Indiana Michigan Power Company 500 Circle Drive Buchanan, Ml 49107 1395 INDIANA MICHIGAN POWER October 11, 2004 AEP:NRC:2691-47 Docket Nos. 50-315 50-316 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop O-PI-17 Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 MONTHLY OPERATING REPORT Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit I and Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for September 2004 is submitted.
There are no new commitments associated with this submittal.
Should you have any questions, please contact Mr. Toby K. Woods, Compliance Supervisor, at (269) 466-2798.
Sincerely,
(>/Jensen Site Vice President JEN/jen Attachment
U. S. Nuclear Regulatory Commission AEP:NRC:2691-47 Page 2 c: R. Aben - Department of Labor and Economic Growth ANI Nuclear Engineering Department L. Brandon - MDEQ - WHMD/HWRPS D. P. Fadel M. J. Finissi G. T. Gaffney - Canton R. A. F. Harris INPO Records Center J. N. Jensen J. T. King - MPSC B. Lewis - McGraw-Hill Companies D. H. Malin K. L. Matheny M. K Nazar NRC Project Manager - NRR NRC Region III NRC Resident Inspector D. W. Paul - Columbus W. H. Schalk J. A. Zwolinski
N.R.C. OPERATING DATA REPORT DOCKET NO. 50-315 DATE 10/1/2004 COMPLETED BY R. Harris TELEPHONE 269-465-5901 OPERATING STATUS
- 1. Unit Name D. C. Cook Unit 1 Notes:
- 2. Reporting Period Sep-04
- 3. Licensed Thermal Power (MWt) 3304
- 4. Name Plate Rating (Gross MWe) 1152
- 5. Design Electrical Rating (Net MWe) 1020
- 6. Maximum Dependable Capacity(GROSS MWe) 1056
- 7. Maximum Dependable Capacity (Net MWe) 1000
- 8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons
- 9. Power Level To Which Restricted. If Any (Net MWe)
- 10. Reasons For Restrictions.
This Mo. Yr. to Date Cumm.
- 11. Hours in Reporting Period 720.0 6576.0 260784.0
- 12. No. of Hrs. Reactor Was Critical 720.0 6390.9 180292.2
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 463.0
- 14. Hours Generator on Line 720.0 6379.9 177559.5
- 15. Unit Reserve Shutdown Hours 0.0 0.0 321.0
- 16. Gross Therm. Energy Gen. (MWH) 2376049.2 21009959.0 532378486.5
- 17. Gross Elect. Energy Gen. (MWH) 761680.0 6770020.0 172811823.0
- 18. Net Elect. Energy Gen. (MWH) 736107.0 6544954.8 166390238.7
- 19. Unit Service Factor 100.0 97.0 68.6
- 20. Unit Availability Factor 100.0 97.0 68.6
- 21. Unit Capacity Factor (MDC Net) 102.2 99.5 65.2
- 22. Unit Capacity Factor (DER Net) 100.2 97.6 63.9
- 23. Unit Forced Outage Rate 0.0 0.0 18.5
- 24. Shutdowns Scheduled over Next Six Months (Type,Date,and Duration):
- 25. If Shut Down At End of Report Period, Est'd Date of Startup:
- 26. Units in Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
AVERAGE DAILY POWER LEVEL (MWe-Net)
DOCKET NO. 50-315 UNIT ONE DATE 01-Oct-04 COMPLETED BY R. Harris TELEPHONE 269-465-5901 MONTH Sep-04 AVERAGE DAILY AVERAGE DAILY DAY POWER LEVEL DAY POWER LEVEL 9/1/2004 1011 9/17/2004 1032 9/2/2004 1009 9/18/2004 1048 9/3/2004 1011 9/19/2004 1014 9/4/2004 1008 9/20/2004 1042 9/5/2004 1011 9/21/2004 1029 9/6/2004 1008 9/22/2004 1029 917/2004 1011 9/23/2004 1031 9/8/2004 1045 9/24/2004 1020 9/9/2004 1027 9/25/2004 1028 9/10/2004 1019 9/26/2004 1031 9/11/2004 1030 9/27/2004 1029 9/12/2004 1004 9/28/2004 1028 9/13/2004 1013 9/29/2004 1037 9/14/2004 1012 9/30/2004 1033 9/15/2004 1012 9/16/2004 1009
DOCKET NO. 50 - 315 UNIT NAME D.C. Cook Unit 1 DATE October 1, 2004 COMPLETED BY J. Newmiller TELEPHONE 269-465-5901 PAGE 1 of 1 UNIT SHUTDOWNS AND POWER REDUCTIONS - September 2004 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE' HOURS REASON 2 REACTOR 3 REPORT NO. CODE 4 CODE5 TO PREVENT RECURRENCE None.
I TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:
F: Forced A: Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit l: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Ucensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)
License Examination F: Administrative G: Operational Error (Explain)
H: Other (Explain)
N.R.C. OPERATiNG DATA REPORT DOCKET NO. 50-316 DATE 1011/2004 COMPLETED BY R. Harris TELEPHONE 269-465-5901 OPERATING STATUS
- 1. Unit Name D.C.Cook Unit 2 Notes:
- 2. Reporting Period Sep-04
- 3. Licensed Thermal Power (MWt) 3468
- 4. Name Plate Rating (Gross MWe) 1133
- 5. Design Electrical Rating (Net MWe) 1090
- 6. Maximum Dependable Capacity(GROSS MWe) 1100
- 7. Maximum Dependable Capacity (Net MWe) 1060
- 8. If Changes Occur inCapacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons
- 9. Power Level To Which Restricted. If Any (Net MWe)
- 10. Reasons For Restrictions.
This Mo. Yr. to Date Cumim.
- 11. Hours In Reporting Period 720.0 6576.0 234930.0
- 12. No. of Hrs. Reactor Was Critical 720.0 6321.0 154604.3
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
- 14. Hours Generator on Une 720.0 6287.2 150641.4
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Therm. Energy Gen. (MWH) 2491583.2 21575698.6 475251558.1
- 17. Gross Elect. Energy Gen. (MWH) 800620.0 6999978.0 154114008.0
- 18. Net Elect. Energy Gen. (MWH) 774703.0 6775637.5 148640544.2
- 19. Unit Service Factor 100.0 95.6 64.8
- 20. Unit Availability Factor 100.0 95.6 64.8
- 21. Unit Capacity Factor (MDC Net) 101.5 97.2 60.8
- 22. Unit Capacity Factor (DER Net) 98.7 94.5 59.1
- 23. Unit Forced Outage Rate 0.0 4.4 22.7
- 24. Shutdowns Scheduled over Next Six Months (Type,Date,and Duration):
Refueling outage currently scheduled for October 2004 with a planned duration of 35 days.
- 25. If Shut Down At End of Report Period, Est'd Date of Startup:
- 26. Units in Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
AVERAGE DAILY POWER LEVEL (MWe-Net)
DOCKET NO. 50-316 UNIT TWO DATE 1-Oct-04 COMPLETED BY R. Harris TELEPHONE 269-465-5901 MONTH Sep-04 AVERAGE DAILY AVERAGE DAILY DAY POWER LEVEL DAY POWER LEVEL 9/1/2004 1058 9/17/2004 1074 9/2/2004 1061 9/18/2004 1096 9/3/2004 1061 9/19/2004 1095 9/4/2004 1058 9/20/2004 1093 9/5/2004 1059 9/21/2004 1092 9/6/2004 1068 9/22/2004 1085 9/7/2004 1049 9/23/2004 1089 9/8/2004 1114 9/24/2004 1081 9/9/2004 1080 9/25/2004 1088 9/10/2004 1121 9/26/2004 1093 9/11/2004 1032 9/27/2004 1070 9/12/2004 1070 9/28/2004 1093 9/13/2004 1069 9/29/2004 1105 9/14/2004 1068 9/30/2004 1033 9/15/2004 1063 9/16/2004 1061
DOCKET NO. 50 - 316 UNIT NAME D.C. Cook Unit 2 DATE October 1, 2004 COMPLETED BY J. Newmiller TELEPHONE 269-465-5901 PAGE 1 of 1 UNIT SHUTDOWNS AND POWER REDUCTIONS - September 2004 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE' HOURS REASON 2 REACTOR 3 REPORT NO. CODE 4 CODE 5 TO PREVENT RECURRENCE None 1 TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:
F: Forced A: Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit I: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)
License Examination F: Administrative G: Operational Error (Explain)
H: Other (Explain)