{{#Wiki_filter:ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2                                                                   Page 1 of 4 UNIT:   1     REVISION #       0     DATE:
{{#Wiki_filter:ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2 Page 1 of 4 UNIT:
TUOI NUMBER:     A1JPM-RO-HTBAL2 SYSTEM:   A.1 - Conduct of Operations TASK:     Perform a Manual Heat Balance Calculation JTA:       ANO-RO-ADMIN-NORM-182 KA VALUE     RO     2.9     SRO     4.0   KA  
1 REVISION #
0 DATE:
TUOI NUMBER:
A1JPM-RO-HTBAL2 SYSTEM:
A.1 - Conduct of Operations TASK:
Perform a Manual Heat Balance Calculation JTA:
ANO-RO-ADMIN-NORM-182 KA VALUE RO 2.9 SRO 4.0 KA  


==REFERENCE:==
==REFERENCE:==
2.1.12 APPROVED FOR ADMINISTRATION TO:           RO     X SRO TASK LOCATION:     INSIDE CR:             OUTSIDE CR:           BOTH:   X SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
2.1.12 APPROVED FOR ADMINISTRATION TO:
PLANT SITE:                 SIMULATOR:   PERFORM     LAB:
RO X
POSITION EVALUTED:     RO     X     SRO ACTUAL TESTING ENVIRONMENT:         PLANT SITE:           SIMULATOR:   X   LAB:
SRO TASK LOCATION:
ACTUAL TESTING METHOD:             SIMULATE:             PERFORM:     X APPROXIMATE COMPLETION TIME IN MINUTES:               45 MINUTES
INSIDE CR:
OUTSIDE CR:
BOTH:
X SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
PLANT SITE:
SIMULATOR:
PERFORM LAB:
POSITION EVALUTED:
RO X
SRO ACTUAL TESTING ENVIRONMENT:
PLANT SITE:
SIMULATOR:
X LAB:
ACTUAL TESTING METHOD:
SIMULATE:
PERFORM:
X APPROXIMATE COMPLETION TIME IN MINUTES:
45 MINUTES  


==REFERENCES:==
==REFERENCES:==
1103.016 Heat Balance Calculation EXAMINEES NAME:                                       SSN:
1103.016 Heat Balance Calculation EXAMINEES NAME:
SSN:
EVALUATORS NAME:
EVALUATORS NAME:
THE EXAMINEES PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
THE EXAMINEES PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
SATISFACTORY:                     UNSATISFACTORY:
SATISFACTORY:
UNSATISFACTORY:
PERFORMANCE CHECKLIST COMMENTS:
PERFORMANCE CHECKLIST COMMENTS:
START TIME:                   STOP TIME:                 TOTAL TIME:
START TIME:
SIGNED:                                                     DATE:
STOP TIME:
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARTED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.
TOTAL TIME:
SIGNED:
DATE:
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARTED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.  


ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2                                                                                               Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2 Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:         It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.
JPM INITIAL TASK CONDITIONS:
It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.
All data has been recorded and 1103.016, Att. 2 has been started.
All data has been recorded and 1103.016, Att. 2 has been started.
TASK STANDARD:       The examinee has correctly calculated Secondary Side Heat Balance in Att. 2, step 2.4 and Best Estimate of Reactor Power, step 2.6.
TASK STANDARD:
TASK PERFORMANCE AIDS:           Copies of partially completed 1103.016.
The examinee has correctly calculated Secondary Side Heat Balance in Att. 2, step 2.4 and Best Estimate of Reactor Power, step 2.6.
TASK PERFORMANCE AIDS:
Copies of partially completed 1103.016.  


ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2                                                                                         Page 3 of 4 INITIATING CUE:
ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2 Page 3 of 4 INITIATING CUE:
The CRS requests that you complete the remainder of 1103.016, Attachment 2, Manual Heat Balance, beginning with step 9.2.
The CRS requests that you complete the remainder of 1103.016, Attachment 2, Manual Heat Balance, beginning with step 9.2.
CRITICAL ELEMENTS (C):         1 (C)       PERFORMANCE CHECKLIST                   STANDARDS                   N/A         SAT         UNSAT NOTE: Provide examinee with a copy of partially completed 1103.016.
CRITICAL ELEMENTS (C):
(C)     1. Perform calculations in         Examinee calculated %FPSEC Attachment 2.                  as 99.989% per step 2.4 in Att. 2. Accept answers between 99.7 and 100.2%.
1 (C)
PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT NOTE: Provide examinee with a copy of partially completed 1103.016.
(C)
: 1. Perform calculations in.
Examinee calculated %FPSEC as 99.989% per step 2.4 in Att. 2. Accept answers between 99.7 and 100.2%.
Examinee calculated %FP as 99.989% per step 2.4 in Att.
Examinee calculated %FP as 99.989% per step 2.4 in Att.
: 2. Accept answers between 99.7 and 100.2%.
: 2. Accept answers between 99.7 and 100.2%.
END
END  


ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2                                                                           Page 4 of 4 JPM INITIAL TASK CONDITIONS:
ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2 Page 4 of 4 JPM INITIAL TASK CONDITIONS:  
* It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.
 It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.  
* All data has been recorded and 1103.016, Att. 2 has been started.
 All data has been recorded and 1103.016, Att. 2 has been started.
INITIATING CUE:
INITIATING CUE:  
* The CRS requests that you complete the remainder of 1103.016, Attachment 2, Manual Heat Balance, beginning with step 9.2.
 The CRS requests that you complete the remainder of 1103.016, Attachment 2, Manual Heat Balance, beginning with step 9.2.  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 1 of 4 UNIT: 1               REV # 0             DATE: ______________________________
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 1 of 4 UNIT: 1 REV # 0 DATE: ______________________________
TUOI NUMBER: A1JPM-RO-DWG1 SYSTEM/DUTY AREA: ADMINISTRATIVE TOPIC - CONDUCT OF OPERATIONS TASK: DETERMINE ISOLATION BOUNDARY USING DRAWINGS AND/OR PRINTS JTA#: ENS-OPER-PTAG-ADMIN-1 KA VALUE RO:       2.8     SRO:     3.1     KA  
TUOI NUMBER: A1JPM-RO-DWG1 SYSTEM/DUTY AREA: ADMINISTRATIVE TOPIC - CONDUCT OF OPERATIONS TASK: DETERMINE ISOLATION BOUNDARY USING DRAWINGS AND/OR PRINTS JTA#: ENS-OPER-PTAG-ADMIN-1 KA VALUE RO:
2.8 SRO:
3.1 KA  


==REFERENCE:==
==REFERENCE:==
2.1.24 APPROVED FOR ADMINISTRATION TO: RO:         X     SRO:   X TASK LOCATION: INSIDE CR: X       OUTSIDE CR:_________ BOTH:________
2.1.24 APPROVED FOR ADMINISTRATION TO: RO: X SRO: X TASK LOCATION: INSIDE CR: X OUTSIDE CR:_________ BOTH:________
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
PLANT SITE:_______________ SIMULATOR: PERFORM           LAB:__________________
PLANT SITE:_______________ SIMULATOR: PERFORM LAB:__________________
POSITION EVALUATED: RO:___       __       SRO:___________
POSITION EVALUATED: RO:___ __
ACTUAL TESTING ENVIRONMENT: SIMULATOR:           X     PLANT SITE:__________ LAB:________
SRO:___________
TESTING METHOD: SIMULATE:_________       PERFORM:___________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:
APPROXIMATE COMPLETION TIME IN MINUTES:           10 MINUTES REFERENCE(S): 1107.001, M-213 sh. 2 EXAMINEE'S NAME:________________________________       SSN ______-_____-____________
X PLANT SITE:__________ LAB:________
TESTING METHOD: SIMULATE:_________
PERFORM:___________
APPROXIMATE COMPLETION TIME IN MINUTES:
10 MINUTES REFERENCE(S): 1107.001, M-213 sh. 2 EXAMINEE'S NAME:________________________________
SSN ______-_____-____________
EVALUATOR'S NAME:__________________________________________________________________
EVALUATOR'S NAME:__________________________________________________________________
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
SATISFACTORY:________________               UNSATISFACTORY:_________________
SATISFACTORY:________________
UNSATISFACTORY:_________________
PERFORMANCE CHECKLIST COMMENTS:
PERFORMANCE CHECKLIST COMMENTS:
____________ Start Time       ____________ Stop Time       ____________ Total Time SIGNED ________________________________ DATE: _______________________
____________ Start Time
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.
____________ Stop Time
____________ Total Time SIGNED ________________________________ DATE: _______________________
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 2 of 4 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 2 of 4 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:  
* The WCO reports the Laundry Drain pump (P-45) has a severe seal leak.

The WCO reports the Laundry Drain pump (P-45) has a severe seal leak.
INITIATING CUE:
INITIATING CUE:
The CRS directs you to determine the isolation boundary (electrical and mechanical) for Laundry Drain pump (P-45) in accordance with approved drawings and procedures.
The CRS directs you to determine the isolation boundary (electrical and mechanical) for Laundry Drain pump (P-45) in accordance with approved drawings and procedures.  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 3 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 3 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
Line 83: Line 129:
JPM INITIAL TASK CONDITIONS: The WCO reports the Laundry Drain pump (P-45) has a severe seal leak.
JPM INITIAL TASK CONDITIONS: The WCO reports the Laundry Drain pump (P-45) has a severe seal leak.
TASK STANDARD: The examinee has correctly identified the isolation boundary for Laundry Drain pump (P-45) using controlled drawings and procedures.
TASK STANDARD: The examinee has correctly identified the isolation boundary for Laundry Drain pump (P-45) using controlled drawings and procedures.
TASK PERFORMANCE AIDS: Simulator drawings and procedures
TASK PERFORMANCE AIDS: Simulator drawings and procedures  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 4 of 4 INITIATING CUE:
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 4 of 4 INITIATING CUE:
The CRS directs you to determine the isolation boundary (electrical and mechanical) for Laundry Drain pump (P-
The CRS directs you to determine the isolation boundary (electrical and mechanical) for Laundry Drain pump (P-
: 45) in accordance with approved drawings and procedures.
: 45) in accordance with approved drawings and procedures.
CRITICAL ELEMENTS (C)                 1 (C)       PERFORMANCE CHECKLIST                             STANDARD                     N/A     SAT   UNSAT NOTE:
CRITICAL ELEMENTS (C) 1 (C)
PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT NOTE:
Inform examinee that this task is to identify the isolation boundary only, a tagout will not be prepared.
Inform examinee that this task is to identify the isolation boundary only, a tagout will not be prepared.
(C)   1. Determine isolation boundaries.       Examinee determined proper boundary isolations to include:
(C)
* B3134, power supply
: 1. Determine isolation boundaries.
* LZ-2A, Suction from T-19
Examinee determined proper boundary isolations to include:  
* LZ-2B, Suction from T-19

* LZ-4411A, Suction from T-109
B3134, power supply  
* LZ-4411B, Suction from T-109

* LZ-4, Discharge
LZ-2A, Suction from T-19  
* Open ABS-25 casing drain(not required for full credit)

LZ-2B, Suction from T-19  

LZ-4411A, Suction from T-109  

LZ-4411B, Suction from T-109  

LZ-4, Discharge  

Open ABS-25 casing drain(not required for full credit)
(Note: Examinee should determine boundary isolations using controlled procedures and drawings, specifically 1107.001 and M-213 sh. 2).
(Note: Examinee should determine boundary isolations using controlled procedures and drawings, specifically 1107.001 and M-213 sh. 2).
END
END  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3                                                               Page 1 of 4 UNIT: 1               REV # 2             DATE: ______________________________
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3 Page 1 of 4 UNIT: 1 REV # 2 DATE: ______________________________
TUOI NUMBER: A1JPM-RO-SURV3 SYSTEM/DUTY AREA: ADMINISTRATIVE TOPIC - EQUIPMENT CONTROL TASK: PERFORM SURVEILLANCE TESTS JTA#: ANO-RO-ADMIN-NORM-23 KA VALUE RO:       3.0     SRO:     3.4     KA  
TUOI NUMBER: A1JPM-RO-SURV3 SYSTEM/DUTY AREA: ADMINISTRATIVE TOPIC - EQUIPMENT CONTROL TASK: PERFORM SURVEILLANCE TESTS JTA#: ANO-RO-ADMIN-NORM-23 KA VALUE RO:
3.0 SRO:
3.4 KA  


==REFERENCE:==
==REFERENCE:==
2.2.12 APPROVED FOR ADMINISTRATION TO: RO:       X           SRO:
2.2.12 APPROVED FOR ADMINISTRATION TO: RO: X SRO:
TASK LOCATION: INSIDE CR:       X     OUTSIDE CR:_________ BOTH:________
TASK LOCATION: INSIDE CR:
X OUTSIDE CR:_________ BOTH:________
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
PLANT SITE:_______________ SIMULATOR: PERFORM             LAB:__________________
PLANT SITE:_______________ SIMULATOR: PERFORM LAB:__________________
POSITION EVALUATED: RO:____       __     SRO:___________
POSITION EVALUATED: RO:____ __
ACTUAL TESTING ENVIRONMENT: SIMULATOR:                 PLANT SITE:__________ LAB:________
SRO:___________
TESTING METHOD: SIMULATE:_________       PERFORM:___________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:
APPROXIMATE COMPLETION TIME IN MINUTES:           10 MINUTES REFERENCE(S): 1104.036, Emergency Diesel Generator Operation EXAMINEE'S NAME:________________________________       SSN ______-_____-____________
PLANT SITE:__________ LAB:________
TESTING METHOD: SIMULATE:_________
PERFORM:___________
APPROXIMATE COMPLETION TIME IN MINUTES:
10 MINUTES REFERENCE(S): 1104.036, Emergency Diesel Generator Operation EXAMINEE'S NAME:________________________________
SSN ______-_____-____________
EVALUATOR'S NAME:__________________________________________________________________
EVALUATOR'S NAME:__________________________________________________________________
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
SATISFACTORY:________________               UNSATISFACTORY:_________________
SATISFACTORY:________________
UNSATISFACTORY:_________________
PERFORMANCE CHECKLIST COMMENTS:
PERFORMANCE CHECKLIST COMMENTS:
____________ Start Time       ____________ Stop Time       ____________ Total Time SIGNED ________________________________ DATE: _______________________
____________ Start Time
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.
____________ Stop Time
____________ Total Time SIGNED ________________________________ DATE: _______________________
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3                                                           Page 2 of 4 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3 Page 2 of 4 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:  
* A surveillance test of DG1 Fuel Transfer Pump P-16A is in progress.

* Supplement 5 of 1104.036 up to step 2.6 is completed.
A surveillance test of DG1 Fuel Transfer Pump P-16A is in progress.  

Supplement 5 of 1104.036 up to step 2.6 is completed.
INITIATING CUE:
INITIATING CUE:
The CRS directs you to complete the surveillance test of P-16A in accordance with 1104.036, Supplement 5.
The CRS directs you to complete the surveillance test of P-16A in accordance with 1104.036, Supplement 5.  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3                                                                     Page 3 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3 Page 3 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS: A surveillance test of DG1 Fuel Transfer Pump P-16A is in progress.
JPM INITIAL TASK CONDITIONS: A surveillance test of DG1 Fuel Transfer Pump P-16A is in progress.
Data gathering of Supplement 5 of 1104.029 up to step 2.6 is completed.
Data gathering of Supplement 5 of 1104.029 up to step 2.6 is completed.
TASK STANDARD: The examinee calculates pump flow rate correctly on Supplement 5 of 1104.036 and determines the data is below the minimum in the acceptance criteria.
TASK STANDARD: The examinee calculates pump flow rate correctly on Supplement 5 of 1104.036 and determines the data is below the minimum in the acceptance criteria.
TASK PERFORMANCE AIDS: 1104.036, Supplement 5, completed to step 2.6.
TASK PERFORMANCE AIDS: 1104.036, Supplement 5, completed to step 2.6.  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3                                                                           Page 4 of 4 INITIATING CUE:
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3 Page 4 of 4 INITIATING CUE:
The CRS directs you to complete the surveillance test of P-16A in accordance with 1104.036, Supplement 5.
The CRS directs you to complete the surveillance test of P-16A in accordance with 1104.036, Supplement 5.
CRITICAL ELEMENTS (C)                 2, 3, 4 (C)       PERFORMANCE CHECKLIST                               STANDARD                   N/A     SAT     UNSAT
CRITICAL ELEMENTS (C) 2, 3, 4 (C)
: 1. Review 1104.036, Supplement 5.         Examinee reviewed 1104.036, Supplement 5.                           ____    ____    ____
PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT
: 1. Review 1104.036, Supplement 5.
Examinee reviewed 1104.036, Supplement 5.
NOTE: Inform examinee that the stopwatch reads 9:41.36 (9 minutes, 41.36 seconds).
NOTE: Inform examinee that the stopwatch reads 9:41.36 (9 minutes, 41.36 seconds).
(C)   2. Calculate pump flow rate.             Examinee correctly calculated pump flow rate.
(C)
Per note, 41.36 seconds equals .68       ____    ____    ____
: 2. Calculate pump flow rate.
minutes.
Examinee correctly calculated pump flow rate.
(200 - 105) / 9.68 = 9.81 gpm (C)   3 Record flow rate in Section 3.0.       Examinee recorded flow rate in           ____    ____    ____
Per note, 41.36 seconds equals.68 minutes.
Section 3.0.
(200 - 105) / 9.68 = 9.81 gpm (C) 3 Record flow rate in Section 3.0.
(C)   4 Evaluate flow rate, compare to         Examinee circled NO in column LIMITING RANGE FOR                    titled IS DATA WITHIN LIMITING         ____    ____    ____
Examinee recorded flow rate in Section 3.0.
OPERABILITY value.                    RANGE.
(C) 4 Evaluate flow rate, compare to LIMITING RANGE FOR OPERABILITY value.
Examinee circled NO in column titled IS DATA WITHIN LIMITING RANGE.
Examinee discussed declaring pump inoperable, notifying SM, writing Condition Report, initiating corrective action, and referring to Tech Specs.
Examinee discussed declaring pump inoperable, notifying SM, writing Condition Report, initiating corrective action, and referring to Tech Specs.
NOTE:
NOTE:
The SM or CRS will consult Tech Specs to determine operability, it is the ROs responsibility to report the inoperability of P-16A only. Diesel operability will be determined by the SM/CRS.
The SM or CRS will consult Tech Specs to determine operability, it is the ROs responsibility to report the inoperability of P-16A only. Diesel operability will be determined by the SM/CRS.
Inform examinee that steps 2.8 through 2.11 have been completed.
Inform examinee that steps 2.8 through 2.11 have been completed.
END
END  


TUOI NUMBER:                                                                                                           Page 1 of 4 A1JPM-RO-DOSE-XX JOB PERFORMANCE MEASURE Unit:               1               Rev #                         1                         Date:         1/12/2004 TUOI NUMBER:           A1JPM-RO- DOSE-XX System/Duty Area:       Administrative Topic-Radiation Control Task:     Calculate Stay times for yourself and another operator JA#
TUOI NUMBER:
KA Value RO       2.6       SRO     3.3     KA Reference       G 2.3.10 Approved For Administration To: RO                                 SRO Task Location: Inside CR:                           Outside CR:                       Both:
Page 1 of 4 A1JPM-RO-DOSE-XX JOB PERFORMANCE MEASURE Unit:
Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:                       Simulator:               Perform                 Lab:
1 Rev #
Position Evaluated: RO:                           X                           SRO:                     X Actual Testing Environment: Simulator:                             Plant Site:                     Lab Testing Method: Simulate:                                                 Perform:
1 Date:
Approximate Completion Time In Minutes:                                         10 Minutes Reference(S):       HP Survey Map of P36C, Pump Room 54.
1/12/2004 TUOI NUMBER:
Examinee's Name:                                                                     SSN:
A1JPM-RO-DOSE-XX System/Duty Area:
Administrative Topic-Radiation Control Task:
Calculate Stay times for yourself and another operator JA#
KA Value RO 2.6 SRO 3.3 KA Reference G 2.3.10 Approved For Administration To: RO SRO Task Location: Inside CR:
Outside CR:
Both:
Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:
Simulator:
Perform Lab:
Position Evaluated: RO:
X SRO:
X Actual Testing Environment: Simulator:
Plant Site:
Lab Testing Method: Simulate:
Perform:
Approximate Completion Time In Minutes:
10 Minutes Reference(S):
HP Survey Map of P36C, Pump Room 54.
Examinee's Name:
SSN:
Evaluator's Name:
Evaluator's Name:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
Satisfactory:                                         Unsatisfactory:
Satisfactory:
Unsatisfactory:
Performance Checklist Comments:
Performance Checklist Comments:
Start Time                                     Stop Time                                     Total Time Signed                                                                 Date:
Start Time Stop Time Total Time Signed Date:
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.  


TUOI NUMBER:                                                                                         Page 2 of 4 A1JPM-RO-DOSE-XX THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:
Page 2 of 4 A1JPM-RO-DOSE-XX THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:
JPM INITIAL TASK CONDITIONS:
Line 176: Line 269:
HP Survey map of P36C Pump Room, Room number 54.
HP Survey map of P36C Pump Room, Room number 54.
SIMULATOR SETUP:
SIMULATOR SETUP:
N/A
N/A  


TUOI NUMBER:                                                                                             Page 3 of 4 A1JPM-RO-DOSE-XX INITIATING CUE: Determine the Stay time for you and the other AO on the job. Also determine the stay time if the air in the pump room was contaminated with a level of 0.29 DAC (stochastic) assuming no respirators are used. Provide answers with 3 significant figures (example 4.50).
TUOI NUMBER:
CRITICAL ELEMENTS (c): 1,2, and 3 C                 PERFORMANCE CHECKLIST                                   STANDARD                 N/A SAT     UN SAT C   1. Determine the HIGHEST general area dose rate in         Examinee has determined the the area of the reduction gear assembly to be used   HIGHEST general area dose rate     ____ ____    ___
Page 3 of 4 A1JPM-RO-DOSE-XX INITIATING CUE: Determine the Stay time for you and the other AO on the job. Also determine the stay time if the air in the pump room was contaminated with a level of 0.29 DAC (stochastic) assuming no respirators are used. Provide answers with 3 significant figures (example 4.50).
from the survey map.                                in the area of the reduction gear assembly to be used from the survey map of P36C pump room.
CRITICAL ELEMENTS (c): 1,2, and 3 C
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT C
: 1. Determine the HIGHEST general area dose rate in the area of the reduction gear assembly to be used from the survey map.
Examinee has determined the HIGHEST general area dose rate in the area of the reduction gear assembly to be used from the survey map of P36C pump room.
(60 mR/hr)
(60 mR/hr)
C   2. Determine Stay time (to 3 significant figures) with     Examinee has determined that no airborne contamination for both operators.       the stay time for him/her is 3.25   ____ ____    ___
C
hrs and the stay time for the other AO is 3.00 hrs plus or minus 0.01 hours.
: 2. Determine Stay time (to 3 significant figures) with no airborne contamination for both operators.
C   3. Determine Stay time( to 3 significant figures) WITH     Examinee has determined that airborne contamination for both operators.           the stay time for him/her is       ____ ____    ___
Examinee has determined that the stay time for him/her is 3.25 hrs and the stay time for the other AO is 3.00 hrs plus or minus 0.01 hours.
3.21hrs and the stay time for the other AO is 2.96 hrs plus or minus 0.01 hours.
C
: 3. Determine Stay time( to 3 significant figures) WITH airborne contamination for both operators.
Examinee has determined that the stay time for him/her is 3.21hrs and the stay time for the other AO is 2.96 hrs plus or minus 0.01 hours.
EXAMINERS CUE: This concludes the JPM.
EXAMINERS CUE: This concludes the JPM.
END
END  


TUOI NUMBER:                                                                                           Page 4 of 4 A1JPM-RO-DOSE-XX EXAMINEES COPY INITIAL CONDITIONS:
TUOI NUMBER:
A1JPM-RO-DOSE-XX Page 4 of 4 EXAMINEES COPY INITIAL CONDITIONS:
You are an AO with the plant at full power. A hot spot has developed on Makeup PUMP P36C. You and another AO will be working in the vicinity of the reduction gear assembly in order to flush the lines reduce the hot spot radiation field.
You are an AO with the plant at full power. A hot spot has developed on Makeup PUMP P36C. You and another AO will be working in the vicinity of the reduction gear assembly in order to flush the lines reduce the hot spot radiation field.
Using the supplied survey map, determine the individual stay times and another AO without exceeding the annual administrative dose limit (Ignore dose received during transit). You have an accumulated annual Whole Body dose of 1810 mR (ANO records). The other AO has an accumulated annual Whole Body dose of 1820 mR (ANO records). No additional dose has been received at any other site.
Using the supplied survey map, determine the individual stay times and another AO without exceeding the annual administrative dose limit (Ignore dose received during transit). You have an accumulated annual Whole Body dose of 1810 mR (ANO records). The other AO has an accumulated annual Whole Body dose of 1820 mR (ANO records). No additional dose has been received at any other site.
Line 195: Line 294:
Calculations should be based on ANO Unit 1 Administrative dose limits. Provide answers with 3 significant figures (example 4.50). Do not consider ALARA task requirements. Any required dose extensions have been processed and approved.
Calculations should be based on ANO Unit 1 Administrative dose limits. Provide answers with 3 significant figures (example 4.50). Do not consider ALARA task requirements. Any required dose extensions have been processed and approved.
INITIATING CUE:
INITIATING CUE:
Determine the Stay time for you and the other AO on the job. Also determine stay time if the air in the pump room was contaminated with a level of 0.29 DAC (stochastic) assuming no respirators are used. Provide answers with 3 significant figures (example 4.50).
Determine the Stay time for you and the other AO on the job. Also determine stay time if the air in the pump room was contaminated with a level of 0.29 DAC (stochastic) assuming no respirators are used. Provide answers with 3 significant figures (example 4.50).  


TUOI NUMBER:                             Administrative Questions A1JPM-RO-EP-XX                   Page 1 of 4 JOB PERFORMANCE MEASURE Unit:               1               Rev #                         1                         Date:         1/12/2004 TUOI NUMBER:           A1JPM-RO- EP-XX System/Duty Area:       Administrative Topic-Emergency Plan Task:     Answer two questions regarding RO responsibilities in Emergency Plan implementation JA#
TUOI NUMBER:
KA Value RO       3.3         SRO   3.1     KA Reference       G 2.4.39 Approved For Administration To: RO                                 SRO Task Location: Inside CR:                             Outside CR:                       Both:
A1JPM-RO-EP-XX Administrative Questions Page 1 of 4 JOB PERFORMANCE MEASURE Unit:
Suggested Testing Environment And Method (Perform Or Simulate): Perform Plant Site:                       Simulator:               Perform                 Lab:
1 Rev #
Position Evaluated: RO:                           X                             SRO:
1 Date:
Actual Testing Environment: Simulator:                             Plant Site:                     Lab Testing Method: Simulate:                                                   Perform:
1/12/2004 TUOI NUMBER:
Approximate Completion Time In Minutes:                                           10 Minutes Reference(S):       1903.030, change 024-03-0, step 6.2.2c.
A1JPM-RO-EP-XX System/Duty Area:
Administrative Topic-Emergency Plan Task:
Answer two questions regarding RO responsibilities in Emergency Plan implementation JA#
KA Value RO 3.3 SRO 3.1 KA Reference G 2.4.39 Approved For Administration To: RO SRO Task Location: Inside CR:
Outside CR:
Both:
Suggested Testing Environment And Method (Perform Or Simulate): Perform Plant Site:
Simulator:
Perform Lab:
Position Evaluated: RO:
X SRO:
Actual Testing Environment: Simulator:
Plant Site:
Lab Testing Method: Simulate:
Perform:
Approximate Completion Time In Minutes:
10 Minutes Reference(S):
1903.030, change 024-03-0, step 6.2.2c.
1903.011, change 024-03-0, form YY.
1903.011, change 024-03-0, form YY.
Examinee's Name:                                                                       SSN:
Examinee's Name:
SSN:
Evaluator's Name:
Evaluator's Name:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
Satisfactory:                                         Unsatisfactory:
Satisfactory:
Unsatisfactory:
Performance Checklist Comments:
Performance Checklist Comments:
Start Time                                     Stop Time                                     Total Time Signed                                                                 Date:
Start Time Stop Time Total Time Signed Date:
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.  


TUOI NUMBER:                     Administrative Questions A1JPM-RO-EP-XX           Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:
A1JPM-RO-EP-XX Administrative Questions Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
Type: Closed Reference Completion Time: 10 minutes Question 1: You are attending requal training in the RETC. A plant evacuation is announced. What is your assembly area?
Type: Closed Reference Completion Time: 10 minutes Question 1: You are attending requal training in the RETC. A plant evacuation is announced. What is your assembly area?
Q1 Answer : The Operations Support Center (OSC).
Q1 Answer : The Operations Support Center (OSC).  


==Reference:==
==Reference:==
Line 221: Line 340:
Comments:
Comments:
Question 2: After declaring an emergency, how soon must the ADH be notified?
Question 2: After declaring an emergency, how soon must the ADH be notified?
Q2 Answer : 15 minutes
Q2 Answer : 15 minutes  


==Reference:==
==Reference:==
Line 227: Line 346:
Comments:
Comments:
TASK STANDARD:
TASK STANDARD:
The examinee has correctly answered both questions.
The examinee has correctly answered both questions.  


TUOI NUMBER:                     Administrative Questions A1JPM-RO-EP-XX           Page 3 of 4 EXAMINEES COPY Type: Closed Reference Completion Time: 10 minutes Question 1: You are attending requal training in the RETC. A plant evacuation is announced. What is your assembly area?
TUOI NUMBER:
A1JPM-RO-EP-XX Administrative Questions Page 3 of 4 EXAMINEES COPY Type: Closed Reference Completion Time: 10 minutes Question 1: You are attending requal training in the RETC. A plant evacuation is announced. What is your assembly area?
Comments:
Comments:
Question 2: After declaring an emergency, how soon must the ADH be notified?
Question 2: After declaring an emergency, how soon must the ADH be notified?
Comments:
Comments:  


ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1                                                                   Page 1 of 4 UNIT:   1     REVISION #       0     DATE:
ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1 Page 1 of 4 UNIT:
TUOI NUMBER:     A1JPM-SRO-HTBAL1 SYSTEM:   A.1 - Conduct of Operations TASK:     Review a Manual Heat Balance Calculation JTA:       ANO-SRO-ADMIN-NORM-200 KA VALUE     RO     2.9     SRO     4.0   KA  
1 REVISION #
0 DATE:
TUOI NUMBER:
A1JPM-SRO-HTBAL1 SYSTEM:
A.1 - Conduct of Operations TASK:
Review a Manual Heat Balance Calculation JTA:
ANO-SRO-ADMIN-NORM-200 KA VALUE RO 2.9 SRO 4.0 KA  


==REFERENCE:==
==REFERENCE:==
2.1.12 APPROVED FOR ADMINISTRATION TO:           RO         SRO     X TASK LOCATION:     INSIDE CR:             OUTSIDE CR:           BOTH:   X SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
2.1.12 APPROVED FOR ADMINISTRATION TO:
PLANT SITE:                 SIMULATOR:   PERFORM     LAB:
RO SRO X
POSITION EVALUTED:     RO             SRO       X ACTUAL TESTING ENVIRONMENT:         PLANT SITE:           SIMULATOR:   X   LAB:
TASK LOCATION:
ACTUAL TESTING METHOD:             SIMULATE:             PERFORM:     X APPROXIMATE COMPLETION TIME IN MINUTES:               45 MINUTES
INSIDE CR:
OUTSIDE CR:
BOTH:
X SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
PLANT SITE:
SIMULATOR:
PERFORM LAB:
POSITION EVALUTED:
RO SRO X
ACTUAL TESTING ENVIRONMENT:
PLANT SITE:
SIMULATOR:
X LAB:
ACTUAL TESTING METHOD:
SIMULATE:
PERFORM:
X APPROXIMATE COMPLETION TIME IN MINUTES:
45 MINUTES  


==REFERENCES:==
==REFERENCES:==
1103.016 Heat Balance Calculation EXAMINEES NAME:                                       SSN:
1103.016 Heat Balance Calculation EXAMINEES NAME:
SSN:
EVALUATORS NAME:
EVALUATORS NAME:
THE EXAMINEES PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
THE EXAMINEES PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
SATISFACTORY:                     UNSATISFACTORY:
SATISFACTORY:
UNSATISFACTORY:
PERFORMANCE CHECKLIST COMMENTS:
PERFORMANCE CHECKLIST COMMENTS:
START TIME:                   STOP TIME:                 TOTAL TIME:
START TIME:
SIGNED:                                                     DATE:
STOP TIME:
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARTED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.
TOTAL TIME:
SIGNED:
DATE:
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARTED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.  


ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1                                                                                             Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1 Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:         It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.
JPM INITIAL TASK CONDITIONS:
It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.
The CBOT has completed 1103.016, Heat Balance Calculation, and calculated Rx thermal power to be 101.483%.
The CBOT has completed 1103.016, Heat Balance Calculation, and calculated Rx thermal power to be 101.483%.
NIs are reading an average of 99.1%. The CBOTs math has been verified to be correct by an extra RO.
NIs are reading an average of 99.1%. The CBOTs math has been verified to be correct by an extra RO.
TASK STANDARD:       The examinee has correctly identified two of four errors in Heat Balance Calculation.
TASK STANDARD:
TASK PERFORMANCE AIDS:           Copies of completed 1103.016.
The examinee has correctly identified two of four errors in Heat Balance Calculation.
TASK PERFORMANCE AIDS:
Copies of completed 1103.016.  


ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1                                                                                       Page 3 of 4 INITIATING CUE:
ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1 Page 3 of 4 INITIATING CUE:  
* Review the operators completed 1103.016 and complete section 11.0.

* In addition, verify compliance with Technical Specification SR 3.3.1.2. .
Review the operators completed 1103.016 and complete section 11.0.  
CRITICAL ELEMENTS (C):         1, 3 (C)       PERFORMANCE CHECKLIST                         STANDARDS                 N/A       SAT       UNSAT NOTE: Provide examinee with a copy of completed 1103.016. Examinee may state initially that the as performed Heat Balance would require adjustment of NIs to be in compliance with Tech Spec SR 3.3.1.2.

