Letter Sequence RAI |
|---|
TAC:ME0274, Steam Generator Tube Integrity (Approved, Closed) |
Results
Other: 3F0111-04, Comments on the Safety Evaluation Report with Open Items Related to the License Renewal and Amendment 18, 3F0412-03, Revised Commitment for the Reactor Vessel Internals Aging Management Program for License Renewal and License Renewal Application Amendment 24, 3F1208-02, Systems Drawings Supporting License Renewal, 3F1209-06, License Renewal Application 10 CFR Part 54.21(b) Annual Update, 3F1211-01, License Renewal Application 10 CFR Part 54.21(b), Annual Update, 3F1212-01, License Renewal Application 10 CFR Part 54.21(b) Annual Update, ML090090233, ML090210171, ML091200415, ML091660559, ML091820465, ML092600889, ML092610309, ML093200023, ML100050166, ML110410597, ML11137A009, ML12213A058
|
MONTHYEAR3F1208-02, Systems Drawings Supporting License Renewal2008-12-16016 December 2008 Systems Drawings Supporting License Renewal Project stage: Other ML0900902332009-02-27027 February 2009 Determination of Acceptability and Sufficiency for Docketing, and Opportunity for a Hearing Regarding the Application from Florida Power Corp., for Renewal of the Operating License for Crystal River Unit 3 Nuclear Generating Plant Project stage: Other ML0902101712009-02-27027 February 2009 Notice of Opportunity for Hearing Regarding Renewal of Facility Operating License No. DPR-72 for an Additional 20-year Period Florida Power Corporation Corporation Crystal River Unit 3 Nuclear Generating Plant Docket No. 50-302 Project stage: Other ML0908501762009-04-20020 April 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI 3F0509-01, Response to Request for Additional Information for the Review of the License Renewal Application2009-05-11011 May 2009 Response to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI ML0912004152009-05-22022 May 2009 Proposed Review Schedule Regarding the Application from Florida Power Corporation for Renewal of the Operating License for Crystal River Unit 3 Nuclear Generating Plant Project stage: Other 3F0509-07, License Amendment Request 303, Revision 1, Supplement 1: Revision to Final Safety Analysis Report Sections 5.4.3, Structural Design Criteria, and 5.4.5.3, Missile Analysis, Response to Request for Additional Information2009-05-22022 May 2009 License Amendment Request 303, Revision 1, Supplement 1: Revision to Final Safety Analysis Report Sections 5.4.3, Structural Design Criteria, and 5.4.5.3, Missile Analysis, Response to Request for Additional Information Project stage: Supplement ML0918204652009-07-0808 July 2009 Plan for the Aging Management Program Regulatory Audit Regarding the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Review Project stage: Other ML0916605592009-07-30030 July 2009 Audit Report Regarding the LRA for the Crystal River, Unit 3 Project stage: Other ML0917400702009-08-0303 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0920800452009-08-14014 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI ML0920302082009-08-14014 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0922507012009-08-20020 August 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0920200122009-08-20020 August 2009 RAI, License Renewal Application Project stage: RAI ML0923303432009-08-31031 August 2009 Nuclear Generating Plant, RAI, License Renewal Application Project stage: RAI ML0923308312009-08-31031 August 2009 Request for Additional Information Regarding License Renewal Application Project stage: RAI ML0923300072009-08-31031 August 2009 RAI for the Review of the Crystal River Unit 3 Nuclear Generating Plant, LRA Project stage: RAI ML0923309042009-09-0202 September 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI 3F0909-02, Response to Request for Additional Information for the Review of the License Renewal Application2009-09-11011 September 2009 Response to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI ML0926008892009-09-11011 September 2009 Areva Np, Inc., 51-9057252-001, Rev. 1, CR3 Reconciliation of 60-Year Fluence Projections Used in Reactor Vessel Beltline Embrittlement Calculations for License Renewal, Enclosure Attachment 3 Project stage: Other ML0921602132009-09-11011 September 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI 3F0909-03, Response to Requests for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application (TAC No. ME0274) and Amendment 22009-09-11011 September 2009 Response to Requests for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application (TAC No. ME0274) and Amendment 2 Project stage: Response to RAI 3F0909-04, Response to Requests for Additional Information for the Review of the License Renewal Application and Amendment 32009-09-18018 September 2009 Response to Requests for Additional Information for the Review of the License Renewal Application and Amendment 3 Project stage: Response to RAI ML0923706692009-09-22022 September 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Unit Plant, License Renewal Application Project