ML031490485: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
Line 22: Line 22:
Georgia Institute of Technology
Georgia Institute of Technology
900 Atlantic Drive
900 Atlantic Drive
Atlanta, GA 30332-0425
Atlanta, GA 30332-0425
SUBJECT:         NRC INSPECTION REPORT NO. 50-160/2002-201
SUBJECT:
NRC INSPECTION REPORT NO. 50-160/2002-201
Dear Dr. Hertel:
Dear Dr. Hertel:
The inspection effort involved the coordination of the confirmatory radiological survey activities
The inspection effort involved the coordination of the confirmatory radiological survey activities
performed by our contractor, Oak Ridge Institute for Science and Education, of your research
performed by our contractor, Oak Ridge Institute for Science and Education, of your research
reactor on October 21-23, 2002. In addition, various aspects of your reactor operations,
reactor on October 21-23, 2002. In addition, various aspects of your reactor operations,
decommissioning, and radiation protection programs were inspected, including selective
decommissioning, and radiation protection programs were inspected, including selective
examinations of procedures and representative records, interviews with personnel, and
examinations of procedures and representative records, interviews with personnel, and
Line 39: Line 40:
20.1401(b)(2).
20.1401(b)(2).
No safety concern or noncompliance with Nuclear Regulatory Commission (NRC) requirements
No safety concern or noncompliance with Nuclear Regulatory Commission (NRC) requirements
was identified. No response to this letter is required.
was identified. No response to this letter is required.


Dr. N. Hertel                                   -2-
Dr. N. Hertel
-2-
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document system
Room or from the Publicly Available Records (PARS) component of NRCs document system
(ADAMS). ADAMS is accessible from the NRC Web site at (the Public Electronic Reading
(ADAMS). ADAMS is accessible from the NRC Web site at (the Public Electronic Reading
Room) http://www.nrc.gov/NRC/ADAMS/index.html. Should you have any questions
Room) http://www.nrc.gov/NRC/ADAMS/index.html. Should you have any questions
concerning this inspection, please contact Mr. Stephen Holmes at 301-415-8583.
concerning this inspection, please contact Mr. Stephen Holmes at 301-415-8583.
                                              Sincerely,
Sincerely,
                                              /RA by Daniel E. Hughes, Acting for/
/RA by Daniel E. Hughes, Acting for/
                                              Patrick M. Madden, Section Chief
Patrick M. Madden, Section Chief
                                              Research and Test Reactors Section
Research and Test Reactors Section
                                              Operating Reactor Improvements Program
Operating Reactor Improvements Program
                                              Division of Regulatory Improvement Programs
Division of Regulatory Improvement Programs
                                              Office of Nuclear Reactor Regulation
Office of Nuclear Reactor Regulation
Docket No.  50-160
License No.  R-97
Enclosures:  1. NRC Inspection Report No. 50-160/2002-201
        2. Confirmatory Survey Plan for the Georgia Tech Research Reactor dated   
October 9, 2002
        3. Confirmatory Survey of the Georgia Tech Research Reactor, dated
February 2003
cc w/enclosures:  Please see next page
 
Georgia Institute of Technology
Docket No. 50-160
Docket No. 50-160
License No. R-97
Enclosures: 1. NRC Inspection Report No. 50-160/2002-201
              2. Confirmatory Survey Plan for the Georgia Tech Research Reactor dated
                October 9, 2002
              3. Confirmatory Survey of the Georgia Tech Research Reactor, dated
                February 2003
cc w/enclosures: Please see next page
Georgia Institute of Technology                            Docket No. 50-160
cc:
cc:
Mr. Charles H. Badger             Ms. Glen Carrol
Mr. Charles H. Badger
Office of Planning and Budget     139 Kings Highway
Office of Planning and Budget
Room 608                         Decatur, GA 30030
Room 608
270 Washington Street, S.W.
270 Washington Street, S.W.
Atlanta, GA 30334                 Charles Bechhoefer, Chairman
Atlanta, GA 30334
                                  Atomic Safety and
Mayor of City of Atlanta
Mayor of City of Atlanta           Licensing Board Panel
55 Trinity Avenue, S.W.
55 Trinity Avenue, S.W.           U.S. NRC, MS: T3-F23
Suite 2400
Suite 2400                       Washington, DC 20555-0001
Atlanta, GA 30335
Atlanta, GA 30335
Dr. William Vernetson
                                  Mr. James C. Hardeman, Jr.
Director of Nuclear Facilities
Dr. William Vernetson             Manager, Environmental
Department of Nuclear Engineering
Director of Nuclear Facilities     Radiation Program
  Sciences
Department of Nuclear Engineering Environmental Protection Division
University of Florida
Sciences                         Dept. of Natural Resources
202 Nuclear Sciences Center
University of Florida             State of Georgia
Gainesville, FL 32611
202 Nuclear Sciences Center       4244 International Parkway
Gainesville, FL 32611             Suite 114
                                  Atlanta, GA 30354
Joe D. Tanner, Commissioner
Joe D. Tanner, Commissioner
Department of Natural Resources   Dr. Jean-Lou Chameau, Dean
Department of Natural Resources
47 Trinity Avenue, S.W.           College of Engineering
47 Trinity Avenue, S.W.
Atlanta, GA 30334                 Georgia Institute of Technology
Atlanta, GA 30334
                                  225 North Avenue
Dr. Rodney Ice, MORS
Dr. Rodney Ice, MORS             Atlanta, GA 30332-0425
Neely Nuclear Research Center
Neely Nuclear Research Center
Georgia Institute of Technology   Dr. Peter S. Lam
Georgia Institute of Technology
900 Atlantic Drive               Atomic Safety and Licensing Board Panel
900 Atlantic Drive
Atlanta, GA 30332-0425           U.S. NRC, MS: T3-F23
Atlanta, GA 30332-0425
                                  Washington, DC 20555-0001
Ms. Pamela Blockey-OBrien
Ms. Pamela Blockey-OBrien
D23 Golden Valley                 Dr. J. Narl Davidson, Interim Dean
D23 Golden Valley
Douglasville, GA 30134            Chair, Technical and Safety Review
Douglasville, GA  30134
                                  Committee
Mr. E.F. Cobb
Mr. E.F. Cobb                    Georgia Institute of Technology
Southern Nuclear Company
Southern Nuclear Company          225 North Avenue
42 Iverness Center
42 Iverness Center                Atlanta, GA 3033-0360
Birmingham, AL  35242
Birmingham, AL 35242
Dr. G. Wayne Clough, President
                                  Dr. Charles Liotta, Vice Provost
Georgia Institute of Technology
Dr. G. Wayne Clough, President    of Research and Dean of
Carnegie Building
Georgia Institute of Technology    Graduate Studies
Atlanta, GA  30332-0325
Carnegie Building                Georgia Institute of Technology
Ms. Glen Carrol
Atlanta, GA 30332-0325            225 North Avenue
139 Kings Highway
                                  Atlanta, GA 30332
Decatur, GA  30030
Charles Bechhoefer, Chairman
Atomic Safety and
  Licensing Board Panel
U.S. NRC, MS:  T3-F23
Washington, DC  20555-0001
Mr. James C. Hardeman, Jr.
Manager, Environmental
  Radiation Program
Environmental Protection Division
Dept. of Natural Resources
State of Georgia
4244 International Parkway
Suite 114
Atlanta, GA  30354
Dr. Jean-Lou Chameau, Dean
College of Engineering
Georgia Institute of Technology
225 North Avenue
Atlanta, GA  30332-0425
Dr. Peter S. Lam
Atomic Safety and Licensing Board Panel
U.S. NRC, MS:  T3-F23
Washington, DC  20555-0001
Dr. J. Narl Davidson, Interim Dean
Chair, Technical and Safety Review
  Committee
Georgia Institute of Technology
225 North Avenue
Atlanta, GA 3033-0360
Dr. Charles Liotta, Vice Provost
  of Research and Dean of
  Graduate Studies
Georgia Institute of Technology
225 North Avenue
Atlanta, GA 30332


Dr. N. Hertel                                     -2-         June 24, 2003
Dr. N. Hertel
-2-
June 24, 2003
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document system
Room or from the Publicly Available Records (PARS) component of NRCs document system
(ADAMS). ADAMS is accessible from the NRC Web site at (the Public Electronic Reading
(ADAMS). ADAMS is accessible from the NRC Web site at (the Public Electronic Reading
Room) http://www.nrc.gov/NRC/ADAMS/index.html. Should you have any questions
Room) http://www.nrc.gov/NRC/ADAMS/index.html. Should you have any questions
concerning this inspection, please contact Mr. Stephen Holmes at 301-415-8583.
concerning this inspection, please contact Mr. Stephen Holmes at 301-415-8583.
                                              Sincerely,
Sincerely,
                                              /RA by Daniel E. Hughes, Acting for/
/RA by Daniel E. Hughes, Acting for/
                                              Patrick M. Madden, Section Chief
Patrick M. Madden, Section Chief
                                              Research and Test Reactors Section
Research and Test Reactors Section
                                              Operating Reactor Improvements Program
Operating Reactor Improvements Program
                                              Division of Regulatory Improvement Programs
Division of Regulatory Improvement Programs
                                              Office of Nuclear Reactor Regulation
Office of Nuclear Reactor Regulation
Docket No. 50-160
Docket No. 50-160
License No. R-97
License No. R-97
Enclosures: 1. NRC Inspection Report No. 50-160/2002-201
Enclosures: 1. NRC Inspection Report No. 50-160/2002-201
              2. Confirmatory Survey Plan for the Georgia Tech Research Reactor dated
        2. Confirmatory Survey Plan for the Georgia Tech Research Reactor dated  
                October 9, 2002
October 9, 2002
              3. Confirmatory Survey of the Georgia Tech Research Reactor, dated
        3. Confirmatory Survey of the Georgia Tech Research Reactor, dated
                February 2003
February 2003
cc w/enclosures: Please see next page
cc w/enclosures: Please see next page
DISTRIBUTION:
DISTRIBUTION:
PUBLIC         RORP/R&TR r/f           TDragoun       PDoyle         WEresian     PIsaac
PUBLIC
SHolmes         CBassett               MMendonca       FGillespie     WBeckner     EHylton
RORP/R&TR r/f
AAdams         BDavis (Ltr.only O5-A4)
TDragoun
ACCESSION NO.: ML031490485                                                   TEMPLATE #: NRR-106
PDoyle
  OFFICE                     RORP:LA                   RORP:RI               RORP:SC
WEresian
  NAME                           EHylton:rdr               SHolmes               PMadden
PIsaac
  DATE                         06/ 04 /2003             06/ 04 /2003           06/ 24 /2003
SHolmes
C = COVER                             E = COVER & ENCLOSURE                             N = NO COPY
CBassett
                                        OFFICIAL RECORD COPY
MMendonca
FGillespie
WBeckner
EHylton
AAdams
BDavis (Ltr.only O5-A4)
ACCESSION NO.: ML031490485
TEMPLATE #: NRR-106
OFFICE
RORP:LA
RORP:RI
RORP:SC
NAME
EHylton:rdr
SHolmes
PMadden
DATE
06/ 04 /2003
06/ 04 /2003
06/ 24 /2003
C = COVER
E = COVER & ENCLOSURE
N = NO COPY
OFFICIAL RECORD COPY




                    U. S. NUCLEAR REGULATORY COMMISSION
U. S. NUCLEAR REGULATORY COMMISSION
Docket No:   50-160
Docket No:
License No: R-97
50-160
Report No:   50-160/2002-201
License No:
Licensee:   Georgia Institute of Technology
R-97
Facility:   Georgia Institute of Technology Research Reactor (GTRR)
Report No:
Location:   900 Atlantic Drive
50-160/2002-201
            Atlanta, GA 30332
Licensee:
Dates:       October 21-23, 2002
Georgia Institute of Technology
Inspector:   Stephen W. Holmes
Facility:
Approved by: Patrick M. Madden, Section Chief
Georgia Institute of Technology Research Reactor (GTRR)
            Research and Test Reactors Section
Location:
            Operating Reactor Improvements Program
900 Atlantic Drive
            Division of Regulatory Improvement Programs
Atlanta, GA 30332
            Office of Nuclear Reactor Regulation
Dates:
October 21-23, 2002
Inspector:
Stephen W. Holmes
Approved by:
Patrick M. Madden, Section Chief
Research and Test Reactors Section
Operating Reactor Improvements Program
Division of Regulatory Improvement Programs
Office of Nuclear Reactor Regulation


                                      EXECUTIVE SUMMARY
EXECUTIVE SUMMARY
                          Georgia Institute of Technology Research Reactor
Georgia Institute of Technology Research Reactor
                                    Report No: 50-160/2002-201
Report No: 50-160/2002-201
This routine, announced inspection involved the confirmatory radiological survey and the on-site
This routine, announced inspection involved the confirmatory radiological survey and the on-site
review of selected activities being performed at the Georgia Institute of Technology Research
review of selected activities being performed at the Georgia Institute of Technology Research
Reactor. In addition, the activities audited during this inspection included: organization and
Reactor. In addition, the activities audited during this inspection included: organization and
staffing; review and audit functions; procedures; removal of materials; decommissioning
staffing; review and audit functions; procedures; removal of materials; decommissioning
activities; release criteria; confirmatory final survey; maintenance and surveillance; and
activities; release criteria; confirmatory final survey; maintenance and surveillance; and
radiation protection program. The inspector was assisted by the NRCs contractor, Oak Ridge
radiation protection program. The inspector was assisted by the NRCs contractor, Oak Ridge
Institute for Science and Education Environmental Survey and Site Assessment Program.
Institute for Science and Education Environmental Survey and Site Assessment Program.
Organization and Staffing
Organization and Staffing
!        The organizational structure and their corresponding functions were consistent with

        Technical Specification Section 5.0, Amendment No. 14, dated July 22, 1999, and the
The organizational structure and their corresponding functions were consistent with
        Decommissioning Plan for the Georgia Institute of Technology Research Reactor facility
Technical Specification Section 5.0, Amendment No. 14, dated July 22, 1999, and the
        dated June 1998.
Decommissioning Plan for the Georgia Institute of Technology Research Reactor facility
Review and Audit Functions
dated June 1998.
!        The audits conducted by the Technical Safety Review Committee and Georgia Institute
Review and Audit Functions  
        of Technology Research Reactor staff were in accordance with the requirements

        specified in Technical Specification Section 5.2. and Decommissioning Plan Section 2.4.
The audits conducted by the Technical Safety Review Committee and Georgia Institute
of Technology Research Reactor staff were in accordance with the requirements
specified in Technical Specification Section 5.2. and Decommissioning Plan Section 2.4.
Procedures
Procedures
!        The procedural control and implementation program was acceptably maintained and

        met Technical Specifications and Decommissioning Plan requirements.
The procedural control and implementation program was acceptably maintained and
met Technical Specifications and Decommissioning Plan requirements.
Removal of Materials
Removal of Materials
!        Fuel and radioactive and non-radioactive waste was removed from the site in

        accordance with the Georgia Institute of Technology Research Reactor
Fuel and radioactive and non-radioactive waste was removed from the site in
        Decommissioning Plan requirements, and Department of Transportation and Nuclear
accordance with the Georgia Institute of Technology Research Reactor
        Regulatory Commission regulations.
Decommissioning Plan requirements, and Department of Transportation and Nuclear
Regulatory Commission regulations.
Decommissioning Activities
Decommissioning Activities
!        Decommissioning activities were performed as required by Decommissioning Plan

        Section 2.3 and licensee procedures.
Decommissioning activities were performed as required by Decommissioning Plan
Section 2.3 and licensee procedures.
Release Criteria
Release Criteria
!        Duratec used the appropriate guideline and screening values, as required by the

        NRC-approved Decommissioning Plan, in performing the final survey.
Duratec used the appropriate guideline and screening values, as required by the
NRC-approved Decommissioning Plan, in performing the final survey.


                                                    -2-
-2-
Confirmatory Final Survey
Confirmatory Final Survey
!      The elevated surface activity and exposure readings in the basement compressor room

      were due to naturally occurring radioactive material.
The elevated surface activity and exposure readings in the basement compressor room
!      Based on the results of the licensees final status survey and Nuclear Regulatory
were due to naturally occurring radioactive material.
      Commissions confirmatory measurements, Georgia Institute of Technology has

      adequately demonstrated that the Georgia Institute of Technology Research Reactor
Based on the results of the licensees final status survey and Nuclear Regulatory
      facility satisfies the criteria for release for unrestricted use.
Commissions confirmatory measurements, Georgia Institute of Technology has
adequately demonstrated that the Georgia Institute of Technology Research Reactor
facility satisfies the criteria for release for unrestricted use.
Maintenance and Surveillance
Maintenance and Surveillance
!      The maintenance program was implemented as required by Georgia Institute of

      Technology procedures.
The maintenance program was implemented as required by Georgia Institute of
!      The licensee's program for surveillance and limiting conditions for operation
Technology procedures.
      confirmations satisfied Technical Specification and Decommissioning Plan

      requirements.
The licensee's program for surveillance and limiting conditions for operation
!      The licensee's design change procedures were in place and were implemented as
confirmations satisfied Technical Specification and Decommissioning Plan
      required by licensee procedures.
requirements.
Radiation Protection Program

!      The radiation protection program satisfied the requirements of 10 CFR 19.12 and
The licensee's design change procedures were in place and were implemented as
      10 CFR Part 20.1101.
required by licensee procedures.
Radiation Protection Program  

The radiation protection program satisfied the requirements of 10 CFR 19.12 and
10 CFR Part 20.1101.
.
.
!      Radiological postings satisfied regulatory requirements.

!      Surveys were performed and documented as required by 10 CFR 20.1501(a), Technical
Radiological postings satisfied regulatory requirements.
      Specifications, and licensee procedures.

