ATWS Uet December 11, 2023 Pre-submittal Meeting Slides
ML23345A036
Person / Time
Site: Byron, Braidwood  Constellation icon.png
Issue date: 12/11/2023
From:
Constellation Energy Generation
To: Joel Wiebe
NRC/NRR/DORL/LPL3
Wiebe J
References
EPID L-2023-LRM-0099
Download: ML23345A036 (1)


Text

Braidwood and Byron ATWS UET December 11, 2023 Agenda

  • Purpose
  • Reason for the Change
  • Analyses and Preliminary Results
  • Defense in Depth
  • Key Milestones
  • Summary

2 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 Pu r p os e

  • To solicit feedback from the NRC on the information presented and gain insight on NRC's information needs and review schedule considerations.

3 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 License Amendment Request Scope

  • After implementing this change, the cycle specific limits and confirmations associated with COLR Reference 5.6.5.b.5 will no longer be applied by CEG. The Moderator Temperature Coefficient will continue to be limited by Technical Specification Figure 3.1.3-1 and will be confirmed to be acceptable with all other COLR references listed in Technical Specification 5.6.5.b.
  • After implementing the proposed change, Byron and Braidwood will continue to meet the ATWS Rule, 10 CFR 50.62, and continue to meet all other licensing basis commitments related to ATWS including those from NRC Generic Letter 83-28, Required Actions Based on Generic Implication of Salem ATWS Events.
  • The proposed change may result in core designs with higher Hot Full Power Critical Boron concentrations and less negative MTCs. The effects of those changes are within the limits of existing regulations and licensing bases.

4 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 Reason for the change

Fuel Cycle Length: CEG is evaluating 24 month cycles for Byron and Braidwood. The MTC limits for the longer cycles would significantly affect fuel cycle cost and feasibility.

Fuel Cycle Analytical Methods: The methodology prescribed by Technical Specification 5.6.5.b.5 is proprietary to Westinghouse, and CEG is pursuing alternative suppliers. The other fuel suppliers do not have this methodology or a practical alternative.

5 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 A n a l yse s

Informed Decisions on Plant-Specific Changes to the Licensing Basis.

  • The CEG PRA model is technically acceptable for the following applications
  • Risk Informed Completion Times
  • 50.69
  • Surveillance Frequency Control

6 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 Preliminary Results

C DF / C DF: 5 E-5 / 5 E-7

LERF / LERF: 2 E-6 / 2 E-10

7 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 Unfavorable Exposure Time (UET) in PRA

UET in Current Licensing Basis (Tech UET in CEG PRA:

Spec 5.6.3.b.5): MTC favorable (Y/N) with complex conditions based on MTC Favorable (<-8pcm/°F) (Y/N) o Rod Insertion {y, n }

2 Pressurizer PORVs o Aux Feedwater Trains {1,2}

2 Trains Auxiliary Feedwater o Pressurizer Safeties {3}

NO Auto or Manual Control Rod o Pressurizer PORVs {0,1,2}

Insertion The CEG Evaluation will determine The conditions above must the CDF and LERF between the demonstrate ATWS peak Pressure < current split fractions and 100% UET.

3200 psi for 95% of the fuel cycle.

Realistically, the UET is shifting from

< 5% to <50%

8 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 Large Early Release Frequency

  • Some studies (WCAP-15831-P-A, WOG Risk -Informed ATWS Assessment and Licensing Implementation Process, August, 2007) conservatively assumed that RCS overpressure >3584 psid would lead to a large early release.
  • CEG PRA does not automatically default to Large Early Release

9 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 Ini ti ati ng Eve nts Defense In Depth

A utomati c SCRA M Trai n A

- Hi gh P re ssuri ze r P re ssure A utomati c SCRA M Trai n B - Over Temperature Delta-T

- Low Steam Generator Level

Manual SCRA M Trai n A

- Unde rV ol tage Tri p

- Shunt Tri p

Manual SCRA M Trai n B

Automati c Rod Inse rti on

Favorabl e MTC

Manual Start Motor Dri v e n FW Pump

AMSAC

10 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 Proprietary

Key Milestones

  • Pre -Submittal Meeting - December 11, 2023
  • Expected Submittal Date - April 30, 2024
  • Requested Approval Date - June 30, 2025

11 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 Summary

  • MTC upper and lower limits for all other Design Basis events is unchanged.
  • ATWS rule commitments unchanged

12 Byron-Braidwood Fuel Transition Project - ATW S UET Pre-submittal Meeting 12/11/2023 Questions

13