(C)   1. Review 1103.016.                     Examinee reviewed 1103.016.
In addition, verify compliance with Technical Specification SR 3.3.1.2..
CRITICAL ELEMENTS (C):
1, 3 (C)
PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT NOTE: Provide examinee with a copy of completed 1103.016. Examinee may state initially that the as performed Heat Balance would require adjustment of NIs to be in compliance with Tech Spec SR 3.3.1.2.
(C)
: 1. Review 1103.016.
Examinee reviewed 1103.016.
Examinee discovered two of four errors in calculations.
Examinee discovered two of four errors in calculations.
: 1. Step 2.4 value used for Q losses was taken from step 2.2 vs. 2.3.
: 1. Step 2.4 value used for Q losses was taken from step 2.2 vs. 2.3.
Line 271: Line 428:
: 3. Step 2.5 value used for Q losses was taken from step 2.2 vs. 2.3.
: 3. Step 2.5 value used for Q losses was taken from step 2.2 vs. 2.3.
: 4. Step 2.6 % full power calculation is incorrect due to above errors.
: 4. Step 2.6 % full power calculation is incorrect due to above errors.
: 2. Instruct CBOT to re-perform           Examinee stated that 1103.016.                           1103.016 should be re-performed.
: 2. Instruct CBOT to re-perform 1103.016.
Examinee stated that 1103.016 should be re-performed.
NOTE: Inform examinee that 1103.016 has been re-performed and calculated Rx thermal power is 99.99%.
NOTE: Inform examinee that 1103.016 has been re-performed and calculated Rx thermal power is 99.99%.
(C)   3. Verify compliance with Technical     Examinee concludes that SR Specification surveillance SR       3.3.1.2 as recalculated Rx 3.3.1.2.                            thermal power is within 2% of initial NI readings.
(C)
END
: 3. Verify compliance with Technical Specification surveillance SR 3.3.1.2.
Examinee concludes that SR 3.3.1.2 as recalculated Rx thermal power is within 2% of initial NI readings.
END  


ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1                                                                           Page 4 of 4 JPM INITIAL TASK CONDITIONS:
ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1 Page 4 of 4 JPM INITIAL TASK CONDITIONS:  
* It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.
 It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.  
* The CBOT has completed 1103.016, Heat Balance Calculation, and calculated Rx thermal power to be 101.483%
 The CBOT has completed 1103.016, Heat Balance Calculation, and calculated Rx thermal power to be 101.483%  
* NIs are reading an average of 99.1%.
 NIs are reading an average of 99.1%.  
* The CBOTs math calculations have been verified to be correct by an extra RO.
 The CBOTs math calculations have been verified to be correct by an extra RO.
INITIATING CUE:
INITIATING CUE:  
* Review the operators completed 1103.016 and complete section 11.0.
 Review the operators completed 1103.016 and complete section 11.0.  
* In addition, verify compliance with Technical Specification SR 3.3.1.2.
 In addition, verify compliance with Technical Specification SR 3.3.1.2.  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4                                                               Page 1 of 4 UNIT: 1               REV # 0             DATE: ______________________________
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4 Page 1 of 4 UNIT: 1 REV # 0 DATE: ______________________________
TUOI NUMBER: A1JPM-SRO-SURV4 SYSTEM/DUTY AREA: ADMINISTRATIVE TOPIC - CONDUCT OF OPERATIONS TASK: MONITOR CONDUCT OF SHIFT SURVEILLANCE TESTS JTA#: ANO-SRO-ADMIN-NORM-200 KA VALUE RO:       3.0     SRO:     3.4     KA  
TUOI NUMBER: A1JPM-SRO-SURV4 SYSTEM/DUTY AREA: ADMINISTRATIVE TOPIC - CONDUCT OF OPERATIONS TASK: MONITOR CONDUCT OF SHIFT SURVEILLANCE TESTS JTA#: ANO-SRO-ADMIN-NORM-200 KA VALUE RO:
3.0 SRO:
3.4 KA  


==REFERENCE:==
==REFERENCE:==
2.2.12 APPROVED FOR ADMINISTRATION TO: RO:                     SRO:   X TASK LOCATION: INSIDE CR:         OUTSIDE CR:_________ BOTH:____X____
2.2.12 APPROVED FOR ADMINISTRATION TO: RO:
SRO:
X TASK LOCATION: INSIDE CR:
OUTSIDE CR:_________ BOTH:____X____
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
PLANT SITE:_______________ SIMULATOR: PERFORM           LAB:__________________
PLANT SITE:_______________ SIMULATOR: PERFORM LAB:__________________
POSITION EVALUATED: RO:____     __       SRO:___________
POSITION EVALUATED: RO:____ __
ACTUAL TESTING ENVIRONMENT: SIMULATOR:                 PLANT SITE:__________ LAB:________
SRO:___________
TESTING METHOD: SIMULATE:_________       PERFORM:___________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:
APPROXIMATE COMPLETION TIME IN MINUTES:           20 MINUTES REFERENCE(S): 1106.006, Emergency Feedwater Pump Operation EXAMINEE'S NAME:________________________________       SSN ______-_____-____________
PLANT SITE:__________ LAB:________
TESTING METHOD: SIMULATE:_________
PERFORM:___________
APPROXIMATE COMPLETION TIME IN MINUTES:
20 MINUTES REFERENCE(S): 1106.006, Emergency Feedwater Pump Operation EXAMINEE'S NAME:________________________________
SSN ______-_____-____________
EVALUATOR'S NAME:__________________________________________________________________
EVALUATOR'S NAME:__________________________________________________________________
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
SATISFACTORY:________________               UNSATISFACTORY:_________________
SATISFACTORY:________________
UNSATISFACTORY:_________________
PERFORMANCE CHECKLIST COMMENTS:
PERFORMANCE CHECKLIST COMMENTS:
____________ Start Time       ____________ Stop Time       ____________ Total Time SIGNED ________________________________ DATE: _______________________
____________ Start Time
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.
____________ Stop Time
____________ Total Time SIGNED ________________________________ DATE: _______________________
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4                                                             Page 2 of 4 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4 Page 2 of 4 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:  
* The quarterly test of Emergency Feedwater Pump (P-7B) per 1106.006, Supplement 11, was performed on the previous shift.

* The SM is performing Section 4, Shift Manager Review and Analysis.
The quarterly test of Emergency Feedwater Pump (P-7B) per 1106.006, Supplement 11, was performed on the previous shift.  
INITIATING CUE:
 The SM is performing Section 4, Shift Manager Review and Analysis.
* The SM requests that you conduct a peer review of the test since he has found some errors.
INITIATING CUE:  
* Identify at least 2 errors in the test.
 The SM requests that you conduct a peer review of the test since he has found some errors.  
 Identify at least 2 errors in the test.  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4                                                                         Page 3 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4 Page 3 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS: The quarterly test of Emergency Feedwater Pump (P-7B) per 1106.006, Supplement 11, was performed on the previous shift. The SM is performing Section 4, Shift Manager Review and Analysis.
JPM INITIAL TASK CONDITIONS: The quarterly test of Emergency Feedwater Pump (P-7B) per 1106.006, Supplement 11, was performed on the previous shift. The SM is performing Section 4, Shift Manager Review and Analysis.
TASK STANDARD: The examinee has reviewed 1106.0006, Supplement 11 and identified at least 2 administrative errors in the test.
TASK STANDARD: The examinee has reviewed 1106.0006, Supplement 11 and identified at least 2 administrative errors in the test.
TASK PERFORMANCE AIDS: Completed 1106.0006, Supplement 11.
TASK PERFORMANCE AIDS: Completed 1106.0006, Supplement 11.  


ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4                                                                         Page 4 of 4 INITIATING CUE:
ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4 Page 4 of 4 INITIATING CUE:  
* The SM requests that you conduct a peer review of the test since he has found some errors.

* Identify at least 2 errors in the test.
The SM requests that you conduct a peer review of the test since he has found some errors.  
CRITICAL ELEMENTS (C)                     2 (C)       PERFORMANCE CHECKLIST                             STANDARD                   N/A     SAT     UNSAT

: 1. Review 1106.006, Supplement 11.       Examinee reviewed 1106.006, Supplement 11.
Identify at least 2 errors in the test.
(C)   2. Identify at least 2 administrative   Examinee identified at least 2 of the errors.                              following administrative errors:
CRITICAL ELEMENTS (C) 2 (C)
* Independent verification initials missing in step 1.2.1.
PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT
* Entry into T.S. time clock step was N/Ad at step 2.1.4.
: 1. Review 1106.006, Supplement 11.
* Acceptance Criteria Table 4, EFW Test Recirc Flow FI-2888 recorded as 532 gpm and YES circled when this value is greater than Limiting Range for Operability.
Examinee reviewed 1106.006, Supplement 11.
* Stopwatch cal due date has expired in step 3.2.1.
(C)
END
: 2. Identify at least 2 administrative errors.
Examinee identified at least 2 of the following administrative errors:  

Independent verification initials missing in step 1.2.1.  

Entry into T.S. time clock step was N/Ad at step 2.1.4.  

Acceptance Criteria Table 4, EFW Test Recirc Flow FI-2888 recorded as 532 gpm and YES circled when this value is greater than Limiting Range for Operability.  

Stopwatch cal due date has expired in step 3.2.1.
END  


TUOI NUMBER:                                                                                                           Page 1 of 4 A1JPM-SRO-XX JOB PERFORMANCE MEASURE Unit:               1               Rev #                         1                         Date:         1/12/2004 TUOI NUMBER:           A1JPM-SRO-XX System/Duty Area:       Administrative Topic-Emergency Procedures/Plan Task:     Determine Emergency Action Level after Scenario #3 of OP test.
TUOI NUMBER:
A1JPM-SRO-XX Page 1 of 4 JOB PERFORMANCE MEASURE Unit:
1 Rev #
1 Date:
1/12/2004 TUOI NUMBER:
A1JPM-SRO-XX System/Duty Area:
Administrative Topic-Emergency Procedures/Plan Task:
Determine Emergency Action Level after Scenario #3 of OP test.
JA#
JA#
KA Value RO                 SRO     4.1     KA Reference       G 2.4.41 Approved For Administration To: RO                               SRO Task Location: Inside CR:                         Outside CR:                         Both:
KA Value RO SRO 4.1 KA Reference G 2.4.41 Approved For Administration To: RO SRO Task Location: Inside CR:
Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:                     Simulator:               Perform                 Lab:
Outside CR:
Position Evaluated: RO:                                                       SRO:                   X Actual Testing Environment: Simulator:                             Plant Site:                     Lab Testing Method: Simulate:                                                 Perform:
Both:
Approximate Completion Time In Minutes:                                         5 Minutes Reference(S):       1903.010 Emergency Action Level Classification, 1903.011, Emergency Response Notifications Examinee's Name:                                                                     SSN:
Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:
Simulator:
Perform Lab:
Position Evaluated: RO:
SRO:
X Actual Testing Environment: Simulator:
Plant Site:
Lab Testing Method: Simulate:
Perform:
Approximate Completion Time In Minutes:
5 Minutes Reference(S):
1903.010 Emergency Action Level Classification, 1903.011, Emergency Response Notifications Examinee's Name:
SSN:
Evaluator's Name:
Evaluator's Name:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
Satisfactory:                                       Unsatisfactory:
Satisfactory:
Unsatisfactory:
Performance Checklist Comments:
Performance Checklist Comments:
Start Time                                   Stop Time                                     Total Time Signed                                                               Date:
Start Time Stop Time Total Time Signed Date:
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.  


TUOI NUMBER:                                                                                           Page 2 of 4 A1JPM-SRO-XX THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:
A1JPM-SRO-XX Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:
JPM INITIAL TASK CONDITIONS:
Line 350: Line 555:
TASK PERFORMANCE AIDS:
TASK PERFORMANCE AIDS:
1903.010 Attachments 1 and 3, 1903.011 Attachment 2, and 1903.011M SIMULATOR SETUP:
1903.010 Attachments 1 and 3, 1903.011 Attachment 2, and 1903.011M SIMULATOR SETUP:
N/A
N/A  


TUOI NUMBER:                                                                                                 Page 3 of 4 A1JPM-SRO-XX INITIATING CUE: For the given plant conditions, determine the applicable EAL classification and initiate notifications per the applicable Shift Manager Emergency Direction and Control Checklist in 1903.011.
TUOI NUMBER:
CRITICAL ELEMENTS (c): 3and 6 C               PERFORMANCE CHECKLIST                                   STANDARD                     N/A   SAT     UN SAT
A1JPM-SRO-XX Page 3 of 4 INITIATING CUE: For the given plant conditions, determine the applicable EAL classification and initiate notifications per the applicable Shift Manager Emergency Direction and Control Checklist in 1903.011.
: 1. Compare event conditions with the Index of EALs,       Turned to Attachment 1 of Attachment 1 of 1903.010, Emergency Action Level     1903.010, Index of EALs.                ____  ____    ___
CRITICAL ELEMENTS (c): 3and 6 C
Classification.
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT
: 2. Turn to appropriate EAL and compare EAL criteria       Turned to a specific EAL in Safety with event conditions.                                System Function, Attachment 3 of       ____  ____    ___
: 1. Compare event conditions with the Index of EALs, of 1903.010, Emergency Action Level Classification.
1903.010.
Turned to Attachment 1 of 1903.010, Index of EALs.
C   3. Declare the emergency classification.                 Declared or stated the event is an SAE per EAL 2.4, based on RCS           ____  ____    ___
: 2. Turn to appropriate EAL and compare EAL criteria with event conditions.
leakage greater than normal makeup capacity (not required to be stated), no fuel clad damage, and SCM not restored.
Turned to a specific EAL in Safety System Function, Attachment 3 of 1903.010.
: 4. Initiate immediate notifications.                     Referred to 1903.011 and turned to Attachment 2.
C
: 3. Declare the emergency classification.
Declared or stated the event is an SAE per EAL 2.4, based on RCS leakage greater than normal makeup capacity (not required to be stated), no fuel clad damage, and SCM not restored.
: 4. Initiate immediate notifications.
Referred to 1903.011 and turned to Attachment 2.
NOTE: Cue the examinee that the Unit 2 Shift Engineer is performing the initial notifications per 1903.011 after the examinee has stated that Unit 2 Shift Engineer (or control room communicator) has been requested.
NOTE: Cue the examinee that the Unit 2 Shift Engineer is performing the initial notifications per 1903.011 after the examinee has stated that Unit 2 Shift Engineer (or control room communicator) has been requested.
: 5. Begin completion of form 1903.011M, Alert             Began completion of form Emergency Direction and Control Checklist for Shift   1903.011M Alert Emergency               ____  ____    ___
: 5. Begin completion of form 1903.011M, Alert Emergency Direction and Control Checklist for Shift Manager.
Manager.                                              Direction and Control Checklist for Shift Manager.
Began completion of form 1903.011M Alert Emergency Direction and Control Checklist for Shift Manager.
Examinee should fill in the data on items 1 and 2.
Examinee should fill in the data on items 1 and 2.
Examinee should simulate (or state) direction of the SE to complete the initial notification.
Examinee should simulate (or state) direction of the SE to complete the initial notification.
C   6. (Simulate) Announce emergency on plant paging         Used plant-paging system to system.                                              (simulate) make announcement           ____  ____    ___
C
per step 4 of form 1903.011M.
: 6. (Simulate) Announce emergency on plant paging system.
Used plant-paging system to (simulate) make announcement per step 4 of form 1903.011M.
EXAMINERS CUE: This concludes the JPM.
EXAMINERS CUE: This concludes the JPM.
END
END  


TUOI NUMBER:                                                                                                     Page 4 of 4 A1JPM-SRO-XX EXAMINEES COPY INITIAL CONDITIONS:
TUOI NUMBER:
A1JPM-SRO-XX Page 4 of 4 EXAMINEES COPY INITIAL CONDITIONS:
The initial conditions for this jpm are the plant conditions when scenario #3 was terminated.
The initial conditions for this jpm are the plant conditions when scenario #3 was terminated.
INITIATING CUE:
INITIATING CUE:
For the given plant conditions, determine the applicable EAL classification and initiate notifications per the applicable Shift Manager Emergency Direction and Control Checklist in 1903.011.
For the given plant conditions, determine the applicable EAL classification and initiate notifications per the applicable Shift Manager Emergency Direction and Control Checklist in 1903.011.  


TUOI NUMBER:                                                                                                             Page 1 of 5 A1JPM-RO-CRD02 JOB PERFORMANCE MEASURE Unit:               1             Rev #                         4                         Date:
TUOI NUMBER:
TUOI NUMBER:           A1JPM-RO-CRD02 System/Duty Area:       CONTROL ROD DRIVE SYSTEM Task:     Perform Transfer To Auxiliary Supply JA#       ANO1-RO-CRD-NORM-12 KA Value RO       3.4       SRO   3.4     KA Reference       001 A4.03 Approved For Administration To: RO                               SRO Task Location: Inside CR:                           Outside CR:                       Both:
Page 1 of 5 A1JPM-RO-CRD02 JOB PERFORMANCE MEASURE Unit:
1 Rev #
4 Date:
TUOI NUMBER:
A1JPM-RO-CRD02 System/Duty Area:
CONTROL ROD DRIVE SYSTEM Task:
Perform Transfer To Auxiliary Supply JA#
ANO1-RO-CRD-NORM-12 KA Value RO 3.4 SRO 3.4 KA Reference 001 A4.03 Approved For Administration To: RO SRO Task Location: Inside CR:
Outside CR:
Both:
Suggested Testing Environment And Method (Perform Or Simulate):
Suggested Testing Environment And Method (Perform Or Simulate):
Plant Site:                     Simulator:               Perform                 Lab:
Plant Site:
Position Evaluated: RO:                                                       SRO:
Simulator:
Actual Testing Environment: Simulator:                             Plant Site:                     Lab Testing Method: Simulate:                                                 Perform:
Perform Lab:
Approximate Completion Time In Minutes:                                         15 Minutes Reference(S):       1105.009 Examinee's Name:                                                                     SSN:
Position Evaluated: RO:
SRO:
Actual Testing Environment: Simulator:
Plant Site:
Lab Testing Method: Simulate:
Perform:
Approximate Completion Time In Minutes:
15 Minutes Reference(S):
1105.009 Examinee's Name:
SSN:
Evaluator's Name:
Evaluator's Name:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
Satisfactory:                                       Unsatisfactory:
Satisfactory:
Unsatisfactory:
Performance Checklist Comments:
Performance Checklist Comments:
Start Time                                   Stop Time                                       Total Time Signed                                                               Date:
Start Time Stop Time Total Time Signed Date:
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.  


TUOI NUMBER:                                                                                                           Page 2 of 5 A1JPM-RO-CRD02 TUOI NUMBER:         ANO-1-JPM-RO-CRD02 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:
Page 2 of 5 A1JPM-RO-CRD02 TUOI NUMBER:
ANO-1-JPM-RO-CRD02 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:
JPM INITIAL TASK CONDITIONS:
Line 397: Line 629:
Group 1 Rods have been transferred to the Auxiliary Power Supply and are enabled for being moved on that power supply in run speed.
Group 1 Rods have been transferred to the Auxiliary Power Supply and are enabled for being moved on that power supply in run speed.
TASK PERFORMANCE AIDS:
TASK PERFORMANCE AIDS:
1105.009, Section 8.0
1105.009, Section 8.0  


TUOI NUMBER:                                                                                                       Page 3 of 5 A1JPM-RO-CRD02 TUOI NUMBER:         ANO-1-JPM-RO-CRD02 INITIATING CUE:         The CRS/SM directs you to transfer Group 1 Rods to the Auxiliary Power Supply for movement of Group 1 at run speed. IAW 1105.009, Section 8.0 CRITICAL ELEMENTS (c): 2, 3, 5, 6, 7, 8, 9, 10, 11 C                 PERFORMANCE CHECKLIST                                     STANDARD                     N/A   SAT     UN SAT INSTRUCTOR NOTE:
TUOI NUMBER:
Page 3 of 5 A1JPM-RO-CRD02 TUOI NUMBER:
ANO-1-JPM-RO-CRD02 INITIATING CUE:
The CRS/SM directs you to transfer Group 1 Rods to the Auxiliary Power Supply for movement of Group 1 at run speed. IAW 1105.009, Section 8.0 CRITICAL ELEMENTS (c): 2, 3, 5, 6, 7, 8, 9, 10, 11 C
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT INSTRUCTOR NOTE:
Verify the Reactor Demand and Diamond are in manual.
Verify the Reactor Demand and Diamond are in manual.
: 1. Verify transfer reset lamp is ON and TR CF is         On CRD Diamond Panel,                   ____  ____    ____
: 1. Verify transfer reset lamp is ON and TR CF is OFF.
OFF.                                                  condition of both lights was checked. Transfer reset lamp was ON and TR CF lamp was OFF.
On CRD Diamond Panel, condition of both lights was checked. Transfer reset lamp was ON and TR CF lamp was OFF.
C
C
: 2. Place Group select switch to Group 1.                 On CRD Diamond Panel, Group             ____  ____    ____
: 2. Place Group select switch to Group 1.
Select Switch was placed in Group 1 position.
On CRD Diamond Panel, Group Select Switch was placed in Group 1 position.
C                                                                                                      ____  ____    ____
: 3. Select Single Select Switch to ALL.                    On CRD Diamond Panel, Single select switch was selected to ALL.
: 4. Set Auto/Manual Switch to Manual, verify Manual        On CRD Diamond Panel, verified          ____  ____    ____
Lamp is ON.                                          manual lamp ON or Auto/Manual pushbutton depressed to select MANUAL.
C
C
: 5. Set SEQ.- SEQ OR. switch to SEQ. OR position.         On CRD Diamond Panel, SEQ.-             ____  ____    ____
: 3. Select Single Select Switch to ALL.
SEQ OR. switch was selected to SEQ. OR position.
On CRD Diamond Panel, Single select switch was selected to ALL.
: 4. Set Auto/Manual Switch to Manual, verify Manual Lamp is ON.
On CRD Diamond Panel, verified manual lamp ON or Auto/Manual pushbutton depressed to select MANUAL.
C
: 5. Set SEQ.- SEQ OR. switch to SEQ. OR position.
On CRD Diamond Panel, SEQ.-
SEQ OR. switch was selected to SEQ. OR position.  


TUOI NUMBER:                                                                                     Page 4 of 5 A1JPM-RO-CRD02 C               PERFORMANCE CHECKLIST                               STANDARD           N/A SAT     UN SAT C
TUOI NUMBER:
: 6. Set Group/Auxiliary Switch to Auxiliary. Aux PB. On CRD Diamond Panel,         ____ ____  ____
Page 4 of 5 A1JPM-RO-CRD02 C
Group/Aux. PB was selected to Aux.
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT C
: 6. Set Group/Auxiliary Switch to Auxiliary. Aux PB.
On CRD Diamond Panel, Group/Aux. PB was selected to Aux.
C
C
: 7. Set Speed Select Switch to "JOG".                   On CRD Diamond Panel, Speed   ____ ____  ____
: 7. Set Speed Select Switch to "JOG".
Select Switch was selected to JOG position.
On CRD Diamond Panel, Speed Select Switch was selected to JOG position.
C
C
: 8. Set Clamp/Clamp Release Switch to CLAMP.           On CRD Diamond Panel, selected ____ ____  ____
: 8. Set Clamp/Clamp Release Switch to CLAMP.
Clamp/Clamp Release Switch to CLAMP.
On CRD Diamond Panel, selected Clamp/Clamp Release Switch to CLAMP.
C
C
: 9. Press Manual Transfer Switch.                       On CRD Diamond Panel, manual   ____ ____  ____
: 9. Press Manual Transfer Switch.
transfer PB was depressed.
On CRD Diamond Panel, manual transfer PB was depressed.
C
C
: 10. Set Clamp/Clamp Release Switch to Clamp               On CRD Diamond Panel,     ____ ____  ____
: 10. Set Clamp/Clamp Release Switch to Clamp Release.
Release.                                              depressed Clamp/Clamp Release Switch.
On CRD Diamond Panel, depressed Clamp/Clamp Release Switch.
C
C
: 11. Set Group/ AUX switch to Group.                   On CRD Diamond Panel,         ____ ____  ____
: 11. Set Group/ AUX switch to Group.
Group/Aux PB was selected to Group.
On CRD Diamond Panel, Group/Aux PB was selected to Group.
: 12. If movement at RUN speed is desired, set speed     On CRD Diamond Panel, Speed   ____ ____  ____
: 12. If movement at RUN speed is desired, set speed switch to RUN.
switch to RUN.                                    Select Switch was selected to RUN position.
On CRD Diamond Panel, Speed Select Switch was selected to RUN position.
END
END  


TUOI NUMBER:                                                                                   Page 5 of 5 A1JPM-RO-CRD02 EXAMINEES COPY INITIAL CONDITIONS:
TUOI NUMBER:
* Preparation to exercise rods per Supplement 2, 1105.009, is in progress.
A1JPM-RO-CRD02 Page 5 of 5 EXAMINEES COPY INITIAL CONDITIONS:  
* Rx Demand and Diamond stations are in manual.
 Preparation to exercise rods per Supplement 2, 1105.009, is in progress.  
 Rx Demand and Diamond stations are in manual.
INITIATING CUE:
INITIATING CUE:
The CRS/SM directs you to transfer Group 1 Rods to the Auxiliary Power Supply for movement of Group 1 at run speed. IAW 1105.009, Section 8.0.
The CRS/SM directs you to transfer Group 1 Rods to the Auxiliary Power Supply for movement of Group 1 at run speed. IAW 1105.009, Section 8.0.  


TUOI NUMBER:                                                                                                             Page 1 of 6 A1JPM-RO-JOB PERFORMANCE MEASURE Unit:               1             Rev #                         1                         Date:
TUOI NUMBER:
TUOI NUMBER:           A1JPM-RO-System/Duty Area:       002 Reactor Coolant System Task:     Restart a Make-up Pump following an RCS leak isolation JA#       ANO1-RO-KA Value RO       4.3       SRO     4.4     KA Reference       002.A2.01 Approved For Administration To: RO                               SRO Task Location: Inside CR:                           Outside CR:                       Both:
A1JPM-RO-Page 1 of 6 JOB PERFORMANCE MEASURE Unit:
1 Rev #
1 Date:
TUOI NUMBER:
A1JPM-RO-System/Duty Area:
002 Reactor Coolant System Task:
Restart a Make-up Pump following an RCS leak isolation JA#
ANO1-RO-KA Value RO 4.3 SRO 4.4 KA Reference 002.A2.01 Approved For Administration To: RO SRO Task Location: Inside CR:
Outside CR:
Both:
Suggested Testing Environment And Method (Perform Or Simulate):
Suggested Testing Environment And Method (Perform Or Simulate):
Plant Site:                     Simulator:           Perform       X             Lab:
Plant Site:
Position Evaluated: RO:                       X                               SRO:                     X Actual Testing Environment: Simulator:                             Plant Site:                     Lab Testing Method: Simulate:                                                 Perform:
Simulator:
Approximate Completion Time In Minutes:                                         20 Minutes Reference(S):       AOP 1203.026 Examinee's Name:                                                                     SSN:
Perform X Lab:
Position Evaluated: RO:
X SRO:
X Actual Testing Environment: Simulator:
Plant Site:
Lab Testing Method: Simulate:
Perform:
Approximate Completion Time In Minutes:
20 Minutes Reference(S):
AOP 1203.026 Examinee's Name:
SSN:
Evaluator's Name:
Evaluator's Name:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
Satisfactory:                                       Unsatisfactory:
Satisfactory:
Unsatisfactory:
Performance Checklist Comments:
Performance Checklist Comments:
Start Time                                   Stop Time                                       Total Time Signed                                                               Date:
Start Time Stop Time Total Time Signed Date:
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.  


TUOI NUMBER:                                                                                                         Page 2 of 6 A1JPM-RO-THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:
A1JPM-RO-Page 2 of 6 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:
JPM INITIAL TASK CONDITIONS:
Line 472: Line 734:
: 7. When PZR level reaches 100 close all Make up valves
: 7. When PZR level reaches 100 close all Make up valves
: 8. Shutdown all running Makeup pumps
: 8. Shutdown all running Makeup pumps
: 9. Store IC
: 9. Store IC  


TUOI NUMBER:                                                                                                     Page 3 of 6 A1JPM-RO-INITIATING CUE:             The CRS/SM directs you to restart Makeup Pump P-36C (STBY pump) IAW section 2 of AOP 1203.026, starting with step 3.6.6 CRITICAL ELEMENTS (c): 3, 8, 9 C                   PERFORMANCE CHECKLIST                                     STANDARD                 N/A SAT     UN SAT INSTRUCTOR NOTE: Examinee may review the AOP 1203.0126 prior to starting the JPM.
TUOI NUMBER:
: 1. Verify Makeup Tank outlet (CV-1275) is open               Operator verifies CV-1275 open.      ____ ____    ____
A1JPM-RO-Page 3 of 6 INITIATING CUE:
(step 3.6.6A of procedure)
The CRS/SM directs you to restart Makeup Pump P-36C (STBY pump) IAW section 2 of AOP 1203.026, starting with step 3.6.6 CRITICAL ELEMENTS (c): 3, 8, 9 C
Operator verifies MUT level is
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT INSTRUCTOR NOTE: Examinee may review the AOP 1203.0126 prior to starting the JPM.
: 2. Add to Makeup tank as necessary to maintain level         > 55.                              ____ ____    ____
: 1. Verify Makeup Tank outlet (CV-1275) is open (step 3.6.6A of procedure)
            > 55 using current RCS boron concentration.
Operator verifies CV-1275 open.
: 2. Add to Makeup tank as necessary to maintain level  
> 55 using current RCS boron concentration.
(step 3.6.6B of procedure)
(step 3.6.6B of procedure)
Operator rotates control handle C                                                                                                     ____ ____    ____
Operator verifies MUT level is
: 3. Start Aux Lube Oil pump for STBY HPI pump (P- for P-36C aux lube oil pump and 36C). (step 3.6.7 of procedure is conditional on         verifies that red light is on, green STBY HPI pump being available which was given light is off.
> 55.
as the initial condition).
C
: 4. Review SPDS data for HPI pump suction pressure           Operator should review the SPDS      ____ ____    ____
: 3. Start Aux Lube Oil pump for STBY HPI pump (P-36C). (step 3.6.7 of procedure is conditional on STBY HPI pump being available which was given as the initial condition).
history, leak location, and lowest suction pressure     data and determine that no pump achieved. (This is the BOXED NOTE prior to step         venting is required.
Operator rotates control handle for P-36C aux lube oil pump and verifies that red light is on, green light is off.
3.6.10 in the procedure).
: 4. Review SPDS data for HPI pump suction pressure history, leak location, and lowest suction pressure achieved. (This is the BOXED NOTE prior to step 3.6.10 in the procedure).
See Cue below See Cue below NOTE: Operator should skip step 3.6.10 since pump venting is not required.
See Cue below NOTE: Operator should skip step 3.6.10 since pump venting is not required.
INSTRUCTOR NOTE: Examinee must review the SPDS.
Operator should review the SPDS data and determine that no pump venting is required.
See Cue below INSTRUCTOR NOTE: Examinee must review the SPDS.
INSTRUCTOR CUE: The lowest suction pressure for the STBY pump should be around 25psig. If the SPDS is not available, then instructor must cue this value. No loss of pump suction occurred therefore candidate should NOT try to vent pump.
INSTRUCTOR CUE: The lowest suction pressure for the STBY pump should be around 25psig. If the SPDS is not available, then instructor must cue this value. No loss of pump suction occurred therefore candidate should NOT try to vent pump.
: 5. Verify HPI suction pressure >10psig.                     Operator verifies suction pressure  ____ ____    ____
: 5. Verify HPI suction pressure >10psig.
(step 3.6.11)                                           >10psig.
(step 3.6.11)
Operator verifies suction pressure
>10psig.  


TUOI NUMBER:                                                                                       Page 4 of 6 A1JPM-RO-C                 PERFORMANCE CHECKLIST                               STANDARD             N/A SAT     UN SAT
TUOI NUMBER:
: 7. Operator verifies white light
A1JPM-RO-Page 4 of 6 C
: 6. Verify the following valves in HAND and                 for HAND is on and red light  ____ ____  ____
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT
CLOSED:                                               for AUTO is off for both CV-1207 (seal injection supply)
: 6. Verify the following valves in HAND and CLOSED:
CV-1207 (seal injection supply)                        and CV-1235 (normal CV-1235 (normal makeup supply)                         makeup supply) and valves (step 3.6.12)                                         both indicate CLOSED with corresponding valve position indicator green lights ON and NOTE: Operator should skip step 3.6.13 since ES       red lights OFF.
CV-1207 (seal injection supply)
pump is not used.
CV-1235 (normal makeup supply)
Operator verifies red light is lit C   8. After AUX lube oil pump has run for > 1 minute,   for AUX lube oil pump and         ____ ____  ____
(step 3.6.12)
start the STBY HPI pump.                          places hand control switch for STBY HPI pump P-36C to start.
NOTE: Operator should skip step 3.6.13 since ES pump is not used.
Verifies the red light ON and (step 3.6.14)                                    green light OFF for P-36C.
: 7. Operator verifies white light for HAND is on and red light for AUTO is off for both CV-1207 (seal injection supply) and CV-1235 (normal makeup supply) and valves both indicate CLOSED with corresponding valve position indicator green lights ON and red lights OFF.
Operator places the hand control C
C
: 9. Stop the AUX lube oil pump for the STBY HPI       switch for the AUX lube oil pump  ____ ____  ____
: 8. After AUX lube oil pump has run for > 1 minute, start the STBY HPI pump.
pump (P-36C).                                    (for P-36C) to the OFF position and verifies green light ON and red light OFF.
(step 3.6.14)
Operator verifies red light is lit for AUX lube oil pump and places hand control switch for STBY HPI pump P-36C to start.
Verifies the red light ON and green light OFF for P-36C.
C
: 9. Stop the AUX lube oil pump for the STBY HPI pump (P-36C).
(step 3.6.15)
(step 3.6.15)
Operator pushes CV-1206 button,
Operator places the hand control switch for the AUX lube oil pump (for P-36C) to the OFF position and verifies green light ON and red light OFF.
: 10. Place CV-1206 pushbutton to OVRD. Open CV-       observes OVRD light is ON, and    ____ ____  ____
: 10. Place CV-1206 pushbutton to OVRD. Open CV-1206 (seal injection isolation valve).
1206 (seal injection isolation valve).            places the valve hand switch to open position and observes red light ON and green light OFF.
(steps 3.6.16 and 3.6.17)
(steps 3.6.16 and 3.6.17)
Operator slowly turns hand switch
Operator pushes CV-1206 button, observes OVRD light is ON, and places the valve hand switch to open position and observes red light ON and green light OFF.
: 11. Slowly open CV-1207 (seal injection control       CCW for CV-1207 in order to        ____ ____  ____
: 11. Slowly open CV-1207 (seal injection control valve) and adjust seal flow to 30-40gpm and place valve in AUTO.
valve) and adjust seal flow to 30-40gpm and place open it enough to get 30-40gpm valve in AUTO.                                   flow and place mode switch for (step 3.6.18B)                                     the valve in AUTO and observe red light is ON, white light is NOTE: step B is used because RCP bleedoff OFF.
(step 3.6.18B)
temperature should be 160 0F or less.
NOTE: step B is used because RCP bleedoff temperature should be 160 0F or less.
Operator should observe CV-
Operator slowly turns hand switch CCW for CV-1207 in order to open it enough to get 30-40gpm flow and place mode switch for the valve in AUTO and observe red light is ON, white light is OFF.
: 12. When RCP seals total flow is above setpoint (CV- 1206 FLOW light is ON and then    ____ ____  ____
: 12. When RCP seals total flow is above setpoint (CV-1206 FLOW light ON), return CV-1206 OVRD pushbutton to normal (OVRD light off).
1206 FLOW light ON), return CV-1206 OVRD         push the OVRD pushbutton in to pushbutton to normal (OVRD light off).            return it to normal and observe the OVRD light is OFF.
(step 3.6.19)
(step 3.6.19)
Operator should observe CV-1206 FLOW light is ON and then push the OVRD pushbutton in to return it to normal and observe the OVRD light is OFF.


