Letter Sequence Withdrawal |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement
|
MONTHYEARLIC-12-0098, Integrated Performance Improvement Plan, Rev. 32012-07-0909 July 2012 Integrated Performance Improvement Plan, Rev. 3 Project stage: Request LIC-12-0165, Integrated Performance Improvement Plan, Revision 42012-11-0101 November 2012 Integrated Performance Improvement Plan, Revision 4 Project stage: Request ML13066A8772013-03-0707 March 2013 Issuance of Revised U.S. Nuclear Regulatory Commission Manual Chapter 0350 Panel Fort Calhoun Station Restart Checklist Basis Document Project stage: Request LIC-13-0007, Response to NRC Request for Additional Information Re Request for Work Hours Exemption2013-03-16016 March 2013 Response to NRC Request for Additional Information Re Request for Work Hours Exemption Project stage: Response to RAI LIC-13-0071, OPPD Commitment to NRC Regarding Request for Work Hours Exemption2013-05-24024 May 2013 OPPD Commitment to NRC Regarding Request for Work Hours Exemption Project stage: Request 05000285/LER-2013-010, Regarding HPSI Pump Flow Imbalance2013-07-0202 July 2013 Regarding HPSI Pump Flow Imbalance Project stage: Request LIC-13-0061, Omaha Public Power District - Exigent License Amendment Request 13-02 Revise Current Licensing Basis to Adopt a Revised Design Basis / Methodology for Addressing Design-Basis Tornado / Tornado Missile Impact2013-07-21021 July 2013 Omaha Public Power District - Exigent License Amendment Request 13-02 Revise Current Licensing Basis to Adopt a Revised Design Basis / Methodology for Addressing Design-Basis Tornado / Tornado Missile Impact Project stage: Request 05000285/LER-2013-011, The Fort Calhoun Station, Inadequate Design for High Energy Line Break in Rooms 13 and 19 of the Auxiliary Building2013-08-12012 August 2013 The Fort Calhoun Station, Inadequate Design for High Energy Line Break in Rooms 13 and 19 of the Auxiliary Building Project stage: Request LIC-13-0121, Request for Exemption from Requirements of 10 CFR 26.205(d)(7)2013-08-16016 August 2013 Request for Exemption from Requirements of 10 CFR 26.205(d)(7) Project stage: Request 05000285/LER-2013-007-01, Regarding Containment Air Cooling Unit (VA-16A/B) Seismic Criteria2013-08-16016 August 2013 Regarding Containment Air Cooling Unit (VA-16A/B) Seismic Criteria Project stage: Request ML13233A2482013-08-26026 August 2013 Supplemental Information Needed for Acceptance of Requested Licensing Action; Request for Exemption, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage in Lieu of 10 CFR 26.205(d)(7) Project stage: Acceptance Review LIC-13-0125, Reply to NRC Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7)2013-08-30030 August 2013 Reply to NRC Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) Project stage: Supplement ML13255A0072013-09-11011 September 2013 Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Project stage: Other ML13261A2122013-09-18018 September 2013 Request for Additional Information Email, Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Project stage: RAI LIC-13-0135, Omaha Public Power District - Reply to NRC Request for Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7)2013-09-23023 September 2013 Omaha Public Power District - Reply to NRC Request for Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) Project stage: Request ML13282A5362013-10-0909 October 2013 Request for Additional Information Email, Round 2, Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Project stage: RAI LIC-13-0147, Reply to NRC Request for Additional Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7)2013-10-11011 October 2013 Reply to NRC Request for Additional Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) Project stage: Request ML13298A8092013-10-25025 October 2013 Partial Withdrawal of Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) for Individuals Performing Duties Described in 10 CFR 26.4(a)(5) Project stage: Withdrawal ML13274A0252013-10-28028 October 2013 Letter, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements Project stage: Other ML13274A0262013-10-28028 October 2013 FRN, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements Project stage: Other NRC-2013-0243, FRN, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements2013-10-28028 October 2013 FRN, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements Project stage: Other 2013-05-24
[Table View] |
Text
-~.:..