!      The personnel dosimetry program was acceptably implemented and doses were in
Surveys were performed and documented as required by 10 CFR 20.1501(a), Technical
      conformance with licensee and 10 CFR Part 20 limits.
Specifications, and licensee procedures.
!      Portable survey meters, radiation monitoring, and counting lab instruments were

      maintained according to Technical Specifications, industry/equipment manufacturer
The personnel dosimetry program was acceptably implemented and doses were in
      standards, and licensee and contractor procedures.
conformance with licensee and 10 CFR Part 20 limits.
!      The evaluation and administration of the respiratory program were adequately

      performed according to Decommissioning Plan and Nuclear Regulatory Commission
Portable survey meters, radiation monitoring, and counting lab instruments were
      requirements.
maintained according to Technical Specifications, industry/equipment manufacturer
!      The program for monitoring, storage, and release of effluents was acceptable.
standards, and licensee and contractor procedures.

The evaluation and administration of the respiratory program were adequately
performed according to Decommissioning Plan and Nuclear Regulatory Commission
requirements.

The program for monitoring, storage, and release of effluents was acceptable.


                                          Report Details
Report Details
Summary of Plant Status
Summary of Plant Status
Georgia Institute of Technology (GIT), in Atlanta Georgia, has completed decommissioning its
Georgia Institute of Technology (GIT), in Atlanta Georgia, has completed decommissioning its
5 MWt Research Reactor (GTRR) and associated systems. The reactor was located within the
5 MWt Research Reactor (GTRR) and associated systems. The reactor was located within the
Neely Nuclear Research Center (NNRC) on GITs main campus. The reactor was designed for
Neely Nuclear Research Center (NNRC) on GITs main campus. The reactor was designed for
several different research applications including experiments using high intensity neutron
several different research applications including experiments using high intensity neutron
beams, gamma ray beams, and an uniform thermal neutron flux through a large sized beam.
beams, gamma ray beams, and an uniform thermal neutron flux through a large sized beam.
Although it was originally designed for 1 MWt output, it was upgraded to produce 5 MWt in
Although it was originally designed for 1 MWt output, it was upgraded to produce 5 MWt in
1974. The GTRR was built in the early 1960's as a research and training reactor. Operating
1974. The GTRR was built in the early 1960's as a research and training reactor. Operating
under the Nuclear Regulatory Commission (NRC) License No. R-97, it went critical for the first
under the Nuclear Regulatory Commission (NRC) License No. R-97, it went critical for the first
time on December 31, 1964.
time on December 31, 1964.
On November 17, 1995, all operations at the reactor ceased. GIT contracted NES, Inc. to
On November 17, 1995, all operations at the reactor ceased. GIT contracted NES, Inc. to
perform the initial characterization survey and to provide a decommissioning plan for the GTRR.
perform the initial characterization survey and to provide a decommissioning plan for the GTRR.  
In October 1997, NES performed a characterization survey of the GTRR, based upon the GIT
In October 1997, NES performed a characterization survey of the GTRR, based upon the GIT
Decommissioning Project - Radiological Characterization Plan. Results of the characterization
Decommissioning Project - Radiological Characterization Plan. Results of the characterization
survey were provided in NES Georgia Institute of Technology Research Reactor
survey were provided in NES Georgia Institute of Technology Research Reactor  
Decommissioning Project Characterization Report issued May 1998. GIT requested the NRC,
Decommissioning Project Characterization Report issued May 1998. GIT requested the NRC,
by letters dated July 1, 1998, February 8, 1999, and May 28, 1999, to grant them the
by letters dated July 1, 1998, February 8, 1999, and May 28, 1999, to grant them the
authorization to decommission the reactor according to their submitted decommissioning plan.
authorization to decommission the reactor according to their submitted decommissioning plan.  
On July 22, 1999, the NRC issued Amendment No. 14 to the reactor licence that approved
On July 22, 1999, the NRC issued Amendment No. 14 to the reactor licence that approved
GITs Decommissioning Plan. GIT contracted with IT Corporation (IT) to decommission the
GITs Decommissioning Plan. GIT contracted with IT Corporation (IT) to decommission the
GTRR facility. IT, through its subcontractor GTS Duratec (Duratec), started decommissioning
GTRR facility. IT, through its subcontractor GTS Duratec (Duratec), started decommissioning
operations December 1999. Final waste shipment was made August 2001.
operations December 1999. Final waste shipment was made August 2001.
The Final Status Survey Report for the GTRR facility was completed and issued June 2002.
The Final Status Survey Report for the GTRR facility was completed and issued June 2002.  
According to the report, all contaminated systems and components had been removed from the
According to the report, all contaminated systems and components had been removed from the
site. Potentially contaminated structural surfaces identified during characterization surveys had
site. Potentially contaminated structural surfaces identified during characterization surveys had
been removed and/or remediated such that the residual radioactivity is less than NRC
been removed and/or remediated such that the residual radioactivity is less than NRC
Regulatory Guide 1.86 limits.
Regulatory Guide 1.86 limits.  
The NRC requested Oak Ridge Institute for Science and Educations (ORISE) Environmental
The NRC requested Oak Ridge Institute for Science and Educations (ORISE) Environmental
Survey and Site Assessment Program (ESSAP) to perform a confirmatory survey of the GTRR
Survey and Site Assessment Program (ESSAP) to perform a confirmatory survey of the GTRR
facility. On October 21-23, 2002, the ESSAP team, accompanied by an NRC inspector,
facility. On October 21-23, 2002, the ESSAP team, accompanied by an NRC inspector,
conducted this survey.
conducted this survey.
1.     ORGANIZATIONAL STRUCTURE AND FUNCTIONS
1.
      a. Inspection Scope (Inspection Procedures (IP) 69001 and 40755)
ORGANIZATIONAL STRUCTURE AND FUNCTIONS  
          The inspector reviewed selected aspects of:
a. Inspection Scope (Inspection Procedures (IP) 69001 and 40755)
          * organization and staffing
The inspector reviewed selected aspects of:
          * qualifications
*
          * management responsibilities
organization and staffing
          * administrative controls
*
          * decommissioning activity records
qualifications
          * GTRR Decommissioning Plan (DP) dated June 1998
*
management responsibilities
*
administrative controls
*
decommissioning activity records  
*
GTRR Decommissioning Plan (DP) dated June 1998


                                  -2-
-2-
* Technical Specifications (TS), Amendment No. 14, dated July 22, 1999
*
Technical Specifications (TS), Amendment No. 14, dated July 22, 1999


                                            -3-
-3-
  b. Observations and Findings
b. Observations and Findings
      The general organizational structure and staffing had not changed since the last
The general organizational structure and staffing had not changed since the last
      inspection. The organizational structure and staffing at the facility were as reported in
inspection. The organizational structure and staffing at the facility were as reported in
      the Annual Report and as required by TS Section 5.1 and Figure 5.1. Review of
the Annual Report and as required by TS Section 5.1 and Figure 5.1. Review of
      records verified that management responsibilities were administered as required by
records verified that management responsibilities were administered as required by
      TS Sections 5.2 thru 5.6 and applicable procedures.
TS Sections 5.2 thru 5.6 and applicable procedures.  
      The decommissioning of the reactor required GTRR management to assume
The decommissioning of the reactor required GTRR management to assume
      additional project management responsibilities. Through record reviews and
additional project management responsibilities. Through record reviews and
      interviews with the reactor manager, radiation safety officer (RSO), and Duratec
interviews with the reactor manager, radiation safety officer (RSO), and Duratec
      project manager, the inspector confirmed that both GTRR management and the
project manager, the inspector confirmed that both GTRR management and the
      decommissioning project organization structures were as required by DP Section 2.4
decommissioning project organization structures were as required by DP Section 2.4
      and Figure 2.2.
and Figure 2.2.  
  c. Conclusions
c.
      The organizational staff and their corresponding functions and responsibilities were
Conclusions
      consistent with TS Section 5.0, Amendment No. 14, dated July 22, 1999, and the DP
The organizational staff and their corresponding functions and responsibilities were
      for the GTRR facility dated June 1998
consistent with TS Section 5.0, Amendment No. 14, dated July 22, 1999, and the DP
2. REVIEW AND AUDIT FUNCTIONS
for the GTRR facility dated June 1998
  a. Inspection Scope (IPs 69001 and 40755)
2.
      The inspector reviewed selected aspects of:
REVIEW AND AUDIT FUNCTIONS
      *   Technical Safety Review Committee (TSRC) meeting minutes
a. Inspection Scope (IPs 69001 and 40755)
      *   GTRR staff safety review records
The inspector reviewed selected aspects of:
      *   TSRC and GTRR staff audit records
*
      *   responses to safety reviews and audits
Technical Safety Review Committee (TSRC) meeting minutes
      *   personnel qualifications
*
      *   GTRR DP dated June 1998
GTRR staff safety review records
      *   TS, Amendment No. 14, dated July 22, 1999
*
  b. Observations and Findings
TSRC and GTRR staff audit records
      DP Section 2.4 states that the TSRC: 1) will review and approve all plans, policies and
*
      procedures to be performed under the GTRR Decommissioning Project, 2) will review
responses to safety reviews and audits
      and audit the decontamination and decommissioning project operations and activities,
*
      3) members will be appointed by the President of Georgia Tech, and 4) will keep a
personnel qualifications  
      written record of the meetings and will report directly to the President.
*
      During inspections in 2000 and 2002, the inspector reviewed the qualifications of the
GTRR DP dated June 1998
      TSRC members and confirmed that they met the requirements specified in TS
*
      Section 5.2 and DP Section 2.4. The results of the 2000 inspections were
TS, Amendment No. 14, dated July 22, 1999
      documented in NRC Inspection Report (IR) No. 50-160/2000-201 dated March 15,
b. Observations and Findings
      2000, NRC IR No. 50-160/2000-202 dated August 31, 2000, and NRC IR
DP Section 2.4 states that the TSRC: 1) will review and approve all plans, policies and
procedures to be performed under the GTRR Decommissioning Project, 2) will review
and audit the decontamination and decommissioning project operations and activities,
3) members will be appointed by the President of Georgia Tech, and 4) will keep a
written record of the meetings and will report directly to the President.
During inspections in 2000 and 2002, the inspector reviewed the qualifications of the
TSRC members and confirmed that they met the requirements specified in TS
Section 5.2 and DP Section 2.4. The results of the 2000 inspections were
documented in NRC Inspection Report (IR) No. 50-160/2000-201 dated March 15,
2000, NRC IR No. 50-160/2000-202 dated August 31, 2000, and NRC IR


                                            -4-
-4-
      No. 50-160/2000-203 dated December 1, 2000. The inspector noted that the TSRC
No. 50-160/2000-203 dated December 1, 2000. The inspector noted that the TSRC
      met more often than the required semiannual frequency and that a quorum was
met more often than the required semiannual frequency and that a quorum was
      present each time. The inspector reviewed the minutes of the TSRC and determined
present each time. The inspector reviewed the minutes of the TSRC and determined
      that they provided guidance, direction, operations oversight, and 10 CFR 50.59
that they provided guidance, direction, operations oversight, and 10 CFR 50.59
      request reviews as required by the DP and TS.
request reviews as required by the DP and TS.
      TSRC meeting minutes and audit records and GTRR staff audit records showed that
TSRC meeting minutes and audit records and GTRR staff audit records showed that
      safety reviews and audits were conducted as required by TS Section 5.2(d). The
safety reviews and audits were conducted as required by TS Section 5.2(d). The
      content of the audits and safety reviews were consistent with the TS. These reviews
content of the audits and safety reviews were consistent with the TS. These reviews
      provided appropriate guidance, direction, and oversight to ensure satisfactory
provided appropriate guidance, direction, and oversight to ensure satisfactory
      decommissioning of the reactor.
decommissioning of the reactor.
      By examining the TSRCs review of the DP and their audits of the operations and
By examining the TSRCs review of the DP and their audits of the operations and
      training programs, the inspector determined that the safety reviews, audits, and
training programs, the inspector determined that the safety reviews, audits, and
      associated findings were satisfactory and that the licensee took the appropriate
associated findings were satisfactory and that the licensee took the appropriate
      corrective actions in response to the findings.
corrective actions in response to the findings.
      The inspector reviewed selected decommissioning and facility change approvals.
The inspector reviewed selected decommissioning and facility change approvals.  
      Records and observations showed that changes at the facility were acceptably
Records and observations showed that changes at the facility were acceptably
      reviewed in accordance with 10 CFR 50.59 and applicable licensee administrative
reviewed in accordance with 10 CFR 50.59 and applicable licensee administrative
      controls. None of the changes constituted an unreviewed safety question or required
controls. None of the changes constituted an unreviewed safety question or required
      a change to the TS. The inspector determined that TSRC 10 CFR 50.59 request
a change to the TS. The inspector determined that TSRC 10 CFR 50.59 request
      reviews were adequately performed.
reviews were adequately performed.
  c. Conclusions
c.
      The audits conducted by the TSRC and GTRR staffs were in accordance with the
Conclusions
      requirements specified in TS Section 5.2 and DP Section 2.4. TSRC 10 CFR 50.59
The audits conducted by the TSRC and GTRR staffs were in accordance with the
      request reviews were adequately performed.
requirements specified in TS Section 5.2 and DP Section 2.4. TSRC 10 CFR 50.59
3. PROCEDURES
request reviews were adequately performed.
  a. Inspection Scope (IPs 69001 and 40755)
3.
      The inspector reviewed selected aspects of:
PROCEDURES
      *   administrative controls
a. Inspection Scope (IPs 69001 and 40755)
      *   records for changes and temporary changes
The inspector reviewed selected aspects of:
      *   DP dated June 1998
*
      *   TS, Amendment No. 14, dated July 22, 1999
administrative controls
      *   decommissioning procedures
*
      *   logs and records
records for changes and temporary changes
  b. Observations and Findings
*
      During decommissioning activities, the inspector confirmed that written health physics
DP dated June 1998
      (HP) and decommissioning procedures were available for those tasks and items
*
      required by TS Section 5.3 and the DP Sections 2.3.1.1. and 3.1.2.2. The procedures
TS, Amendment No. 14, dated July 22, 1999
*
decommissioning procedures
*
logs and records
b. Observations and Findings  
During decommissioning activities, the inspector confirmed that written health physics
(HP) and decommissioning procedures were available for those tasks and items
required by TS Section 5.3 and the DP Sections 2.3.1.1. and 3.1.2.2. The procedures


                                            -5-
-5-
      were routinely updated and then approved by the TSRC while minor modifications to
were routinely updated and then approved by the TSRC while minor modifications to
      the procedures were approved by the facility director.
the procedures were approved by the facility director.
      Decommissioning procedures and operating plans reviewed and approved by the
Decommissioning procedures and operating plans reviewed and approved by the
      TSRC included those dealing with:
TSRC included those dealing with:
      -   Initial Radiological Survey Plan and Procedures
-
      -   Health and Safety Plan and Procedures
Initial Radiological Survey Plan and Procedures
      -   Waste Management Plan and Procedures
-  
      -   Management Plan
Health and Safety Plan and Procedures
      -   Quality Assurance Plan and Procedures
-  
      -   Radiation Protection Plan and Procedures
Waste Management Plan and Procedures
      -   Decommissioning Work Plan
-  
      -   Final Radiological Survey Plan
Management Plan
      Through review of the 2000 training records and interviews with staff, the inspector
-  
      determined that the training of staff and contractor personnel concerning procedures
Quality Assurance Plan and Procedures
      was adequate. During the inspectors tours of the facility, it was observed that
-  
      personnel performing radiation surveys, conducting instrument checks, issuing
Radiation Protection Plan and Procedures
      dosimetry, and performing the decommissioning work were doing so in accordance
-  
      with applicable procedures.
Decommissioning Work Plan
  c. Conclusions
-  
      Based on the procedures and records reviewed and observations of personnel during
Final Radiological Survey Plan
      the inspections in 2000, it was determined that the procedural control and
Through review of the 2000 training records and interviews with staff, the inspector
      implementation program was acceptably maintained and met TS and DP
determined that the training of staff and contractor personnel concerning procedures
      requirements.
was adequate. During the inspectors tours of the facility, it was observed that
4. REMOVAL OF MATERIALS
personnel performing radiation surveys, conducting instrument checks, issuing
  a. Inspection Scope (IPs 69001, 86740, and 85102)
dosimetry, and performing the decommissioning work were doing so in accordance
      The inspector reviewed selected aspects of:
with applicable procedures.
      *   transportation records
c.
      *   disposal records
Conclusions
      *   NRC Forms 741 and 742
Based on the procedures and records reviewed and observations of personnel during
      *   DP dated June 1998
the inspections in 2000, it was determined that the procedural control and
  b. Observations and Findings
implementation program was acceptably maintained and met TS and DP
      From 1964 through 1995, the licensee operated a heavy water moderated and cooled
requirements.
      research reactor at the NNRC. The reactor was shut down on November 17, 1995, in
4.
      preparation for the summer Olympic Games in Atlanta, GA, and was never restarted.
REMOVAL OF MATERIALS
      As noted in a previous NRC IR No. 50-160/1996-01, the irradiated fuel was shipped to
a. Inspection Scope (IPs 69001, 86740, and 85102)
      the Savannah River Site on February 18, 1996. The licensee had previously shipped
The inspector reviewed selected aspects of:
*
transportation records
*
disposal records
*
NRC Forms 741 and 742
*
DP dated June 1998
b. Observations and Findings
From 1964 through 1995, the licensee operated a heavy water moderated and cooled
research reactor at the NNRC. The reactor was shut down on November 17, 1995, in
preparation for the summer Olympic Games in Atlanta, GA, and was never restarted.  
As noted in a previous NRC IR No. 50-160/1996-01, the irradiated fuel was shipped to
the Savannah River Site on February 18, 1996. The licensee had previously shipped