TUOI NUMBER:                                                                                         Page 5 of 6 A1JPM-RO-C                 PERFORMANCE CHECKLIST                                 STANDARD             N/A SAT     UN SAT C                                                           Operator should SLOWLY turn
TUOI NUMBER:
: 13. Slowly open CV-1235 until makeup flow               CV-1235 position switch CCW to    ____ ____  ____
A1JPM-RO-Page 5 of 6 C
indication is on-scale and adjust CV-1235 setpoint open the valve and watch for flow to desired value and place in AUTO.                 indications on scale. Operator should then adjust the SP to a (steps 3.6.20 and 3.6.21)                           nominal value, place valve hand station in AUTO and observe white light OFF and RED light ON.
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT C
C                                                           Operator places hand station for
: 13. Slowly open CV-1235 until makeup flow indication is on-scale and adjust CV-1235 setpoint to desired value and place in AUTO.
: 14. Re-establish letdown.                               letdown isolation valve CV-1221   ____ ____  ____
(steps 3.6.20 and 3.6.21)
to CCW position to initiate (step 3.7)                                          letdown and observes letdown flow rate and red light ON and green light OFF (for valve open JPM is complete indication).
Operator should SLOWLY turn CV-1235 position switch CCW to open the valve and watch for flow indications on scale. Operator should then adjust the SP to a nominal value, place valve hand station in AUTO and observe white light OFF and RED light ON.
END
C
: 14. Re-establish letdown.
(step 3.7)
JPM is complete Operator places hand station for letdown isolation valve CV-1221 to CCW position to initiate letdown and observes letdown flow rate and red light ON and green light OFF (for valve open indication).
END  


TUOI NUMBER:                                                                                           Page 6 of 6 A1JPM-RO-EXAMINEES COPY INITIAL CONDITIONS:
TUOI NUMBER:
You are the CBOR and AOP 1202.026 was entered because of a small leak in the Makeup system on the discharge side of the pumps . The reactor was tripped and the plant is stable in Mode 3 conditions. All Makeup pumps had to be stopped to repair the leak. The leak has been repaired. Make up pump line up: P-36A is ES, P-36B is OP, P-36C is STBY. RCP seal bleedoff temperature is 1600F.
A1JPM-RO-Page 6 of 6 EXAMINEES COPY INITIAL CONDITIONS:
You are the CBOR and AOP 1202.026 was entered because of a small leak in the Makeup system on the discharge side of the pumps. The reactor was tripped and the plant is stable in Mode 3 conditions. All Makeup pumps had to be stopped to repair the leak. The leak has been repaired. Make up pump line up: P-36A is ES, P-36B is OP, P-36C is STBY. RCP seal bleedoff temperature is 1600F.
INITIATING CUE:
INITIATING CUE:
The CRS/SM directs you to restart Makeup Pump P-36C (STBY pump) IAW AOP 1203.026, starting with step 3.6.6.
The CRS/SM directs you to restart Makeup Pump P-36C (STBY pump) IAW AOP 1203.026, starting with step 3.6.6.  


PROC./WORK PLAN NO.     PROCEDURE/WORK PLAN TITLE:                                                     PAGE: 8 of 1203.026                 11 LOSS OF REACTOR COOLANT MAKEUP                                             CHANGE: 009-04-0 SECTION 2 -- LARGE MAKEUP AND PURIFICATION SYSTEM LEAK (continued)
PROC./WORK PLAN NO. PROCEDURE/WORK PLAN TITLE: PAGE: 8 of 1203.026 11 LOSS OF REACTOR COOLANT MAKEUP CHANGE: 009-04-0 SECTION 2 -- LARGE MAKEUP AND PURIFICATION SYSTEM LEAK (continued)
NOTE The SPDS Safety System Diagnostic Inst. display contains the previous 20 minutes of data.
NOTE The SPDS Safety System Diagnostic Inst. display contains the previous 20 minutes of data.
3.6.4         Select Safety System Diagnostic Inst. display on SPDS for OP HPI pump and evaluate suction pressure and flow stability prior to event.
3.6.4 Select Safety System Diagnostic Inst. display on SPDS for OP HPI pump and evaluate suction pressure and flow stability prior to event.
3.6.5         If radiation levels prohibit leak isolation, perform the following:
3.6.5 If radiation levels prohibit leak isolation, perform the following:
A. Open BWST Outlet (CV-1407 or CV-1408) to ES HPI pump.
A. Open BWST Outlet (CV-1407 or CV-1408) to ES HPI pump.
B. Operate ES HPI pump and associated HPI Block valve (CV-1220 or CV-1285) only as necessary to maintain RCS inventory.
B. Operate ES HPI pump and associated HPI Block valve (CV-1220 or CV-1285) only as necessary to maintain RCS inventory.
C. GO TO step 3.7.
C. GO TO step 3.7.
3.6.6         When system leakage has been isolated, perform the following:
3.6.6 When system leakage has been isolated, perform the following:
A. Verify Makeup Tank Outlet (CV-1275) open.
A. Verify Makeup Tank Outlet (CV-1275) open.
B. Add to MU tank as necessary to maintain level 55" using current RCS boron concentration.
B. Add to MU tank as necessary to maintain level 55" using current RCS boron concentration.
3.6.7         If STBY HPI pump is available, perform the following:
3.6.7 If STBY HPI pump is available, perform the following:
A. Start AUX lube oil pump for STBY HPI pump.
A. Start AUX lube oil pump for STBY HPI pump.
B. GO TO step 3.6.10 to place STBY HPI pump in service.
B. GO TO step 3.6.10 to place STBY HPI pump in service.
3.6.8         If STBY HPI pump is not available, and OP HPI pump damage is not suspected, perform the following:
3.6.8 If STBY HPI pump is not available, and OP HPI pump damage is not suspected, perform the following:
A. Start AUX lube oil pump for OP HPI pump.
A. Start AUX lube oil pump for OP HPI pump.
B. GO TO step 3.6.10 to place OP HPI pump in service.
B. GO TO step 3.6.10 to place OP HPI pump in service.
3.6.9         If both OP and STBY HPI pumps are not available, perform the following:
3.6.9 If both OP and STBY HPI pumps are not available, perform the following:
A. Start AUX lube oil pump for ES HPI pump.
A. Start AUX lube oil pump for ES HPI pump.
B. Place ES standby HPI pump in service per step 3.6.10.
B. Place ES standby HPI pump in service per step 3.6.10.  


PROC./WORK PLAN NO.         PROCEDURE/WORK PLAN TITLE:                                                     PAGE: 8 of 1203.026                   11 LOSS OF REACTOR COOLANT MAKEUP                                           CHANGE: 009-04-0 SECTION 2 -- LARGE MAKEUP AND PURIFICATION SYSTEM LEAK (continued)
PROC./WORK PLAN NO. PROCEDURE/WORK PLAN TITLE: PAGE: 8 of 1203.026 11 LOSS OF REACTOR COOLANT MAKEUP CHANGE: 009-04-0 SECTION 2 -- LARGE MAKEUP AND PURIFICATION SYSTEM LEAK (continued)
NOTE Decision to vent HPI pump should be based on suction pressure from SPDS history as well as leak location and lowest suction pressure achieved.
NOTE Decision to vent HPI pump should be based on suction pressure from SPDS history as well as leak location and lowest suction pressure achieved.
3.6.10           If loss of pump suction was indicated, perform the following:
3.6.10 If loss of pump suction was indicated, perform the following:
A. If ES HPI pump is being re-aligned per Attachment A, verify associated P-36 Makeup Pump Suction Cross-Over open prior to venting.
A. If ES HPI pump is being re-aligned per Attachment A, verify associated P-36 Makeup Pump Suction Cross-Over open prior to venting.
B. Vent pump using applicable Makeup Pump P-36 Vent to ABV Header:
B. Vent pump using applicable Makeup Pump P-36 Vent to ABV Header:
P-36A       P-36B     P-36C ABV-9A ABV-9B ABV-9C 3.6.11           Verify HPI pump suction pressure >10 psig.
P-36A P-36B P-36C ABV-9A ABV-9B ABV-9C 3.6.11 Verify HPI pump suction pressure >10 psig.
3.6.12           Verify the following valves in HAND and closed:
3.6.12 Verify the following valves in HAND and closed:
* CV-1207
* CV-1207
* CV-1235 3.6.13           If ES HPI pump will be used, verify Attachment A steps 1 through 6 complete.
* CV-1235 3.6.13 If ES HPI pump will be used, verify Attachment A steps 1 through 6 complete.
CAUTION Operation of Aux Lube Oil Pump with HPI/MU Pump running should be minimized.
CAUTION Operation of Aux Lube Oil Pump with HPI/MU Pump running should be minimized.
3.6.14           After AUX lube oil pump has run for 1 minute, start HPI pump.
3.6.14 After AUX lube oil pump has run for 1 minute, start HPI pump.
3.6.15           Stop AUX lube oil pump for HPI pump.
3.6.15 Stop AUX lube oil pump for HPI pump.
3.6.16           Place CV-1206 pushbutton in OVRD (OVRD light on).
3.6.16 Place CV-1206 pushbutton in OVRD (OVRD light on).
3.6.17           Open CV-1206.
3.6.17 Open CV-1206.
3.6.18           Slowly open CV-1207 as follows:
3.6.18 Slowly open CV-1207 as follows:
A. If seal bleedoff temperature is >180&deg;F, establish and maintain 8 to 12 gpm RCP Seal Total INJ Flow until <180&deg;F.
A. If seal bleedoff temperature is >180&deg;F, establish and maintain 8 to 12 gpm RCP Seal Total INJ Flow until <180&deg;F.  


PROC./WORK PLAN NO.       PROCEDURE/WORK PLAN TITLE:                                               PAGE: 8 of 1203.026                  11 LOSS OF REACTOR COOLANT MAKEUP                                       CHANGE: 009-04-0 B. When seal bleedoff temperature is <180&deg;F, adjust CV-1207 for 30-40 gpm and place in AUTO.
PROC./WORK PLAN NO.
SECTION 2 -- LARGE MAKEUP AND PURIFICATION SYSTEM LEAK (continued) 3.6.19         When RCP Seals Total INJ Flow is above setpoint (CV-1206 FLOW light on),
1203.026 PROCEDURE/WORK PLAN TITLE: PAGE: 8 of 11 LOSS OF REACTOR COOLANT MAKEUP CHANGE: 009-04-0 B. When seal bleedoff temperature is <180&deg;F, adjust CV-1207 for 30-40 gpm and place in AUTO.
SECTION 2 -- LARGE MAKEUP AND PURIFICATION SYSTEM LEAK (continued) 3.6.19 When RCP Seals Total INJ Flow is above setpoint (CV-1206 FLOW light on),
return CV-1206 OVRD pushbutton to normal (OVRD light off).
return CV-1206 OVRD pushbutton to normal (OVRD light off).
3.6.20         Slowly open CV-1235 until makeup flow indication is on-scale.
3.6.20 Slowly open CV-1235 until makeup flow indication is on-scale.
3.6.21         Adjust CV-1235 setpoint to desired value and place in AUTO.
3.6.21 Adjust CV-1235 setpoint to desired value and place in AUTO.
3.7           If normal makeup is in service, reestablish letdown.
3.7 If normal makeup is in service, reestablish letdown.  


TUOI NUMBER:                                                                                                             Page 1 of 6 A1JPM-RO-JOB PERFORMANCE MEASURE Unit:               1             Rev #                         1                         Date:
TUOI NUMBER:
TUOI NUMBER:           A1JPM-RO-System/Duty Area:
Page 1 of 6 A1JPM-RO-JOB PERFORMANCE MEASURE Unit:
Task:     Perform ERV (PSV-1000) Exercise Test JA#       ANO1-RO-KA Value RO       3.0       SRO     3.2     KA Reference       010.A3.01 Approved For Administration To: RO                               SRO Task Location: Inside CR:                           Outside CR:                       Both:
1 Rev #
1 Date:
TUOI NUMBER:
A1JPM-RO-System/Duty Area:
Task:
Perform ERV (PSV-1000) Exercise Test JA#
ANO1-RO-KA Value RO 3.0 SRO 3.2 KA Reference 010.A3.01 Approved For Administration To: RO SRO Task Location: Inside CR:
Outside CR:
Both:
Suggested Testing Environment And Method (Perform Or Simulate):
Suggested Testing Environment And Method (Perform Or Simulate):
Plant Site:                     Simulator:           Perform       X             Lab:
Plant Site:
Position Evaluated: RO:                       X                               SRO:                     X Actual Testing Environment: Simulator:                             Plant Site:                     Lab Testing Method: Simulate:                                                 Perform:
Simulator:
Approximate Completion Time In Minutes:                                         10 Minutes Reference(S):
Perform X Lab:
Position Evaluated: RO:
X SRO:
X Actual Testing Environment: Simulator:
Plant Site:
Lab Testing Method: Simulate:
Perform:
Approximate Completion Time In Minutes:
10 Minutes Reference(S):
OP 1103.005 Supplement 1 (change 030-02-0), 1203.012H (change 031-03-0),
OP 1103.005 Supplement 1 (change 030-02-0), 1203.012H (change 031-03-0),
and AOP 1203.015 (change 011-00-0)
and AOP 1203.015 (change 011-00-0)
Examinee's Name:                                                                     SSN:
Examinee's Name:
SSN:
Evaluator's Name:
Evaluator's Name:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
Satisfactory:                                       Unsatisfactory:
Satisfactory:
Unsatisfactory:
Performance Checklist Comments:
Performance Checklist Comments:
Start Time                                   Stop Time                                       Total Time Signed                                                               Date:
Start Time Stop Time Total Time Signed Date:
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.  


TUOI NUMBER:                                                                                                         Page 2 of 6 A1JPM-RO-THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:
Page 2 of 6 A1JPM-RO-THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:
JPM INITIAL TASK CONDITIONS:
Line 605: Line 900:
: 2. RC Temperature = 1200F, RC Pressure = 55 psig
: 2. RC Temperature = 1200F, RC Pressure = 55 psig
: 3. When step 2.2.4 is reached, ERV (PSV-1000) sticks open and will not close
: 3. When step 2.2.4 is reached, ERV (PSV-1000) sticks open and will not close
: 4. When ERV Isolation valve is closed (CV-1000), the leak stops
: 4. When ERV Isolation valve is closed (CV-1000), the leak stops  


TUOI NUMBER:                                                                                                           Page 3 of 6 A1JPM-RO-INITIATING CUE:             The CRS/SM directs you to perform the ERV exercise test per OP 1103.005, Supplement 1 (change 030-02-0) in order to meet the regularly scheduled 18 month test.
TUOI NUMBER:
CRITICAL ELEMENTS (c): 5, 6, 8 C                   PERFORMANCE CHECKLIST                                     STANDARD                   N/A     SAT     UN SAT INSTRUCTOR NOTE: Examinee may review the OP 1103.005, Supplement 1 prior to starting the JPM. Also, the Examinee should initial each step on the procedure forms although it is not written into the JPM.
Page 3 of 6 A1JPM-RO-INITIATING CUE:
: 1. Check purpose of test (step 1.1 of procedure)             Operator checks B for regularly       ____    ____    ____
The CRS/SM directs you to perform the ERV exercise test per OP 1103.005, Supplement 1 (change 030-02-0) in order to meet the regularly scheduled 18 month test.
scheduled 18 month test.
CRITICAL ELEMENTS (c): 5, 6, 8 C
Operator enters stopwatch cal
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT INSTRUCTOR NOTE: Examinee may review the OP 1103.005, Supplement 1 prior to starting the JPM. Also, the Examinee should initial each step on the procedure forms although it is not written into the JPM.
: 2. Records stop watch M & TE # and cal date in               data, initials for correct RCS          ____    ____    ____
: 1. Check purpose of test (step 1.1 of procedure)
section 3.0 of procedure.                               temp/pressure, and checks ERV isolation valve light RED is ON Checks RC Temp > 100oF                                 and GREEN is OFF.
Operator checks B for regularly scheduled 18 month test.
Checks RC Pressure < 70 psig Checks ERV Isolation (CV-1000) open (steps 1.2 thru 1.5 of procedure)
: 2. Records stop watch M & TE # and cal date in section 3.0 of procedure.
: 3. If elevated airborne activity is expected as a result     Operator should ask CRS about            ____    ____    ____
Checks RC Temp > 100oF Checks RC Pressure < 70 psig Checks ERV Isolation (CV-1000) open (steps 1.2 thru 1.5 of procedure)
of ERV operations, personnel hatch interlock           expected airborne activity.
Operator enters stopwatch cal data, initials for correct RCS temp/pressure, and checks ERV isolation valve light RED is ON and GREEN is OFF.
enabled or .                                          Instructor cues as given below.
: 3. If elevated airborne activity is expected as a result of ERV operations, personnel hatch interlock enabled or.
Instructor Cue here                                    Operator should N/A the step after the cue.
Instructor Cue here NOTE: No elevated airborne activity is expected See Instructor Cue below Operator should ask CRS about expected airborne activity.
NOTE: No elevated airborne activity is expected See Instructor Cue below INSTRUCTOR CUE: CRS reports that there is no elevated airborne activity expected. N/A the step on the form.
Instructor cues as given below.
: 4. Verify no one is at the vicinity of the ERV.               Operator asks CRS to determine          ____    ____    ____
Operator should N/A the step after the cue.
(step 2.1)                                               or uses radio to call and determine that no one is near the ERV.
INSTRUCTOR CUE: CRS reports that there is no elevated airborne activity expected. N/A the step on the form.
Instructor Cue: when operator calls on radio or asks CRS, reply back that no one is in the vicinity of ERV.        See Instructor Cue at left.
: 4. Verify no one is at the vicinity of the ERV.
(step 2.1)
Instructor Cue: when operator calls on radio or asks CRS, reply back that no one is in the vicinity of ERV See Instructor Cue at left.
Operator asks CRS to determine or uses radio to call and determine that no one is near the ERV.  


TUOI NUMBER:                                                                                             Page 4 of 6 A1JPM-RO-C                 PERFORMANCE CHECKLIST                                   STANDARD               N/A SAT     UN SAT Operator selects 1 g position for C   5. Perform the following steps while ensuring RCS         ERV Acoustic Monitor with          ____ ____    ____
TUOI NUMBER:
pressure remains > 30psig:                           Acoustic selector switch.
Page 4 of 6 A1JPM-RO-C PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT C
Operator places hand switch for
: 5. Perform the following steps while ensuring RCS pressure remains > 30psig:  
          -Place ERV Acoustic Monitor Full Scale Range         ERV to open position and selector to 1 g position.                           verifies ERV open by using all three parameter indications listed
-Place ERV Acoustic Monitor Full Scale Range selector to 1 g position.  
        -Open and measure stroke time of ERV                   here:
-Open and measure stroke time of ERV (Record in Section 3.0).
(Record in Section 3.0).
(steps 2.2.1 - 2.2.2)
* Acoustic Monitor indicating light on panel (steps 2.2.1 - 2.2.2)                                         C04
Operator selects 1 g position for ERV Acoustic Monitor with Acoustic selector switch.
* Dropping RCS pressure (Operator should not let pressure drop below 30psig)
Operator places hand switch for ERV to open position and verifies ERV open by using all three parameter indications listed here:
* Rising Quench Tank Pressure Operator then enters the stroke time in Section 3.0.

Operator places hand switch for C   6. Close and measure the stroke time of ERV (Record       ERV to close position and        ____ ____    ____
Acoustic Monitor indicating light on panel C04  
should attempt to verify that the in Section 3.0).                                     ERV is closed by using all three parameter indications listed here:

Dropping RCS pressure (Operator should not let pressure drop below 30psig)  

Rising Quench Tank Pressure Operator then enters the stroke time in Section 3.0.
C
: 6. Close and measure the stroke time of ERV (Record in Section 3.0).
(step 2.2.4)
(step 2.2.4)
* Acoustic Monitor indicating light on panel C04 (displays open)
NOTE: This is the alternate path portion of the JPM.
NOTE: This is the alternate path portion of the JPM.
* Stable RCS pressure (It The ERV will stick completely open and will not move               should continue to drop) under any conditions. The block valve (CV-1000)
The ERV will stick completely open and will not move under any conditions. The block valve (CV-1000) should be closed to stop the release.
* Stable Quench Tank should be closed to stop the release.                             Pressure (It should continue to rise)
Operator places hand switch for ERV to close position and should attempt to verify that the ERV is closed by using all three parameter indications listed here:
NOTE: This is the alternate path portion of the JPM. The ERV will stick completely open and will not move under any conditions. The block valve (CV-1000) should be closed to stop the release per Alarm procedure OP 1203.012H for alarm K09-A1, Relief Valve Open, page 2.

Acoustic Monitor indicating light on panel C04 (displays open)

Stable RCS pressure (It should continue to drop)

Stable Quench Tank Pressure (It should continue to rise)
NOTE: This is the alternate path portion of the JPM. The ERV will stick completely open and will not move under any conditions. The block valve (CV-1000) should be closed to stop the release per Alarm procedure OP 1203.012H for alarm K09-A1, Relief Valve Open, page 2.  


TUOI NUMBER:                                                                                           Page 5 of 6 A1JPM-RO-C                 PERFORMANCE CHECKLIST                                   STANDARD             N/A SAT     UN SAT
TUOI NUMBER:
: 7. Operator should enter the Annunciator Response             Operator acknowledges alarm  ____ ____    ____
Page 5 of 6 A1JPM-RO-C PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT
OP 1203.012H for alarm K09-A1, Relief Valve               and enters Alarm procedure Open, page 2.                                             OP 1203.012H for alarm Operator is directed by OP1203.012H to refer to           K09-A1, Relief Valve procedure AOP 1203.015 for Pressurizer Systems            Open, page 2.
: 7. Operator should enter the Annunciator Response OP 1203.012H for alarm K09-A1, Relief Valve Open, page 2.
Failure. Operator should refer to section 1.0 of         This procedure directs this procedure for ERV Failure or Leak.                 Operator to AOP 1203.015 for Pressurizer Systems Failure. Operator should refer to section 1.0 of this procedure for ERV failure or Leak.
s Failure s
Operator closes the isolation C
Failure.
: 8. Operator should commence follow-up actions for         valve with hand switch for CV-    ____ ____    ____
Operator is directed by OP1203.012H to refer to procedure AOP 1203.015 for Pressurizer System
section 1.0, which include:                          1000 and observes the following:
. Operator should refer to section 1.0 of this procedure for ERV Failure or Leak.
Operator acknowledges alarm and enters Alarm procedure OP 1203.012H for alarm K09-A1, Relief Valve Open, page 2.
This procedure directs Operator to AOP 1203.015 for Pressurizer System Operator should refer to section 1.0 of this procedure for ERV failure or Leak.
C
: 8. Operator should commence follow-up actions for section 1.0, which include:
: a. Close the ERV Isolation valve (CV-1000).
: a. Close the ERV Isolation valve (CV-1000).
* Acoustic Monitor
: b. Trip reactor if cant maintain pressure (N/A in this JPM)
: b. Trip reactor if cant maintain pressure (N/A in             indicating light on panel C04 (displays closed) this JPM)
(steps 3.1-3.2)
(steps 3.1-3.2)
* Stable RCS pressure
Operator closes the isolation valve with hand switch for CV-1000 and observes the following:
* Stable Quench Tank Pressure NOTE: Closing the ERV block or isolation valve CV-1000 will stop the leak.

Operator notifies the OPS
Acoustic Monitor indicating light on panel C04 (displays closed)
: 9. If closing CV-1000 stops the leak, perform the         manager of the stuck open ERV,    ____ ____    ____

following:                                           block valve has contained the
Stable RCS pressure  
: a. Continue power operations with ERV isolated       leak, and logs the entry in the (N/A for this JPM)                               station log and PSB.

Stable Quench Tank Pressure NOTE: Closing the ERV block or isolation valve CV-1000 will stop the leak.
: 9. If closing CV-1000 stops the leak, perform the following:
: a. Continue power operations with ERV isolated (N/A for this JPM)
: b. Notify OPS manager
: b. Notify OPS manager
: c. Log in station log and on plant status board (step 3.3)
: c. Log in station log and on plant status board (step 3.3)
END of JPM INSTRUCTOR CUE: This concludes the JPM.
END of JPM Operator notifies the OPS manager of the stuck open ERV, block valve has contained the leak, and logs the entry in the station log and PSB.
END
INSTRUCTOR CUE: This concludes the JPM.
END  


TUOI NUMBER:                                                                                         Page 6 of 6 A1JPM-RO-EXAMINEES COPY INITIAL CONDITIONS:
TUOI NUMBER:
Page 6 of 6 A1JPM-RO-EXAMINEES COPY INITIAL CONDITIONS:
You are the CBOR and you are directed by the CRS to perform OP 1103.005, Supplement 1, Exercising of the Pressurizer Electromatic Relief Valve (PSV-1000) in order to meet the regularly scheduled 18 month test. The plant conditions are as follows:
You are the CBOR and you are directed by the CRS to perform OP 1103.005, Supplement 1, Exercising of the Pressurizer Electromatic Relief Valve (PSV-1000) in order to meet the regularly scheduled 18 month test. The plant conditions are as follows:
RC Temperature = 1200F RC Pressure = 55 psig INITIATING CUE:
RC Temperature = 1200F RC Pressure = 55 psig INITIATING CUE:
The CRS/SM directs you to perform the ERV exercise test per OP 1103.005, Supplement 1 (change 030-02-0) in order to meet the regularly scheduled 18-month test.
The CRS/SM directs you to perform the ERV exercise test per OP 1103.005, Supplement 1 (change 030-02-0) in order to meet the regularly scheduled 18-month test.  


PROC./WORK PLAN NO.           PROCEDURE/WORK PLAN TITLE:                                                   Page 33 of 38 1103.005                           PRESSURIZER OPERATION                                         CHANGE: 030-02-0 SUPPLEMENT 1 Page 1 of 4 EXERCISING OF THE PRESSURIZER ELECTROMATIC RELIEF VALVE (PSV-1000)
PROC./WORK PLAN NO.
PROCEDURE/WORK PLAN TITLE: Page 33 of 38 1103.005 PRESSURIZER OPERATION CHANGE: 030-02-0 SUPPLEMENT 1 Page 1 of 4 EXERCISING OF THE PRESSURIZER ELECTROMATIC RELIEF VALVE (PSV-1000)
This test demonstrates operability of the pressurizer ERV by exercising the valve. This test satisfies TS 5.5.8 (ANO IST program requirements) for stroke time measurement, exercising, and fail-safe operation. This test also satisfies part of Surveillance TR 3.4.2.1 for RCS vent path operability. This test is related to SR 3.4.11.5 "Channel calibration of ERV opening circuitry".
This test demonstrates operability of the pressurizer ERV by exercising the valve. This test satisfies TS 5.5.8 (ANO IST program requirements) for stroke time measurement, exercising, and fail-safe operation. This test also satisfies part of Surveillance TR 3.4.2.1 for RCS vent path operability. This test is related to SR 3.4.11.5 "Channel calibration of ERV opening circuitry".
1.0     INITIAL CONDITIONS                                                                                 INITIALS 1.1     Check the purpose of this test:                                                             _________
1.0 INITIAL CONDITIONS INITIALS 1.1 Check the purpose of this test:
__A) Regularly scheduled cold shutdown test.
__A) Regularly scheduled cold shutdown test.
__B) Regularly scheduled 18 month test
__B) Regularly scheduled 18 month test
__C) Operability test following significant maintenance.
__C) Operability test following significant maintenance.
__D) Other (describe in section 4.0).
__D) Other (describe in section 4.0).
1.2     Stop watch available for measuring valve stroke time.                                     _________
1.2 Stop watch available for measuring valve stroke time.
1.2.1   Record Stopwatch M&TE# and Cal Due Date in Section 3.0.
1.2.1 Record Stopwatch M&TE# and Cal Due Date in Section 3.0.
1.3     RC temperature > 1000F.                                                                     _________
1.3 RC temperature > 1000F.
1.4     RC pressure < 70 psig.                                                                     _________
1.4 RC pressure < 70 psig.
1.5     ERV Isolation (CV-1000) open.                                                               _________
1.5 ERV Isolation (CV-1000) open.
1.6     If elevated airborne activity is expected as a result of                                   _________
1.6 If elevated airborne activity is expected as a result of ERV operations, personnel Hatch interlock enabled or Personnel Hatch watch stationed to ensure only one door opened at a time. Otherwise N/A.
ERV operations, personnel Hatch interlock enabled or Personnel Hatch watch stationed to ensure only one door opened at a time. Otherwise N/A.
2.0 TEST METHOD WARNING Opening the ERV causes a localized steam release at the pilot valve vent.
2.0     TEST METHOD WARNING Opening the ERV causes a localized steam release at the pilot valve vent.
This is a radiation and safety hazard.
This is a radiation and safety hazard.
2.1 Verify no one is at the vicinity of the ERV.
2.1 Verify no one is at the vicinity of the ERV.  


PROC./WORK PLAN NO.         PROCEDURE/WORK PLAN TITLE:                               Page 34 of 38 1103.005                           PRESSURIZER OPERATION                     CHANGE: 030-02-0 SUPPLEMENT 1 Page 2 of 4 NOTE ERV position and vent path operability are obtained using:
PROC./WORK PLAN NO.
* Acoustic Monitor indication on C04 and
PROCEDURE/WORK PLAN TITLE: Page 34 of 38 1103.005 PRESSURIZER OPERATION CHANGE: 030-02-0 SUPPLEMENT 1 Page 2 of 4 NOTE ERV position and vent path operability are obtained using:  
* dropping RCS pressure and

* rising Quench Tank pressure.
Acoustic Monitor indication on C04 and  
2.2     Perform the following steps while ensuring RCS pressure remains < 30 psig.

2.2.1   Place ERV Acoustic Monitor Full Scale Range                           _______
dropping RCS pressure and  
selector to 1 g position.

2.2.2   Open and measure stroke time of ERV                                   _______
rising Quench Tank pressure.
(Record in Section 3.0).
2.2 Perform the following steps while ensuring RCS pressure remains < 30 psig.
2.2.3   Verify ERV open using all of the following:                           _______
2.2.1 Place ERV Acoustic Monitor Full Scale Range selector to 1 g position.
* Acoustic Monitor Indication on C04
2.2.2 Open and measure stroke time of ERV (Record in Section 3.0).
* Dropping RCS pressure
2.2.3 Verify ERV open using all of the following:  
* Rising Quench Tank pressure.

2.2.4   Close and measure stroke time of ERV                                   _______
Acoustic Monitor Indication on C04  
(Record in Section 3.0).

2.2.5   Verify ERV closed using all of the following:                         _______
Dropping RCS pressure  
* Acoustic Monitor Indication on C04

* Stable RCS pressure
Rising Quench Tank pressure.
* Stable Quench Tank pressure.
2.2.4 Close and measure stroke time of ERV (Record in Section 3.0).
2.2.6   Place ERV Acoustic Monitor Full Scale Range                           _______
2.2.5 Verify ERV closed using all of the following:  
selector to 10 g position.

Acoustic Monitor Indication on C04  

Stable RCS pressure  

Stable Quench Tank pressure.
2.2.6 Place ERV Acoustic Monitor Full Scale Range selector to 10 g position.  


PROC./WORK PLAN NO.         PROCEDURE/WORK PLAN TITLE:                                                 Page 35 of 38 1103.005                          PRESSURIZER OPERATION                                       CHANGE: 030-02-0 SUPPLEMENT 1 Page 3 of 4 3.0     ACCEPTANCE CRITERIA 3.1   Record stroke time measured during testing and compare with "Limiting Value For Operability".
PROC./WORK PLAN NO.
1103.005 PROCEDURE/WORK PLAN TITLE: Page 35 of 38 PRESSURIZER OPERATION CHANGE: 030-02-0 SUPPLEMENT 1 Page 3 of 4 3.0 ACCEPTANCE CRITERIA 3.1 Record stroke time measured during testing and compare with "Limiting Value For Operability".
Stopwatch M&TE#___________ Cal Due Date ________________
Stopwatch M&TE#___________ Cal Due Date ________________
Valve   Control     Test         Measured Stroke       Acceptable  Limiting  Is Measured  Design Panel    Direction  Time (nearest 1/10 second)   Normal     Value    Stroke Time  Bases Range       For      Less Than    Value (Sec)   Operability "Limiting (Sec)     Value For Operability" PSV-1000    C04      Open                                   < 2.0     < 2.0     Yes   No     < 2.0 Closed                                 2.6-7.8   <10.4*     Yes   No     N/A
Valve Control Panel Test Direction Measured Stroke Time (nearest 1/10 second)
Acceptable Normal Range (Sec)
Limiting Value For Operability (Sec)
Is Measured Stroke Time Less Than "Limiting Value For Operability" Design Bases Value Open  
< 2.0  
< 2.0 Yes No  
< 2.0 PSV-1000 C04 Closed 2.6-7.8  
<10.4*
Yes No N/A
* Valve closure verifies proper fail-safe operation.
* Valve closure verifies proper fail-safe operation.
3.2   If "No" is circled in 3.1 above, declare PSV-1000                                       _______
3.2 If "No" is circled in 3.1 above, declare PSV-1000 inoperable, immediately notify the Shift Manager/CRS, write a Condition Report, initiate corrective action. Reference applicable Tech Spec for LCO.
inoperable, immediately notify the Shift Manager/CRS, write a Condition Report, initiate corrective action. Reference applicable Tech Spec for LCO.
3.3 If any measured stroke time does not fall within the "Acceptable Normal Range", immediately retest valve or declare that valve inoperable. Refer to "Operability" section of this procedure for additional guidance.
3.3   If any measured stroke time does not fall within the                                     _______
PERFORMED BY _______________________OPERATOR DATE/TIME ______/______  
                      "Acceptable Normal Range", immediately retest valve or declare that valve inoperable. Refer to "Operability" section of this procedure for additional guidance.
PERFORMED BY _______________________OPERATOR DATE/TIME ______/______


Page 1 of 5 TUOI: A1JPM-DHR01 JOB PERFORMANCE MEASURE UNIT: ______1_______ REV # ______8_______       DATE: ______________________________
Page 1 of 5 TUOI: A1JPM-DHR01 JOB PERFORMANCE MEASURE UNIT: ______1_______ REV # ______8_______
DATE: ______________________________
TUOI NUMBER:_A1JPM-RO-DHR01_____________
TUOI NUMBER:_A1JPM-RO-DHR01_____________
SYSTEM/DUTY AREA:_DECAY HEAT REMOVAL______________________________________________
SYSTEM/DUTY AREA:_DECAY HEAT REMOVAL______________________________________________
TASK:__ESTABLISH DECAY HEAT REMOVAL USING P-34A____________________________________
TASK:__ESTABLISH DECAY HEAT REMOVAL USING P-34A____________________________________
JTA#:__ANO1-RO-DHR-NORM-2__________                                       ________________
JTA#:__ANO1-RO-DHR-NORM-2__________
KA VALUE RO:___3.6____ SRO:__3.4_____ KA  
KA VALUE RO:___3.6____ SRO:__3.4_____ KA  


Line 732: Line 1,062:
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________
PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________
POSITION EVALUATED: RO:__________       SRO:___________
POSITION EVALUATED: RO:__________
SRO:___________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________
TESTING METHOD: SIMULATE:_________       PERFORM:___________
TESTING METHOD: SIMULATE:_________
PERFORM:___________
APPROXIMATE COMPLETION TIME IN MINUTES:___20 MINUTES_______________________________
APPROXIMATE COMPLETION TIME IN MINUTES:___20 MINUTES_______________________________
REFERENCE(S):__1104.004                               _____________________________
REFERENCE(S):__1104.004 EXAMINEE'S NAME:________________________________
EXAMINEE'S NAME:________________________________     SSN ______-_____-____________
SSN ______-_____-____________
EVALUATOR'S NAME:__________________________________________________________________
EVALUATOR'S NAME:__________________________________________________________________
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
SATISFACTORY:________________           UNSATISFACTORY:_________________
SATISFACTORY:________________
UNSATISFACTORY:_________________
PERFORMANCE CHECKLIST COMMENTS:
PERFORMANCE CHECKLIST COMMENTS:
____________ Start Time     ____________ Stop Time       ____________ Total Time SIGNED ________________________________ DATE: _______________________
____________ Start Time
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.
____________ Stop Time
____________ Total Time SIGNED ________________________________ DATE: _______________________
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.  


Page 2 of 5 TUOI: A1JPM-DHR01 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:
Page 2 of 5 TUOI: A1JPM-DHR01 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:  
* Plant shutdown and cooldown per 1102.010 is complete to step 10.8.
 Plant shutdown and cooldown per 1102.010 is complete to step 10.8.  
* Breakers B-5255/B-6255/B-5651 are closed.
 Breakers B-5255/B-6255/B-5651 are closed.  
* 1104.004 is complete up to step 7.2.3.
 1104.004 is complete up to step 7.2.3.
INITIATING CUE:
INITIATING CUE:
The CRS directs that Decay Heat Pump P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.
The CRS directs that Decay Heat Pump P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.  


