ML072290167

From kanterella
Revision as of 20:39, 12 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
08/17/2007 Cooper Nuclear Station - Final Significance Determination for a White Finding and Notice of Violation - NRC Special Inspection Report 05000298/2007007
ML072290167
Person / Time
Site: Cooper Entergy icon.png
Issue date: 08/17/2007
From: Mallett B
Region 4 Administrator
To: Minahan S
Nebraska Public Power District (NPPD)
References
EA-07-090, IR-07-007
Download: ML072290167 (96)


See also: IR 05000298/2007007

Text

UNITED STATES . NUCLEAR REGULATORY

COMMISSION

REGION IV 611 RYAN PLAZA DRIVE, SUITE 400

ARLINGTON, TEXAS 76011-4005

August 17,2007 EA 07-090 Stewart B. Minahan, Vice President-Nuclear and CNO

Nebraska Public Power District 72676648AAvenue

Brownville, NE 68321 SUBJECT: FINAL SIGNIFICANCE DETERMINATION

FOR A WHITE FINDING AND NOTICE COOPER NUCLEAR STATION OF VIOLATION - NRC SPECIAL INSPECTION REPORT 05000298/2007007 - Dear Mr. Minahan: The purpose

of this letter

is to provide you the final results of

our significance

determination

of the preliminary

White finding identified in

the subject inspection report.

The inspection finding

was assessed using the

Significance Determination Process

and was preliminarily characterized as White, a

finding with low to moderate increased importance to safety, that may require additional

NRC inspections. This proposed White finding involved

an apparent violation

of IO CFR Part 50, Appendix B, Criterion VI "Instructions Procedures, and Drawings," involving

the failure to establish

procedural

controls for evaluating

the use of parts prior

to their installation

in safety-related applications, (e.g. the

emergency diesel generator).

At your request, a Regulatory Conference

was held on July 13, 2007. During

this conference

your staff presented information related

to the voltage regulator failures that

adversely

affected Emergency

Diesel Generator (EDG) 2. This included information

regarding the failure mechanism of the voltage regulator circuit

board, results of your root cause evaluations, and associated corrective actions.

The July 13, 2007, Regulatory Conference meeting summary, dated July 18, 2007 (ML072000280), includes a copy of the CNS presentation.

Based on NRC review

of all available information, including

the information

discussed

during the Regulatory Conference, the NRC has decided not

to pursue a violation

of 10 CFR Part 50, Appendix B, Criterion

V. However, the

NRC has determined a

violation

of 10 CFR Part 50, Appendix B, Criterion

XVI, "Corrective Action," did

occur in that CNS failed to

promptly identify a significant condition

adverse to quality that resulted

in the reduced reliability

of EDG 2. Two distinct and reasonable opportunities to identify

the condition

adverse to quality existed

yet the condition

was not promptly identified and corrected

to preclude recurrence.

Specifically, your inadequate procedural guidance

for evaluating

the suitability

of parts used in safety related

applications presented one missed

opportunity

to identify that

an EDG voltage regulating circuit

board was defective prior

to its installation

on November 8, 2006. Following

installation

of the defective EDG 2 voltage regulator circuit

board two high voltage conditions, one resulting in

an EDG automatic

high voltage trip, occurred on November 13, 2006. Your evaluation

of these high voltage events missed another

opportunity

to identify and correct the deficient condition.

Nebraska Public Power

District -2- The failure to identify and correct this

deficiency resulted in

an additional

high voltage trip of EDG 2 that occurred on January 18, 2007. This violation

is cited in the enclosed Notice of

Violation (Enclosure

I). The details describing the

10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Action," violation are described

in Enclosure 2. The NRC's

preliminary

assessment

of the safety significance

of the inspection finding

is documented

in Attachment

3 of NRC Inspection

Report 05000298/2007007 (ML071430289).

This assessment

resulted in a change in core damage frequency (delta CDF) of 5.6E-6, being a finding of low to moderate safety significance, or White. Our preliminary

assessment

used the loss of offsite power (LOOP) initiating event frequency and EDG non-recovery/repair

probabilities, as described

in NUREG/CR-6890, "Reevaluation

of Station Blackout Risk at Nuclear Power Plants, Analysis of Loss of Offsite Power Events: 1986-2004." This

assessment

assumed that the voltage regulator

degraded only during times

that the EDG was

in operation.

The assessment

assumed the voltage regulator

could not be repaired or

replaced in time to affect the outcome of any core damage sequences.

The ability to take manual

control of EDG 2 was not credited because procedures did not exist and training was not

performed

in this EDG mode of operation.

As a sensitivity assessment a case

for diagnosing the

failure of the automatic

voltage regulator

and successfully

operating

the EDG in manual mode

was considered. A recovery failure probability

for EDG 2 of 0.3 was assumed that lowered the delta CDF to a value of 1.7E-6. A value characterized

as having low to moderate safety significance, or White. Based on additional information indicating that the

voltage regulator

card failure mechanism

was intermittent, the NRC determined

that a revised safety significance

assessment

was warranted. This

revised assessment

is provided as Enclosure

3. This assessment

was performed

assuming that the faulty voltage regulator card reduced the reliability

of EDG 2. The reduced reliability factor

was calculated

assuming that two failures resulting in

high voltage EDG trips occurred within a period of 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> during which the subject voltage

regulator

card was energized.

This assumption

was made recognizing

that an additional

high voltage condition

occurred on November 13, 2006, that did not result

in an EDG trip because the duration of the high voltage

condition

was shorter than the time

delay setting. Additionally, the NRC revised

assessment

refined the probability

of failing to recover the

failed EDG 2 to a value of 0.275. This value corresponds

to an 83 percent probability for successfully diagnosing

the automatic voltage regulator failure, during

a station blackout event, and a 90 percent

probability

for successfully implementing recovery

actions. I During the Regulatory Conference, CNS asserted the finding was

of very low safety significance, or Green. On July 27, 2007, CNS provided

to the NRC their "Probabilistic

Safety Assessment" that is provided as Enclosure 4.

The CNS assessment of

very low safety significance

was made based

on five key assumptions that differed

from the NRC's. The first difference was that following failure

of EDG 2, CNS assumed recovery of EDG 2 prior to core damage occurring with

a failure probability

of 0.032. This failure probability of recovery significantly differed from the NRC assessment of

0.275. The NRC determined

that 0.275 was a more realistic

value after reviewing the human error factors present. Factors assessed

are discussed in detail in the NRC Phase

3 Analysis provided

in Enclosure 3. These

factors included:

Nebraska Public Power District

-3- I) the high complexity

of diagnosing an automatic voltage regulator failure during a station blackout event that

would involve the support of CNS engineering

staff; and 2) recovering

the failed EDG

in manual voltage control during a station blackout

event having incomplete procedural guidance

and a lack of operator training and experience involving operating

the EDG in manual voltage

control during loaded conditions.

The second difference was that CNS calculated the reduced reliability factor

for EDG 2 assuming that one failure was

the result of

the defective diode during

the 36-hour duration

the subject voltage regulator was energized.

CNS asserted that conclusive evidence did

not exist that

the cause of the November 13, 2006, event was the result

of intermittent voltage regulator card diode

failure. The NRC reviewed all available information provided

by CNS related to the November

13 event. This included

the apparent cause evaluation, the laboratory failure analysis report, industry operating experience, and electrical schematic review of

the EDG voltage regulating system. Based

on our reviews

the NRC determined that an intermittent diode failure

of the voltage regulator circuit board was

the most plausible failure

mechanism. Therefore, the NRC concluded that two failures should

be used in the EDG 2 reliability calculation.

The third difference involved CNS evaluating the

aspect of convolution related

to the probability

of recovering offsite power

or EDG 1 before or close

in time to the assumed failure of EDG

2. This consideration would render the safety consequences

of these events

to be less significant.

The NRC agreed that our

model was overly conservative

in this aspect, and performed an assessment that incorporated credit

for convolution. This resulted

in a reduction of delta CDF.

The fourth difference involved CNS crediting the station Class

1 E batteries

for periods greater

than the 8-hour duration utilized in the current risk model. Based on information reviewed

the NRC concluded that

extended battery operation beyond eight

hours was plausible, however, other operational challenges would be present

as described

in Appendix A, "Station Blackout Event Tree Adjustments,"

Table A-I of the CNS Probabilistic Safety Assessment (Enclosure

4). Based on these considerations the NRC adjusted

our model extending the Class

1 E batteries

to 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />. In addition, an adjustment was made

to account for the recovery dependency associated with

the failure of both EDGs. The fifth difference involved CNS asserting that implementation of specific station blackout mitigating actions, that were not currently credited in either the

NRC or the CNS risk models, would reduce the risk significance

of the finding. These specific actions included the use

of fire water injection to

the core, manual operation

of the reactor core isolation cooling (RCIC) system, and the ability to black

start an EDG following

battery depletion events. Based on our review, and as discussed

in the NRC Phase 3 Analysis (Enclosure

3), the NRC determined the success

of using these alternative mitigation strategies were offset by

the risk contribution of external events. After careful consideration of the information provided

at the Regulatory Conference, the information provided

in your risk assessment received on July 27, 2007, and the information developed during

the inspection, the NRC has concluded that

the best characterization of risk

for this finding is

of low to moderate safety significance (White), with a delta CDF

of 1.2E-6.

Nebraska Public Power District

-4- You have 30 calendar days from the

date of this letter

to appeal the

NRC's determination

of significance for the

identified White finding. Such appeals will be considered

to have merit

only if they meet the criteria given

in NRC Inspection Manual Chapter 0609, Attachment

2. In accordance with the NRC Enforcement

Policy, the Notice

of Violation

is considered

an escalated enforcement action

because it is associated with a

White finding. You are required

to respond to this letter and should

follow the instructions specified

in the enclosed Notice when

preparing

your response.

In addition, we will use the NRC Action

Matrix to determine the most appropriate NRC response

and any increase in NRC oversight, or actions you

need to take in response to the most recent performance deficiencies.

We will notify you by separate correspondence

of that determination. In accordance

with 10 CFR 2.390 of the NRC's "Rules

of Practice," a copy

of this letter, its enclosures, and

your response will

be made available electronically for

public inspection

in the NRC Public Document

Room or from the Publicly Available Records component

of NRC's document system (ADAMS).

ADAMS is accessible

from the NRC Web site at h t t P : //w. n rc . a ov/ r e a d i n a - r m/a d a m s . h t m I (the Pub I i c E I ec t ro n i c Read i n g Room ) . To the extent possible, your response

should not include any personal privacy, proprietary, or safeguards

information

so that it can be made available

to the Public without redaction.

Sincerely, Bru& S. Mallett Regional Administrator

Docket: 50-298 License: DPR-46

Enclosure

1 : Notice of Violation

Enclosure

2: Notice of Violation Details

Enclosure

3: NRC Phase

3 Analysis Enclosure

4: CNS Probabilistic Safety Assessment cc w/Enclosures: Gene Mace Nuclear Asset Manager Nebraska Public Power District

P.O. Box 98 Brownville, NE 68321 John C. McClure, Vice President

Nebraska Public Power

District P.O. Box 499 Columbus, NE 68602-0499

and General Counsel

Nebraska Public Power

District -5- D. Van Der Kamp, Acting Licensing Manager

Nebraska Public Power

District P.O. Box 98 Brownville, NE 68321 Michael J. Linder, Director Nebraska Department

of Environmental

Quality P.O. Box 98922

Lincoln, NE 68509-8922

Chairman Nemaha County Board

of Commissioners Nemaha County Courthouse

1824 N Street Auburn, NE 68305 Julia Schmitt, Manager Radiation Control Program Nebraska Health

& Human Services

Dept. of Regulation

& Licensing

Division of Public Health Assurance 301 Centennial

Mall, South P.O. Box 95007 Lincoln, NE 68509-5007

H. Floyd Gilzow

Deputy Director for Policy Missouri Department

of Natural Resources

P. 0. Box 176 Jefferson

City, MO 651 02-01 76 Director, Missouri State Emergency

P.O. Box 11 6 Jefferson

City, MO 651 02-01

16 Management

Agency Chief, Radiation

and Asbestos Kansas Department

of Health Bureau of Air and Radiation

1000 SW Jackson, Suite 31 0 Topeka, KS 66612-1366 Control Section

and Environment Daniel K. McGhee, State Liaison Officer

Bureau of Radiological

Health Iowa Department

of Public Health Lucas State Office Building, 5th Floor 321 East 12th Street Des Moines, IA 50319 Melanie Rasmussen, Radiation

Control Bureau of Radiological

Health Iowa Department

of Public Health Lucas State Office Building, 5th

Floor 321 East 12th Street Des Moines, IA 50319 Program Director Ronald D. Asche, President

and Chief Executive

Officer Nebraska Public Power

District 141 4 15th Street Columbus, NE 68601 P. Fleming, Director of Nebraska Public Power

District P.O. Box 98 Brownville, NE 68321 Nuclear Safety Assurance

John F. McCann, Director, Licensing

Entergy Nuclear Northeast

Entergy Nuclear Operations, Inc. 440 Hamilton Avenue White Plains, NY 10601-1813

Keith G. Henke, Planner Division of Community

and Public Health Office of Emergency Coordination 930 Wildwood, P.O. Box 570 Jefferson City, MO 65102 Chief, Radiological

Emergency Preparedness Section

Kansas City Field Office

Chemical and Nuclear Preparedness

and Protection Division

Dept. of Homeland Security 9221 Ward Parkway Suite 300 Kansas City, MO 641 14-3372

Nebraska Public Power

District -6- I Distribution:

RIDSSECYMAILCENTER

RI DSEDOMAI LCENTER RI DSOGCMAILCENTER

R I DSNRRAD I P RI DSOIMAILCENTER

RIDSOCFOMAILCENTER

RI DSRGN2MAI

LCENTER RlDSNRRDlPMl

IPB OEMAIL /RA MCHay for/ IRA/ /RA/ /RA/ /RA/ 07/26/07 08/09/07 08/09/07 07/26/07

07130107 RIDSOCAMAILCENTER

RI DSOEMAILCENTER

RIDSNRROD

RlDSOPAMAl L

RlDSOlGMAl

LCENTER RlDSRGNl MAILCENTER

RIDSRGN3MAILCENTER

OEWEB RC:ACES DD:DRP KSFuller AVegel cc wlenclosures (via ADAMS e-mail distribution):

B. Mallett (BSMI) T.P. Gwynn (TPG) K. Fuller (KSF) W. Maier (WAM) A. Howell (ATH) T. Vegel (AXV) D. Chamberlain (DDC) R. Caniano (RJCI) W. Jones (WBJ) M. Hay (MCH2) N. Taylor (NHT) J. Wray, OE (JRW3) DRS BC's (DAP, LJS, ATG, MPSI) M. Herrera (MSH3) D. Starkey, OE (DRS) M. Ashley, NRR (MAB) N. Hilton, OE (NDH) M. Haire (MSH2) M. Vasquez (GMV) C. Carpenter, OE (CAC) V. Dricks (VLD) J. Cai, OE (JXCII) S. Farmer (SEFI) - ~- - - _- - NRR NRR NRR SMWong M Franovich

SARichards

SUNS1 Review Completed: MCH ADAMS:

Yes0 No Initials:

MCH 611 Publicly Available

Non-Publicly

Available

0 Sensitive

EI Non-Sensitive

/RA/ /RA electronic/

/RA electronic/

/RA ECollins for/

081 09 107 081 09 107 081 09 I07 081 09 I07 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

  • Previous

Concurrence

NOTICE OF VIOLATION

Nebraska Public Power

District Cooper Nuclear

Station Docket No. 50-298 License No. DPR-46 EA-07-090

During an NRC inspection

completed on April 24, 2007, and following a Regulatory Conference

conducted

on July 13, 2007, a violation

of NRC requirements

was identified. In

accordance

with the NRC Enforcement Policy, the violation

is listed below: 10 CFR Part 50, Appendix B, Criterion

XVI, requires, in part, that

measures shall be established

to assure that conditions

adverse to quality, such as failures and malfunctions, are promptly

identified

and corrected.

In the case of significant conditions

adverse to quality, the measures

shall assure that the cause

of the condition

is determined and corrective action

taken to preclude repetition.

Contrary to the above, as of January 18, 2007, the licensee failed to establish

measures to promptly identify and correct a significant condition

adverse to quality, and failed to

assure that the cause of a significant condition

adverse to quality

was determined and that corrective action

was taken to preclude repetition. Specifically, the licensee's

inadequate procedural guidance for evaluating

the suitability

of parts used in safety related

applications

presented

an opportunity

in which the licensee failed to

promptly identify a defective

voltage regulator circuit board used

in Emergency

Diesel Generator (EDG) 2 prior to its installation

on November 8, 2006, a significant condition

adverse to quality. Following

installation

of the defective EDG

2 voltage regulator

circuit board, the licensee failed to determine

the cause of two high voltage conditions

which occurred on

November 13, 2006, and failed to

take corrective action to

preclude repetition.

As a result, an additional high

voltage condition

occurred resulting

in a failure of EDG 2 on January 18,2007. This violation

is associated

with a White SDP finding.

Pursuant to the provisions

of 10 CFR 2.201, Nebraska Public Power District is hereby required to submit a written statement

or explanation

to the U.S. Nuclear Regulatory Commission, ATN: Document Control Desk, Washington, DC 20555-0001

with a copy to the Regional Administrator, Region IV, and a copy to the NRC Resident Inspector

at the facility that

is the subject of this Notice, within 30 days of the date of the letter transmitting this

Notice of Violation (Notice).

This reply should be clearly marked as a "Reply to a Notice of Violation;

EA-07-090," and should include for

each violation: (1) the reason

for the violation, or, if contested, the basis for

disputing

the violation

or severity level, (2) the corrective

steps that have been taken and the results

achieved, (3) the corrective

steps that will be taken to avoid further violations, and (4) the date when

full compliance

will be achieved. Your response may reference

or include previous docketed correspondence, if the correspondence adequately addresses the required

response.

If an adequate reply is not received within the

time specified

in this Notice, an order

or a Demand for Information may

be issued as to why the license

should not be modified, suspended, or revoked, or why such other

action as may be

proper should not be taken. Where good cause is shown, consideration

will be given to extending

the response time. -1 - Enclosure

1

Because your

response will be made available

electronically

for public inspection

in the NRC Public Document Room or from the NRC's document system (ADAMS), accessible from

the NRC Web site at http://www.nrc.qov/readinq-rm/adams.html, to the extent possible, it

should not include any personal privacy, proprietary, or safeguards

information

so that it can be made

available to the public

without redaction.

If personal privacy or proprietary information

is necessary

to provide an acceptable response, then please provide a bracketed copy of your

response that identifies

the information that

should be protected and a redacted

copy of your response that deletes such

information.

If you request withholding

of such material, you must specifically

identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g., explain why the disclosure of information

will create an unwarranted invasion

of personal privacy or provide the information required

by 10 CFR 2.390(b) to support a request

for withholding

confidential

commercial or financial information). If

safeguards

information

is necessary

to provide an acceptable response, please

provide the level

of protection

described

in 10 CFR 73.21. Dated this 17th day of August 2007.

-2- Enclosure

1

Notice of Violation Details

Scope Following

issuance of NRC Inspection Report 05000298/2007007 (ML071430289), that identified an apparent violation of

10 CFR Part 50, Appendix B, Criterion

V, "Instructions

Procedures, and Drawings," additional information was reviewed that included the CNS Probabilistic

Safety Assessment, laboratory information related to

the failure mechanism

of the voltage

regulator circuit board, and information discussed during

the Regulatory Conference

held on July 13, 2007, related to this potential finding. After

reviewing

all available information related

to the Emergency

Diesel Generator (EDG) 2 high voltage

events, the NRC decided not to pursue a violation

of 10 CFR Part 50, Appendix B, Criterion

V. However, the NRC determined

an apparent violation of

10 CFR Part 50, Appendix B, Criterion

XVI, "Corrective Action," did

occur in that CNS failed to promptly identify a significant condition

adverse to quality that resulted in the reduced

reliability

of EDG 2. Two distinct

and reasonable

opportunities

to identify the condition

adverse to quality existed yet the condition was not

promptly identified

and corrected

to preclude recurrence.

The following

details discuss the additional information reviewed and

provide the basis for our decision.

