ Identify equivalent training and experience for which the inspector is to be given credit Training Courses for Fire Protection Inspector Qualification Fire Protection for Power Plants MC 0609 Appendix F Fire Protection Significance Determination Process (SDP) Training (P-108) Circuit Analysis Post Fire Safe Shut Down Analysis Individual Study Activities ISA-1 Fire Protection Inspector: Deterministic Fire Protection Regulations/Generic Communications ISA-2 Fire Protection Inspector: Fire Hazards Analysis and Fire Modeling ISA-3 Fire Protection Inspector: NFPA 805 Fire Protection Risk-Informed, Performance-Based Regulations (ISA-FP-4) Mitigation Measures for Loss of a Large Area On-the-Job Training Activity OJT-1 Fire protection Inspector: Participate in Regional Fire Protection Inspection Recommendation Signature/Date_______________________________ Signature/Date_______________________________ Copies to: Inspector Human Resources Office Supervisor Issue Date: 07/30/18 Att1-1 1245 Appendix C7 Attachment 1 - Revision History Sheet for IMC 1245 Appendix C7 Commitment Tracking Number Accession Number Issue Date Change Notice Description of Change Description of Training Required and Completion Date Comment Resolution and Closed Feedback Form Accession Number (Pre-Decisional, Non-Public) N/A 07/08/09 CN 09-017 Initial issuance. Completed 4 year historical CN search None ML091590710 N/A 12/2911 CN 11-044 ML11105A143 This revision updates required training and adds a new ISA (ISA-4) to familiarize inspectors with mitigation measures that licensees were required to develop and implement in response to the Section B.5.b of the Interim Countermeasures Order EA-02-026 of February 25, 2002, subsequently imposed License Conditions, and 10 CFR 50.54(hh)(2). None ML11339A061 N/A ML12251A068 12/19//12 CN-12-029 This revision corrects the point of contact for B.5.b issues and adds several references to ISA-4. None ML12290A180 Closed FF: 1245C7-1758 N/A ML15177A292 10/21/15 CN 15-020 This revision updates required training courses, references, and format; and clarifies that an oral qualification board is required, if not completed previously. None ML15195A178 Closed FF: 1245-1855 ML15054A211 N/A ML18047A188 07/30/18 CN 18-023 This revision updates the point of contact for B.5.b issues from the Generic Communication Branch to the Beyond Design Basis Management Branch. ML18065A656 Closed FF: 1245C7-2284 ML18186A548