Page 3 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER:       ANO-1-JPM-RO-DHR01 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
Page 3 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER: ANO-1-JPM-RO-DHR01 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS: Plant shutdown and cooldown per 1102.010 is complete to step 10.8. Decay heat removal with P34A is to be established per 1104.004. Breakers B-5255/B-6255/B-5651 are closed.
JPM INITIAL TASK CONDITIONS: Plant shutdown and cooldown per 1102.010 is complete to step 10.8. Decay heat removal with P34A is to be established per 1104.004. Breakers B-5255/B-6255/B-5651 are closed.
TASK STANDARD: P-34A decay heat pump running per OP 1104.004. Flow indicated
TASK STANDARD: P-34A decay heat pump running per OP 1104.004. Flow indicated  
  < 3500 gpm and discharge pressure <400 psig.
  < 3500 gpm and discharge pressure <400 psig.
TASK PERFORMANCE AIDS: 1104.004 Section 7.0
TASK PERFORMANCE AIDS: 1104.004 Section 7.0  


Page 4 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER:       ANO-1-JPM-RO-DHR01 INITIATING CUE:
Page 4 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER: ANO-1-JPM-RO-DHR01 INITIATING CUE:
The CRS directs that P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.
The CRS directs that P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.
INSTRUCTOR NOTE: Ensure B-5255, B-6255,and B-5651 are closed and Programmable Annunciator alarm for P34A (P1404) set at 400 psig.
INSTRUCTOR NOTE: Ensure B-5255, B-6255,and B-5651 are closed and Programmable Annunciator alarm for P34A (P1404) set at 400 psig.
CRITICAL ELEMENTS (C):         1, 2, 5, 7, 8, 9, 10, 11, 12, 15 C           PERFORMANCE CHECKLIST                             STANDARDS           N/A SAT     UNSAT (C)     1. Close Decay Heat P-34A Suction from           CV-1436 red light off,     ____ ____      ____
CRITICAL ELEMENTS (C): 1, 2, 5, 7, 8, 9, 10, 11, 12, 15 C
BWST (CV-1436).                            green light on.
PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT (C)
(C)     2. Open Decay Heat P-34A Suction from           CV-1434 red light on,     ____ ____      ____
: 1. Close Decay Heat P-34A Suction from BWST (CV-1436).
RCS (CV-1434).                              green light off.
CV-1436 red light off, green light on.
: 3. Open E-35A and E-35B sample valves           Contacted the WCO and      ____ ____      ____
(C)
SS-41A and SS-41B.                         instructed the WCO to open SS-41A and SS-41B.
: 2. Open Decay Heat P-34A Suction from RCS (CV-1434).
CV-1434 red light on, green light off.
: 3. Open E-35A and E-35B sample valves SS-41A and SS-41B.
Contacted the WCO and instructed the WCO to open SS-41A and SS-41B.
NOTE: Inform examinee that Category E log entry has been made.
NOTE: Inform examinee that Category E log entry has been made.
: 4. Verify white Open Permit light ON at         Verified white open permit ____ ____      ____
: 4. Verify white Open Permit light ON at CV-1410 handswitch on C16.
CV-1410 handswitch on C16.                 light on.
Verified white open permit light on.
(C)     5. Open CV-1410.                                 Opened DH suction valve   ____ ____      ____
(C)
CV-1410.
: 5. Open CV-1410.
: 6. Verify white Open Permit light ON at       Verified white open permit ____ ____      ____
Opened DH suction valve CV-1410.
CV-1050 handswitch on C18.                 light on.
: 6.
C     7. Open DH Suction Valve CV-1050             Opened DH suction valve CV-1050.                   ____ ____      ____
Verify white Open Permit light ON at CV-1050 handswitch on C18.
C     8. Open DH suction RB isolation CV-           Opened CV-1404.
Verified white open permit light on.
1404.                                                                ____ ____      ____
C
C      9. Close decay heat cooler E-35A             Closed CV-1428.
: 7.
outlet valve CV-1428.                                                 ____ ____      ____
Open DH Suction Valve CV-1050 Opened DH suction valve CV-1050.
C
: 8.
Open DH suction RB isolation CV-1404.
Opened CV-1404.
C
: 9.
Close decay heat cooler E-35A outlet valve CV-1428.
Closed CV-1428.  


Page 5 of 5 TUOI: A1JPM-DHR01 C           PERFORMANCE CHECKLIST                         STANDARDS           N/A SAT   UNSAT C     10. Position E-35A Cooler Bypass (CV-       Positioned CV-1433 to ~
Page 5 of 5 TUOI: A1JPM-DHR01 C
1433) to ~ 50% as indicated on HIC-     50% open.                 ____ ____    ____
PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT C
1433.
: 10.
Position E-35A Cooler Bypass (CV-1433) to ~ 50% as indicated on HIC-1433.
Positioned CV-1433 to ~
50% open.
C
: 11. Open Decay Heat Block Valve CV-1401 Opened CV-1401.
C
C
: 11. Open Decay Heat Block Valve CV-           Opened CV-1401.
: 12. Start P-34A.
1401                                                                ____ ____    ____
Started P-34A.
: 13.
Verify LPI/Decay Heat Pump Brg CLR E-50A Inlet (CV-3840) and Decay HT CLR Service Water E-35A Inlet (CV-3822) open.
On C-18, verified CV-3840 and CV-3822 open.
: 14.
Monitor pressurizer level.
Monitored pressurizer level on C04 or SPDS.
C
C
: 12. Start P-34A.                              Started P-34A.
: 15.
: 13. Verify LPI/Decay Heat Pump Brg          On C-18, verified CV-CLR E-50A Inlet (CV-3840) and          3840 and CV-3822 open. ____ ____    ____
Adjust CV-1433 to establish decay heat removal flow at < 3500 gpm from P-34A and discharge pressure  
Decay HT CLR Service Water E-35A Inlet (CV-3822) open.
< 400 psig.
: 14. Monitor pressurizer level.              Monitored pressurizer      ____ ____    ____
Adjusted DHR flow to
level on C04 or SPDS.
<3500 gpm and discharge pressure < 400 psig using CV-1433.
C    15. Adjust CV-1433 to establish decay       Adjusted DHR flow to      ____ ____    ____
heat removal flow at < 3500 gpm         <3500 gpm and from P-34A and discharge pressure       discharge pressure < 400
                < 400 psig.                            psig using CV-1433.
NOTE: Inform examinee that it is not necessary to perform Part 2 of Supplement 3.
NOTE: Inform examinee that it is not necessary to perform Part 2 of Supplement 3.
: 16. Verify LPI Room Cooler VUC-1A           At panel C-19, verified   ____ ____    ____
: 16.
starts.                                VUC-1A started (red light on).
Verify LPI Room Cooler VUC-1A starts.
: 17. Adjust the DECAY HEAT VORTEX           Selected the U5 function   ____ ____    ____
At panel C-19, verified VUC-1A started (red light on).
WARNING SETPOINT.                      of the SPDS computer and set KP34ALO just below the Decay Heat Pump motor current and adjusted KP34AHI just above the Decay Heat Pump motor current.
: 17.
END
Adjust the DECAY HEAT VORTEX WARNING SETPOINT.
Selected the U5 function of the SPDS computer and set KP34ALO just below the Decay Heat Pump motor current and adjusted KP34AHI just above the Decay Heat Pump motor current.
END  


Page 1 of 5 TUOI: A1JPM-DHR01 JOB PERFORMANCE MEASURE UNIT: ______1_______ REV # ______8_______       DATE: ______________________________
Page 1 of 5 TUOI: A1JPM-DHR01 JOB PERFORMANCE MEASURE UNIT: ______1_______ REV # ______8_______
DATE: ______________________________
TUOI NUMBER:_A1JPM-RO-DHR01_____________
TUOI NUMBER:_A1JPM-RO-DHR01_____________
SYSTEM/DUTY AREA:_DECAY HEAT REMOVAL______________________________________________
SYSTEM/DUTY AREA:_DECAY HEAT REMOVAL______________________________________________
TASK:__ESTABLISH DECAY HEAT REMOVAL USING P-34A____________________________________
TASK:__ESTABLISH DECAY HEAT REMOVAL USING P-34A____________________________________
JTA#:__ANO1-RO-DHR-NORM-2__________                                       ________________
JTA#:__ANO1-RO-DHR-NORM-2__________
KA VALUE RO:___3.6____ SRO:__3.4_____ KA  
KA VALUE RO:___3.6____ SRO:__3.4_____ KA  


Line 816: Line 1,173:
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________
PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________
POSITION EVALUATED: RO:__________       SRO:___________
POSITION EVALUATED: RO:__________
SRO:___________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________
TESTING METHOD: SIMULATE:_________       PERFORM:___________
TESTING METHOD: SIMULATE:_________
PERFORM:___________
APPROXIMATE COMPLETION TIME IN MINUTES:___20 MINUTES_______________________________
APPROXIMATE COMPLETION TIME IN MINUTES:___20 MINUTES_______________________________
REFERENCE(S):__1104.004                               _____________________________
REFERENCE(S):__1104.004 EXAMINEE'S NAME:________________________________
EXAMINEE'S NAME:________________________________     SSN ______-_____-____________
SSN ______-_____-____________
EVALUATOR'S NAME:__________________________________________________________________
EVALUATOR'S NAME:__________________________________________________________________
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
SATISFACTORY:________________           UNSATISFACTORY:_________________
SATISFACTORY:________________
UNSATISFACTORY:_________________
PERFORMANCE CHECKLIST COMMENTS:
PERFORMANCE CHECKLIST COMMENTS:
____________ Start Time     ____________ Stop Time       ____________ Total Time SIGNED ________________________________ DATE: _______________________
____________ Start Time
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.
____________ Stop Time
____________ Total Time SIGNED ________________________________ DATE: _______________________
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.  


Page 2 of 5 TUOI: A1JPM-DHR01 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:
Page 2 of 5 TUOI: A1JPM-DHR01 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:  
* Plant shutdown and cooldown per 1102.010 is complete to step 10.8.
 Plant shutdown and cooldown per 1102.010 is complete to step 10.8.  
* Breakers B-5255/B-6255/B-5651 are closed.
 Breakers B-5255/B-6255/B-5651 are closed.  
* 1104.004 is complete up to step 7.2.3.
 1104.004 is complete up to step 7.2.3.
INITIATING CUE:
INITIATING CUE:
The CRS directs that Decay Heat Pump P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.
The CRS directs that Decay Heat Pump P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.  


Page 3 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER:       ANO-1-JPM-RO-DHR01 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
Page 3 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER: ANO-1-JPM-RO-DHR01 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS: Plant shutdown and cooldown per 1102.010 is complete to step 10.8. Decay heat removal with P34A is to be established per 1104.004. Breakers B-5255/B-6255/B-5651 are closed.
JPM INITIAL TASK CONDITIONS: Plant shutdown and cooldown per 1102.010 is complete to step 10.8. Decay heat removal with P34A is to be established per 1104.004. Breakers B-5255/B-6255/B-5651 are closed.
TASK STANDARD: P-34A decay heat pump running per OP 1104.004. Flow indicated
TASK STANDARD: P-34A decay heat pump running per OP 1104.004. Flow indicated  
  < 3500 gpm and discharge pressure <400 psig.
  < 3500 gpm and discharge pressure <400 psig.
TASK PERFORMANCE AIDS: 1104.004 Section 7.0
TASK PERFORMANCE AIDS: 1104.004 Section 7.0  


Page 4 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER:       ANO-1-JPM-RO-DHR01 INITIATING CUE:
Page 4 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER: ANO-1-JPM-RO-DHR01 INITIATING CUE:
The CRS directs that P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.
The CRS directs that P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.
INSTRUCTOR NOTE: Ensure B-5255, B-6255,and B-5651 are closed and Programmable Annunciator alarm for P34A (P1404) set at 400 psig.
INSTRUCTOR NOTE: Ensure B-5255, B-6255,and B-5651 are closed and Programmable Annunciator alarm for P34A (P1404) set at 400 psig.
CRITICAL ELEMENTS (C):         1, 2, 5, 7, 8, 9, 10, 11, 12, 15 C           PERFORMANCE CHECKLIST                             STANDARDS           N/A SAT     UNSAT (C)     1. Close Decay Heat P-34A Suction from           CV-1436 red light off,     ____ ____      ____
CRITICAL ELEMENTS (C): 1, 2, 5, 7, 8, 9, 10, 11, 12, 15 C
BWST (CV-1436).                            green light on.
PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT (C)
(C)     2. Open Decay Heat P-34A Suction from           CV-1434 red light on,     ____ ____      ____
: 1. Close Decay Heat P-34A Suction from BWST (CV-1436).
RCS (CV-1434).                              green light off.
CV-1436 red light off, green light on.
: 3. Open E-35A and E-35B sample valves           Contacted the WCO and      ____ ____      ____
(C)
SS-41A and SS-41B.                         instructed the WCO to open SS-41A and SS-41B.
: 2. Open Decay Heat P-34A Suction from RCS (CV-1434).
CV-1434 red light on, green light off.
: 3. Open E-35A and E-35B sample valves SS-41A and SS-41B.
Contacted the WCO and instructed the WCO to open SS-41A and SS-41B.
NOTE: Inform examinee that Category E log entry has been made.
NOTE: Inform examinee that Category E log entry has been made.
: 4. Verify white Open Permit light ON at         Verified white open permit ____ ____      ____
: 4. Verify white Open Permit light ON at CV-1410 handswitch on C16.
CV-1410 handswitch on C16.                 light on.
Verified white open permit light on.
(C)     5. Open CV-1410.                                 Opened DH suction valve   ____ ____      ____
(C)
CV-1410.
: 5. Open CV-1410.
: 6. Verify white Open Permit light ON at       Verified white open permit ____ ____      ____
Opened DH suction valve CV-1410.
CV-1050 handswitch on C18.                 light on.
: 6.
C     7. Open DH Suction Valve CV-1050             Opened DH suction valve CV-1050.                   ____ ____      ____
Verify white Open Permit light ON at CV-1050 handswitch on C18.
C     8. Open DH suction RB isolation CV-           Opened CV-1404.
Verified white open permit light on.
1404.                                                                ____ ____      ____
C
C      9. Close decay heat cooler E-35A             Closed CV-1428.
: 7.
outlet valve CV-1428.                                                 ____ ____      ____
Open DH Suction Valve CV-1050 Opened DH suction valve CV-1050.
C
: 8.
Open DH suction RB isolation CV-1404.
Opened CV-1404.
C
: 9.
Close decay heat cooler E-35A outlet valve CV-1428.
Closed CV-1428.  


Page 5 of 5 TUOI: A1JPM-DHR01 C           PERFORMANCE CHECKLIST                         STANDARDS           N/A SAT   UNSAT C     10. Position E-35A Cooler Bypass (CV-       Positioned CV-1433 to ~
Page 5 of 5 TUOI: A1JPM-DHR01 C
1433) to ~ 50% as indicated on HIC-     50% open.                 ____ ____    ____
PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT C
1433.
: 10.
Position E-35A Cooler Bypass (CV-1433) to ~ 50% as indicated on HIC-1433.
Positioned CV-1433 to ~
50% open.
C
: 11. Open Decay Heat Block Valve CV-1401 Opened CV-1401.
C
C
: 11. Open Decay Heat Block Valve CV-           Opened CV-1401.
: 12. Start P-34A.
1401                                                                ____ ____    ____
Started P-34A.
: 13.
Verify LPI/Decay Heat Pump Brg CLR E-50A Inlet (CV-3840) and Decay HT CLR Service Water E-35A Inlet (CV-3822) open.
On C-18, verified CV-3840 and CV-3822 open.
: 14.
Monitor pressurizer level.
Monitored pressurizer level on C04 or SPDS.
C
C
: 12. Start P-34A.                              Started P-34A.
: 15.
: 13. Verify LPI/Decay Heat Pump Brg          On C-18, verified CV-CLR E-50A Inlet (CV-3840) and          3840 and CV-3822 open. ____ ____    ____
Adjust CV-1433 to establish decay heat removal flow at < 3500 gpm from P-34A and discharge pressure  
Decay HT CLR Service Water E-35A Inlet (CV-3822) open.
< 400 psig.
: 14. Monitor pressurizer level.              Monitored pressurizer      ____ ____    ____
Adjusted DHR flow to
level on C04 or SPDS.
<3500 gpm and discharge pressure < 400 psig using CV-1433.
C    15. Adjust CV-1433 to establish decay       Adjusted DHR flow to      ____ ____    ____
heat removal flow at < 3500 gpm         <3500 gpm and from P-34A and discharge pressure       discharge pressure < 400
                < 400 psig.                            psig using CV-1433.
NOTE: Inform examinee that it is not necessary to perform Part 2 of Supplement 3.
NOTE: Inform examinee that it is not necessary to perform Part 2 of Supplement 3.
: 16. Verify LPI Room Cooler VUC-1A           At panel C-19, verified   ____ ____    ____
: 16.
starts.                                VUC-1A started (red light on).
Verify LPI Room Cooler VUC-1A starts.
: 17. Adjust the DECAY HEAT VORTEX           Selected the U5 function   ____ ____    ____
At panel C-19, verified VUC-1A started (red light on).
WARNING SETPOINT.                      of the SPDS computer and set KP34ALO just below the Decay Heat Pump motor current and adjusted KP34AHI just above the Decay Heat Pump motor current.
: 17.
END
Adjust the DECAY HEAT VORTEX WARNING SETPOINT.
Selected the U5 function of the SPDS computer and set KP34ALO just below the Decay Heat Pump motor current and adjusted KP34AHI just above the Decay Heat Pump motor current.
END  


TUOI NUMBER:_ANO-1-JPM-RO-RPS02_                                           Page 1 of 5 JOB PERFORMANCE MEASURE UNIT: ______1_______     REV # ______4________   DATE: ______________________________
TUOI NUMBER:_ANO-1-JPM-RO-RPS02_
TUOI NUMBER:_A1JPM-RO-RPS02           ______________
Page 1 of 5 JOB PERFORMANCE MEASURE UNIT: ______1_______
SYSTEM/DUTY AREA:_REACTOR PROTECTION SYSTEM________________________________________
REV # ______4________ DATE: ______________________________
TUOI NUMBER:_A1JPM-RO-RPS02 SYSTEM/DUTY AREA:_REACTOR PROTECTION SYSTEM________________________________________
TASK:_REMOVE A CHANNEL OF RPS FROM MANUAL BYPASS___________________________________
TASK:_REMOVE A CHANNEL OF RPS FROM MANUAL BYPASS___________________________________
JTA#:_ANO1-RO-RPS-NORM-6___________________________
JTA#:_ANO1-RO-RPS-NORM-6___________________________
Line 896: Line 1,280:
==REFERENCE:==
==REFERENCE:==
__012 A4.03_________________
__012 A4.03_________________
APPROVED FOR ADMINISTRATION TO:   RO:____X___ SRO:___ X ___
APPROVED FOR ADMINISTRATION TO: RO:____X___ SRO:___ X ___
TASK LOCATION: INSIDE CR:____X____ OUTSIDE CR:_________ BOTH:________
TASK LOCATION: INSIDE CR:____X____ OUTSIDE CR:_________ BOTH:________
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________
PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________
POSITION EVALUATED:   RO:__________   SRO:___________
POSITION EVALUATED: RO:__________ SRO:___________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________
TESTING METHOD: SIMULATE:_________   PERFORM:___________
TESTING METHOD: SIMULATE:_________ PERFORM:___________
APPROXIMATE COMPLETION TIME IN MINUTES:___   15 MINUTES______________________________
APPROXIMATE COMPLETION TIME IN MINUTES:___ 15 MINUTES______________________________
REFERENCE(S):__1105.001                       ______________________________________
REFERENCE(S):__1105.001 EXAMINEE'S NAME:________________________________
EXAMINEE'S NAME:________________________________         SSN ______-_____-____________
SSN ______-_____-____________
EVALUATOR'S NAME:__________________________________________________________________
EVALUATOR'S NAME:__________________________________________________________________
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
SATISFACTORY:________________         UNSATISFACTORY:_________________
SATISFACTORY:________________
UNSATISFACTORY:_________________
PERFORMANCE CHECKLIST COMMENTS:
PERFORMANCE CHECKLIST COMMENTS:
____________ Start Time           ____________ Stop Time       ____________ Total Time SIGNED ________________________________ DATE: _______________________
____________ Start Time
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.
____________ Stop Time
____________ Total Time SIGNED ________________________________ DATE: _______________________
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.  


TUOI NUMBER:_ANO-1-JPM-RO-RPS02_                                       Page 2 of 5 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:_ANO-1-JPM-RO-RPS02_
Page 2 of 5 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:_The plant is operating at 100% power with ICS in auto-_
JPM INITIAL TASK CONDITIONS:_The plant is operating at 100% power with ICS in auto-_
Line 920: Line 1,308:
TASK STANDARD:_The A RPS channel is removed from manual bypass.___________________
TASK STANDARD:_The A RPS channel is removed from manual bypass.___________________
TASK PERFORMANCE AIDS:_Manual bypass key, 1105.001_________________________________
TASK PERFORMANCE AIDS:_Manual bypass key, 1105.001_________________________________
SIMULATOR SETUP: Power operations, place A RPS in manual bypass, select SASS Neutron Flux selector to the Y position.
SIMULATOR SETUP: Power operations, place A RPS in manual bypass, select SASS Neutron Flux selector to the Y position.  


TUOI NUMBER:_ANO-1-JPM-RO-RPS02_                                         Page 3 of 5 TUOI NUMBER:_ANO-1-JPM-RO-RPS02_
TUOI NUMBER:_ANO-1-JPM-RO-RPS02_
Page 3 of 5 TUOI NUMBER:_ANO-1-JPM-RO-RPS02_
INITIATING CUE:
INITIATING CUE:
The SM/CRS directs you to remove the A RPS channel from manual bypass per section 11.0 of 1105.001, NI & RPS Operating Procedure.
The SM/CRS directs you to remove the A RPS channel from manual bypass per section 11.0 of 1105.001, NI & RPS Operating Procedure.
CRITICAL ELEMENTS (C):__2__
CRITICAL ELEMENTS (C):__2__
(C)       PERFORMANCE CHECKLIST                 STANDARD           N/A     SAT     UNSAT NOTE: Due to the uniqueness of the design in the simulator, all channel indications are located in one RPS cabinet.
(C)
: 1. Verify A RPS channel is   Inside the RPS cabinet in reset.                      the back of the control room:
PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT NOTE: Due to the uniqueness of the design in the simulator, all channel indications are located in one RPS cabinet.
: 1. Verify A RPS channel is reset.
Inside the RPS cabinet in the back of the control room:
a) Verified all test modules are in operate with the On Test lamps ON dim.
a) Verified all test modules are in operate with the On Test lamps ON dim.
b) Depressed and released the Output State and Output Memory Reset switches for all bistables with Output State and/or Output Memory   _____    _____    _____
b) Depressed and released the Output State and Output Memory Reset switches for all bistables with Output State and/or Output Memory lamps ON bright.
lamps ON bright.
c) Verified the Building Pressure contact buffer is reset (both Input State lamps OFF).
c) Verified the Building Pressure contact buffer is reset (both Input State lamps OFF).
d) On the Channel A Reactor Trip Module, placed Subsystem Reset switch to down position.
d) On the Channel A Reactor Trip Module, placed Subsystem Reset switch to down position.
e) Verified the Subsystem No. 1 lamps ON dim for Reactor Trip modules and Cabinet Indicating Panels on all RPS Channels.
e) Verified the Subsystem No. 1 lamps ON dim for Reactor Trip modules and Cabinet Indicating Panels on all RPS Channels.
(C)   2. Turn Manual Bypass key     On the Reactor Trip Module switch out of bypass        in A RPS, turned keyswitch _____    _____    _____
(C)
position.                  out of bypass position.
: 2. Turn Manual Bypass key switch out of bypass position.
On the Reactor Trip Module in A RPS, turned keyswitch out of bypass position.
Reactor Trip Module did NOT trip (verifies previous step properly performed).
Reactor Trip Module did NOT trip (verifies previous step properly performed).
: 3. Verify Manual Bypass lamps On the Reactor Trip module ON dim.                    and indicating panel, verified the Manual Bypass   _____    _____    _____
: 3. Verify Manual Bypass lamps ON dim.
lamps are ON dim.
On the Reactor Trip module and indicating panel, verified the Manual Bypass lamps are ON dim.  


TUOI NUMBER:_ANO-1-JPM-RO-RPS02_                                       Page 4 of 5 (C)       PERFORMANCE CHECKLIST               STANDARD           N/A     SAT     UNSAT
TUOI NUMBER:_ANO-1-JPM-RO-RPS02_
: 4. Verify annunciator K08-D3 Verified that annunciator clear.                    K08-D3 RPS CHANNEL BYPASSED _____    _____    _____
Page 4 of 5 (C)
is clear.
PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT
: 5. Verify A EFIC channel   Verified A EFIC channel Maintenance Bypass light  Maintenance Bypass light ON ON solid.                  solid on the upper right of _____    _____    _____
: 4. Verify annunciator K08-D3 clear.
the A EFIC cabinet.
Verified that annunciator K08-D3 RPS CHANNEL BYPASSED is clear.
: 6. Remove Manual Bypass key  Removed Manual Bypass key from Reactor Trip module  from Reactor Trip module and _____    _____    _____
: 5. Verify A EFIC channel Maintenance Bypass light ON solid.
and return to Shift Mgr. returned to Shift Mgr.
Verified A EFIC channel Maintenance Bypass light ON solid on the upper right of the A EFIC cabinet.
: 7. Verify <1% difference     Used panel readings on C03 between NI-5/NI-6 high and or plant computer points NI-7/NI-8 high.           N1I56HI and N1I78HI to       _____    _____    _____
: 6. Remove Manual Bypass key from Reactor Trip module and return to Shift Mgr.
determine the difference between the highest of NI5/NI6 is <1% different from the highest of NI7/NI8.
Removed Manual Bypass key from Reactor Trip module and returned to Shift Mgr.
: 8. Return the SASS Neutron   On C03, the SASS Neutron Flux selector switch to    Flux switch is placed in the SASS Enable.              SASS Enable position after   _____    _____    _____
: 7. Verify <1% difference between NI-5/NI-6 high and NI-7/NI-8 high.
the signals (N1I56HI and N1I78HI) had been compared.
Used panel readings on C03 or plant computer points N1I56HI and N1I78HI to determine the difference between the highest of NI5/NI6 is <1% different from the highest of NI7/NI8.
END
: 8. Return the SASS Neutron Flux selector switch to SASS Enable.
On C03, the SASS Neutron Flux switch is placed in the SASS Enable position after the signals (N1I56HI and N1I78HI) had been compared.
END  


TUOI NUMBER:_ANO-1-JPM-RO-RPS02_                                                   Page 5 of 5 EXAMINEES COPY INITIAL CONDITIONS:
TUOI NUMBER:_ANO-1-JPM-RO-RPS02_
* The plant is operating at 100% power with ICS in automatic.
Page 5 of 5 EXAMINEES COPY INITIAL CONDITIONS:  
* The A RPS channel is in manual bypass for maintenance.
 The plant is operating at 100% power with ICS in automatic.  
* The maintenance has been completed.
 The A RPS channel is in manual bypass for maintenance.  
 The maintenance has been completed.
INITIATING CUE:
INITIATING CUE:
The SM/CRS directs you to remove the A RPS channel from manual bypass per section 11.0 of 1105.001, NI & RPS Operating Procedure.
The SM/CRS directs you to remove the A RPS channel from manual bypass per section 11.0 of 1105.001, NI & RPS Operating Procedure.  


TUOI NUMBER:                                                                                                             Page 1 of 6 A1JPM-RO-EOP11 JOB PERFORMANCE MEASURE Unit:               1             Rev #                         1                         Date:
TUOI NUMBER:
TUOI NUMBER:           A1JPM-RO- EOP11 System/Duty Area:       Emergency and Abnormal Operations Task:     Perform Actions during ESAS Actuation to swap ECCS suction to RB sump (ALTERNATE PATH JPM)
Page 1 of 6 A1JPM-RO-EOP11 JOB PERFORMANCE MEASURE Unit:
JA#       ANO1-RO-KA Value RO       4.0       SRO     3.8     KA Reference       006.A4.02 Approved For Administration To: RO                               SRO Task Location: Inside CR:                           Outside CR:                       Both:
1 Rev #
1 Date:
TUOI NUMBER:
A1JPM-RO-EOP11 System/Duty Area:
Emergency and Abnormal Operations Task:
Perform Actions during ESAS Actuation to swap ECCS suction to RB sump (ALTERNATE PATH JPM)
JA#
ANO1-RO-KA Value RO 4.0 SRO 3.8 KA Reference 006.A4.02 Approved For Administration To: RO SRO Task Location: Inside CR:
Outside CR:
Both:
Suggested Testing Environment And Method (Perform Or Simulate):
Suggested Testing Environment And Method (Perform Or Simulate):
Plant Site:                     Simulator:           Perform       X             Lab:
Plant Site:
Position Evaluated: RO:                       X                               SRO:                     X Actual Testing Environment: Simulator:                             Plant Site:                     Lab Testing Method: Simulate:                                                 Perform:
Simulator:
Approximate Completion Time In Minutes:                                         20 Minutes Reference(S):
Perform X Lab:
Examinee's Name:                                                                     SSN:
Position Evaluated: RO:
X SRO:
X Actual Testing Environment: Simulator:
Plant Site:
Lab Testing Method: Simulate:
Perform:
Approximate Completion Time In Minutes:
20 Minutes Reference(S):
Examinee's Name:
SSN:
Evaluator's Name:
Evaluator's Name:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
Satisfactory:                                       Unsatisfactory:
Satisfactory:
Unsatisfactory:
Performance Checklist Comments:
Performance Checklist Comments:
Start Time                                   Stop Time                                       Total Time Signed                                                               Date:
Start Time Stop Time Total Time Signed Date:
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.  


TUOI NUMBER:                                                                               Page 2 of 6 A1JPM-RO-EOP11 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 with the examinee.
Page 2 of 6 A1JPM-RO-EOP11 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 with the examinee.
JPM INITIAL TASK CONDITIONS:
JPM INITIAL TASK CONDITIONS:
ESAS has actuated due to a LOCA. RCS pressure is &#xa3; 50 psig. All unnecessary people have been evacuated from the Aux Building. Aux Spray has been aligned from LPI system. BWST level is at ~
ESAS has actuated due to a LOCA. RCS pressure is  50 psig. All unnecessary people have been evacuated from the Aux Building. Aux Spray has been aligned from LPI system. BWST level is at ~
6 feet, BWST LO and LO LO annunciators are in alarm.
6 feet, BWST LO and LO LO annunciators are in alarm.
TASK STANDARD:
TASK STANDARD:
Line 985: Line 1,399:
RT15 from 1202.012, change 004-02-0.
RT15 from 1202.012, change 004-02-0.
SIMULATOR SETUP:
SIMULATOR SETUP:
IC2, then insert large RCS leak so that full ESAS actuation occurs. Trip all RCPs and go to reflux boiling setpoint for EFW. Close CV-1000 and CV-1009. Close CV-2415 and CV-2419 (CFT Outlets).Secure HPI pumps, close all HPI block valves, close CV-1206. Secure EFW-- P-7B in P-T-L, close CV-2613/CV-2663 in manual, close MFIVs and MSIVs. Throttle RB Spray to 1050-1200 gpm. Fail CV-1405 closed.
IC2, then insert large RCS leak so that full ESAS actuation occurs. Trip all RCPs and go to reflux boiling setpoint for EFW. Close CV-1000 and CV-1009. Close CV-2415 and CV-2419 (CFT Outlets).Secure HPI pumps, close all HPI block valves, close CV-1206. Secure EFW-- P-7B in P-T-L, close CV-2613/CV-2663 in manual, close MFIVs and MSIVs. Throttle RB Spray to 1050-1200 gpm. Fail CV-1405 closed.  


TUOI NUMBER:                                                                                         Page 3 of 6 A1JPM-RO-EOP11 INITIATING CUE: The CRS/SM directs you to shift to RB sump suction using RT-15.
TUOI NUMBER:
CRITICAL ELEMENTS (c): 9, 10, 11, 12 C                 PERFORMANCE CHECKLIST                             STANDARD                 N/A SAT     UN SAT
Page 3 of 6 A1JPM-RO-EOP11 INITIATING CUE: The CRS/SM directs you to shift to RB sump suction using RT-15.
: 1. Verify both LPI pumps running (P34A and B).       On C16 and C18, operator           ____ ____    ___
CRITICAL ELEMENTS (c): 9, 10, 11, 12 C
verifies RED lights ON and                         _
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT
GREEN lights OFF for both P34A and P34B.
: 1. Verify both LPI pumps running (P34A and B).
: 2. Verify LPI Room Coolers running: VUC1A or         On C19, operator verifies RED       ____ ____    ___
On C16 and C18, operator verifies RED lights ON and GREEN lights OFF for both P34A and P34B.
VUC1B AND VUC1C or VUC1D.                      lights ON and GREEN lights OFF                     _
: 2. Verify LPI Room Coolers running: VUC1A or VUC1B AND VUC1C or VUC1D.
for VU1CA and VU1CC.
On C19, operator verifies RED lights ON and GREEN lights OFF for VU1CA and VU1CC.
: 3. Verify both LPI Block valves fully open (CV-1400 On C16 and C18, operator           ____ ____    ___
: 3. Verify both LPI Block valves fully open (CV-1400 and CV-1401).
and CV-1401).                                    verifies valves are open with RED                 _
On C16 and C18, operator verifies valves are open with RED lights ON and GREEN lights OFF for CV-1400 and CV-1401.
lights ON and GREEN lights OFF for CV-1400 and CV-1401.
: 4. Verify Letdown isolated by CV-1221 closed on C16 or CV-1214/CV-1216 closed on C18.
: 4. Verify Letdown isolated by CV-1221 closed on C16 On C-16, operator verifies          ____ ____    ___
On C-16, operator verifies letdown isolated by observing CV-1221 closed with the GREEN light ON and RED light OFF or on C-18, operator verifies letdown isolated by observing CV-1214/CV-1216 closed with the GREEN lights ON and RED lights OFF.
or CV-1214/CV-1216 closed on C18.               letdown isolated by observing CV-                 _
: 5. Verify both Decay Heat Supply to Makeup Pump Suctions open (CV-1276 and CV-1277).
1221 closed with the GREEN light ON and RED light OFF or on C-18, operator verifies letdown isolated by observing CV-1214/CV-1216 closed with the GREEN lights ON and RED lights OFF.
NOTE: valves will be shut when examinee gets to this step, after examinee goes to open on these valves give the POSITIVE CUE.
: 5. Verify both Decay Heat Supply to Makeup Pump     Operator Opens CV1276 and CV-Suctions open (CV-1276 and CV-1277).             1277 on panels C16 and C18 and observes Red lights ON, green      ____ ____    ___
Operator Opens CV1276 and CV-1277 on panels C16 and C18 and observes Red lights ON, green lights OFF.
NOTE: valves will be shut when examinee gets to     lights OFF.                                        _
: 6. Verify RB Spray flow throttled to maintain 1050-1200 gpm per train.
this step, after examinee goes to open on these valves give the POSITIVE CUE.
Operator verifies that RB Spray flow is throttled to maintain 1050-1200 gpm per train (as indicated on SPDS, C16/C18 or recorder on C14, approximately 1150 gpm indicated flow on each train)  
Operator verifies that RB Spray
: 6. Verify RB Spray flow throttled to maintain 1050- flow is throttled to maintain 1050-1200 gpm per train (as indicated   ____ ____    ___
1200 gpm per train.                              on SPDS, C16/C18 or recorder                       _
on C14, approximately 1150 gpm indicated flow on each train)


TUOI NUMBER:                                                                                         Page 4 of 6 A1JPM-RO-EOP11 C               PERFORMANCE CHECKLIST                                 STANDARD               N/A SAT     UN SAT
TUOI NUMBER:
: 7. If NaOH Tank T10 level is &#xa3;25 ft, THEN close RB     Operator Closes CV-1616 and spray NaOH Addition T-10 Outlets (CV-1616 and       CV-1617 IF T-10 level is &#xa3;25 ft CV-1617).                                          and observes GREEN lights ON and RED lights OFF.
Page 4 of 6 A1JPM-RO-EOP11 C
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT
: 7. If NaOH Tank T10 level is 25 ft, THEN close RB spray NaOH Addition T-10 Outlets (CV-1616 and CV-1617).
NOTE: if this JPM is being simulated, tell examinee that T10 level is 20 ft then give POSITIVE CUE after examinee goes to close on the valves.
NOTE: if this JPM is being simulated, tell examinee that T10 level is 20 ft then give POSITIVE CUE after examinee goes to close on the valves.
: 8. Verify RB Sump Outlets open (CV-1414 and CV         On C16 and C18, operator 1415).                                            verifies CV-1414 and CV-1415 open with RED lights ON and GREEN lights OFF.
Operator Closes CV-1616 and CV-1617 IF T-10 level is 25 ft and observes GREEN lights ON and RED lights OFF.
: 8. Verify RB Sump Outlets open (CV-1414 and CV 1415).
On C16 and C18, operator verifies CV-1414 and CV-1415 open with RED lights ON and GREEN lights OFF.
NOTE: This is the alternate path portion of the JPM. The RB sump outlet valve CV-1405 will fail to open.
NOTE: This is the alternate path portion of the JPM. The RB sump outlet valve CV-1405 will fail to open.
: 9. Open RB Sump Outlets (CV-1405 and CV-1406).         On panel C16 operator attempts C                                                          to open CV-1405 (it will not open) and observes the GREEN light ON and RED light OFF for it.
C
: 9. Open RB Sump Outlets (CV-1405 and CV-1406).
On panel C16 operator attempts to open CV-1405 (it will not open) and observes the GREEN light ON and RED light OFF for it.
On panel C18, operator opens CV-1406 and observes RED light ON and GREEN light OFF for it.
On panel C18, operator opens CV-1406 and observes RED light ON and GREEN light OFF for it.
See note: This is the Alternate Path step for the JPM
See note: This is the Alternate Path step for the JPM C
: 10. Stop associated LPI, HPI, and RB Spray pumps,       On C-16 and C-18, operator C                                                          secures LPI pump P-34A AND which includes:                                                                      ____ ____    ___
: 10. Stop associated LPI, HPI, and RB Spray pumps, which includes:
secures RB Spray pump P-35A.
RB Spray pump P-35A LPI pump P-34A On C-16 and C-18, operator secures LPI pump P-34A AND secures RB Spray pump P-35A.
RB Spray pump P-35A                              (HPI is already secured) and                     _
(HPI is already secured) and observes GREEN lights ON and RED lights OFF.
LPI pump P-34A                                    observes GREEN lights ON and RED lights OFF.
C
C   11. Take manual control of BWST outlets CV-1407         On C16 and C18, operator and CV-1408.                                    depresses the manual pushbutton   ____ ____    ___
: 11. Take manual control of BWST outlets CV-1407 and CV-1408.
on each of two AUTO/MANUAL                       _
On C16 and C18, operator depresses the manual pushbutton on each of two AUTO/MANUAL pushbuttons for CV-1407 and CV-1408 in MANUAL and observes WHITE light ON and RED light OFF for each.
pushbuttons for CV-1407 and CV-1408 in MANUAL and observes WHITE light ON and RED light OFF for each.
C
C   12. Close BWST Outlets (CV-1407 and CV-1408).           On C16 and C18, operator verifies GREEN lights ON and RED lights OFF for closed valves CV-1407 and CV-1408.
: 12. Close BWST Outlets (CV-1407 and CV-1408).
On C16 and C18, operator verifies GREEN lights ON and RED lights OFF for closed valves CV-1407 and CV-1408.  