stage: RAI ML0926103092009-09-29029 September 2009 Scoping and Screening Audit Report Regarding the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: Other 3F0909-06, Response to Requests for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application (TAC ME0274) and Amendment 42009-09-30030 September 2009 Response to Requests for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application (TAC ME0274) and Amendment 4 Project stage: Response to RAI 3F1009-06, Response to Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application (TAC No. ME0274) - Sections B.2.37-1, 3.3.2.2, and XI.S82009-10-0202 October 2009 Response to Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application (TAC No. ME0274) - Sections B.2.37-1, 3.3.2.2, and XI.S8 Project stage: Response to RAI 3F1009-07, Response to Request for Additional Information for the Review of Unit 3 Nuclear Generating Plant License Renewal Application and Amendment 52009-10-13013 October 2009 Response to Request for Additional Information for the Review of Unit 3 Nuclear Generating Plant License Renewal Application and Amendment 5 Project stage: Response to RAI ML0926405542009-10-15015 October 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI 3F1009-08, Response to Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application (TAC No. ME0274) - and Amendment 62009-10-22022 October 2009 Response to Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application (TAC No. ME0274) - and Amendment 6 Project stage: Response to RAI ML0929606602009-10-27027 October 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML0929403222009-11-0303 November 2009 Request for Additional Information for the Review of the Crystal River, Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI 3F1109-05, Response to Request for Additional Information for Review of License Renewal Application, Section 2.32009-11-12012 November 2009 Response to Request for Additional Information for Review of License Renewal Application, Section 2.3 Project stage: Response to RAI ML0932305592009-11-30030 November 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application Project stage: RAI ML0930301472009-12-0101 December 2009 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Review Application Project stage: RAI 3F1209-03, Response to Request for Additional Information for the Review of the License Renewal Application2009-12-0303 December 2009 Response to Request for Additional Information for the Review of the License Renewal Application Project stage: Response to RAI ML0932704962009-12-10010 December 2009 Areva Np, Inc. - Request for Withholding Information from Public Disclosure for Crystal River Unit 3 Nuclear Generating Plant Project stage: Withholding Request Acceptance ML0933102952009-12-10010 December 2009 Areva Np, Inc.- Request for Withholding Information from Public Disclosure for Crystal River Unit 3 Nuclear Generating Plant Project stage: Withholding Request Acceptance 3F1209-06, License Renewal Application 10 CFR Part 54.21(b) Annual Update2009-12-14014 December 2009 License Renewal Application 10 CFR Part 54.21(b) Annual Update Project stage: Other ML0932000232009-12-14014 December 2009 AMP Audit Report Regarding the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: Other 3F1209-11, 10 CFR 50.46 Loss-of-Coolant Accident Evaluation Model Change and Peak Cladding Temperature Change Report2009-12-16016 December 2009 10 CFR 50.46 Loss-of-Coolant Accident Evaluation Model Change and Peak Cladding Temperature Change Report Project stage: Request 3F1209-12, Response to Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application (TAC No. ME0274) and Amendment 82009-12-30030 December 2009 Response to Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application (TAC No. ME0274) and Amendment 8 Project stage: Response to RAI ML1000501662010-01-25025 January 2010 Revised Review Schedule Regarding the Application from Florida Power Corporation for Renewal of the Operating License for Crystal River Unit 3 Nuclear Generating Plant Project stage: Other 3F0110-04, Response to Request for Additional Information for the Review of the License Renewal Application & Amendment 92010-01-27027 January 2010 Response to Request for Additional Information for the Review of the License Renewal Application & Amendment 9 Project stage: Response to RAI ML1001000102010-02-0202 February 2010 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI 3F0310-01, Response to Request for Additional Information for Review of License Renewal Application and Amendment 102010-03-0303 March 2010 Response to Request for Additional Information for Review of License Renewal Application and Amendment 10 Project stage: Response to RAI ML1011302232010-05-21021 May 2010 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI ML1014105122010-06-0202 June 2010 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI 3F0610-02, Response to Requests for Additional Information for the Review of License Renewal Application (TAC No. ME0274) and Amendment 112010-06-21021 June 2010 Response to Requests for Additional Information for the Review of License Renewal Application (TAC No. ME0274) and Amendment 11 Project stage: Response to RAI ML1017404972010-07-0808 July 2010 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application Project stage: RAI 2009-07-30