                                              -6-
-6-
      the unirradiated fuel to the Oak Ridge National Laboratory site in Tennessee on
the unirradiated fuel to the Oak Ridge National Laboratory site in Tennessee on
      January 31, 1996. The inspector confirmed that, as noted by DP Section 1.5, all fuel
January 31, 1996. The inspector confirmed that, as noted by DP Section 1.5, all fuel
      had been removed from NNRC prior to decommissioning.
had been removed from NNRC prior to decommissioning.
      Fifty-six (56) total radioactive waste shipments were made during the GTRR
Fifty-six (56) total radioactive waste shipments were made during the GTRR
      decommissioning. The final waste shipment occurred on August 3, 2001. Radioactive
decommissioning. The final waste shipment occurred on August 3, 2001. Radioactive
      waste was sent to one of four consignees: 1 Duratek Inc.; 2 CNSI Barnwell; 3
waste was sent to one of four consignees: 1 Duratek Inc.; 2 CNSI Barnwell; 3  
      Envirocare of Utah; and 4 Westinghouse Savannah River Site. During 2000, the
Envirocare of Utah; and 4 Westinghouse Savannah River Site. During 2000, the
      inspector confirmed through records review, interviews with licensee staff, and actual
inspector confirmed through records review, interviews with licensee staff, and actual
      observation, that radioactive waste was disposed of as required by DP Section 3.2
observation, that radioactive waste was disposed of as required by DP Section 3.2
      and in accordance with Department of Transportation and NRC regulations.
and in accordance with Department of Transportation and NRC regulations.
  c. Conclusions
c.
      As a result of the records review and on-site observations made during
Conclusions
      decommissioning tours, it was confirmed that the fuel and radioactive waste were
As a result of the records review and on-site observations made during
      removed from the site in accordance with the GTRR DP requirements, and
decommissioning tours, it was confirmed that the fuel and radioactive waste were
      Department of Transportation and NRC regulations.
removed from the site in accordance with the GTRR DP requirements, and
5. DECOMMISSIONING ACTIVITIES
Department of Transportation and NRC regulations.  
  a. Inspection Scope (IPs 69001 and 40755)
5.
      The inspector reviewed selected aspects of:
DECOMMISSIONING ACTIVITIES
      *   operational logs and records
a. Inspection Scope (IPs 69001 and 40755)
      *   decommissioning procedures
The inspector reviewed selected aspects of:
      *   decommissioning logs and records
*
      *   DP dated June 1998
operational logs and records
      *   the facility during tours
*
  b. Observations and Findings
decommissioning procedures
      As noted above, the reactor was permanently shut down on November 17, 1995. All
*
      irradiated reactor fuel was removed from the site on February 18, 1996. On July 22,
decommissioning logs and records
      1999, following a request by the licensee and a review by the NRC, Amendment No.
*
      14 to Facility License No. R-97 was issued which authorized decommissioning of the
DP dated June 1998
      GTRR. The licensees contractor started its decommissioning of the facility in January
*
      2000. (Actual decommissioning of the facility was completed in May 2001, although
the facility during tours
      the contractors final survey of the facility continued for several months afterwards.)
b. Observations and Findings
      Decommissioning activities focused on the dismantling and removal of the reactor
As noted above, the reactor was permanently shut down on November 17, 1995. All
      proper, its support structures, auxiliary equipment and components, and the biological
irradiated reactor fuel was removed from the site on February 18, 1996. On July 22,
      shield. The inspector examined the following selected tasks as directly described in
1999, following a request by the licensee and a review by the NRC, Amendment No.
      DP Section 2.3, Decommissioning Activities and Tasks:
14 to Facility License No. R-97 was issued which authorized decommissioning of the
      Reactor Complex
GTRR. The licensees contractor started its decommissioning of the facility in January
2000. (Actual decommissioning of the facility was completed in May 2001, although
the contractors final survey of the facility continued for several months afterwards.)
Decommissioning activities focused on the dismantling and removal of the reactor
proper, its support structures, auxiliary equipment and components, and the biological
shield. The inspector examined the following selected tasks as directly described in
DP Section 2.3, Decommissioning Activities and Tasks:
Reactor Complex


                                    -7-
-7-
Vertical Beam Ports - The vertical beam ports will be removed - including the
Vertical Beam Ports - The vertical beam ports will be removed - including the
thimbles, thimble plugs, sample tubes, and liners. The lead will be removed from
thimbles, thimble plugs, sample tubes, and liners. The lead will be removed from
the plugs and sent to a mixed waste processor. The other items will be
the plugs and sent to a mixed waste processor. The other items will be
segmented as necessary, packaged, and disposed of as radioactive waste.
segmented as necessary, packaged, and disposed of as radioactive waste.
Shim Safety Rods and Drives - The four shim safety rods will be disconnected
Shim Safety Rods and Drives - The four shim safety rods will be disconnected
from the drives, removed through the top shield, cut in half, and disposed of as
from the drives, removed through the top shield, cut in half, and disposed of as
mixed waste. The shim safety rod drives will be disconnected, removed,
mixed waste. The shim safety rod drives will be disconnected, removed,
segmented, and disposed of as radioactive waste.
segmented, and disposed of as radioactive waste.
Horizontal Beam Gates - The ten horizontal beam gate drive motors will be
Horizontal Beam Gates - The ten horizontal beam gate drive motors will be
disconnected and removed. The gates will be separated from the shafts and cut
disconnected and removed. The gates will be separated from the shafts and cut
open. The lead inside will be removed and disposed of as mixed waste, and the
open. The lead inside will be removed and disposed of as mixed waste, and the
remainder disposed of as radioactive waste.
remainder disposed of as radioactive waste.
Spent Fuel Storage Holes - The spent fuel storage hole plugs will be removed and
Spent Fuel Storage Holes - The spent fuel storage hole plugs will be removed and
disposed of as radioactive waste. The hole liners will be core drilled out and each
disposed of as radioactive waste. The hole liners will be core drilled out and each
liner will be cut in half, packaged, and disposed of as radioactive waste.
liner will be cut in half, packaged, and disposed of as radioactive waste.
Piping and Instrumentation - This task involved the removal of miscellaneous
Piping and Instrumentation - This task involved the removal of miscellaneous
piping and ventilation in and around the reactor complex. The materials will be
piping and ventilation in and around the reactor complex. The materials will be
disposed of as radioactive waste.
disposed of as radioactive waste.
Lead Cover Plate - The lead cover plate will be removed in two distinct pieces - the
Lead Cover Plate - The lead cover plate will be removed in two distinct pieces - the
inner plate and outer plate. The 24 lead and steel port plugs will be removed from
inner plate and outer plate. The 24 lead and steel port plugs will be removed from
the inner plate and cut open with an abrasive saw. The lead will be removed and
the inner plate and cut open with an abrasive saw. The lead will be removed and
disposed of as mixed waste, and the steel will be disposed of as radioactive waste.
disposed of as mixed waste, and the steel will be disposed of as radioactive waste.
Upper Top Shield - The upper top shield will also be removed in two distinct pieces
Upper Top Shield - The upper top shield will also be removed in two distinct pieces
- the inner shield plug and outer shield plug. The 24 concrete and steel inner port
- the inner shield plug and outer shield plug. The 24 concrete and steel inner port
plugs and eight concrete and steel outer port plugs will be removed and disposed
plugs and eight concrete and steel outer port plugs will be removed and disposed
of as radioactive waste. The inner concrete and steel upper top shield will be
of as radioactive waste. The inner concrete and steel upper top shield will be
removed and disposed of as radioactive waste. The outer concrete and steel
removed and disposed of as radioactive waste. The outer concrete and steel
upper shield plug will be removed and disposed of as radioactive waste.
upper shield plug will be removed and disposed of as radioactive waste.
Lower Shield Plug - The 31 lead, concrete, and steel port plugs will be removed
Lower Shield Plug - The 31 lead, concrete, and steel port plugs will be removed
from the lower top shield plug and cut open with an abrasive saw. The lead will be
from the lower top shield plug and cut open with an abrasive saw. The lead will be
removed and disposed of as mixed waste. The remaining concrete and steel will
removed and disposed of as mixed waste. The remaining concrete and steel will
be disposed of as radioactive waste.
be disposed of as radioactive waste.
Fuel Spray Manifold - The fuel spray manifold pipe will be cut free within the
Fuel Spray Manifold - The fuel spray manifold pipe will be cut free within the
Line 465: Line 596:
waste.
waste.
Reactor Vessel - A remote operated robotic arm will be installed in the reactor
Reactor Vessel - A remote operated robotic arm will be installed in the reactor
vessel to facilitate segmentation. Using an abrasive saw connected to the robotic
vessel to facilitate segmentation. Using an abrasive saw connected to the robotic
arm, the horizontal beam ports and through tubes will be cut free and lifted out.
arm, the horizontal beam ports and through tubes will be cut free and lifted out.  


                                    -8-
-8-
The bottom pipes will be core bored and removed. The reactor vessel will be cut
The bottom pipes will be core bored and removed. The reactor vessel will be cut
into sections using an abrasive saw mounted on the robotic arm. Lifting holes will
into sections using an abrasive saw mounted on the robotic arm. Lifting holes will
first be drilled into each section with a drill attached to the robotic arm, and each
first be drilled into each section with a drill attached to the robotic arm, and each
section rigged. Each section will be lifted out with the overhead crane, transferred
section rigged. Each section will be lifted out with the overhead crane, transferred
to the packaging area and disposed of as radioactive waste.
to the packaging area and disposed of as radioactive waste.
Graphite Retaining Sleeve - The graphite retaining sleeve will be removed in a
Graphite Retaining Sleeve - The graphite retaining sleeve will be removed in a
similar fashion as the vessel. Each section will be disposed of as radioactive
similar fashion as the vessel. Each section will be disposed of as radioactive
waste.
waste.
Graphite Removal - The 4-inch by 4-inch graphite stringers will be removed using
Graphite Removal - The 4-inch by 4-inch graphite stringers will be removed using
long-handled tools from either the top of the biological shield or through the
long-handled tools from either the top of the biological shield or through the
thermal column. The graphite will be packaged and disposed of as radioactive
thermal column. The graphite will be packaged and disposed of as radioactive
waste.
waste.
Horizontal Beam Ports - The beam port and through tube plugs will be removed
Horizontal Beam Ports - The beam port and through tube plugs will be removed
and disposed as radioactive waste. Lead will first be removed from the through
and disposed as radioactive waste. Lead will first be removed from the through
tube plugs by cutting the top off the plugs with an abrasive saw. The lead will be
tube plugs by cutting the top off the plugs with an abrasive saw. The lead will be
disposed of as mixed waste.
disposed of as mixed waste.
Boral Removal - The 1/4-inch boral sheet staked to the inside of the steel tank will
Boral Removal - The 1/4-inch boral sheet staked to the inside of the steel tank will
be removed in a similar fashion as the vessel. Each section will be disposed of as
be removed in a similar fashion as the vessel. Each section will be disposed of as
radioactive waste.
radioactive waste.
Inner Steel Tank - The inner steel tank will follow a similar removal scenario to that
Inner Steel Tank - The inner steel tank will follow a similar removal scenario to that
described for the boral removal. The tank will be cut into sections using an
described for the boral removal. The tank will be cut into sections using an
abrasive saw mounted on the robotic arm. Lifting holes will first be drilled into
abrasive saw mounted on the robotic arm. Lifting holes will first be drilled into
each section, and each section will then be rigged. After cutting, the section will be
each section, and each section will then be rigged. After cutting, the section will be
transferred to the packaging area using the overhead crane. Each section will be
transferred to the packaging area using the overhead crane. Each section will be
disposed of as radioactive waste.
disposed of as radioactive waste.
Lead Thermal Shield - The lead thermal shield was formed by pouring molten lead
Lead Thermal Shield - The lead thermal shield was formed by pouring molten lead
into the space between the inner and outer steel tanks. With the inner tank and
into the space between the inner and outer steel tanks. With the inner tank and
cooling coils removed, the lead will be pried free of the outer tank in easily handled
cooling coils removed, the lead will be pried free of the outer tank in easily handled
pieces with long-handled tools. The pieces will be lowered into a basket and
pieces with long-handled tools. The pieces will be lowered into a basket and
transferred to a waste container. The lead will be disposed of as mixed waste.
transferred to a waste container. The lead will be disposed of as mixed waste.
Outer Steel Tank - The outer steel tank will be removed using the same methods
Outer Steel Tank - The outer steel tank will be removed using the same methods
as the removal of the inner steel tank. The tank may have to be pried free of the
as the removal of the inner steel tank. The tank may have to be pried free of the
concrete prior to removal. Each section will be disposed of as radioactive waste.
concrete prior to removal. Each section will be disposed of as radioactive waste.
Thermal Column Shutter and Shielding - In order to remove the thermal column
Thermal Column Shutter and Shielding - In order to remove the thermal column
shutter and shields, the two thermal column door plugs will be removed first,
shutter and shields, the two thermal column door plugs will be removed first,
segmented with an abrasive saw and the lead removed. The steel cover plate will
segmented with an abrasive saw and the lead removed. The steel cover plate will
then be removed, segmented and packaged. The exposed lead shield will then be
then be removed, segmented and packaged. The exposed lead shield will then be
removed and packaged for processing. The concrete and steel blocks will also be
removed and packaged for processing. The concrete and steel blocks will also be
removed and packaged. Segmenting of these blocks is not required. The
removed and packaged. Segmenting of these blocks is not required. The
concrete, steel and lead doors will be removed, segmented and packaged. Any
concrete, steel and lead doors will be removed, segmented and packaged. Any


                                              -9-
-9-
          remaining lead will then be removed and packaged for disposal. The concrete and
remaining lead will then be removed and packaged for disposal. The concrete and
          steel will be disposed of as radioactive waste and the lead as mixed waste.
steel will be disposed of as radioactive waste and the lead as mixed waste.
          Biomedical Irradiation Facility Shutter and Shielding - In order to remove the
Biomedical Irradiation Facility Shutter and Shielding - In order to remove the
          biomedical irradiation facility shutter, the aluminum cover plate will be removed first
biomedical irradiation facility shutter, the aluminum cover plate will be removed first
          and segmented. The exposed lead bricks will then be removed and packaged.
and segmented. The exposed lead bricks will then be removed and packaged.  
          The movable shield plugs and doors will also be removed. The outer bismuth
The movable shield plugs and doors will also be removed. The outer bismuth
          shield, the water tank, and the inner bismuth plug will be removed and packaged.
shield, the water tank, and the inner bismuth plug will be removed and packaged.  
          Due to the package restrictions, segmenting of these items will have to be
Due to the package restrictions, segmenting of these items will have to be
          performed. The materials will be disposed as radioactive waste.
performed. The materials will be disposed as radioactive waste.
          Fission Chambers - The fission chambers will be removed and packaged for
Fission Chambers - The fission chambers will be removed and packaged for
          disposal. The remaining U-235 will be packaged and shipped to an appropriate
disposal. The remaining U-235 will be packaged and shipped to an appropriate
          site.
site.
      Biological Shield
Biological Shield
          Activated Concrete - Due to the relatively small amount of activated concrete and
Activated Concrete - Due to the relatively small amount of activated concrete and
          the limited access, the concrete will be removed with a bobcat/jackhammer. The
the limited access, the concrete will be removed with a bobcat/jackhammer. The
          waste will be packaged and disposed of as radioactive waste.
waste will be packaged and disposed of as radioactive waste.
          Bottom Shield - As above, due to the relatively small amount of activated concrete
Bottom Shield - As above, due to the relatively small amount of activated concrete
          and the limited access the concrete will be removed with a bobcat/jackhammer.
and the limited access the concrete will be removed with a bobcat/jackhammer.  
          The waste will be packaged and disposed of as radioactive waste.
The waste will be packaged and disposed of as radioactive waste.
      During the inspections in 2000, the inspector observed various of these activities as
During the inspections in 2000, the inspector observed various of these activities as
      they were being conducted including: piping and instrumentation, upper top shield,
they were being conducted including: piping and instrumentation, upper top shield,
      graphite removal, lead thermal shield, fission chambers, and activated concrete. In
graphite removal, lead thermal shield, fission chambers, and activated concrete. In
      order to verify that all the above tasks had been performed in accordance with the DP,
order to verify that all the above tasks had been performed in accordance with the DP,
      the inspector also reviewed the related licensee and contractor records and surveys,
the inspector also reviewed the related licensee and contractor records and surveys,
      and toured the facility. The inspector determined that the above tasks had been
and toured the facility. The inspector determined that the above tasks had been
      completed in accordance with final approved DP.
completed in accordance with final approved DP.
  c. Conclusions
c.
      Based on the observations made during the inspection, decommissioning activities
Conclusions
      have been performed as required by DP Section 2.3 and licensee procedures.
Based on the observations made during the inspection, decommissioning activities
6. RELEASE CRITERIA
have been performed as required by DP Section 2.3 and licensee procedures.
  a. Inspection Scope (IPs 69001 and 40755)
6.
      The inspector reviewed selected aspects of:
RELEASE CRITERIA
      *   DP dated June 1998
a. Inspection Scope (IPs 69001 and 40755)
      *   Georgia Institute of Technology Research Reactor Decommissioning Project
The inspector reviewed selected aspects of:
          Characterization Report, issued May 1998
*
      *   Final Status Survey Report for the GTRR facility issued June 2002
DP dated June 1998
*
Georgia Institute of Technology Research Reactor Decommissioning Project
Characterization Report, issued May 1998
*
Final Status Survey Report for the GTRR facility issued June 2002