Details On November 8, 2006, .a potentiometer mechanically failed during planned maintenance

on the Emergency

Diesel Generator (EDG) 2 voltage

regulator. Work order 4514076 provided

the technical instructions

for this maintenance

activity and contained a contingency

for the replacement

of the voltage regulator printed circuit

board. Replacement

of the circuit board was performed on November

8, 2006. Following replacement, the

circuit board required tuning. The tuning process was conducted

on November 13, 2006, and included making incremental

adjustments

to the R13 feedback

adjust potentiometer

and then introducing

small voltage demand changes. Approximately

ten seconds after one voltage demand change EDG 2 experienced a

pair of output voltage spikes, the first to approximately

5500 volts, and the second

to greater than 5900

volts. The second voltage spike resulted in

a high voltage trip of EDG 2. The NRC noted that at the time the voltage spikes

occurred, maintenance personnel

were reviewing strip chart

recorder traces and no voltage

regulator components were being manipulated and

no changes in demanded voltage

were occurring.

The licensee conducted

a failure modes effects analysis (FMEA) and completed troubleshooting

activities

consisting

of diagnostic

tests and test runs of EDG 2 between November 13-15, 2006.

Based on the lack of any additional high

voltage events during

the test runs, completion

of the FMEA, and input from a vendor field representative, the

licensee concluded

that the high voltage events that occurred on November 13 were

attributable

to erratic behavior of the feedback potentiometer being adjusted

to tune the circuit board.

This conclusion

is described in the apparent cause evaluation attached

to Condition

Report CR-CNS-2006-09096.

After completion

of a subsequent

series of satisfactory surveillance test runs, EDG 2 was declared operable on

November 19,2006. Subsequently, on January 18, 2007, EDG 2 experienced another

high voltage trip during surveillance testing.

The licensee's root cause

evaluation

of this high

voltage trip, as described

in Condition

Report CR-CNS-2007-00480, determined

that a manufacturing

defect of a diode, attached to the printed circuit

board installed

on November 8, 2006, caused

the high voltage conditions

observed.

-1 - Enclosure

2

The NRC reviewed the Condition Report CR-CNS-2006-9096 apparent cause evaluation addressing the high voltage

conditions experienced on

November 13, 2006, conducted

interviews

with engineers and maintenance personnel, and reviewed applicable technical manuals. The

NRC determined that erratic

behavior of either

or both potentiometers

on the printed circuit

board was not a likely cause for the November 13, 2006, high voltage events. The NRC discussed

this observation with licensee

management

on February 1 , 2007, after which the licensee initiated Condition Report CR-CNS-2007-00959 documenting

the concern. Following

these discussions, the licensee completed a

more detailed evaluation of the apparent cause. This more

detailed evaluation

concluded

that the erratic behavior of the feedback potentiometer, combined

with the possibility that

an oxidation layer

could have built up on the potentiometer slide wire, could have caused an open circuit on the voltage regulator printed circuit board. The licensee believed

that this open circuit could have resulted in the

high voltage condition that EDG 2 experienced. The

NRC noted that this evaluation was

not based on direct observation or circuit

modeling, but on hypothetical information from a field service

vendor. The NRC questioned the licensee if the vendors were aware

of any similar EDG high voltage condition occurring due to erratic potentiometer operation during the

tuning process of the voltage regulator circuit

board. The licensee provided the NRC a

written response from the vendor that stated, "No.

In addition, we

have not seen or heard of such an event while adjusting the Range and/or

Stability

potentiometers

on any make or model of voltage regulator." The NRC noted that the November 13, 2006, high voltage trip of EDG 2 was not viewed by the licensee as a possible precursor

to the January 18, 2007, event until the receipt of a laboratory

report on May 8, 2007. This laboratory report contained the

results of destructive testing

of the VRI zener diode from the voltage

regulator

printed circuit board. This

report provided definitive

evidence that the January 18, 2007, overvoltage

trip of EDG 2 was caused by an intermittent

discontinuity

in the diode resulting from a manufacturing

defect. Based on this new information, the licensee revised

the root cause report in CR-CNS-2007-00480 and viewed

the November 13, 2006, EDG 2 high voltage trip as a possible precursor

to the January

18, 2007, EDG 2 high voltage trip. Additionally, the NRC noted that when the faulted circuit

board was being evaluated

at the laboratory, no actions were taken to validate if the potentiometers

on the card were potentially

the source of the high voltage events that occurred on November 13, 2006, as their FMEA

had concluded.

The NRC reviewed the FMEA performed

in Condition Report CR-CNS-2006-9096. The

NRC noted that operating and maintenance instructions of the EDG voltage

regulator

system are described

in the Basler Electric Company Operation and Service Manual, Series Boost

Exciter- Regulator, Type SBSR HV, dated November 1970. In addition, the NRC noted that Electric Power Research

Institute (EPRI) published a technical report, Basler SBSR Voltage Regulators

for Emergency

Diesel Generators, dated

November 2004, that provided updated

operating, maintenance, and troubleshooting

recommendations

to industry users.

The licensee used both

of these resources

extensively

for procedure development and

to guide troubleshooting

efforts. The NRC noted Section

5 of the Basler vendor manual provided recommendations

for maintenance

and troubleshooting.

Table 5-1 of this manual provided a

symptom based-probable

cause table for voltage regulator

problems. In the case of the November 13, 2006, EDG 2 high voltage trip, the following

guidance was applicable:

-2- Enclosure 2

Svmptom Voltage high, uncontrollable with voltage adjust

rheostat.

Remedy If no voltage control on automatic operation, replace

fuse F1. If no voltage control on

manual operation, replace fuse F2. Replace printed circuit board

assembly. Probable Cause Open fuse

F1 in voltage regulator power stage.

Defect in voltage regulator printed circuit board. No current indicated on saturable transformer control current meter.

Section 8 of the EPRl technical report also provided troubleshooting recommendations. The section of the table

that provided valuable insight for the November 13 trip is as follows: Symptom Voltage high

and uncontrollable with

motor operated potentiometer (MOP) Problem No or low voltage from sensing

potential

transformers Shorted MOP

T2 transformer set to wrong tap Faulty voltage regulator assembly

Solution Verify that there are no blown potential transformer fuses

and that there are good connections

at the potential

transformers

Replace R60 or entire MOP assern bly Verify tap setting of 120 VAC Replace voltage

regulator assembly

The NRC noted that

the FMEA discussed each

of the probable causes of

the uncontrollable high

voltage on EDG 2, but

that not all of the recommended actions were taken. Specifically, the licensee did not

replace the faulty voltage regulator assembly even though both the Basler technical manual and

the EPRl technical report recommended its replacement following uncontrollable high voltage conditions.

In addition, the NRC noted that Condition Report CR-CNS-2006-9096, contained a summary

of industry operating experience regarding failures

of Basler voltage regulators. Of the

58 Basler -3- Enclosure 2

failures listed in the report, 33 involved Basler

SBSR voltage regulators, the same type used at Cooper Nuclear Station. Of these, four involved manufacturing defects on the printed circuit boards. The

NRC identified another eight Basler voltage regulator failures

related to manufacturing quality

in publicly available sources

of operating experience.

The NRC also noted that none of these failures occurred due

to erratic potentiometer operation utilized during the tuning process.

As previously documented

in NRC Inspection Report 05000298/2007007, the licensee root

cause report evaluating

the January 18, 2007, EDG 2 high voltage event, documented

in CR-CNS-2007-00480, determined that the cause of the failure

was that the original procurement

process did not provide technical requirements

to reduce the probability of infant mortality failure

in the voltage regulator board.

The licensee determined that the failed circuit

board had been purchased from the Basler Electric Company

in 1973, but that the procurement of the part had not specified

any technical requirements from

the vendor. In effect, the part was purchased

as a commercial grade item

from a non-Appendix B source and placed into

storage as an essential component, ready for

use in safety-related applications, without

any documentation of

its suitability for that purpose.

The licensee determined that the specification of proper technical requirements, such

as inspections and/or testing, would have provided

an opportunity

to discover the latent defect prior

to installing the card

in an essential application. During the Regulatory

Conference

on July 13, 2007, the licensee stated that even if

they had performed additional testing, such

as a burn in, of

the voltage regulator card

prior to its installation on November 8, 2006, that such testing would probably not identify

the faulty diode.

In addition, the licensee stated that since

this card was purchased

in 1973, Generic Letter

91-05, "Licensee Commercial-Grade Procurement and Dedication

Programs," discussed that the

NRC did not expect licensee's

to review all past procurements.

With respect to these assertions, the NRC determined that had the licensee performed testing

of the card prior

to its installation

in accordance with standard industry recommendations, there

was some probability that

such a defect would have been identified. This conclusion was based on

the fact the laboratory

findings coupled with

the actual high voltage occurrences experienced

on November 13, 2006, and January 18, 2007, confirmed that the failure was of an intermittent nature and variations such as temperature alone could cause

the condition

to manifest itself.

With respect to the assertion that Generic Letter 91-05 did not require licensee's

to review past commercial grade procurements that may have been inappropriately dedicated suitable for

safety related applications, the NRC determined

the licensee missed an opportunity

to perform additional evaluations concerning

the suitability of the voltage regulating circuit

board prior to its installation. Specifically, Generic Letter 91-05 states, in part, that

the NRC does not

expect licensee's

to review all past procurements. However, if failure experience or current information on supplier adequacy indicates that a component

may not be suitable

for service, then

corrective actions are required

for all such installed and stored items

in accordance

with 10 CFR Part 50, Appendix B, Criterion

XVI, "Corrective Action." Based on

the previously discussed operating experience related

to quality concerns associated with Basler voltage regulating cards, the

NRC determined that the licensee missed an opportunity

to evaluate this information prior to installing

the EDG 2 voltage regulating card on November 8, 2006. Additionally, following

the high voltage conditions experienced

on November 13, 2006, this operating experience, although obtained, did not result

in the licensee questioning

the quality of the component as reflected in Item 10 of the licensee's Equipment

Failure Evaluation Checklist dated November 30, 2006, stating there

were no concerns associated with

the quality of

the part. -4- Enclosure 2

Additionally, the NRC reviewed Condition

Report CR-CNS-2007-04278, which reported that

the licensee had

failed to perform a required root cause analysis

following

the diesel generator

failure on November 13, 2006. Administrative Procedure

05.CR, "Condition Report

Initiation, Review, and Classification,"

Revision 7, requires that

a condition

report be classified

as Category A (root cause investigation)

for "repeat Critical 1 Component

equipment failures that have previously been addressed

with a root or apparent cause evaluation."

Voltage control problems on

EDG 2, a "critical

I component"

in the licensee's equipment reliability program, had been addressed using apparent cause evaluations

on four separate occasions

in the twelve months

prior to the November 13, 2006, high voltage

trip. Contrary to the guidance in Procedure

0.5CR, the November 13 trip was again assigned an apparent cause evaluation versus the required

root cause evaluation.

When EDG 2 subsequently

tripped again on January 18, 2007, a root cause team was assembled, which resulted in the identification

of a defective

diode on the voltage regulator printed circuit

board. Based on the previously discussed observations the NRC concluded that multiple opportunities existed for the

licensee to promptly identify that the EDG 2 voltage

regulating

card installed

on November 8, 2006, was defective prior

to declaring the EDG operable on November 19, 2006. Based on the failure to

promptly identify this

degraded condition corrective actions were

not implemented

in accordance

with 10 CFR Part 50, Appendix B, Criterion

XVI, "Corrective Action," resulting in

the failure of EDG 2 on January 18, 2007.

Analvsis:

This finding is a performance deficiency because the licensee

failed to promptly identify that a defective

Emergency

Diesel Generator (EDG) 2 voltage regulator circuit

board was installed

that resulted in

adversely affecting the

safety function of equipment important

to safety. This finding is more than minor because it is associated

with the equipment performance

attribute

of the Mitigating Systems cornerstone and adversely

affects the cornerstone

objective

of ensuring the availability, reliability, and capability

of systems that

respond to initiating

events. This finding was evaluated using the

Significance Determination Process (SDP) Phase

1 Screening Worksheet provided

in Manual Chapter 0609, Appendix A, "Significance

Determination of Reactor

Inspection

Findings for At-Power Situations." The screening

indicated

that a Phase 2

analysis was required because the finding

represents

a loss of safety function for EDG 2 for greater than its Technical

Specification allowed completion

time. The Phase 2 and 3 evaluations

concluded

that the finding was of low to moderate safety significance (See Enclosure

3 for details).

The cause of this finding

is related to the problem identification

and resolution crosscutting

components

of the corrective action

program and operating experience because

the licensee failed to thoroughly evaluate the EDG high

voltage condition

such that resolutions

address the causes and the licensee

failed to effectively use operating

experience, including

vendor recommendations, resulting

in changes to plant equipment (P.l (c)), and (P.2(b)).

-5- Enclosure 2

Cooper Nuclear Station

Failure of EDG 2 Voltage Regulator

NRC Phase 3 Analysis The NRC estimated

the risk increase resulting from

the degraded Emergency Diesel Generator (EDG) 2 voltage regulator.

The diesel was run at the following times with durations reported

as the period of time that

the voltage regulator

was energized (all of these operational runs were conducted after the defective voltage regulator circuit board was installed):

11/11/06 0 hrs 3 min 11/13/06 1 hr

30 min (first

failure) 11/14/06 6 hrs 46 rnin 11/15/06 1 hr 35 rnin

11/16/06 9 hrs 23 rnin

11/17/06 5 hrs 3 min 11/18/06 2 hrs 28

min 12/12/06 5 hrs 41 rnin 01/18/07 4 hrs 16 min (second

failure) The unit was returned to Mode 1 on November 22, 2006, and

ran at power until the last failure occurred on January 18, 2007.

The period of exposure was 57 days.

Assumptions

1. The licensee

determined that the voltage regulator failures were caused

by an intermittent

condition

resulting

from a faulty diode. Two failures of the voltage regulator occurred within a period

of 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> during which the voltage regulator

was energized. This information was

used to calculate

an hourly failure rate for use in the risk analysis. The

NRC noted the licensee had

calculated

an increased unreliability

of the voltage regulator

by performing a Bayesian update

of industry data. However, the NRC determined that

the risk impact

is more accurately expressed

by modeling the condition

as a new failure

mode of the diesel

generator.

2. 3. Common cause vulnerabilities for EDG 1 did not exist, that

is, the failure

mode is assumed to be independent

in nature. This is because the root

caus'e investigation determined that

the failure was the result of a manufacturing defect resulting

in an infant

mortality.

The same component in

EDGI had been installed since initial plant operations and had operated reliably beyond the "burn-in" period, providing evidence that it did not have the same manufacturing defect. The NRC considered the probability of EDG 1 failing from

defective voltage regulator within a short period of time

of the EDG 2 failure to be too low to affect the

results of this analysis. The standard

CNS SPAR model credited the Class 1 E batteries with an 8-hour discharge capability following a station blackout. Based on information received from the licensee, this credit was

extended to 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />. Although

the batteries could potentially function

beyond IO hours under certain conditions other challenges related to

the operation of

RCIC and HPCl in station blackout conditions would

be present. These challenges

included the availability of adequate injection supply water and operational concerns

of -1- Enclosure 3

RClC under

high back pressure

conditions

as a result of

the unavailability

of suppression pool cooling

during an extended station blackout event. Performance Shaping

Factor 4. Using the SPAR-H methodology, it was estimated

that the probability of recovering from the failure, using manual voltage

regulation control, in a time frame

consistent

with the core damage sequences

was 72.5 percent, or a 0.275 non-recovery

probability.

Recovery would involve diagnosing the problem and then making a decision to either

replace the automatic voltage regulating circuit

board or operate the EDG in a manual voltage

regulating

mode. Diagnosis

(0.01) The results of this analysis are

presented in the table

below: Experiencenraining

Procedures

~ Low (1 0) Incomplete

(20) Available

Time I Expansive Time

(0.01) (>2X nominal and > 30 min.) Work Processes

Total' Stress I High (2) Nominal 0.168 Complexity

I High (5) Ergonomics

1 Nominal Action (0.001) >5 Times Required

(0.1) High (2) I I Moderate (2) Incomplete

(20) Nominal I Poor (5) I Overall Total

HRA I 0.275 I (1) This reflects the result using the formula for cases where

3 or more negative

PSFs are present. The nominal time

for performing the

actions was small compared

to the minimum time of 4 or 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> available (for most core damage

sequences) to restore

power following

a loss of offsite

power (LOOP) event. The time available

for diagnosis

was considered

to be expansive because

it exceeded twice

what would be considered nominal

and is greater than 30 minutes. Extra time was credited for the action steps because at least 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> would be available for

most sequences and it was assumed that approximately

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> would be required.

High stress was

assumed because the station would be in a blackout condition.

The steps needed

to diagnose the problem and decide on

an action plan to either replace the voltage

regulator

or attempt manual voltage

control operation

were considered

to be highly complex because procedural guidance did not direct operators

to take manual voltage regulation control

of the EDG following high voltage

trip conditions. Diagnosing the

failed voltage regulator

and determining subsequent recovery

actions would be an unfamiliar maintenance task requiring high skill. During NRC

discussions

-2- Enclosure

3

5. with control

room operators they stated engineering support would be required to evaluate

the diesel failure

rather than attempt to start the EDG in manual control, potentially damaging the

machine. The NRC addressed diagnosis recovery

as presented in the SPAR-H Method

in NUREG/CR-6883, Section 2.8, "Recovery." Additional credit

for this finding

was not considered applicable because of a lack of additional alarms or cues that would occur after the initial diagnosis effort

was completed. Also, the

NRC determined that recovery from an initial diagnosis failure was already adequately accounted

for in the 0.01 factor that was applied for the availability

of expansive time. The actions needed

to operate the diesel generator

in a manual voltage regulating mode were considered to be moderately

complex. Low training and experience

was assumed because

the plant staff had

not performed this

mode of operation

and had not received specific training. Procedures focused on

manual operation

of the diesel were not available, but credit for incomplete procedures was

applied because various technical sources were available that could be pieced together

to generate a temporary working procedure.

Work processes for actions were considered

poor because a substantive crosscutting issue is currently open related

to personnel failing

to adhere to procedural compliance, reflective

of a trend of poor work practices.

The result of

the SPAR-H analysis

was a failure probability

of 0.275. For the short-term (30-minute) sequences in

the SPAR model (corresponding

to the failure

of steam-powered

high pressure injection sources), credit

for recovery of

the EDG 2 voltage regulator failure was not applied because

of inadequate

time available. For cutsets that contained both recovery of EDG

2 from the voltage regulator failure and a standard generic recovery

for EDGs, which

in this case would apply

only to a recovery of

EDG 1, a dependency correction

was applied as discussed in the SPAR-H Method in NUREG/CR-6883, Section 2.6. The dependency rating

was determined to be

"high," based on the rating factors of "same crew" (crew in this case was defined

as the team of managers and engineers who would

be making decisions

related to the recovery of both EDGs), "close

in time", and "different location. To account for the dependency on

the recovery of EDG 1 , the formula of (1 + base SPAR non-recovery probability)/2

was used. The use of a dependency correction accounts for several issues, including the fact that the standard

EDG recovery factors

in SPAR models address

the probability

of recovering

one of two EDGs that have failed, meaning that

the more easily recoverable

unit can be selected for this

purpose. In this case, the recovery factor is limited to only one EDG, and the option to select

the other EDG

is not available within

the mathematics of the model. The dependency also accounts for situations where recovery

of one EDG may be abandoned

in favor of recovery the other unit, and where

the recovery team loses confidence after experiencing a failure

to recover the first EDG.

It also accounts for the splitting

of resources

in the double-EDG failure scenario.

6. For EDG fail-to-run

basic events, the Cooper SPAR

model assumes that the failure occurs

immediately

following

the loss of offsite power event. This

is a conservative modeling

assumption

because it fails to account for scenarios where

offsite power or the other EDG is recovered prior to the moment that the EDG 2 experiences a failure

to run. For the assumed intermittent failure condition of EDG 2, failure is

assumed to be equally probable

throughout

the 24-hour mission time. Therefore, recovery of offsite power

or the other diesel generator

before or close in time following the assumed EDG 2 failure renders the safety consequences of

the performance deficiency to

be insignificant

in those cases.

To -3- Enclosure

3

correct for this conservatism, the Cooper

SPAR model was modified with sequence specific convolution correction factors that

were applied whenever an EDG fail-to-run event appeared

in a cutset. Delta-CDF Result

in SPAR 7.846-6 /vr. Internal Events

Analysis Result for 57-Day Exposure 1.2E-6 The Cooper SPAR model, Revision 3.31 , dated October

IO, 2006, was used in the analysis. A

cutset truncation

of 1 .OE-I 2

was used. Average test and maintenance

was assumed. The model

was modified as previously discussed

to apply convolution correction factors and

to credit the battery with a IO-hour discharge capability. In addition, a modeling error

was discovered and corrected related

to the failure of a battery charger on a train alternate to an EDG failure.

