Notification of Supplemental Inspection Scheduling
ML072190168
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/03/2007
From: Julio Lara
Engineering Branch 3
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
Download: ML072190168 (3)


Text

August 3, 2007Mr. Christopher M. CranePresident and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

CLINTON POWER STATIONSUPPLEMENTAL INSPECTION SCHEDULING

Dear Mr. Crane:

By the letter dated February 7, 2007, the NRC finalized a White finding having low tomoderate safety significance for your Clinton Power Station facility. The finding involved inadequate consideration of vortexing in design calculations. In June 2007 we were notified by Mr. James Peterson of your staff that applicable corrective actions for that finding had either been completed or initiated, and that you were ready for the NRC to conduct our supplemental inspection to review the actions taken to address the White finding. Accordingly, we plan to conduct a supplemental inspection, beginning on August 28, 2007, at Clinton Power Station using Inspection Procedure 95001, "Inspection for One or Two White Inputs in a Strategic Performance Area." The schedule for the on-site inspection activity is August 28-30, 2007, and September 5-7, 2007. The inspector for this inspection, Mr. Ronald A. Langstaff, discussed this schedule with Mr. James Peterson of your organization in July 2007. We understand that our regulatory contact for this inspection is Mr. Ronald Frantz of your organization, and that our technical contact is Mr. Roger Weber, also of your organization. We have received your root cause evaluation, and corrective action plan for the finding, and do not require any additional information at this time. If there are any questions about the inspection, please contact the lead inspector at (630) 829-9747 or via e-mail at ral4@nrc.gov

.In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will beavailable electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the PublicElectronic Reading Room).Sincerely,/RA/Julio F. Lara, ChiefEngineering Branch 3 Division of Reactor SafetyDocket No. 50-461License No. NPF-62See Attached Distribution List C. Crane-2-cc:Site Vice President - Clinton Power StationPlant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Manager Licensing - Clinton Power Station Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer, State of Illinois Chairman, Illinois Commerce Commission C. Crane-2-cc:Site Vice President - Clinton Power StationPlant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Manager Licensing - Clinton Power Station Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer, State of Illinois Chairman, Illinois Commerce CommissionDISTRIBUTION

TEB RAG1 SPS1 MMT RidsNrrDirsIrib GEG KGO RML2 SAM9 SRI Clinton

CAA1 LSL CDP1 DRSIII DRPIII PLB1 TXN ROPreports@nrc.govDOCUMENT NAME: C:\FileNet\ML072190168.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-SensitiveTo receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copyOFFICERIIIRIIIRIIIRIIINAMERLangstaffABarker for MRingJLaraDATE08/02/0708/02/0708/03/07OFFICIAL RECORD COPY