                                          -10-
-10-
b. Observations and Findings
b. Observations and Findings
  The primary contaminants of concern for the GTRR are beta-gamma emittersfission
The primary contaminants of concern for the GTRR are beta-gamma emittersfission
  and activation productsresulting from reactor operation. The NRC-approved
and activation productsresulting from reactor operation. The NRC-approved
  guidelines for release for unrestricted use for building surfaces were based on those
guidelines for release for unrestricted use for building surfaces were based on those
  for beta-gamma emitters contained in NRC Regulatory Guide 1.86 (NRC 1974). These
for beta-gamma emitters contained in NRC Regulatory Guide 1.86 (NRC 1974). These
  guidelines are:
guidelines are:
        5,000 -- dpm/100 cm2, averaged over a 1 m2 area
  5,000 -- dpm/100 cm2, averaged over a 1 m2 area
      15,000 -- dpm/100 cm2, maximum in a 100 cm2 area
15,000 -- dpm/100 cm2, maximum in a 100 cm2 area
        1,000 -- dpm/100 cm2, removable.
  1,000 -- dpm/100 cm2, removable.
  However, due to the presence of the hard-to-detect-radionuclides H-3 and Fe-55, the
However, due to the presence of the hard-to-detect-radionuclides H-3 and Fe-55, the
  above guidelines were modified to account for the contributing activity of these
above guidelines were modified to account for the contributing activity of these
  radionuclides. The modified guidelines are (Shaw 2002):
radionuclides. The modified guidelines are (Shaw 2002):
      2,400 -- dpm/100 cm2 average activity in a 1 m2 area
2,400 -- dpm/100 cm2 average activity in a 1 m2 area
      7,200 -- dpm/100 cm2 maximum activity in a 100 cm2 area
7,200 -- dpm/100 cm2 maximum activity in a 100 cm2 area
        313 -- dpm/100 cm2 removable activity
  313 -- dpm/100 cm2 removable activity
  GITs final survey plan (GTS 2000) stated that radionuclide concentrations in soil for
GITs final survey plan (GTS 2000) stated that radionuclide concentrations in soil for
  the contaminants of concern would meet the NRC published (Federal Register Vol. 64
the contaminants of concern would meet the NRC published (Federal Register Vol. 64
  page 68396, December 7, 1999) screening values for selected radionuclides in
page 68396, December 7, 1999) screening values for selected radionuclides in
  surface soils. The screening values for the GTRR radionuclides of interest are
surface soils. The screening values for the GTRR radionuclides of interest are
  summarized below.
summarized below.
                  Radionuclide           Guideline Value (pCi/g)
Radionuclide
                        H-3                         110
Guideline Value (pCi/g)
                      Fe-55                       10,000
H-3
                    Pu-239/240                       2.3
110
                    U-233/234                       13.0
Fe-55
                      U-238                         14.0
10,000
                      Ni-59                       5,500
Pu-239/240
                      Cs-134                         5.7
2.3
                      Cs-137                         11.0
U-233/234
                      Co-60                         3.8
13.0
                      Eu-152                         8.7
U-238
                      Eu-154                         8.0
14.0
                      Mn-54                         15.0
Ni-59
                    Ag-110m                         3.9
5,500
                      Zn-65                         6.2
Cs-134
                      Sr-90                         1.7
5.7
                      C-14                         12.0
Cs-137
                      Ni-63                       2,100
11.0
                      Tc-99                         19.0
Co-60
3.8
Eu-152
8.7
Eu-154
8.0
Mn-54
15.0
Ag-110m
3.9
Zn-65
6.2
Sr-90
1.7
C-14
12.0
Ni-63
2,100
Tc-99
19.0


                                            -11-
-11-
      The inspector observed and interviewed Duratec, ITs representative.
The inspector observed and interviewed Duratec, ITs representative.  
      The inspector determined that Duratec used the appropriate guideline and screening
The inspector determined that Duratec used the appropriate guideline and screening
      values as calculated in the Characterization Report and specified in the approved DP.
values as calculated in the Characterization Report and specified in the approved DP.
  c. Conclusions
c.   Conclusions
      Duratec used the appropriate guideline and screening values as required by the DP, in
Duratec used the appropriate guideline and screening values as required by the DP, in
      performing the final survey.
performing the final survey.
7. CONFIRMATORY FINAL SURVEY
7.
  a. Inspection Scope (IPs 69001 and 40755)
CONFIRMATORY FINAL SURVEY
      The inspector reviewed selected aspects of:
a. Inspection Scope (IPs 69001 and 40755)
      *   DP dated June 1998
The inspector reviewed selected aspects of:
      *   Georgia Institute of Technology Research Reactor Decommissioning Project
*
          Characterization Report, issued May 1998
DP dated June 1998
      *   Final Status Survey Report for the GTRR facility issued June 2002
*
  b. Observations and Findings
Georgia Institute of Technology Research Reactor Decommissioning Project
      (1) Overview
Characterization Report, issued May 1998
          DP Section 4.0, Proposed Final Radiation Survey Plan, describes the final
*
          radiation survey to be conducted of the facility prior to license termination. This
Final Status Survey Report for the GTRR facility issued June 2002
          survey is required in order to ensure that the area satisfies the unrestricted
b. Observations and Findings
          release criteria for radioactive material according to NUREG/CR- 5849. (DP
(1) Overview
          Section 4.1) Additionally, DP Section 4.2.3 specifies, As stated in
DP Section 4.0, Proposed Final Radiation Survey Plan, describes the final
          NUREG/CR-5849, proper documentation of every aspect of the final survey is
radiation survey to be conducted of the facility prior to license termination. This
          necessary for future reference to the decommissioning survey. An accurate
survey is required in order to ensure that the area satisfies the unrestricted
          mapping of the reactor containment building and surrounding areas within this
release criteria for radioactive material according to NUREG/CR- 5849. (DP
          decommissioning project will be maintained for future review and verification by a
Section 4.1) Additionally, DP Section 4.2.3 specifies, As stated in
          regulatory inspector.
NUREG/CR-5849, proper documentation of every aspect of the final survey is
          Although the licensee is responsible for performing and documentation the
necessary for future reference to the decommissioning survey. An accurate
          decommissioning and final status survey (Final Status Survey Report for the
mapping of the reactor containment building and surrounding areas within this
          GTRR facility issued June 2002), the NRC verifies the licensees performance
decommissioning project will be maintained for future review and verification by a
          through inspections during decommissioning and a confirmatory final survey at the
regulatory inspector.  
          end.
Although the licensee is responsible for performing and documentation the
          As part of this confirmatory process ESSAP reviewed and evaluated GITs final
decommissioning and final status survey (Final Status Survey Report for the
          survey plan and report (GTS 2000 and Shaw 2002). The documents were
GTRR facility issued June 2002), the NRC verifies the licensees performance
          reviewed for general thoroughness, accuracy, and consistency. Data were
through inspections during decommissioning and a confirmatory final survey at the
          evaluated to assure that areas exceeding guidelines were identified and had
end.
          undergone remediation. Final status survey results were compared with guidelines
As part of this confirmatory process ESSAP reviewed and evaluated GITs final
          to ensure that the data had been interpreted correctly. Comments were provided
survey plan and report (GTS 2000 and Shaw 2002). The documents were
reviewed for general thoroughness, accuracy, and consistency. Data were
evaluated to assure that areas exceeding guidelines were identified and had
undergone remediation. Final status survey results were compared with guidelines
to ensure that the data had been interpreted correctly. Comments were provided


                                      -12-
-12-
    to the NRC, documenting the review of the final survey plan and the final survey
to the NRC, documenting the review of the final survey plan and the final survey
    report.
report.
    The procedures, methods, and data submitted by GIT were considered to be
The procedures, methods, and data submitted by GIT were considered to be
    appropriate and adequately documented the radiological status of the GTRR.
appropriate and adequately documented the radiological status of the GTRR.  
    ESSAP confirmed that the licensee modified the gross activity guidelines to
ESSAP confirmed that the licensee modified the gross activity guidelines to
    account for hard-to-detect radionuclides. This data was reviewed by ESSAP to
account for hard-to-detect radionuclides. This data was reviewed by ESSAP to
    evaluate its appropriateness of use and determined it to be satisfactory.
evaluate its appropriateness of use and determined it to be satisfactory.
    ESSAP performed confirmatory surveys of the GTRR during the period October 21
ESSAP performed confirmatory surveys of the GTRR during the period October 21
    to 23, 2002. The surveys were performed in accordance with the site-specific
to 23, 2002. The surveys were performed in accordance with the site-specific
    survey plan submitted to and approved by the NRC and the ORISE/ESSAP Survey
survey plan submitted to and approved by the NRC and the ORISE/ESSAP Survey
    Procedures and Quality Assurance Manuals (ORISE 2002a, 2000a, and 2002b).
Procedures and Quality Assurance Manuals (ORISE 2002a, 2000a, and 2002b).  
    ESSAP surveys, their individual findings, and overall results are described in the
ESSAP surveys, their individual findings, and overall results are described in the
    sections following.
sections following.
(2) Surface Scans
(2) Surface Scans
    Surface scans for beta and gamma radiation were performed over approximately
Surface scans for beta and gamma radiation were performed over approximately
    100 percent of the floor surfaces in the basement and on the first floor and 50
100 percent of the floor surfaces in the basement and on the first floor and 50
    percent of the floor surfaces on the second floor. Surface scans for beta radiation
percent of the floor surfaces on the second floor. Surface scans for beta radiation
    were performed over approximately 50 percent of the lower walls in the basement,
were performed over approximately 50 percent of the lower walls in the basement,
    excluding the Stairwell General Area, 10 percent on the first floor, and 5 percent
excluding the Stairwell General Area, 10 percent on the first floor, and 5 percent
    on the second floor. Surface scans for beta radiation were also performed in the
on the second floor. Surface scans for beta radiation were also performed in the
    vessel tunnel over approximately 50 percent of the surface.
vessel tunnel over approximately 50 percent of the surface.
    Particular attention was given to remediated and adjacent surfaces, cracks and
Particular attention was given to remediated and adjacent surfaces, cracks and
    joints in the floors and walls, and other locations where residual radioactive
joints in the floors and walls, and other locations where residual radioactive
    material may have accumulated. Surface scans were not performed on any upper
material may have accumulated. Surface scans were not performed on any upper
    wall or ceiling surfaces, in the Helium Rupture Disk Chamber, or in the Reactor
wall or ceiling surfaces, in the Helium Rupture Disk Chamber, or in the Reactor
    Building Ventilation Hold-Up Duct areas. Scans were performed using gas
Building Ventilation Hold-Up Duct areas. Scans were performed using gas
    proportional and NaI scintillation detectors coupled to ratemeters or ratemeter-
proportional and NaI scintillation detectors coupled to ratemeters or ratemeter-
    scalers with audible indicators. Locations of elevated direct radiation were noted
scalers with audible indicators. Locations of elevated direct radiation were noted
    for further investigation.
for further investigation.
    ESSAP identified two areas of elevated beta surface radiation. One area was
ESSAP identified two areas of elevated beta surface radiation. One area was
    found on a scabbled portion of the wall in the Bismuth Leak area. Another area
found on a scabbled portion of the wall in the Bismuth Leak area. Another area
    was found on the floor of the processor equipment room. The concrete block walls
was found on the floor of the processor equipment room. The concrete block walls
    in the air compressor room were also noted as being uniformly elevated. Scans of
in the air compressor room were also noted as being uniformly elevated. Scans of
    the remaining surfaces did not identify any additional locations of elevated beta or
the remaining surfaces did not identify any additional locations of elevated beta or
    gamma radiation.
gamma radiation.
    Surface scans of outdoor locations including soil areas, paved areas, and gravel
Surface scans of outdoor locations including soil areas, paved areas, and gravel
    surfaces were performed over approximately 50 to 100 percent of the accessible
surfaces were performed over approximately 50 to 100 percent of the accessible
    areas using a sodium iodide scintillation detector coupled to a ratemeter.
areas using a sodium iodide scintillation detector coupled to a ratemeter.


                                        -13-
-13-
    Gamma surface scans were within the range of ambient background levels except
Gamma surface scans were within the range of ambient background levels except
    for an area adjacent to the NNRC that was determined to be caused by radiation
for an area adjacent to the NNRC that was determined to be caused by radiation
    shine from the hot cell facility and storage vault.
shine from the hot cell facility and storage vault.
(3) Surface Activity Measurements
(3) Surface Activity Measurements
    Construction material-specific backgrounds were determined in areas of similar
Construction material-specific backgrounds were determined in areas of similar
    construction, but without a history of radioactive material use. Ambient gamma
construction, but without a history of radioactive material use. Ambient gamma
    backgrounds were determined in areas where direct beta measurements were
backgrounds were determined in areas where direct beta measurements were
    performed; these background measurements were used to correct gross beta
performed; these background measurements were used to correct gross beta
    surface activity measurements.
surface activity measurements.
    Direct measurements for total beta activity were performed at 35 locations, chosen
Direct measurements for total beta activity were performed at 35 locations, chosen
    randomly and based on surface scan results. Additional measurements to
randomly and based on surface scan results. Additional measurements to
    determine the average activity level in one area were also performed. Dry smears
determine the average activity level in one area were also performed. Dry smears
    were collected at each direct measurement location for determining removable
were collected at each direct measurement location for determining removable
    gross alpha and gross beta activity. Wet smears were collected from areas
gross alpha and gross beta activity. Wet smears were collected from areas
    adjacent to direct measurement locations to determine the H-3 and C-14 activity.
adjacent to direct measurement locations to determine the H-3 and C-14 activity.  
    Direct measurements were performed using gas proportional detectors coupled to
Direct measurements were performed using gas proportional detectors coupled to
    ratemeter-scalers.
ratemeter-scalers.  
    ESSAP identified an activity of 9,700 dpm/100 cm2 over approximately 0.5 m2 in
ESSAP identified an activity of 9,700 dpm/100 cm2 over approximately 0.5 m2 in
    the elevated area identified in the Bismuth Leak area, with an average activity of
the elevated area identified in the Bismuth Leak area, with an average activity of
    1700 dpm/100 cm2 over the contiguous one square meter area. The elevated
1700 dpm/100 cm2 over the contiguous one square meter area. The elevated
    area identified in the process equipment room was limited to approximately
area identified in the process equipment room was limited to approximately
    100 cm2 with an activity of 4,100 dpm/100 cm2. An activity range of 2,700 to
100 cm2 with an activity of 4,100 dpm/100 cm2.   An activity range of 2,700 to
    5,100 dpm/100 cm2 was determined for the concrete block in the air compressor
5,100 dpm/100 cm2 was determined for the concrete block in the air compressor
    room, which GIT claimed resulted from naturally occurring radioactive material in
room, which GIT claimed resulted from naturally occurring radioactive material in
    the blocks. Confirmatory scans on the interior and exterior of the room found the
the blocks. Confirmatory scans on the interior and exterior of the room found the
    radiation levels to be evenly distributed throughout the blocks, confirming the
radiation levels to be evenly distributed throughout the blocks, confirming the
    activity was from the material used to make them. Removable activity levels
activity was from the material used to make them. Removable activity levels
    ranged from 0 to 3 dpm/100 cm2 for gross alpha and from -5 to 45 dpm/100 cm2
ranged from 0 to 3 dpm/100 cm2 for gross alpha and from -5 to 45 dpm/100 cm2
    for gross beta. H-3 removable activity levels ranged from 3 to 466 dpm/100 cm2.
for gross beta. H-3 removable activity levels ranged from 3 to 466 dpm/100 cm2.
    C-14 removable activity levels ranged from -2 to 86 dpm/100 cm2.
C-14 removable activity levels ranged from -2 to 86 dpm/100 cm2.
(4) Exposure Rate Measurements
(4) Exposure Rate Measurements
    ESSAP obtained background exposure rate measurements from various locations
ESSAP obtained background exposure rate measurements from various locations
    within the NNRC, having similar construction as the GTRR. The NNRC has a site
within the NNRC, having similar construction as the GTRR. The NNRC has a site
    history of radiological material usage; however, there are no other buildings similar
history of radiological material usage; however, there are no other buildings similar
    in construction to the GTRR and NNRC on the GIT campus. Exposure rate
in construction to the GTRR and NNRC on the GIT campus. Exposure rate
    measurements, using a microrem meter at one meter above the floor, were
measurements, using a microrem meter at one meter above the floor, were
    performed in the center of selected areas or rooms within the GTRR.
performed in the center of selected areas or rooms within the GTRR.
    Average interior building exposure rates ranged from 9 to 25 FR/h. Background
Average interior building exposure rates ranged from 9 to 25 R/h. Background
    exposure rates performed in the NNRC ranged from 18 to 20 FR/h.
exposure rates performed in the NNRC ranged from 18 to 20 R/h.


