Entergy Nuclear Operations, Inc.
SEntergy Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 July 2, 2008 Stephen J. Bethay Director, Nuclear Assessment U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Entergy Nuclear Operations, Inc Pilgrim Nuclear Power Station Docket No.: 50-293 License No.: DPR-35 Withdrawal of In-service Inspection (ISI) Pilgrim Relief Request No.
PRR-16, Implementation of BWRVIP Guidelines in lieu of ASME Section Xl Code Requirements on Reactor Vessel Internals and Components Inspection REFERENCE 1: Entergy Letter No. 2.08.008, Request for Approval of Pilgrim Relief Request No. PRR-16, Implementation of BWRVIP Guidelines in lieu of ASME Section Xl Code Requirements on Reactor Vessel Internals and Components Inspection, dated February 14, 2008 LETTER NUMBER: 2.08.037
Dear Sir or Madam:
Entergy submitted Pilgrim Relief Request, PRR-16 (Reference 1) for NRC approval to credit various examinations performed using the Boiling Water Reactor Vessel Internals Program (BWRVIP) guidelines in lieu of the American Society of Mechanical Engineers (ASME)Section XI Code inspection. requirements on reactor vessel internals and components.
Since then, Entergy has reviewed the Pilgrim reactor pressure vessel internal inspection plan for Refueling Outage 17 (RFO-17) and future outages, and has concluded that Entergy will continue to comply with the ASME-required examinations, irrespective of BWRVIP guidelines.
Therefore, Pilgrim withdraws PRR-1 6 at this time.
This withdrawal does not impact the ASME-required examinations of reactor vessel internal components.
Should you have any questions concerning this letter, please contact Pilgrim Licensing Manager, Mr. Joseph R. Lynch, at (508) 830-8403.
There are no new commitments made in this letter.
Sincerely, Steve J.
A r Director, Nuclear Safety Assessment WGL/dl AN9
Entergy Nuclear Operations, Inc. Letter Number: 2.08.037 Pilgrim Nuclear Power Station Page 2 cc: Mr. James S. Kim, Project Manager Plant Licensing Branch I-1 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission One White Flint North 4D9A 11555 Rockville Pike Rockville, MD 20852 Regional Administrator, Region 1 U.S. Nuclear Regulator Commission 475 Allendale Road King of Prussia, PA 19406 Senior Resident Inspector Pilgrim Nuclear Power Station