Text
'REGULATORY l, ORMATION DISTRIBUTION 'SYS (RIDS)
'AOCESSION NBR:8302010513 DOC ~ DATE ~ 83/01/24 NOTARI'ZED; NO DOCKET FACIL:50 389 'St ~ Lucie Plant~ UniIt 2~,Florida Power tI Light Co. 05000389 AUTH ~ NAME AUTHOR AFF IL I ATION UHRIGg R,E, Florida 'Power 8 Light Co, REC IP ~ NAME RECIPIENT AFF IL'IATION EISENHUTgDwG ~ Division of Licensing SUBJEOT: Forwards const/startup .progress repts for Nov .8 Dec 1982 ION,CODE: 8001'S COPIES RECEIVED:LTR / ENCL,g 'SIZEe.
~ 'I'STRIBUT
.TITLE: Licensing 'Submittal:,PSAR/FSAR Amdts K Related Cornespondence RECOPIES
,NOTES:
RECIPIENT RECIPIENT COPIES IO CODE/NAME LTTR ENCL .ID CODE/NAME LT(TR ENCL A/D LICENSNG 1 0 LIC BR 43 BC LIC BR 03 LA 1 0 NERSESgV ~ 01 1 1 I NT>ERNAL! '-ELO/HDS2 1 0 IE FILE 1 IE/DEP EPDS 35 1 IE/OEP/EPLB ~36 13 NRR/DE/AEAB <<0 NRR/DE/CEB 11 1 NRR/DE/EQB 13 2 "2 NRR/DK/GB 28 2
,NRR/DE/HGEB 30 1 1 NRR/DE/MEB 18 1 1 NRR/OE/MTEB 17 1 1 NRR/DE/QAB 21 1 NRR/DE/SAB 24 1 1 NRR/DE/SEB 25 1 NRR/OHFS/HFEB40 1 1 NRR/DHFS/LQB 32 1 1 NRR/DHFS/OLB .34 1 NRR/DL/SSPB 1 0 NRR/DS I/AKB 26 1 1 NRR/DSI/ASB 1 1 NRR/OSI/CPB 10 1 .1 NRR/DS I/CSB 09 1 1 NRR/OS I/ICS8 16 1 1 NRR/DS I/METB 12 1 NRR/DSI/PSB 19 1 N RAB 22'G 1 -1 NRA/OS I/RSB 23 1 1 Fl Q4 1 1 RGN2 3 3 AMI/MIB 1 0 EXTERNAL: ACRS 41, 6 BNL(AMDTS ONLY) 1 1 LPOR'3 OMB/DSS NSIC (AMDTS) 05 1
1 1
1 1
1 FEMA REP DIV 39 NRC 'PDR NTIS 02
.1 1
1 1
1 1
.TOTAL- NUMBER OF COPIES REQUIRED: LTTR 53 ENCL 46
t3 ~ Ia W W 'I Wt >>~W OK hl III~I i, If '>>hi Ir ~ '
>~3. k ')') W I Il 3 Ih, I g I' I3
>>I WI>> 3 rt
<<gpy ~<<r ,Jll I I" i W>>
ii, ttlhgt)rig f,hit i IQ fi K I, Ih,f . Igt '
"II W I i I I>> i" II II J>>i, I,hip il JV I I it I>> IIt, W k I>>
I Irll >>I>> t I/Sy i I Jg
't I I Ji
'W' Jt 3 I I J>>
I
' 33'g'N n
I, I t>>
JI JI >>I>> I<<
fi ',
Ji ilti It JI J'I 'JI l I 3' I/g I
1
P. 'OX 14000, JUNO BEACH, FL 33408
~
~
FLORIDA POWER & LIGHT COMPANY January 24, 1983 L-83-32 Office of Nuclear Reactor Regulation
- Attention: Mr. Darrell G. Eisenhut, Director Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C. 20555
Dear Mr. Eisenhut:
RE: St. Lucie Unit 2 Docket No. 50-389 Construction/Start-u Pro ress U date Attached are the reports of the construction/start-up progress for St. Lucie Unit 2 for the months of November and December l982. If you have any questions regarding the attached information, or would like additional information from Florida Power & Light Company (FPL), please feel free to call me or W. B.