                                          -14-
-14-
        Exterior exposure rate measurements, using a microrem meter at one meter
Exterior exposure rate measurements, using a microrem meter at one meter
        above the surface, were performed at five random locations from the reactor yard
above the surface, were performed at five random locations from the reactor yard
        area surrounding the GTRR.
area surrounding the GTRR.
        Average exterior exposure rates ranged from 14 to 18 FR/h. Background
Average exterior exposure rates ranged from 14 to 18 R/h. Background
        exposure rates performed at various intersections on the GIT campus ranged from
exposure rates performed at various intersections on the GIT campus ranged from
        12 to 20 FR/h.
12 to 20 R/h.
  (5) Sampling
(5) Sampling
        ESSAP collected surface soil (0-15 cm) samples at each exposure rate
ESSAP collected surface soil (0-15 cm) samples at each exposure rate
        measurement location.
measurement location.  
        Analysis of the soil samples by gamma spectroscopy for gamma-emitting mixed
Analysis of the soil samples by gamma spectroscopy for gamma-emitting mixed
        fission and activation products identified Cs-137 at typical fall out concentrations.
fission and activation products identified Cs-137 at typical fall out concentrations.  
        Radionuclide concentrations for Co-60 and Cs-137, which are the predominant
Radionuclide concentrations for Co-60 and Cs-137, which are the predominant
        radionuclides of concern at research reactor facilities ranged from -0.02 to 0.03
radionuclides of concern at research reactor facilities ranged from -0.02 to 0.03
        pCi/g for Co-60 and -0.02 to 0.21 pCi/g for Cs-137. All other radionuclides of
pCi/g for Co-60 and -0.02 to 0.21 pCi/g for Cs-137. All other radionuclides of
        concern were reported as less than the respective minimum detectable
concern were reported as less than the respective minimum detectable
        concentration of the procedure, which ranged from 0.03 to 0.11 pCi/g.
concentration of the procedure, which ranged from 0.03 to 0.11 pCi/g.
  (6) ESSAP Results
(6) ESSAP Results
        Compliance for residual surface activity was shown using the GIT calibration
Compliance for residual surface activity was shown using the GIT calibration
        methodology approved by the NRC. Since ESSAPs calibration method differs,
methodology approved by the NRC. Since ESSAPs calibration method differs,
        this required adjusting the ESSAP-calculated surface activity by the ratio of the
this required adjusting the ESSAP-calculated surface activity by the ratio of the
        efficiencies for the GIT and ESSAP methods. The correction factor was
efficiencies for the GIT and ESSAP methods. The correction factor was
        approximately 2.3. All corrected ESSAP confirmatory surface activity
approximately 2.3. All corrected ESSAP confirmatory surface activity
        measurements, including the identified elevated areas, met guidelines and did not
measurements, including the identified elevated areas, met guidelines and did not
        require further remediation. Additional investigation by the inspector verified that
require further remediation. Additional investigation by the inspector verified that
        the concrete block in the air compressor room was made from material with a high
the concrete block in the air compressor room was made from material with a high
        composition of naturally occurring radioactive material.
composition of naturally occurring radioactive material.
        Except for the air compressor room in the basement, all exposure rate
Except for the air compressor room in the basement, all exposure rate
        measurements were less than 5 FR/h above background for each survey unit.
measurements were less than 5 R/h above background for each survey unit.
        Confirmatory surface soil samples were less than the screening values listed in the
Confirmatory surface soil samples were less than the screening values listed in the
        GIT final survey plan (GTS 2000).
GIT final survey plan (GTS 2000).
c. Conclusions
c.
  Based on the above observations, surveys, evaluations, and analyses, the inspector
Conclusions
  concluded that: 1) the elevated surface activity and exposure readings in the
Based on the above observations, surveys, evaluations, and analyses, the inspector
  basement compressor room were due to naturally occurring radioactive material; and
concluded that: 1) the elevated surface activity and exposure readings in the
  2) based on the results of the licensees final status survey and ESSAPs confirmatory
basement compressor room were due to naturally occurring radioactive material; and
  measurements, GIT has adequately demonstrated that the GTRR facility satisfies the
2) based on the results of the licensees final status survey and ESSAPs confirmatory
  criteria for release for unrestricted use.
measurements, GIT has adequately demonstrated that the GTRR facility satisfies the
criteria for release for unrestricted use.


                                            -15-
-15-
8. MAINTENANCE AND SURVEILLANCE
8.
  a. Inspection Scope (IP 40755)
MAINTENANCE AND SURVEILLANCE
      The inspector reviewed selected aspects of:
a. Inspection Scope (IP 40755)
      *   maintenance procedures
The inspector reviewed selected aspects of:
      *   equipment maintenance records
*
      *   surveillance and calibration procedures
maintenance procedures
      *   surveillance, calibration, and test data sheets and records
*
      *   reactor periodic checks, tests, verification, and decommissioning activities
equipment maintenance records
      *   facility design and DP changes and records
*
      *   NNRC Procedure 4200, 10 CFR 50.59 Review Program for Changes and Tests
surveillance and calibration procedures
          During Decommissioning, Revision 01, dated November 1, 1999
*
      *   TS, Amendment No. 14, dated July 22, 1999
surveillance, calibration, and test data sheets and records
*
reactor periodic checks, tests, verification, and decommissioning activities
*
facility design and DP changes and records
*
NNRC Procedure 4200, 10 CFR 50.59 Review Program for Changes and Tests
During Decommissioning, Revision 01, dated November 1, 1999
*
TS, Amendment No. 14, dated July 22, 1999


                                          -16-
-16-
  b. Observations and Findings
b. Observations and Findings
      (1) General Maintenance
(1) General Maintenance
          During decommissioning general maintenance was focused on the support
During decommissioning general maintenance was focused on the support
          services and equipment and not on any reactor systems. The inspector reviewed
services and equipment and not on any reactor systems. The inspector reviewed
          maintenance records, interviewed staff and observed minor maintenance
maintenance records, interviewed staff and observed minor maintenance
          performed on the various systems in operation. Based on the inspectors
performed on the various systems in operation. Based on the inspectors
          interviews and observations, general maintenance was acceptable for an
interviews and observations, general maintenance was acceptable for an
          industrial site.
industrial site.
      (2) Surveillance
(2) Surveillance
          The inspector reviewed records of the TS Section 3 required surveillance
The inspector reviewed records of the TS Section 3 required surveillance
          verifications performed during 2000. The results of the surveillances for the
verifications performed during 2000. The results of the surveillances for the
          radiation monitoring system and the ventilation system were within prescribed TS
radiation monitoring system and the ventilation system were within prescribed TS
          limits and procedure parameters, and in close agreement with the previous
limits and procedure parameters, and in close agreement with the previous
          surveillance results.
surveillance results.
      (3) Change Control
(3) Change Control
          TS or DP related 10 CFR 50.59 changes required review by the TSRC in
TS or DP related 10 CFR 50.59 changes required review by the TSRC in
          accordance with TS Section 5.2.
accordance with TS Section 5.2.
          The inspector reviewed various TSRC approved change packages for changing
The inspector reviewed various TSRC approved change packages for changing
          the method of accomplishing certain decommissioning activities. The inspector
the method of accomplishing certain decommissioning activities. The inspector
          determined that the changes had been evaluated, reviewed, and approved as
determined that the changes had been evaluated, reviewed, and approved as
          required by NNRC Procedure 4200, 10 CFR 50.59 Review Program for Changes
required by NNRC Procedure 4200, 10 CFR 50.59 Review Program for Changes
          and Tests During Decommissioning, Revision 01, dated November 1, 1999. The
and Tests During Decommissioning, Revision 01, dated November 1, 1999. The
          reviews were technically complete and adequately documented. Additionally, the
reviews were technically complete and adequately documented. Additionally, the
          inspector concluded that TSRC 10 CFR 50.59 reviews and approvals were
inspector concluded that TSRC 10 CFR 50.59 reviews and approvals were
          focused on safety, and met licensee program requirements.
focused on safety, and met licensee program requirements.
  c. Conclusions
c.
      The licensee's program for surveillance and limiting conditions for operation
Conclusions
      verification satisfied TS and DP requirements. The licensee's maintenance and
The licensee's program for surveillance and limiting conditions for operation
      design change programs were in place and were being implemented as required by
verification satisfied TS and DP requirements. The licensee's maintenance and
      licensee procedures.
design change programs were in place and were being implemented as required by
9. RADIATION PROTECTION
licensee procedures.
  a. Inspection Scope (IPs 69001 and 40755)
9.
      The inspector reviewed selected aspects of the radiation protection program (RPP):
RADIATION PROTECTION
      *   Radiation Protection Training
a. Inspection Scope (IPs 69001 and 40755)
      *   radiological signs and posting
The inspector reviewed selected aspects of the radiation protection program (RPP):
*
Radiation Protection Training
*
radiological signs and posting


                                          -17-
-17-
  *   facility and equipment during tours
*
  *   routine surveys and monitoring
facility and equipment during tours
  *   survey and monitoring procedures
*
  *   dosimetry records
routine surveys and monitoring
  *   maintenance and calibration of radiation monitoring equipment
*
  *   periodic checks, quality control, and test source certification records
survey and monitoring procedures
  *   NNRC Radiation Protection Program (RPP)
*
  *   event/incident records
dosimetry records
*
maintenance and calibration of radiation monitoring equipment
*
periodic checks, quality control, and test source certification records
*
NNRC Radiation Protection Program (RPP)
*
event/incident records
b. Observations and Findings
b. Observations and Findings
  (1) Radiation Protection Program
(1) Radiation Protection Program  
      Although individual procedures had been revised and some added, the RPP had
Although individual procedures had been revised and some added, the RPP had
      not functionally changed since the last inspection. The licensee reviewed the RPP
not functionally changed since the last inspection. The licensee reviewed the RPP
      at least annually in accordance with 10 CFR 20.1101(c). This review and
at least annually in accordance with 10 CFR 20.1101(c). This review and
      oversight was provided by the TSRC as required by TS Section 5.2.d(9) and DP
oversight was provided by the TSRC as required by TS Section 5.2.d(9) and DP
      Section 2.4.3.
Section 2.4.3.
      The inspectors review of procedure change records, revisions, and radiation work
The inspectors review of procedure change records, revisions, and radiation work
      permits (RWP), confirmed that the RSO, individually and as a TSRC member,
permits (RWP), confirmed that the RSO, individually and as a TSRC member,
      reviewed and approved RWPs, and advised the Director and TSRC on matters
reviewed and approved RWPs, and advised the Director and TSRC on matters
      regarding radiological safety as required by TS Section 5.1.b, DP Section 2.4.1,
regarding radiological safety as required by TS Section 5.1.b, DP Section 2.4.1,
      and the RPP.
and the RPP.
      Through record reviews and interviews with GTRR and Duratec staffs, the
Through record reviews and interviews with GTRR and Duratec staffs, the
      inspector confirmed that the RPP was applied to all activities during the
inspector confirmed that the RPP was applied to all activities during the
      decommissioning project, as required by DP Section 3.1 and GTRR procedures.
decommissioning project, as required by DP Section 3.1 and GTRR procedures.
  (2) Radiation Protection Postings
(2) Radiation Protection Postings
      The inspector observed that caution signs, postings and controls to radiation and
The inspector observed that caution signs, postings and controls to radiation and
      contaminated areas at the NNRC were acceptable for the hazards involved and
contaminated areas at the NNRC were acceptable for the hazards involved and
      were implemented as required by 10 CFR Part 20, Subpart J. The inspector
were implemented as required by 10 CFR Part 20, Subpart J. The inspector
      observed licensee and contractor personnel and verified that they complied with
observed licensee and contractor personnel and verified that they complied with
      the indicated precautions for access to such areas. The inspector confirmed that
the indicated precautions for access to such areas. The inspector confirmed that
      current copies of NRC Form-3 and notices to workers were posted in appropriate
current copies of NRC Form-3 and notices to workers were posted in appropriate
      areas in the facility as required by 10 CFR Part 19.11.
areas in the facility as required by 10 CFR Part 19.11.
  (3) Radiation Protection Surveys
(3) Radiation Protection Surveys
      The inspector audited the GTRR daily, monthly, quarterly, and other periodic
The inspector audited the GTRR daily, monthly, quarterly, and other periodic
      contamination and radiation surveys, including airborne activity sampling,
contamination and radiation surveys, including airborne activity sampling,
      performed from 2000 to 2003. The surveys were performed and documented as
performed from 2000 to 2003. The surveys were performed and documented as
      required by DP Section 3.0, and GTRR survey procedures. HP surveys required
required by DP Section 3.0, and GTRR survey procedures. HP surveys required
      for special decommissioning activities, such as RWPs, were also performed and
for special decommissioning activities, such as RWPs, were also performed and
      documented as required. Results were evaluated and corrective actions taken and
documented as required. Results were evaluated and corrective actions taken and
      documented when readings/results exceeded set action levels.
documented when readings/results exceeded set action levels.


-18-
-18-
                                      -19-
 
-19-
(4) Dosimetry
(4) Dosimetry
    The inspector confirmed that dosimetry was issued to staff, contractors, and
The inspector confirmed that dosimetry was issued to staff, contractors, and
    visitors as outlined in licensee procedures. The licensees dosimetry issuing
visitors as outlined in licensee procedures. The licensees dosimetry issuing
    criteria specified that dosimetry should be issued to individuals who might receive
criteria specified that dosimetry should be issued to individuals who might receive
    a dose equivalent exceeding 10 percent of the annual limits specified in 10 CFR
a dose equivalent exceeding 10 percent of the annual limits specified in 10 CFR
    Part 20.1201(a). This criteria meet the requirements of 10 CFR 20.1502 for
Part 20.1201(a). This criteria meet the requirements of 10 CFR 20.1502 for
    individual monitoring. Training records showed that personnel were acceptably
individual monitoring. Training records showed that personnel were acceptably
    trained in radiation protection practices. During the inspection the inspector
trained in radiation protection practices. During the inspection the inspector
    observed that workers and staff wore their dosimetry as required.
observed that workers and staff wore their dosimetry as required.
    The licensee used a National Voluntary Laboratory Accreditation Program-
The licensee used a National Voluntary Laboratory Accreditation Program-
    accredited vendor to process personnel thermoluminescent dosimetry. Dosimetry
accredited vendor to process personnel thermoluminescent dosimetry. Dosimetry
    results were reviewed by the RSO and doses above the facilitys ALARA limits
results were reviewed by the RSO and doses above the facilitys ALARA limits
    were investigated as required. The inspectors review of the licensees radiological
were investigated as required. The inspectors review of the licensees radiological
    exposure records from 2000 to 2003 verified that occupational doses were within
exposure records from 2000 to 2003 verified that occupational doses were within
    10 CFR Part 20 limitations.
10 CFR Part 20 limitations.
(5) Radiation Monitoring Equipment
(5) Radiation Monitoring Equipment
    The calibration and periodic checks of the portable survey meters, radiation
The calibration and periodic checks of the portable survey meters, radiation
    monitoring, air sampling, and counting lab instruments were performed by facility
monitoring, air sampling, and counting lab instruments were performed by facility
    staff or by certified contractors. The inspector confirmed that the licensees
staff or by certified contractors. The inspector confirmed that the licensees
    calibration procedures and annual, quarterly, semiannual and monthly calibration,
calibration procedures and annual, quarterly, semiannual and monthly calibration,
    test, and check frequencies satisfied TS Section 4.3.3, DP Section 3.1, and
test, and check frequencies satisfied TS Section 4.3.3, DP Section 3.1, and
    10 CFR 20.1501(b) requirements, and the American National Standards Institute
10 CFR 20.1501(b) requirements, and the American National Standards Institute
    N323 Radiation Protection Instrumentation Test and Calibration or the
N323 Radiation Protection Instrumentation Test and Calibration or the
    instruments manufacturers' recommendations. The inspector verified that the
instruments manufacturers' recommendations. The inspector verified that the
    calibration and check sources used were traceable to the National Institute of
calibration and check sources used were traceable to the National Institute of
    Standards and Technology and that the sources geometry and energies matched
Standards and Technology and that the sources geometry and energies matched
    those used in actual detection/analyses.
those used in actual detection/analyses.
    The inspector also reviewed Duratec instrument calibrations. Their calibration and
The inspector also reviewed Duratec instrument calibrations. Their calibration and
    periodic checks of the portable survey meters, radiation monitoring, air sampling,
periodic checks of the portable survey meters, radiation monitoring, air sampling,
    and counting lab instruments were performed by their staffs or by certified
and counting lab instruments were performed by their staffs or by certified
    contractors. The inspector confirmed that calibration procedures and annual,
contractors. The inspector confirmed that calibration procedures and annual,
    semiannual quarterly, monthly, and daily calibrations, tests, and check frequencies
semiannual quarterly, monthly, and daily calibrations, tests, and check frequencies
    satisfied Duratec HPS procedures. Calibrations also met 10 CFR Part 20.1501(b)
satisfied Duratec HPS procedures. Calibrations also met 10 CFR Part 20.1501(b)
    requirements, and the American National Standards Institute N323 Radiation
requirements, and the American National Standards Institute N323 Radiation
    Protection Instrumentation Test and Calibration or the instruments manufacturers'
Protection Instrumentation Test and Calibration or the instruments manufacturers'
    recommendations. The inspector verified that the calibration and check sources
recommendations. The inspector verified that the calibration and check sources
    used were traceable to the National Institute of Standards and Technology and
used were traceable to the National Institute of Standards and Technology and
    that the sources geometry and energies matched those used in actual
that the sources geometry and energies matched those used in actual
    detection/analyses.
detection/analyses.
    The inspector reviewed the calibration lists and confirmed that calibrations for the
The inspector reviewed the calibration lists and confirmed that calibrations for the
    radiation monitoring and counting lab equipment in use had been performed and
radiation monitoring and counting lab equipment in use had been performed and
    that all portable instruments in use were calibrated.
that all portable instruments in use were calibrated.