The result of this correction reduced the base CDF result of

the model. For the estimate of

the voltage regulator failure rate, the NRC assumed a "zero" prior distribution

which resulted in a lambda value of 0.556 for two failures occurring

in a 36-hour time period (Assumption

1). Using a Poisson distribution, this equates

to a probability of 0.736 that

the EDG will fail to run within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> following a demand. A 24-hour period

is used as the standard mission time within

the SPAR model.

The NRC created a new basic event for the failure of

the voltage regulator and placed

it into the fault tree for "Diesel Generator 2 Faults." Under the same "AND" gate, a basic event

for recovery of the EDG 2 voltage regulator failure (0.275)

was inserted. As previously discussed, for cutsets that contained both

failure to recover EDG 2 from the voltage regulator failure and a standard

SPAR EDG recovery

term, which would

in this case only apply

to EDG 1, a correction

to the standard EDG non-recovery probability

was applied to account for

the dependency between these two

recoveries.

Using the SPAR-H methodology, a

high dependency was determined

and the calculation using

this assumption resulted in

an increase in the non-recovery probability

for EDG 1 within the affected cutsets. Additionally, for cutsets containing a 30-minute recovery term, related to the loss of high pressure injection sources, the value of the EDG 2 voltage regulator

non-recovery probability was

set to 1 .O, because recovery of EDG 2 would not be possible

in that time frame. The common

cause EDG fail-to-run term

was not changed and therefore all cutsets containing this term were completely offset

by the base case. The following table displays the result of

the analysis: The major cutsets were reviewed and no anomalies were identified. External Events

Analysis The risk increase

from fire initiating events

was reviewed and determined

to have a small impact on the risk of the finding. Only two fire scenarios were identified where equipment damage could

cause an unintentional

LOOP to occur. These are a fire

in control room board C

or a fire in control room vertical

board F. For these control room fires, the probability of causing a

LOOP are remote because of the confined specificity of their locations and

the fact that a combination

of hot shorts of a specific polarity are needed

to cause the emergency and startup transformer breakers -4- Enclosure 3

to open. Breakers

to these transformers

do not lock out and recovery of power

can be achieved

by pulling the control

power fuses at the breakers and operating

the breakers manually.

Procedures

are available

to perform these actions. The combination

of the low event frequency and high recovery probability means that fires

in these locations

do not add appreciably

to the risk of this finding. The other class of fires resulting

in a LOOP required an evacuation of the control room. In this case, plant procedures

require isolating offsite power from the vital buses and using the preferred

source of power, Division 2 EDG. The sequences that could lead

to core damage would include a failure of the Division

1 EDG, such that ultimate success in averting core

damage would rely on recovery of either EDG

or of offsite power. A review

of the onsite electrical distribution

system did not reveal any particular difficulties

in restoring switchyard power to the vital buses

in this scenario, especially

given that at least 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> are available

to accomplish

this task for the

bulk of the core damage scenarios. Switchgear room fires only affected the ability

to power one of the two vital

buses from offsite power, leaving at least

one vital bus available for plant recovery. Therefore, a

fire in Switchgear Room A would not

require operation of EDG 2 and a fire

in Switchgear

Room B would not affect the risk difference

of the finding because it would cause the same consequence as

in the base case. In general, the

fire risk importance for this finding is small compared

to that associated

with internal events because onsite fires

do not remove

the availability

of offsite power in the switchyard, whereas, in the internal events scenarios, long-term unavailability

of offsite power is presumed to occur as a consequence

of such events

as severe weather or significant electrical grid failures. The Cooper IPEEE

Internal Fire Analysis screened the

fire zones that

had a significant

impact on overall plant risk.

When adjusted for the exposure period

of this finding, the cumulative

baseline core damage frequency for the zones having

the potential for a control room evacuation (and a

procedure-induced

LOOP) or an induced plant centered LOOP was approximately 3.6E-7/yr. The methods used to screen

these areas were not rigorous and used several bounding assumptions, the refinement of which would likely lower the result. Based on these considerations, the

NRC concluded that

the risk related to fires would not be sufficient to change

the risk characterization of this finding. The seismicity at

Cooper is low and would likely have a small impact

on risk for an EDG issue. As a sensitivity, data

from the RASP External Events Handbook was used

to estimate the

scope of the seismic risk particular

to this finding.

The generic median earthquake acceleration

assumed to cause a loss of offsite power is 0.3g. The estimated frequency

of earthquakes

at Cooper of this

magnitude or greater

is 9.828E-5/yr. The generic median

earthquake

frequency

assumed to cause a loss of the diesel generators

is 3.lg, though essential equipment

powered by the EDGs would likely

fail at approximately 2.0g. The seismic information

for Cooper is

capped at a magnitude

of 1 .Og with a frequency of 8.187E-6. This would

suggest that an earthquake could

be expected to occur with an approximate frequency of

9.OE-5/yr that would remove offsite power

but not damage other equipment important to safe shutdown. To model the seismic

risk, that NRC assumed that offsite power could not

be recovered

within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and therefore

zeroed all offsite power recoveries in the SPAR model. A CCDP

was -5- Enclosure 3

generated for the base case and, using the same assumptions

for the failure probability of the voltage regulator, for the analysis case. The result is presented

in the following table: (I EF=9E- 57-Day

Exposure I .279E-3 7.560E-3 5.7E-7

8.9E-8 Flooding could

be a concern because of the proximity

to the Missouri River. However, floods that would remove offsite power would also likely flood the EDG compartments and therefore not result in a significant change

to the risk associated with

the finding. The switchyard elevation is

below that of the power block

by several feet, but it is not likely that a slight inundation of the switchyard would cause a

loss of offsite power. The low frequency

of floods within the thin slice of water elevations that

would remove offsite

power for at least

4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, but not debilitate the diesel generators indicates

that external flooding would not add appreciably

to the risk of this

finding. The NRC determined

that although external

events would add risk

to the overall assessment, the

amount of risk would be small and not change the safety significance of the finding.

Alternative Mitigation Strategies

The NRC noted that several alternative mitigation strategies

discussed

by the licensee during the Regulatory Conference

on July 13, 2007, were

not modeled or were disabled

in the SPAR model. These strategies included

the ability to operate RClC

in a manual mode of operation following battery depletion, the use of firewater injection into the

RCS, and the capability

to blackstart an EDG following

loss of the Class IE dc buses. With respect to the use of fire water injection the

NRC noted that

the CNS SPAR model integrates a recovery

based on firewater injection into the station blackout event tree.

In the base case, this recovery is

set at a non-recovery probability of 1 .O, which implies

no recovery credit.

As a sensitivity study, the NRC assumed a baseline firewater

failure probability

of 0.1 and noted that the final delta CDF result

was decreased

by only 2.1 percent because firewater was

only modeled in depressurized reactor coolant system sequences

that were not large risk contributors

to this finding.

With respect to manual operation of the RClC

system, the NRC noted that this mitigation strategy was not credited in either the NRC or CNS risk assessment models. Nonetheless, the feasibility

of this strategy was assessed

by reviewing station procedures, interviewing station personnel, performing a field walkdown of

the procedural

steps with station operators, and evaluating the

human error factors that would be present following an extended station blackout event resulting in depletion of

the station essential batteries. Based on this qualitative review, the NRC concluded that

this strategy would not significantly change

the overall risk assessment conclusion

for this specific type of event. Factors assessed that affected

this decision included:

1) following depletion of

the battery supporting

RClC operation the initial valve lineup supporting manual system operation would

take at least 75 minutes; 2) no cooling over an extended period of time

in the RClC turbine room causes

an extremely high temperature environment that would significantly restrict personnel stay times;

3) reactor vessel level indication is

on a different

-6- Enclosure 3

elevation than the RCIC flow

controls;

4) manual starting of the RClC pump in this configuration

has not been tested; 5) position indication

is not readily available

for motor operated

valves; 6) procedures are

not clear ensuring proper

system alignment;

7) procedures do

not verify adequate RClC water supply tank level prior to starting

the pump nor supply adequate guidance to maintain adequate level during RClC operation

to prevent vortexing

concerns in the supply tank; 8) one identified

motor operated valve that is required to be manually operated

is approximately

12 feet above the floor and is not readily accessible because it is directly above the

RClC turbine; 9) operators would be

required to travel up and down multiple levels (in an extremely hot

environment)

repeatedly;

and IO) a substantive

crosscutting

issue is currently

open related to

personnel

failing to follow procedural guidance

reflective

of a trend related to poor work

practices.

Additionally, the ability

to black start an EDG was reviewed by the NRC. The

NRC concluded

that because of

the many uncertainties

and associated variables that credit

for this mitigation

strategy was not readily

quantifiable.

After review of

the particular

procedures, activities, and conditions under which these

actions would be taken, none of these strategies were considered

to appreciably

affect the risk significance

of the finding. Nevertheless, in a qualitative

sense, they would improve

the chances for avoiding core

damage. The NRC determined the success

of using these alternative mitigation

strategies

were comparable

to the additional risk

due to external events.

Based on this qualitative

assessment

these alternative mitigation strategies were considered

offset by the risk contribution

of the external events. Large Early Release Frequency:

In accordance with Manual Chapter 0609, Appendix

A, Attachment

1, Step 2.6, "Screening

for the Potential Risk

Contribution

Due to LERF," the NRC reviewed the core damage

sequences

to determine an

estimate of the change in

large early release frequency caused by

the finding. The LERF consequences of this performance

deficiency

were similar to those documented

in a previous SDP Phase 3 evaluation regarding a misalignment

of gland seal water to the service water pumps.

The final determination

letter was issued on March 31 , 2005, and is located in ADAMS, Accession No. ML050910127.

The following excerpt from

this document addressed

the LERF issue: "The NRC reevaluated

the portions of the preliminary significance

determination

related to the change in LERF. In the regulatory

conference, the licensee

argued that the dominant sequences

were not contributors to

the LERF. Therefore, there

was no change in LERF resulting

from the subject performance

deficiency. Their argument

was based on the longer than usual core damage sequences, providing

for additional

time to core damage, and the relatively short time estimated

to evacuate the close

in population surrounding

Cooper Nuclear Station. LERF is defined in NRC Inspection

Manual Chapter 0609, Appendix

H, "Containment

Integrity Significance Determination Process" as: "the frequency

of those accidents

leading to significant, unmitigated release from containment

in a time frame prior to the effective

evacuation of the close-in population such

that there is a potential for

early health effect." The NRC noted

that the dominant

core damage sequences documented

in the -7- Enclosure 3

preliminary significance

determination

were long sequences

that took greater than

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to proceed to reactor

pressure vessel breach. The shortest calculated interval

from the time reactor conditions

would have met the requirements for entry

into a general emergency (requiring the evacuation)

until the time of postulated containment

rupture was 3.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. The licensee stated that the average evacuation time

for Cooper, from the

declaration

of a General Emergency

was 62 minutes. The NRC determined

that, based on a 62-minute average evacuation time, effective

evacuation

of the close-in population

could be achieved within 3.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. Therefore, the dominant core damage sequences

affected by the subject performance

deficiency

were not LERF contributors. As such, the

NRC's best estimate determination

of the change in LERF resulting from the performance

deficiency was zero."

In the current analysis, the total

contribution

of the 30-minute sequences

to the current case

CDF is only 0.17% of the total. For 2-hour sequences, the contribution

is only 0.04%. That

is, almost all of the risk associated with this

performance

deficiency

involves sequences

of duration 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> or longer following the

loss of all ac power. Based on the average 62-minute evacuation

time as documented above, the NRC determined that large

early release did not contribute

to the significance

of the current finding.

References

NUREG/CR-6890, "Reevaluation

of Station Blackout Risk

at Nuclear Power Plants, Analysis of

Loss of Offsite Power Events: 1986-2004" "Incremental Change

in Core Damage

Probability Resulting from Degraded Voltage Regulator

Diode Installed in the Division

2 Diesel Generator," PSA-ES083, Revision

0 NUREG/CR-6883, "SPAR-H Human

Reliability

Analysis Method" Peer Review John Kramer, NRR See-Meng Wong, NRR Jeff Circle, NRR David Loveless, RIV

-8- Enclosure

3

Enclosure

4 Number Description

0 Original Issue

PROBABILISTIC

SAFETY ASSESSMENT

COOPER NUCLEAR STATION ENGINEERING

STUDY Reviewed Approved BY Date BY Date See Above

See Above Incremental

Change in Core Damage Probability

Resulting

from Degraded Voltage Regulator Diode Installed

in the Division

2 Diesel Generator

PSA-ES082

Revision 0 Prepared By: Reviewed By: Approval:

Risk Management Engineer

$isk Management

Engineer Risk Management

Supervisor

Revisions:

PROBABILISTIC

SAFETY ASSESSMENT COOPER NUCLEAR

STATION ENGINEERING STUDY

Number Description Incremental Change in Core Damage Probability Resulting from Degraded Voltage Regulator Diode Installed

in the Division

2 Diesel Generator

Reviewed Approved BY Date BY Date PSA-ES082

Revision 0 0 S ignature/Date

See Original for Signatures

Original Issue See Above See Above Prepared By: Ole Olson 7/27/2007

Reviewed By: Risk Management Engineer John Branch

7/27/2007

Approval: Risk Management Engineer

Kent Sutton 7/27/2007 Risk Management Supervisor

Revisions:

Incremental

Change in Core Damage Probability

Resulting from Degraded

Voltage Regulator

Diode Installed in the

Division 2 Diesel Generator

TABLE OF CONTENTS EXECUTIVE SUMMARY

.........................................................................................................................................

2 NOMENCLATURE

......................

......................................................

DEFINITIONS

...................................................................................................................................

7 I .2.1 1.2.2 Discussion of the

AC Electrical Power System

at CNS .................................................................. Defective Diode's Impact on Normal Operation

2.0 EVALUATION

....................................................................................................................................................

10 ............

IO 2.1.1 ASSUMPTIONS

AND CHARACTERISTICS OF THE MODEL

...........................................................

10 2.1.2 DERIVATION OF ICCDP ...............................................................

13 2.1.2.1 Base CDF Quantification 13

2,1.3 RISK SIGNIFICANCE CONCLUSIONS WITH

RESPECT TO ICCDP ................................................

16 2.1 SPECIFIC INCREASE

IN RISK RESULTING FROM

THE DEFECTIVE

DIODE 2.1.2.2 Conditional

CDF Quantification

................................................................................................................

15 2.2 RISK INSIGHTS FROM BOUNDING ANALYSIS

2.2.2 ICCDP SENSITIVITY

IN 2.2.3 BOUNDING ANALYSIS 2.3 LARGE EARLY RELEASE F

...............................................................................

20 2.4 EXTERNAL EVENT EVALUATION

..................... 2.4.1 Intcrnal Fire

3.0 CONCLUSION

................................................................................................

4.0 REFERENCES

.............................................................

22 Appendix A Station Blackout Event Tree Adjustinelits

Appendix B Human Reliability

Analysis Appendix C Data Analysis for Defective Diode Installed in Voltage Regulator Card

Appendix D DG2 Voltage Control Board Diode Failure

FIRE-LOOP

Evaluation

Appendix E Time Weighted LOOP Recoveries for SBO Sequences

Page 1 of 23

Incremental

Change in Core Damage Probability Resulting

from Degraded Voltage Regulator Diode

Installed

in the Division

2 Diesel Generator

Change in CDF resulting

from Defective Diode

Duration of Full Power ODerations with Defective

Diode EXECUTIVE

SUMMARY 8.806E-08Nr 56 Davs A focused probabilistic Risk assessment (PRA) based

on the Cooper Nuclear

Station PRA model and the CNS SPAR model has been performed to evaluate the safety significance

of a January

18, 2007, run failure of the division 2 emergency diesel generator (DG-GEN-DG2). This

assessment

concluded

that the increased risk can be characterized as veiy low

in significance

in term of incremental change

in core damage probability resulting

from at power internal and

exteimal events. The run failure of DG-GEN-DG2 was the result of a diesel generator trip from

an over voltage

condition

that occuil-ed during routine surveillance testing.

The failure occurred approximately

4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> into the suiveillance

run with the diesel generator synchronized

to the grid.

Investigation

found the over voltage condition was caused by an open circuit failure

of a diode on the voltage regulator

card for DG-GEN-DG2.

The voltage regulator card was

installed

in DG-GEN-DG2

during refLieling

outage RE23 on November 8, 2006. Dissection

of the diode

at a laboratory

found that the open circuit was caused by a poor electrical connection inside the diode package. Cross sectioning

of the failed diode

showed that connections between the die and the heat sinks

were at best marginal and

that these marginal connections

were the result

of a manufacturing defect. This manufacturing defect manifested itself

as a random and intermittent

open circuit failure of the diode.

This assessment evaluates safety significance of this manufacturing defect

in tenns of incremental

change in core damage probability (ICCDP). The ICCDP reflects the

overall change in risk resulting froin at power operations

of Cooper Nuclear Station (CNS) while

the defective

voltage regulator

diode was installed

in DG-GEN-DG2.

The resulting ICCDP, computed

with the CNS PRA model of record is 1.35

1 E-08 and is summarized

in the following table.

ICCDP Derivation

Base CDF for CNS Full Power Oueration

I 1.359E-OYYr

I Bounding Conditional CDF resulting

froin Defective Diode

I 1.3678E-OYYr

I ICCDP Resulting from

Defective

Diode I 1.351E-08

The risk significance

of the condition is characterized as very low significance.

This is based on the fact that the ICCDP is below an established threshold

of safety significance

set at 1.OE-06. This risk significance threshold is

used in various PSA applications including the Nuclear Regulatory Commission Significance Determination Process, and the Maintenance Rule

Configuration Risk Assessments

(1 O.CFR50.65(a)(4)).

An additional

bounding ICCDP evaluation

was also perfonned.

This evaluation

also characterized

risk as very low in significance with an ICCDP that was less than

1.OE-06. It was performed using the CNS SPAR model.

It is important

to note that incremental change

to Large Early Release

Probability

is negligible

and less than

1.OE-07 based on the fact that ICCDP is less Page 2 of 23

Incremental Change in Core Damage Probability Resulting from Degraded Voltage Regulator Diode Installed

in the Division

2 Diesel Generator

than 1 .OE-07. However, a qualitative evaluation of LERF impact was provided. This qualitative evaluation found that change

in LEW was negligible.

The DG2 over voltage trip also resulted in

very low risk change

in teiins of large early release

frequency (LEW), and core damage probability resulting

from extei-nal

events. Both the change in LEW and core damage probability resulting from external events is characterized

as very low in safety significance.

Page 3 of 23

Incremental

Change in Core Damage Probability

Resulting from Degraded

Voltage Regulator Diode

Installed

in the Division

2 Diesel Generator

NOMENCLATURE

CDF Core Damage Frequency

CNS Cooper Nuclear Station

ICCDP ICLERP Incremental

Change in Core Damage Probability

Incremental

Change in Large Early Release Probability

DG DG -GEN-DG 2 DIV I DIV I1 HEP HPCI IPE LERF LOOP LOSP NRC PDS PRA PSA RPV SDP Diesel Generator

Division 2 Emergency Diesel Generator Division I

Division I1 Human Error Probability High Pressure Coolant Injection

Individual

Plant Examination

Large Early Release Frequency

Loss of Offsite Power

Loss of Offsite Power United States Nuclear Regulatory Coininission

Plant Damage State

Probabilistic

Risk Analysis Probabilistic Safety Assessment Reactor Pressure Vessel Significance Determination Process

Page 4 of 23

Incremental

Change in Core Damage Probability Resulting from Degraded Voltage

Regulator Diode Installed

in the Division

2 Diesel Generator

DEFINITIONS

Accident sequence - a representation in teims of an initiating

event followed by a combination

of system, fiinction

and operator failures

or successes, of an accident that can lead to undesired consequences, with a specified

end state (e.g., core damage

or large early release). An accident

sequence may contain many unique variations

of events (minimal

cut sets) that are similar.

Core damage - uncovery and heat-up of

the reactor core

to the point at which prolonged oxidation and

severe file1 damage is anticipated

and involving enough of

the core to cause a significant release.

