{{#Wiki_filter:CLINTON POWER STATION Job Performance Measure Determine an emergency dose for a job and select a worker to perform the job JPM Number: | {{#Wiki_filter:CLINTON POWER STATION Job Performance Measure Determine an emergency dose for a job and select a worker to perform the job JPM Number: 997777.0301 Revision Number: 00 Date: 7/29/03 Developed By: | ||
T. Pickley 8/10/03 Instructor Date Validated By: | |||
J. Anderson 10/16/03 SME or Instructor Date Review By: | |||
P. Ryan | |||
_8/18/03 Operations Representative Date | |||
JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: | Page 2 of 8 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: | ||
All steps of this checklist should be performed upon initial validation. Prior to JPM usage, revalidate JPM using steps 8 through 11 below. | |||
: 1. Task description and number, JPM description and number are identified. | |||
: 2. Knowledge and Abilities (K/A) references are included. | |||
: 3. Performance location specified. (in-plant, control room, or simulator) | |||
: 4. Initial setup conditions are identified. | |||
: 5. Initiating and terminating cues are properly identified. | |||
: 6. Task standards identified and verified by SME review. | |||
: 7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*). | |||
: 8. Verify the procedure referenced by this JPM matches the most current revision of that procedure: | |||
Procedure Rev. _____ Date _____________ | Procedure Rev. _____ Date _____________ | ||
: 9. Pilot test the JPM: | |||
: a. verify cues both verbal and visual are free of conflict, and | : a. verify cues both verbal and visual are free of conflict, and | ||
: b. ensure performance time is accurate. | : b. ensure performance time is accurate. | ||
: 10. If the JPM cannot be performed as written with proper responses, then revise the JPM. | |||
: 11. When JPM is revalidated, SME or Instructor sign and date JPM cover page. | |||
SME/Instructor | SME/Instructor Date SME/Instructor Date SME/Instructor Date | ||
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 | CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 3 of 8 Revision Record (Summary) | ||
: 1. Revision 00, | : 1. Revision 00, This is a new JPM | ||
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 | CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 4 of 8 Operators Name: | ||
SSN: | |||
Job | Job | ||
==Title:== | ==Title:== | ||
NLO | NLO RO SRO STA SRO Cert JPM Title/Number: 997777.0301, Determine an emergency dose for a job and select a worker to perform the job Revision Number: | ||
00 Task Number and | |||
==Title:== | ==Title:== | ||
997777.03, Complete Emergency Plan Activities performed by an SRO Suggested Testing Environment: Any Actual Testing Environment: | 997777.03, Complete Emergency Plan Activities performed by an SRO Suggested Testing Environment: | ||
Any Actual Testing Environment: I Simulator Plant Control Room Testing Method: | |||
Simulate Faulted: | |||
No I | |||
Perform Alternate Path: | |||
No Time Critical: | |||
No Estimated Time to Complete: 6 _minutes Actual Time Used: | |||
minutes | |||
==References:== | ==References:== | ||
EVALUATION | EVALUATION | ||
==SUMMARY== | ==SUMMARY== | ||
Were all the Critical Elements performed satisfactorily? | Were all the Critical Elements performed satisfactorily? | ||
Yes | |||
No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be: | |||
Satisfactory | |||
Unsatisfactory Comments: | |||
Evaluators Name: __________________________ | Evaluators Name: __________________________ | ||
Evaluators Signature: | Evaluators Signature: | ||
Date: | |||
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 | CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 5 of 8 READ TO THE OPERATOR I will explain the initial conditions, which step(s) to simulate or discuss, and provide the initiating cues. When you complete the task successfully, the objective of this Job Performance Measure will be satisfied. | ||
SIMULATOR SET-UP CONDITIONS: | SIMULATOR SET-UP CONDITIONS: | ||
None TASK STANDARDS: | None TASK STANDARDS: | ||
| Line 65: | Line 90: | ||
==REFERENCES:== | ==REFERENCES:== | ||
