ML20196D648: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot change) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 1: | Line 1: | ||
{{Adams | |||
| number = ML20196D648 | |||
| issue date = 11/20/1998 | |||
| title = Informs That Ssei Repts 50-324/99-01 & 50-325/99-01 at Brunswick Facility Have Been Scheduled for 990111-15 & 25-29.Insp Objective Will Be to Evaluate Capability of Hpci& RCIC Sys to Perform Safety Functions Required | |||
| author name = Landis K | |||
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) | |||
| addressee name = Keenan J | |||
| addressee affiliation = CAROLINA POWER & LIGHT CO. | |||
| docket = 05000324, 05000325 | |||
| license number = | |||
| contact person = | |||
| document report number = 50-324-99-01, 50-324-99-1, 50-325-99-01, 50-325-99-1, NUDOCS 9812020300 | |||
| document type = CORRESPONDENCE-LETTERS, OUTGOING CORRESPONDENCE | |||
| page count = 4 | |||
}} | |||
See also: [[see also::IR 05000324/1999001]] | |||
=Text= | |||
{{#Wiki_filter:_- | |||
-... | |||
-, | |||
- ~ . - . - - - _ . . _ . . - - . - - . . - - | |||
. . . - - . . _ . . | |||
, | |||
,7. | |||
November 20,1998 | |||
Carolina Power and Light Company - | |||
- ATTN: Mr. J. S. Keenan - | |||
Vice President | |||
Brunswick Steam Electric Plant | |||
-l | |||
0. O. Box 10429 | |||
i | |||
Southport, NC 28461 | |||
' | |||
. | |||
. | |||
SUBJECT: | |||
SAFETY SYSTEM ENGINEERING INSPECTION (NRC INSPECTION REPORT | |||
J | |||
NO. 50-325,324/99-01) | |||
Dear Mr. Keenan: | |||
I | |||
; | |||
The purpose of this letter is to announce a safety system engineering inspection (SSEI) at your | |||
; | |||
Brunswick facilny which is scheduled for January 11-15 and 25-29,1999. The designated team | |||
leader, Joseph J. Lenahan, will make arrangements with your staff to discuss the inspection | |||
plan in more detail. | |||
l | |||
The inspection objective will be to evaluate the capability of the high pressure coolant injection | |||
' (HPCI) and reactor core isolation cooling (RCIC) systems to perform safety functions required | |||
!. | |||
by their design bases. The inspection will be conducted using Inspection Procedure 93809, | |||
" Safety System Engineering Inspection (SSEI)", and willinvolve a team of five inspectors. | |||
The team will require the information outlined in the enclosure for the HPCI and RCIC systems | |||
!- | |||
to review in preparation for the inspection. This information will be needed by December 16, | |||
l | |||
1998 in order to support the inspection effort. | |||
! | |||
l' | |||
Thank you for your cooperation in this matter. If you have any questions regarding this | |||
I | |||
inspection, please contact Mr. J. Lenahan at (404) 562-4625 or Mr. K. Landis at (404) 562-4605. | |||
; | |||
' | |||
r | |||
l- | |||
Sincerely, | |||
; | |||
Original signed by | |||
l | |||
Kerry D. Landis | |||
' | |||
p | |||
Kerr) D. Landis, Chief - | |||
- | |||
Engineering Branch | |||
Division of Reactor Safety | |||
- | |||
Docket Nos. 50-325, 50-324 | |||
l | |||
- License Nos. DPR-71, DPR-62 | |||
i: | |||
Enclosure: | |||
Information Requested for High Pressure Coolant injection (HPCI) and | |||
[ | |||
Reactor Core isolation Cooling (RCIC) Systems | |||
