ML081120496
| ML081120496 | |
| Person / Time | |
|---|---|
| Site: | Fort Calhoun |
| Issue date: | 04/21/2008 |
| From: | Laura Smith NRC/RGN-IV/DRS/EB2 |
| To: | Bannister D Omaha Public Power District |
| References | |
| IR-08-006 | |
| Download: ML081120496 (7) | |
See also: IR 05000285/2008006
Text
April 21, 2008
D. J. Bannister
Vice President and CNO Omaha Public Power District Fort Calhoun Station FC-2-4 Adm. P.O. Box 550 Fort Calhoun, NE 68023-0550
SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF AN NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION 05000285/2008006
Dear Mr. Bannister:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC),
Region IV staff will conduct a triennial fire protection baseline inspection at your Fort Calhoun Station in July and August of 2008. The inspection team will be comprised of reactor inspectors from the NRC Region IV office and a contractor. The team will conduct the inspection in accordance with the baseline Inspection Procedure 71111.05T, "Fire Protection (Triennial)."
The schedule for the inspection is as follows:
- Information gathering visit: July 8-10, 2008 * Onsite inspection: July 28-August 1, 2008 August 11-15, 2008
The team will visit the Fort Calhoun Station on July 8-10, 2008, to gather information, select the fire areas for evaluation, identify documents needed to support the inspection, obtain unescorted access, and to become familiar with your fire protection program. The enclosure to this letter provides an initial list of the documents the team will want to review. The team leader
will request that you transmit copies of some of the documents to the NRC Region IV office for team use in preparation for the inspection. We would appreciate it if you could send this information so that it will arrive in our office in Arlington, Texas, by the dates listed in the enclosure.
We request that during the onsite inspection weeks, you ensure that copies of analyses, evaluations, or documentation regarding the implementation and maintenance of the fire
protection program, including post-fire safe shutdown capability, be readily accessible to the team for their review. Of specific interest are those documents that establish that your fire protection program satisfies NRC regulatory requirements and conforms to applicable NRC and
UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV611 RYAN PLAZA DRIVE, SUITE 400ARLINGTON, TEXAS 76011-4005
Omaha Public Power District - 2 -
industry fire protection guidance. Also, appropriate personnel knowledgeable of: (1) plant systems required to achieve and maintain safe shutdown conditions from inside and outside the control room, (2) the electrical aspects of the post-fire safe shutdown analyses, (3) reactor plant
fire protection systems, and (4) the fire protection program and its implementation should be available to support the team at the site during the inspection.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Your cooperation and support during this inspection will be appreciated. If you have questions concerning this inspection or the inspection team's information or logistical needs, please contact Greg Pick at 817-860-8270.
Sincerely,
/RA/
Linda J. Smith, Chief Engineering Branch 2 Division of Reactor Safety
Docket: 50-285
License: DPR-40
Enclosure: Triennial Fire Protection Inspection Supporting Documentation
cc: Joe l. McManis, Manager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
P.O. Box 550 Fort Calhoun, NE 68023-0550
Winston & Strawn Attn: James R. Curtiss 1700 K Street NW Washington, DC 20006-3817
Chairman Washington County Board of Supervisors P.O. Box 466 Blair, NE 68008
Omaha Public Power District - 3 -
Julia Schmitt, Manager Radiation Control Program Nebraska Health & Human Services Dept. of Regulation & Licensing
Division of Public Health Assurance 301 Centennial Mall, South P.O. Box 95007 Lincoln, NE 68509-5007
Melanie Rasmussen Bureau of Radiological Health Iowa Department of Public Health Lucas State Office Building, 5th Floor 321 East 12th Street Des Moines, IA 50319
Ronald L. McCabe, Chief Technological Hazards Branch National Preparedness Division DHS/FEMA 9221 Ward Parkway
Suite 300 Kansas City, MO 64114-3372
Omaha Public Power District - 4 -
Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov) DRP Director (Dwight.Chamberlain@nrc.gov) DRS Director (Roy.Caniano@nrc.gov)
DRS Deputy Director (Troy.Pruett@nrc.gov) Senior Resident Inspector (John.Hanna@nrc.gov) Branch Chief, DRP/E (Jeff.Clark@nrc.gov) Senior Project Engineer, DRP/E (George.Replogle@nrc.gov) Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
SUNSI Review Completed: _GAP__ ADAMS: X Yes Initials: __GAP____ X Publicly Available X Non-Sensitive
S:\DRS\REPORTS\FC2008006-GAP ML081120496 SRI:DRS/EB2 C: EB2 GAP/tek LJSmith
04/ /08 04/ /08
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
ENCLOSURE Triennial Fire Protection Inspection Documentation Requested
Please provide the following documentation prior to the onsite information-gathering trip, preferably no later than June 23, 2008. Where practical, please provide copies electronically.