TUOI NUMBER:                                                                                             Page 5 of 6 A1JPM-RO-EOP11 C               PERFORMANCE CHECKLIST                                       STANDARD               N/A SAT     UN SAT
TUOI NUMBER:
: 13. Check LPI/RB Spray flow is maintained.                   Checked proper LPI/RB Spray flow is being maintained by observing SPDS or meters on C16/C18 or recorder on C14 with values for spray @ 1100 gpm, LPI
Page 5 of 6 A1JPM-RO-EOP11 C
                                                                  @ 3000 gpm.
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT
: 14. Notify HP to monitor BWST suction line for               Notified Health Physics.
: 13. Check LPI/RB Spray flow is maintained.
indication of back-leakage from LPI suction.
Checked proper LPI/RB Spray flow is being maintained by observing SPDS or meters on C16/C18 or recorder on C14 with values for spray @ 1100 gpm, LPI  
@ 3000 gpm.
: 14. Notify HP to monitor BWST suction line for indication of back-leakage from LPI suction.
POSITIVE CUE:
POSITIVE CUE:
HP has been notified.
HP has been notified.
Notified Health Physics.
Instructor Note: INFORM EXAMINEE THAT MAKEUP TANK LEVEL IS STEADY AT 50 INCHES.
Instructor Note: INFORM EXAMINEE THAT MAKEUP TANK LEVEL IS STEADY AT 50 INCHES.
: 15. IF NaOH Tank T10 Level >25 ft, THEN open CV-         Opened CV-1616 and CV-1617 IF 1616 and CV-1617.                                    T10 level >25 ft.
: 15. IF NaOH Tank T10 Level >25 ft, THEN open CV-1616 and CV-1617.
NOTE: If being simulated tell examinee that T10 level is 20 ft which will make this step (14 and 14.a) N/A.
NOTE: If being simulated tell examinee that T10 level is 20 ft which will make this step (14 and 14.a) N/A.
a) WHEN T10 level is 11-25 ft, THEN close CV-1616           a) Closed CV-1616 and CV-1617 and CV-1617.                                                after T10 level is in range of 11-25 ft.
a) WHEN T10 level is 11-25 ft, THEN close CV-1616 and CV-1617.
Opened CV-1616 and CV-1617 IF T10 level >25 ft.
a) Closed CV-1616 and CV-1617 after T10 level is in range of 11-25 ft.
INFORM EXAMINEE THAT RB LEVELS HAVE STABILIZED AND BWST REFILL HAS BEEN INITIATED.
INFORM EXAMINEE THAT RB LEVELS HAVE STABILIZED AND BWST REFILL HAS BEEN INITIATED.
INSTRUCTOR CUE: This concludes the JPM.
INSTRUCTOR CUE: This concludes the JPM.
END
END  


TUOI NUMBER:                                                                         Page 6 of 6 A1JPM-RO-EOP11 EXAMINEES COPY INITIAL CONDITIONS:
TUOI NUMBER:
ESAS has actuated due to a LOCA. RCS pressure is &#xa3; 50 psig. All unnecessary people have been evacuated from the Aux Building. Aux Spray has been aligned from LPI system. BWST level is at ~ 6 feet, BWST LO and LO LO annunciators are in alarm.
Page 6 of 6 A1JPM-RO-EOP11 EXAMINEES COPY INITIAL CONDITIONS:
ESAS has actuated due to a LOCA. RCS pressure is  50 psig. All unnecessary people have been evacuated from the Aux Building. Aux Spray has been aligned from LPI system. BWST level is at ~ 6 feet, BWST LO and LO LO annunciators are in alarm.
INITIATING CUE:
INITIATING CUE:
The CRS/SM directs you to shift to RB sump suction using RT-15.
The CRS/SM directs you to shift to RB sump suction using RT-15.  
 
PROC./WORK PLAN N


==O. PROCEDURE==
PROC./WORK PLAN NO.
/WORK PLAN TITLE:   Page 28 of 30 1202.012              REPETITIVE TASKS   CHANGE: 004-02-0
1202.012 PROCEDURE/WORK PLAN TITLE: Page 28 of 30 REPETITIVE TASKS CHANGE: 004-02-0  


TUOI NUMBER:_A1JPM-RO-EDG04                                             Page 1 of 5 JOB PERFORMANCE MEASURE UNIT: ______1_______     REV # ______1_______   DATE: ______________________________
TUOI NUMBER:_A1JPM-RO-EDG04 Page 1 of 5 JOB PERFORMANCE MEASURE UNIT: ______1_______
TUOI NUMBER:_A1JPM-RO-EDG04__             ___________
REV # ______1_______
DATE: ______________________________
TUOI NUMBER:_A1JPM-RO-EDG04__
SYSTEM/DUTY AREA:_EMERGENCY DIESEL GENERATOR (EDG) SYSTEM__________________________
SYSTEM/DUTY AREA:_EMERGENCY DIESEL GENERATOR (EDG) SYSTEM__________________________
TASK:_LOAD EDG1____________________________________________________________________
TASK:_LOAD EDG1____________________________________________________________________
Line 1,060: Line 1,483:
==REFERENCE:==
==REFERENCE:==
__064 A4.07_________________
__064 A4.07_________________
APPROVED FOR ADMINISTRATION TO:   RO:____X___ SRO:___ X ___
APPROVED FOR ADMINISTRATION TO: RO:____X___ SRO:___ X ___
TASK LOCATION:   INSIDE CR:____X____ OUTSIDE CR:_________ BOTH:________
TASK LOCATION: INSIDE CR:____X____ OUTSIDE CR:_________ BOTH:________
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________
PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________
POSITION EVALUATED:   RO:__________ SRO:___________
POSITION EVALUATED: RO:__________ SRO:___________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________
ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________
TESTING METHOD: SIMULATE:_________   PERFORM:___________
TESTING METHOD: SIMULATE:_________ PERFORM:___________
APPROXIMATE COMPLETION TIME IN MINUTES:___ 15 MINUTES______________________________
APPROXIMATE COMPLETION TIME IN MINUTES:___ 15 MINUTES______________________________
REFERENCE(S):_1104.036                                     ________________________
REFERENCE(S):_1104.036 ________________________
EXAMINEE'S NAME:________________________________       SSN ______-_____-____________
EXAMINEE'S NAME:________________________________
SSN ______-_____-____________
EVALUATOR'S NAME:__________________________________________________________________
EVALUATOR'S NAME:__________________________________________________________________
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
SATISFACTORY:________________       UNSATISFACTORY:_________________
SATISFACTORY:________________
UNSATISFACTORY:_________________
PERFORMANCE CHECKLIST COMMENTS:
PERFORMANCE CHECKLIST COMMENTS:
____________ Start Time         ____________ Stop Time     ____________ Total Time SIGNED ________________________________ DATE: _______________________
____________ Start Time
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.
____________ Stop Time
____________ Total Time SIGNED ________________________________ DATE: _______________________
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.  


TUOI NUMBER:_A1JPM-RO-EDG04                                             Page 2 of 5 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:_A1JPM-RO-EDG04 Page 2 of 5 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:_EDG1 is running with its output breaker open and its___
JPM INITIAL TASK CONDITIONS:_EDG1 is running with its output breaker open and its___
_service water inlet valve (CV-3806) open._ ________________________________________
_service water inlet valve (CV-3806) open._ ________________________________________
TASK STANDARD:_EDG1 tripped by examinee after its load increases without operator __
TASK STANDARD:_EDG1 tripped by examinee after its load increases without operator __
_control._This is an Alternate Success Path JPM.__________________________   ________
_control._This is an Alternate Success Path JPM.__________________________ ________
TASK PERFORMANCE AIDS:__1104.036 Section 7.0                     ___________________
TASK PERFORMANCE AIDS:__1104.036 Section 7.0 NOTE: When the EDG1 output breaker is closed, insert override DI CS3-DG1_RO2; true and CS3-DG1_W02; false which will fail the governor handswitch in the raise position; this will cause the EDG load to rise without control.  
NOTE: When the EDG1 output breaker is closed, insert override DI CS3-DG1_RO2; true and CS3-DG1_W02; false which will fail the governor handswitch in the raise position; this will cause the EDG load to rise without control.


TUOI NUMBER:_A1JPM-RO-EDG04                                             Page 3 of 5 INITIATING CUE:
TUOI NUMBER:_A1JPM-RO-EDG04 Page 3 of 5 INITIATING CUE:
The SM/CRS directs you to parallel EDG1 to the grid and load EDG1 to ~2750 KW per 1104.036 Step 7.10.
The SM/CRS directs you to parallel EDG1 to the grid and load EDG1 to ~2750 KW per 1104.036 Step 7.10.
CRITICAL ELEMENTS (C):_2, 6, 7 (C)       PERFORMANCE CHECKLIST                 STANDARD           N/A     SAT     UNSAT
CRITICAL ELEMENTS (C):_2, 6, 7 (C)
: 1. Inform dispatcher that     Called the dispatcher, EDG1 will be loaded and   informed him/her that EDG1 inquire about weather. is ready for loading and       ____    ____      ____
PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT
asked about proper weather conditions.
: 1.
(C)   2. Turn on synchronize       On C10, placed synchronize switch for EDG1 output    switch for A-308 to ON         ____    ____      ____
Inform dispatcher that EDG1 will be loaded and inquire about weather.
breaker A-308.            position.
Called the dispatcher, informed him/her that EDG1 is ready for loading and asked about proper weather conditions.
: 3. Verify voltage control. Verified voltage control by raising and/or lowering voltage using the EDG1         ____    ____      ____
(C)
voltage regulator control switch on C10.
: 2.
: 4. Verify frequency control. Verified frequency control by raising and/or lowering frequency by using the EDG1   ____    ____      ____
Turn on synchronize switch for EDG1 output breaker A-308.
governor control switch on C10.
On C10, placed synchronize switch for A-308 to ON position.
: 5. Match running and         On C10, matched running and incoming voltages.        incoming voltages by adjusting EDG1 voltage regulator.                     ____    ____      ____
: 3.
Verify voltage control.
Verified voltage control by raising and/or lowering voltage using the EDG1 voltage regulator control switch on C10.
: 4.
Verify frequency control.
Verified frequency control by raising and/or lowering frequency by using the EDG1 governor control switch on C10.
: 5.
Match running and incoming voltages.
On C10, matched running and incoming voltages by adjusting EDG1 voltage regulator.
NOTE: Voltages may be verified matched on C10 or SPDS or on plant computer.
NOTE: Voltages may be verified matched on C10 or SPDS or on plant computer.
(C)   6. Adjust EDG1 frequency. On C10, adjusted EDG1 governor control to achieve
(C)
                                    ~60 hz with synchroscope       ____    ____      ____
: 6.
rotating slowly in the FAST direction.
Adjust EDG1 frequency.
NOTE: IA Operator When the EDG1 output breaker is closed, insert override DI CS3-DG1_RO2; true and DI CS3-DG1_W02; false which will fail the governor handswitch in the raise position, this will cause the EDG load to rise without control.
On C10, adjusted EDG1 governor control to achieve  
~60 hz with synchroscope rotating slowly in the FAST direction.
NOTE: IA Operator  When the EDG1 output breaker is closed, insert override DI CS3-DG1_RO2; true and DI CS3-DG1_W02; false which will fail the governor handswitch in the raise position, this will cause the EDG load to rise without control.  


TUOI NUMBER:_A1JPM-RO-EDG04                                       Page 4 of 5 (C)     PERFORMANCE CHECKLIST               STANDARD         N/A     SAT     UNSAT (C)   7. As synchroscope           Closed EDG1 output breaker approaches 12 oclock     A-308.                    ____    ____      ____
TUOI NUMBER:_A1JPM-RO-EDG04 Page 4 of 5 (C)
position (~5 min. til) close EDG1 output breaker A-308.
PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT (C)
(C)   8. Operator identifies       On C10, tripped EDG1.
: 7.
increasing load and trips                           ____    ____      ____
As synchroscope approaches 12 oclock position (~5 min. til) close EDG1 output breaker A-308.
the EDG.
Closed EDG1 output breaker A-308.
END
(C)
: 8.
Operator identifies increasing load and trips the EDG.
On C10, tripped EDG1.
END  


TUOI NUMBER:_A1JPM-RO-EDG04                                                             Page 5 of 5 EXAMINEES COPY INITIAL CONDITIONS:
TUOI NUMBER:_A1JPM-RO-EDG04 Page 5 of 5 EXAMINEES COPY INITIAL CONDITIONS:
EDG1 is running with its output breaker open and its service water inlet valve (CV-3806) open.
EDG1 is running with its output breaker open and its service water inlet valve (CV-3806) open.
INITIATING CUE:
INITIATING CUE:
The SM/CRS directs you to parallel EDG1 to the grid and load EDG1 to ~2750 KW per 1104.036 Step 7.10.
The SM/CRS directs you to parallel EDG1 to the grid and load EDG1 to ~2750 KW per 1104.036 Step 7.10.  


JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030                                                               Page 1 of 5 UNIT: 1               REV # 0             DATE: ______________________________
JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030 Page 1 of 5 UNIT: 1 REV # 0 DATE: ______________________________
TUOI NUMBER: A1JPM-RO-ED030 SYSTEM/DUTY AREA: BATTERY AND 125V DC DISTRIBUTION TASK: PLACE BATTERY CHARGER D-03B IN SERVICE JTA#: ANO1-AO-125DC-NORM-12 KA VALUE RO:       3.9     SRO:     3.4     KA  
TUOI NUMBER: A1JPM-RO-ED030 SYSTEM/DUTY AREA: BATTERY AND 125V DC DISTRIBUTION TASK: PLACE BATTERY CHARGER D-03B IN SERVICE JTA#: ANO1-AO-125DC-NORM-12 KA VALUE RO:
3.9 SRO:
3.4 KA  


==REFERENCE:==
==REFERENCE:==
2.1.30 APPROVED FOR ADMINISTRATION TO: RO:         X           SRO:   X TASK LOCATION: INSIDE CR:         X       OUTSIDE CR:_________ BOTH:________
2.1.30 APPROVED FOR ADMINISTRATION TO: RO: X SRO:
X TASK LOCATION: INSIDE CR:
X OUTSIDE CR:_________ BOTH:________
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):
PLANT SITE:____ X_____SIMULATOR:                         LAB:_________________
PLANT SITE:____ X_____SIMULATOR:
POSITION EVALUATED: RO:         X                 SRO:     X ACTUAL TESTING ENVIRONMENT: SIMULATOR:                 PLANT SITE:__________ LAB:________
LAB:_________________
TESTING METHOD: SIMULATE:___X______       PERFORM:___________
POSITION EVALUATED: RO:
APPROXIMATE COMPLETION TIME IN MINUTES:           20 MINUTES REFERENCE(S): 1107.004 EXAMINEE'S NAME:________________________________       SSN ______-_____-____________
X SRO:
X ACTUAL TESTING ENVIRONMENT: SIMULATOR:
PLANT SITE:__________ LAB:________
TESTING METHOD: SIMULATE:___X______
PERFORM:___________
APPROXIMATE COMPLETION TIME IN MINUTES:
20 MINUTES REFERENCE(S): 1107.004 EXAMINEE'S NAME:________________________________
SSN ______-_____-____________
EVALUATOR'S NAME:__________________________________________________________________
EVALUATOR'S NAME:__________________________________________________________________
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:
SATISFACTORY:________________               UNSATISFACTORY:_________________
SATISFACTORY:________________
UNSATISFACTORY:_________________
PERFORMANCE CHECKLIST COMMENTS:
PERFORMANCE CHECKLIST COMMENTS:
____________ Start Time       ____________ Stop Time       ____________ Total Time SIGNED ________________________________ DATE: _______________________
____________ Start Time
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.
____________ Stop Time
____________ Total Time SIGNED ________________________________ DATE: _______________________
SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.  


JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030                                                         Page 2 of 5 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:
JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030 Page 2 of 5 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:  
    &sect;  Battery Charger D-03A is in service on Bus D01.
 Battery Charger D-03A is in service on Bus D01.
INITIATING CUE:
INITIATING CUE:
The Shift Manager requests you to place Battery Charger D-03B in service on Bus D01 and remove Battery Charger D-03A from service per 1107.004, Battery and 125V DC Distribution, Attachment B.
The Shift Manager requests you to place Battery Charger D-03B in service on Bus D01 and remove Battery Charger D-03A from service per 1107.004, Battery and 125V DC Distribution, Attachment B.  


JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030                                                                   Page 3 of 5 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030 Page 3 of 5 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:
JPM INITIAL TASK CONDITIONS:
Line 1,144: Line 1,598:
TASK STANDARD: IAW 1107.004, Att. B, examinee places charger D-03B in service, removes D-03A from service, and performs actions for D-03A DC output voltage drifting to zero.
TASK STANDARD: IAW 1107.004, Att. B, examinee places charger D-03B in service, removes D-03A from service, and performs actions for D-03A DC output voltage drifting to zero.
THIS IS AN ALTERNATE SUCCESS PATH JPM.
THIS IS AN ALTERNATE SUCCESS PATH JPM.
TASK PERFORMANCE AIDS: 1107.0004 Attachment B
TASK PERFORMANCE AIDS: 1107.0004 Attachment B  


JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030                                                                               Page 4 of 5 INITIATING CUE:
JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030 Page 4 of 5 INITIATING CUE:
The Shift Manager requests you to place Battery Charger D-03B in service on Bus D01 and remove Battery Charger D-03A from service.
The Shift Manager requests you to place Battery Charger D-03B in service on Bus D01 and remove Battery Charger D-03A from service.
CRITICAL ELEMENTS (C)                   5, 6, 8, 9, 12, 14, 16 (C)         PERFORMANCE CHECKLIST                                 STANDARD                   N/A     SAT     UNSAT TRANSITION NOTE: Proceed to El. 372 in Auxiliary Building off Corridor 98 to Rm. 109, DC Equipment Room.
CRITICAL ELEMENTS (C) 5, 6, 8, 9, 12, 14, 16 (C)
: 1. Verify breakers open for charger         On front of charger D-03B, verified the D-03B.                                  AC Input and DC Output breakers
PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT TRANSITION NOTE: Proceed to El. 372 in Auxiliary Building off Corridor 98 to Rm. 109, DC Equipment Room.
* AC Input breaker                      open (OFF).                             _____  _____    _____
: 1. Verify breakers open for charger D-03B.
* DC Output breaker TRANSITION NOTE: Proceed to MCC B57 in South ES Switchgear Room on the same elevation.

: 2. Verify AC feeder breaker to charger       Verified breaker B-5733 closed (ON).
AC Input breaker
D-03B closed (B-5733).                                                           _____  _____    _____

DC Output breaker On front of charger D-03B, verified the AC Input and DC Output breakers open (OFF).
TRANSITION NOTE: Proceed to MCC B57 in South ES Switchgear Room on the same elevation.
: 2. Verify AC feeder breaker to charger D-03B closed (B-5733).
Verified breaker B-5733 closed (ON).
TRANSITION NOTE: Return to DC Equipment Room.
TRANSITION NOTE: Return to DC Equipment Room.
In the following step, Caution the examinee not to break plane of cubicle door.
In the following step, Caution the examinee not to break plane of cubicle door.
: 3. Verify charger D-03B supply to bus       Inside panel D01, verified breaker breaker closed (D01-42).                 D01-42 closed (ON).                     _____  _____    _____
: 3. Verify charger D-03B supply to bus breaker closed (D01-42).
: 4. Verify Manual Disconnect for battery     At D13, verified manual disconnect for  _____  _____    _____
Inside panel D01, verified breaker D01-42 closed (ON).
D-07 closed (D-13).                     battery D07 closed (ON).
: 4. Verify Manual Disconnect for battery D-07 closed (D-13).
(C)   5. Close D-03B AC Input breaker.             On front of charger D-03B, closed the   _____  _____    _____
At D13, verified manual disconnect for battery D07 closed (ON).
AC Input breaker (ON).
(C)
(C)   6. Close D-03B DC Output breaker.           On front of charger D-03B, closed the   _____  _____    _____
: 5. Close D-03B AC Input breaker.
DC Output breaker (ON).
On front of charger D-03B, closed the AC Input breaker (ON).
: 7. Wait ~1 minute for automatic load         Waited ~1 minute, observed rising      _____  _____    _____
(C)
sharing to occur.                       amps on D-03B and falling amps on D-03A.
: 6. Close D-03B DC Output breaker.
CUE:    Amps are rising on D-03B and amps are falling on D-03A.
On front of charger D-03B, closed the DC Output breaker (ON).
(C)   8. Open D-03A DC Output breaker.             On front of charger D-03A, opened       _____  _____    _____
: 7. Wait ~1 minute for automatic load sharing to occur.
the DC Output breaker (OFF).
CUE:
Amps are rising on D-03B and amps are falling on D-03A.
Waited ~1 minute, observed rising amps on D-03B and falling amps on D-03A.
(C)
: 8. Open D-03A DC Output breaker.
On front of charger D-03A, opened the DC Output breaker (OFF).  


JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030                                                                           Page 5 of 5 (C)       PERFORMANCE CHECKLIST                             STANDARD                   N/A       SAT     UNSAT (C)   9. Open D-03A AC Input breaker.         On front of charger D-03A, opened       _____    _____    _____
JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030 Page 5 of 5 (C)
the AC Input breaker (OFF).
PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT (C)
: 10. Check Charger D-03B picks up         At charger D-03B checked ammeter         _____    _____    _____
: 9. Open D-03A AC Input breaker.
load.                                deflected to a nominal value, and at D01 checked bus voltage maintained CUE:                                    at ~130 volts.
On front of charger D-03A, opened the AC Input breaker (OFF).
* D-03B DC Out ~100 amps
: 10. Check Charger D-03B picks up load.
* AC In ~30 amps
CUE:
* D01 bus voltage 130V

: 11. Reset local alarm panel for Charger At charger D-03B, pressed R button     _____    _____    _____
D-03B DC Out ~100 amps
D-03B.                              on RIS panel.

(C)   12. Place D-03B alarm to control room   At charger D-03B, placed control         _____    _____    _____
AC In ~30 amps
toggle switch ON.                    room alarm switch to ON (up).

: 13. Place D-03A alarm to control room   At charger D-03A, placed control         _____    _____    _____
D01 bus voltage 130V
toggle switch OFF.                  room alarm switch to OFF (down).

: 14. Check annunciator D01 CHARGER       Called control room and requested        _____    _____    _____
At charger D-03B checked ammeter deflected to a nominal value, and at D01 checked bus voltage maintained at ~130 volts.
TROUBLE (K01-E7) clears.             check for clear annunciator K01-E7.
: 11. Reset local alarm panel for Charger D-03B.
ALTERNATE PATH CUE:             Inform examinee that D-03A DC Output Voltage drifted to zero, also inform examinee that one minute has passed since D-03A was de-energized.
At charger D-03B, pressed R button on RIS panel.
(C)   15. Close D-03A AC Input breaker.       On front of charger D-03A, closed the   _____    _____    _____
(C)
AC Input breaker (ON).
: 12. Place D-03B alarm to control room toggle switch ON.
: 16. Check D-03A DC output voltage and   On charger D-03A, observed DC           _____    _____    _____
At charger D-03B, placed control room alarm switch to ON (up).
AC input voltage.                    output voltage and AC input voltage meters.
: 13. Place D-03A alarm to control room toggle switch OFF.
CUE:
At charger D-03A, placed control room alarm switch to OFF (down).
* DC Output Voltage ~90V          Examinee stated that he would
: 14. Check annunciator D01 CHARGER TROUBLE (K01-E7) clears.
* AC Input Voltage ~480V          contact electrical maintenance for support.
Called control room and requested check for clear annunciator K01-E7.
(C)   17. Open D-03A AC Input breaker.         On front of charger D-03A, opened       _____    _____    _____
ALTERNATE PATH CUE:
the AC Input breaker (OFF).
Inform examinee that D-03A DC Output Voltage drifted to zero, also inform examinee that one minute has passed since D-03A was de-energized.
: 18. Submit condition report and WR.     Examinee stated that he would submit     _____    _____    _____
(C)
a condition report and Work Request or Work Order on D-03A.
: 15. Close D-03A AC Input breaker.
END
On front of charger D-03A, closed the AC Input breaker (ON).
: 16. Check D-03A DC output voltage and AC input voltage.
CUE:

DC Output Voltage ~90V

AC Input Voltage ~480V On charger D-03A, observed DC output voltage and AC input voltage meters.
Examinee stated that he would contact electrical maintenance for support.
(C)
: 17. Open D-03A AC Input breaker.
On front of charger D-03A, opened the AC Input breaker (OFF).
: 18. Submit condition report and WR.
Examinee stated that he would submit a condition report and Work Request or Work Order on D-03A.
END  


TUOI NUMBER:                                                                                                     Page 1 of 6 A1JPM-RO-AOP08 JOB PERFORMANCE MEASURE Unit:               1             Rev #                         4                         Date:       11/04/2003 TUOI NUMBER:           A1JPM-RO- AOP08 System/Duty Area:     Emergency and Abnormal Operations Task:     RO #1 Duties for Alternate Shutdown with immediate Control Room evacuation JA#       13035210401 KA Value RO       4.3       SRO     4.2   KA Reference       A06.AA1.1 Approved For Administration To: RO                               SRO Task Location: Inside CR:                         Outside CR:                       Both:
TUOI NUMBER:
Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:     Perform         Simulator:                                       Lab:
A1JPM-RO-AOP08 Page 1 of 6 JOB PERFORMANCE MEASURE Unit:
Position Evaluated: RO:                       X                             SRO:                     X Actual Testing Environment: Simulator:                           Plant Site:                     Lab Testing Method: Simulate:                     X                         Perform:
1 Rev #
Approximate Completion Time In Minutes:                                       20 Minutes Reference(S):       OP 1203.002 change 015-05-0 Examinee's Name:                                                                   SSN:
4 Date:
11/04/2003 TUOI NUMBER:
A1JPM-RO-AOP08 System/Duty Area:
Emergency and Abnormal Operations Task:
RO #1 Duties for Alternate Shutdown with immediate Control Room evacuation JA#
13035210401 KA Value RO 4.3 SRO 4.2 KA Reference A06.AA1.1 Approved For Administration To: RO SRO Task Location: Inside CR:
Outside CR:
Both:
Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:
Perform Simulator:
Lab:
Position Evaluated: RO:
X SRO:
X Actual Testing Environment: Simulator:
Plant Site:
Lab Testing Method: Simulate:
X Perform:
Approximate Completion Time In Minutes:
20 Minutes Reference(S):
OP 1203.002 change 015-05-0 Examinee's Name:
SSN:
Evaluator's Name:
Evaluator's Name:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
Satisfactory:                                       Unsatisfactory:
Satisfactory:
Unsatisfactory:
Performance Checklist Comments:
Performance Checklist Comments:
Start Time                                 Stop Time                                       Total Time Signed                                                               Date:
Start Time Stop Time Total Time Signed Date:
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.  


TUOI NUMBER:                                                                                     Page 2 of 6 A1JPM-RO-AOP08 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:
A1JPM-RO-AOP08 Page 2 of 6 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:
JPM INITIAL TASK CONDITIONS:
Line 1,218: Line 1,716:
OP 1203.002 and Section 1C, change 015-05-0.
OP 1203.002 and Section 1C, change 015-05-0.
SIMULATOR SETUP:
SIMULATOR SETUP:
N/A
N/A  


TUOI NUMBER:                                                                                         Page 3 of 6 A1JPM-RO-AOP08 INITIATING CUE: The first 3 steps of OP 1203.002 Section 1C have been completed. Perform the actions required of RO
TUOI NUMBER:
A1JPM-RO-AOP08 Page 3 of 6 INITIATING CUE: The first 3 steps of OP 1203.002 Section 1C have been completed. Perform the actions required of RO  
#1 through step 3.14.
#1 through step 3.14.
CRITICAL ELEMENTS (c): 1, 7, 9, 11, 12, and 13 C                 PERFORMANCE CHECKLIST                               STANDARD               N/A   SAT     UN SAT C   1. At The MSIV's, open the instrument air vent      Opened instrument air vent valves for each MSIV (IA-2691B through E and    valves IA-2691B through E and IA-2692B through E).                             IA-2692B through E.              ____    ____    ___
CRITICAL ELEMENTS (c): 1, 7, 9, 11, 12, and 13 C
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT C
: 1.
At The MSIV's, open the instrument air vent valves for each MSIV (IA-2691B through E and IA-2692B through E).
POSITIVE CUE:
POSITIVE CUE:
All 8 vent valves have stem full out, with each valves handwheel fully CW.
All 8 vent valves have stem full out, with each valves handwheel fully CW.
: 2. Verify CV-2667 open.                             CV-2667 verified open by visually observing stem or valve position POSITIVE CUE:                                           indicator.                        ____    ____    ___
Opened instrument air vent valves IA-2691B through E and IA-2692B through E.
: 2.
Verify CV-2667 open.
POSITIVE CUE:
CV-2667 has stem full out, with the valve handwheel fully CW.
CV-2667 has stem full out, with the valve handwheel fully CW.
: 3.      Verify CV-2617 open.                            CV-2617 verified open by visually observing stem or valve position POSITIVE CUE:                                           indicator.                        ____    ____    ___
CV-2667 verified open by visually observing stem or valve position indicator.
: 3.
Verify CV-2617 open.
POSITIVE CUE:
CV-2617 has stem full out, with the valve handwheel fully CW.
CV-2617 has stem full out, with the valve handwheel fully CW.
: 4.      Verify CV-2663 open.                            CV-2663 verified open by visually observing stem or valve position POSITIVE CUE:                                           indicator.                        ____    ____    ___
CV-2617 verified open by visually observing stem or valve position indicator.
: 4.
Verify CV-2663 open.
POSITIVE CUE:
CV-2663 has stem full out, with the valve handwheel fully CW.
CV-2663 has stem full out, with the valve handwheel fully CW.
: 5.      Verify CV-2613 open.                            CV-2613 verified open by visually observing stem or valve position POSITIVE CUE:                                           indicator.                        ____    ____    ___
CV-2663 verified open by visually observing stem or valve position indicator.
: 5.
Verify CV-2613 open.
POSITIVE CUE:
CV-2613 has stem full out, with the valve handwheel fully CW.
CV-2613 has stem full out, with the valve handwheel fully CW.
: 6.       Notify TSC of completion                       Communicated via phone or radio the Completion of Item 1.A       ____    ____    ___
CV-2613 verified open by visually observing stem or valve position indicator.
POSITIVE CUE:
: 6.
TSC notified of completion of actions EXAMINERS NOTE: The examinee should proceed to the Auxiliary Building 354 elevation.
Notify TSC of completion POSITIVE CUE:
C     7.       Proceed to Aux Bldg, 354. Slowly open CV-     Used manual lever and 1407 manually                                 handwheel, fully opened CV-      ____    ____    ___
TSC notified of completion of actions Communicated via phone or radio the Completion of Item 1.A EXAMINERS NOTE: The examinee should proceed to the Auxiliary Building 354 elevation.
1407.
C
POSITIVE CUE:
: 7.
Proceed to Aux Bldg, 354. Slowly open CV-1407 manually POSITIVE CUE:
Valve has stem full out, with the valve handwheel fully CW.
Valve has stem full out, with the valve handwheel fully CW.
Used manual lever and handwheel, fully opened CV-1407.