Core damage frequency - expected number

of core damage events

per unit of time. Cutsets - Accident sequence failure combinations.

EizdStnte - is the set

of conditions at

the end of an event sequence

that characterizes

the impact of the sequence on the plant

or the environment. End

states typically include: success states, core damage sequences, plant damage states for Level

1 sequences, and release categories

for Level 2 sequences. Event tree - a quantifiable, logical network that begins

with an initiating event

or condition

and progresses through a series

of branches that represent expected system

or operator performance

that either succeeds

or fails and arrives at either a successfiil

or failed end state. Initintiizg

Event - An initiating event is

any event that

pei-turbs the steady state operation of the plant, if operating, or the steady state operation

of the decay heat

removal systems during shutdown operations

such that a transient is initiated in the plant. Initiating events trigger

sequences

of events that challenge the plant control

and safety systems.

Large early release - the rapid, unmitigated release

of airborne fission products from the containment

to the environment occurring before

the effective implementation

of off-site emergency response and protective actions.

Lnrge early release

frequency - expected number

of large early releases per unit

of time. Level I - identification

and quantification

of the sequences

of events leading to the onset of core damage. Level 2 - evaluation

of Containment

response to severe accident challenges and quantification

of the mechanisms, amounts, and probabilities

of subsequent radioactive material releases from

the containment.

Plant daiiznge state - Plant damage states are collections

of accident sequence

end states according

to plant conditions at the onset of severe core damage. The plant conditions considered are those

that determine

the capability of the Containment

to cope with a severe core damage

Page 5 of 23

Incremental

Change in Core Damage Probability Resulting

from Degraded Voltage

Regulator

Diode Installed

in the Division

2 Diesel Generator

accident.

The plant damage states represent the interface

between the Level

1 and Level

2 analyses.

Probability - is a numerical measure

of a state of knowledge, a degree

of belief, or a state of confidence

about the outcome of

an event. Probabilistic risk

assessiizeizt - a qualitative

and quantitative assessment

of the risk associated

with plant operation

and maintenance that is measured in tenns of frequency

of occurrence

of risk metrics, such

as core damage or a radioactive inaterial release and its effects on the

health of the public (also referred to

as a probabilistic safety assessment, PSA).

Release category - radiological source

tenn for a given accident sequence that consists

of the release fractions for various radionuclide

groups (presented

as fractions

of initial core inventory), and the timing, elevation, and energy of release. The factors addressed

in the definition of the release categories include

the response of the containment structure, timing, and mode

of containment failure; timing, magnitude, and mix of any releases

of radioactive inaterial;

thermal energy of release; and key factors affecting deposition and filtration

of radionuclides. Release categories can

be considered

the end states of the Level

2 portion of a PSA. Risk - encompasses what

can happen (scenario), its likelihood (probability), and its level

of damage (consequences).

Severe accident - an accident that involves extensive core

damage and fission product

release into the reactor vessel and containment, with potential

release to the environment.

Vessel Breach - a failure of the reactor vessel

occurring

during core melt (e.g., at a penetration or

due to thermal attack of the vessel bottom

head or wall by molten core debris). Page 6 of 23

Incremental

Change in Core Damage Probability Resulting from Degraded Voltage Regulator Diode Installed

in the Division 2 Diesel Generator

1.0 INTRODUCTION On Januaiy

18,2007, DG-GEN-DG2 tripped

after running for approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> during a

surveillance

test. The trip resulted from an over voltage condition. The over

voltage condition

resulted from an open circuit failure

of a defective diode contained on

the voltage regulator

card for DG-GEN-DG2.

1.1 PURPOSE In order to assist

in a significance determination of the DG-GEN-DG2

trip, a risk assessment

is provided herein.

The card with the defective diode

was installed on November

8, 2006 during

refuel outage, RE23. Cooper Nuclear Station resumed full

power operations

from RE23 on November 23, 2006. Based on

this timeline, this risk assessment evaluates

this condition for

an exposure time of 56 days. This risk assessment predicts

the incremental change

in core damage probability (ICCDP)

and relates the significance

of the risk increase using industry established

ICCDP thresholds.

The risk assessment also evaluates impacts to the baseline Large Early Release Frequency (LERF) as well as core damage probabilities attributed to external events.

1.2 BACKGROUND

1.2.1 The station electrical power systems provide a

diversity

of dependable power sources which are physically isolated.

The station electrical power systems consist of the normal and startup

AC power source, the emergency

AC power source, the 4160 volt

and 480 volt auxiliaiy

power distribution systems, standby

AC power source, 125 and 250 volt DC power systems, 24 volt DC power system, 115/230 volt

AC no break power system, and the 120/240

volt AC critical power

system. Discussion

of the AC Electrical Power System

at CNS Figure 1.1 illustrates the power supplies and

distribution

for the station loads at the 41 60 volt AC bus level. The noi-mal AC power source provides

AC power to all station auxiliaries and is

the normal AC power source

when the main generator is operating.

The startup AC power source provides

AC power to all station auxiliaries and is noiinally in use when the noma1 AC power source

is unavailable.

The emergency

AC power source provides AC power to emergency station auxiliaries.

It is normally used to supply emergency station

auxiliary loads when the main generator is shutdown and the startup AC power source

is unavailable.

The station 4160

volt and 480 volt auxiliaiy

power distribution systems distribute

all AC power necessary

for startup, operation, or shutdown of station loads.

All poi-tions

of this distribution system receive

AC power from the normal AC power source or the startup AC power source. The critical service portions

of this distribution system

also can receive

AC power from

the standby AC power source or the emergency

AC power source.

Page 7 of 23

Incremental

Change in Core Damage

Probability Resulting from Degraded Voltage Regulator Diode

Installed

in the Division

2 Diesel Generator

The standby AC power source provides

two independent

41 60 volt DGs as the on-site sources of

AC power to the critical service portions

of the auxiliary

power systems. Each DG provides AC power to safely shutdown the reactor, maintain the safe shutdown condition, and operate all

auxiliaries

necessary for station safety.

The above power sources are integrated

into the following protection

scheme to insure that the CNS emergency loads will

be supplied at all times.

If the normal station service transformer (powered

by the main generator) is lost, the startup station service transformer, which is normally energized, will automatically energize

4 160 volt buses 1A and 1B as well as their connected loads, including the critical buses. If the

stamp station service transformer fails

to energize the critical buses, the emergency station service transformer, which is normally energized, will automatically energize both

critical buses. If the emergency station service

transformer

were also to fail, the DGs would automatically energize

their respective buses. The defective diode

was installed

in the voltage regulator

for 56 days while CNS was at power. The voltage regulator card was part of the excitation control for

DG-GEN-DG2 (illustrated as

diesel generator

  1. 2 in Figure 1.1). All other power sources available

to the 41 60 Volt AC buses remained available and unaffected by the defective diode.

Page 8 of 23

Incremental Change

in Core Damage Probability Resulting

from Degraded Voltage Regulator

Diode Installed

in the Division

2 Diesel Generator

Figure 1.1 Cooper Nuclear Station

Single Line, 4160 Volt Distribution FROM FROM MAIN GENERATOR

345 KV1161 KV GRID v v STATION SERVICE STATION SERVICE TRANSFORMER

TRANSFORMER

EMERGENCY

TRANSFORMER

STATION SERVICE 4160v'69 Kv s" BE:; ) DIESEL GENERATOR

  1. 2 0 f 6 DIESEL GENERATOR
  1. 1 0.PS'S. LINE Page 9 of 23

Incremental

Change in Core Damage Probability Resulting from Degraded Voltage Regulator Diode

Installed

in the Division

2 Diesel Generator

1.2.2 During nonnal operations the DG-GEN-DG2 is not

required to provide power

to support plant loads. DG-GEN- DG2 is tested during nonnal operations and electrical

load is supplied through synchronization

of DG2 to the offsite power grid. Protective relaying

is provided to prevent iinpact

to noma1 operations should DG-GEN-DG2 encounter electrical failures while being tested.

These protective devices remained fully operation while

the defective

diode was installed.

Thus, installation

of the defective diode had

no impact on nonnal plant operations and resulted

in negligible increase

in the frequency

of occurrence

of plant events. Defective Diode's Impact

on Normal Operation

1.2.3 During a plant emergency, which includes the inability

to provide power

to the 4160 Volt AC buses with offsite power, DG-GEN-DG2

is the remaining power

source for 4160 critical bus 1G. Defective Diode's Impact

on Emergency Operation The defective diode installed in

DG-GEN-DG2

affected the ability of

the generator's excitation controls

to regulate voltage. The defective diode's open circuit

failure inode resulted in an over voltage

condition

which tripped DG-GEN-DG2 rendering

it incapable

of providing power

to 4160 Volt AC bus 1G in the automatic

voltage control mode. It should also be noted that the defective diode is a subcomponent

of the automatic

voltage regulating portion

of DG-GEN-DG2. DG-GEN-DG2 would

be fully recoverable

when started and loaded to bus 1 G using the

inanual voltage regulating controls provided locally in

the diesel generator room.

2.0 EVALUATION This section

evaluates

the specific increase

in risk resulting

fioin the defective diode found

in DG-GEN-DG2

and documents

other bounding analysis coinpleted

to provide key insights into

the overall risk significance of the defective

diode. Section 2.1 evaluates

the incremental increase

in core dainage probability that results from the

risk increase caused by the defective diode installed in the

voltage regulator card. This section provides the

specific conclusions of overall risk

impact. Section 2.2 provides bounding analysis

to fiirther substantiate the conclusions provided

in section 2.1.

Sections 2.3 and 2.4 discuss exteinal events

and large early release frequency changes

that resulted froin the

defective

diode. 2.1 SPECIFIC INCREASE IN RISK RESULTING

FROM THE DEFECTIVE

DIODE 2.1.1 ASSUMPTIONS

AND CHARACTERISTICS OF THE MODEL

1 ) The CNS 2006TM PRA inodel and the

NRC CNS SPAR inodel (Revision

3.31, dated October

IO, 2006) werc applicable for use in this evaluation. Page 10 of

23

Incremental

Change in Core Damage Probability Resulting from

Degraded Voltage Regulator Diode

Installed

in the Division

2 Diesel Generator

Quantification was truncated at

1 .OE-12 to ensure results

captured all relative combinations

in the PRA sequences.

The condition evaluated

is limited to the time in which the defective

diode was installed during at power

conditions.

This was approximated

as the time in which reactor power

was above turbine bypass valve

capacity and correlates

to the period starting

November 23,2006 to January 18,2007. The exposure period for the condition is 56

days. Fire water injection

for the purposes

of reactor inventory makeup and cooling is

not credited in

this evaluation.

It should be noted, however, that this injection source

is viable and available for

mitigation

of SBO sequences. The use of the diesel driven fire protection pump

has been identified

as a mitigation

system during several

emergency

drills by the Emergency Response Organization.

The system provides

WV injection through one of three possible hose connections to the RHR system. The procedure

(5.3ALT-STRATEGY)

and equipment needed

to accomplish RPV injection using the

fire protection

pump are in place. The ability to black start DG-GEN-DG1

or DG2 was not credited in this

study. Procedures are

in place at CNS (5.3 ALT-STRATEGY) that direct the "black start"

of a diesel generator.

This means a DG can be started and tied to the critical AC bus after the station batteries are depleted. The diesel generator "fail

to run" failure rate

and probability contained

in the CNS SPAR model

of record (Reference

3) will be used for

this evaluation

to allow a more direct comparison between CNS

PRA results and the CNS SPAR Model

results. This failure probability

is defined as 2.07E-02 in the SPAR model.

Both the CNS PRA Model and

SPAR Model event trees for station blackout

will use the actual battery

depletion

times documented

in CNS PRA internal events analysis. Refer

to Appendix A

for details on

these depletion

times. The failure

rate for the defective diode was derived

per the guidance

of NUREG CR6823 (Reference

4). This derivation included Bayesian estimation through application

of a constrained noninformative prior

to best represent failure rates given

the existing diesel generator failure data available

in the PRA models and the small amount

of nm time experienced

by the defective diode.

See Appendix C for derivation

of the defective diode failure rates.

Further sensitivity analysis was provided

to ensure that bounding diode failure

rates using other statistical approaches result in negligible

risk increase (refer to Section

2.2.2). Actual failures of the defective diode while installed

in the excitation

control circuit for DG-GEN-DG2

has been deteiinined

to be 1 (one) for

the purposes of failure rate derivations. Evaluation of

perfoiinance leading to the over voltage trip

of DG-GEN-DG2 on January 18, 2007

and subsequent

root cause lab

testing found that there were two

other instances that could be attributed

to the open circuit failure condition of the defective diode. However both

of these instances

were dismissed

as fo 11 ow s : During post

maintenance testing of DG-GEN-DG2 on November 1

1, 2006, an over voltage condition was

noted while tuning the control

circuit that contained the defective diode. Because

this testing did not provide conclusive evidence that the diode was

the cause of the over voltage condition

and because DG- Page 11 of 23

Incremental Change

in Core Damage Probability Resulting from Degraded Voltage

Regulator

Diode Installed

in the Division

2 Diesel Generator GEN-DG2 demonstrated over

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of successful

i-un time after occurrence

of the November

1 1, 2006 condition, this instance is dismissed

as a attributable failure

of the defective diode. A post failure

test of the circuit card that included the defective diode resulted

in both satisfactory card operation followed

by unsatisfactory

card operation

with subsequent determination that the defective diode was

in a permanent

open circuit state. This lab testing failure

has been dismissed in this shidy due to the large amounts

of variability introduced

by shipping of the card to the lab, the

differences

between lab bench top testing

and actual installed conditions, and equipment and human errors that could be

attributed

to test techniques. Section 2.2 provides analysis

to address sensitivity

in the assumption

of number of actual diode failures. Expected operator actions that would be taken to recover from the over voltage trip that was experienced

on January 18, 2007 include a successful restart of DG-GEN-DG2 and loading

of the generator

using the manual voltage controls provided

locally in the diesel generator room.

The diagnosis and performance

of this recovery has been determined

to have a non-recovery probability

of 3.OE-02. The detailed evaluation

for this human

reliability analysis is included

in Appendix B. The CNS Level 1 and Level 2 PRA Model was developed based on plant specific fiinctions and

system success criteria

for each of the important

safety functions and support systems relied

upon for accident

prevention

or mitigation

for the duration of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> following

an event. The systems included in the model were those that supported

the overall objective

of maintaining adequate core and containment cooling. There

are two figures-of-merit

for meeting these objectives:

core damage frequency

and large early release frequency. The definitions used

in this study are consistent

with the CNS PRA. For the purposes

of this study, the mission

time for the DG iun was assumed to be 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. To compensate

for this overly conservative assumption, the

sensitivity study in Section 2.2.2 includes

sequence dependent time-weighted offsite power non-recoveiy probabilities.

The derivation

of these non-recovery

probabilities is discussed

in Appendix E. The Diesel Generator

failure-to-run

events are treated in the CNS PRA with a lumped parameter approximation. All

i-un failures are treated

as failures occurring

at accident initiation (t=O). This treatment

results in not accounting for diesel offsite power

recoveiy at extended

times associated

with these failure modes

even though adequate

AC power is available

during the initial diesel run. To ininiinize the conservative impact

of this lumped parameter assumption in the regular CNS PRA model (as

opposed to the model used

for this analysis), a

iyin time of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> is used in establishing

nin failure probability. This

is based on the following: The

DG mission time accounts for two competing effects.

The first is the running failure rate of the

DG and the second is

the recovery of offsite or on-site AC power. All cutsets with a DG fail to i-un event must also include

an offsite or on-site AC power non-recovery event. The

time dependent product

of these two events is maximized

at about 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> into the accident.

The offsite power non-recoveiy probability is dominated

by weather related events beyond

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> into the accident. The

initiating

frequencies

used in this shidy include costal effects such as sea spray

and hurricanes.

Due to the location of

CNS, inclusion of these events results

is overly conservative when included in

non- recoveiy probabilities.

The exclusion of these events from the LOOP non-recovery

probabilities

is appropriate; however, the events are included in the LOOP frequency.

Page 12 of 23

Incremental

Change in Core Damage

Probability Resulting from Degraded

Voltage Regulator

Diode Installed

in the Division 2 Diesel Generator

Base CDF Conditional

CDF Resulting

from the Defective

Diode 1.359E-O5/Yr 1.3678E-O5/Yr 2.1.2 DERIVATION

OF ICCDP Derivation

of ICCDP resulting

from the over voltage trip

of DG-DEN-DG2 that occurred on January

18,2007 provides the following results.

Change in CDF Exposure (days)

Incremental

Change in Core Damage Probability

8.806E-08Nr 56 1.35 1 E-08 2.1.2.1 Base

CDF Quantification

Base CDF was derived

by quantification

of the CNS PRA model of record with the following adjustments

to best fit this application.

1. The diesel generator fail

to run basic event probabilities

were changed to reflect those in the SPAR model. Specifically, basic events EAC-DGN-FR-DG1

and EAC-DGN-FR-DG2 probabilities

were changed from

1.45E-03 to 2.07E-02.

This was done to allow a better comparison between SPAR

results and CNS PRA model results. This

also changed the

DG mission times to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> as opposed to the 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> that is noiinally used

in the CNS PRA model. 2. Loss of offsite power frequencies and recoveries

were revised to best reflect current industry performance data. NUREG CR 6890 (Reference 2) was used

to derive these

new values. These values are reflected

in Table 2.1.2-1. This table also details the

10 and 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> DG recoveries

required to support the event tree adjustments

made in Appendix A. All DG recoveries were

obtained using the existing

CNS PRA model basis documents. (Reference

6). 3. The SBO portions of the event trees were revised to better

reflect the SPAR SBO structure.

The SBO portion of the event trees

were also revised to extend recovery times. This accurately models actual battery depletion times

that are in excess of those currently modeled.

Refer to Appendix A

for further discussions

on the event tree revisions.

Page 13 of 23

lncrernental

Change in Core Damage Probability Resulting from Degraded Voltage Regulator

Diode Installed

in the Division 2 Diesel Generator %TI G-INIT

I Grid Centered Loss Of Offsite Power Table 2.1.2- 1

Loss of Offsite Power Frequency

and Non-recoveiy Updates

7.18E-03 %T 1 P-INIT YoT 1 W-INIT I Plant Centered Loss Of Offsite Power

I Weather Centered Loss Of Offsite Power

1.3 1 E-02 4.83E-03 I NR-DG-IOHR

I Non-Recoverv Of DG Within

10 Hours I 2.60E-01 I NR-LOSP-G

1 OHR NR-LOSP-GI

2HR I Conditional Non-Recovery Grid Centered Off-Site Power

In 10hr I Conditional Non-Recovery Grid Centered Off-Site Power

In 1211r 3.64E-02 2.42E-02 NR-LOSP-G

1 HR NR-LOSP-G24HR

NR-LOSP-G6HR

NR-LOSP-GgHR

NR-LOSP-PI

OHR Non-Recovery

Of Grid-Centered LOSP Within

1 Hr Conditional Non-Recovery Of Grid Centered Off-Site Power

In 24 Hrs Conditional Non-Recovery Of

Grid Centered Off-Site Power In

6 Hrs Conditional Non-Recovery Of Grid Centered Off-Site Power In

8 Hr 3.73E-0 1 4.15E-03 9.76E-02 5.73 E-02 Conditional Non-Recoverv Plant Centered Off-Site Power In

1 Olir 2.48E-02 NR-LOSP-P 12HR

NR-LOSP-P

1 HR NR-LOSP-P24HR

NR-LOSP-P6HR

NR-LOSP-P8HR

NR-LOSP-W

1 OHR I NR-LOSP-W 12HR Conditional Non-Recovery Plant Centered Off-Site Power In 1211r Non-Recovery Of Plant-Centered LOSP Within

1 Hr Conditional Non-Recovery Of

Plant Centered Off-Site

Power In 24 Hrs Conditional Non-Recovery Of Plant Centered Off-Site

Power In 6 Hrs Conditional Non-Recovery

Of Plant Centered Off-Site Power

In 8 Hr Conditional

Non-Recovery

Weather Off-Site Power

In I Ohr 1.71E-02 1.18E-01 . 3.49E-03 6.42E-02 3.83E-02 2.89E-01 Conditional

Non-Recovei-v Weather Off-Site Power

In 1211r 2.5 5 E-0 1 Page 14 of 23 NR-LOSP-W

1 HR NR-LOSP-W24HR

NR-LOSP-W6HR NR-LOSP-W 8HR

Non-Recovery Of Weather-Related LOSP Within

1 Hr Conditional Non-Recovery Of Weather Centered Off-Site Power In 24 Hrs Conditional Non-Recovery Of Weather Centered Off-Site

Power In 6 Hrs Conditional Non-Recovery Of

Weather Off-Site Power

In 8 Hr 6.568-01 1.48E-0 1 3.97E-01 3.34E-01

Incremental Change

in Core Damage Probability Resulting

from Degraded Voltage Regulator

Diode Installed

in the Division 2 Diesel Generator

2.1.2.2 Conditional CDF Quantification

Conditional

CDF was also quantified using

the CNS model of record with the adjustments

detailed for the base CDF. The defective diode was modeled as

a new and separate event placed in the diesel generator fault

tree as an input to gate

EAC-DG2-007, "Diesel Generator DG2 Failures".