[Table View] |
Text
August 20, 2009 Mr. Jon Franke, Vice President Crystal River Nuclear Plant (NA1B) ATTN: Supervisor, Licensing & Regulatory Programs 15760 W. Power Line Street Crystal River, FL 34428-6708
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT, LICENSE RENEWAL APPLICATION (TAC NO. ME0274)
Dear Mr. Franke:
By letter dated December 16, 2008, Florida Power Corporation submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses Crystal River Unit 3 Nuclear Generating Plant (CR-3), for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review. Further requests for additional information may be issued in the future. Items in the enclosure were discussed with Mr. Michael Heath, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-3733 or by e-mail robert.kuntz@nrc.gov. Sincerely, /RA/
Robert F. Kuntz, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302
Enclosure:
As stated cc w/encl: See next page
ML092250701 OFFICE PM:RPB2:DLR LA:DLR BC:RER2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME RKuntz SFigueroa RAuluck DWrona RKuntz DATE 08/18/09 08/18/09 08/19/09 08/20/09 08/20/09 REQUEST FOR ADDITIONAL INFORMATION LICENSE RENEWAL APPLICATION FOR CRYSTAL RIVER UNIT 3 DOCKET NO: 50-302 (TAC NO. ME0274)
RAI 2.1-1
Background
10 CFR 54.4(a)(1) requires that safety-related systems, structures, and components required to be within the scope of license renewal are those which are relied upon to remain functional during and following design basis events to ensure (i) the integrity of the reactor coolant pressure boundary; (ii) the capability to shut down the reactor and maintain it in a safe shutdown condition; or (iii) the capability to prevent or mitigate the consequences of accidents which could result in potential offsite exposures comparable to those referred to in 10 CFR 50.34(a)(1), 50.67(b)(2), or 100.11. During the scoping and screening methodology audit, performed June 23-25, 2009, the staff reviewed the applicant's implementing documents and reports relative to the evaluation of safety-related SSC's for inclusion within the scope of license renewal.
Issue The staff determined that there were components identified as safety-related in the equipment data base which were not included within the scope for license renewal in accordance with 10 CFR 54.4(a)(1) as follows:
- As discussed in implementing documents and reports, the applicant had identified SSC's located in the turbine building that were designated as safety-related in the equipment database but were evaluated and determined to not meet the criteria of 10 CFR 54.4(a)(1). In addition, certain SSC's are connected to safety-related cables attached to safety-related buses.
- As discussed in implementing documents and reports, safety-related supports are attached to a common wall between the turbine building and the intermediate building, and located within the turbine building space. However, although the supports are physically located within the turbine building, they have been evaluated as a portion of the intermediate building.
Request The staff requests that the applicant provide the basis for not including the safety-related SSC's and supports, located within the turbine building, in accordance with 10 CFR 54.4(a)(1), and, as applicable, for not performing an evaluation of nonsafety-related SSC's, located within the same space, for inclusion within the scope of license in accordance with 10 CFR 54.4(a)(2).
List any additional SSCs which were included within the scope of license renewal as a result of your review performed in response to this RAI and list those structures and components for which aging management reviews were conducted. For each additional structure and component, describe the aging management programs, as applicable, to be credited for managing the identified aging effects.
RAI 2.1-2
=
Background===
10 CFR 54.4(a)(2) requires that nonsafety-related SSC's whose failure could prevent satisfactory accomplishment of functions identified in 10 CFR 54.4(a)(1) be included within the scope of license renewal. During the scoping and screening methodology audit, performed June 23-25, 2009, the staff reviewed the applicant's implementing documents and reports relative to the evaluation of nonsafety-related SSC's for inclusion within the scope of license renewal. Issue The staff was not able to determine that nonsafety-related pipe, attached to safety-related SSC's and extending beyond the space or structure containing the nonsafety-related/safety-related interface, was included within the scope of license renewal up to, and including, an anchor, equivalent anchor or bounding condition.
