Text
EDO Principal Correspondence Control FROM: DUE: / /EDO CONTROL: G20090108 DOC DT: 02/03/09 FINAL REPLY: Congressman John H. Adler Congressman Frank A. LoBiondo Congressman Rush Holt TO: Chairman Klein FOR SIGNATURE OF :** GRN **CRC NO: 09-0037 Borchardt, EDO DESC: ROUTING: Postponement of Commission Decision on Relicensing of the Oyster Creek Nuclear Generating Station (EDATS: SECY-2009-0084)
DATE: 03/03/09 Borchardt Virgilio Mallett Ash Ordaz Cyr/Burns Schmidt, OCA Cyr, OGC Collins, RI Shoop, OEDO Trocine, OEDO ASSIGNED TO: NRR CONTACT: Leeds SPECIAL INSTRUCTIONS OR REMARKS: For Appropriate Action.Coordinate with OGC to determine if a response is necessary.
If a response is written, create an individual letter for each Congressman for EDO signature.
~iQ -~2 tEýý eAJ2ýý --SEýcq -0 ý EDATS Number: SECY-2009-0084 Source: SECY Geea Ifraio Assigned To: NRR OEDO Due Date: NONE Other Assignees:
SECY Due Date: NONE
Subject:
Postponement of Commission Decision on Relicensing of the Oyster Creek Nuclear Generating Station
Description:
CC Routing: OGC ADAMS Accession Numbers -Incoming:
NONE Response/Package:
NONE I Ote Infrmaio Cross Reference Number: G20090108, LTR-09-0037 Related Task: File Routing: EDATS Staff Initiated:
NO Recurring Item: NO Agency Lesson Learned: NO Roadmap Item: NO ArctssIonfType:appropraeAtonrirt:Mdu Action Type: Appropriate Action Priority:
Mediun Sensitivity:
None Signature Level: EDO Urgenc OEDO Concurrence:
NO OCM Concurrence:
NO OCA Concurrence:
NO Special Instructions:
For Appropriate Action. Coordinate with OGC to determine if a response is necessary.
If a response is written, create an individual letter for each Congressman for EDO signature.
y: NO Doumn Infomaio Originator Name: John H. Adler, Frank A. LoBiondo, and Date of Incoming:
2/3/2009 Rush Holt Originating Organization:
Congress Document Received by SECY Date: 2/3/2009 Addressee:
Chairman Klein Date Response Requested by Originator:
NONE Incoming Task Received:
Letter Page 1 of l OFFICE OF THE SECRETARY CORRESPONDENCE CONTROL TICKET Date Printed: Mar 03, 2009 15:47 PAPER NUMBER: ACTION OFFICE: LTR-09-0037 EDO LOGGING DATE: 02/04/2009 AUTHOR: AFFILIATION:
ADDRESSEE:
SUBJECT:
ACTION: DISTRIBUTION:
LETTER DATE: ACKNOWLEDGED SPECIAL HANDLING: NOTES: FILE LOCATION: REP John Adler CONG CHRM Dale Klein Request the Commission postpone its decision on relicensing of the Oyster Creek Nuclear Geneating Statioin Appropriate RF, OCA, Chairman, Comrs 02/03/2009 No Ex Parte response to Rep Adler signed by Annette Vietti-Cook 03/03/2009 (copy attached)ADAMS DATE DUE: DATE SIGNED: EDO --G20090108 JOHN H. ADLER 1223 LONGWORTH HOusE OFFICE BUILoING 1202) 2215-4765 3D DISTRICT, NEW JERSEY Togmi.e of ?glni i5-311113 February 3, 2009 The Honorable Dale E. Klein Chairman U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
Dear Chairman Klein:
We understand that the Nuclear Regulatory Commission has tentatively scheduled an affirmation session on February 4, 2009 on the relicensing of the Oyster Creek Nuclear Generating Station. We are writing to request the Commission postpone its decision on relicensing until recommendations by two NRC advisory boards are further reviewed and appropriate measures are taken to avert future drywell corrosion.
One issue concerns certain recommendations issued by the Atomic Committee on Reactor Safety (ACRS) and the Atomic Safety Licensing Board (ASLB). l'he Commission cannot be sure whether Oyster Creek meets current safety requirements unless these recommendations, which are designed to enhance public safety,.have been fully reviewed.
We therefore request the Commission to ensure that NRC Staff and Exelon implement necessary and appropriate recommendations set forth by the ASLB and the ACRS.In addition, we are aware of Citizen's notification to the NRC regarding'the staff inspection report released on January 19, 2009 and the report itself. The report appears to indicate that water continues to seep into the drywell and is causing ongoing corrosion.
Therefore, we ask the Commission to take appropriate steps to monitor for water and prevent water leaks.Finally, in an effort to ensure the public has adequate'information pertaining to the Oyster Creek relicensing, we ask that appropriate additional materials be made available to the public for independent review and that you encourage NRC staff to work more closely with citizens groups (and their representatives) that are interested in improving safety at Oyster Creek.We recognize the crucial role nuclear power plays in meeting America's ongoing energy needs. Oyster Creek, however, faces a unique set of circumstances that warrants an abundance of caution. We believe that the NRC should delay a final decision concerning relicensing until the issues set forth in this letter are addressed.
Should any renewal be granted, we expect the NRC to monitor corrosion in the facility's drywell and ensure the timely implementation of appropriate ASLB and ACRS recommendations.
PRINTED ON RECYCLED PAPER Sincerely, John H. tde'r Member of Congress tankA. LoBiondo Member of Congress Rush Holt Member of Congress 7 SEC UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 3, 2009 RETARY The Honorable John H. Adler United States House of Representatives Washington, D.C. 20515 Dear Congressman Adler: I am responding to your letter dated February 3, 2009, in which you requested that the Commission postpone an affirmation session that was tentatively scheduled for February 4, 2009, in connection with adjudicatory matters pending before the Commission with respect to the license renewal application for the Oyster Creek Nuclear Generating Station (Oyster Creek).Among other things, you requested that the Commission postpone its decision on the license renewal application until the NRC Staff and Exelon implement recommendations made by the Advisory Committee on Reactor Safeguards and the Atomic Safety and Licensing Board. You also requested that NRC staff take specific action based upon a recent NRC inspection report relevant to the Oyster Creek drywell liner, that NRC staff work more closely with citizens groups (and their representatives), and that additional information be made available to the public pertaining to the Oyster Creek license renewal application.
The Commission postponed the affirmation session that was tentatively scheduled for February 4, and the Oyster Creek license renewal matter remains under consideration by the Commission.
Under Commission regulations, the Commission has an adjudicatory role in the Oyster Creek license renewal proceeding.
An appeal is currently pending before the Commission with respect to the license renewal application.
Due to the nature of the Commission's role, all members of the Commission must remain impartial while the case is pending. At this time, therefore, the Commission cannot discuss or comment on issues.involved in this matter, including those raised in your letter. The Commission may, however, always discuss the status of the proceeding and the performance of the facility generally.
I am referring your letter to the Office of Nuclear Reactor Regulation, which is responsible for reviewing the Oyster Creek license renewal application.
A copy of your letter and this response will be served on the participants in the Oyster Creek proceeding.
Sincerely,/ F Annette L. Vietti-Cook cc: Congressman Frank A. LoBiondo Congressman Rush Holt Oyster Creek Service List