The original DG2 fail-to-nin event EAC-DGN-

FR-DG2 was also retained in

the tree. The defective diode probability

was set at 5.70E-02 (see Appendix

C) and adjusted to reflect a non-recovery probability

of 0.03 (see Appendix B). The following represents the addition of

defective

diode modeling.

I , .. I I I I I U, I P Page 15 of 23

Incremental Change

in Core Damage Probability Resulting

from Degraded Voltage Regulator

Diode Installed in the Division

2 Diesel Generator

2.1.3 The exposure of DG-GEN-DG2

to the failure

mode presented

by the defective diode found

in the voltage regulator card resulted

in quantifiable increases

in risk. Increase

was quantified as an incremental change

in core damage probability

of 1.351E-08. This is

judged as not risk significant and well below the risk significance ICCDP threshold

of 1.OE-6 set for PRA applications.

RISK SIGNIFICANCE

CONCLUSIONS

WITH RESPECT TO ICCDP The low significance

is a result of a small exposure

time (56 days), Cooper Nuclear Station design features that provide redundancy

to DG-GEN-DG2, and the ability to recover from the diode's

open circuit failure

mode. 2.2 RISK INSIGHTS FROM BOUNDING ANALYSIS

The assumptions made for this risk change application were chosen

to most accurately reflect

conditions

that existed at the time

of the over voltage trip of DG-GEN-DG2 on January

18, 2007. Review of the assumptions found the following are key contributors in the overall

derivation

of ICCDP: 1. The non-recoveiy

probability

derived in Appendix B 2. The defective diode failure probability estimated in

Appendix C 3, The statistical methodology used

to determine the diode failure probability This section performs

bounding analysis using both

SPAR and the CNS PRA models to provide insight with

respect to the sensitivity

of the diode non-recovery

and failure probabilities.

2.2.1 ICCDP SENSITIVITY

IN RELATION TO NON-RECOVERY AND DIODE FAILURE

RATE Tables 2.2.1-1 and 2.2.1-2, as well as Figure 2.2.1-1, represent the sensitivity

of ICCDP in relation

to both non-recoveiy probabilities

and diode failure probabilities. Diode failure probabilities

are varied to detail how

the assumed number of failures experienced while

the defective

diode was installed affects overall ICCDP. Non-recovery probabilities

are increinented

in steps of 0.5 to provide relative sensitivity insights. The ICCDP values were derived

using the same methods outlined

in Section 2.1 above.

The SPAR model of reference was used including

the adjustments detailed in

Appendix A. Page 16 of 23

!9 U-I Y 8 u-) Y

> E a, E: 5 .3 ti; a, M E: CQ .c u 2 u I 3 I 3 cd C a, a, L 0 Y 2 5 E M .3 ,. C Y Lo W 0 4 9 T- co 4 F d0331 s x T- o 0 M N Ccl 0 00 i c4

Incremental Change

in Core Damage Probability

Resulting from Degraded

Voltage Regulator

Diode Installed in

the Division 2 Diesel Generator

2.2.2 A bounding ICCDP

was also derived using a conservative

statistical

approach in which a inaxiinuin likelihood estimation was applied

This bounding analysis assumed

two failures of the defective diode

occurred in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> of nin time. The inaxiinin likelihood estimation (MLE) allows the diode failure probability

to be calculated

directly through use of

Poisson as follows: ICCDP SENSITIVITY IN RELATIONS TO STATISTICAL METHOD ( 1 -Exp(-A,,w

  • 24)), or (1 -Exp(-(2/36)

"24)) = 0.736 This diode failure probability increases the'actual

ICCDP derived in section 2.1 by a factor of

8.5. This increase approaches the risk significance threshold

of 1 .OE-06. Further evaluation

found it prudent to adjust ICCDP

to account for the conservatisin resulting

in the assumption that all diesel generator

run failures occur at

the start of station blackout events. This adjustment is similar to

application

of the convolution integral

and is detailed in Appendix E. Results of application of

Appendix E, specifically

Tables 5.1 through 5.3, results are

as follows: Table 2.2.2-1 Diode Failure Probability

as a Function

of DG Non-Recovery

Probability

Number of diode failures

in 36 hour4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />s>>> Diode Failure Probability (24

how mission)>>>

2 failures (CNS MODEL w/ MLE and Time Weighted NR-LOSP) 0.736402862

DG Non-Recovery

Probability

+ 0.03 ICCDP + 1.01345E-07

0.05 0.1 0.15 1.68909E-07

3.378 17E-07 5.06726E-07

0.2 0.25 0.3 0.35 0.4 1 2.2.3 BOUNDING ANALYSIS CONCLUSIONS Sensitivity results support

the overall conclusion

that the ICCDP risk increase resulting froin the

installation

of the defective diode

is below the threshold of risk significance.

This is supported

by both the SPAR and CNS PRA models. 6.75634E-07

8.44543E-07

1.01345E-06

1.18236E-06

1.35127E-06

3.37817E-06

Semi tivity results detail that the extremes

of both the diode failure probabilities

and non-recovery probabilities would have

to be applied

to push the ICCDP above the

risk significance threshold

of Page 19 of 23

Incremental

Change in Core Damage Probability

Resulting from Degraded Voltage Regulator

Diode Installed

in the Division 2 Diesel Generator

1 .OE-06. These extremes, though insightful, are

judged not to be viable or representative

of the actual conditions that existed at

the time of the over voltage trip of DG-GEN-DG2.

2.3 LARGE EARLY RELEASE FREQUENCY

ANALYSIS It is important to note that incremental change

to Large Early Release Probability is negligible and less than

1.OE-07 based on the fact that

ICCDP is less than 1.OE-07. However, a qualitative

evaluation

of LERF impact was provided. This qualitative evaluation found

that change in LERF was negligible.

The qualitative evaluation is provided below.

The LERF consequences of

exposure to the defective diode were similar

to those documented

in a previous

SDP Phase 3 evaluation regarding a inisalignment

of gland seal water to

the seivice water pumps (Reference

5). The following excerpt

from NRC Special Inspection

Report 2007007 addresses the LERF issue:

The NRC reevaluated the

portions ofthe preliniinary signijicance determination related

to the change in

LERF. In the regulatory conference, the licensee argued that the dominant sequences were not

contribzitors

to the LERF. Therefore, there was no change in

LERF resulting

fi"oni the subject

peiforinance

deficiency.

Their argument was based

on the longer than

ziszial core darnage sequences, providiiigfor additional time

to core damage, and the relatively short

time estimated

to evacuate the close in popzilation

szirrozinding

Cooper Nuclear Station..

LERF is de$tied in NRC Inspection Manual Chapter

0609, Appendix H, "Containnient

Integrity Significance Deterinination Process" as:

"the fiequency ofthose accidents leading

to significant, uninitigated

release,fi.om containnient in

a time fianze prior

to the effective evacuation

ofthe close-in population

szich that there

is apotentialfor early health

effect.

The NRC noted that the

dominant core damage sequences docziniented in

the preliminary signijicance determination were

long seqziences

that tool: greater than I2 hours to proceed to reactor presszire

vessel breach. The shortest

calciilated

internalfioni the time reactor conditions would have ?net the

reqtiirei~ients

for entiy into a genei~al emergency (keqtriring the

evacuation)

until the time ofpostailated containment

ruptaire was 3.5 lioaii~s.

The licensee stated that

the average evacuation

time for CNS, fioni the declaration

of a Genei-a1 Eniergency was 62 nzintites. . The NRC determined that, based on a

62-nzinute average evacuation time, effective evacuation

ofthe close-in poptilation

could be achieved within 3.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. Therefore, the dominant core damage

sequences

afected by the subject

performance

deficiency

were not LERF contributors.

As such, the NRC's best estimate deterinination

ofthe change in LERF resultingfioni

the performance

deficiency

was zero. In the current analysis, tlie totaI

contribution

ofthe 30-ininute

sequences

to the current case CDF is only 0. I 7% ofthe total. For two hour sequences, the contribution

is only 0.04 percent. That is, almost all of the risk associated with this

performance deficiency involves sequences

of diiration,foair

hours 01" longer following

the loss of all ac power. Based on the average

62 niinzite evacuation

time as docziniented

above, the analyst determined that large

eady release did not contribute

to the signijkance

ofthe current ,finding.

This same excerpt is true for

this analysis also.

Page 20 of 23

Incremental Change

in Core Damage Probability Resulting from Degraded Voltage Regulator

Diode Installed

in the Division

2 Diesel Generator 2.4 EXTERNAL

EVENT EVALUATION 2.4.1 Internal Fire

An evaluation of this condition with respect to

fire initiated accidents concluded

that the ICCDP

due to these initiators is

not a significant contributor

to the overall condition ICCDP, and does

not warrant inclusion into the overall quantitative results.

While some postulated

CNS fires can cause a loss of offsite power requiring

the use of the

Diesel Generators, manual recovery

of the offsite power does

not require repair activities and is

relatively

easy. The bulk of the postulated fires do not cause an unintentional LOOP. Rather, they cause abandonment

of the inain control rooin and a procedurally administrated

LOOP. Only two fires can

actually cause an unintentional LOOP. These are a fire

in control rooin board

C or a fire in the control rooin vertical board

F. Multiple hot shorts in either of these locations

can cause the emergency and startup transformer breakers

to open. The breakers to the emergency transformers do

NOT lock out in a manner that prevents recovery

from inside the plant. Recovery froin these events involves pulling the control power fuses

at the breakers and operating

the beakers manually. Considerable procedural guidance

is available

for these actions.

The IPEEE Internal Fire Analysis conservatively estimated that

the probability

of a fire induced LOOP is almost an order of magnitude

lower that the 1E-6 ICCDP cutoff frequency.

2.4.2 External Events

The contribution

to the ICCDP froin external events is considered

to be insignificant.

The NRC in IR07-07 determined

that the risk increase from external events (seismic and flooding)

"did not add significantly

to the risk of the finding".

This was based on a condition that the DG2 ran for 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> before failing and

is a follows:

As a seiisitivioi, datafioin

the RASP External Events Handbook was used to estimate the scope

of the seismic risk

particular

to this finding. The generic median earthquake

acceleration

asstinzed

to catise a loss of offsite power is 0.39. The estiinatedfieqiieiicy ojearthqiialces at

CNS of this magnitude

or greater is 9.828E-5/yr. The generic median

eartlzqiialce

fiequeiicy assumed to cause a loss of the diesel generatoi-s is

3.19, though essential

eqziipment

powered bj} the EDGs would

likely fail at approxiinatelj

2. Og. The seismic informatioiifoi~

CNS is capped at a inagnittrde

of 1.Og with a frequency

of 8.187E-6.

This would suggest that

an earthquake could

be expected to

occw with an approximate

fie qtiency of 9.OE-5/yr-

that would remove offsite

powere but not damage other equipment

iinpoi-taiit to safe shutdown.

In the internal events discussion above, it was estimated

that LOOPS that exceeded

four how-s duration would occur

with a ,fi-equeiicy

of 3.91 E-3/yi-.

Most LOOP events that exceed the

four hour diiration

wozild likely have recovery characteristics closely matching that

fioin an earthquake.

The ratio between these

two fieqiiencies

is 43. Based

on this, the analyst qualitatively

concliided

that the risk associated with seismic

events would be sinall

conipared

to the internal

1-esiilt. Flooding could

be a concei*n because of the proximity

to the Missoziri

River. However-, floods that wotild ieenzove offsite power woiild also IilcelyJlood

the EDG coinpartmerits

Page 21 of 23

Incremental Change in Core Damage Probability Resulting from Degraded Voltage Regulator

Diode Installed

in the Division

2 Diesel Generator

and thei-efore not result

iii a significant change

to the risk associated with the

finding. The switchyard elevation

is below that of the power block by several

feet, but it is not likely that a slight in~indation

of the switchyard

would came a loss of offsite power. The low fieqwency

ofjloods within the

thin slice of water elevations that

would reinove offsite

power, for at least fotir hows, but not render the diesel generators inoperable, indicates

that extei-nal~floodiiig would not

add appreciably

to the risk of this finding. Based on the above, the analyst determined that external events

did not add signijkantly

to the risk of thejnding, The above logic remains valid when the four hour DG2 run assumption is eliminated and a random intermittent voltage regulator

board diode failure is assumed.

In addition, external floods applicable

to CNS are veiy slow developing

events. The plant would have one

to three days warning.

Plant procedures require

the plant to be shut down, depressurized, and the

vessel flooded with the head vents open

when flood levels

are anticipated

to exceed the 902 level.

3.0 CONCLUSION When examining the risk significance resulting froin

the installation

of the defective diode

contained

in the voltage regulator

controls for DG-GEN-DG2, it was concluded that increases

in core damage probability and LERF were

below risk significant thresholds established

by the industry.

Consideration

of the uncertainties

involved in significance deteiinination process (probabilistic

risk assessments)

was alternatively addressed by separately evaluating bounding cases using

conservative

inputs and assumptions.

The conclusion is that the

safety impact associated

with the defective diode is not risk significant.

4.0 REFERENCES

1. 2. 3. 4. 5. 6. NRC Special Inspection

Report 2007007, dated

May 22,2007, froin Arthur

T. Howell 111, to Stewart B. Minehan NUREG CR 6890, Reevaluation of Station

Blackout Risk at Nuclear Power plants, published December, 200

CNS SPAR model version

3.3.1, dated October

IO, 2006 NUREG CR 6823, Handbook of Parameter Estimation for Probabilistic

Risk Assessinent, Published September, 2003 Cooper Nuclear

Station - NRC Inspection Report 05000298/2004014 - Final Significance

Determination

for a Preliininaiy Greater than

Green Finding, dated

March 3 1, 2005, fioin Arthur T. Howell 111, to Randall K. Edington AC Power Recoveiy Evaluation, Prepared by Erin Engineering

and Research, Inc, dated October

1995 Page 22 of 23

Incremental Change

in Core Damage Probability

Resulting

from Degraded Voltage Regulator

Diode Installed in the Division

2 Diesel Generator

7. ASME RA-S-2002, Standard for Probabilistic

Risk Assessment for Nuclear Power Plant Applications and Addenda

ASME RA-Sb-2005 Page 23 of 23

APPENDIX A STATION BLACKOUT EVENT TREE ADJUSTMENTS

The Station Black-out (SBO) portion

of the CNS Loss

of Offsite Power (LOOP) event tree

was modified to reflect updated timing insights gained through thermal hydraulic

and battery depletion calculations perfonned to support the

PRA upgrade project.

Of particular importance

to SBO mitigation

are timing for potential challenges

to high pressure injection systems (HPCI and RCIC)

and individual battery depletion timing (with and without load shed). The revised

LOOP event tree considers updated information regarding: Batteiy depletion timing

for each DC bus, Potential

RPV low pressure isolation

challenges due to operator actions

to emergency

depressurize

the RPV in response to EOP required actions on Heat

Capacity Temperature Limit (HCTL), Pressure Suppression Pressure (PSP), and

high diywell temperahire, Potential equipment trips

due to high exhaust back pressure, Potential

suction source impacts associated

with ECST depletion

or suction temperahire if automatic suction swap

to the suppression pool is anticipated, and Post event

room heat-up impacts on equipment reliability. Use of the on-site diesel driven fire

pump was added to the event tree

for potential credit

provided initial success of HPCI or RCIC, but was given a failure probability

of 1 .O for this study. The failure probability

for actions to extend HPCI or RCIC operation

was assumed to be 0.06. This assuinption was utilized for consistency

in comparing results

to SPAR modeling and is considered a conservative estimate of the failure probability given the relatively long time to accomplish

the relatively simple

human actions (e.g. gravity fill

of ECST, shedding one large DC load, etc.). Figure A-1 shows a graphical representation

of the revised

LOOP event tree. The new core

damage sequences are named

TlSBO-1 through TlSBO-8 and are described

as follows: Sequence T1 SBO-1 : /U2*/RCI-EXT*/Xl "VS"REC-LOSP-DGl2H Following a

LOOP with failure of the emergency diesel generators, RCIC (U2) provides

initial inventory

make-up to the RPV. Manual operator actions

to extend RCIC

operation

are considered

successfd at a 94% probability.

Successfil depressurization (X

1) in support of fire water injection occurs, but fire water injection (V5) fails (assumed

1 .O failure probability

in this analysis).

Recovery of AC power within

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is not successful for

this sequence, resulting

in core damage. Twelve hours is allowed

to recover AC power based on calculation

NEDC 07- 053, which documents a limiting

division 1 (RCIC supply) battery capability

for providing all

required loads for 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> without

any load shedding. Due

to extended boil-off time an

additional hour is allowed to recover AC power prior

to core damage.

Page A1 of A6

Sequence T1 SBO-2:

/U2*/RCI-EXT*Xl

  • REC-LOSP-DG12H

Same as sequence T1 SBO-1, except depressurization

of the RPV fails resulting in failure

of fire water injection (V5). The basis for AC recovery is the same

as described for sequence

TlSBO- 1. Sequence Tl SBO-3:

/U2*RCI-EXT*/Xl*REC-LOSP-DGIOH Following a

LOOP with failure of the emergency diesel generators, RCIC (U2) provides

initial inventoiy

make-up to the RPV. Manual operator actions

to extend RCIC operation are considered failed at a

6% probability. Successful depressurization (Xl) in support of fire water injection occurs, but fire

water injection (V5) fails (assumed 1.0 failure probability in this

analysis).

Recovery of AC power within

10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> is not successful for

this sequence, resulting

in core damage. Ten hours is allowed

to recover AC power based on the limiting time for manual operator action for

any anticipated challenge

to continued

RCIC operation. The

first potential

challenge

to RCIC operation occurs due

to the need to manually align

gravity fill of the Emergency Condensate Storage Tank (ECST)

within 9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br />. Due to extended boil-off time an additional hour

is allowed to recover AC power prior

to core damage.

It is noted that the next most limiting challenge for continued RCIC operation does

not occur until after

10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> due

to potential high exhaust back-pressure turbine trip.

Sequence T1 SBO-4:

/U2*RCI-EXT*Xl

  • REC-LOSP-DGlOH

Same as sequence T1 SBO-3, except depressurization

of the RPV fails resulting

in failure of fire water injection (V5). The

basis for AC recovery is the same as described for sequence

TlSBO- 3. Sequence TI SBO-5: U2*/UlB*/HCI-EXT*/Xl

  • VS*REC-LOSP-DGl OH Following a

LOOP with failure of the emergency diesel generators, RCIC (U2) fails and HPCI (U1 B) provides initial inventoiy

make-up to the RPV. Manual operator actions

to extend HPCI operation are considered successful at a 94% probability.

Successfiil

depressurization (Xl) in support of fire water injection occurs, but fire water injection (V5) fails (assumed 1 .O failure probability in

this analysis). Recovery of AC power within 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> is not successfiil

for this sequence, resulting

in core damage.