* | |||
G | |||
; | |||
.cc w/ encl: (See page 2) | |||
' | |||
( | |||
.. | |||
f | |||
- | |||
9812O20300 981120 | |||
> | |||
PDR | |||
ADOCK 05000324 | |||
t | |||
' | |||
G | |||
PDR | |||
; | |||
fdd/ ; | |||
. . . . . | |||
. | |||
. | |||
- | |||
_ | |||
_ . | |||
_ | |||
- | |||
_- | |||
. . . _ | |||
_ _ _ _ . . _ . | |||
. | |||
_ . _ _ _ _ _ .... _ _ _ _ _ .. _ _ _ . | |||
.- _ . - . . . . | |||
. | |||
p | |||
CP&L | |||
2 | |||
- cc w/ encl: | |||
Director | |||
Karen E. Long | |||
Site Operations | |||
Assistant Attorney General | |||
Brunswick Steam Electric Plant | |||
State of North Carolina | |||
Carolina Power & Light Company | |||
P. O. Box 629 | |||
P. O. Box 10429 | |||
Raleigh, NC 27602 | |||
Southport, NC 28461 | |||
Robert P. Gruber | |||
j | |||
J. J. Lyash, Plant Manager. | |||
Executive Director | |||
l | |||
Brunswick Steam Electric Plant | |||
Public Staff NCUC | |||
' | |||
Carolina Power & Light Company | |||
P. O. Box 29520 | |||
P. O. Box 10429 | |||
Raleigh, NC 27626-0520 | |||
Southport, NC 28461 | |||
Public Service Commission | |||
D. B. Alexander, Manager | |||
State of South Carolina | |||
Performance Evaluation and | |||
P. O. Box 11649 | |||
Regulatory Affairs CPB 9 | |||
Columbia, SC 29211 | |||
i | |||
Carolina Power & Light Company | |||
i | |||
P. O. Box 1551 ' | |||
Jerry W. Jones, Chairman | |||
Raleigh, NC 27602-1551_ | |||
Brunswick County Board of | |||
1 | |||
Commissioners | |||
K. R. Jury, Manager | |||
P. O. Box. 249 | |||
Regulatory Affairs | |||
Bolivia, NC 28422 | |||
Carolina Power & Light Company | |||
' | |||
Brunswick Steam Electric Plant | |||
Dan E. Summers | |||
P. O. Box 10429 | |||
Emergency Management Coordinator | |||
_ | |||
Southport, NC 28461-0429 | |||
New Hanover County Department of | |||
l | |||
_ | |||
Emergency Management | |||
l | |||
William D. Johnson | |||
P. O. Box 1525 | |||
!- | |||
; Vice President & Senior Counsel - | |||
Wilmington, NC 28402 | |||
Carolina Power and Light Company | |||
P. O. Box 1551 | |||
William H. Crowe, Mayor | |||
Raleigh, NC 27602 | |||
City of Southport | |||
201 E. Moore Street | |||
Mel Fry, Director | |||
Southport, NC 28461 | |||
Division of Radiation Protection | |||
N. C. Department of Environment | |||
(Distribution w/enci - See next page) | |||
- and Natural Resources | |||
l | |||
3825 Barrett Drive | |||
. | |||
! | |||
Raleigh, NC 27609-7721 | |||
i | |||
'k ::L | |||
- . . | |||
- | |||
. . - | |||
-.. . | |||
- . _ . _ _ . | |||
. | |||
+ | |||
CP&L | |||
3 | |||
Distribution w/ encl: | |||
L. Plisco, Ril | |||
M. Ernstes, Ril | |||
D. Trimble, NRR | |||
J. Coley, Ril | |||
R. Baldwin, Rll | |||
J.Lenahan,Ril | |||
E. Testa, Rll | |||
D. Thompson, Rll | |||
D. Jones,Rll | |||
G. West, Rll | |||
PUBLIC | |||
NRC Resident inspector | |||
U. S. Nuclear Regulatory Commission | |||
8470 River Road, SE | |||
Southport, NC 28461 | |||
T | |||
OFFICE | |||
Rit: PRS | |||
Rit:DRS ( | |||
F | |||
Ril:oRP | |||
g | |||
_ | |||
SIGNATURE | |||
%b | |||
M | |||
M/ | |||
NAME | |||
Jien'ahan:pd | |||
Klandit | |||
. | |||
BBonser | |||
~ | |||
" | |||
DATE | |||
_11/!# /98 | |||
f@ 198 | |||
_11/4 0/98 | |||
11/ /98 | |||
11/ 19 8 | |||
11/ 19 8 | |||
til 19 8 | |||
COPY? | |||
IYiS) | |||