TUOI NUMBER:                                                                                         Page 4 of 6 A1JPM-RO-AOP08 C                 PERFORMANCE CHECKLIST                                 STANDARD               N/A   SAT     UN SAT
TUOI NUMBER:
: 8.       Check for flow noise as CV-1407 is opened.       Checked for flow noise as CV-1407 was opened.                ____  ____    ___
A1JPM-RO-AOP08 Page 4 of 6 C
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT
: 8.
Check for flow noise as CV-1407 is opened.
POSITIVE CUE:
POSITIVE CUE:
No flow noise is heard.
No flow noise is heard.
Checked for flow noise as CV-1407 was opened.
EXAMINERS NOTE: The examinee should proceed to the UNPPR.
EXAMINERS NOTE: The examinee should proceed to the UNPPR.
C   9.       Manually open CV-1219 and CV-1220. Close         Opened CV-1219, CV-1220, CV-1206                                           closed CV-1206 with manual      ____  ____    ___
C
lever and handwheel, verified POSITIVE CUE:                                             valve movement CV1219 and CV1220 have stems full out, with the valves handwheels fully CW, CV1206 has stem full in, with the valve handwheel fully CCW.
: 9.
: 10.     Notify TSC of completion                         Established communication with TSC telephone or radio, notified ____  ____    ___
Manually open CV-1219 and CV-1220. Close CV-1206 POSITIVE CUE:
POSITIVE CUE:                                              of action HPI Item 5.A, 5.B, TSC notified of completion of actions EXAMINERS NOTE:
CV1219 and CV1220 have stems full out, with the valves handwheels fully CW, CV1206 has stem full in, with the valve handwheel fully CCW.
Opened CV-1219, CV-1220, closed CV-1206 with manual lever and handwheel, verified valve movement
: 10.
Notify TSC of completion POSITIVE CUE:
TSC notified of completion of actions Established communication with TSC telephone or radio, notified of action HPI Item 5.A, 5.B, EXAMINERS NOTE:
When TSC is notified have examinee throttle EFW P-7A to SG-A ISOL, CV-2627 to approximately 50 % open.
When TSC is notified have examinee throttle EFW P-7A to SG-A ISOL, CV-2627 to approximately 50 % open.
C
C
: 11.     Close CV-2627 to approximately 50% open.         Moved to CV-2627, and used the manual lever and hand wheel to   ____  ____    ___
: 11.
POSITIVE CUE:                                              close CV-2627 to approximately CV-2627 has stem approximately halfway out.                to 50% open.
Close CV-2627 to approximately 50% open.
EXAMINERS NOTE:         Inform examinee that EFW flow is controlled.
POSITIVE CUE:
C   12.     Open valves:                                     Opened EFW P-7B to SG-A ISOL EFW P-7B to SG-A ISOL (CV-2670)                   (CV-2670), B HPI Block Valve  ____  ____    ___
CV-2627 has stem approximately halfway out.
B HPI Block Valve (CV-1227)                     (CV-1227), and A HPI Block A HPI Block Valve (CV1228)                     Valve (CV1228) using manual handwheel and clutch lever.
Moved to CV-2627, and used the manual lever and hand wheel to close CV-2627 to approximately to 50% open.
EXAMINERS NOTE:
Inform examinee that EFW flow is controlled.
C
: 12.
Open valves:
EFW P-7B to SG-A ISOL (CV-2670)
B HPI Block Valve (CV-1227)
A HPI Block Valve (CV1228)
POSITIVE CUE:
POSITIVE CUE:
CV-2670, CV-1227, CV-1228 have stems full out, with each valves handwheel fully CW.
CV-2670, CV-1227, CV-1228 have stems full out, with each valves handwheel fully CW.
Opened EFW P-7B to SG-A ISOL (CV-2670), B HPI Block Valve (CV-1227), and A HPI Block Valve (CV1228) using manual handwheel and clutch lever.
TRANSITION NOTE: The examinee should proceed to the 354 elevation waste gas room.
TRANSITION NOTE: The examinee should proceed to the 354 elevation waste gas room.
C   13.     Slowly open BWST Outlet CV-1408.                 Opened CV-1408 using clutch lever and manual handwheel.      ____  ____    ___
C
: 13.
Slowly open BWST Outlet CV-1408.
POSITIVE CUE:
POSITIVE CUE:
CV-1408 has stem full out, with the valve handwheel fully CW.
CV-1408 has stem full out, with the valve handwheel fully CW.
Opened CV-1408 using clutch lever and manual handwheel.


TUOI NUMBER:                                                                                       Page 5 of 6 A1JPM-RO-AOP08 C                 PERFORMANCE CHECKLIST                                   STANDARD             N/A   SAT     UN SAT
TUOI NUMBER:
: 14.     Check for flow noise as CV-1408 is opened.       Checked for flow noise as CV1408 was opened.              ____  ____    ___
A1JPM-RO-AOP08 Page 5 of 6 C
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT
: 14.
Check for flow noise as CV-1408 is opened.
POSITIVE CUE:
POSITIVE CUE:
No flow noise is heard.
No flow noise is heard.
Checked for flow noise as CV1408 was opened.
TRANSITION NOTE: The examinee should proceed to the 335 elevation letdown filter area.
TRANSITION NOTE: The examinee should proceed to the 335 elevation letdown filter area.
: 15.     Verify service water header pressure >40 psig. Opened RB Coolers VCC-2C &
: 15.
2D PI-3813A ISOL SW-3813A        ____  ____    ___
Verify service water header pressure >40 psig.
POSITIVE CUE:                                             and verified pressure >40 psig.
POSITIVE CUE:
Service water pressure is 50 psig.
Service water pressure is 50 psig.
NEGATIVE CUE:
NEGATIVE CUE:
Service water pressure is 0 psig.
Service water pressure is 0 psig.
: 16.     Establish communications with the TSC and       Operator Calls TSC via radio or report completion of steps.                     telephone and reports completion of steps 2.B, 6.A, 6.B, 7.B. ____  ____    ___
Opened RB Coolers VCC-2C &
2D PI-3813A ISOL SW-3813A and verified pressure >40 psig.
: 16.
Establish communications with the TSC and report completion of steps.
POSITIVE CUE:
POSITIVE CUE:
All steps have been reported to TSC.
All steps have been reported to TSC.
Line 1,284: Line 1,827:
Step 9. A OTSG level is going up rapidly.
Step 9. A OTSG level is going up rapidly.
Step 7, 10b or c, 11. Unable to establish HPI flow.
Step 7, 10b or c, 11. Unable to establish HPI flow.
Operator Calls TSC via radio or telephone and reports completion of steps 2.B, 6.A, 6.B, 7.B.
INSTRUCTOR CUE: This concludes the JPM.
INSTRUCTOR CUE: This concludes the JPM.
END
END  


TUOI NUMBER:                                                                                     Page 6 of 6 A1JPM-RO-AOP08 EXAMINEES COPY INITIAL CONDITIONS:
TUOI NUMBER:
A1JPM-RO-AOP08 Page 6 of 6 EXAMINEES COPY INITIAL CONDITIONS:
There is a Fire in the Cable Spreading Room. An Alternate Shutdown is in progress. At the Alternate Shutdown Cabinet, you have received a copy of OP 1203.002 and Section 1C.
There is a Fire in the Cable Spreading Room. An Alternate Shutdown is in progress. At the Alternate Shutdown Cabinet, you have received a copy of OP 1203.002 and Section 1C.
INITIATING CUE:
INITIATING CUE:
The first 3 steps of OP 1203.002 Section 1C have been completed. Perform the actions required of RO #1 through step 3.14.
The first 3 steps of OP 1203.002 Section 1C have been completed. Perform the actions required of RO #1 through step 3.14.  


TUOI NUMBER:                                                                                                           Page 1 of 5 A1JPM-RO-EFW01 JOB PERFORMANCE MEASURE Unit:               1               Rev #                       10                         Date:         11/04/2003 TUOI NUMBER:           A1JPM-RO- EFW01 System/Duty Area:       Emergency Feedwater and EFIC Task:     Reset the Steam Driven Emergency Feedwater Pump after an overspeed trip JA#       ANO1-RO-EFW-NORM-13 KA Value RO       3.4       SRO     3.8     KA Reference       061 A2.04 Approved For Administration To: RO                               SRO Task Location: Inside CR:                           Outside CR:                       Both:
TUOI NUMBER:
Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:     Perform         Simulator:                                         Lab:
Page 1 of 5 A1JPM-RO-EFW01 JOB PERFORMANCE MEASURE Unit:
Position Evaluated: RO:                         X                             SRO:                     X Actual Testing Environment: Simulator:                             Plant Site:                     Lab Testing Method: Simulate:                       X                       Perform:
1 Rev #
Approximate Completion Time In Minutes:                                         15 Minutes Reference(S):       1106.006 Exhibit A, change 063-08-0.
10 Date:
Examinee's Name:                                                                     SSN:
11/04/2003 TUOI NUMBER:
A1JPM-RO-EFW01 System/Duty Area:
Emergency Feedwater and EFIC Task:
Reset the Steam Driven Emergency Feedwater Pump after an overspeed trip JA#
ANO1-RO-EFW-NORM-13 KA Value RO 3.4 SRO 3.8 KA Reference 061 A2.04 Approved For Administration To: RO SRO Task Location: Inside CR:
Outside CR:
Both:
Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:
Perform Simulator:
Lab:
Position Evaluated: RO:
X SRO:
X Actual Testing Environment: Simulator:
Plant Site:
Lab Testing Method: Simulate:
X Perform:
Approximate Completion Time In Minutes:
15 Minutes Reference(S):
1106.006 Exhibit A, change 063-08-0.
Examinee's Name:
SSN:
Evaluator's Name:
Evaluator's Name:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:
Satisfactory:                                       Unsatisfactory:
Satisfactory:
Unsatisfactory:
Performance Checklist Comments:
Performance Checklist Comments:
Start Time                                     Stop Time                                     Total Time Signed                                                               Date:
Start Time Stop Time Total Time Signed Date:
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.
Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.  


TUOI NUMBER:                                                                                   Page 2 of 5 A1JPM-RO-EFW01 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
TUOI NUMBER:
Page 2 of 5 A1JPM-RO-EFW01 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.
JPM INITIAL TASK CONDITIONS:
JPM INITIAL TASK CONDITIONS:
Line 1,313: Line 1,880:
OP 1106.006 Exhibit A, change 063-08-0.
OP 1106.006 Exhibit A, change 063-08-0.
SIMULATOR SETUP:
SIMULATOR SETUP:
N/A
N/A  


TUOI NUMBER:                                                                                             Page 3 of 5 A1JPM-RO-EFW01 INITIATING CUE: The SM/CRS directs you to reset P7A overspeed trip per 1106.006, Exhibit A.
TUOI NUMBER:
CRITICAL ELEMENTS (c): 2, 3, and 8 C                 PERFORMANCE CHECKLIST                                     STANDARD             N/A SAT     UN SAT EXAMINERS NOTE: Simulate communications with the Control Room.
Page 3 of 5 A1JPM-RO-EFW01 INITIATING CUE: The SM/CRS directs you to reset P7A overspeed trip per 1106.006, Exhibit A.
: 1. Verify the following valves are closed. If EFW           Called control room to verify SV-initiate signal is present, manual control is required. 2613, SV-2663, CV-2613, CV-
CRITICAL ELEMENTS (c): 2, 3, and 8 C
* EFW Pump Turbine K3 Steam Admission                   2663 are closed.
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT EXAMINERS NOTE: Simulate communications with the Control Room.
Valves (CV-2613 and CV-2663)
: 1. Verify the following valves are closed. If EFW initiate signal is present, manual control is required.  
* EFW Pump Turbine K3 Steam Admission                                                     ____ ____    ____

Valve Bypasses (SV-2613 and SV-2663)
EFW Pump Turbine K3 Steam Admission Valves (CV-2613 and CV-2663)  

EFW Pump Turbine K3 Steam Admission Valve Bypasses (SV-2613 and SV-2663)
POSITIVE CUE:
POSITIVE CUE:
SV-2613, SV-2663, CV-2613, CV-2663 have valve stems full out with handwheels full CW.
SV-2613, SV-2663, CV-2613, CV-2663 have valve stems full out with handwheels full CW.
C   2. Turn EFW Turbine K3 Trip-Throttle Valve (CV-             Trip/ Throttle valve (CV-6601A) 6601A) handwheel clockwise. Observe rotation of       handwheel turned clockwise until screw raises sliding nut and latch lever to where it   sliding nut rises and latch lever will engage the trip hook.                             engages the trip hook.            ____ ____    ___
Called control room to verify SV-2613, SV-2663, CV-2613, CV-2663 are closed.
C
: 2. Turn EFW Turbine K3 Trip-Throttle Valve (CV-6601A) handwheel clockwise. Observe rotation of screw raises sliding nut and latch lever to where it will engage the trip hook.
POSITIVE CUE:
POSITIVE CUE:
Trip/ Throttle valve (CV-6601A) sliding nut raised and latch lever has engaged the trip hook.
Trip/ Throttle valve (CV-6601A) sliding nut raised and latch lever has engaged the trip hook.
Trip/ Throttle valve (CV-6601A) handwheel turned clockwise until sliding nut rises and latch lever engages the trip hook.
EXAMINERS NOTE: The following steps will reset the mechanical trip linkage.
EXAMINERS NOTE: The following steps will reset the mechanical trip linkage.
C   3. Pull spring-loaded connecting rod against spring         Connecting rod pulled against force to move head lever away from tappet and          spring force to move head lever  ____ ____    ___
C
tappet nut.                                            away from tappet and tappet nut.
: 3. Pull spring-loaded connecting rod against spring force to move head lever away from tappet and tappet nut.
POSITIVE CUE:
POSITIVE CUE:
Head lever moved away from tappet and tappet nut.
Head lever moved away from tappet and tappet nut.
: 4. Lift and release tappet assembly                         Tappet assembly lifted and released.                         ____ ____    ___
Connecting rod pulled against spring force to move head lever away from tappet and tappet nut.
POSITIVE CUE:
: 4. Lift and release tappet assembly POSITIVE CUE:
Tappet assembly lifted and released.
Tappet assembly lifted and released.
Tappet assembly lifted and released.
: 5. Verify tappet nut in trip reset position.               Verified tappet nut in trip reset position.                        ____ ____    ___
: 5. Verify tappet nut in trip reset position.
POSITIVE CUE:
POSITIVE CUE:
Tappet nut in trip reset position.
Tappet nut in trip reset position.
Verified tappet nut in trip reset position.


TUOI NUMBER:                                                                                             Page 4 of 5 A1JPM-RO-EFW01 C                 PERFORMANCE CHECKLIST                                     STANDARD               N/A SAT     UN SAT
TUOI NUMBER:
: 6. Observe tappet returns to reset position.               Observed tappet returns to reset position.                          ____ ____    ___
Page 4 of 5 A1JPM-RO-EFW01 C
PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT
: 6. Observe tappet returns to reset position.
POSITIVE CUE:
POSITIVE CUE:
Tappet is in reset position.
Tappet is in reset position.
: 7. Verify the following:                                   Verified tappet nut in trip reset
Observed tappet returns to reset position.
* Tappet nut in trip reset position and properly      position and properly aligned. ____ ____    ___
: 7. Verify the following:  
aligned.                                            Verified spring tension holds

* Spring tension holds connecting rod in position. connecting rod in position.

Tappet nut in trip reset position and properly aligned.
Spring tension holds connecting rod in position.
POSITIVE CUE:
POSITIVE CUE:
Tappet nut in trip reset position and properly aligned.
Tappet nut in trip reset position and properly aligned.
Spring tension is holding connecting rod in position.
Spring tension is holding connecting rod in position.
C   8. Slowly turn CV-6601A handwheel                           CV-6601A fully opened.
Verified tappet nut in trip reset position and properly aligned.
counterclockwise until valve is fully open.                                               ____ ____    ___
Verified spring tension holds connecting rod in position.
C
: 8. Slowly turn CV-6601A handwheel counterclockwise until valve is fully open.
POSITIVE CUE:
POSITIVE CUE:
CV-6601A has valve stem full out with handwheel in the full CW position.
CV-6601A has valve stem full out with handwheel in the full CW position.
: 9. Close valve (CV-6601A) 3/4 turn to prevent binding       CV-6601A closed 3/4 turn.
CV-6601A fully opened.
on heatup.                                                                               ____ ____    ___
: 9. Close valve (CV-6601A) 3/4 turn to prevent binding on heatup.
POSITIVE CUE:
POSITIVE CUE:
CV-6601A as you see it.
CV-6601A as you see it.
CV-6601A closed 3/4 turn.
EXAMINERS NOTE: Simulate communications with the Control Room.
EXAMINERS NOTE: Simulate communications with the Control Room.
: 10. Verify P-7A TURBINE TRIP (K12-B5) clear.               Call Control Room and verified that P-7A TURBINE TRIP (K12-       ____ ____    ___
: 10. Verify P-7A TURBINE TRIP (K12-B5) clear.
POSITIVE CUE:                                              B5) is clear.
POSITIVE CUE:
P-7A TURBINE TRIP (K12-B5) clear
P-7A TURBINE TRIP (K12-B5) clear Call Control Room and verified that P-7A TURBINE TRIP (K12-B5) is clear.
: 11. Notify Control Room that P-7A is ready for restart. Control Room notified that P-7A is ready for restart.                ____ ____    ___
: 11. Notify Control Room that P-7A is ready for restart.
POSITIVE CUE:
POSITIVE CUE:
Control Room notified that P-7A is ready for restart.
Control Room notified that P-7A is ready for restart.
Control Room notified that P-7A is ready for restart.
EXAMINERS CUE: This concludes the JPM.
EXAMINERS CUE: This concludes the JPM.
END
END  


TUOI NUMBER:                                                                   Page 5 of 5 A1JPM-RO-EFW01 EXAMINEES COPY INITIAL CONDITIONS:
TUOI NUMBER:
A1JPM-RO-EFW01 Page 5 of 5 EXAMINEES COPY INITIAL CONDITIONS:
P7A Emergency Feedwater Pump has tripped on overspeed during an EFIC actuation.
P7A Emergency Feedwater Pump has tripped on overspeed during an EFIC actuation.
INITIATING CUE:
INITIATING CUE:
The SM/CRS directs you to reset P7A overspeed trip per 1106.006, Exhibit A.
The SM/CRS directs you to reset P7A overspeed trip per 1106.006, Exhibit A.  


Appendix D                   Operator Actions                   Form ES-D-1 Facility: ANO-1                   Scenario No.: 1 (NEW)                     Op-Test No.: 2004-1 Page 1 of 10 Examiners:                                                         Operators:
Appendix D Operator Actions Form ES-D-1 Facility: ANO-1 Scenario No.: 1 (NEW) Op-Test No.: 2004-1 Page 1 of 10 Examiners:
Operators:
Initial Conditions:
Initial Conditions:
100% MOL; Severe Thunderstorm Warning for Pope and Conway counties.
100% MOL; Severe Thunderstorm Warning for Pope and Conway counties.
Turnover::
Turnover::
National Weather service has issued a Severe Thunderstorm Warning for Pope and Conway Counties until 8:00 pm today. AOP 1203.025, Natural Emergencies, Section 2, High Winds/Tornado/Thunderstorm, steps 3.1 and 3.2 have been completed. #2 EDG OOS for fuel leak repairs. 1104.036 Supplement 11 is due right after turn-over.
National Weather service has issued a Severe Thunderstorm Warning for Pope and Conway Counties until 8:00 pm today. AOP 1203.025, Natural Emergencies, Section 2, High Winds/Tornado/Thunderstorm, steps 3.1 and 3.2 have been completed. #2 EDG OOS for fuel leak repairs. 1104.036 Supplement 11 is due right after turn-over.
Event         Malf. No.       Event                                 Event No.                          Type*                             Description 1             N/A         N (ALL)     Perform 1104.036 Supplement 11 for EDG #1 2           TR568         I (BOR)     A OTSG operating level transmitter fails high 3         CAE RX7460       I (BOT)     RB atmosphere radioactivity monitor fails low. TS 3.4.15 determination.
Event No.
4             N/A         R (BOR)     Dispatcher orders down power to 650 MWe due to weather that has damaged Mablevale sub-station.
Malf. No.
5           RX150         I (BOT)     Turbine EHC fails to respond in auto mode for ICS (manual control required) 6           CV2692         C (BOR)     One MSIV for B OTSG drifts shut-requires manual reactor trip per EOP 1202.001 7           MS131         M (ALL)     A OTSG steam leak in containment (MSLI activates). Transfer to 1202.003 overcooling if necessary.
Event Type*
8           ES264         I (BOT)     Containment pressure >4psig but B train RBIC CV2214                    will fail to actuate automatically and an ICW isolation valve will fail open that should shut.
Event Description 1
Operator will be required to manually initiate B RBIC and verify shut the redundant ICW valve to isolate ICW.
N/A N (ALL)
* (N)ormal,     (R)eactivity, (I)nstrument, (C)omponent,       (M)ajor
Perform 1104.036 Supplement 11 for EDG #1 2
TR568 I (BOR)
A OTSG operating level transmitter fails high 3
CAE RX7460 I (BOT)
RB atmosphere radioactivity monitor fails low. TS 3.4.15 determination.
4 N/A R (BOR)
Dispatcher orders down power to 650 MWe due to weather that has damaged Mablevale sub-station.
5 RX150 I (BOT)
Turbine EHC fails to respond in auto mode for ICS (manual control required) 6 CV2692 C (BOR)
One MSIV for B OTSG drifts shut-requires manual reactor trip per EOP 1202.001 7
MS131 M (ALL)
A OTSG steam leak in containment (MSLI activates). Transfer to 1202.003 overcooling if necessary.
8 ES264 CV2214 I (BOT)
Containment pressure >4psig but B train RBIC will fail to actuate automatically and an ICW isolation valve will fail open that should shut.
Operator will be required to manually initiate B RBIC and verify shut the redundant ICW valve to isolate ICW.  
* (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor  


Appendix D             Operator Actions                     Form ES-D-1 Page 2 of 10 Event Time     Malf. No. Value/Ramp                             Event No.                      Time                                Description 8     T=0     IMF ES264       N/A     B Train of Reactor Bldg. Isolation and Cooling fails to auto actuate (ESAS channel 6)
Appendix D Operator Actions Form ES-D-1 Page 2 of 10 Event No.
IMF CV2214        1      ICW valve CV2214 fails to close upon ESAS actuation 1     T=0         N/A           N/A     Perform surveillance test of the #1 EDG for operability due to maintenance of #2 EDG.
Time Malf. No.
2   T=~15     IMF TR568 292 / Ramp 3   A OTSG Operating Range Level Transmitter Min.      fails high.
Value/Ramp Time Event Description 8
3     T=20   CAE RX7460         N/A     RB Sump Radiation Monitor fails low (RX7460) 4     T=25       N/A           N/A     The dispatcher requests an emergency power reduction to ~650 MWe to maintain system integrity.
T=0 IMF ES264 IMF CV2214 N/A 1
5   T=25.5   IMF RX150       N/A     Turbine EHC fails to respond.
B Train of Reactor Bldg. Isolation and Cooling fails to auto actuate (ESAS channel 6)
6     T=30   IMF CV2692 0 / Ramp 1 Min. B MSIV drifts shut requiring manual reactor trip.
ICW valve CV2214 fails to close upon ESAS actuation 1
7     T=35     IMF MS131 .4 / Ramp 3Min. A OTSG Main Steam Line Leak inside containment.
T=0 N/A N/A Perform surveillance test of the #1 EDG for operability due to maintenance of #2 EDG.
2 T=~15 IMF TR568 292 / Ramp 3 Min.
A OTSG Operating Range Level Transmitter fails high.
3 T=20 CAE RX7460 N/A RB Sump Radiation Monitor fails low (RX7460) 4 T=25 N/A N/A The dispatcher requests an emergency power reduction to ~650 MWe to maintain system integrity.
5 T=25.5 IMF RX150 N/A Turbine EHC fails to respond.
6 T=30 IMF CV2692 0 / Ramp 1 Min.
B MSIV drifts shut requiring manual reactor trip.
7 T=35 IMF MS131  
.4 / Ramp 3Min.
A OTSG Main Steam Line Leak inside containment.  


Appendix D                     Operator Actions                       Form ES-D-2 Op-Test No: 2004-1         Scenario No: 1             Event No: 1                         Page 3 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 1 Page 3 of 10 Event


== Description:==
== Description:==
Perform surveillance test of the #1 EDG for operability due to maintenance of #2 EDG.
Perform surveillance test of the #1 EDG for operability due to maintenance of #2 EDG.
Time   Position                                 Applicants Actions or Behavior T=0     CRS       Directs the performance of the #1 EDG surveillance test per Supplement 11 of 1104.036.
Time Position Applicants Actions or Behavior T=0 CRS Directs the performance of the #1 EDG surveillance test per Supplement 11 of 1104.036.
CBOT     Make plant announcement of the starting of #1 EDG.
CBOT Make plant announcement of the starting of #1 EDG.
CBOT     Verify DG1 Volts Select switch NOT in OFF on C10.
CBOT Verify DG1 Volts Select switch NOT in OFF on C10.
CBOT     Simultaneously depress the START pushbutton for #1 EDG and start the stopwatch.
CBOT Simultaneously depress the START pushbutton for #1 EDG and start the stopwatch.
CBOT     Stop the stopwatch when DG1 voltage exceeds 3750 volts.
CBOT Stop the stopwatch when DG1 voltage exceeds 3750 volts.
CBOT     Record the time from start to >3750 volts in section 3.0.
CBOT Record the time from start to >3750 volts in section 3.0.
CBOT     Verify service water to DG1 coolers (CV3806) opens and record verification in section 3.0.
CBOT Verify service water to DG1 coolers (CV3806) opens and record verification in section 3.0.
CBOT     Adjust the voltage and frequency within the acceptable operating bands.
CBOT Adjust the voltage and frequency within the acceptable operating bands.
CBOT     Stop DG1 by depressing the STOP pushbutton.
CBOT Stop DG1 by depressing the STOP pushbutton.
CBOT     Verify associated critical and non-critical alarms on K01 clear.
CBOT Verify associated critical and non-critical alarms on K01 clear.
EVENT TERMINATION CRITERIA
EVENT TERMINATION CRITERIA  
                                    #1 EDG is stopped or Next Event
#1 EDG is stopped or Next Event  


Appendix D                       Operator Actions                     Form ES-D-2 Op-Test No: 2004-1         Scenario No: 1             Event No: 2                             Page 4 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 2 Page 4 of 10 Event


== Description:==
== Description:==
A OTSG Operating Range Level Transmitter fails high.
A OTSG Operating Range Level Transmitter fails high.
Time   Position                                 Applicants Actions or Behavior T=15   CBOR       Acknowledge and report annunciator K07 B4, SASS MISMATCH.
Time Position Applicants Actions or Behavior T=15 CBOR Acknowledge and report annunciator K07 B4, SASS MISMATCH.
CRS       Obtain Annunciator Corrective Action for K07 B4 for guidance.
CRS Obtain Annunciator Corrective Action for K07 B4 for guidance.
CBOR       Acknowledge and report annunciator K07 A2, A OTSG Hi Level Limit.
CBOR Acknowledge and report annunciator K07 A2, A OTSG Hi Level Limit.
CRS       Obtain Annunciator Corrective Action for K07 A2 for guidance.
CRS Obtain Annunciator Corrective Action for K07 A2 for guidance.
CBOT     Observe/verify A Operating range level on C13 level recorder.
CBOT Observe/verify A Operating range level on C13 level recorder.
CRS       Direct the CBOR to place the A feed pump H/A station in HAND and stabilize plant.
CRS Direct the CBOR to place the A feed pump H/A station in HAND and stabilize plant.
CBOR       Place the A main feed pump H/A station in HAND and balanced feed flows.
CBOR Place the A main feed pump H/A station in HAND and balanced feed flows.
CRS       Direct board operators to validate level transmitters by comparing to other (redundant) instruments.
CRS Direct board operators to validate level transmitters by comparing to other (redundant) instruments.
CBOT/R     Determine the A OTSG operating level transmitter is failing high.
CBOT/R Determine the A OTSG operating level transmitter is failing high.
CRS       Verify plant stable and ICS in condition for instrument swap and direct the CBOR to select the other instrument.
CRS Verify plant stable and ICS in condition for instrument swap and direct the CBOR to select the other instrument.
CBOT     Verify the Operating Range Level for A is indicating properly on C13.
CBOT Verify the Operating Range Level for A is indicating properly on C13.
CRS       Direct placing ICS (A feed pump H/A station) back to AUTO EVENT TERMINATION CRITERIA ICS in AUTO or next event
CRS Direct placing ICS (A feed pump H/A station) back to AUTO EVENT TERMINATION CRITERIA ICS in AUTO or next event  


Appendix D                       Operator Actions                     Form ES-D-2 Op-Test No: 2004-1         Scenario No: 1             Event No: 3                     Page 5 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 3 Page 5 of 10 Event


== Description:==
== Description:==
RB atmosphere radioactivity monitor fails low.
RB atmosphere radioactivity monitor fails low.
Time   Position                                 Applicants Actions or Behavior T=20   CBOR       Acknowledge and report annunciator K10 C1, Radiation Monitor Trouble.
Time Position Applicants Actions or Behavior T=20 CBOR Acknowledge and report annunciator K10 C1, Radiation Monitor Trouble.
CBOT     Observe monitors at C24 and C25 and determine that RX7460 has FAILURE lights ON and BOTH monitors, RI7460 and RI7461, are reading 0 CPM.
CBOT Observe monitors at C24 and C25 and determine that RX7460 has FAILURE lights ON and BOTH monitors, RI7460 and RI7461, are reading 0 CPM.
CRS       Refer to ACA 1203.012I for corrective action and guidance.
CRS Refer to ACA 1203.012I for corrective action and guidance.
CRS       Determine RB Atmosphere Gaseous Monitor is inoperable and refer to Tech Spec 3.4.15B.
CRS Determine RB Atmosphere Gaseous Monitor is inoperable and refer to Tech Spec 3.4.15B.
CRS       Initiate steps to meet requirements per Tech Specs.
CRS Initiate steps to meet requirements per Tech Specs.
CRS       Initiate steps to have the failed monitor checked and repaired.
CRS Initiate steps to have the failed monitor checked and repaired.
EVENT TERMINATION CRITERIA Tech Spec determination made
EVENT TERMINATION CRITERIA Tech Spec determination made  


Appendix D                       Operator Actions                     Form ES-D-2 Op-Test No: 2004-1           Scenario No: 1             Event No: 4 & 5                       Page 6 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 4 & 5 Page 6 of 10 Event


== Description:==
== Description:==
The Mablevale substation experiences storm damage causing the breakers in the switchyard supplying that line to open. The dispatcher requests an emergency power reduction to ~650 MWe to maintain system integrity. The Turbine fails to respond to lowering demand.
The Mablevale substation experiences storm damage causing the breakers in the switchyard supplying that line to open. The dispatcher requests an emergency power reduction to ~650 MWe to maintain system integrity. The Turbine fails to respond to lowering demand.
Time     Position                               Applicants Actions or Behavior ROLE PLAY Call control room as EOC Dispatcher and direct unit to reduce power to 650 MWe as soon as possible due to transformer damage at the Mablevale substation.
Time Position Applicants Actions or Behavior ROLE PLAY Call control room as EOC Dispatcher and direct unit to reduce power to 650 MWe as soon as possible due to transformer damage at the Mablevale substation.
If asked by control room personnel inform them that there is serious concern over grid stability due to the severe weather and substation damage.
If asked by control room personnel inform them that there is serious concern over grid stability due to the severe weather and substation damage.
T=25       CRS     Direct CBOR to reduce unit load to 650 MWe.
T=25 CRS Direct CBOR to reduce unit load to 650 MWe.
CRS     Direct operations per 1203.045, Rapid Plant Shutdown.
CRS Direct operations per 1203.045, Rapid Plant Shutdown.
CBOR     Commence reduction in unit load to 650 MWe using the ULD.
CBOR Commence reduction in unit load to 650 MWe using the ULD.
NOTE: Turbine may revert to Operator Auto mode before operator takes action.
NOTE: Turbine may revert to Operator Auto mode before operator takes action.
CBOT/R     Recognize and report to the CRS that the turbine is not responding during the power reduction.
CBOT/R Recognize and report to the CRS that the turbine is not responding during the power reduction.
NOTE: The crew may elect to place both the SG/RX master and the Turbine in the MANUAL mode. In this configuration, the CBOR controls the change in load demand and the CBOT will maintain turbine header pressure.
NOTE: The crew may elect to place both the SG/RX master and the Turbine in the MANUAL mode. In this configuration, the CBOR controls the change in load demand and the CBOT will maintain turbine header pressure.
CRS     Direct the CBOT to place the turbine in Operator Auto or Manual mode and control steam header pressure.
CRS Direct the CBOT to place the turbine in Operator Auto or Manual mode and control steam header pressure.
CBOT     Take the turbine to manual or operator auto CRS     Direct the CBOR to place the SG/RX Master H/A station in HAND and lower load to 650 MWe.
CBOT Take the turbine to manual or operator auto CRS Direct the CBOR to place the SG/RX Master H/A station in HAND and lower load to 650 MWe.
CBOR     Place the SG/RX master in HAND and slowly toggle down.
CBOR Place the SG/RX master in HAND and slowly toggle down.
continued
continued  


Appendix D                       Operator Actions                     Form ES-D-2 Op-Test No: 2004-1         Scenario No: 1             Event No: 4 & 5                       Page 7 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 4 & 5 Page 7 of 10 Event


== Description:==
== Description:==
The Mablevale substation experiences storm damage causing the breakers in the switchyard supplying that line to open. The dispatcher requests an emergency power reduction to ~650 MWe to maintain system integrity. The Turbine fails to respond to lowering demand.
The Mablevale substation experiences storm damage causing the breakers in the switchyard supplying that line to open. The dispatcher requests an emergency power reduction to ~650 MWe to maintain system integrity. The Turbine fails to respond to lowering demand.
Time     Position                               Applicants Actions or Behavior NOTE: In the manual mode on the SG/RX master, the operator has control of the rate the plant will change. It is expected the operator will maintain the rate of change near the directed rate by the CRS.
Time Position Applicants Actions or Behavior NOTE: In the manual mode on the SG/RX master, the operator has control of the rate the plant will change. It is expected the operator will maintain the rate of change near the directed rate by the CRS.
CBOT     Verify Turbine EHC responds to lowering load and maintains header pressure at or near setpoint of 895#. (Operator Auto or Manual)
CBOT Verify Turbine EHC responds to lowering load and maintains header pressure at or near setpoint of 895#. (Operator Auto or Manual)
ROLE PLAY If asked about PPAS information, report ICS signal to EHC good.
ROLE PLAY If asked about PPAS information, report ICS signal to EHC good.
CBOR     Stabilize load at ~650MWe. Power should be near 65-67%.
CBOR Stabilize load at ~650MWe. Power should be near 65-67%.
EVENT TERMINATION CRITERIA Power reduction is complete OR the next event occurs
EVENT TERMINATION CRITERIA Power reduction is complete OR the next event occurs  


Appendix D                       Operator Actions                     Form ES-D-2 Op-Test No: 2004-1         Scenario No: 1             Event No: 6                           Page 8 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 6 Page 8 of 10 Event


== Description:==
== Description:==
The B Main Steam Isolation Valve drifts shut, requiring a manual reactor trip per EOP 1202.001.
The B Main Steam Isolation Valve drifts shut, requiring a manual reactor trip per EOP 1202.001.
Time   Position                               Applicants Actions or Behavior T=30   CBOR       Acknowledge and report annunciator K07 C6, Main Steam Pressure Hi/Lo in alarm.
Time Position Applicants Actions or Behavior T=30 CBOR Acknowledge and report annunciator K07 C6, Main Steam Pressure Hi/Lo in alarm.
CRS       Refer to ACA 1203.012I for guidance.
CRS Refer to ACA 1203.012I for guidance.
CBOR/T     Observe the B MSIV, CV2692, closing.
CBOR/T Observe the B MSIV, CV2692, closing.
CRS       Direct the CBOR to TRIP the reactor and Carryout the immediate actions.
CRS Direct the CBOR to TRIP the reactor and Carryout the immediate actions.
CBOR       Trip the reactor by depressing the pushbutton on C03 and observing all control rods inserted and power dropping.
CBOR Trip the reactor by depressing the pushbutton on C03 and observing all control rods inserted and power dropping.
CBOT     Manually trip the turbine by depressing the pushbutton on C01 and observing the throttle and governor valves close and output and exciter field breakers open.
CBOT Manually trip the turbine by depressing the pushbutton on C01 and observing the throttle and governor valves close and output and exciter field breakers open.
CBOR/T     Verify subcooling margin adequate.
CBOR/T Verify subcooling margin adequate.
CRS       Provide direction to the crew per Reactor Trip EOP, 1202.001.
CRS Provide direction to the crew per Reactor Trip EOP, 1202.001.
EVENT TERMINATION CRITERIA B MSIV closed and Reactor is tripped OR As determined by the lead examiner.
EVENT TERMINATION CRITERIA B MSIV closed and Reactor is tripped OR As determined by the lead examiner.  