Ten hours is allowed

to recover AC power based on calculation

NEDC 07-053, which documents a limiting division 2 (HPCI supply) battery capability for providing

all required loads

for 9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br /> with manual action

to shed one major DC load. Due to extended boil-off time

an additional hour

is allowed to recover AC power prior

to core damage. Sequence T1 SBO-6:

U2*/UlB*/HCI-EXT*Xl

  • REC-LOSP-DGlOH

Same as sequence T1

SBO-5, except depressurization

of the RPV fails resulting

in failure of fire water injection (V5). The basis for

AC recovery is the same

as described for sequence

TlSBO- 5. Page A2 of A6

Sequence T1 SBO-7:

U2*/UlB*HCI-EXT*/Xl

  • VS*REC-LOSP-DG6H Following a

LOOP with failure of the emergency diesel generators, RCIC (U2) fails and HPCI (U1 B) provides initial inventory make-up

to the RPV. Manual operator actions to extend

HPCI operation are considered failed at a

6% probability. Successful depressurization (Xl) in support of fire water injection occurs, but

fire water injection (V5) fails (assumed 1 .O failure probability

in this analysis). Recovery

of AC power within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is not successful for this sequence, resulting

in core damage. Six hours is allowed

to recover AC power based on calculation

NEDC 07-053, which documents a limiting division 2 (HPCI supply) battery capability

for providing

all required loads for 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> without manual action to shed any loads. Due

to extended boil-off time an additional hour is

allowed to recover

AC power prior to core damage. Sequence T1

SBO-8: U2*/UlB*HCI-EXT*Xl "REC-LOSP-DG6H

Same as sequence TlSBO-7, except depressurization

of the RPV fails resulting in failure of

fire water injection (V5). The basis for

AC recovery is the same

as described for sequence

TISBO- 7. Table A- 1 suininarizes the basis for

timing insights associated

with potential

high pressure injection and

batteiy depletion challenges during SBO type scenarios.

Table A-1 HPCI Challenpe

Exhaust Pressure Suction Temperature

PSP ED HCTL I-ligh DW Temperature ED

Area Temperature ECST inventory

Time (hrs) NIA 8 hrs 14.5 hrs 1 I .4 hrs 17 hrs. >I2 hrs. 9.5 hrs. Reference

Calculation

NEDC 92-50W MAAP run CN06058, NEDC 01-29A, B, C MAAP run CN06058 MAAP run CN06058 and EOP IHCTL curve MAAP run CN06058 Calculation

NEDC 07-065, PSA-ES72 and

PSA-ES73 PSA-ES66, NEDC 92-050K, and NEDC 98-001 Description HPCI high exhaust back pressure set-point is - set high enough to not cause a concern of tripping the turbine during

an SBO. Nominal set-point

is 136 psig. HPCI is expected

to be capable of operating

at full load conditions with cooling water

temperatures of 180°F for

greater than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. This temperature is

not reached until

greater than 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> into

the event, and HPCI would be expected to function

for an additional 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />

at a minimum. The timing to the Pressure Suppression

Curve in EOPs is estimated based

on variation

in suppression

pool water levels seen in the analysis.

Timing based on ability

to maintain RPV pressure below HCTL curve yet around 200

psi to allow continued

HPCI operation. Based on 200 psig in the RPV the

suppression

pool temperature to

exceed HCTL occurs

at approximately 235°F.

Equipment reliability for HPCI and RCIC areas not impacted for

a 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> SBO scenario. Timing based on interpolated

time for integrated decay

heat make-up for 87,000

gallons consumed to prevent the low level suction swap. Note that HPCI would

be anticipated

to auto swap to torus and this challenge

is not limiting for HPCI operation, ~~ Page A3 of A6

9.0 hrs DC battery depletion with load

shed RCIC Challenge Exhaust Pressure

Time (hrs) 10.5 hrs Suction Temperature

I 1.5 hrs PSP ED 17.5 hrs I-ICTL 14.1 hrs .4rc;1 Tcinpc.r;i[urc

> I2 hrs. ECST inventory

9.5 hrs. I 1 .O hrs DC battery depletion without

load shed Reference NEDC 07-053

NEDC 07-053 Reference

MAAP run CN06059A.

Calculation

NEDC 92-050AP MAAP run CN06059A MAAP run CN06059A MAAP run CN06059A and EOP HCTL curve

MAAP run CN06059A C;ilculntion

NEDC 07-065. PSA-ES72 and PSA-ES73.

PSA-ES66, NEDC 92-050K, and NEDC 98-001 NEDC 07-053 Assumed action to isolate the Main Turbine

Emergency

Oil Pump within the first 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />

results in extending the 250 V Division 2

battery time to 9 9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br />

The limiting time reported here

is for 125 V Division 2 battery

DescriDtion

Based on nominal set-point and conservative

accounting

of head-loss.

Not a limiting concern for RCIC due

to no automatic suction swap from

ECST on high suppression

pool water level. The timing to the

Pressure Suppression Curve

in EOPs is estimated based

on variation

in suppression

pool water levels

seen in the analysis.

Timing based on ability to maintain

RPV pressure below

IHCTL curve yet around 200

psi lo allow continued HPCI

operation.

Based on 200 psig in the RPV the

suppression

pool temperature to exceed

HCTL occurs at approximately 235°F.

Equipment

reliability

for HPCI and RCIC areas not impacted

for a 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> SBO scenario.

Timing based on interpolated time

for integrated decay heat make-up for 87,000 gallons consumed to prevent the low level suction swap. Note that HPCI would

be anticipated

to auto swap to torus and this challenge

is not limiting for HPCI operation. Page A4 of A6

U E .r C li: i c[ c T C t 4 a e ? D U !Y a W t E 2 i Y.. I U a ! E ii

W 41 0 \o 4 4 5 a

APPENDIX B Human Reliability

Analysis Introduction

Division 2 DG failed a monthly Surveillance

Test on January

18, 2007. The DG VAR loading rapidly spiked until the Diesel

Generator Breaker tripped

on Over-Voltage. The DG VAR loading spiked to approximately 10,667

KVAR prior to tripping the Diesel Generator.

After trouble shooting the

Diesel Generator, it was deteiinined that a diode

on the Voltage

Regulator

card had failed

and caused the

VAR excursion

and subsequent Diesel Generator failure.

A risk evaluation of this condition

was documented

in CR-CNS-2007-00480 which credits recoveiy from the DG2 failure. This is also a key input to the significance deteiinination of this failure, since recoveiy of the DG trip restores critical on-site AC

power. This paper provides

the basis for recovery, identifying the activities

that accomplish recovery

and discusses factors affecting

the successful outcome.

An estimate of the probability

of failure of the recovery is determined for the limiting core damage scenarios

as defined in the

plant PRA and SPAR models , Conclusion

Recovery of DG2 is considered likely due to time available for diagnosis using existing Station Blackout procedures

that place priority on

restart of emergency

AC power. The most limiting core damage event

for failure of Diesel Generator 2 is a

LOOP with the Diesel Generator

1 not available.

In these sequences

high pressure core cooling

is initially successful. More

than 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> is available

to recover at least one

AC electrical power source prior

to core damage. With the station

in a blackout condition, DG2 restart is directed

by 5.3SBO which is applicable to greater

than 95% of the core darnage sequences. Given

an extended coping period available for

diagnosis and execution, the

likelihood

of successful

recoveiy for DG2 is estimated

to be at or below 3.2E-2, depending on the HRA model used. Review of Expected Plant Response

The increase in

risk due to emergency

AC failure occurs in sequences where core

and containment

cooling was successful when relying solely

on Division 2

DG during the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> mission

time of the PRA supplying

all required loads. These sequences require a

Loss of Offsite Power event concurrent

with DG1 out of service for maintenance (or

as result of system failures). After the scram, DG2 trips

due to random (intermittent) diode failure. When the diode

fails, the DG VAR (voltage)

output rapidly increases until the

DG trips on output breaker lockout (86 relay) on over voltage. The loss of DG2 emergency

AC power occurs almost instantaneously following

the diode failure. The DG2 would

trip and lockout

on over-voltage given

the Voltage Control

Mode Selector (VCMS) switch is

positioned

to Auto. In response to a LOOP, the Control Room would

be operating the

plant using HPCI

or RCIC to control level and pressure while depressurizing the reactor.

An RHR pump, a Service Water

Pump Page B1 of B20

and a Service Water Booster Pump would

be in service to cool the suppression pool. These

loads would be supplied

by DG2. Since DG 1 is not credited, once the Control Rooin

validates that offsite

power will not be available promptly (prior

to DG2 failure), the RCIC loads will be transferred

to the Division I1 batteries and supplied by

Division I1 Diesel Generator (via 5.3AC480, Attachment

8). This action would extend

the available battery depletion time to

approximately

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> after DG2 diode

failure. A realistic

battery depletion

of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> is modeled in the

CNS PRA. The depletion times assume

that both divisions

of batteries

are both at 90% capacity. Calculation

NEDC 07-053 estimates

how long the batteries would

last using the

Design Basis calculations

NEDC 87-131A3, By C and D as inputs. The average loading

assumed in these calculations

is determined and

divided by the actual battery capacity. The result of this

calculation validates that both divisions of batteries would be capable

of supplying all required

loads for a ininiinum

of approximately

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. At the end of the scenario, the battery terminal voltage was compared

with the ininiinum battery teiininal voltage required

to ensure adequate voltage

to start the Diesel Generator

was available.

Based on this analysis, both RCIC

and/or HPCI are available

for a minimnuin

of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. Review of Other Issues Effecting:

Recovery There are a number of issues that should be addressed

as part of crediting restoration

of the DG2 lockout. These issues and their resolution are

listed below: Diagnosis:

In order to diagnose the DG2 voltage regulator failure, an operator (in the DG2 room)

inust confirm there are no obvious gross mechanical

or electrical issues effecting

DG operation.

This is accomplished

by procedure

2.2.20. land supports the decision to restart. Since a LOOP event would

have occurred, the plant would be in the Emergency Power procedure

(5.3EMPWR). A station operator monitors diesel operation (Operations Procedure

2.2.20 and 2.2.20.1, the DG operating

procedures)

and during a LOOP would be expected to be nearby (not necessarily in the diesel

rooin). Once the SBO

is entered, the station operator returns

to the diesel rooin and confirms overall integrity

of the machine

to support restart

as needed. Effects of DC2 Restart: The nature of the failure becomes apparent when initial

restart fails due to over-voltage and sanie

annunciation

re-occurs (Procedure

2.3-C-4, Page 8, Tile C-4/A-5

.) Given a failure attempt

to restai-t from the Control Rooin per 2.2.20.1, the Operations

crew would focus

on local operation

in Procedure

2.2.20.2, Section 9 (or 5) as directed by 5.3SBO. Procedure 2.2.20.2 provides guidance for placing DG control in ISOLATE

which defeats the standing emergency start

signal. The decision for local operation in inanual voltage control would

be driven by the high priority of AC power restoration given the

SBO condition.

Staffing: At the initiation

of the LOOP event, the plant would have been placed in a Notification

of Unusual Event. Although a

NOUE does not require initiating actions

to bring the

ERO on site, Operations Management

would expect the SM to call in additional personnel, once the Control

Rooin contacted the Doniphan Control Center and

determined that offsite power would not be restored

promptly.

In the event that

the SM did not initiate ERO pagers to activate facilities, the Operations

Management

team would require

the SM to take these actions

as follow-up

to notification Page B2 of B20

of change

in plant status. The needed staff, including management, maintenance, and engineering, would be called out and mobilized

to respond to the plant event. After the

SBO occurred due

to the loss of DG2, a Site Area Emergency

would be declared and the ERO would be activated, if not already

staffed. Lighting: When DG2 is running

the plant would be in a LOOP with normal lighting powered from

MCC-DG2. When DG2 failed, a station blackout would occur given

DG1 is unavailable. Local inspections would be facilitated

by emergency Appendix R lighting. A

set of emergency lights

are located in the DG2 room and they are directed in the general direction

of the local control panels.

The emergency lights are

rated at 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> on battery. Lighting levels

are adequate for general

activities

such as getting around

in the room and gross inspection

of the diesel. The lighting would be

sufficient

to support local control using

the VC Mode Selector and Manual Voltage Regulator Adjust, each

which are within aims reach on the front control panel in the

DG2 room. Execution:

Loading of the DG during manual operation

was reviewed for system response. The

first loads the

DG would supply are the 480 volt load center including the

460 volt MCC loads. This loading is expected

to be approximately

500 to 750 1VA. Based on the rating

of the DG compared to this load, the DG output voltage is not expected

to change significantly. Following these

loads, an RHR pump, a Service Water Booster

Pump and a Service Water

pump would be manually

started from the Control Rooin.

These loads would be started individually

by the operator

in the DG Room. The operator

stationed

in the DG room would

monitor DG voltage after each

large motor start and adjust the voltage back

to approximately

4200 volts after the

motors had started and a steady state

voltage had been achieved. Conversations with the

DG System Engineer and

two MPR representatives

indicated that with the DG

in manual voltage control, the voltage drop between

no load and full load would probably be around

5%. Since each of the large motors that would

be started represents

approximately

'/4 of the total

capacity of the generator, a voltage drop

of 1.25% would be expected.

Due to the uncertainties associated with operating a

DG in this manner, a value

of 5% voltage drop

for each motor start

will be conservatively utilized.

Given the minimal loading and the significant

margin between the

original voltage of 4200 volts

and the minilnuin required voltage, the Station

Operator would be able to maintain the

output voltage of the DG at above the minimum voltage requirements for the equipment

at all times. Recovery Time Line A list of actions is described for

the recovery of DG2, including consideration of the issues described

above. These actions are shown in the following

table, with estimates

of the range

of times required

to perform each

action (Time Estimate

column). A narrative

of the Operator response is given here

to support the list in Table 1. After the DG2 trip, the

Control Room would enter procedure 5.3SBO which

would direct the Operator located near DG2

to do a visual inspection

of the Diesel Generator

to ensure that fluid levels

and other parameters are

in specifications

(5.3SBO Attachment 3, Step 1.2.3.2 ff). When the 86 lockout relay is reset in the Control Room, DG2 restart is expected due

to the standing safety system

actuation

signal. Due to the failed diode

in the voltage regulator card, the diesel generator will fail almost

instantly

upon starting.

As a result of

this trip, the same alarms and trip indications will re-occur. Once DG2 trips the second time, the Control

Room would have received

the same annunciation

and breaker flags on both trips (indicates a voltage

control problem.)

The Control Room would be

directed Page B3 of B20

to place DG2 in ISOLATE (5.3SB0, Step 1.2.3.5) which defeats the emergency start signal. The

Control Room directs use

of Section 9, Procedure 2.2.20.2, Operation

of Diesel Generators froin

Diesel Generator

Rooms, by placing Control

Mode Selector Switch to LOCAL. At Step 9.6.1 the Control Room would require the VC Mode Selector switch

be positioned

to Manual to start the

DG and the Manual Voltage Regulator Adjust

be set and maintained

at approximately

4200 volts. It should be noted that this control

will probably already be set

to approximately 4200

volts. Once the DG was running and not tripping, the Operations

Crew would load the DG per plant procedures (refer

to 5.3SB0, Attachment

3, Step 1.2.3.6.)

1, Control room responds to

LOOP, 5.3EMPWR verifies DG2 runiiiiig

2. Station Operator dispatched

to DG2 room B. TSC Activation

Table 1 Recovery Activities and Duration

I Activitv I Time Estimate finin) I Time Lim (tniti) 1 1-2 1-2 2-5 3-7 I A. LOOP ResDonse I I t=O I 4. Station

Operator performs checklist, contact Coiitrol

rooin 5. Station Operator observes DG2 start sequence and trip

2-5 6-14 1-1 7-15 I 1. TSC Activatioii

I 60 I 60 I 45- 105 6. Decision to Restart

DG2, 5.3SB0, Att. 3, Step 1.2.3.5 using 2.2.20.2 (DG2 Isolated, cliaiige

VC Mode to Manual and Man Volt Control)

D. Execution

I 3. Decisioii to Restart DG2. 5.3SBO.

SteD 1.2.3.4 Der 2.2.20.1 I 1-2 I 4-9 I 51-120 I 1. Station ODerator restart DG2

in Manual I 5-10 I 56-130 I The time required

to recover the DG is estimated at 120 minutes for diagnosis (steps

C.l through C.6) and 10 minutes for execution (step D. 1) froin

the time the DG lockout occurs. (The ininiinum

time estimated to perform

the recoveiy is 56 minutes.) This is supported

by the expected time

to review the

alanns and step through existing procedures

to determine applicable steps. This restoration, operating

the DG in manual, is a relatively simple task which is

accomplished

by the Operating

crew member assigned to the DG unit. These times

are used in the next section, where the recoveiy failure probabilities

are estimated

in SPAR-H method.

The minilnuin

retui-n to service time available is

10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />, based on 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> RCIC operation plus 120 minute boil-off period. (Similar time for recovery exists

for the HPCI success case, with actions to extend injection

to 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> following DG2 failure.) This treatment is applicable

to more than 95% of the sequences contributing

to core damage.

The remaining

5% of the sequences

have considerably shorter time frame for recoveiy

and are assumed not recovered. This assumption

has negligible impact

on expected change

to core damage

frequency.

Probability

of Failure to Recover The SPAR-H model was used

to estimate the probability of failure

to recover the DG as a function of

the time required

to perform the manual restart (the time from the timelines) and the time available

to complete the actions

in order to mitigate core

damage (which comes from the accident sequence

Page B4 of B20

analysis in the PSA).

The recovery will be considered

in two parts, Diagnosis

and Execution, per the SPAR-H method.

The time available

to make the restoration

is the time the plant is able to cope with a SBO. The DC battery depletion time is 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> with either high pressure injection source with

an additional 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />

for core boil-off time. This evaluation assumes

the 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> depletion

time starts at the time of the SBO event. For this scenario no credit

is given for possibility of using the swing charger on Division

1 batteries when DG2 is running.

A bounding 10 hour1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> recovery

period is assumed

to apply to both HPCI

and RCIC depletion sequences. The following perfoiinance

shaping factors from the SPAR-H method are

assumed for the diagnosis

portion: a W W W a W Time Available

= Long (9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br />), time needed

-120 minutes Stress = High, LOOP, then station blackout conditions

Complexity

= Nominal, indications are compelling, interpretation and action

is clear Training = Nominal, address symptoms use TSC support to diagnose Procedures

= Nominal, use alarms

as defined and steps in procedures problem is self-revealing

Ergonomics

= Nominal, CR emergency lighting exists The following performance shaping factors from

the SPAR-H method are assumed for

the execution

portion: a Time Available

= Long (-10 min), with

>60 min available

Stress = High, focused

on DG recovery, however action

does not create conflict Complexity

= Nominal, actions are simple and gradual

Training = Low, however manual operation uses familiar

controls at DG panel Procedures

= Not complete, TSC to add steps

to Section 9 for manual start and load Ergonomics

= Nominal, emergency lighting in

place a W W a a As seen on the following

SPAR-H table, the estimate for the probability of failure

to recover the

DG is 3.2E-2. This is calculated using conservative

estimates

of repair activity

times. Discussion

of SPAR-H Performance Shapinp Factors

Diagnosis

Factors: Location: Information from

the Control Room and the Diesel

Generator Room would be utilized

to diagnose this event. Time Available:

The minimum time available is considered

long (>60 minutes) because

total time to diagnose the DG is approximately

120 minutes and the execution

is expected to take about 10 min. Stress: The stress is considered high because the plant

would be in an SBO. With

the ERO staffed, the

Operations

Crew would have additional resources

to help diagnose the problem and significant insight into the problem would be available.

Complexity:

The Control Room would have

at least two distinct annunciator and a breaker

trip flag cues - indicate a voltage control

problem as confirmed by alarm card listing. There is

not conflicting

infoiinatioii

since both cues lead to the same conclusion, the complexity is

considered

Nominal. Page B.5 of B20

Training: Operations is

trained on how to operate the DG and a procedure is available

for operation

of the DG from the Diesel Generator

Room which is considered

adequate. Procedures: Procedures

5.3EMPRY 5.3SB0, 2.2.20.1, and 2.2.20.2 provide guidance

on what actions

should occur during

an SBO. The guidance in 2.2.20.2 (refer

to Section 9) to start the

DG in auto voltage control

would establish

the DG voltage trouble. The

vendor manual states

that DG operation

in manual should be used if

there are voltage control issues. By modifying Procedure

2.2.20.2, at Step 9.6.1 the Control Room would require the

VC Mode Selector switch be positioned

to Manual to start the DG and the Manual Voltage Regulator Adjust be set and maintained

at approximately 4200 volts. Therefore, the procedures are considered nominal

for diagnosis.

Ergonomics:

The operator would be required

to operate the

DG from the Diesel Generator Room and the actions of starting the

DG and adjusting

DG voltage would occur

at different

times. The actions the operator would be required

to perfom are considered ininiinal and

the position of the equipment is

considered

adequate.

Therefore, the ergonomics of this recovery is considered nominal.