1. The current version of your fire protection program and fire hazards analysis.
2. Post-fire safe shutdown analysis and the supporting calculations that demonstrate acceptable plant response.
3. Copies of the licensing basis documents for fire protection (Safety Evaluation Reports, pertinent sections of the Final Safety Analysis Report, exemptions, deviations, letters to/from the NRC regarding fire protection/fire safe shutdown, etc.).
4. The Fire PRA or portions of the plant's IPEEE addressing fire events.
Please provide the following documentation during the information-gathering visit or by July 18, 2008, in order to support inspection preparation. Where practical, please provide
copies electronically. However, drawings should be provided as paper copies of sufficient size that all details are legible.
5. Fire protection program implementing procedures (e.g., administrative controls, operator response procedures for fires, fire fighting procedures, etc.).
6. Operating procedures used for achieving and maintaining hot and cold shutdown conditions from the control room in the event of a fire outside the control room (III.G.2 areas).
7. Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas) capability with or without control room evacuation.
8. Pre-fire plans for the selected fire areas (areas to be selected by the team during the information-gathering trip).
9. A list of equipment used to achieve and maintain hot standby and cold shutdowns in the event of a fire (safe shutdown equipment lists).
10. Piping and instrumentation (flow) diagrams showing the components used to achieve and maintain hot standby and cold shutdowns for fires outside the control room and those components used for those areas requiring alternative shutdown capability. Two
copies of the piping and instrumentation (flow) diagrams for these systems of a size sufficient to read all details. These should include the systems used for RCS makeup, RCS pressure control, decay heat removal, and reactivity control, including the essential support systems.
11. Plant layout and equipment drawings for the selected fire areas that identify (a) the physical plant locations of major hot standby and cold shutdown equipment; (b) plant fire area and/or fire zone delineation; and (c) the locations of fire protection equipment, such as detection, suppression, and post-fire emergency lighting units, and (d) fire area boundaries.
12. A listing of design change packages, which were determined to impact fire protection and post-fire safe shutdowns, performed in the last 3 years.
13. Copies of Generic Letter 86-10 evaluations performed in the last 3 years.
14. A listing of open and closed corrective action documents initiated in the last 3 years, which relate to the fire protection program or equipment. Include corrective action document number, date, and subject.
15. A listing of the applicable codes and standards (with the versions) related to the design of plant fire protection features and evaluations of any code deviations.
16. Drawings of the portions of the emergency lighting system which support fire response.
17. Procedures used to remove smoke from safety-related areas and the engineering studies or calculations which support the design basis.
18. Drawings of communication systems credited in the license basis for firefighting and plant operations during fires where control room is occupied and/or evacuated.
19. Piping and instrumentation (flow) diagrams for the fire water and sprinkler systems.
20. A listing of maintenance and surveillance testing procedures for alternative shutdown capability and fire barriers, detectors, pumps and suppression systems.
21. Maintenance Rule performance criteria and a summary of the last 3 years' performance history for fire protection program systems or functions monitored within the Maintenance Rule program.
22. A copy of fire protection program requirements (e.g. limiting conditions for operation, surveillance test requirements) covered by Technical Specifications, Technical
Requirements Manual, UFSAR, or similar documents.
23. Copies of internal and external self-assessments, audits, peer-assessments or similar reviews related to post-fire safe shutdown capability or the fire protection program completed since July 1, 2005.
24. A list of manual actions taken outside the control room which are credited to mitigate the consequences of fires in III.G.2 areas (non-alternative shutdown areas). The list should group actions by the initiating fire area or zone and indicate where the action must take place. 25. Electronic copies of operator study guides (i.e. lesson plan text and graphics) or design basis documents that describe the purpose/function/operating characteristics of the safe
shutdown systems (RCS makeup, RCS pressure control, decay heat removal, and reactivity control, including the essential support systems).
26. Two copies of one-line diagrams of the electrical distribution system. These should depict how power gets from the switchyard to ESF loads (480V and 4160V). Also,
include the vital DC distribution system one-line diagrams.
27. A list of automatic and manually initiated gaseous fire suppression systems in the plant, giving location and the key equipment being protected.
28. A list of repairs (and the procedure that controls the actions) needed to: a) reach and/or maintain hot shutdown and b) reach and/or maintain cold shutdown.
29. A list of high to low pressure interface valves.
30. A copy of procedures governing the training and operation of the fire brigade.
31. Organization charts of site personnel down to the level of fire protection staff personnel.
32. A contact list of key site personnel who will be supporting this inspection, giving location of their office and phone number onsite.
33. The team would like to observe a fire brigade drill in the plant, if possible, during the week of August 11, 2008. Please put us in contact with the appropriate personnel for planning drills during the onsite information gathering trip.
34. The team would like to perform a walkthrough of the procedure for control room due to fire with qualified operators in the plant during the week of July 28, 2008. Please put us in contact with the appropriate personnel for planning the walkthrough during the onsite information gathering trip.