                                              -20-
-20-
          All instruments checked by the inspector had current calibrations appropriate for
All instruments checked by the inspector had current calibrations appropriate for
          the types and energies of radiation they were used to detect and/or measure.
the types and energies of radiation they were used to detect and/or measure.
      (6) Respiratory Protection
(6) Respiratory Protection
          DP Section 3.1.6 states that the Respiratory Protection Program will be
DP Section 3.1.6 states that the Respiratory Protection Program will be
          implemented by the decommissioning contractor in compliance with ANSI Z-88.2,
implemented by the decommissioning contractor in compliance with ANSI Z-88.2,
          US NRC Regulatory Guide 8.15, 10 CFR 20.1701 through 20.1704, and OSHA
US NRC Regulatory Guide 8.15, 10 CFR 20.1701 through 20.1704, and OSHA
          requirements.
requirements.
          While conducting inspections during decommissioning activities at the facility, the
While conducting inspections during decommissioning activities at the facility, the
          inspector reviewed the respiratory protection program in use by contractor
inspector reviewed the respiratory protection program in use by contractor
          personnel. The inspector noted that the licensee and contractor had established a
personnel. The inspector noted that the licensee and contractor had established a
          respiratory protection program as required by DP Section 3.1.6 and were using
respiratory protection program as required by DP Section 3.1.6 and were using
          tested and certified NIOSH/MSHA equipment as required. Records and
tested and certified NIOSH/MSHA equipment as required. Records and
          observation showed that air sampling was being conducted, surveys and
observation showed that air sampling was being conducted, surveys and
          bioassays were completed as required, testing of respirators was being done, fit
bioassays were completed as required, testing of respirators was being done, fit
          testing of individuals was performed, and individuals were required to pass a
testing of individuals was performed, and individuals were required to pass a
          physical in order to qualify to use a respirator. The respiratory protection program
physical in order to qualify to use a respirator. The respiratory protection program
          was in compliance with 10 CFR 20.1703 and the DP.
was in compliance with 10 CFR 20.1703 and the DP.
      (4) Effluents
(4) Effluents
          The program for the monitoring and storage of radioactive liquid, gases, and solids
The program for the monitoring and storage of radioactive liquid, gases, and solids
          was acceptable. Radioactive effluents were monitored and released when within
was acceptable. Radioactive effluents were monitored and released when within
          established limits as outlined in licensee procedures and the regulations. The
established limits as outlined in licensee procedures and the regulations. The
          principles of As Low As Reasonably Achievable (ALARA) were acceptably
principles of As Low As Reasonably Achievable (ALARA) were acceptably
          implemented to minimize radioactive releases. Monitoring equipment was
implemented to minimize radioactive releases. Monitoring equipment was
          maintained and calibrated as required. Records were current and acceptably
maintained and calibrated as required. Records were current and acceptably
          maintained.
maintained.
  c. Conclusions
c.
      Based on the observations made and records audited, it was determined that,
Conclusions
      because: 1) surveys were completed and documented as required by
Based on the observations made and records audited, it was determined that,
      10 CFR 20.1501(a) and licensee procedures, 2) postings met regulatory requirements,
because: 1) surveys were completed and documented as required by
      3) the personnel dosimetry program was acceptably implemented and doses were in
10 CFR 20.1501(a) and licensee procedures, 2) postings met regulatory requirements,
      conformance with licensee and 10 CFR Part 20 limits, 4) portable survey meters,
3) the personnel dosimetry program was acceptably implemented and doses were in
      radiation monitoring, and counting lab instruments were maintained and calibrated as
conformance with licensee and 10 CFR Part 20 limits, 4) portable survey meters,
      required, 5) the evaluation and administration of the respiratory program were
radiation monitoring, and counting lab instruments were maintained and calibrated as
      adequately performed, and 6) the program for monitoring, storage, and release of
required, 5) the evaluation and administration of the respiratory program were
      effluents was acceptable, the RPP implemented by the licensee satisfied NRC and DP
adequately performed, and 6) the program for monitoring, storage, and release of
      requirements.
effluents was acceptable, the RPP implemented by the licensee satisfied NRC and DP
5. EXIT MEETING SUMMARY
requirements.
  The inspector presented the inspection results to members of licensee management at
5.
  the conclusion of the inspection on October 23, 2002. The licensee acknowledged the
EXIT MEETING SUMMARY
The inspector presented the inspection results to members of licensee management at
the conclusion of the inspection on October 23, 2002. The licensee acknowledged the


      findings presented and did not identify as proprietary any of the material provided to or
findings presented and did not identify as proprietary any of the material provided to or
      reviewed by the inspector during the inspection.
reviewed by the inspector during the inspection.
                          PARTIAL LIST OF PERSONS CONTACTED
PARTIAL LIST OF PERSONS CONTACTED
  *T. Bauer           Project Leader, ESSAP
  *T. Bauer
  *T. Brown           Field Staff, ESSAP
Project Leader, ESSAP
  *R. Eby             Executive Engineer, (Vice President Energy, Environment, and Systems)
  *T. Brown
                      CH2M HILL
Field Staff, ESSAP
  *N. Hertel           Director, Neely Nuclear Research Center
  *R. Eby
  *R. Ice             Manager, Office of Radiation Safety
Executive Engineer, (Vice President Energy, Environment, and Systems)
   P. Jones           Project Manager, GTS Duratek Field Services
CH2M HILL
   G. Kalinauskas     Senior Project Engineer, IT Corporation
  *N. Hertel
   R. Morton           Field Staff, ESSAP
Director, Neely Nuclear Research Center
  *R. Ice
Manager, Office of Radiation Safety
   P. Jones
Project Manager, GTS Duratek Field Services
   G. Kalinauskas
Senior Project Engineer, IT Corporation
   R. Morton
Field Staff, ESSAP
* Attended exit meeting.
* Attended exit meeting.
The inspector also contacted other supervisory, technical and administrative staff personnel
The inspector also contacted other supervisory, technical and administrative staff personnel
as well.
as well.
                              INSPECTION PROCEDURE (IP) USED
INSPECTION PROCEDURE (IP) USED
IP 69001     Class II Non-Power Reactors
IP 69001
IP 40755     Class III Non-power Reactors
Class II Non-Power Reactors
IP 85102     Material Control and Accounting - Reactors
IP 40755
IP 86740     Inspection of Transportation Activities
Class III Non-power Reactors
                                  ITEMS OPENED AND CLOSED
IP 85102
Material Control and Accounting - Reactors
IP 86740
Inspection of Transportation Activities
ITEMS OPENED AND CLOSED
Open
Open
None
None
Closed
Closed
None
None
                              PARTIAL LIST OF ACRONYMS USED
PARTIAL LIST OF ACRONYMS USED
Duratec       GTS Duratec
Duratec  
DP           Georgia Institute of Technology Research Reactor Decommissioning Plan dated
GTS Duratec
              June 1998
DP  
ESSAP         Environmental Survey and Site Assessment Program
Georgia Institute of Technology Research Reactor Decommissioning Plan dated
GIT           Georgia Institute of Technology
June 1998  
GTRR         Georgia Institute of Technology Research Reactor
ESSAP  
HP           Health Physics
Environmental Survey and Site Assessment Program  
IT           IT Corporation
GIT
NNRC         Neely Nuclear Research Center
Georgia Institute of Technology  
NRC           Nuclear Regulatory Commission
GTRR
ORISE         Oak Ridge Institute for Science and Education
Georgia Institute of Technology Research Reactor  
RWP           Radiation Work Permits
HP  
RPP           Radiation Protection Program
Health Physics
RSO           Radiation Safety Officer
IT
TS           Technical Specifications
IT Corporation  
NNRC
Neely Nuclear Research Center  
NRC
Nuclear Regulatory Commission
ORISE  
Oak Ridge Institute for Science and Education
RWP  
Radiation Work Permits
RPP  
Radiation Protection Program
RSO
Radiation Safety Officer  
TS  
Technical Specifications


                                  -22-
-22-
TSRC Technical Safety Review Committee
TSRC
Technical Safety Review Committee
}}
}}

Latest revision as of 09:38, 16 January 2025

IR 05000160-02-201, on 10/21/2002 Through 10/23/2002, for Georgia Institute of Technology, Atlanta, Ga
ML031490485
Person / Time
Site: Neely Research Reactor
Issue date: 06/24/2003
From: Madden P
NRC/NRR/DRIP/RORP
To: Hertel N
Neely Research Reactor
Holmes S, NRC/NRR/DRIP/RORP, 415-8583
References
IR-02-201
Download: ML031490485 (30)


See also: IR 05000160/2002201

Text

June 24, 2003

Dr. Nolan Hertel, Director

Neely Nuclear Research Center

Georgia Institute of Technology

900 Atlantic Drive

Atlanta, GA 30332-0425

SUBJECT:

NRC INSPECTION REPORT NO. 50-160/2002-201

Dear Dr. Hertel:

The inspection effort involved the coordination of the confirmatory radiological survey activities

performed by our contractor, Oak Ridge Institute for Science and Education, of your research

reactor on October 21-23, 2002. In addition, various aspects of your reactor operations,

decommissioning, and radiation protection programs were inspected, including selective

examinations of procedures and representative records, interviews with personnel, and

observations of the facility.

Based on the results of this inspection, it has been determined that: 1) the decommissioning of

the 5 MWt Research Reactor has been performed in accordance with the approved

Decommissioning Plan; 2) the terminal radiation survey and associated documentation from the

licensee demonstrated that residual radioactive material at the facility and site is less than the

NRC-approved guideline limits; and 3) since the licensee has met their NRC-approved guideline

limits, the facility and site meet the criteria for license termination set forth in 10 CFR Part 20.1401(b)(2).

No safety concern or noncompliance with Nuclear Regulatory Commission (NRC) requirements

was identified. No response to this letter is required.

Dr. N. Hertel

-2-

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at (the Public Electronic Reading

Room) http://www.nrc.gov/NRC/ADAMS/index.html. Should you have any questions

concerning this inspection, please contact Mr. Stephen Holmes at 301-415-8583.

Sincerely,

/RA by Daniel E. Hughes, Acting for/

Patrick M. Madden, Section Chief

Research and Test Reactors Section

Operating Reactor Improvements Program

Division of Regulatory Improvement Programs

Office of Nuclear Reactor Regulation

Docket No. 50-160

License No. R-97

Enclosures: 1. NRC Inspection Report No. 50-160/2002-201

2. Confirmatory Survey Plan for the Georgia Tech Research Reactor dated

October 9, 2002

3. Confirmatory Survey of the Georgia Tech Research Reactor, dated

February 2003

cc w/enclosures: Please see next page

Georgia Institute of Technology

Docket No. 50-160

cc:

Mr. Charles H. Badger

Office of Planning and Budget

Room 608

270 Washington Street, S.W.

Atlanta, GA 30334

Mayor of City of Atlanta

55 Trinity Avenue, S.W.

Suite 2400

Atlanta, GA 30335

Dr. William Vernetson

Director of Nuclear Facilities

Department of Nuclear Engineering

Sciences

University of Florida

202 Nuclear Sciences Center

Gainesville, FL 32611

Joe D. Tanner, Commissioner

Department of Natural Resources

47 Trinity Avenue, S.W.

Atlanta, GA 30334

Dr. Rodney Ice, MORS

Neely Nuclear Research Center

Georgia Institute of Technology

900 Atlantic Drive

Atlanta, GA 30332-0425

Ms. Pamela Blockey-OBrien

D23 Golden Valley

Douglasville, GA 30134

Mr. E.F. Cobb

Southern Nuclear Company

42 Iverness Center

Birmingham, AL 35242

Dr. G. Wayne Clough, President

Georgia Institute of Technology

Carnegie Building

Atlanta, GA 30332-0325

Ms. Glen Carrol

139 Kings Highway

Decatur, GA 30030

Charles Bechhoefer, Chairman

Atomic Safety and

Licensing Board Panel

U.S. NRC, MS: T3-F23

Washington, DC 20555-0001

Mr. James C. Hardeman, Jr.

Manager, Environmental

Radiation Program

Environmental Protection Division

Dept. of Natural Resources

State of Georgia

4244 International Parkway

Suite 114

Atlanta, GA 30354

Dr. Jean-Lou Chameau, Dean

College of Engineering

Georgia Institute of Technology

225 North Avenue

Atlanta, GA 30332-0425

Dr. Peter S. Lam

Atomic Safety and Licensing Board Panel

U.S. NRC, MS: T3-F23

Washington, DC 20555-0001

Dr. J. Narl Davidson, Interim Dean

Chair, Technical and Safety Review

Committee

Georgia Institute of Technology

225 North Avenue

Atlanta, GA 3033-0360

Dr. Charles Liotta, Vice Provost

of Research and Dean of

Graduate Studies

Georgia Institute of Technology

225 North Avenue

Atlanta, GA 30332

Dr. N. Hertel

-2-

June 24, 2003

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at (the Public Electronic Reading

Room) http://www.nrc.gov/NRC/ADAMS/index.html. Should you have any questions

concerning this inspection, please contact Mr. Stephen Holmes at 301-415-8583.

Sincerely,

/RA by Daniel E. Hughes, Acting for/

Patrick M. Madden, Section Chief

Research and Test Reactors Section

Operating Reactor Improvements Program

Division of Regulatory Improvement Programs

Office of Nuclear Reactor Regulation

Docket No. 50-160

License No. R-97

Enclosures: 1. NRC Inspection Report No. 50-160/2002-201

2. Confirmatory Survey Plan for the Georgia Tech Research Reactor dated

October 9, 2002

3. Confirmatory Survey of the Georgia Tech Research Reactor, dated

February 2003

cc w/enclosures: Please see next page

DISTRIBUTION:

PUBLIC

RORP/R&TR r/f

TDragoun

PDoyle

WEresian

PIsaac

SHolmes

CBassett

MMendonca

FGillespie

WBeckner

EHylton

AAdams

BDavis (Ltr.only O5-A4)

ACCESSION NO.: ML031490485

TEMPLATE #: NRR-106

OFFICE

RORP:LA

RORP:RI

RORP:SC

NAME

EHylton:rdr

SHolmes

PMadden

DATE

06/ 04 /2003

06/ 04 /2003

06/ 24 /2003

C = COVER

E = COVER & ENCLOSURE

N = NO COPY

OFFICIAL RECORD COPY

U. S. NUCLEAR REGULATORY COMMISSION

Docket No:

50-160

License No:

R-97

Report No:

50-160/2002-201

Licensee:

Georgia Institute of Technology

Facility:

Georgia Institute of Technology Research Reactor (GTRR)

Location:

900 Atlantic Drive

Atlanta, GA 30332

Dates:

October 21-23, 2002

Inspector:

Stephen W. Holmes

Approved by:

Patrick M. Madden, Section Chief

Research and Test Reactors Section

Operating Reactor Improvements Program

Division of Regulatory Improvement Programs

Office of Nuclear Reactor Regulation

EXECUTIVE SUMMARY

Georgia Institute of Technology Research Reactor

Report No: 50-160/2002-201

This routine, announced inspection involved the confirmatory radiological survey and the on-site

review of selected activities being performed at the Georgia Institute of Technology Research

Reactor. In addition, the activities audited during this inspection included: organization and

staffing; review and audit functions; procedures; removal of materials; decommissioning

activities; release criteria; confirmatory final survey; maintenance and surveillance; and

radiation protection program. The inspector was assisted by the NRCs contractor, Oak Ridge

Institute for Science and Education Environmental Survey and Site Assessment Program.

Organization and Staffing



The organizational structure and their corresponding functions were consistent with

Technical Specification Section 5.0, Amendment No. 14, dated July 22, 1999, and the

Decommissioning Plan for the Georgia Institute of Technology Research Reactor facility

dated June 1998.

Review and Audit Functions



The audits conducted by the Technical Safety Review Committee and Georgia Institute

of Technology Research Reactor staff were in accordance with the requirements

specified in Technical Specification Section 5.2. and Decommissioning Plan Section 2.4.

Procedures



The procedural control and implementation program was acceptably maintained and

met Technical Specifications and Decommissioning Plan requirements.

Removal of Materials



Fuel and radioactive and non-radioactive waste was removed from the site in

accordance with the Georgia Institute of Technology Research Reactor

Decommissioning Plan requirements, and Department of Transportation and Nuclear

Regulatory Commission regulations.

Decommissioning Activities



Decommissioning activities were performed as required by Decommissioning Plan

Section 2.3 and licensee procedures.

Release Criteria



Duratec used the appropriate guideline and screening values, as required by the

NRC-approved Decommissioning Plan, in performing the final survey.

-2-

Confirmatory Final Survey



The elevated surface activity and exposure readings in the basement compressor room

were due to naturally occurring radioactive material.



Based on the results of the licensees final status survey and Nuclear Regulatory

Commissions confirmatory measurements, Georgia Institute of Technology has

adequately demonstrated that the Georgia Institute of Technology Research Reactor

facility satisfies the criteria for release for unrestricted use.

Maintenance and Surveillance



The maintenance program was implemented as required by Georgia Institute of

Technology procedures.



The licensee's program for surveillance and limiting conditions for operation

confirmations satisfied Technical Specification and Decommissioning Plan

requirements.



The licensee's design change procedures were in place and were implemented as

required by licensee procedures.

Radiation Protection Program



The radiation protection program satisfied the requirements of 10 CFR 19.12 and

10 CFR Part 20.1101.

.



Radiological postings satisfied regulatory requirements.



Surveys were performed and documented as required by 10 CFR 20.1501(a), Technical

Specifications, and licensee procedures.



The personnel dosimetry program was acceptably implemented and doses were in

conformance with licensee and 10 CFR Part 20 limits.



Portable survey meters, radiation monitoring, and counting lab instruments were

maintained according to Technical Specifications, industry/equipment manufacturer

standards, and licensee and contractor procedures.



The evaluation and administration of the respiratory program were adequately

performed according to Decommissioning Plan and Nuclear Regulatory Commission

requirements.



The program for monitoring, storage, and release of effluents was acceptable.

Report Details

Summary of Plant Status

Georgia Institute of Technology (GIT), in Atlanta Georgia, has completed decommissioning its

5 MWt Research Reactor (GTRR) and associated systems. The reactor was located within the

Neely Nuclear Research Center (NNRC) on GITs main campus. The reactor was designed for

several different research applications including experiments using high intensity neutron

beams, gamma ray beams, and an uniform thermal neutron flux through a large sized beam.

Although it was originally designed for 1 MWt output, it was upgraded to produce 5 MWt in

1974. The GTRR was built in the early 1960's as a research and training reactor. Operating

under the Nuclear Regulatory Commission (NRC) License No. R-97, it went critical for the first

time on December 31, 1964.

On November 17, 1995, all operations at the reactor ceased. GIT contracted NES, Inc. to

perform the initial characterization survey and to provide a decommissioning plan for the GTRR.

In October 1997, NES performed a characterization survey of the GTRR, based upon the GIT

Decommissioning Project - Radiological Characterization Plan. Results of the characterization

survey were provided in NES Georgia Institute of Technology Research Reactor

Decommissioning Project Characterization Report issued May 1998. GIT requested the NRC,

by letters dated July 1, 1998, February 8, 1999, and May 28, 1999, to grant them the

authorization to decommission the reactor according to their submitted decommissioning plan.

On July 22, 1999, the NRC issued Amendment No. 14 to the reactor licence that approved

GITs Decommissioning Plan. GIT contracted with IT Corporation (IT) to decommission the

GTRR facility. IT, through its subcontractor GTS Duratec (Duratec), started decommissioning

operations December 1999. Final waste shipment was made August 2001.

The Final Status Survey Report for the GTRR facility was completed and issued June 2002.