Request The staff requests that the applicant provide a discussion on the methodology used to determine the portion of nonsafety-related pipe, attached to safety-related SSC's, where the nonsafety-related pipe extends beyond the space or structure containing the nonsafety-related/safety-related interface, to be included within the scope of license renewal in accordance with 10 CFR 54.4(a)(2). In addition, provide a discussion on the use of anchors, equivalent anchors and bounding conditions used as the boundary for nonsafety-related pipe, attached to safety-related SSC's, included within the scope of license renewal.
Issue The staff determined that the applicant had performed an evaluation to not include fluid filled nonsafety-related SSC's located in specific portions of structures, which also contained safety-related SSC's, within the scope of license renewal. This evaluation identified approximately five areas located in the auxiliary building which contained low or moderate energy fluid-filled nonsafety-related SSCs in addition to safety-related pipe or cables and connectors (which had been included within the scope of license renewal in accordance with 10 CFR 54.4(a)(1)). However, the low or moderate energy fluid-filled nonsafety-related SSC's had not been included within the scope of license renewal in accordance with 10 CFR 54.4(a)(2).
Request The staff requests that the applicant provide the basis for not including fluid-filled nonsafety-related SSC's, located in the same space as safety-related SSC's, within the scope of license renewal in accordance with 10 CFR 54.4(a)(2).
Issue The staff identified several open penetrations in a wall connecting the turbine building to the intermediate building. The staff was not able to determine if the applicant had performed an evaluation to identify the potential effect of the failure of nonsafety-related SSC's located in the turbine building on safety-related SSC's located in the intermediate building.
Request The staff requests that the applicant provide the basis for not including fluid-filled nonsafety-related SSC's, located in the turbine building, which have the potential to interact with safety-related SSC's located within the intermediate building, within the scope of license renewal in accordance with 10 CFR 54.4(a)(2).
List any additional SSCs which were included within the scope of license renewal as a result of your review performed in response to this RAI and list those structures and components for which aging management reviews were conducted. For each additional structure and component, describe the aging management programs, as applicable, to be credited for managing the identified aging effects.
Letter to J. Franke from R. Kuntz, dated August 20, 2009 DISTRIBUTION:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT, LICENSE RENEWAL APPLICATION (TAC NO. ME0274)
HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter _ _ _ _ _ _ _ _
RKuntz DBrittner AJones, OGC LLake, RII MSykes, RII TMorrissey, RII RReyes, RI
Crystal River Nuclear Generating Plant, Unit 3 cc: Mr. R. Alexander Glenn Associate General Counsel (MAC-BT15A) Florida Power Corporation P.O. Box 14042 St. Petersburg, FL 33733-4042
Mr. James W. Holt Plant General Manager Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, FL 34428-6708 Mr. William A. Passetti, Chief Department of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin #C21 Tallahassee, FL 32399-1741
Attorney General Department of Legal Affairs The Capitol Tallahassee, FL 32304
Mr. Ruben D. Almaluer, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, FL 32399-2100
Chairman Board of County Commissioners Citrus County 110 North Apopka Avenue Inverness, FL 34450-4245 Mr. Stephen J. Cahill Engineering Manager Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, FL 34428-6708
Mr. Daniel R. Westcott Supervisor, Licensing & Regulatory Programs Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428-6708 Mr. Jon A. Franke, Vice President Crystal River Nuclear Plant (NA1B)
ATTN: Supervisor, Licensing & Regulator Programs 15760 W. Power Line Street Crystal River, FL 34428-6708
Senior Resident Inspector Crystal River Unit 3 U.S. Nuclear Regulatory Commission 6745 N. Tallahassee Road Crystal River, FL 34428 Ms. Phyllis Dixon Manager, Nuclear Assessment Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, FL 34428-6708
Mr. David T. Conley Associate General Counsel II - Legal Dept. Progress Energy Service Company, LLC Post Office Box 1551 Raleigh, NC 27602-1551
Mr. Daniel L. Roderick Vice President, Nuclear Projects & Construction Crystal River Nuclear Plant (SA2C) 15760 W. Power Line Street Crystal River, FL 34428-6708 Mr. Mark Rigsby Manager, Support Services - Nuclear Crystal River Nuclear Plant (SA2C) 15760 W. Power Line Street Crystal River, FL 34428-6708 Mr. Robert J. Duncan II Vice President, Nuclear Operations Progress Energy Post Office Box 1551 Raleigh, NC 27602-1551 Mr. Brian C. McCabe Manager, Nuclear Regulatory Affairs Progress Energy Post Office Box 1551 Raleigh, NC 27602-1551