Execution

Factors: Location:

The recoveiy of the DG would occur in the Diesel Generator

Room. Time Available:

The time available is considered long because the actual starting of the DG in manual voltage control

is estimated

to take approximately

10 minutes and the available time is much greater

than 5 times that amount. Stress: Since the operator would

have been in the DG room inspecting the

DG and resetting breakers since the

time the DG failed, the stress is considered high. Since the DG would start

once procedure

2.2.20.2 was utilized, the stress would

only decrease as the recovery continued.

Complexity:

The start and operation

of the DG in manual voltage control is provided

by the Control

Room using 2.2.20.2 with the exception that

the operator does not perform the step

to start the DG

in automatic voltage control. The

control room would provide guidance

on manual operation

to be followed prior to running in manual. Once the DG was running and not tripping, the Operations

Crew would load the DG per plant procedures (refer to 5.3SB0, Attachment 3, Step

1.2.3.6.) With the DG

in manual, the need for adjusting

the voltage as loads are added is considered minimal. Overall the complexity is considered nominal. Training: Procedure

2.2.20.2 does not provide explicit guidance on how to manually adjust voltage, therefore the training is considered low.

Manual voltage control of the DG

is not specifically

trained on, however, the required voltage

band is large and the control of the DG voltage is

simple. Overall, training is considered low

for this recovery.

Ergonomics:

The ergonomics for this recovery is considered adequate.

The controls for the DG are readily available and are the same controls used

in other DG evolutions.

Once the DG is started, the

only operator input required

is occasionally verifying the output

voltage and malting minor

adjustments

as needed. Overall, the

ergonomics is considered nominal

for this recovery.

Page B6 of B20

+ -----I- ", :Ic & -I ' 1 Y i- 4 I f .- " KKSSK c s 0 .o .o .o .o .o CI-C-lII $Mu,, 23x33 a,a,a,a,a, cxxxxx .zwwwww L m I1 ~ h =!. c3 n c m m 0 0 -I - b

Discussion

of EPRI HRA Calculator Analysis

EPS-XHE-FO-DG2, Operator fails to recover

DG2 after VC board failure Table 1: Basic Event Summary Table 2: EPS-XHE-FO-DG2

SUMMARY Related Human Interactions:

Cue: - The increase in

risk due to emergency

AC failure occurs in

sequences where core and containment cooling was successful

when relying solely on Division 2

DG during the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> mission time

of the PRA supplying

all required loads. These sequences

require a Loss of Offsite Power event concurrent

with DG 1 out of service for maintenance (or

as result of

system failures). The DG2 continues to run for 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> prior to the diode failure causing

the DG to trip. When the diode fails, the DG VAR (voltage) output rapidly increases

until the DG trips on output breaker lockout

(86 relay) on over voltage.

The loss of DG2 emergency

AC power occurs almost instantaneously following

the diode failure. The DG2

would trip and lockout on over-

voltage given the Voltage Control

Mode Selector (VCMS)

switch is positioned to Auto. In response to a LOOP, the Control Room would be operating

the plant using HPCI

or RCIC to control level and pressure while depressurizing the reactor.

An RHR pump, a Service Water Pump and a Service Water Booster

Pump would be in service to cool the suppression pool.

These loads would be supplied by DG2. Since DG1 is

not credited, once the Control

Room validates

that offsite power will

not be available

proiiiptly (prior to DG2 failure), the RCIC loads will be transferred

to the Division

I1 batteries and supplied

by Division I1 Diesel Generator (via 5.3AC480, Attachment

8). This action would extend the available battery depletion time to approximately

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> after

DG2 diode failure. The cue is the trip of the DG2 and entry into SBO conditions. It would be indicated by

numerous alarms and indications and clearly identifiable.

Degree of Clarity of Cues & Indications:

Very Good Page B8 of B22

Procedures:

Cognitive:

5.3SBO (STATION BLACKOUT)

Revision:

14 Execution: 2.2.20.2 (OPERATION OF DIESEL

GENERATORS

FROM DIESEL GENERATOR ROOMS)

Revision:

36 Other: () Revision: Cognitive Procedure:

Step: 1.2.3.1 Instmction:

LOCALLY CONFIRM DG INTEGRITY Procedure and

step governing

HI: Plant Response : DG2 automatically starts

and loads Essential Bus

4160 Volt 1G. Main Control Room (MCR) declares a NOUE and enters 5.3EMPR, Attachment

2, Step 1.8.3 "If normal power cannot be restored

or is subsequently lost, ensure

TSC activated and have

TSC activate Attachment

5 (Page 18)

to restore power to PPGB 1 .I1 Attachment

3, Step 1.2.3 "If only one DG is providing power, perform following:

Monitor DG load in accordance with

Step 1.1.2 and Attachment 4 (Page 1

l)." DG2 Voltage Regulator Card

Fails causing DG2 Failure

Plant Response:

MCR declares a Site Area Emergency and activates

the ERO if the ERO has not already

been activated due to the extended LOOP. MCR enters 5.3SBO Step 1.2.3, Attachment 3

1.2.3 "If a DG is not running, perform following: 1.2.3.1 Check

local control boards, valve lineups, and control power fiises if degraded conditions such as shorts, fires, or mechanical

damage are not evident.

1.2.3.2 Reset any

trip condition.

Page B9 of B22

a At VBD-Cy check white light

above DIESEL GEN

l(2) SEQ RESET button light is off. If

on, press RESET button to reset trip.

INCOMPLETE b Locally in

DG Room, check ENGINE OVERSPEED alarm is not in alaim. If alaimed, reset per alarm procedure. c Locally in DG Room, on DIESEL GENERATOR #1(2) RELAYING panel

check white light above DGl(2) LOCKOUT relay is on. If off, check relays to determine cause

and reset. 1.2.3.3 If starting air pressure is low, start diesel

air compressor per Procedure

2.2.20.1.

1.2.3.4 Start and load DG per Procedure 2.2.20.1." MCR and DG Operators would enter Procedure 2.2.20.1, Section 7. Section

7 contains several steps designed for maintaining the availability

of the DG during surveillance runs, however, the steps

of interest are:

Plant Enters 2.2.20.1 "DIESEL GENERATOR

OPERATIONS" 7.13 STOP light tui-ns off. Place and

hold DIESEL GEN 2 STOPETART

switch to START until 7.14 4200V. This step does

not state specifically

the voltage regulator would be in "Automatic" at this time, however, since

this is a Restart froin

the Main Control Room, the only option for restarting the Diesel Generator froin

the Control Rooin

is in Automatic.

Due to this fact, the DG would trip and cause

an over-voltage

lock- out, an over-voltage annunciation exactly the

same as the first

trip. Using DIESEL

GEN 2 VOLTAGE REGULATOR, adjust voltage

to - Plant Continues

in Procedure

5.3SBO Attachment

3, Step 1.2.3.5 provides

the following guidance: "If DG(s) cannot be started and loaded, start and load DG(s) with ISOLATION

SWITCHES in ISOLATE per

Procedure

2.2.20.2".

Procedure

2.2.20.2 has 3 Sections that are applicable

to DG2. Sections 5, "DG2 STARTUP AND SHUTDOWN

AFTER MAJOR MAINTENANCE", Section 7, "DG2 STANDBY

STARTUP AND SHUTDOWN FROM

DG2 ROOM Page B 10 of B22

Section 9, "DG2 OPERATION

WHEN REQUIRED BY PROCEDURE 5.3SBO

OR 5.4POST-FIRE" The obvious

section that would be applicable for this condition

would be Section

9 since it references

5.3SB0, however, upon reviewing

this section, the

steps are virtually identical

to the steps in 2.2.20.1 except that the DG is physically started in

the DG rooin. The Voltage Control remains

in Automatic and thus the DG would trip

as soon as the DG started resulting in the same annunciation, alarms and flags. Reviewing the procedure

further reveals that Section 5 provides

the appropriate guidance for starting

the DG in manual voltage control. Since Operations use

this section of the procedure

each outage if

any major maintenance

is performed on

the DG, it is reasonable

to assume that this section

of the procedure would be utilized

under these conditions with these combined expertise

of the TSC and the on-shift operating crew and potentially the entirely

ERO staffed. Following

either section 5

or section 9 would accomplish the same actions, and both would lead

to a successful

stai-t of the DG. Plant Enters

2.2.20.2 "OPERATION

OF DIESEL GENERATORS

FROM DIESEL GENERATOR

ROOMS" 1. Section 5 "DG2 STARTUP AND SHUTDOWN AFTER MAJOR

MAINTENANCE" 5.8 Place

VOLTAGE CONTROL MODE SELECTOR switch to MANUAL. 5.16 Press and hold START button until blue

AVAILABLE

light t~irns off. 5.20 Using MANUAL

VOLTAGE CONTROL ADJUST knob, adjust

5.23 GENERATOR VOLTAGE

to - 4200V. Place VOLTAGE CONTROL MODE SELECTOR

switch to AUTO. At this time

the DG would trip and cause

an over-voltage lock-out, an over-voltage annunciation exactly the same as the previous

trips. Since the trip would occur

immediately

after the switch was placed in automatic, the cause of the failure would

be self revealing.

Once the cause the

DG trip was determined, the procedures would easily be revised to

eliminate

the step that puts the

DG in automatic voltage control

and adds a step that

has the DG operator check and/or adjust the DG

voltage as necessary within a

few minutes after

large motors are added and

as a periodic task.

This task would be identical

to the task the operator perforin

to add load to the DG for the Monthly

Suiveillance tests with

the only exception being that they would be monitoring voltage

and total load rather than

just total load. Therefore, the operators receive training on

this type of activity twice a month.

Operation

of the DG in manual voltage control

is also discussed in the Vendor Manual.

Training: Classroom, Frequency: Initial

OJT, Frequency: Initial Routine Operation:

The operators perform a manual start

from the DG rooin per procedure

2.2.20.2, section 5, at least once per outage. Page B11 of B22

JPM Procedure:

Environment:

() Revision:

Lighting Einergeiicy

Heatkluinidity

Hot I Huinid Radiation

B aclcgsouiid

Atmosphere

Nonnal HFE Scenario Description: Division 2

DG failed a monthly Surveillance Test on January

18,2007. The DG VAR loading rapidly spiked until the Diesel Generator Breaker tripped on Over-Voltage.

The DG VAR loading spiked

to approximately 10,667

KVAR prior to tripping the Diesel Generator.

After trouble shooting

the Diesel Generator, it was detennined

that a diode on the Voltage Regulator card had failed and

caused the VAR excursion

and subsequent Diesel

Generator

failure. Special Requirements:

Comdexitv

of ResDonse:

A risk evaluation

of this condition was

documented

in CR-CNS-2007-00480 which

credits recovery from the DG2 failme. This

is also a key input to the significance deteiinination of this failure, since recovery

of the DG trip restores critical on-site

AC power. Comitive Coinulex This HRA estimates

the probability of failure of the recovery.

Equipment

Accessibility: Execution Performance Shaping Factors: Executioii Complex

CONTROL ROOM Accessible

DIESEL GENERATOR ROOM

Accessible

Stress: High Plant Response As Expecled:

No Workload:

NIA Pei:fonnance Sliapiiig

Factors: NIA Page B12 of B22

Performance

Shaping; Factor Notes: Cognitive Unrecovered

EPS-XHE-FO-DGZ

Timing: 6no.00 sw I Cue I Irrevekble

DamageS tate I t=o I Timing Analysis:

The time required

to recover the

DG is estimated

at 120 minutes for diagnosis (steps C.l through (2.6) and 10 minutes for execution (step

D.l) from the time the

DG lockout occurs. (The

minimum time estimated

to perform the recovery is 56 minutes.)

This is supported by the expected time to review the alarms and

step through existing procedures

to determine applicable steps.

This restoration, operating

the DG in manual, is a relatively simple task which is accomplished

by the Operating

crew member assigned

to the DG unit. The time available

to inalte the restoration

is the time the plant is able to cope with a

SBO. The DC battery depletion

time is 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> with either high pressure injection source with

an additional

2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> for core boil-off time.

This evaluation assumes

the 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> depletion

time starts at the time of the SBO event. For

this scenario no credit is given for possibility

of using the

swing charger on Division 1 batteries

when DG2 is running.

A bounding 10 hour1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> recovery period is

assumed to apply to both HPCI and RCIC depletion sequences. Time available for recovery:

470.00 Minutes SPAR-H Available time (cognitive):

590.00 Minutes SPAR-H Available time (execution) ratio:

48.00 Minimum level of dependence for

recovery:

ZD Page B 13 of B22

Table 3: EPS-XHE-FO-DG2

COGNITIVE

UNRECOVERED

Page B14 of B22

Indication

Avail in CR Most necessary indications are available

in tlie main control

rooin. CR Indication

Warning/Alternate

Training on Accurate in Procedure

Indicators Lockout relay and diesel integrity

information

is necessary

for the cognitive

task and is readily available from the diesel generator room.

Low vs. Hi Workload Check vs. Monitor Front

vs. Back Alarmed

vs.Not Panel Alarmed Low Monitor Front Back (b) 1.5e-04 (c) 3.0e-03 Check (a) neg. (m) Me-02 Back (n) 1.5e-03 1 Monitor Front (d) 1.5s-04 (e) 3.0e-03 I (0) 3.0e-02 Per procedure

during a SBO, recoveiy of the EDGs is tlie operators' primary concern and focus. Most

of the necessary

information

is available

on a front control panel

or tlie DG local panel. Page B 15 of B22

indicators Easy

to Locate I (h) 7.0e-03 While diesel noise could hinder coinmunication while

the diesel is running, it will not be

ruiiniiig

during the cognitive

phase and communication froin

the DG room to the CR should be

normal. GoodlBad indicator Formal

Communications

pcd: Information misleading

Yes -_ No Ail Cues as Stated Warning

of Specific Training General Training

Differences (b) 3.0e-03 ~ pce: Skip a step in procedure

Obvious vs. Single vs. Multiple Graphically Placekeeping

Aids I Hidden Distinct r------- No I (a) 1.0e-03 (b) 3.0e-03 (c) 3.0e-03 (d) 1.0e-02 (e) 2.0e-03 (f) 4.Oe-03 (i) 1.Oe-01 Page B 16 of B22

pcf: Misinterpret

instruction "NOT" Statement

Standard or All Required Training on Step Ambiguous wording Information "AND or "OR" Both "AND" B Practiced Scenario

Statement "OR I Belief in Adequacy of Instruction

I (d) 3.0e-03 (e) 3.0e-02 Adverse Reasonable Policy of

Consequence

if Alternatives "Verbatim" I I (f) 6.0e-03 (9) 6.0e-02 (a) 1.6e-02 (b) 4.Be-02 (e) 6.0e-03 (d) 1.08-02 (e) 2.0e-03 (f) 6.0e-03 Page B17 of B22

e s e L VI e! V w A w W n 0 2 il 2 2 2 0 V W V C 3 e t; E B 5 z m Q 0 d 0 V Q 0 > -1 Q 3 z 2 s t; 2 W V a 5

0 x - N m m 2 3 C

% x

APPENDIX C Data analysis The following section describes

the process and results

of the data analysis performed

to determine

the failure probability

of the defective

diode in the DG-GEN-DG2 voltage

regulator

card. In Service Performance

for the Defective Diode The diodes

in service life included

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> of run time and one failure

of ftinction.

The defective diode was

installed

in as pai-t of the voltage regulator control card on November

8, 2006. The card was in service for 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> following installation

as the diesel generator was

ran for post maintenance testing and surveillance testing

up until its failure

and reinoval on

January 18, 2007. Evaluation

of performance leading to the over voltage trip

of DG-GEN-DG2 on

January 18, 2007 and subsequent root cause

lab testing found that

there were two other instances that could be attributed

to the open circuit failure condition

of the defective diode. However both of these

instances

were dismissed

as follows: During post maintenance testing

of DG-GEN-DG2 on November

1 1, 2006, an over voltage condition was

noted while tuning

the control circuit that contained the defective diode.

Because this testing did not provide conclusive evidence that the diode was the

cause of the over voltage condition and based on the

fact that DG-GEN-DG2 demonstrated over

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of successful

iun time after occurrence

of the November 1

1, 2006 condition, this instance is dismissed

as a attributable failure

of the defective diode.

A post failure test of the circuit card that included

the defective diode resulted in both satisfactory card operation followed

by unsatisfactory

card operation with subsequent

determination

that the defective

diode was in a permanent

open circuit state. Though this lab testing could

have been interpreted

as an additional failure

of the diode, it has been dismissed due

to the large amounts

of variability introduced

by shipping of the card to the lab, the differences between lab bench top

testing and actual installed conditions, and errors that could be

attributed

to test techniques and human errors.

Priors A bounding approach was taken

in the application

of diesel generator failure

to nin data used

to assess the change in risk resulting

fonn the January 18, 2007 over voltage

trip. This bounding approach includes use of a higher diesel generator

fail to An failure rate modeled

in the CNS SPAR model. The SPAR model diesel generator fail to run probability is 2.07E-02

for a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> mission time. The mean failure rate can be derived by solving the following poison

derivation

for the diesel generator failure probability

of 2.07E-02:

Page C1 of C2

2.07E-02=1-Exp(-h"24)

or h = 8.715E-O4/Hr Number of

Diode Failures (N)

This failure rate will

be used as a noninfonnative prior to

derive the failure rate

of the defective

diode. Diode In Service hpost, Diesel Generator Diode Failure

Tiine (Hours) (dc+N)/p+3

6) Mission Time

Probability

(1- E~p(-Api,,t

"24) Bayesian Estimation

N= 1 N=2 Guidance provided

in NUREG CR6823 (Reference

4) was used to deteiinine

that a Constrained

Noninfonnative Prior Bayesian

Estimation

was the best method to utilize in

the derivation of the defective diode failure rate.

Section 6.5.1 of NUREG CR6823 discusses failure

to run during mission events and directs the

use of Bayesian estimates using section 6.2.

Section 6.2.2.5.3 recoininends use

of the constrained noninformative prior as a coinpromise

to a Jeffi-ies

prior when prior belief is available but the dispersion is defined to

correspond

to little information. Because the

SPAR fail to run data provides prior belief

with unknown infomation

on possible industry failures resulting

fonn the diode defect a constrained

noninfonnative

prior was applied. 36 2.46E-03

24 HOU~S 5.7E-02 36 4.1 1 E-03 24 Hours 9.3 9E-02 This estimation

assumes an dc of 0.5 and derives p as follows using the 8.715E-04

mean failure rate froin the SPAR data: hprior = dc/p p = 573 Where dc=0.5, hp~i,,=8.715E-04/Hr Applying the

in service performance for the defective diode

the following table can be

generated

to detail the diodes failure probability.

Apost is derived using the Constrained

Noninfonnative Prior with

an dc=0.5 and p = 573. I N=3 I36 I 5.75E-03 I 24 Hours I 1.29E-01 Note the above table includes

1, 2 and 3 failures

to support bounding analysis

done in section 2.2. The overall ,change in risk imparted

by the defective diode derived

in section 2.1 of this study concludes

an overall failure

of 1 to best reflect the actual conditions. Page C2 of C2

APPENDIX D DG2 VOLTAGE

CONTROL BOARD DIODE FAILURE FIRE-LOOP EVALUATION

Introduction During surveillance testing

on January 18,2007 the Division 2 Emergency Diesel Generator (DG2) tripped unexpectedly

after running for approximately 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />

in automatic voltage

control mode. This paper evaluates

the impact of

internal fires on offsite

AC power availability

and recoveiy actions. Internal

fires can contribute

to the Incremental Conditional Core Damage Probability (ICCDP) for

this condition, and that contribution

is assessed using

the results of the CNS IPEEE Internal Fire Analysis coupled with additional condition specific analysis. This evaluation is limited

to conditional fire initiated accident sequences where the DGs are demanded. Therefore, for

the evaluated

fire sequences

to contribute to the overall

ICCDP, they inust cause a Loss of Offsite Power (LOOP). The LOOP can

be caused in

one of two ways. Either the fire physically

damages equipment that causes offsite power

to be lost, or it forces the

operators

to intentionally (per procedure)

isolate offsite power from

the plant. Sequences

that include a

partial LOOP event occurring as result

of loss of the start-up transformer are

also possible. However the onsite

LOOP recovery (as addressed

in 5.4POST-FIRE)

from these sequences are not discussed

here. Evaluation

Summary Only two credible fires

will cause a LOOP due to equipment damage.