According to the report, all contaminated systems and components had been removed from the

site. Potentially contaminated structural surfaces identified during characterization surveys had

been removed and/or remediated such that the residual radioactivity is less than NRC

Regulatory Guide 1.86 limits.

The NRC requested Oak Ridge Institute for Science and Educations (ORISE) Environmental

Survey and Site Assessment Program (ESSAP) to perform a confirmatory survey of the GTRR

facility. On October 21-23, 2002, the ESSAP team, accompanied by an NRC inspector,

conducted this survey.

1.

ORGANIZATIONAL STRUCTURE AND FUNCTIONS

a. Inspection Scope (Inspection Procedures (IP) 69001 and 40755)

The inspector reviewed selected aspects of:

organization and staffing

qualifications

management responsibilities

administrative controls

decommissioning activity records

GTRR Decommissioning Plan (DP) dated June 1998

-2-

Technical Specifications (TS), Amendment No. 14, dated July 22, 1999

-3-

b. Observations and Findings

The general organizational structure and staffing had not changed since the last

inspection. The organizational structure and staffing at the facility were as reported in

the Annual Report and as required by TS Section 5.1 and Figure 5.1. Review of

records verified that management responsibilities were administered as required by

TS Sections 5.2 thru 5.6 and applicable procedures.

The decommissioning of the reactor required GTRR management to assume

additional project management responsibilities. Through record reviews and

interviews with the reactor manager, radiation safety officer (RSO), and Duratec

project manager, the inspector confirmed that both GTRR management and the

decommissioning project organization structures were as required by DP Section 2.4

and Figure 2.2.

c.

Conclusions

The organizational staff and their corresponding functions and responsibilities were

consistent with TS Section 5.0, Amendment No. 14, dated July 22, 1999, and the DP

for the GTRR facility dated June 1998

2.

REVIEW AND AUDIT FUNCTIONS

a. Inspection Scope (IPs 69001 and 40755)

The inspector reviewed selected aspects of:

Technical Safety Review Committee (TSRC) meeting minutes

GTRR staff safety review records

TSRC and GTRR staff audit records

responses to safety reviews and audits

personnel qualifications

GTRR DP dated June 1998

TS, Amendment No. 14, dated July 22, 1999

b. Observations and Findings

DP Section 2.4 states that the TSRC: 1) will review and approve all plans, policies and

procedures to be performed under the GTRR Decommissioning Project, 2) will review

and audit the decontamination and decommissioning project operations and activities,

3) members will be appointed by the President of Georgia Tech, and 4) will keep a

written record of the meetings and will report directly to the President.

During inspections in 2000 and 2002, the inspector reviewed the qualifications of the

TSRC members and confirmed that they met the requirements specified in TS Section 5.2 and DP Section 2.4. The results of the 2000 inspections were

documented in NRC Inspection Report (IR) No. 50-160/2000-201 dated March 15,

2000, NRC IR No. 50-160/2000-202 dated August 31, 2000, and NRC IR

-4-

No. 50-160/2000-203 dated December 1, 2000. The inspector noted that the TSRC

met more often than the required semiannual frequency and that a quorum was

present each time. The inspector reviewed the minutes of the TSRC and determined

that they provided guidance, direction, operations oversight, and 10 CFR 50.59

request reviews as required by the DP and TS.

TSRC meeting minutes and audit records and GTRR staff audit records showed that

safety reviews and audits were conducted as required by TS Section 5.2(d). The

content of the audits and safety reviews were consistent with the TS. These reviews

provided appropriate guidance, direction, and oversight to ensure satisfactory

decommissioning of the reactor.

By examining the TSRCs review of the DP and their audits of the operations and

training programs, the inspector determined that the safety reviews, audits, and

associated findings were satisfactory and that the licensee took the appropriate

corrective actions in response to the findings.

The inspector reviewed selected decommissioning and facility change approvals.

Records and observations showed that changes at the facility were acceptably

reviewed in accordance with 10 CFR 50.59 and applicable licensee administrative

controls. None of the changes constituted an unreviewed safety question or required

a change to the TS. The inspector determined that TSRC 10 CFR 50.59 request

reviews were adequately performed.

c.

Conclusions

The audits conducted by the TSRC and GTRR staffs were in accordance with the

requirements specified in TS Section 5.2 and DP Section 2.4. TSRC 10 CFR 50.59

request reviews were adequately performed.

3.

PROCEDURES

a. Inspection Scope (IPs 69001 and 40755)

The inspector reviewed selected aspects of:

administrative controls

records for changes and temporary changes

DP dated June 1998

TS, Amendment No. 14, dated July 22, 1999

decommissioning procedures

logs and records

b. Observations and Findings

During decommissioning activities, the inspector confirmed that written health physics

(HP) and decommissioning procedures were available for those tasks and items

required by TS Section 5.3 and the DP Sections 2.3.1.1. and 3.1.2.2. The procedures

-5-

were routinely updated and then approved by the TSRC while minor modifications to

the procedures were approved by the facility director.

Decommissioning procedures and operating plans reviewed and approved by the

TSRC included those dealing with:

-

Initial Radiological Survey Plan and Procedures

-

Health and Safety Plan and Procedures

-

Waste Management Plan and Procedures

-

Management Plan

-

Quality Assurance Plan and Procedures

-

Radiation Protection Plan and Procedures

-

Decommissioning Work Plan

-

Final Radiological Survey Plan

Through review of the 2000 training records and interviews with staff, the inspector

determined that the training of staff and contractor personnel concerning procedures

was adequate. During the inspectors tours of the facility, it was observed that

personnel performing radiation surveys, conducting instrument checks, issuing

dosimetry, and performing the decommissioning work were doing so in accordance

with applicable procedures.

c.

Conclusions

Based on the procedures and records reviewed and observations of personnel during

the inspections in 2000, it was determined that the procedural control and

implementation program was acceptably maintained and met TS and DP

requirements.

4.

REMOVAL OF MATERIALS

a. Inspection Scope (IPs 69001, 86740, and 85102)

The inspector reviewed selected aspects of:

transportation records

disposal records

NRC Forms 741 and 742

DP dated June 1998

b. Observations and Findings

From 1964 through 1995, the licensee operated a heavy water moderated and cooled

research reactor at the NNRC. The reactor was shut down on November 17, 1995, in

preparation for the summer Olympic Games in Atlanta, GA, and was never restarted.

As noted in a previous NRC IR No. 50-160/1996-01, the irradiated fuel was shipped to

the Savannah River Site on February 18, 1996. The licensee had previously shipped

-6-

the unirradiated fuel to the Oak Ridge National Laboratory site in Tennessee on

January 31, 1996. The inspector confirmed that, as noted by DP Section 1.5, all fuel

had been removed from NNRC prior to decommissioning.

Fifty-six (56) total radioactive waste shipments were made during the GTRR

decommissioning. The final waste shipment occurred on August 3, 2001. Radioactive

waste was sent to one of four consignees: 1 Duratek Inc.; 2 CNSI Barnwell; 3

Envirocare of Utah; and 4 Westinghouse Savannah River Site. During 2000, the

inspector confirmed through records review, interviews with licensee staff, and actual

observation, that radioactive waste was disposed of as required by DP Section 3.2

and in accordance with Department of Transportation and NRC regulations.

c.

Conclusions

As a result of the records review and on-site observations made during

decommissioning tours, it was confirmed that the fuel and radioactive waste were

removed from the site in accordance with the GTRR DP requirements, and

Department of Transportation and NRC regulations.

5.

DECOMMISSIONING ACTIVITIES

a. Inspection Scope (IPs 69001 and 40755)

The inspector reviewed selected aspects of:

operational logs and records

decommissioning procedures

decommissioning logs and records

DP dated June 1998

the facility during tours

b. Observations and Findings

As noted above, the reactor was permanently shut down on November 17, 1995. All

irradiated reactor fuel was removed from the site on February 18, 1996. On July 22,

1999, following a request by the licensee and a review by the NRC, Amendment No.

14 to Facility License No. R-97 was issued which authorized decommissioning of the

GTRR. The licensees contractor started its decommissioning of the facility in January

2000. (Actual decommissioning of the facility was completed in May 2001, although

the contractors final survey of the facility continued for several months afterwards.)

Decommissioning activities focused on the dismantling and removal of the reactor

proper, its support structures, auxiliary equipment and components, and the biological

shield. The inspector examined the following selected tasks as directly described in

DP Section 2.3, Decommissioning Activities and Tasks:

Reactor Complex

-7-

Vertical Beam Ports - The vertical beam ports will be removed - including the

thimbles, thimble plugs, sample tubes, and liners. The lead will be removed from

the plugs and sent to a mixed waste processor. The other items will be

segmented as necessary, packaged, and disposed of as radioactive waste.

Shim Safety Rods and Drives - The four shim safety rods will be disconnected

from the drives, removed through the top shield, cut in half, and disposed of as

mixed waste. The shim safety rod drives will be disconnected, removed,

segmented, and disposed of as radioactive waste.

Horizontal Beam Gates - The ten horizontal beam gate drive motors will be

disconnected and removed. The gates will be separated from the shafts and cut

open. The lead inside will be removed and disposed of as mixed waste, and the

remainder disposed of as radioactive waste.

Spent Fuel Storage Holes - The spent fuel storage hole plugs will be removed and

disposed of as radioactive waste. The hole liners will be core drilled out and each

liner will be cut in half, packaged, and disposed of as radioactive waste.

Piping and Instrumentation - This task involved the removal of miscellaneous

piping and ventilation in and around the reactor complex. The materials will be

disposed of as radioactive waste.

Lead Cover Plate - The lead cover plate will be removed in two distinct pieces - the

inner plate and outer plate. The 24 lead and steel port plugs will be removed from

the inner plate and cut open with an abrasive saw. The lead will be removed and

disposed of as mixed waste, and the steel will be disposed of as radioactive waste.

Upper Top Shield - The upper top shield will also be removed in two distinct pieces

- the inner shield plug and outer shield plug. The 24 concrete and steel inner port

plugs and eight concrete and steel outer port plugs will be removed and disposed

of as radioactive waste. The inner concrete and steel upper top shield will be

removed and disposed of as radioactive waste. The outer concrete and steel

upper shield plug will be removed and disposed of as radioactive waste.

Lower Shield Plug - The 31 lead, concrete, and steel port plugs will be removed

from the lower top shield plug and cut open with an abrasive saw. The lead will be

removed and disposed of as mixed waste. The remaining concrete and steel will

be disposed of as radioactive waste.

Fuel Spray Manifold - The fuel spray manifold pipe will be cut free within the

reactor, utilizing long-handled tools, and transferred to the contamination control

envelope. The manifold will be further segmented and disposed of as radioactive

waste.

Reactor Vessel - A remote operated robotic arm will be installed in the reactor

vessel to facilitate segmentation. Using an abrasive saw connected to the robotic

arm, the horizontal beam ports and through tubes will be cut free and lifted out.

-8-

The bottom pipes will be core bored and removed. The reactor vessel will be cut

into sections using an abrasive saw mounted on the robotic arm. Lifting holes will

first be drilled into each section with a drill attached to the robotic arm, and each

section rigged. Each section will be lifted out with the overhead crane, transferred

to the packaging area and disposed of as radioactive waste.

Graphite Retaining Sleeve - The graphite retaining sleeve will be removed in a

similar fashion as the vessel. Each section will be disposed of as radioactive

waste.

Graphite Removal - The 4-inch by 4-inch graphite stringers will be removed using

long-handled tools from either the top of the biological shield or through the

thermal column. The graphite will be packaged and disposed of as radioactive

waste.

Horizontal Beam Ports - The beam port and through tube plugs will be removed

and disposed as radioactive waste. Lead will first be removed from the through

tube plugs by cutting the top off the plugs with an abrasive saw. The lead will be

disposed of as mixed waste.

Boral Removal - The 1/4-inch boral sheet staked to the inside of the steel tank will

be removed in a similar fashion as the vessel. Each section will be disposed of as

radioactive waste.

Inner Steel Tank - The inner steel tank will follow a similar removal scenario to that

described for the boral removal. The tank will be cut into sections using an

abrasive saw mounted on the robotic arm. Lifting holes will first be drilled into

each section, and each section will then be rigged. After cutting, the section will be

transferred to the packaging area using the overhead crane. Each section will be

disposed of as radioactive waste.

Lead Thermal Shield - The lead thermal shield was formed by pouring molten lead

into the space between the inner and outer steel tanks. With the inner tank and

cooling coils removed, the lead will be pried free of the outer tank in easily handled

pieces with long-handled tools. The pieces will be lowered into a basket and

transferred to a waste container. The lead will be disposed of as mixed waste.

Outer Steel Tank - The outer steel tank will be removed using the same methods

as the removal of the inner steel tank. The tank may have to be pried free of the

concrete prior to removal. Each section will be disposed of as radioactive waste.

Thermal Column Shutter and Shielding - In order to remove the thermal column

shutter and shields, the two thermal column door plugs will be removed first,

segmented with an abrasive saw and the lead removed. The steel cover plate will

then be removed, segmented and packaged. The exposed lead shield will then be

removed and packaged for processing. The concrete and steel blocks will also be

removed and packaged. Segmenting of these blocks is not required. The

concrete, steel and lead doors will be removed, segmented and packaged. Any

-9-

remaining lead will then be removed and packaged for disposal. The concrete and

steel will be disposed of as radioactive waste and the lead as mixed waste.

Biomedical Irradiation Facility Shutter and Shielding - In order to remove the

biomedical irradiation facility shutter, the aluminum cover plate will be removed first

and segmented. The exposed lead bricks will then be removed and packaged.

The movable shield plugs and doors will also be removed. The outer bismuth

shield, the water tank, and the inner bismuth plug will be removed and packaged.

Due to the package restrictions, segmenting of these items will have to be

performed. The materials will be disposed as radioactive waste.

Fission Chambers - The fission chambers will be removed and packaged for

disposal. The remaining U-235 will be packaged and shipped to an appropriate

site.

Biological Shield

Activated Concrete - Due to the relatively small amount of activated concrete and

the limited access, the concrete will be removed with a bobcat/jackhammer. The

waste will be packaged and disposed of as radioactive waste.

Bottom Shield - As above, due to the relatively small amount of activated concrete

and the limited access the concrete will be removed with a bobcat/jackhammer.

The waste will be packaged and disposed of as radioactive waste.

During the inspections in 2000, the inspector observed various of these activities as

they were being conducted including: piping and instrumentation, upper top shield,

graphite removal, lead thermal shield, fission chambers, and activated concrete. In

order to verify that all the above tasks had been performed in accordance with the DP,

the inspector also reviewed the related licensee and contractor records and surveys,

and toured the facility. The inspector determined that the above tasks had been

completed in accordance with final approved DP.

c.

Conclusions

Based on the observations made during the inspection, decommissioning activities

have been performed as required by DP Section 2.3 and licensee procedures.

6.

RELEASE CRITERIA

a. Inspection Scope (IPs 69001 and 40755)

The inspector reviewed selected aspects of:

DP dated June 1998

Georgia Institute of Technology Research Reactor Decommissioning Project

Characterization Report, issued May 1998

Final Status Survey Report for the GTRR facility issued June 2002

-10-

b. Observations and Findings

The primary contaminants of concern for the GTRR are beta-gamma emittersfission

and activation productsresulting from reactor operation. The NRC-approved

guidelines for release for unrestricted use for building surfaces were based on those

for beta-gamma emitters contained in NRC Regulatory Guide 1.86 (NRC 1974). These

guidelines are:

5,000 -- dpm/100 cm2, averaged over a 1 m2 area

15,000 -- dpm/100 cm2, maximum in a 100 cm2 area

1,000 -- dpm/100 cm2, removable.

However, due to the presence of the hard-to-detect-radionuclides H-3 and Fe-55, the

above guidelines were modified to account for the contributing activity of these

radionuclides. The modified guidelines are (Shaw 2002):

2,400 -- dpm/100 cm2 average activity in a 1 m2 area

7,200 -- dpm/100 cm2 maximum activity in a 100 cm2 area

313 -- dpm/100 cm2 removable activity

GITs final survey plan (GTS 2000) stated that radionuclide concentrations in soil for

the contaminants of concern would meet the NRC published (Federal Register Vol. 64

page 68396, December 7, 1999) screening values for selected radionuclides in

surface soils. The screening values for the GTRR radionuclides of interest are

summarized below.

Radionuclide

Guideline Value (pCi/g)

H-3

110

Fe-55

10,000

Pu-239/240

2.3

U-233/234

13.0

U-238

14.0

Ni-59

5,500

Cs-134

5.7

Cs-137

11.0

Co-60

3.8

Eu-152

8.7

Eu-154

8.0

Mn-54

15.0

Ag-110m

3.9

Zn-65

6.2

Sr-90

1.7

C-14

12.0

Ni-63

2,100

Tc-99

19.0

-11-

The inspector observed and interviewed Duratec, ITs representative.

The inspector determined that Duratec used the appropriate guideline and screening

values as calculated in the Characterization Report and specified in the approved DP.

c. Conclusions

Duratec used the appropriate guideline and screening values as required by the DP, in

performing the final survey.

7.

CONFIRMATORY FINAL SURVEY

a. Inspection Scope (IPs 69001 and 40755)

The inspector reviewed selected aspects of:

DP dated June 1998

Georgia Institute of Technology Research Reactor Decommissioning Project

Characterization Report, issued May 1998

Final Status Survey Report for the GTRR facility issued June 2002

b. Observations and Findings

(1) Overview

DP Section 4.0, Proposed Final Radiation Survey Plan, describes the final

radiation survey to be conducted of the facility prior to license termination. This

survey is required in order to ensure that the area satisfies the unrestricted

release criteria for radioactive material according to NUREG/CR- 5849. (DP

Section 4.1) Additionally, DP Section 4.2.3 specifies, As stated in

NUREG/CR-5849, proper documentation of every aspect of the final survey is

necessary for future reference to the decommissioning survey. An accurate

mapping of the reactor containment building and surrounding areas within this

decommissioning project will be maintained for future review and verification by a

regulatory inspector.