NO | |||
DYES / NO | |||
/VnS | |||
NO | |||
YES | |||
NO | |||
YES | |||
NO | |||
YES | |||
NO | |||
YES | |||
NO | |||
OFAetIL RECORD CDPI | |||
DOCUii4ENT NAME: S:\\DRS\\EB\\BRUSSEll.WPD | |||
. | |||
j'_ | |||
. ~ . , | |||
- | |||
-. | |||
.- | |||
. | |||
. | |||
- | |||
. | |||
- | |||
=- | |||
. | |||
- | |||
. | |||
, | |||
* | |||
y | |||
INFORMATION REQUESTED FOR | |||
< | |||
THE HIGH COOLANT INJECTION (HPCI) AND | |||
- | |||
REACTOR CORE ISOLATION COOLING (RCIC) SYSTEMS | |||
Site specific administrative procedures related to standard operation, abnormal | |||
. | |||
operation, and emergency operation of the HPCI and RCIC systems. | |||
i | |||
Design criteria for the HPCI and RCIC Systems in addition to support systems and | |||
- | |||
interfaces including but not limited to the Main Steam System, Conden sate /feedwater | |||
System, the Class 1E AC Power System and the Class 1E DC Power system. | |||
- | |||
HPCI and RCIC Technical Specification requirements and associated surveillance | |||
. | |||
test / calibration procedures. | |||
HPCI and RCIC systems piping and instrumentation drawings; one line diagrams; | |||
. | |||
electrical schematics; wiring and logic diagrams. | |||
A list of engineering calculations (Electrical, Instrumentation and Controls and | |||
. | |||
Mechanical / Nuclear) applicable to the HPCI and RCIC systems. | |||
A list of plant modifications to the HPCI and RCIC systems implemented since plant | |||
. | |||
licensing. | |||
) | |||
i | |||
i | |||
Relevant regulatory information regarding information notices, generic letters and special | |||
. | |||
j | |||
studies that CP&L has performed for the HPCI and RCIC systems, | |||
j | |||
HPCI and RCIC systems related LERs for the past 24 months. | |||
- | |||
A list of Adverse Condition Reports and Condition Reports initiated since 1990 affecting | |||
. | |||
the HPCI and RCIC systems. | |||
List of current open temporary modifications and operator work arounds involving | |||
. | |||
operation of the HPCI and RCIC systems. | |||
System Health Report and Performance Trends for the HPCI and RCIC systems. | |||
. | |||
' Maintenance Rule Performance criteria for the HPCI system. | |||
. | |||
Documentation of corrective and preventive maintenance activities, including the | |||
. | |||
maintenance rule event log, performed on the HPCI and RCIC systems in the past 12 | |||
months. | |||
Copies of applicable sections of the UFSAR for the HPCI and RCIC systems. | |||
. | |||
An index of drawings for the HPCI and RCIC systems. | |||
. | |||
Copies of self-assessment pertamed on the HPCI and RCIC systems in the last 24 | |||
. | |||
months. | |||
The system description and operator training module for the HPCI and RCIC systems. | |||
- | |||
. | |||
b | |||
Enclosure | |||
l | |||
}} | |||
Latest revision as of 07:10, 24 May 2025
| ML20196D648 | |
| Person / Time | |
|---|---|
| Site: | Brunswick |
| Issue date: | 11/20/1998 |
| From: | Landis K NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Keenan J CAROLINA POWER & LIGHT CO. |
| References | |
| 50-324-99-01, 50-324-99-1, 50-325-99-01, 50-325-99-1, NUDOCS 9812020300 | |
| Download: ML20196D648 (4) | |
See also: IR 05000324/1999001
Text
_-
-...