Those fire initiators are

1) a control

room fire originating at

either Vertical Board

F or Board C, and 2) a fire in Division

I1 critical switchgear

room 1G. The latter switchgear

room fire is not considered

because this fire is assumed to disable Division

I1 AC power regardless of the success of the DG2 voltage

control board. There are

two locations in the control room where a fire can conceivably cause a LOOP. Both of these locations contain control circuits for

the critical bus

tie breakers from both the station

startup transformer (SSST) and the emergency

transformer (ESST). A fire in each

location is considered a separate initiator.

One of those sequences requires

an unmitigated fire

involving

at least 4 feet of a control

board to affect the necessaiy breakers.

Both fire sequences would

require a combination of hot shorts to open the breakers before

the breaker control circuits were shorted to ground. The 69 ItV transmission

line that supplies

the ESST does not have a local 69kV

breaker and therefore the

86 Lockout and

87 Differential

relays cannot de-energize

the transformer. Instead the

86 Lockout and the 87 Differential

relays cause the

41 60 Volt breakers

1F and 1G to trip. Therefore, power from

the ESST is recoverable

by pulling the fuses at

the brealter(s) and manually

closing the breaker(s).

Ifjust one (out of

two) of the 1G breaker

control circuits is either not shorted to power (hot short) or

blows a fuse due to a short to ground, the 1G critical AC

bus will remain energized from

an offsite source. Due to the required complexity

of these fires, the probability

of the short combinations is

on the order

of 1E-3. The four lockout relays are individually fiised

and required 125 VDC control

power to operate. A fire creating a

Page D1 of D6

short would have

to simulate a

CLOSED contact from

an initiating device without

blowing a control power fuse

to actuate the lockout relay

or affect current transfoiiner wiring from the current transformer

to the neutral over-current

or differential relay causing the relay to actuate.

The contribution

to risk from these sequences

is negligible. There are

several fires that result in the transfer

of control of the plant to the ASD Panel.

When this occurs operators are directed

to isolate offsite power and then power

bus 1G with DG2. These fire initiators are

1) a control room fire requiring evacuation, 2) a fire

in the cable spreading

room, 3) a fire in the cable expansion room, 4) a fire in the NE comer of the reactor building, and 5) a fire in the auxiliary relay room. Procedure 5.4FIRE-SD provides instructions

on isolating offsite power

and powering the plant

from DG2. In these cases, the LOOP is administratively induced

and fiilly recoverable if needed.

In response to the above sequences, the Emergency Response Organization (ERO) will be available after 60 minutes

to assist operations

in restoring offsite power if

DG2 fails. (Refer

to EAL 5.2.1, a fire that effects any system required to be operable, directs

an Alert classification

with ERO activation.) For example, if 4160 VAC buslF is energized, an alternate

breaker alignment could be use

to power the 4160

VAC bus 1G (Div. 11) loads that are controlled from

the Alternate Shutdown (ASD) Panel.

Overview of CNS 4160 VAC Distribution Design

The configuration

of the CNS offsite power sources and the main generator supply is illustrated

in Figure 1. CNS supplies power to the grid at 345kV.

The 345kV switchyard

is designed with a "breaker and

a half scheme, so if the CNS Main Generator output breakers

trip, the remainder

of the 345kV yard is unaffected.

The primary offsite power source at

CNS is the Startup

Station Service Transformer (SSST) which

is supplied via a step-down transformer T2 from

the 345kV switchyard. The SSST can also

be supplied by a 161kV transmission line that

leaves the site and terminates close

to the city of Auburn. At power, CNS norinally supplies the non-1E and 1E 4160 VAC switchgear from the station unit auxiliary transformer (Normal Station

Seivice Transformer or NSST). If the CNS generator

trips or the NSST de-energizes without a generator trip, the station switchgear

is designed to transfer

station to the SSST if available

via a "fast transfer".

The fast transfer occurs within

3-5 cycles such that no loads are shed during this transfer.

Since the 4160 volt Essential

Buses 1F and 1G are supplied

by 4160 Volt Buses A

and B, the Essential Buses also "fast

transfer" to the SSST.

The SSST is supplied

by the 161kV

CNS switchyard which is connected

to the CNS 3451cV switchyard

via an auto-transformer

and a 16 1 kV switchyard

via the CNS to Auburn 16 1 kV transmission

line. If the SSST is not available

or the tie breakers between

4160 Volt BL~S A and F (and B and G) trip, the Essential Buses

1F and 1G transfer

to the Emergency Station Service

Transformer

via a short duration dead bus transfer.

Page D2 of D6

FROM MAIN GENEWTOR FROM 345 KV/161 KV GRID v N 22 W/4 160V NORMAL STATION SERVICE TRANSFORMER

V I STARTUP STATION SERVICE UAAJ TRANSFORMER - I161 KV/4160'/

OESEL GENERATOR

P2 f OPPO LINE DIESEL GENERATOR

RI Figure 1. CNS 4160 VAC Distribution

Page D3 of D6

The ESST is supplied by a 69kV sub-transmission

line from the 691tV Substation near

Brock, Nebraska which has inultiple sources. A

trip of the CNS main generator

supply would have a minimal affect on the voltage at the

Brock Substation.

If the ESST is available and breakers

1FA and 1GB are OPEN, the ESST supply breakers (1FS

and 1GS) to the 1F and 1G switchgear

will close after a short delay (in which the 4160 motors trip) and the ESST will supply both class

1E switchgear.

' If the ESST is also unavailable

or one of the supply breakers (IFS or IGS) does not close, the diesel generator(s) will supply the associated

41 60 VAC switchgear. Devices that will prevent

the ESST or SSST from automatically supplying

the 1E switchgear

are the 86/EGP Lockout Relay (ESST Sudden Gas

Pressure), 86/SGP (SSST Sudden Gas Pressure), 86IST (SSST Differential

Current) and the 86/STL (SSST Neutral

Over-current). These lockout

relays will trip the 4160 VAC supply breakers

froin the offsite

power transformers

and prevent remote closure froin the control room of the 4160 VAC supply breakers. Reference B&R Drawing 3012, Sheet 4

Rev N1 1 . The lockout relays associated with the SSST

will also trip the

16 1 kV breakers 1604 and 1606.

The four lockout relays associated with the

ESST and SSST are located on

Vertical Board F in

the CNS Control Room. The 86/EGP is actuated

by a normally

open contact at the ESST.

Tlie 86/SGP is actuated by a normally

open contact at the SSST.

The 86/STL is actuated by over- cui-rent relay 5 lN/STL (also located

on Board F) with a

cui-rent transformer

on the neutral of the SSST. The 86/ST is actuated by the differential

relay 87/ST (also located in Board F) with cui-rent transformers located

in the Non-Critical Switchgear

Room. Discussion

of Fire Induced

Unintentional

LOOP A Control Rooin fire

originating

at either Vertical Board F or Board C could cause a LOOP due to control circuit faults.

Tlie following is a discussion

of the fire damage scenario needed

to result in a LOOP. Postulated Control Rooin

Fire on Vertical Board F

or Board C: In order to cause 4160 VAC busses

A, B, F and G

to de-energize

due to a fire under Board C

in the control room, the following actions must

be caused by the fire before the control room staff

pull the fiises as part of the alternate shutdown

procedure.

These actions can either

be caused by a fire a Board C

or Vertical Board F but the result

of the fire must cause

damage that results

in the following conditions:

1. The fire would have

to cause the breakers 1AS and lBS, the breakers that close to supply buses 1A and 1B froin the SSST, to fail such that a trip signal

would be present. 2. The fire would have

to cause the wires for

breakers 1FS and IGS, the breakers that close

to supply the buses 1F and

1G froin the

ESST, to fail such that a trip signal

would be present.

3. The fire would have to cause the

wires for breakers 1 FE and 1 GE, the breakers that close

to supply the buses from the DGs, to fail such that a trip signal

would be present. Page D4 of D6

All of the above failures would have

to occur or the under-voltage protection scheme at CNS

would cause the loads to be transferred

to the next source. The under-voltage scheme

only transfers loads

in one direction, thus once

the loads are transferred

from the SSST, the under- voltage protection scheme would not cause

the loads to be loaded back onto the SSST if it becomes available.

This latter transfer

would be a manual action only. These breakers

could be manually reset

from the Essential Switchgear

Room once the trip signal is removed.

The trip signal could

be removed by the fire causing a short

in the control wiring

that would cause the Control Power Transformer fuses

to blow or pulling these fuses at the breakers 1FS

and/or 1GS and close the breakers manually.

The switches on Board C where

the above control wires are teiininated for division

I breakers are located between

3 to 5 feet from

the corresponding

Division I1 switches on Board C in the control room.

The fire would have

to damage both switch groups and/or corresponding

wire bundles in the manner described above

in order to initiate

a LOOP. The 86 and 87 relays are located on Vertical Board

F. The four 86

lockout relays open the 4160 VAC tie breakers from

the SSST and ESST in the event

of either a high transfoiiner pressure

or a neutral over-current.

The four relays are

in close proximity

to each other and could conceivably be involved

in a single fire.

One of these four relays controls

the tie breakers from the ESST and the other

three control the tie breakers from the SSST. For a fire to isolate all of

the offsite power, it must involve the 86 relay for the ESST and at least one of the relays for the

SSST. The fire must cause

hot shorts that energize the 86

relay coils for all four tie breakers before

any shorts to ground occur that

blow the power supply fuses to these relays. Fire Induced Intentional LOOP For postulated fires

that could impair the ability

of the operators

to control the plant froin

the control room, CNS procedure 5.4FIRE-SD direct

the operators

to isolate offsite power, and then

supply power to the plant with DG2. Consequently, the LOOP is administratively induced and leaves the plant

in a configuration

where Division I1 equipment is controlled from the

ASD panel (Div I equipment cannot

be controlled

from the ASD panel.) These postulated fire initiators are

1) fire in the cable spreading room (zone 9A), 2) a fire in

the cable expansion

room (zone 9B), 3) a fire in the

auxiliaiy relay rooin (zone 8A), 4) a fire in each of the remaining

35 control rooin panels, and 5) a fire

in the NE corner of the Reactor Building (zone

2N2C). If DG2 fails

and cannot be recovered, the operations

shift manager (SM) may determine

that offsite power is available

and restoration

is needed. The ERO can then direct offsite power

recovery using simple breaker operations combined

with removing fuses. If needed, the NPPD Distribution Control Center

located at Doniphan

can operate 16 lkV switchyard breakers 1604

or 1606 to restore power

to the SSST. CNS IPEEE Internal Fire Analysis The CNS IPEEE Internal Fire Analysis addressed

the above fire zones.

The results of that analysis are summarized in

the following

table. These sequences

are limited to those that result in the potential for control

rooin evacuation

and induced plant centered LOOP.

The screening values are the reported screening frequencies in the IPEEE adjusted

for the condition exposure

Page D5 of D6

time. This time was determined

by taking the tiine

fioin plant starhip from the refueling

outage to the DG2 failure (56 days). Fire Location Cable &reading Room

Table 1. Adjusted screening

value 6.3 1E-8 See Note 2 Auxiliary Relay

Room NE Corner of RX Building Control Room Vertical Board F Control Room Board C I Cable ExDansion

Room I 2.65E-8 See Note 2 I 2.81E-8 See Note 2 6.26E-8 See

Note 1, 2 1.28E-7 See Note 2 4.3 1E-8 See Note

2 I Control Room All Other Panels

I 6.86E-8 See Note 2 Notes: 1. Value for the 903 '-6" Rx Building Elevation that includes

the NE corner; however, only the contribution

from NE corner requires controlling

the plant from the ASD. 2. Since the recovery

of offsite AC power in each of these sequences does not involve a

repair, can be performed

from within the plant, and

has significant procedural guidance, a non-recovery probability

of 5E-1 is estimated and applied

to each sequence.

Table 1 lists the applicable results

for the base case, including various

DG2 failure inodes

and illustrates

the order of magnitude

importance

for areas that include induced

LOOP sequences.

The ICCDP for fire would essentially be

the sum of the additional cutsets formed

by replacing

the DG2 failure events

with the voltage control board failure event, and the normal

DG non- recovery with

the specific non-recovery

of a failed voltage control board. The

cutset multiplier to

estimate this replacement

would be just slightly over 1 .O and would result

in an ICCDP of much less than 1E-6. Page D6 of D6

APPENDIX E

TIME WEIGHTED LOSP RECOVERIES

FOR SBO SEQUENCES

1. OBJECTIVE

The purpose of this calculation file is

to update of the offsite power

recovery failure probability for the Cooper PRA. It also documents

the calculation

of time-weighted offsite power recovery failure factors for application

in SBO sequences

in which diesel

generators

i-un for a period of time before the

SBO occurs. 2. INPUTS AND REFERENCES

The following inputs and references

were used to generate offsite

power recovery:

1. NUREG CR 6890, Reevaluation

of Station Blackout

Risk at Nuclear

Power plants, published December, 2005 3. DEFINITIONS

Time-weighted

LOSP Recovery:

This represents

the average offsite

power recovery failure probability assuming temporary

operation of the EDG

after loss of offsite

power. 4. ASSUMPTIONS Offsite Power

Recovery 1. General industry loss

of offsite power data

as reported in References

1 are considered

to be applicable

to Cooper. Loss

of offsite power events at other

nuclear power plants documented

in these references could

also occur at Cooper

due to the similarity in the

design of their power grid. Pooling all applicable events would provide a better estimate

of the offsite

power recoveiy failure probability

as a fiinction of time than

relying simply on data for Cooper. Recovery Time 1. Refer to Appendix A

for discussions

of batteiy depletion times

5. ANALYSIS Method Einployed and Suminailr

of Results The analysis is performed

in two steps: Derive offsite power recoveiy failure probability

as a fiinction of time for

three conditions

Plant centered loss

of offsite power Grid centered loss

of offsite power

Page El of E9

Weather related loss of offsite power Develop a time

weighted offsite power recovery factor

to account for the possibility that a diesel generator

may run for a period

of time before a station blackout occurs. Successful diesel operation, even if temporarily, can provide additional time to recover offsite power. Offsite Power Recovery

The methodology used here develops a discrete probability profile generated from

compilation of loss of offsite power durations which is then fit to a continuous distribution fiinction using least-square curve fit.

The data used

in this analysis was collected

by the NRC [References

11. The loss of offsite power events were used to form the inputs

for deriving the discrete offsite power failure recovery probability.

Time Weighted Offsite Power Recovery Factor:

The Cooper station blackout (SBO) sequences consider seven different means

of reaching core damage. Extended RCIC Success (Case

1) - Modeled recovery of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> RCIC Success (Case 2) - Modeled recovery of 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> Extended HPCI Success (Case

3) - Modeled recovery of 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> HPCI Success (Case

4) - Modeled recoveiy of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> One SORV, RCIC Success (Case

5) - Modeled recovery

of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Two SORV (Case

6) - Modeled recovery

of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Injection Failure (Case

7) - Modeled recovery of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> For the above scenarios, the

current SBO accident sequences are quantified

as though the SBO event occurs at

the time of the loss of offsite power event (time

= 0). This assumption

is considered conservative

from an offsite power recovery standpoint given that

one or both EDGs may be available for a while

to provide support for operation of AC powered accident mitigating systems.

Temporary

operation

of an EDG would allow inore time for operators

to recover offsite power

and thus would reduce the

SBO CDF. Explicitly accounting for the SBO scenarios where the EDG(s) runs temporarily requires integration of the run failure rate and the offsite power recovery probability over the mission time

of the accident sequence.

A discrete approximation to this integration

can be performed

by breaking out the original 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> EDG mission

time into equal run time segments (1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> segments) with corresponding

EDG failure probabilities. Since offsite

power is lost at time zero, the latest time to recover power increases

by an hour for each succeeding EDG successful run segment. Correspondingly, with

each succeeding

hour that the SBO event is delayed, the offsite power

recoveiy failure probability would decrease.

The event tree shown in Figure 5-1 illustrates

the EDG run scenarios

to be quantified

to obtain a time-weighted offsite power

recovery failure probability for the extended

RCIC success sequences.

Page E2 of E14

ct, = Pt, / Plosp,o PtW = Averaged offsite power recovery factor

Ch,, = Time Weighted Correction Factor

Page E3 of E14

Figure 5-1 : EDG Time Dependent

Loss of Offsite Power

Event Tree (Plant Centered)

Plant Centererl

0 EDG Run Time-Segment

(1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />) Must Case

0 1 2 4 5 6 7

8 Recv 1 Bat -------- - - - - - - - - - - - - - -- OSP Depl 12 3 5 6 7 8 9 10 11 12131415161718192021222324 9 10 11 12 13 14 15 16 17 18 192021 22 23 Seq byhr PLOSP 1 I- .) I -11 P :: 16 17 18 19 20 dI 24 I EDG I FTS *Time weighted recovery(Ptw)

= SUM(recoveries over 24 hr)/24 **Correction Factor (Ctw) = Time weighted recovery/FTS

OSP fail to recover 24 23

22 21 20 19

18 17 16 15 14 13 P( 12h) 0.004 0.005 0.005 0.006 0.007 0.008 0.091 0.010 0.012 0.014 0.0 17 0.020 = 0.024 SUM 0.199 Period 24

'Ptw 0.008 **ch 0.345 The time weighted correction

factor would be applied

to SBO accident sequence cut sets in which a diesel fail to run

basic event occurred.

Analysis Page E4 of E9

Using the methods described in

the preceding section, this section presents the derivation of the probability

of failure to recover offsite

power as a fiinction

of time. As explained

in Section 5.1, offsite power recovery

factors are initially applied

in the PRA as though the station blackout occurred at

time zero. In fact, a portion

of the station blackout accident sequences may have an emergency diesel generator available

as a power source for a short period

of time before the blackout occurs.

These diesel generator failure

to run sequences actually have a

longer period of time for operators

to recover offsite power than those sequences

in which both offsite power and the

diesels are lost at the LOSP event. Tables 5-1 through 5-3 below coinpile the offsite

power recovery failure

as a function of

the available recoveiy

times for diesel generator failure

to mn sequences for each of the three LOSP event categories (plant centered, grid

centered, weather related).

The first coluinn

represents

the sequence in the event tree

shown in Figure

5-1. The second coluinn is the time at which it is assumed that the last diesel generator

fails to run following the loss of offsite power

initiator.

The coluinns labeled "AC Recovery Required" represent the time at which core damage

is assumed and

the associated offsite power

recovery failure probability (PLosp

iJ. The offsite power recoveiy

factor as a fiinction

of time (Plosp-i)

is calculated

as illustrated

in Figure 5-1 for all seven cases. Since offsite power recovery failure for the

three SBO scenarios are represented

by point values

in the accident sequence quantification, it is necessary

to obtain representative average values

for sequences

in which a diesel fail

to run occurs. The average values

are time-weighted

on the EDG i-un cases and are calculated by the following equation.

Equation 4 Where: Ptw = Time weighted

loss of offsite power recovery factor

Ch,. = Time weighted loss

of offsite power recovery correction factor (normalized

to recovery assuming blackout conditions at

t=O) Plosp - i = Probability

of offsite power

recovery failure by time segment i

Plosp~~s = Probability

of offsite power

recovery failure assumes

EDG fails at t=O tl = Recovery time (Case specific)

t2 = EDG mn mission time (24 hr) For example, for battery depletion scenarios, accident sequence quantification is perfoiined

assuming a failure

to recover offsite power probability

at 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. The time weighted correction factor Ch,, is calculated

by averaging offsite

power recovery failure over the

9 hour1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br /> to 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> time frame and

noiinalizing

to the recovery failure probability at

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. For any cut set

Page E5 of E14

containing

an EDG fail to nm event, the time weighted

coi-rection

factor (C,,) is applied as

a recovery factor.

This approach to SBO accident sequence quantification

assuines that the EDG mission time is set to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> for

all accident sequences.

Page E6 of E14

2 w 4. 0 M w a, a 2 I1

2 W cr 0 m W

The above tables derive

conditional

time weighted recovery factors

for the CNS PRA model

and were used to derive

values in Table 2.2.2-1 Because the CNS model combines plant centered

and switchyard

centered events into one initiator with recoveries, no specific switchyard recovery factors

are provided.

A separate analysis, specific

to Cooper Nuclear Station, was performed

to provide recovery

factors for switchyard centered events.

This is reflected in

the following

4 tables (5.4 through 5.7). The recovery factors in

Tables 5.4 through 5.7 are provided

to allow other analyst

the option to apply recovery time weighted factors should

the analyst's

PRA model separate

the switchyard

centered LOSP recoveries

from the plant centered

LOSP recoveries.

Page E10 of E14

2 c! W rcr 0 W e, M cd a

c d W r, 0 m W c al 3 a