Although the licensee is responsible for performing and documentation the

decommissioning and final status survey (Final Status Survey Report for the

GTRR facility issued June 2002), the NRC verifies the licensees performance

through inspections during decommissioning and a confirmatory final survey at the

end.

As part of this confirmatory process ESSAP reviewed and evaluated GITs final

survey plan and report (GTS 2000 and Shaw 2002). The documents were

reviewed for general thoroughness, accuracy, and consistency. Data were

evaluated to assure that areas exceeding guidelines were identified and had

undergone remediation. Final status survey results were compared with guidelines

to ensure that the data had been interpreted correctly. Comments were provided

-12-

to the NRC, documenting the review of the final survey plan and the final survey

report.

The procedures, methods, and data submitted by GIT were considered to be

appropriate and adequately documented the radiological status of the GTRR.

ESSAP confirmed that the licensee modified the gross activity guidelines to

account for hard-to-detect radionuclides. This data was reviewed by ESSAP to

evaluate its appropriateness of use and determined it to be satisfactory.

ESSAP performed confirmatory surveys of the GTRR during the period October 21

to 23, 2002. The surveys were performed in accordance with the site-specific

survey plan submitted to and approved by the NRC and the ORISE/ESSAP Survey

Procedures and Quality Assurance Manuals (ORISE 2002a, 2000a, and 2002b).

ESSAP surveys, their individual findings, and overall results are described in the

sections following.

(2) Surface Scans

Surface scans for beta and gamma radiation were performed over approximately

100 percent of the floor surfaces in the basement and on the first floor and 50

percent of the floor surfaces on the second floor. Surface scans for beta radiation

were performed over approximately 50 percent of the lower walls in the basement,

excluding the Stairwell General Area, 10 percent on the first floor, and 5 percent

on the second floor. Surface scans for beta radiation were also performed in the

vessel tunnel over approximately 50 percent of the surface.

Particular attention was given to remediated and adjacent surfaces, cracks and

joints in the floors and walls, and other locations where residual radioactive

material may have accumulated. Surface scans were not performed on any upper

wall or ceiling surfaces, in the Helium Rupture Disk Chamber, or in the Reactor

Building Ventilation Hold-Up Duct areas. Scans were performed using gas

proportional and NaI scintillation detectors coupled to ratemeters or ratemeter-

scalers with audible indicators. Locations of elevated direct radiation were noted

for further investigation.

ESSAP identified two areas of elevated beta surface radiation. One area was

found on a scabbled portion of the wall in the Bismuth Leak area. Another area

was found on the floor of the processor equipment room. The concrete block walls

in the air compressor room were also noted as being uniformly elevated. Scans of

the remaining surfaces did not identify any additional locations of elevated beta or

gamma radiation.

Surface scans of outdoor locations including soil areas, paved areas, and gravel

surfaces were performed over approximately 50 to 100 percent of the accessible

areas using a sodium iodide scintillation detector coupled to a ratemeter.

-13-

Gamma surface scans were within the range of ambient background levels except

for an area adjacent to the NNRC that was determined to be caused by radiation

shine from the hot cell facility and storage vault.

(3) Surface Activity Measurements

Construction material-specific backgrounds were determined in areas of similar

construction, but without a history of radioactive material use. Ambient gamma

backgrounds were determined in areas where direct beta measurements were

performed; these background measurements were used to correct gross beta

surface activity measurements.

Direct measurements for total beta activity were performed at 35 locations, chosen

randomly and based on surface scan results. Additional measurements to

determine the average activity level in one area were also performed. Dry smears

were collected at each direct measurement location for determining removable

gross alpha and gross beta activity. Wet smears were collected from areas

adjacent to direct measurement locations to determine the H-3 and C-14 activity.

Direct measurements were performed using gas proportional detectors coupled to

ratemeter-scalers.

ESSAP identified an activity of 9,700 dpm/100 cm2 over approximately 0.5 m2 in

the elevated area identified in the Bismuth Leak area, with an average activity of

1700 dpm/100 cm2 over the contiguous one square meter area. The elevated

area identified in the process equipment room was limited to approximately

100 cm2 with an activity of 4,100 dpm/100 cm2. An activity range of 2,700 to

5,100 dpm/100 cm2 was determined for the concrete block in the air compressor

room, which GIT claimed resulted from naturally occurring radioactive material in

the blocks. Confirmatory scans on the interior and exterior of the room found the

radiation levels to be evenly distributed throughout the blocks, confirming the

activity was from the material used to make them. Removable activity levels

ranged from 0 to 3 dpm/100 cm2 for gross alpha and from -5 to 45 dpm/100 cm2

for gross beta. H-3 removable activity levels ranged from 3 to 466 dpm/100 cm2.

C-14 removable activity levels ranged from -2 to 86 dpm/100 cm2.

(4) Exposure Rate Measurements

ESSAP obtained background exposure rate measurements from various locations

within the NNRC, having similar construction as the GTRR. The NNRC has a site

history of radiological material usage; however, there are no other buildings similar

in construction to the GTRR and NNRC on the GIT campus. Exposure rate

measurements, using a microrem meter at one meter above the floor, were

performed in the center of selected areas or rooms within the GTRR.

Average interior building exposure rates ranged from 9 to 25 R/h. Background

exposure rates performed in the NNRC ranged from 18 to 20 R/h.

-14-

Exterior exposure rate measurements, using a microrem meter at one meter

above the surface, were performed at five random locations from the reactor yard

area surrounding the GTRR.

Average exterior exposure rates ranged from 14 to 18 R/h. Background

exposure rates performed at various intersections on the GIT campus ranged from

12 to 20 R/h.

(5) Sampling

ESSAP collected surface soil (0-15 cm) samples at each exposure rate

measurement location.

Analysis of the soil samples by gamma spectroscopy for gamma-emitting mixed

fission and activation products identified Cs-137 at typical fall out concentrations.

Radionuclide concentrations for Co-60 and Cs-137, which are the predominant

radionuclides of concern at research reactor facilities ranged from -0.02 to 0.03

pCi/g for Co-60 and -0.02 to 0.21 pCi/g for Cs-137. All other radionuclides of

concern were reported as less than the respective minimum detectable

concentration of the procedure, which ranged from 0.03 to 0.11 pCi/g.

(6) ESSAP Results

Compliance for residual surface activity was shown using the GIT calibration

methodology approved by the NRC. Since ESSAPs calibration method differs,

this required adjusting the ESSAP-calculated surface activity by the ratio of the

efficiencies for the GIT and ESSAP methods. The correction factor was

approximately 2.3. All corrected ESSAP confirmatory surface activity

measurements, including the identified elevated areas, met guidelines and did not

require further remediation. Additional investigation by the inspector verified that

the concrete block in the air compressor room was made from material with a high

composition of naturally occurring radioactive material.

Except for the air compressor room in the basement, all exposure rate

measurements were less than 5 R/h above background for each survey unit.

Confirmatory surface soil samples were less than the screening values listed in the

GIT final survey plan (GTS 2000).

c.

Conclusions

Based on the above observations, surveys, evaluations, and analyses, the inspector

concluded that: 1) the elevated surface activity and exposure readings in the

basement compressor room were due to naturally occurring radioactive material; and

2) based on the results of the licensees final status survey and ESSAPs confirmatory

measurements, GIT has adequately demonstrated that the GTRR facility satisfies the

criteria for release for unrestricted use.

-15-

8.

MAINTENANCE AND SURVEILLANCE

a. Inspection Scope (IP 40755)

The inspector reviewed selected aspects of:

maintenance procedures

equipment maintenance records

surveillance and calibration procedures

surveillance, calibration, and test data sheets and records

reactor periodic checks, tests, verification, and decommissioning activities

facility design and DP changes and records

NNRC Procedure 4200, 10 CFR 50.59 Review Program for Changes and Tests

During Decommissioning, Revision 01, dated November 1, 1999

TS, Amendment No. 14, dated July 22, 1999

-16-

b. Observations and Findings

(1) General Maintenance

During decommissioning general maintenance was focused on the support

services and equipment and not on any reactor systems. The inspector reviewed

maintenance records, interviewed staff and observed minor maintenance

performed on the various systems in operation. Based on the inspectors

interviews and observations, general maintenance was acceptable for an

industrial site.

(2) Surveillance

The inspector reviewed records of the TS Section 3 required surveillance

verifications performed during 2000. The results of the surveillances for the

radiation monitoring system and the ventilation system were within prescribed TS

limits and procedure parameters, and in close agreement with the previous

surveillance results.

(3) Change Control

TS or DP related 10 CFR 50.59 changes required review by the TSRC in

accordance with TS Section 5.2.

The inspector reviewed various TSRC approved change packages for changing

the method of accomplishing certain decommissioning activities. The inspector

determined that the changes had been evaluated, reviewed, and approved as

required by NNRC Procedure 4200, 10 CFR 50.59 Review Program for Changes

and Tests During Decommissioning, Revision 01, dated November 1, 1999. The

reviews were technically complete and adequately documented. Additionally, the

inspector concluded that TSRC 10 CFR 50.59 reviews and approvals were

focused on safety, and met licensee program requirements.

c.

Conclusions

The licensee's program for surveillance and limiting conditions for operation

verification satisfied TS and DP requirements. The licensee's maintenance and

design change programs were in place and were being implemented as required by

licensee procedures.

9.

RADIATION PROTECTION

a. Inspection Scope (IPs 69001 and 40755)

The inspector reviewed selected aspects of the radiation protection program (RPP):

Radiation Protection Training

radiological signs and posting

-17-

facility and equipment during tours

routine surveys and monitoring

survey and monitoring procedures

dosimetry records

maintenance and calibration of radiation monitoring equipment

periodic checks, quality control, and test source certification records

NNRC Radiation Protection Program (RPP)

event/incident records

b. Observations and Findings

(1) Radiation Protection Program

Although individual procedures had been revised and some added, the RPP had

not functionally changed since the last inspection. The licensee reviewed the RPP

at least annually in accordance with 10 CFR 20.1101(c). This review and

oversight was provided by the TSRC as required by TS Section 5.2.d(9) and DP

Section 2.4.3.

The inspectors review of procedure change records, revisions, and radiation work

permits (RWP), confirmed that the RSO, individually and as a TSRC member,

reviewed and approved RWPs, and advised the Director and TSRC on matters

regarding radiological safety as required by TS Section 5.1.b, DP Section 2.4.1,

and the RPP.

Through record reviews and interviews with GTRR and Duratec staffs, the

inspector confirmed that the RPP was applied to all activities during the

decommissioning project, as required by DP Section 3.1 and GTRR procedures.

(2) Radiation Protection Postings

The inspector observed that caution signs, postings and controls to radiation and

contaminated areas at the NNRC were acceptable for the hazards involved and

were implemented as required by 10 CFR Part 20, Subpart J. The inspector

observed licensee and contractor personnel and verified that they complied with

the indicated precautions for access to such areas. The inspector confirmed that

current copies of NRC Form-3 and notices to workers were posted in appropriate

areas in the facility as required by 10 CFR Part 19.11.

(3) Radiation Protection Surveys

The inspector audited the GTRR daily, monthly, quarterly, and other periodic

contamination and radiation surveys, including airborne activity sampling,

performed from 2000 to 2003. The surveys were performed and documented as

required by DP Section 3.0, and GTRR survey procedures. HP surveys required

for special decommissioning activities, such as RWPs, were also performed and

documented as required. Results were evaluated and corrective actions taken and

documented when readings/results exceeded set action levels.

-18-

-19-

(4) Dosimetry

The inspector confirmed that dosimetry was issued to staff, contractors, and

visitors as outlined in licensee procedures. The licensees dosimetry issuing

criteria specified that dosimetry should be issued to individuals who might receive

a dose equivalent exceeding 10 percent of the annual limits specified in 10 CFR Part 20.1201(a). This criteria meet the requirements of 10 CFR 20.1502 for

individual monitoring. Training records showed that personnel were acceptably

trained in radiation protection practices. During the inspection the inspector

observed that workers and staff wore their dosimetry as required.

The licensee used a National Voluntary Laboratory Accreditation Program-

accredited vendor to process personnel thermoluminescent dosimetry. Dosimetry

results were reviewed by the RSO and doses above the facilitys ALARA limits

were investigated as required. The inspectors review of the licensees radiological

exposure records from 2000 to 2003 verified that occupational doses were within

10 CFR Part 20 limitations.

(5) Radiation Monitoring Equipment

The calibration and periodic checks of the portable survey meters, radiation

monitoring, air sampling, and counting lab instruments were performed by facility

staff or by certified contractors. The inspector confirmed that the licensees

calibration procedures and annual, quarterly, semiannual and monthly calibration,

test, and check frequencies satisfied TS Section 4.3.3, DP Section 3.1, and

10 CFR 20.1501(b) requirements, and the American National Standards Institute

N323 Radiation Protection Instrumentation Test and Calibration or the

instruments manufacturers' recommendations. The inspector verified that the

calibration and check sources used were traceable to the National Institute of

Standards and Technology and that the sources geometry and energies matched

those used in actual detection/analyses.

The inspector also reviewed Duratec instrument calibrations. Their calibration and

periodic checks of the portable survey meters, radiation monitoring, air sampling,

and counting lab instruments were performed by their staffs or by certified

contractors. The inspector confirmed that calibration procedures and annual,

semiannual quarterly, monthly, and daily calibrations, tests, and check frequencies

satisfied Duratec HPS procedures. Calibrations also met 10 CFR Part 20.1501(b)

requirements, and the American National Standards Institute N323 Radiation

Protection Instrumentation Test and Calibration or the instruments manufacturers'

recommendations. The inspector verified that the calibration and check sources

used were traceable to the National Institute of Standards and Technology and

that the sources geometry and energies matched those used in actual

detection/analyses.

The inspector reviewed the calibration lists and confirmed that calibrations for the

radiation monitoring and counting lab equipment in use had been performed and

that all portable instruments in use were calibrated.

-20-

All instruments checked by the inspector had current calibrations appropriate for

the types and energies of radiation they were used to detect and/or measure.

(6) Respiratory Protection

DP Section 3.1.6 states that the Respiratory Protection Program will be

implemented by the decommissioning contractor in compliance with ANSI Z-88.2,

US NRC Regulatory Guide 8.15, 10 CFR 20.1701 through 20.1704, and OSHA

requirements.

While conducting inspections during decommissioning activities at the facility, the

inspector reviewed the respiratory protection program in use by contractor

personnel. The inspector noted that the licensee and contractor had established a

respiratory protection program as required by DP Section 3.1.6 and were using

tested and certified NIOSH/MSHA equipment as required. Records and

observation showed that air sampling was being conducted, surveys and

bioassays were completed as required, testing of respirators was being done, fit

testing of individuals was performed, and individuals were required to pass a

physical in order to qualify to use a respirator. The respiratory protection program

was in compliance with 10 CFR 20.1703 and the DP.

(4) Effluents

The program for the monitoring and storage of radioactive liquid, gases, and solids

was acceptable. Radioactive effluents were monitored and released when within

established limits as outlined in licensee procedures and the regulations. The

principles of As Low As Reasonably Achievable (ALARA) were acceptably

implemented to minimize radioactive releases. Monitoring equipment was

maintained and calibrated as required. Records were current and acceptably

maintained.

c.

Conclusions

Based on the observations made and records audited, it was determined that,

because: 1) surveys were completed and documented as required by

10 CFR 20.1501(a) and licensee procedures, 2) postings met regulatory requirements,

3) the personnel dosimetry program was acceptably implemented and doses were in

conformance with licensee and 10 CFR Part 20 limits, 4) portable survey meters,

radiation monitoring, and counting lab instruments were maintained and calibrated as

required, 5) the evaluation and administration of the respiratory program were

adequately performed, and 6) the program for monitoring, storage, and release of

effluents was acceptable, the RPP implemented by the licensee satisfied NRC and DP

requirements.

5.

EXIT MEETING SUMMARY

The inspector presented the inspection results to members of licensee management at

the conclusion of the inspection on October 23, 2002. The licensee acknowledged the

findings presented and did not identify as proprietary any of the material provided to or

reviewed by the inspector during the inspection.

PARTIAL LIST OF PERSONS CONTACTED

  • T. Bauer

Project Leader, ESSAP

  • T. Brown

Field Staff, ESSAP

  • R. Eby

Executive Engineer, (Vice President Energy, Environment, and Systems)

CH2M HILL

  • N. Hertel

Director, Neely Nuclear Research Center

  • R. Ice

Manager, Office of Radiation Safety

P. Jones

Project Manager, GTS Duratek Field Services

G. Kalinauskas

Senior Project Engineer, IT Corporation

R. Morton

Field Staff, ESSAP

  • Attended exit meeting.

The inspector also contacted other supervisory, technical and administrative staff personnel

as well.

INSPECTION PROCEDURE (IP) USED

IP 69001

Class II Non-Power Reactors

IP 40755

Class III Non-power Reactors

IP 85102

Material Control and Accounting - Reactors

IP 86740

Inspection of Transportation Activities

ITEMS OPENED AND CLOSED

Open

None

Closed

None

PARTIAL LIST OF ACRONYMS USED

Duratec

GTS Duratec

DP

Georgia Institute of Technology Research Reactor Decommissioning Plan dated

June 1998

ESSAP

Environmental Survey and Site Assessment Program

GIT

Georgia Institute of Technology

GTRR

Georgia Institute of Technology Research Reactor

HP

Health Physics

IT

IT Corporation

NNRC

Neely Nuclear Research Center

NRC

Nuclear Regulatory Commission

ORISE

Oak Ridge Institute for Science and Education

RWP

Radiation Work Permits

RPP

Radiation Protection Program

RSO

Radiation Safety Officer

TS

Technical Specifications

-22-

TSRC

Technical Safety Review Committee