Derrickson, the St. Lucie Unit 2 Project General Manager (305) 863-3044.
Very truly yours, Robert E. Uhrig Vice President Advanced Systems & Technology REU/R JS/cab Attachment cc: William H. Lovelace, Office Management & Program Analysis U. S. Nuclear Regulatory Commission J. P. O'Reilly, Regional Administrator, Region ll Harold F. Reis, Esquire goo f 83020iOSi3 830i24 PDR ADOCK 05000389 R PEOPLE... SERVING PEOPLE
FLORIDA POWER 6 LIGHT COMPANY ST. LUCIE UNIT 2 CONSTRUCTION/STARTUP MONTHLY STATUS REPORT CURRENT PERIOD: November 1982 h h SCHEDULE STATUS: OVERALL PRMECT Percent complete not applicable CONSTRUCTION/STARTUP at this stage of project CRITICAL PATH VARIANCE 14. 0 TARGET FUEL LOAD DATE 10/28/82 (Original Schedule)
'MAJOR WORK HIGHLIGHTS< SCHEDULED AGTUAL
- 1. Completed Hot Operational Testing of Plant 8/03/82 11/16/82
- 2. 'ommenced ZLRT 8/27/82 11/24/82 3.. Completed ILRT 9/02/82 12/02/82
- 4. RCB Maintenance Hatch Door set on it's rails 11/01/82 11/05/82 S. Completed the Dry Storage Warehouse roof installation 12/03/82 11/23/82
- 6. CBI completed weldout of the Containment Vessel Dollar Plate 11/30/82 11/20/82 BULK QUANTITY STATUS AVERAGE MONTHLY ZNSTAL, RATE
( TY MO) 10%-90hL TOTAL QTY QTY PERCENT CURRENT 10/28 INSTALLED COMPLETE MONTH TO DATE FORECASTED TO DATE TO DATE Concrete (cy) 140, 411 99.4 83 ESSENTIALLY COMPLETE Large Bore Piping (lf) 78,978 98.4 604 ESSENTIALLY. COMPLETE Small Bore Piping (lf) 92,285 96.3 3,880 ESSENTIALLY COMPLETE Instrument Tubing (lf) ~
112,116 92.7 1~421 ESSENTIALLY COMPLETE Large Bore Hangers (ea) 3,920 88.8 74 90 ~
135 Whipping Restraints (tn) 539 93.6 ESSENTIALLY. COMPLETE Cable Tray (lf) 39.828 95.6 ESSENTIALLY COMPLETE Conduit (Exp., Emb., U/D) (lf) 398,357 95.0 8i 351 ESSENTIALLY COMPLETE Lighting Conduit. (1 f) 112,447 93.6 532 ESSENTIALLY COMPLETE
,Power Cable Pull (lf) 509,586 90.2 4,506 ESSENTIALLY COMPLETE Control Cable Pull Inc. Comm. 2,047,714 88.2 44~235 75,650 90~790 Signal Cable Pull (lf) 1,144,207 86.7 68,455 48,200 44,455 Terms - Pwr Hi (ea) 483 97.8 DECURRENT ESSENTIALLY COMPLETE Terms - Pwr Lo (ea) 11,929 91. 7 122 ESSENTIALLY COMPLETE
- Control (ea) 'Terms 54,865 81.9 1,904 2,190 3i480 Terms - Signal (ea) 26,074 80.2 1,799 1~520 3,535 START-UP PROGRAM STATUS SCHEDULED SCHEDULE COMPLETED TOTAL TO DATE FOR MONTH D UZ RED System Turnover (PTO) 311N 26 44 317 System Turnover (CTO) 132N ]9I 122 161 Preoperational Test Procedures 223 4 4 185, 223
. Prpoperational Test Performed 211 15/89".+
1 183 43 223
[
i
'NOTE: INFORMATION CURRENT AS OF PROJECT SCHEDULE DATED 11/30/82
~NOTE: I INCLUDES PACKAGES N SIGN-OFF CIRCUIT