nlllln Omaha Public Power Oistrict 444 South 1ftn Street Mall Omaha, NE 68102-2247 October 25,2013 LlC-13-0157 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station P1 -137 Washington, D.C. 20555
References:
- 1. Docket No. 50-285
- 2. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Request for Exemption from Requirements of 10 CFR 26.205(d)(7)," dated August 16, 2013 (ML13231A018) (LlC-13-0121)
- 3. Letter from NRC (J. M. Sebrosky) to OPPD (L. P. Cortopassi), "Fort Calhoun Station, Unit No. 1 - Supplemental Information Needed for Acceptance of Requested Licensing Action RE: Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) (TAC No. MF2571)," dated August 26, 2013 (ML13233A248)
(NRC-13-0109)
- 4. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Reply to NRC Request for Supplemental Information Needed for Acceptance of Requested Licensing Action RE: Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) (TAC No. MF2571)," dated August 30,2013 (ML13246A182) (LlC-13-0125
- 5. Email from NRC (J . Sebrosky) to OPPD (S. R. Hansher), "Request for Information Associated with the August 16, 2013, Work Hour Exemption Request (MF2571),"
dated September 18, 2013 (ML13261A212) (NRC-13-0124)
- 6. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Reply to NRC Request for Information RE: Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) (TAC No. MF2571)," dated September 23, 2013 (ML13267A186) (LlC-13-0135)
- 7. Email from NRC (L. Wilkins) to OPPD (S. R. Hansher), "Request for Additional Information Re: Fort Calhoun Station Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) (TAC No. MF2571)," dated October 9, 2013
- 8. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Reply to NRC Request for Additional Information Re: Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) (TAC No. MF2571 )," dated October 11, 2013 (LlC-13-0147)
SUBJECT:
Partial Withdrawal of Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) for Individuals Performing Duties Described in 10 CFR 26.4(a)(5)
On August 16, 2013, the Omaha Public Power District (OPPD) submitted a request (Reference 2) for an exemption from requirements of paragraph 26.205(d)(7) of Title 10 of the Code of Federal Regulations (10 CFR) for Fort Calhoun Station, Unit No.1. Reference 2 requested an exemption from specific requirements of 10 CFR 26.205(d)(7), to allow the use of the less restrictive work hour limitations described in 10 CFR 26.205(d)(4) and (d)(5) to support activities required for plant startup Employment with Equal Opportunity
LlC-13-0157 Attachment Page 2 from the current extended outage, for a period not to exceed 45 days. In Reference 3, the NRC determined that additional information was needed before the staff could begin a detailed review of the Reference 2 exemption request and OPPD provided its response in Reference 4. References 5 and 7 transmitted additional NRC requests for information to which OPPD responded in References 6 and 8 respectively.
Following a teleconference with NRC Staff on October 25, 2013, OPPD requests to withdraw the portion of its request contained in Reference 2 and Reference 8 for exemption from the work hour requirements of 10 CFR 26.205(d)(7) for individuals performing duties described in 10 CFR 26.4(a)(5)
(Le., personnel performing security duties). OPPD continues to request that the exemption apply to individuals performing duties described in 10 CFR 26.4(a)(1) through (a)(4). This would change the limitation proposed in Reference 8 to read as follows:
Because the exemption is tied to activities that directly relate to heating the reactor coolant Teold greater than 210°F (i.e., exiting Mode 4 or 5), the exemption is being issued coincident with the date that OPPD intends to heat the reactor coolant Teold greater than 210°F (i.e., exit Mode 4 or 5). Further, the exemption is granted to those individuals who perform duties described in 10 CFR 26.4(a)(1) through (a)(4) that, as of the date of this exemption, have not exceeded a 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> average work week for the 6 week period prior to the date of this exemption.
This letter contains no new regulatory commitments.
If you should have any additional questions or require additional information, please contact Mr. Bill Hansher at (402) 533-6894.
Louis P. Cortopassi Site Vice President and CNO c: M. L. Dapas, NRC Regional Administrator, Region IV J. M. Sebrosky, NRC Senior Project Manager L. E. Wilkins, NRC Project Manager J. C. Kirkland, NRC Senior Resident Inspector