ML20211F440
| ML20211F440 | |
| Person / Time | |
|---|---|
| Site: | Seabrook |
| Issue date: | 09/26/1997 |
| From: | NORTH ATLANTIC ENERGY SERVICE CORP. (NAESCO) |
| To: | |
| Shared Package | |
| ML20211F438 | List: |
| References | |
| NUDOCS 9710010077 | |
| Download: ML20211F440 (11) | |
Text
. - . ._.._-.._._.__ .- _.-_ _._ __.- ___.._ _ _ ..._ .___.-.. _ _._ _-. _ _. ..,. . _ . .
2 o
. -. . l
. . Docket No. 50443 .
i-1 ..- .
- 2. .- ,
d -
1-1 I
t . --
4 i
i
). ,
(
5 ,7 3 . -.
4 I
a 4
4 .; .
t i
SEABROOK STATION -
UNIT NO,1 STARTUP TEST REPORT CYCLE 6 ,
V Y
9710010077 970926 PDR. ADOCK 05000443 ~
P PDR 'a
- ,, . -,m,;. - - ~ . ,-..~.a , ,,- -. ,-- n ---
- INDEX
'I.0 CIIRONOLOGICAL
SUMMARY
2.0 CORE DESIGN
SUMMARY
3.0 LOW POWER PHYSICS TESTING
SUMMARY
(LPPT)
~4.0. POWER ASCENSION TESTING
SUMMARY
(PAT) 5.0 TEST RESULTS TABLE 1 LPPT RESULTS
- TABLE 2 PAT FLUX MAP RESULTS TABLE 3 FULL POWER THERMAUHYDRAULIC DATA 1-
l'.0 ' CIIRONOLOGICAL
SUMMARY
4 Cycle 6 Fuel Load was completed June 12, 1997. Subsequent operation / testing milestones were completed as follows:
INITIAL CRITICALITY 06/26/97 LPPT COMPLETED 06/27/97 ON LINE 06/28/97 30% PAT COMPLETED 06/29/97 50% PAT COMPLETED 06/30/97 75% PAT COMPLETED 07/01/97 l 90% PAT COMPLETED 07/02/97 l
FULL IOWER 07/02/97 t-5
2'.0 CORE des 1GN
SUMMARY
The Cycle 6 core is designed to operate for 22,253 MWD /MTU (575 Effective Full Power Days). Eighty Four (84) fresh fuel assemblies wrn loaded into the Cycle 6 core. Eighty have an enrichment of 4.95 w/o. In addition, the top and bottom 6 inches have an j enrichment of 2.6 w/o creating an axial annular blanket. The remaining four fuel assemblies have an enrichment of 2.4 w/o. They are replacements for four once burned fuel assemblies i
that had degraded fuel rodsi By comparison, Cycle 5 utilized 80 fresh fuel assemblies with i
enrichments of 4.4 and 4.8 w/o with a similar 2.6 w/o axial annular blanket configuration.
1
- . Fresh assemblies for this cycle are Vantage 511 ZlRLO. This design utilizes ZIRLO for fuel clad, control rod guide tubes and instrument thimbles and Zircaloy-4 for the six low pressure drop mid grids. The mechanical design is identical to the Cycle 5 design which utilized the Inconel protective bottom grid.
i 4
F P
2-l l
J
3.0 -- LOW POWER PIIYSICS TESTING
SUMMARY
Testing was performed in accordance with the following general sequence:
1 Initial Criticality: Criticality was achieved using a controlled withdrawal of the Control banks once all the Shutdown banks had been withdrawn.
I
- 2. Zero Power Test Range Determination: This was determir.ed after the point of adding
- heat had been demonstrated. Additional emphasis was placed on this measurement to
- prevent testing too low in the test range, thus minimizing gamma contribution to the L excore signal.
i
- 3. On-line Verification of the Reactivity Computer: This was detennined using stable startup rates du.'ing flux doubling measurements.
^
- 4. Boron Endpoint Measurement: This was determined with all the Control and Shutdown banks withdrawn and again with only the Control banks inserted.
- 5. Isothcnnal Temperature Coefficient Measurement (lTC): This was determined from the reactivity change measured during a Reactor Coolant temperature change. The Moderator Temperature Coefficient (MTC) was calculated from the ITC Data.
- 6. Rod Worth Measurement: Individual Control Bank wcrths were measured during rod insertion.
l
i
. l 4.0 POWER ASCENSION TESTING
SUMMARY
c . Testing was perfonned_ at- specified power plateaus of 30%, 50%, 75%, 90%_ and 100%
l . Rated Thermal Power (RTP). Power changes were governed by operating procedures and-L fuel preconditioning guidelines specified by the fuel vendor, Westinghouse.
'In order to determine' the core power distribution, flux mapping was performed at 30%,
j- :50L 90% and 100% RTP using the Fixed Incore Detector System. The resultant' peaking
[
factors were compared to Technical Specification limits to verify that the core was operating '
within its design limits.
- - Thermal-hydraulic parameters, -nuclear parameters and related instrumentation were C
monitored throughout the Power Ascension, Data was compared to previous cycle power
-ascension data at each test plateau to identify calibration or system problems. - The major
- areas analyzed were
j:
- 1~. Nuclear Instrumentation Indication: Overlap data was obtained between the Intermediate Range and Power Range channels. Secondary plant: heat balance calculations were performed to verify the Nuclear Instrumentation indications.
g 2. RCS Delta-T Indication: The initial scaling of RCS AT was left the same as' Cycle 5. At 90% RTP, aemal full power AT was extrapolated out using data fro.n 30E 50%,75%
and 90% and AT was rescaled accordingly. Final adjustments were performed at 100%
RTP.
