ML13164A030

From kanterella
Revision as of 03:34, 2 March 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Comanche Peak Nuclear Power Plant Units 1 and 2 - Notification of Inspection (NRC Inspection Report 05000445/2013405 and 05000446/2013405) and Request for Information
ML13164A030
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 06/12/2013
From: Vincent Gaddy
Operations Branch IV
To: Flores R
Luminant Generation Co
References
IR-13-405
Download: ML13164A030 (4)


See also: IR 05000445/2013405

Text

June 12, 2013

Rafael Flores, Senior Vice President and Chief Nuclear Officer Luminant Generation Company, LLC Comanche Peak Nuclear Power Plant P.O. Box 1002 Glen Rose, TX 76043

SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT UNITS 1 AND 2 - NOTIFICATION OF INSPECTION (NRC INSPECTION REPORT 05000445/2013405 AND 05000446/2013405) AND REQUEST FOR INFORMATION

Dear Mr. Flores:

From July 30 to August 1, 2013, inspectors from the Nuclear Regulatory Commission's (NRC) Region IV office will perform the Temporary Instruction (TI)-186, "Inspection of Procedures and Processes for Responding to Potential Aircraft Threats." In order to minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection. Also, in order to demonstrate compliance with TI-186, we ask that you have the necessary staff members available to the inspection team to assist in any plant walk-throughs, interviews, and simulator demonstrations. We have discussed the schedule for these inspection activities with your staff and understand that our point of contact for this inspection will be Mr. Robert Kidwell, Manager, Emergency Preparedness. If there are any questions about this inspection or the material requested, please contact Steve Garchow, lead inspector, at (817) 200-1216 (steve.garchow@nrc.gov) or Kelly Clayton at (817) 200-1570 (kelly.clayton@nrc.gov). This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA/

Vincent G. Gaddy, Chief Operations Branch Division of Reactor Safety Docket: 50-445, 50-446, License: NPF-87, NPF-89,

Enclosure:

TI-186 Inspection Document Request cc: Electronic Distribution for Comanche Peak Nuclear Power Plant