Appendix D                         Operator Actions                     Form ES-D-2 Op-Test No: 2004-1           Scenario No: 1             Event No: 7 & 8                   Page 9 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 7 & 8 Page 9 of 10 Event


== Description:==
== Description:==
Main Steam Line rupture inside containment. Channel 6 of ESAS fails to auto actuate. ICW valve CV2214 fails to close.
Main Steam Line rupture inside containment. Channel 6 of ESAS fails to auto actuate. ICW valve CV2214 fails to close.
Time     Position                                   Applicants Actions or Behavior T=35     CBOR       Recognize A OTSG pressure dropping OR noticeably lower than B OTSG pressure.
Time Position Applicants Actions or Behavior T=35 CBOR Recognize A OTSG pressure dropping OR noticeably lower than B OTSG pressure.
CBOR       Monitor RB pressure and temperature.
CBOR Monitor RB pressure and temperature.
NOTE:
NOTE:
Due to rise in reactor building pressure and temperature, ESAS may actuate prior to the direction to trip the Reactor if CRS fails to recognize MSIV drifting shut in event 6 above.
Due to rise in reactor building pressure and temperature, ESAS may actuate prior to the direction to trip the Reactor if CRS fails to recognize MSIV drifting shut in event 6 above.
Annunciator K12A1 will alarm due to the environmental conditions inside the Reactor Building. If panel 463 is checked for location of the alarm, instruct that module A2-5 lower, RB UNEP ZONE 32-K, in alarm.
Annunciator K12A1 will alarm due to the environmental conditions inside the Reactor Building. If panel 463 is checked for location of the alarm, instruct that module A2-5 lower, RB UNEP ZONE 32-K, in alarm.
CBOR/T     Identify and announce ESAS has actuated on high RB Pressure.
CBOR/T Identify and announce ESAS has actuated on high RB Pressure.
CRS       Transition to ESAS Procedure , EOP1202.010 and direct crew actions.
CRS Transition to ESAS Procedure, EOP1202.010 and direct crew actions.
CRS       Direct the verification of ESAS per RT10.
CRS Direct the verification of ESAS per RT10.
CBOR/T     Recognize failure of Channel 6 of ESAS to auto actuate. Tech Spec 3.3.7A.
CBOR/T Recognize failure of Channel 6 of ESAS to auto actuate. Tech Spec 3.3.7A.
CT     CBOR       Manually actuate Channel 6 of ESAS using the button on C04.
CT CBOR Manually actuate Channel 6 of ESAS using the button on C04.
CBOT       Identify and report failure of CV2214 to close.
CBOT Identify and report failure of CV2214 to close.
CRS       Direct the CBOT to verify the redundant ICW valve on Channel 6, CV2215, closed.
CRS Direct the CBOT to verify the redundant ICW valve on Channel 6, CV2215, closed.
CBOT       Verify actuation of ESAS per RT 10.
CBOT Verify actuation of ESAS per RT 10.
CREW       Recognize SG pressure < 900#
CREW Recognize SG pressure < 900#
continued
continued  


Appendix D                   Operator Actions                     Form ES-D-2 Op-Test No: 2004-1         Scenario No: 1           Event No: 7 & 8                     Page 10 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 7 & 8 Page 10 of 10 Event


== Description:==
== Description:==
Main Steam Line rupture inside containment. Channel 6 of ESAS fails to auto actuate. ICW valve CV2214 fails to close.
Main Steam Line rupture inside containment. Channel 6 of ESAS fails to auto actuate. ICW valve CV2214 fails to close.
Time     Position                           Applicants Actions or Behavior CRS     Transition to Overcooling Emergency Operating procedure (1202.003).
Time Position Applicants Actions or Behavior CRS Transition to Overcooling Emergency Operating procedure (1202.003).
CT         CBOT   Manually override and secure HPI as directed by the CRS and the Emergency Operating Procedure.
CT CBOT Manually override and secure HPI as directed by the CRS and the Emergency Operating Procedure.
CBOR     Report A MSLI actuated.
CBOR Report A MSLI actuated.
EAL NUE 3.1 Uncontrolled OTSG Depressurization Resulting in MSLI Actuation CRS     Provide RT6 to CBOR to verify proper MSLI and EFW actuation and control.
EAL NUE 3.1 Uncontrolled OTSG Depressurization Resulting in MSLI Actuation CRS Provide RT6 to CBOR to verify proper MSLI and EFW actuation and control.
CBOR     Verify proper MSLI and EFW actuation and control per RT6.
CBOR Verify proper MSLI and EFW actuation and control per RT6.
CBOR     Control RCS pressure within the limits of Figure 3 per RT14 using PZR heaters EVENT AND SCENARIO TERMINATION CRITERIA RCS pressure and temperature stable with the A OTSG isolated, channel 6 of ESAS manually actuated, with the ICW flowpath isolated OR As determined by the lead examiner.
CBOR Control RCS pressure within the limits of Figure 3 per RT14 using PZR heaters EVENT AND SCENARIO TERMINATION CRITERIA RCS pressure and temperature stable with the A OTSG isolated, channel 6 of ESAS manually actuated, with the ICW flowpath isolated OR As determined by the lead examiner.  


Appendix D                   Operator Actions                 Form ES-D-1 Facility: ANO-1                 Scenario No.: 2 (MOD)                   Op-Test No.: 2004-1 Page 1 of 11 Examiners:                                                       Operators:
Appendix D Operator Actions Form ES-D-1 Facility: ANO-1 Scenario No.: 2 (MOD) Op-Test No.: 2004-1 Page 1 of 11 Examiners:
Operators:
Initial Conditions:
Initial Conditions:
100% MOL, equilibrium Xenon, P4A and P4B in service (P4C down for maintenance).
100% MOL, equilibrium Xenon, P4A and P4B in service (P4C down for maintenance).
Sluice gates SG-1, SG-2, and SG-4 open.
Sluice gates SG-1, SG-2, and SG-4 open.
Turnover:
Turnover:
100% power, MOL, equilibrium Xenon. Expected P4C return to service and restore normal line-up within next 2 hours. . #2 EDG is OOS to repair its governor (day 1 of 7 day LCO 3.8.1.B).
100% power, MOL, equilibrium Xenon. Expected P4C return to service and restore normal line-up within next 2 hours.. #2 EDG is OOS to repair its governor (day 1 of 7 day LCO 3.8.1.B).
Event       Malf. No.     Event                                 Event No.                        Type*                             Description 1           TR625       I (BOT)       A CFT-LT LIS2416 fails low. SRO TS determination required.
Event No.
2           N/A         N (BOT)       Shift service water pump to P4A/P4C line-up, return P4B to standby 3           TR051       I (BOR)       Selected PZR level transmitter fails high 4           TR558       I (BOR)       B Main Feed flow transmitter drifts low slowly 5       BAT P1B_vibes   C (BOR)       MFP B has excessive vibration.
Malf. No.
6           N/A         R (BOR)       Perform normal shutdown to repair MFP B.
Event Type*
7           ED183       M (ALL)       Loss of Offsite power, Rx trip.
Event Description 1
DG175        C (BOT)      #1 EDG fails to auto start and pushbutton on C10 fails to start it.
TR625 I (BOT)
STATION BLACK-OUT 8         CV2645       C (BOR)       EFW valve fails open to A OTSG, resulting in level being raised higher than EFIC controlled SP.
A CFT-LT LIS2416 fails low. SRO TS determination required.
* (N)ormal,     (R)eactivity, (I)nstrument,   (C)omponent,   (M)ajor NUREG-1021, Revision 8, Supplement 1
2 N/A N (BOT)
Shift service water pump to P4A/P4C line-up, return P4B to standby 3
TR051 I (BOR)
Selected PZR level transmitter fails high 4
TR558 I (BOR)
B Main Feed flow transmitter drifts low slowly 5
BAT P1B_vibes C (BOR)
MFP B has excessive vibration.
6 N/A R (BOR)
Perform normal shutdown to repair MFP B.
7 ED183 DG175 M (ALL)
C (BOT)
Loss of Offsite power, Rx trip.  
#1 EDG fails to auto start and pushbutton on C10 fails to start it.
STATION BLACK-OUT 8
CV2645 C (BOR)
EFW valve fails open to A OTSG, resulting in level being raised higher than EFIC controlled SP.  
* (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor NUREG-1021, Revision 8, Supplement 1  


Appendix D               Operator Actions                   Form ES-D-1 Page 2 of 11 Event Time     Malf. No. Value/Ramp                           Event No.                        Time                              Description 7&8   T=0     IMF DG175         N/A     #1 EDG fails to autostart IOR DI_DG1S        False    Pushbutton on C10 fails to start the EDG.
Appendix D Operator Actions Form ES-D-1 Page 2 of 11 Event No.
ICM CV2645          1      EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.
Time Malf. No.
1     T=2     IMF TR625     0 Ramp 0   A Core Flood Tank LT(LIS2416) fails low.
Value/Ramp Time Event Description 7&8 T=0 IMF DG175 IOR DI_DG1S ICM CV2645 N/A False 1
2   T=~10       N/A           N/A     Shift service water pumps to P4A/P4C line-up, return P4B to standby 3     T=20     IMF TR051         320     PZR level transmitter (LT1001) fails to high Ramp 2 Min.
#1 EDG fails to autostart Pushbutton on C10 fails to start the EDG.
4    T=27     IMF TR558       1.0e06   B Main Feed flow transmitter drifts low slowly Ramp 4 Min.
EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.
5    T=30 BAT P1B_vibes       N/A     Report that B Main Feed Pump has excessive vibration 6   T=~32       N/A           N/A     Perform normal shutdown to repair B MFP 7     T=40     IMF ED183         N/A     Loss of offsite power occurs. Reactor trip.
1 T=2 IMF TR625 0 Ramp 0 A Core Flood Tank LT(LIS2416) fails low.
STATION BLACKOUT NUREG-1021, Revision 8, Supplement 1
2 T=~10 N/A N/A Shift service water pumps to P4A/P4C line-up, return P4B to standby 3
T=20 IMF TR051 320 Ramp 2 Min.
PZR level transmitter (LT1001) fails to high 4
T=27 IMF TR558 1.0e06 Ramp 4 Min.
B Main Feed flow transmitter drifts low slowly 5
T=30 BAT P1B_vibes N/A Report that B Main Feed Pump has excessive vibration 6
T=~32 N/A N/A Perform normal shutdown to repair B MFP 7
T=40 IMF ED183 N/A Loss of offsite power occurs. Reactor trip.
STATION BLACKOUT NUREG-1021, Revision 8, Supplement 1  


Appendix D                     Operator Actions                         Form ES-D-2 Op-Test No: 2004-1         Scenario No: 2             Event No: 1                           Page 3 of 11 Event
Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 1 Page 3 of 11 Event


== Description:==
== Description:==
A CFT Level transmitter (LIS2416) fails low.
A CFT Level transmitter (LIS2416) fails low.
Time   Position                                 Applicants Actions or Behavior T=2   CBOR       Recognize and report that annunciator K10 C5, A CFT LEVEL HI/LO, in alarm.
Time Position Applicants Actions or Behavior T=2 CBOR Recognize and report that annunciator K10 C5, A CFT LEVEL HI/LO, in alarm.
CRS       Refer to ACA 1203.012I for corrective action.
CRS Refer to ACA 1203.012I for corrective action.
CBOT     Diagnose LIS2416 failure after comparing level indications for T2A on C16 and C18.
CBOT Diagnose LIS2416 failure after comparing level indications for T2A on C16 and C18.
CRS       Refer to Technical Specifications for applicability. ACA 1203.012I refers to TS 3.5.1 if actual level is high or low. Reference to the Technical Requirement Manual for instrumentation should be performed.
CRS Refer to Technical Specifications for applicability. ACA 1203.012I refers to TS 3.5.1 if actual level is high or low. Reference to the Technical Requirement Manual for instrumentation should be performed.
Technical Requirements Manual 3.3.5, Miscellaneous Instrumentation.
Technical Requirements Manual 3.3.5, Miscellaneous Instrumentation.
(Only one pressure and one level transmitter is required for operability)
(Only one pressure and one level transmitter is required for operability)
EVENT TERMINATION CRITERIA Next Event NUREG-1021, Revision 8, Supplement 1
EVENT TERMINATION CRITERIA Next Event  


Appendix D                     Operator Actions                           Form ES-D-2 Op-Test No: 2004-1         Scenario No: 2             Event No: 2                           Page 4 of 11 Event
Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 2 Page 4 of 11 Event


== Description:==
== Description:==
Shift Service Water Pumps Time   Position                               Applicants Actions or Behavior T~10     Role     Call as work week manager and report P4C is ready for operation and rotation of Play    pumps can proceed as anticipated.
Shift Service Water Pumps Time Position Applicants Actions or Behavior T~10 Role Play Call as work week manager and report P4C is ready for operation and rotation of pumps can proceed as anticipated.
CRS       Direct shifting the service water pump configuration to P4A and P4C running and return P4B to standby status.
CRS Direct shifting the service water pump configuration to P4A and P4C running and return P4B to standby status.
CBOT     Notify Chemistry of pump rotation so chemical injection can be appropriately aligned.
CBOT Notify Chemistry of pump rotation so chemical injection can be appropriately aligned.
CBOT     Refer to Table 9.3 of 1104.029 to determine the service water alignment necessary for the pumps that will remain in service.
CBOT Refer to Table 9.3 of 1104.029 to determine the service water alignment necessary for the pumps that will remain in service.
CBOT     Verify sluice gates aligned to supply water to the desired SW Pumps.
CBOT Verify sluice gates aligned to supply water to the desired SW Pumps.
CBOT     Start P4C CBOT     Stop P4B CBOT     Notify the Outside AO to check for reverse rotation of P4B.
CBOT Start P4C CBOT Stop P4B CBOT Notify the Outside AO to check for reverse rotation of P4B.
CBOT     Align service water system per Table 9.3 CBOR/T     Verify normal service water loop pressures.
CBOT Align service water system per Table 9.3 CBOR/T Verify normal service water loop pressures.
CBOR/T     Monitor SW bay level, CW bay level, and bay differentials for proper operation of SW bay strainiers.
CBOR/T Monitor SW bay level, CW bay level, and bay differentials for proper operation of SW bay strainiers.
EVENT TERMINATION CRITERIA Service Water Pumps rotated and system aligned OR Next Event NUREG-1021, Revision 8, Supplement 1
EVENT TERMINATION CRITERIA Service Water Pumps rotated and system aligned OR Next Event  


Appendix D                       Operator Actions                         Form ES-D-2 Op-Test No: 2004-1           Scenario No: 2           Event No: 3                               Page 5 of 11 Event
Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 3 Page 5 of 11 Event


== Description:==
== Description:==
PZR level transmitter (LT1001) fails to upscale Time   Position                                 Applicants Actions or Behavior T=20     CBOR       Recognize and report that PZR level indications are mismatched CREW       Diagnose LT1001 failure Tech. Spec. 3.3.15A CRS       Direct operations per 1203.015 Pressurizer Systems Failure, section 4.0.
PZR level transmitter (LT1001) fails to upscale Time Position Applicants Actions or Behavior T=20 CBOR Recognize and report that PZR level indications are mismatched CREW Diagnose LT1001 failure Tech. Spec. 3.3.15A CRS Direct operations per 1203.015 Pressurizer Systems Failure, section 4.0.
CRS       Direct CBOR to select valid PZR level indicator for PZR level control.
CRS Direct CBOR to select valid PZR level indicator for PZR level control.
CBOR       Select LT1002 to control PZR level control valve (CV-1235) using hand switch on upright section of C04.
CBOR Select LT1002 to control PZR level control valve (CV-1235) using hand switch on upright section of C04.
CBOR       Verify CV-1235 opens to control PZR level at setpoint.
CBOR Verify CV-1235 opens to control PZR level at setpoint.
EVENT TERMINATION CRITERIA Pressurizer level control is selected to LT1002 and PZR level control valve is controlling level in auto.
EVENT TERMINATION CRITERIA Pressurizer level control is selected to LT1002 and PZR level control valve is controlling level in auto.  
NUREG-1021, Revision 8, Supplement 1


Appendix D                         Operator Actions                       Form ES-D-2 Op-Test No: 2004-1         Scenario No: 2               Event No: 4                         Page 6 of 11 Event
Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 4 Page 6 of 11 Event


== Description:==
== Description:==
B Main Feed flow transmitter drifts low slowly Time   Position                                 Applicants Actions or Behavior T=27   CBOR       Acknowledge and report annunciator K07 B4, SASS MISMATCH.
B Main Feed flow transmitter drifts low slowly Time Position Applicants Actions or Behavior T=27 CBOR Acknowledge and report annunciator K07 B4, SASS MISMATCH.
CBOR/T     Determine the cause of the alarm by scanning C03, C04, and C13 for SASS ENABLE light that is not illuminated. Identify the B MFW flow SASS Enable not illuminated.
CBOR/T Determine the cause of the alarm by scanning C03, C04, and C13 for SASS ENABLE light that is not illuminated. Identify the B MFW flow SASS Enable not illuminated.
CBOR       Determine that SASS did not transfer to the Y instrument for control.
CBOR Determine that SASS did not transfer to the Y instrument for control.
CRS       Refer to ACA 1203.012F for corrective action and guidance.
CRS Refer to ACA 1203.012F for corrective action and guidance.
CRS       Direct the CBOR to place both FW pump H/A stations , and control rods in MANUAL. (Reactor Demand or Diamond station to MANUAL is acceptable)
CRS Direct the CBOR to place both FW pump H/A stations, and control rods in MANUAL. (Reactor Demand or Diamond station to MANUAL is acceptable)
CBOR       Place the BOTH MFW pump H/A stations to MANUAL and Reactor Demand or Diamond Station to MANUAL.
CBOR Place the BOTH MFW pump H/A stations to MANUAL and Reactor Demand or Diamond Station to MANUAL.
CRS       Direct the CBOR to stabilize the plant CBOR       Using the MFW pump H/A stations and control rods, balance feedwater flows and Tave to return to normal values.
CRS Direct the CBOR to stabilize the plant CBOR Using the MFW pump H/A stations and control rods, balance feedwater flows and Tave to return to normal values.
CRS       Direct the CBOT to compare failed instrument to the non-selected instrument using PMS.
CRS Direct the CBOT to compare failed instrument to the non-selected instrument using PMS.
CBOT     Using PMS, verify the non-selected MFW flow is reading correctly.
CBOT Using PMS, verify the non-selected MFW flow is reading correctly.
CRS       Direct the CBOR to select the Y MFW flow instrument for loop B.
CRS Direct the CBOR to select the Y MFW flow instrument for loop B.
CBOR       Select the Y instrument for loop B MFW flow.
CBOR Select the Y instrument for loop B MFW flow.
continued NUREG-1021, Revision 8, Supplement 1
continued  


Appendix D                   Operator Actions                         Form ES-D-2 Op-Test No: 2004-1         Scenario No: 2             Event No: 4                         Page 7 of 11 Event
Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 4 Page 7 of 11 Event


== Description:==
== Description:==
B Main Feed flow transmitter drifts low slowly Time   Position                               Applicants Actions or Behavior NOTE: A caution placard on both C03 and C13 provides direction of selecting the associated X or Y MFW Temperature instrument when the MFW flow instrument is selected due to hard wired temperature compensation of the MFW flow instrument.
B Main Feed flow transmitter drifts low slowly Time Position Applicants Actions or Behavior NOTE: A caution placard on both C03 and C13 provides direction of selecting the associated X or Y MFW Temperature instrument when the MFW flow instrument is selected due to hard wired temperature compensation of the MFW flow instrument.
CRS       Direct the CBOT to select the Y MFW temperature instrument for loop B on C13.
CRS Direct the CBOT to select the Y MFW temperature instrument for loop B on C13.
CBOT     Select the Y MFW temperature instrument for loop B.
CBOT Select the Y MFW temperature instrument for loop B.
CBOR       Place ICS in AUTO in accordance with 1105.004, ICS Operations.
CBOR Place ICS in AUTO in accordance with 1105.004, ICS Operations.
EVENT TERMINATION CRITERIA B Main Feedwater Flow Y instrument selected and ICS in AUTO NUREG-1021, Revision 8, Supplement 1
EVENT TERMINATION CRITERIA B Main Feedwater Flow Y instrument selected and ICS in AUTO  


Appendix D                     Operator Actions                         Form ES-D-2 Op-Test No: 2004-1         Scenario No: 2           Event No: 5 & 6                   Page 8 of 11 Event
Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 5 & 6 Page 8 of 11 Event


== Description:==
== Description:==
B Main Feedwater pump excessive vibration and power reduction to secure B MFW pump for repair.
B Main Feedwater pump excessive vibration and power reduction to secure B MFW pump for repair.
Time   Position                               Applicants Actions or Behavior T=30   CBOR       Acknowledge and report annunciator K06 C3, B MFP TURB CONTROL SYS TROUBLE.
Time Position Applicants Actions or Behavior T=30 CBOR Acknowledge and report annunciator K06 C3, B MFP TURB CONTROL SYS TROUBLE.
CRS       Refer to ACA 1203.012E for corrective action and guidance.
CRS Refer to ACA 1203.012E for corrective action and guidance.
CBOR/T     Report vibration alarm on B MFP from OIT alarm panel OR TSI.
CBOR/T Report vibration alarm on B MFP from OIT alarm panel OR TSI.
CRS       Direct AO to verify/confirm B MFP has excessive vibration.
CRS Direct AO to verify/confirm B MFP has excessive vibration.
CRS       Direct the CBOR and CBOT to perform a power reduction to approxiomately 40%
CRS Direct the CBOR and CBOT to perform a power reduction to approxiomately 40%
power to secure the B MFP.
power to secure the B MFP.
CBOR       Begin a power reduction to 40% power using the Unit Load Demand (ULD).
CBOR Begin a power reduction to 40% power using the Unit Load Demand (ULD).
EVENT TERMINATION CRITERIA Power reduction >10%
EVENT TERMINATION CRITERIA Power reduction >10%  
NUREG-1021, Revision 8, Supplement 1


Appendix D                     Operator Actions                         Form ES-D-2 Op-Test No: 2004-1         Scenario No: 2             Event No: 7 & 8                         Page 9 of 11 Event
Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 7 & 8 Page 9 of 11 Event


== Description:==
== Description:==
Loss of offsite power occurs. Reactor trip. #1 EDG fails to autostart and the pushbutton on C10 fails to start the EDG. STATION BLACKOUT. EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.
Loss of offsite power occurs. Reactor trip. #1 EDG fails to autostart and the pushbutton on C10 fails to start the EDG. STATION BLACKOUT. EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.
Time   Position                               Applicants Actions or Behavior T=40   CREW       Recognize loss of offsite power CRS       Direct actions per the Reactor Trip Procedure, 1202.001.
Time Position Applicants Actions or Behavior T=40 CREW Recognize loss of offsite power CRS Direct actions per the Reactor Trip Procedure, 1202.001.
CBOR       Manually trip the reactor by depressing the Rx. Trip pushbutton. Verify all rods on bottom and power dropping.
CBOR Manually trip the reactor by depressing the Rx. Trip pushbutton. Verify all rods on bottom and power dropping.
CBOT     Manually trip the turbine by depressing the Turbine Trip pushbutton CBOR/     Verify adequate subcooling margin.
CBOT Manually trip the turbine by depressing the Turbine Trip pushbutton CBOR/
CBOT CRS       Transition to the Degraded Power Emergency Operating Procedure (1202.007).
CBOT Verify adequate subcooling margin.
CRS Transition to the Degraded Power Emergency Operating Procedure (1202.007).
Direct operations per 1202.007.
Direct operations per 1202.007.
(Tech Spec. 3.8.1.G, AC Sources - Operating, Three or more required AC sources inoperable.)
(Tech Spec. 3.8.1.G, AC Sources - Operating, Three or more required AC sources inoperable.)
CBOT     Recognize the failure of #1 EDG to autostart CBOT     Attempt to manually start #1 EDG using push-button on C10.
CBOT Recognize the failure of #1 EDG to autostart CBOT Attempt to manually start #1 EDG using push-button on C10.
CRS       Transition to the Blackout Emergency Operating Procedure (1202.008) and direct operations.
CRS Transition to the Blackout Emergency Operating Procedure (1202.008) and direct operations.
(Tech Spec. 3.8.1.G, AC Sources - Operating, Three or more required AC sources inoperable.)
(Tech Spec. 3.8.1.G, AC Sources - Operating, Three or more required AC sources inoperable.)
CBOR       Verify EFW actuated and perform RT5 CRS       Dispatch AO to #1 EDG continued NUREG-1021, Revision 8, Supplement 1
CBOR Verify EFW actuated and perform RT5 CRS Dispatch AO to #1 EDG continued  


Appendix D                   Operator Actions                         Form ES-D-2 Op-Test No: 2004-1         Scenario No: 2             Event No: 7 & 8                     Page 10 of 11 Event
Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 7 & 8 Page 10 of 11 Event


== Description:==
== Description:==
Loss of offsite power occurs. Reactor trip. #1 EDG fails to autostart and the pushbutton on C10 fails to start the EDG. STATION BLACKOUT. EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.
Loss of offsite power occurs. Reactor trip. #1 EDG fails to autostart and the pushbutton on C10 fails to start the EDG. STATION BLACKOUT. EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.
Time   Position                               Applicants Actions or Behavior CRS       Communicate with Unit 2 to make the AAC generator available for use by Unit 1.
Time Position Applicants Actions or Behavior CRS Communicate with Unit 2 to make the AAC generator available for use by Unit 1.
CRS       Direct manual isolation of letdown and RCP seal return.
CRS Direct manual isolation of letdown and RCP seal return.
CBOR       Close CV1223 on C04.
CBOR Close CV1223 on C04.
CBOT     Place RCP seal Bleedoff alternate path to quench tank valves in CLOSED position on C13.
CBOT Place RCP seal Bleedoff alternate path to quench tank valves in CLOSED position on C13.
CRS       Dispatch the WCO to isolate letdown by manually closing CV1221 and isolating RCP seal return by manually closing CV1274.
CRS Dispatch the WCO to isolate letdown by manually closing CV1221 and isolating RCP seal return by manually closing CV1274.
CBOR       Close both MSIVs (CV2691 and CV2692) on C09.
CBOR Close both MSIVs (CV2691 and CV2692) on C09.
CBOR       Report the EFW valve, CV2645 to the A OTSG, will not control and will not move in manual.
CBOR Report the EFW valve, CV2645 to the A OTSG, will not control and will not move in manual.
CT   CBOR       Manually throttle CV2627 on C09 to establish approximately 280 gpm.
CT CBOR Manually throttle CV2627 on C09 to establish approximately 280 gpm.
CRS       Direct the CBOT to place the AAC generator on the A3 bus utilizing O.P. 1107.002.
CRS Direct the CBOT to place the AAC generator on the A3 bus utilizing O.P. 1107.002.
INSTRUCTOR NOTE: Make the AAC generator available to the crew by performing the following; RMF EDA901 TRUE Call as the Unit 2 CRS and report the AAC generator is available for loading the vital bus.
INSTRUCTOR NOTE: Make the AAC generator available to the crew by performing the following; RMF EDA901 TRUE Call as the Unit 2 CRS and report the AAC generator is available for loading the vital bus.
CT     CBOT     Place the AAC generator on the A3 bus.
CT CBOT Place the AAC generator on the A3 bus.
continued NUREG-1021, Revision 8, Supplement 1
continued  


Appendix D                       Operator Actions                         Form ES-D-2 Op-Test No: 2004-1         Scenario No: 2             Event No: 7 & 8                       Page 11 of 11 Event
Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 7 & 8 Page 11 of 11 Event


== Description:==
== Description:==
Loss of offsite power occurs. Reactor trip. #1 EDG fails to autostart and the pushbutton on C10 fails to start the EDG. STATION BLACKOUT. EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.
Loss of offsite power occurs. Reactor trip. #1 EDG fails to autostart and the pushbutton on C10 fails to start the EDG. STATION BLACKOUT. EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.
Time   Position                                 Applicants Actions or Behavior CRS       Transition back to the Degraded Power procedure (1202.007).
Time Position Applicants Actions or Behavior CRS Transition back to the Degraded Power procedure (1202.007).
CT     CBOR       Start P7B by releasing handswitch from Pull-to-lock and placing handswitch in the start position.
CT CBOR Start P7B by releasing handswitch from Pull-to-lock and placing handswitch in the start position.
CRS       Direct the CBOR to establish EFW to both OTSGs using P7B.
CRS Direct the CBOR to establish EFW to both OTSGs using P7B.
CBOR       Verify EFW flow to the OTSGs.
CBOR Verify EFW flow to the OTSGs.
EVENT AND SCENARIO TERMINATION CRITERIA Power restored to the A3 bus from the AAC generator and EFW re-established to both OTSGs from P7B OR as directed by the lead examiner.
EVENT AND SCENARIO TERMINATION CRITERIA Power restored to the A3 bus from the AAC generator and EFW re-established to both OTSGs from P7B OR as directed by the lead examiner.  
NUREG-1021, Revision 8, Supplement 1


Appendix D                   Operator Actions                 Form ES-D-1 Facility: ANO-1                 Scenario No.: 3 (MOD)                     Op-Test No.: 2004-1 Page 1 of 10 Examiners:                                                         Operators:
Appendix D Operator Actions Form ES-D-1 Facility: ANO-1 Scenario No.: 3 (MOD) Op-Test No.: 2004-1 Page 1 of 10 Examiners:
Operators:
Initial Conditions:
Initial Conditions:
90% power, equilibrium Xenon, MOL, #2 EDG SW valve fails to open on manual start.
90% power, equilibrium Xenon, MOL, #2 EDG SW valve fails to open on manual start.
Turnover::
Turnover::
90% power, MOL, equilibrium Xenon. AO routinely checking traveling screens due to mild shad run over past 24 hrs. System Engineering and Ops Management have discussed rotation of operating Makeup pumps. They will call control room when they want this evolution performed.
90% power, MOL, equilibrium Xenon. AO routinely checking traveling screens due to mild shad run over past 24 hrs. System Engineering and Ops Management have discussed rotation of operating Makeup pumps. They will call control room when they want this evolution performed.
Event         Malf. No.       Event                              Event No.                          Type*                           Description 1           IMF C5A         C (BOT)     Condenser Vacuum Pump C5A trips 2             N/A         N (ALL)     Shift running make up pumps from P36B to P36C to equalize run times 3             N/A         R (BOR)     Load dispatcher orders power increase to 100%
Event No.
Malf. No.
Event Type*
Event Description 1
IMF C5A C (BOT)
Condenser Vacuum Pump C5A trips 2
N/A N (ALL)
Shift running make up pumps from P36B to P36C to equalize run times 3
N/A R (BOR)
Load dispatcher orders power increase to 100%
due to grid loading.
due to grid loading.
4           TR458         I (BOR)     Controlling RCS pressure fails to 2280#
4 TR458 I (BOR)
5         IMF CV1008       C (BOR)     PZR spray valve leaks by after cycling 6         IMF ED453       I (ALL)     SPDS failure 7         IMF RC005       M (ALL)     SB LOCA 8         IMF CV1400       C (BOR)     LPI injection valve CV1400 does not open.
Controlling RCS pressure fails to 2280#
9         IMF ES259       C (BOR)     ESAS channels 1, 2 fail to actuate at RCS IMF ES260                    pressure set point
5 IMF CV1008 C (BOR)
* (N)ormal,     (R)eactivity, (I)nstrument, (C)omponent,     (M)ajor NUREG-1021, Revision 8, Supplement 1
PZR spray valve leaks by after cycling 6
IMF ED453 I (ALL)
SPDS failure 7
IMF RC005 M (ALL)
SB LOCA 8
IMF CV1400 C (BOR)
LPI injection valve CV1400 does not open.
9 IMF ES259 IMF ES260 C (BOR)
ESAS channels 1, 2 fail to actuate at RCS pressure set point  
* (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor NUREG-1021, Revision 8, Supplement 1  


Appendix D               Operator Actions                   Form ES-D-1 Page 2 of 10 Event   Time   Malf. No. Value/Ramp                           Event No.                        Time                              Description 8&9       T=0   IMF CV1400     0 Ramp 0   LPI Block valve, CV1400, does not open.
Appendix D Operator Actions Form ES-D-1 Page 2 of 10 Event No.
IMF ES259        N/A    ES channels 1 and 2 fail to auto actuate IMF ES260 IMF CV3807    0 Ramp 0    #2 EDG SW valve fails to open when EDG autostarts 1       T=2     IMF C5A         OFF     Condenser Vacuum Pump C5A trips 2     T=~10     N/A           N/A     Shift running Makeup Pumps 3     T=20       N/A           N/A     Load dispatcher orders power escalation to 100%
Time Malf. No.
Value/Ramp Time Event Description 8 & 9 T=0 IMF CV1400 IMF ES259 IMF ES260 IMF CV3807 0 Ramp 0 N/A 0 Ramp 0 LPI Block valve, CV1400, does not open.
ES channels 1 and 2 fail to auto actuate  
#2 EDG SW valve fails to open when EDG autostarts 1
T=2 IMF C5A OFF Condenser Vacuum Pump C5A trips 2
T=~10 N/A N/A Shift running Makeup Pumps 3
T=20 N/A N/A Load dispatcher orders power escalation to 100%
due to grid loading.
due to grid loading.
4     T=25   IMF TR458       2280     Controlling RCS pressure fails to 2280 psig Ramp 2 Min.
4 T=25 IMF TR458 2280 Ramp 2 Min.
5    T=Spray IMF CV1008         .12     PZR Spray Valve leaks through valve closure 6     T=30   IMF ED453         N/A     SPDS failure 7     T=35   IMF RC005     .007 R 0   Small Break LOCA into the Containment Building NUREG-1021, Revision 8, Supplement 1
Controlling RCS pressure fails to 2280 psig 5
T=Spray valve closure IMF CV1008  
.12 PZR Spray Valve leaks through 6
T=30 IMF ED453 N/A SPDS failure 7
T=35 IMF RC005  
.007 R 0 Small Break LOCA into the Containment Building NUREG-1021, Revision 8, Supplement 1  


Appendix D                       Operator Actions                   Form ES-D-2 Op-Test No: 2004-1         Scenario No:   3         Event No: 1                         Page 3 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 1 Page 3 of 10 Event


== Description:==
== Description:==
Condenser Vacuum Pump, C5A, trips.
Condenser Vacuum Pump, C5A, trips.
Time   Position                               Applicants Actions or Behavior T=2     CBOR       Acknowledge and report annunciator K05 A3, Vacuum Pump Trip, alarm CRS       Refer to ACA 1203.012D for corrective action and guidance.
Time Position Applicants Actions or Behavior T=2 CBOR Acknowledge and report annunciator K05 A3, Vacuum Pump Trip, alarm CRS Refer to ACA 1203.012D for corrective action and guidance.
CBOT     Verify C5A has tripped by observing pump status on C02.
CBOT Verify C5A has tripped by observing pump status on C02.
CBOT     Manually start standby Vacuum Pump, C5B.
CBOT Manually start standby Vacuum Pump, C5B.
CRS       Initiate steps to determine cause of pump trip. Call AO to investigate.
CRS Initiate steps to determine cause of pump trip. Call AO to investigate.
CBOT     Monitor condenser vacuum for return to normal value.
CBOT Monitor condenser vacuum for return to normal value.
CRS       If condenser vacuum lowers to < 26.5 Hg, then go to Loss of Condenser Vacuum, 1203.016.
CRS If condenser vacuum lowers to < 26.5 Hg, then go to Loss of Condenser Vacuum, 1203.016.
CBOT     IF DESIRED, place the hand switch for C5A in normal-after-stop or Pull-To-Lock to clear the alarm.
CBOT IF DESIRED, place the hand switch for C5A in normal-after-stop or Pull-To-Lock to clear the alarm.
EVENT TERMINATION CRITERIA C5B started and vacuum returned to normal OR Next Event NUREG-1021, Revision 8, Supplement 1
EVENT TERMINATION CRITERIA C5B started and vacuum returned to normal OR Next Event NUREG-1021, Revision 8, Supplement 1  