+*NOTE: INCLUDES PREOPERATI ONAL TEST IN PROGRESS, AT I'HE',END OF NOVEMBER THERE ARE 125 PREOPERATIONAL TESTS COMPLETED DUE TO THE COMPLETION OF HOT-FUNCTIONAL TEST
~ ILRT AND THE LLRT~ FINAL REVIEW AND SIGN OFF TO BE COMPLETED+
3\4 f 1
'P I IDA POWER 6 LIGHT COMPANY i~ ST. LUCIE UNIT 2 CONSTRUCTXON/START-U MONTHLY STATUS REPORT CURRENT PERIOD: DECEMBER 1982 SCHEDULE STATUS: OVERALL PROJECT Percent complete not applicable at CONSTRUCTION/STARTUP this stage of project CRITICAL PATH VARIANCE 21.0 TARGET FUEL LOAD DATE 10/28/82 (Original Schedule)
A re-evaluation of the project schedule, just completed, places the current fuel load at March 23, 1983 MAJOR .WORK HIGHLIGHTS: SCHEDULED ACTUAL
- 1. Placed RCB dome cap 12/03/82 12/03/82'2/08/82
- 2. Started placing RCB ZLRT blockout concrete 12/06/82
- 3. Completed setting MST missile protection steel 12/22/82 12/22/82
- 4. Completed all structural work for the "Dry. 2/01/83 12/21/82 Storage Warehouse'
- 5. New fuel receipt and storage started 12/01/82 12/01/82 BULK QUANTITY STATUS AVERAGE MONTHLY INST. RATE
( TY/MO) 1096-9096 TOTAL QTY QTY PERCENT CURRENT '0/28 INSTALLED COMPLETE MONTH TO DATE FORECASTED TO DATE TO DATE Concrete (cy) 140, 828 99.6 417 ESSENTIALLY COMPLETE Large Bore Piping (lf) 79, 99.6 947 ESSENTIALLY COMPLETE Small Bore Piping (lf) 925'2,415 96.3 130 ESSENTIALLY COMPLETE Instrument Tubing (lf), 115,799 94.7 3, 683'98 ESSENTIALLY COMPLETE Large Bore Hangers (ea) 4,118 93.3 ESSENTIALLY COMPLETE Whipping Restraints 539.. 93.6 ESSENTIALLY COMPLETE Cable Tray (lf) 39,928 98.6 100 ESSENTIALLY COMPLETE Conduit (Exp.,Emb.~U/D)(lf) 410, 132 95.3 11,775 ESSENTIALLY COMPLETE Lighting Conduit 113,508 94.5 1,061 ESSENTIALLY COMPLETE Power Cable Pull (lf) 523,161 93.8 13,575 ESSENTIALLY COMPLETE Control Cable Pull (Inc.
Comm. ) (1 f) 2, 104, 284 93. 6 56,570 ESSENTIALLY COMPLETE Signal Cable Pull (lf) 1g 209'97 91. 5 65,190 ESSENTIALLY COMPLETE Terms PWR HZ- (ea) 483 97. 8 ESSENTIALLY COMPLETE Terms PWR LO (ea) 12,086 92.9 157 ESSENTIALLY COMPLETE Terms CONTROL (ea) 56,697 84.6 1,832 2,170 3,480 Terms SIGNAL (ea) 28,689 88. 3 2,615 1,590 3,535 START-UP PROGRAM STATUS: SCHEDULED COMPLETED SCHEDULED CURRENT TOTAL TO DATE TO DATE PER MONTH MONTH RE UZRED System Turnover (PTO) 317 ¹ 305 27 17* 319 System Turnover (CTO) 145¹ 131 26 , 12* 162 Preoperational Test Procedures 216 215 1 0 216 Preoperational Test Performed 214 54 171 12/88** 216
¹NOTE: INFORMATION CURRENT AS OF PROJECT SCHEDULE DATED 12/31/82
- NOTE: INCLUDES PACKAGES IN SIGN-OFF CIRCUXT
- NOTE: INCLUDES PREOPERATIONAL TESTS IN PROGRESS'25 PREOPEBATIONAL TESTS WERE PERFORMED DURING THE HOT OPS MILESTONE. SOME OF THESE ARE WAITING ON CLEARING UP EXCEPTIONS TO TOTALLY CLOSE OUT THE PREOP.