-,
- ~ . - . - - - _ . . _ . . - - . - - . . - -
. . . - - . . _ . .
,
,7.
November 20,1998
Carolina Power and Light Company -
- ATTN: Mr. J. S. Keenan -
Vice President
Brunswick Steam Electric Plant
-l
0. O. Box 10429
i
Southport, NC 28461
'
.
.
SUBJECT:
SAFETY SYSTEM ENGINEERING INSPECTION (NRC INSPECTION REPORT
J
NO. 50-325,324/99-01)
Dear Mr. Keenan:
I
The purpose of this letter is to announce a safety system engineering inspection (SSEI) at your
Brunswick facilny which is scheduled for January 11-15 and 25-29,1999. The designated team
leader, Joseph J. Lenahan, will make arrangements with your staff to discuss the inspection
plan in more detail.
l
The inspection objective will be to evaluate the capability of the high pressure coolant injection
' (HPCI) and reactor core isolation cooling (RCIC) systems to perform safety functions required
!.
by their design bases. The inspection will be conducted using Inspection Procedure 93809,
" Safety System Engineering Inspection (SSEI)", and willinvolve a team of five inspectors.
The team will require the information outlined in the enclosure for the HPCI and RCIC systems
!-
to review in preparation for the inspection. This information will be needed by December 16,
l
1998 in order to support the inspection effort.
!
l'
Thank you for your cooperation in this matter. If you have any questions regarding this
I
inspection, please contact Mr. J. Lenahan at (404) 562-4625 or Mr. K. Landis at (404) 562-4605.
'
r
l-
Sincerely,
Original signed by
l
Kerry D. Landis
'
p
Kerr) D. Landis, Chief -
-
Engineering Branch
Division of Reactor Safety
-
Docket Nos. 50-325, 50-324
l
i:
Enclosure:
Information Requested for High Pressure Coolant injection (HPCI) and
[
Reactor Core isolation Cooling (RCIC) Systems
G
.cc w/ encl: (See page 2)
'
(
..
f
-
9812O20300 981120
>
ADOCK 05000324
t
'
G
fdd/ ;
. . . . .
.
.
-
_
_ .
_
-
_-
. . . _
_ _ _ _ . . _ .
.
_ . _ _ _ _ _ .... _ _ _ _ _ .. _ _ _ .
.- _ . - . . . .
.
p
2
- cc w/ encl:
Director
Karen E. Long
Site Operations
Assistant Attorney General
Brunswick Steam Electric Plant
State of North Carolina
Carolina Power & Light Company
P. O. Box 629
P. O. Box 10429
Raleigh, NC 27602
Southport, NC 28461
Robert P. Gruber
j
J. J. Lyash, Plant Manager.
Executive Director
l
Brunswick Steam Electric Plant
Public Staff NCUC
'
Carolina Power & Light Company
P. O. Box 29520
P. O. Box 10429
Raleigh, NC 27626-0520
Southport, NC 28461
Public Service Commission
D. B. Alexander, Manager
State of South Carolina
Performance Evaluation and
P. O. Box 11649
Regulatory Affairs CPB 9
Columbia, SC 29211
i
Carolina Power & Light Company
i
P. O. Box 1551 '
Jerry W. Jones, Chairman
Raleigh, NC 27602-1551_
Brunswick County Board of
1
Commissioners
K. R. Jury, Manager
P. O. Box. 249
Regulatory Affairs
Bolivia, NC 28422
Carolina Power & Light Company
'
Brunswick Steam Electric Plant
Dan E. Summers
P. O. Box 10429
Emergency Management Coordinator
_
Southport, NC 28461-0429
New Hanover County Department of
l
_
Emergency Management
l
William D. Johnson
P. O. Box 1525
!-
- Vice President & Senior Counsel -
Wilmington, NC 28402
Carolina Power and Light Company
P. O. Box 1551
William H. Crowe, Mayor
Raleigh, NC 27602
City of Southport
201 E. Moore Street
Mel Fry, Director
Southport, NC 28461
Division of Radiation Protection
N. C. Department of Environment
(Distribution w/enci - See next page)
- and Natural Resources
l
3825 Barrett Drive
.