F
- 3. Upper Plenum Anomaly: In early 1992, Westinghouse notified North; Atlantic.that-Seabroek Station may be susceptible to a phenomenon known as- the Upper Plenum Anomaly _(UPA). The UPA is primarily characterid by a periodic step changes of 1*F to 2*F in hot leg temperature. A Design _ Document was prepared at that time to.
- implement a number.of operating contingencies should the UPA be present. Cycle 6 data -
collected at 100% RTP identified the presence of UPA for RCS loops 2 and 3. ~ Revised Tuor Average Scaling (RTAS) was not implemented.
- 4. RCS Temperatures: _ Data was obtained for the-Narrow Range Loop temperatures.
Evalua: ions for Delta-T ( F), Tavo Deviation Alarm Setpoint and T A va / Tars Indication ;
were performed.
4'.0 POWER ASCENSION TESTING
SUMMARY
(Continued)
Evaluations for deviations between redundant channels on individual steam generators were perforned.'
~
- 6. Steam Generator Pressures: Data- was obtained for the steam generator pressures.
Evaluations for deviations betwe(n redundant channels on individual steam generators were performed.
- 7. Turbine Impulse Pressure (Tarr): The initial scaling of impulse pressure was left the same as Cycle 5. Impulse pressure was evaluated at the 75% and 90 % RTP plateaus to determine if the existing scaling would support continued power increase. The Cycle 6 full power value was within 4 PSIG of the initial scaling value. The need for rescaling to the Cycle 6 full power value is being evaluated.
- 8. Incore/Excore Calibration: Scaling factors were calculated from flux map data using tim single point calibration methodology. The nuclear instrumentation power range _ channels were rescaled at 50% and 100% RTP.
- 9. RCS Flow: 'A primary heat balatee was performed at 90% RTP to determine total RCS flow. The measured flow was coirected for the effects of RCS " hot leg temperature streaming" using Westinghouse methodology [WCAP-145-11]. 1 The power ascension test program required no major changes from Cycle 5. 1
, . _ _ _ _ . _ _ . . _ _ . _ . .._ _ __. _ ._. _ _ ._.. _ ...__ .. _ _ _ . _ _ ._ _.. _.._.. ._.-__._m..__.
$.0 'RFSULTS
- 1. Low- Power Physics Testing: The acceptance and review criteria were revised per
- ' Westinghouse letter 94 NA#-G-0030, Recommended Westinghouse Physics Test Results.
- The acceptance criteria and review criteria were met. See Table 1 for results.
2.- Flux Mapping: No problems were identified during the flux maps a: 30%,50%,90%
and 100% RTP. See Table 2 for results.
- 3. Full Power Thermal /Ilydraulic Evaluation: No problems were encountered with the ;
instrumentat:an. An Upper Plenum-Anomaly was identified, however, RTAS was not-implemented. See Table 3 for results.
f
TABLE 1 LOW POWER PHYSICS RESULTS CYCLE 6 ITEM- MEASURED PREDICTED ERROR CRITERIA -
- CONTROL BANK D POSITION 174 steps 116 steps 166 pcm 1500 pcm AT CRITICALITY BORON END POINTS:
- - Al.L RODS OUT 2096 ppm 2138 ppm 257 pcm i 1000 pcm o CONTROL BANKS INSERTED 1622 ppm 1632 ppm 62 pcm 2 500 pcm *
- ALL RODS OUT ITC- (pcm/*F) -2.45 -1.80 0.65 i 2*
ALL RODS OUT MTC (pcm/*F) -0.81 -0.14 N/A < l.16**
CONTROL BANK ROD WORTilS: (pcm)
- D 426 401' 25 i 100*
'e .C 918 942 24 2 141*
- B- 920 951 31 i 142*
- A 845 842 3-- i 126*
'o TOTAL 3109 3136 27 2 2822
- 314 NOTE:
- Review criteria, all others are acceptance criteria.
TABLE 2 POWER ASCENSION FLUX MAP RESULTS CYCLE 6 1
ITEM MAP 1 MAP 2 MAP 3 MAP 4
. DATE OF MAP . 06/29/97 06/30/97 07/02/97 07/02/97 POWER LEVEL (%) 29.5 47.6 91.2 100.0 CONTROL BANK D POSITION (steps) 169 191 210 225 RCS BORON (ppm) 1888 1774 1544 1480 Fo- 2.3419 2.2346 1.9272 1.8952 Fm 1.6453 1.5999 1.5368 1.5200 INCORE TILT 1.0178 1.0185 1.0170 1.0169
~
TA BLE 3 FULL POWER THERMAL-IIYDRAULIC DATA: CYCLE 6 ITEM VALUE REACTOR COOLANT T4va 586.05 *F REACTOR COOLANT DELTA-T:
- LOOP 1 57.46 *F
= LOOP 2 57.61 F
= LOOP 3 57.19 F e LOOP 4 57.96 *F REAGOR COOLANT FLOWS: (corrected for hot leg streaming affects)
. LOOP 1 100745 GPM
= LOOP 2 99559 GPM e LOOP 3 103971 GPM e LOOP 4 99695 GPM e TOTAL 403969 GPM AUCTIONEERED 111G11 TAvo 587.13 *F Tatr 587.I8'F TURBINE IMPULSE PRESSURE 669.7 PSIG STEAM GENERATOR PRESSURES:
- A 970.5 PSIG
= B 968.4 PSIG
= C 970.I PSIG
= D 967.9 PSIG 9