ML18067A085: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 19: | Line 19: | ||
=Text= | =Text= | ||
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 8, 2018 | ||
Ms. Barbara Nick President and Chief Executive Officer Dairyland Power Cooperative 3200 East Ave. S., P.O. Box 817 La Crosse, WI 54602-0817 | Ms. Barbara Nick President and Chief Executive Officer Dairyland Power Cooperative 3200 East Ave. S., P.O. Box 817 La Crosse, WI 54602-0817 | ||
==SUBJECT:== | ==SUBJECT:== | ||
REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVE'S DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION | REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVE'S DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION | ||
==Dear Ms. Nick:== | ==Dear Ms. Nick:== | ||
By letter dated March 14, 2016, Dairyland Power Cooperative (DPC) submitted for U.S. Nuclear Regulatory Commission (NRC) staff | By letter dated March 14, 2016, Dairyland Power Cooperative (DPC) submitted for U.S. Nuclear Regulatory Commission (NRC) staff rev iew and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installation (ISFSI) at La Crosse Boiling Water Reactor (Agencywide Documents Access and Management System Accession No. ML16102A101). The NRC staff reviewed DPC's DFP update for the ISFSI and believes DPC's submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). The DFP update does not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered. | ||
The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by | The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty-five (45) working day of the date of this letter. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date. To assist us in re-scheduling your review, you should include a new proposed submittal date and the reasons for the delay. Discussion of the request for additional information (RAI) and RAI response date occurred February 27, 2018. | ||
The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov | |||
. Sincerely, | |||
/RA/ | /RA/ | ||
Pamela Longmire, Ph.D. Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards | Pamela Longmire, Ph.D. Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-46 CAC No.: 001028 EPID No.: L-2017-FPR-0037 | ||
==Enclosure:== | ==Enclosure:== | ||
Request for Additional Information | Request for Additional Information | ||
B. Nick 3 REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVE'S DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE: MARCH 8, 2018 | B. Nick 3 REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVE'S DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE: MARCH 8, 2018 | ||
DISTRIBUTION: SFM R/F JMcKirgan ABowers SHarwell KLois MHenderson BWatson MVaaler | DISTRIBUTION: SFM R/F JMcKirgan ABowers SHarwell KLois MHenderson BWatson MVaaler | ||
ADAMS Package No.: ML18067A084 Letter: ML18067A085 Encl.: ML18067A086 | ADAMS Package No.: ML18067A084 Letter: ML18067A085 Encl.: ML18067A086 C = COVER E = COVER & ENCLOSURE N = NO COPY OFC NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley via e-mail JMcKirgan DATE 2/27/18 3/6/18 3/8/18 OFFICIAL RECORD COPY}} | ||
Revision as of 01:11, 29 June 2018
| ML18067A085 | |
| Person / Time | |
|---|---|
| Site: | 07100046 |
| Issue date: | 03/08/2018 |
| From: | Pamela Longmire Spent Fuel Licensing Branch |
| To: | Nick B Dairyland Power Cooperative |
| Longmire P | |
| Shared Package | |
| ML18067A084 | List: |
| References | |
| CAC 001028, EPID L-2017-FPR-0037 | |
| Download: ML18067A085 (3) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 8, 2018
Ms. Barbara Nick President and Chief Executive Officer Dairyland Power Cooperative 3200 East Ave. S., P.O. Box 817 La Crosse, WI 54602-0817
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVE'S DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION
Dear Ms. Nick:
By letter dated March 14, 2016, Dairyland Power Cooperative (DPC) submitted for U.S. Nuclear Regulatory Commission (NRC) staff rev iew and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installation (ISFSI) at La Crosse Boiling Water Reactor (Agencywide Documents Access and Management System Accession No. ML16102A101). The NRC staff reviewed DPC's DFP update for the ISFSI and believes DPC's submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). The DFP update does not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered.
The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty-five (45) working day of the date of this letter. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date. To assist us in re-scheduling your review, you should include a new proposed submittal date and the reasons for the delay. Discussion of the request for additional information (RAI) and RAI response date occurred February 27, 2018.
The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov
. Sincerely,
/RA/
Pamela Longmire, Ph.D. Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-46 CAC No.: 001028 EPID No.: L-2017-FPR-0037
Enclosure:
Request for Additional Information
B. Nick 3 REQUEST FOR ADDITIONAL INFORMATION REGARDING DAIRYLAND POWER COOPERATIVE'S DECOMMISSIONING FUNDING PLAN UPDATE FOR LA CROSSE BOILING WATER REACTOR INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE: MARCH 8, 2018
DISTRIBUTION: SFM R/F JMcKirgan ABowers SHarwell KLois MHenderson BWatson MVaaler
ADAMS Package No.: ML18067A084 Letter: ML18067A085 Encl.: ML18067A086 C = COVER E = COVER & ENCLOSURE N = NO COPY OFC NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley via e-mail JMcKirgan DATE 2/27/18 3/6/18 3/8/18 OFFICIAL RECORD COPY