!
Raleigh, NC 27609-7721
i
'k ::L
- . .
-
. . -
-.. .
- . _ . _ _ .
.
+
3
Distribution w/ encl:
L. Plisco, Ril
M. Ernstes, Ril
D. Trimble, NRR
J. Coley, Ril
R. Baldwin, Rll
J.Lenahan,Ril
E. Testa, Rll
D. Thompson, Rll
D. Jones,Rll
G. West, Rll
PUBLIC
NRC Resident inspector
U. S. Nuclear Regulatory Commission
8470 River Road, SE
Southport, NC 28461
T
OFFICE
Rit: PRS
Rit:DRS (
F
Ril:oRP
g
_
SIGNATURE
%b
M
M/
NAME
Jien'ahan:pd
Klandit
.
BBonser
~
"
DATE
_11/!# /98
f@ 198
_11/4 0/98
11/ /98
11/ 19 8
11/ 19 8
til 19 8
COPY?
IYiS)
NO
DYES / NO
/VnS
NO
YES
NO
YES
NO
YES
NO
YES
NO
OFAetIL RECORD CDPI
DOCUii4ENT NAME: S:\\DRS\\EB\\BRUSSEll.WPD
.
j'_
. ~ . ,
-
-.
.-
.
.
-
.
-
=-
.
-
.
,
y
INFORMATION REQUESTED FOR
<
THE HIGH COOLANT INJECTION (HPCI) AND
-
REACTOR CORE ISOLATION COOLING (RCIC) SYSTEMS
Site specific administrative procedures related to standard operation, abnormal
.
operation, and emergency operation of the HPCI and RCIC systems.
i
Design criteria for the HPCI and RCIC Systems in addition to support systems and
-
interfaces including but not limited to the Main Steam System, Conden sate /feedwater
System, the Class 1E AC Power System and the Class 1E DC Power system.
-
HPCI and RCIC Technical Specification requirements and associated surveillance
.
test / calibration procedures.
HPCI and RCIC systems piping and instrumentation drawings; one line diagrams;
.
electrical schematics; wiring and logic diagrams.
A list of engineering calculations (Electrical, Instrumentation and Controls and
.
Mechanical / Nuclear) applicable to the HPCI and RCIC systems.
A list of plant modifications to the HPCI and RCIC systems implemented since plant
.
licensing.
)
i
i
Relevant regulatory information regarding information notices, generic letters and special
.
j
studies that CP&L has performed for the HPCI and RCIC systems,
j
HPCI and RCIC systems related LERs for the past 24 months.
-
A list of Adverse Condition Reports and Condition Reports initiated since 1990 affecting
.
List of current open temporary modifications and operator work arounds involving
.
operation of the HPCI and RCIC systems.
System Health Report and Performance Trends for the HPCI and RCIC systems.
.
' Maintenance Rule Performance criteria for the HPCI system.
.
Documentation of corrective and preventive maintenance activities, including the
.
maintenance rule event log, performed on the HPCI and RCIC systems in the past 12
months.
Copies of applicable sections of the UFSAR for the HPCI and RCIC systems.
.
An index of drawings for the HPCI and RCIC systems.
.
Copies of self-assessment pertamed on the HPCI and RCIC systems in the last 24
.
months.
The system description and operator training module for the HPCI and RCIC systems.
-
.
b
Enclosure
l