Initial Admin SRO JPM 997777.0301
ML041070064
Person / Time
Site: Clinton Constellation icon.png
Issue date: 01/06/2004
From: James Anderson, Pickley T, Ryan P
Exelon Generation Co, Exelon Nuclear
To:
Office of Nuclear Reactor Regulation
References
-RFPFR, 50-461/04-301, JPM 997777.0301, Rev 00 50-461/04-301
Download: ML041070064 (10)


Text

CLINTON POWER STATION Job Performance Measure Determine an emergency dose for a job and select a worker to perform the job JPM Number: 997777.0301 Revision Number: 00 Date: 7/29/03 Developed By: T. Pickley 8/10/03 Instructor Date Validated By: J. Anderson 10/16/03 SME or Instructor Date Review By: P. Ryan _8/18/03 Operations Representative Date

JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation. Prior to JPM usage, revalidate JPM using steps 8 through 11 below.

________ 1. Task description and number, JPM description and number are identified.

________ 2. Knowledge and Abilities (K/A) references are included.

________ 3. Performance location specified. (in-plant, control room, or simulator)

________ 4. Initial setup conditions are identified.

________ 5. Initiating and terminating cues are properly identified.

________ 6. Task standards identified and verified by SME review.

________ 7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*).

________ 8. Verify the procedure referenced by this JPM matches the most current revision of that procedure:

Procedure Rev. _____ Date _____________

________ 9. Pilot test the JPM:

a. verify cues both verbal and visual are free of conflict, and
b. ensure performance time is accurate.

________ 10. If the JPM cannot be performed as written with proper responses, then revise the JPM.

________ 11. When JPM is revalidated, SME or Instructor sign and date JPM cover page.

SME/Instructor Date SME/Instructor Date SME/Instructor Date Page 2 of 8

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Revision Record (Summary)

1. Revision 00, This is a new JPM Page 3 of 8

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Operators Name: SSN:

Job

Title:

NLO RO SRO STA SRO Cert JPM Title/Number: 997777.0301, Determine an emergency dose for a job and select a worker to perform the job Revision Number: 00 Task Number and

Title:

997777.03, Complete Emergency Plan Activities performed by an SRO Suggested Testing Environment: Any Actual Testing Environment: Simulator Plant Control Room Testing Method: Simulate Faulted: No Perform Alternate Path: No Time Critical: No Estimated Time to Complete: 6 _minutes Actual Time Used: minutes

References:

EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: Satisfactory Unsatisfactory Comments:

Evaluators Name: __________________________

Evaluators Signature: Date:

Page 4 of 8

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 READ TO THE OPERATOR I will explain the initial conditions, which step(s) to simulate or discuss, and provide the initiating cues. When you complete the task successfully, the objective of this Job Performance Measure will be satisfied.

SIMULATOR SET-UP CONDITIONS:

None TASK STANDARDS:

The dose is determined to be 30 Rem and Ted Knight is selected to perform the job TOOLS, EQUIPMENT, OTHER SPECIAL REQUIREMENTS:

None PROCEDURAL/

REFERENCES:

EP-AA-113r4 Personnel Protective Actions EVALUATOR INSTRUCTIONS:

Amplifying cues are provided within the JPM steps.

Supply the operator the partially filled out EP-AA-113 Attachment 2s for the volunteers.

INITIAL CONDITIONS AND INITIATING CUE:

An emergency life saving operation must be performed. The operation will take 10 minutes in a 180 Rem/hr field.

Three personnel have volunteered for the operation: Alvin Jones age 35, Bob Smith age 35 and Ted Knight age 45.

One person is needed for the operation. What will the dose for the operation be? Which volunteer would be at the least risk of health effects?

START TIME:

Page 5 of 8

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00

==============================================================

PERFORMANCE INFORMATION Critical steps are denoted with an asterisk (*) to the left of the step number and appear in BOLDED letters. Failure to meet the standards for a critical step constitutes failure of the Job Performance Measure. The sequence of steps is assumed unless denoted in the comments section of the JPM.

==============================================================

PERFORMANCE STEPS

  • 1. Determines total dose for the operation Standard Dose is 30 Rem CUE Comments SAT UNSAT Comment Number
  • 2. Determines volunteer at least risk of health effects Standard Volunteer is Ted Knight CUE Comments SAT UNSAT Comment Number STOP TIME: _____________

Page 6 of 8

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 TERMINATING CUES:

Total dose and volunteer are determined.

K/A REFERENCE NUMBERS Importance Rating K/A SYSTEM NUMBER K/A NUMBER RO SRO 2.3.4 2.5 3.1 Page 7 of 8

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 INITIATING CUE An emergency life saving operation must be performed. The operation will take 10 minutes in a 180 Rem/hr field. Three personnel have volunteered for the operation: Alvin Jones age 35, Bob Smith age 35 and Ted Knight age 45. One person is needed for the operation. What will the dose for the operation be? Which volunteer would be at the least risk of health effects?

Page 8 of 8