EP-AA-113r4 Personnel Protective Actions EVALUATOR INSTRUCTIONS: | EP-AA-113r4 Personnel Protective Actions EVALUATOR INSTRUCTIONS: | ||
Amplifying cues are provided within the JPM steps. | Amplifying cues are provided within the JPM steps. | ||
| Line 73: | Line 97: | ||
Three personnel have volunteered for the operation: Alvin Jones age 35, Bob Smith age 35 and Ted Knight age 45. | Three personnel have volunteered for the operation: Alvin Jones age 35, Bob Smith age 35 and Ted Knight age 45. | ||
One person is needed for the operation. What will the dose for the operation be? Which volunteer would be at the least risk of health effects? | One person is needed for the operation. What will the dose for the operation be? Which volunteer would be at the least risk of health effects? | ||
START TIME: | START TIME: | ||
Page | |||
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 6 of 8 | |||
========================================================================== | ========================================================================== | ||
PERFORMANCE INFORMATION Critical steps are denoted with an asterisk (*) to the left of the step number and appear in BOLDED letters. Failure to meet the standards for a critical step constitutes failure of the Job Performance Measure. The sequence of steps is assumed unless denoted in the comments section of the JPM. | PERFORMANCE INFORMATION Critical steps are denoted with an asterisk (*) to the left of the step number and appear in BOLDED letters. Failure to meet the standards for a critical step constitutes failure of the Job Performance Measure. The sequence of steps is assumed unless denoted in the comments section of the JPM. | ||
========================================================================== | ========================================================================== | ||
PERFORMANCE STEPS | PERFORMANCE STEPS | ||
*1. | *1. | ||
*2. | Determines total dose for the operation Standard Dose is 30 Rem CUE Comments SAT UNSAT Comment Number | ||
*2. | |||
Determines volunteer at least risk of health effects Standard Volunteer is Ted Knight CUE Comments SAT UNSAT Comment Number STOP TIME:_____________ | |||
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 | CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 7 of 8 TERMINATING CUES: | ||
Total dose and volunteer are determined. | Total dose and volunteer are determined. | ||
K/A REFERENCE NUMBERS Importance Rating K/A SYSTEM NUMBER | K/A REFERENCE NUMBERS Importance Rating K/A SYSTEM NUMBER K/A NUMBER RO SRO 2.3.4 2.5 3.1 | ||
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 | CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 8 of 8 INITIATING CUE An emergency life saving operation must be performed. The operation will take 10 minutes in a 180 Rem/hr field. Three personnel have volunteered for the operation: Alvin Jones age 35, Bob Smith age 35 and Ted Knight age 45. One person is needed for the operation. What will the dose for the operation be? Which volunteer would be at the least risk of health effects?}} | ||
Latest revision as of 03:34, 16 January 2025
| ML041070064 | |
| Person / Time | |
|---|---|
| Site: | Clinton |
| Issue date: | 01/06/2004 |
| From: | James Anderson, Pickley T, Ryan P Exelon Generation Co, Exelon Nuclear |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| -RFPFR, 50-461/04-301, JPM 997777.0301, Rev 00 50-461/04-301 | |
| Download: ML041070064 (10) | |
Text
CLINTON POWER STATION Job Performance Measure Determine an emergency dose for a job and select a worker to perform the job JPM Number: 997777.0301 Revision Number: 00 Date: 7/29/03 Developed By:
T. Pickley 8/10/03 Instructor Date Validated By:
J. Anderson 10/16/03 SME or Instructor Date Review By:
P. Ryan
_8/18/03 Operations Representative Date
Page 2 of 8 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE:
All steps of this checklist should be performed upon initial validation. Prior to JPM usage, revalidate JPM using steps 8 through 11 below.
- 1. Task description and number, JPM description and number are identified.
- 2. Knowledge and Abilities (K/A) references are included.
- 3. Performance location specified. (in-plant, control room, or simulator)
- 4. Initial setup conditions are identified.
- 5. Initiating and terminating cues are properly identified.
- 6. Task standards identified and verified by SME review.
- 7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*).
- 8. Verify the procedure referenced by this JPM matches the most current revision of that procedure:
Procedure Rev. _____ Date _____________
- 9. Pilot test the JPM:
- a. verify cues both verbal and visual are free of conflict, and
- b. ensure performance time is accurate.
SME/Instructor Date SME/Instructor Date SME/Instructor Date
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 3 of 8 Revision Record (Summary)
- 1. Revision 00, This is a new JPM
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 4 of 8 Operators Name:
SSN:
Job
Title:
NLO RO SRO STA SRO Cert JPM Title/Number: 997777.0301, Determine an emergency dose for a job and select a worker to perform the job Revision Number:
00 Task Number and
Title:
997777.03, Complete Emergency Plan Activities performed by an SRO Suggested Testing Environment:
Any Actual Testing Environment: I Simulator Plant Control Room Testing Method:
Simulate Faulted:
No I
Perform Alternate Path:
No Time Critical:
No Estimated Time to Complete: 6 _minutes Actual Time Used:
minutes
References:
EVALUATION
SUMMARY
Were all the Critical Elements performed satisfactorily?
Yes
No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be:
Satisfactory
Unsatisfactory Comments:
Evaluators Name: __________________________
Evaluators Signature:
Date:
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 5 of 8 READ TO THE OPERATOR I will explain the initial conditions, which step(s) to simulate or discuss, and provide the initiating cues. When you complete the task successfully, the objective of this Job Performance Measure will be satisfied.
SIMULATOR SET-UP CONDITIONS:
None TASK STANDARDS:
The dose is determined to be 30 Rem and Ted Knight is selected to perform the job TOOLS, EQUIPMENT, OTHER SPECIAL REQUIREMENTS:
None PROCEDURAL/
REFERENCES:
EP-AA-113r4 Personnel Protective Actions EVALUATOR INSTRUCTIONS:
Amplifying cues are provided within the JPM steps.
Supply the operator the partially filled out EP-AA-113 Attachment 2s for the volunteers.
INITIAL CONDITIONS AND INITIATING CUE:
An emergency life saving operation must be performed. The operation will take 10 minutes in a 180 Rem/hr field.
Three personnel have volunteered for the operation: Alvin Jones age 35, Bob Smith age 35 and Ted Knight age 45.
One person is needed for the operation. What will the dose for the operation be? Which volunteer would be at the least risk of health effects?
START TIME:
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 6 of 8
==============================================================
PERFORMANCE INFORMATION Critical steps are denoted with an asterisk (*) to the left of the step number and appear in BOLDED letters. Failure to meet the standards for a critical step constitutes failure of the Job Performance Measure. The sequence of steps is assumed unless denoted in the comments section of the JPM.
==============================================================
PERFORMANCE STEPS
- 1.
Determines total dose for the operation Standard Dose is 30 Rem CUE Comments SAT UNSAT Comment Number
- 2.
Determines volunteer at least risk of health effects Standard Volunteer is Ted Knight CUE Comments SAT UNSAT Comment Number STOP TIME:_____________
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 7 of 8 TERMINATING CUES:
Total dose and volunteer are determined.
K/A REFERENCE NUMBERS Importance Rating K/A SYSTEM NUMBER K/A NUMBER RO SRO 2.3.4 2.5 3.1
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 997777.0301 REVISION: 00 Page 8 of 8 INITIATING CUE An emergency life saving operation must be performed. The operation will take 10 minutes in a 180 Rem/hr field. Three personnel have volunteered for the operation: Alvin Jones age 35, Bob Smith age 35 and Ted Knight age 45. One person is needed for the operation. What will the dose for the operation be? Which volunteer would be at the least risk of health effects?