Appendix D                     Operator Actions                   Form ES-D-2 Op-Test No: 2004-1         Scenario No:   3         Event No: 2                       Page 4 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 2 Page 4 of 10 Event


== Description:==
== Description:==
Shift Running Makeup pumps from P36B to P36C to equalize run times.
Shift Running Makeup pumps from P36B to P36C to equalize run times.
Time   Position                               Applicants Actions or Behavior T=10     CRS       Direct the CBOR and CBOT to shift makeup pumps by starting P36C and stopping P36B per 1104.002, Makeup and Purification System Operations Procedure.
Time Position Applicants Actions or Behavior T=10 CRS Direct the CBOR and CBOT to shift makeup pumps by starting P36C and stopping P36B per 1104.002, Makeup and Purification System Operations Procedure.
CBOT     Start P64C, Aux. Lube Oil pump for P36C.
CBOT Start P64C, Aux. Lube Oil pump for P36C.
CBOT     After one minute of P64C operation, Start P36C.
CBOT After one minute of P64C operation, Start P36C.
CBOT     Stop P64C.
CBOT Stop P64C.
CBOT     Start P64B CBOT     Stop P36B.
CBOT Start P64B CBOT Stop P36B.
CBOR       Verify proper discharge pressure on C04 and/or SPDS.
CBOR Verify proper discharge pressure on C04 and/or SPDS.
CBOT     After one minute of P64B operation, Stop P64B.
CBOT After one minute of P64B operation, Stop P64B.
CBOT     Change the pump status tags for the correct alignment.
CBOT Change the pump status tags for the correct alignment.
EVENT TERMINATION CRITERIA P36C running, P36B off NUREG-1021, Revision 8, Supplement 1
EVENT TERMINATION CRITERIA P36C running, P36B off NUREG-1021, Revision 8, Supplement 1  


Appendix D                       Operator Actions                       Form ES-D-2 Op-Test No: 2004-1         Scenario No:     3         Event No: 3                           Page 5 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 3 Page 5 of 10 Event


== Description:==
== Description:==
Power escalation to 100%.
Power escalation to 100%.
Time   Position                                 Applicants Actions or Behavior T=20     CRS       Direct the crew to continue power escalation to 100% at ~30/Hr.
Time Position Applicants Actions or Behavior T=20 CRS Direct the crew to continue power escalation to 100% at ~30/Hr.
CBOR       Begin power escalation by verifying the rate of change set at ~.5%/min. and raising the demand with the ULD station.
CBOR Begin power escalation by verifying the rate of change set at ~.5%/min. and raising the demand with the ULD station.
CBOT     Verify turbine load is rising and the turbine is maintaining header pressure at the desired setpoint.
CBOT Verify turbine load is rising and the turbine is maintaining header pressure at the desired setpoint.
CBOR       Verify Reactor power rising and feedwater flow rising to maintain proper Tave.
CBOR Verify Reactor power rising and feedwater flow rising to maintain proper Tave.
EVENT TERMINATION CRITERIA Power returned to 100%
EVENT TERMINATION CRITERIA Power returned to 100%
OR Next Event NUREG-1021, Revision 8, Supplement 1
OR Next Event NUREG-1021, Revision 8, Supplement 1  


Appendix D                         Operator Actions                     Form ES-D-2 Op-Test No: 2004-1         Scenario No:     3           Event No: 4 & 5                     Page 6 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 4 & 5 Page 6 of 10 Event


== Description:==
== Description:==
Controlling RCS pressure fails and PZR Spray Valve leaks through.
Controlling RCS pressure fails and PZR Spray Valve leaks through.
Time   Position                                   Applicants Actions or Behavior T=25   CBOR       Identify and report a disparity between RCS pressure indications.
Time Position Applicants Actions or Behavior T=25 CBOR Identify and report a disparity between RCS pressure indications.
NOTE: Crew may or may not identify the PZR Spray valve simultaneous with pressure indication failure.
NOTE: Crew may or may not identify the PZR Spray valve simultaneous with pressure indication failure.
CREW       Diagnose failed RCS pressure indication using panel indications, plant computer and SPDS. (Tech. Spec. 3.3.1A)
CREW Diagnose failed RCS pressure indication using panel indications, plant computer and SPDS. (Tech. Spec. 3.3.1A)
CBOR       If not identified earlier, report RCS pressure lowering and the pressurizer spray valve open.
CBOR If not identified earlier, report RCS pressure lowering and the pressurizer spray valve open.
CRS       Direct operation per 1203.015, PZR Systems Failures, Section 6 CBOR       Determine and report that the failed indication is controlling RCS pressure.
CRS Direct operation per 1203.015, PZR Systems Failures, Section 6 CBOR Determine and report that the failed indication is controlling RCS pressure.
CBOR       Manually close the pressurizer spray valve, CV1008.
CBOR Manually close the pressurizer spray valve, CV1008.
CBOR       Report RCS pressure continues to lower.
CBOR Report RCS pressure continues to lower.
CRS       Direct the CBOR to close the pressurizer spray isolation, CV-1009.
CRS Direct the CBOR to close the pressurizer spray isolation, CV-1009.
CT     CBOR       Close CV1009, Pressurizer Spray Valve Isolation.
CT CBOR Close CV1009, Pressurizer Spray Valve Isolation.
CRS       Direct the CBOR to select the alternate RCS pressure indication for control.
CRS Direct the CBOR to select the alternate RCS pressure indication for control.
continued NUREG-1021, Revision 8, Supplement 1
continued NUREG-1021, Revision 8, Supplement 1  


Appendix D                     Operator Actions                   Form ES-D-2 Op-Test No: 2004-1         Scenario No:   3         Event No: 4 & 5                   Page 7 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 4 & 5 Page 7 of 10 Event


== Description:==
== Description:==
Controlling RCS pressure fails and PZR Spray Valve leaks through.
Controlling RCS pressure fails and PZR Spray Valve leaks through.
Time   Position                             Applicants Actions or Behavior CBOR       Select PT1038 using the handswitch on panel C04.
Time Position Applicants Actions or Behavior CBOR Select PT1038 using the handswitch on panel C04.
CRS       Reference 1203.015, Pressurizer Systems Failures, Pressurizer Spray Valve (CV-1008) Failure section. (Tech Spec. TRM 3.4.3.A for differential temperature of spray fluid and pressurizer temperature of >430&deg;F)
CRS Reference 1203.015, Pressurizer Systems Failures, Pressurizer Spray Valve (CV-1008) Failure section. (Tech Spec. TRM 3.4.3.A for differential temperature of spray fluid and pressurizer temperature of >430&deg;F)
CBOR       Recognize and report that RCS pressure is recovering.
CBOR Recognize and report that RCS pressure is recovering.
EVENT TERMINATION CRITERIA Alternate RCS pressure instrument selected and Pressurizer Spray valve closed OR Next Event NUREG-1021, Revision 8, Supplement 1
EVENT TERMINATION CRITERIA Alternate RCS pressure instrument selected and Pressurizer Spray valve closed OR Next Event NUREG-1021, Revision 8, Supplement 1  


Appendix D                     Operator Actions                       Form ES-D-2 Op-Test No: 2004-1         Scenario No: 3               Event No: 6                       Page 8 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 6 Page 8 of 10 Event


== Description:==
== Description:==
SPDS Loss of Power.
SPDS Loss of Power.
Time   Position                                 Applicants Actions or Behavior T=30   CREW       Recognize and report the failure of the SPDS displays in the control room on panels C09 and C19.
Time Position Applicants Actions or Behavior T=30 CREW Recognize and report the failure of the SPDS displays in the control room on panels C09 and C19.
CRS       Contact Unit 2 or Computer Support to attempt to reboot the SPDS computers.
CRS Contact Unit 2 or Computer Support to attempt to reboot the SPDS computers.
CRS       Refer to 1105.014, SPDS Operation, to determine that there is a one hour time limit to restore operation of at least one SPDS system OR it will become a reportable item.
CRS Refer to 1105.014, SPDS Operation, to determine that there is a one hour time limit to restore operation of at least one SPDS system OR it will become a reportable item.
EVENT TERMINATION CRITERIA This event will exist for the remainder of the scenario.
EVENT TERMINATION CRITERIA This event will exist for the remainder of the scenario.
NUREG-1021, Revision 8, Supplement 1
NUREG-1021, Revision 8, Supplement 1  


Appendix D                         Operator Actions                   Form ES-D-2 Op-Test No: 2004-1         Scenario No: 3               Event No: 7, 8, & 9                 Page 9 of 10 Event
Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 7, 8, & 9 Page 9 of 10 Event


== Description:==
== Description:==
LOCA in the A RCS loop Tcold. ESAS channels 1 and 2 fail to auto actuate. #2 EDG service water valve fails to open when the EDG autostarts.
LOCA in the A RCS loop Tcold. ESAS channels 1 and 2 fail to auto actuate. #2 EDG service water valve fails to open when the EDG autostarts.
Time     Position                                 Applicants Actions or Behavior T=35     CBOR     Identify pressurizer level and RCS pressure dropping.
Time Position Applicants Actions or Behavior T=35 CBOR Identify pressurizer level and RCS pressure dropping.
CBOT     Recognize and report RCS leakage into the Reactor Building.
CBOT Recognize and report RCS leakage into the Reactor Building.
(Tech Spec. 3.4.13.B RCS Operational LEAKAGE)
(Tech Spec. 3.4.13.B RCS Operational LEAKAGE)
EAL 2.2, ALERT(RCS leakage >Normal Makeup capacity)
EAL 2.2, ALERT(RCS leakage >Normal Makeup capacity)
CRS     Direct actions per the Reactor Trip Procedure, 1202.001.
CRS Direct actions per the Reactor Trip Procedure, 1202.001.
CBOR     Manually trip the reactor by depressing the Rx. Trip pushbutton. Verify all rods on bottom and power dropping.
CBOR Manually trip the reactor by depressing the Rx. Trip pushbutton. Verify all rods on bottom and power dropping.
CBOT     Manually trip the turbine by depressing the Turbine Trip pushbutton CBOR/     Verify adequate subcooling margin.
CBOT Manually trip the turbine by depressing the Turbine Trip pushbutton CBOR/
CBOT CRS     Direct initiation of HPI per RT 2.
CBOT Verify adequate subcooling margin.
CRS Direct initiation of HPI per RT 2.
NOTE The crew may manually initiate ESAS due to the imminent automatic actuation prior to reaching the setpoint and therefore may not identify the failure of channel 1 and 2 to auto actuate.
NOTE The crew may manually initiate ESAS due to the imminent automatic actuation prior to reaching the setpoint and therefore may not identify the failure of channel 1 and 2 to auto actuate.
CREW       Recognize the actuation of ESAS on low RCS pressure.
CREW Recognize the actuation of ESAS on low RCS pressure.
CBOR     Identify the failure of channels 1 and 2 of ESAS to actuate.
CBOR Identify the failure of channels 1 and 2 of ESAS to actuate.
CT       CBOR     Manually initiate channel 1 and 2 from the pushbuttons on C04 CRS     Transition to ESAS procedure, 1202.010, and direct crew operations CBOR     Check for adequate subcooling margin.
CT CBOR Manually initiate channel 1 and 2 from the pushbuttons on C04 CRS Transition to ESAS procedure, 1202.010, and direct crew operations CBOR Check for adequate subcooling margin.
continued NUREG-1021, Revision 8, Supplement 1
continued NUREG-1021, Revision 8, Supplement 1  


Appendix D                       Operator Actions                     Form ES-D-2 Op-Test No: 2004-1         Scenario No: 3               Event No: 7, 8, & 9               Page 10 of 10 Event
Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 3 Event No: 7, 8, & 9 Page 10 of 10 Event


== Description:==
== Description:==
LOCA in the A RCS loop Tcold. ESAS channels 1 and 2 fail to auto actuate. #2 EDG service water valve fails to open when the EDG autostarts.
LOCA in the A RCS loop Tcold. ESAS channels 1 and 2 fail to auto actuate. #2 EDG service water valve fails to open when the EDG autostarts.
Time     Position                                 Applicants Actions or Behavior CBOT     Verify proper ESAS actuation per RT 10.
Time Position Applicants Actions or Behavior CBOT Verify proper ESAS actuation per RT 10.
CBOT     Identify the failure of the service water valve for the #2 EDG to open when the EDG autostarts.
CBOT Identify the failure of the service water valve for the #2 EDG to open when the EDG autostarts.
CBOT     Attempt to open the service water valve for #2 EDG.
CBOT Attempt to open the service water valve for #2 EDG.
CRS     Direct the stopping of the #2 EDG.
CRS Direct the stopping of the #2 EDG.
CBOT     Stop the #2 EDG by placing the #2 EDG control switch in LOCKOUT position.
CBOT Stop the #2 EDG by placing the #2 EDG control switch in LOCKOUT position.
CBOR     Close or verify closed the following valves; CV-1008, CV-1009, and CV-1000 CRS     Transition to Loss of subcooling margin procedure, 1202.002, and direct crew actions.
CBOR Close or verify closed the following valves; CV-1008, CV-1009, and CV-1000 CRS Transition to Loss of subcooling margin procedure, 1202.002, and direct crew actions.
CBOR     Control RCS pressure within limits of Figure 3 of EOP (RT 14)
CBOR Control RCS pressure within limits of Figure 3 of EOP (RT 14)
EVENT and SCENARIO TERMINATION CRITERIA All appropriate channels of ESAS actuated and HPI injecting water into RCS and RCS pressure stable.
EVENT and SCENARIO TERMINATION CRITERIA All appropriate channels of ESAS actuated and HPI injecting water into RCS and RCS pressure stable.
OR As directed by the lead examiner NUREG-1021, Revision 8, Supplement 1}}
OR As directed by the lead examiner}}

Latest revision as of 03:04, 16 January 2025

ANO 1 - January 2004-Draft Operating Examination
ML041330337
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 07/23/2003
From:
Operations Branch IV
To:
Entergy Operations
References
-RFPFR, 50-313/04-301
Download: ML041330337 (128)


Text

ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2 Page 1 of 4 UNIT:

1 REVISION #

0 DATE:

TUOI NUMBER:

A1JPM-RO-HTBAL2 SYSTEM:

A.1 - Conduct of Operations TASK:

Perform a Manual Heat Balance Calculation JTA:

ANO-RO-ADMIN-NORM-182 KA VALUE RO 2.9 SRO 4.0 KA

REFERENCE:

2.1.12 APPROVED FOR ADMINISTRATION TO:

RO X

SRO TASK LOCATION:

INSIDE CR:

OUTSIDE CR:

BOTH:

X SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):

PLANT SITE:

SIMULATOR:

PERFORM LAB:

POSITION EVALUTED:

RO X

SRO ACTUAL TESTING ENVIRONMENT:

PLANT SITE:

SIMULATOR:

X LAB:

ACTUAL TESTING METHOD:

SIMULATE:

PERFORM:

X APPROXIMATE COMPLETION TIME IN MINUTES:

45 MINUTES

REFERENCES:

1103.016 Heat Balance Calculation EXAMINEES NAME:

SSN:

EVALUATORS NAME:

THE EXAMINEES PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:

SATISFACTORY:

UNSATISFACTORY:

PERFORMANCE CHECKLIST COMMENTS:

START TIME:

STOP TIME:

TOTAL TIME:

SIGNED:

DATE:

SIGNATURE INDICATES THIS JPM HAS BEEN COMPARTED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.

ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2 Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:

It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.

All data has been recorded and 1103.016, Att. 2 has been started.

TASK STANDARD:

The examinee has correctly calculated Secondary Side Heat Balance in Att. 2, step 2.4 and Best Estimate of Reactor Power, step 2.6.

TASK PERFORMANCE AIDS:

Copies of partially completed 1103.016.

ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2 Page 3 of 4 INITIATING CUE:

The CRS requests that you complete the remainder of 1103.016, Attachment 2, Manual Heat Balance, beginning with step 9.2.

CRITICAL ELEMENTS (C):

1 (C)

PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT NOTE: Provide examinee with a copy of partially completed 1103.016.

(C)

1. Perform calculations in.

Examinee calculated %FPSEC as 99.989% per step 2.4 in Att. 2. Accept answers between 99.7 and 100.2%.

Examinee calculated %FP as 99.989% per step 2.4 in Att.

2. Accept answers between 99.7 and 100.2%.

END

ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-RO-HTBAL2 Page 4 of 4 JPM INITIAL TASK CONDITIONS:

 It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.

 All data has been recorded and 1103.016, Att. 2 has been started.

INITIATING CUE:

 The CRS requests that you complete the remainder of 1103.016, Attachment 2, Manual Heat Balance, beginning with step 9.2.

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 1 of 4 UNIT: 1 REV # 0 DATE: ______________________________

TUOI NUMBER: A1JPM-RO-DWG1 SYSTEM/DUTY AREA: ADMINISTRATIVE TOPIC - CONDUCT OF OPERATIONS TASK: DETERMINE ISOLATION BOUNDARY USING DRAWINGS AND/OR PRINTS JTA#: ENS-OPER-PTAG-ADMIN-1 KA VALUE RO:

2.8 SRO:

3.1 KA

REFERENCE:

2.1.24 APPROVED FOR ADMINISTRATION TO: RO: X SRO: X TASK LOCATION: INSIDE CR: X OUTSIDE CR:_________ BOTH:________

SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):

PLANT SITE:_______________ SIMULATOR: PERFORM LAB:__________________

POSITION EVALUATED: RO:___ __

SRO:___________

ACTUAL TESTING ENVIRONMENT: SIMULATOR:

X PLANT SITE:__________ LAB:________

TESTING METHOD: SIMULATE:_________

PERFORM:___________

APPROXIMATE COMPLETION TIME IN MINUTES:

10 MINUTES REFERENCE(S): 1107.001, M-213 sh. 2 EXAMINEE'S NAME:________________________________

SSN ______-_____-____________

EVALUATOR'S NAME:__________________________________________________________________

THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:

SATISFACTORY:________________

UNSATISFACTORY:_________________

PERFORMANCE CHECKLIST COMMENTS:

____________ Start Time

____________ Stop Time

____________ Total Time SIGNED ________________________________ DATE: _______________________

SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 2 of 4 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:



The WCO reports the Laundry Drain pump (P-45) has a severe seal leak.

INITIATING CUE:

The CRS directs you to determine the isolation boundary (electrical and mechanical) for Laundry Drain pump (P-45) in accordance with approved drawings and procedures.

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 3 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS: The WCO reports the Laundry Drain pump (P-45) has a severe seal leak.

TASK STANDARD: The examinee has correctly identified the isolation boundary for Laundry Drain pump (P-45) using controlled drawings and procedures.

TASK PERFORMANCE AIDS: Simulator drawings and procedures

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-DWG1 Page 4 of 4 INITIATING CUE:

The CRS directs you to determine the isolation boundary (electrical and mechanical) for Laundry Drain pump (P-

45) in accordance with approved drawings and procedures.

CRITICAL ELEMENTS (C) 1 (C)

PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT NOTE:

Inform examinee that this task is to identify the isolation boundary only, a tagout will not be prepared.

(C)

1. Determine isolation boundaries.

Examinee determined proper boundary isolations to include:



B3134, power supply



LZ-2A, Suction from T-19



LZ-2B, Suction from T-19



LZ-4411A, Suction from T-109



LZ-4411B, Suction from T-109



LZ-4, Discharge



Open ABS-25 casing drain(not required for full credit)

(Note: Examinee should determine boundary isolations using controlled procedures and drawings, specifically 1107.001 and M-213 sh. 2).

END

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3 Page 1 of 4 UNIT: 1 REV # 2 DATE: ______________________________

TUOI NUMBER: A1JPM-RO-SURV3 SYSTEM/DUTY AREA: ADMINISTRATIVE TOPIC - EQUIPMENT CONTROL TASK: PERFORM SURVEILLANCE TESTS JTA#: ANO-RO-ADMIN-NORM-23 KA VALUE RO:

3.0 SRO:

3.4 KA

REFERENCE:

2.2.12 APPROVED FOR ADMINISTRATION TO: RO: X SRO:

TASK LOCATION: INSIDE CR:

X OUTSIDE CR:_________ BOTH:________

SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):

PLANT SITE:_______________ SIMULATOR: PERFORM LAB:__________________

POSITION EVALUATED: RO:____ __

SRO:___________

ACTUAL TESTING ENVIRONMENT: SIMULATOR:

PLANT SITE:__________ LAB:________

TESTING METHOD: SIMULATE:_________

PERFORM:___________

APPROXIMATE COMPLETION TIME IN MINUTES:

10 MINUTES REFERENCE(S): 1104.036, Emergency Diesel Generator Operation EXAMINEE'S NAME:________________________________

SSN ______-_____-____________

EVALUATOR'S NAME:__________________________________________________________________

THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:

SATISFACTORY:________________

UNSATISFACTORY:_________________

PERFORMANCE CHECKLIST COMMENTS:

____________ Start Time

____________ Stop Time

____________ Total Time SIGNED ________________________________ DATE: _______________________

SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3 Page 2 of 4 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:



A surveillance test of DG1 Fuel Transfer Pump P-16A is in progress.



Supplement 5 of 1104.036 up to step 2.6 is completed.

INITIATING CUE:

The CRS directs you to complete the surveillance test of P-16A in accordance with 1104.036, Supplement 5.

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3 Page 3 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS: A surveillance test of DG1 Fuel Transfer Pump P-16A is in progress.

Data gathering of Supplement 5 of 1104.029 up to step 2.6 is completed.

TASK STANDARD: The examinee calculates pump flow rate correctly on Supplement 5 of 1104.036 and determines the data is below the minimum in the acceptance criteria.

TASK PERFORMANCE AIDS: 1104.036, Supplement 5, completed to step 2.6.

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-SURV3 Page 4 of 4 INITIATING CUE:

The CRS directs you to complete the surveillance test of P-16A in accordance with 1104.036, Supplement 5.

CRITICAL ELEMENTS (C) 2, 3, 4 (C)

PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT

1. Review 1104.036, Supplement 5.

Examinee reviewed 1104.036, Supplement 5.

NOTE: Inform examinee that the stopwatch reads 9:41.36 (9 minutes, 41.36 seconds).

(C)

2. Calculate pump flow rate.

Examinee correctly calculated pump flow rate.

Per note, 41.36 seconds equals.68 minutes.

(200 - 105) / 9.68 = 9.81 gpm (C) 3 Record flow rate in Section 3.0.

Examinee recorded flow rate in Section 3.0.

(C) 4 Evaluate flow rate, compare to LIMITING RANGE FOR OPERABILITY value.

Examinee circled NO in column titled IS DATA WITHIN LIMITING RANGE.

Examinee discussed declaring pump inoperable, notifying SM, writing Condition Report, initiating corrective action, and referring to Tech Specs.

NOTE:

The SM or CRS will consult Tech Specs to determine operability, it is the ROs responsibility to report the inoperability of P-16A only. Diesel operability will be determined by the SM/CRS.

Inform examinee that steps 2.8 through 2.11 have been completed.

END

TUOI NUMBER:

Page 1 of 4 A1JPM-RO-DOSE-XX JOB PERFORMANCE MEASURE Unit:

1 Rev #

1 Date:

1/12/2004 TUOI NUMBER:

A1JPM-RO-DOSE-XX System/Duty Area:

Administrative Topic-Radiation Control Task:

Calculate Stay times for yourself and another operator JA#

KA Value RO 2.6 SRO 3.3 KA Reference G 2.3.10 Approved For Administration To: RO SRO Task Location: Inside CR:

Outside CR:

Both:

Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:

Simulator:

Perform Lab:

Position Evaluated: RO:

X SRO:

X Actual Testing Environment: Simulator:

Plant Site:

Lab Testing Method: Simulate:

Perform:

Approximate Completion Time In Minutes:

10 Minutes Reference(S):

HP Survey Map of P36C, Pump Room 54.

Examinee's Name:

SSN:

Evaluator's Name:

The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:

Satisfactory:

Unsatisfactory:

Performance Checklist Comments:

Start Time Stop Time Total Time Signed Date:

Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.

TUOI NUMBER:

Page 2 of 4 A1JPM-RO-DOSE-XX THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:

You are an AO with the plant at full power. A hot spot has developed on Makeup PUMP P36C. You and another AO will be working in the vicinity of the reduction gear assembly in order to flush the lines reduce the hot spot radiation field.

Using the supplied survey map, determine the individual stay times for yourself AND the other AO without exceeding the annual administrative dose limit (Ignore dose received during transit). You have an accumulated annual Whole Body dose of 1805 mR (ANO records). The other AO has an accumulated annual Whole Body dose of 1820 mR (ANO records). No additional dose has been received at any other site.

Also, calculate stay time if the air in the pump room was contaminated with a level of 0.29 DAC (stochastic) assuming no respirators are used.

Calculations should be based on ANO Unit 1 Administrative dose limits. Provide answers with 3 significant figures (example 4.50). Do not consider ALARA task requirements. Any required dose extensions have been processed and approved.

TASK STANDARD:

The examinee has correctly determined the stay times for himself and the other AO on the assignment.

TASK PERFORMANCE AIDS:

HP Survey map of P36C Pump Room, Room number 54.

SIMULATOR SETUP:

N/A

TUOI NUMBER:

Page 3 of 4 A1JPM-RO-DOSE-XX INITIATING CUE: Determine the Stay time for you and the other AO on the job. Also determine the stay time if the air in the pump room was contaminated with a level of 0.29 DAC (stochastic) assuming no respirators are used. Provide answers with 3 significant figures (example 4.50).

CRITICAL ELEMENTS (c): 1,2, and 3 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT C

1. Determine the HIGHEST general area dose rate in the area of the reduction gear assembly to be used from the survey map.

Examinee has determined the HIGHEST general area dose rate in the area of the reduction gear assembly to be used from the survey map of P36C pump room.

(60 mR/hr)

C

2. Determine Stay time (to 3 significant figures) with no airborne contamination for both operators.

Examinee has determined that the stay time for him/her is 3.25 hrs and the stay time for the other AO is 3.00 hrs plus or minus 0.01 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

C

3. Determine Stay time( to 3 significant figures) WITH airborne contamination for both operators.

Examinee has determined that the stay time for him/her is 3.21hrs and the stay time for the other AO is 2.96 hrs plus or minus 0.01 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

EXAMINERS CUE: This concludes the JPM.

END

TUOI NUMBER:

A1JPM-RO-DOSE-XX Page 4 of 4 EXAMINEES COPY INITIAL CONDITIONS:

You are an AO with the plant at full power. A hot spot has developed on Makeup PUMP P36C. You and another AO will be working in the vicinity of the reduction gear assembly in order to flush the lines reduce the hot spot radiation field.

Using the supplied survey map, determine the individual stay times and another AO without exceeding the annual administrative dose limit (Ignore dose received during transit). You have an accumulated annual Whole Body dose of 1810 mR (ANO records). The other AO has an accumulated annual Whole Body dose of 1820 mR (ANO records). No additional dose has been received at any other site.

Also calculate stay time if the air in the pump room was contaminated with a level of 0.29 DAC (stochastic) assuming no respirators are used.

Calculations should be based on ANO Unit 1 Administrative dose limits. Provide answers with 3 significant figures (example 4.50). Do not consider ALARA task requirements. Any required dose extensions have been processed and approved.

INITIATING CUE:

Determine the Stay time for you and the other AO on the job. Also determine stay time if the air in the pump room was contaminated with a level of 0.29 DAC (stochastic) assuming no respirators are used. Provide answers with 3 significant figures (example 4.50).

TUOI NUMBER:

A1JPM-RO-EP-XX Administrative Questions Page 1 of 4 JOB PERFORMANCE MEASURE Unit:

1 Rev #

1 Date:

1/12/2004 TUOI NUMBER:

A1JPM-RO-EP-XX System/Duty Area:

Administrative Topic-Emergency Plan Task:

Answer two questions regarding RO responsibilities in Emergency Plan implementation JA#

KA Value RO 3.3 SRO 3.1 KA Reference G 2.4.39 Approved For Administration To: RO SRO Task Location: Inside CR:

Outside CR:

Both:

Suggested Testing Environment And Method (Perform Or Simulate): Perform Plant Site:

Simulator:

Perform Lab:

Position Evaluated: RO:

X SRO:

Actual Testing Environment: Simulator:

Plant Site:

Lab Testing Method: Simulate:

Perform:

Approximate Completion Time In Minutes:

10 Minutes Reference(S):

1903.030, change 024-03-0, step 6.2.2c.

1903.011, change 024-03-0, form YY.

Examinee's Name:

SSN:

Evaluator's Name:

The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:

Satisfactory:

Unsatisfactory:

Performance Checklist Comments:

Start Time Stop Time Total Time Signed Date:

Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.

TUOI NUMBER:

A1JPM-RO-EP-XX Administrative Questions Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.

Type: Closed Reference Completion Time: 10 minutes Question 1: You are attending requal training in the RETC. A plant evacuation is announced. What is your assembly area?

Q1 Answer : The Operations Support Center (OSC).

Reference:

1903.030, change 024-03-0, step 6.2.2c.

Comments:

Question 2: After declaring an emergency, how soon must the ADH be notified?

Q2 Answer : 15 minutes

Reference:

1903.011, change 024-03-0, form YY.

Comments:

TASK STANDARD:

The examinee has correctly answered both questions.

TUOI NUMBER:

A1JPM-RO-EP-XX Administrative Questions Page 3 of 4 EXAMINEES COPY Type: Closed Reference Completion Time: 10 minutes Question 1: You are attending requal training in the RETC. A plant evacuation is announced. What is your assembly area?

Comments:

Question 2: After declaring an emergency, how soon must the ADH be notified?

Comments:

ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1 Page 1 of 4 UNIT:

1 REVISION #

0 DATE:

TUOI NUMBER:

A1JPM-SRO-HTBAL1 SYSTEM:

A.1 - Conduct of Operations TASK:

Review a Manual Heat Balance Calculation JTA:

ANO-SRO-ADMIN-NORM-200 KA VALUE RO 2.9 SRO 4.0 KA

REFERENCE:

2.1.12 APPROVED FOR ADMINISTRATION TO:

RO SRO X

TASK LOCATION:

INSIDE CR:

OUTSIDE CR:

BOTH:

X SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):

PLANT SITE:

SIMULATOR:

PERFORM LAB:

POSITION EVALUTED:

RO SRO X

ACTUAL TESTING ENVIRONMENT:

PLANT SITE:

SIMULATOR:

X LAB:

ACTUAL TESTING METHOD:

SIMULATE:

PERFORM:

X APPROXIMATE COMPLETION TIME IN MINUTES:

45 MINUTES

REFERENCES:

1103.016 Heat Balance Calculation EXAMINEES NAME:

SSN:

EVALUATORS NAME:

THE EXAMINEES PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:

SATISFACTORY:

UNSATISFACTORY:

PERFORMANCE CHECKLIST COMMENTS:

START TIME:

STOP TIME:

TOTAL TIME:

SIGNED:

DATE:

SIGNATURE INDICATES THIS JPM HAS BEEN COMPARTED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.

ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1 Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:

It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.

The CBOT has completed 1103.016, Heat Balance Calculation, and calculated Rx thermal power to be 101.483%.

NIs are reading an average of 99.1%. The CBOTs math has been verified to be correct by an extra RO.

TASK STANDARD:

The examinee has correctly identified two of four errors in Heat Balance Calculation.

TASK PERFORMANCE AIDS:

Copies of completed 1103.016.

ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1 Page 3 of 4 INITIATING CUE:



Review the operators completed 1103.016 and complete section 11.0.



In addition, verify compliance with Technical Specification SR 3.3.1.2..

CRITICAL ELEMENTS (C):

1, 3 (C)

PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT NOTE: Provide examinee with a copy of completed 1103.016. Examinee may state initially that the as performed Heat Balance would require adjustment of NIs to be in compliance with Tech Spec SR 3.3.1.2.

(C)

1. Review 1103.016.

Examinee reviewed 1103.016.

Examinee discovered two of four errors in calculations.

1. Step 2.4 value used for Q losses was taken from step 2.2 vs. 2.3.
2. Step 2.5 a value of 600 was given for HHA instead of real value.
3. Step 2.5 value used for Q losses was taken from step 2.2 vs. 2.3.
4. Step 2.6 % full power calculation is incorrect due to above errors.
2. Instruct CBOT to re-perform 1103.016.

Examinee stated that 1103.016 should be re-performed.

NOTE: Inform examinee that 1103.016 has been re-performed and calculated Rx thermal power is 99.99%.

(C)

3. Verify compliance with Technical Specification surveillance SR 3.3.1.2.

Examinee concludes that SR 3.3.1.2 as recalculated Rx thermal power is within 2% of initial NI readings.

END

ADMINISTATIVE JOB PERFORMANCE MEASURE A1JPM-SRO-HTBAL1 Page 4 of 4 JPM INITIAL TASK CONDITIONS:

 It is desired to verify the accuracy of the PMS calculated Rx Thermal Power (XPP) in order to ensure compliance with Technical Specification SR 3.3.1.2.

 The CBOT has completed 1103.016, Heat Balance Calculation, and calculated Rx thermal power to be 101.483%

 NIs are reading an average of 99.1%.

 The CBOTs math calculations have been verified to be correct by an extra RO.

INITIATING CUE:

 Review the operators completed 1103.016 and complete section 11.0.

 In addition, verify compliance with Technical Specification SR 3.3.1.2.

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4 Page 1 of 4 UNIT: 1 REV # 0 DATE: ______________________________

TUOI NUMBER: A1JPM-SRO-SURV4 SYSTEM/DUTY AREA: ADMINISTRATIVE TOPIC - CONDUCT OF OPERATIONS TASK: MONITOR CONDUCT OF SHIFT SURVEILLANCE TESTS JTA#: ANO-SRO-ADMIN-NORM-200 KA VALUE RO:

3.0 SRO:

3.4 KA

REFERENCE:

2.2.12 APPROVED FOR ADMINISTRATION TO: RO:

SRO:

X TASK LOCATION: INSIDE CR:

OUTSIDE CR:_________ BOTH:____X____

SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):

PLANT SITE:_______________ SIMULATOR: PERFORM LAB:__________________

POSITION EVALUATED: RO:____ __

SRO:___________

ACTUAL TESTING ENVIRONMENT: SIMULATOR:

PLANT SITE:__________ LAB:________

TESTING METHOD: SIMULATE:_________

PERFORM:___________

APPROXIMATE COMPLETION TIME IN MINUTES:

20 MINUTES REFERENCE(S): 1106.006, Emergency Feedwater Pump Operation EXAMINEE'S NAME:________________________________

SSN ______-_____-____________

EVALUATOR'S NAME:__________________________________________________________________

THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:

SATISFACTORY:________________

UNSATISFACTORY:_________________

PERFORMANCE CHECKLIST COMMENTS:

____________ Start Time

____________ Stop Time

____________ Total Time SIGNED ________________________________ DATE: _______________________

SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4 Page 2 of 4 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:



The quarterly test of Emergency Feedwater Pump (P-7B) per 1106.006, Supplement 11, was performed on the previous shift.

 The SM is performing Section 4, Shift Manager Review and Analysis.

INITIATING CUE:

 The SM requests that you conduct a peer review of the test since he has found some errors.

 Identify at least 2 errors in the test.

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4 Page 3 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS: The quarterly test of Emergency Feedwater Pump (P-7B) per 1106.006, Supplement 11, was performed on the previous shift. The SM is performing Section 4, Shift Manager Review and Analysis.

TASK STANDARD: The examinee has reviewed 1106.0006, Supplement 11 and identified at least 2 administrative errors in the test.

TASK PERFORMANCE AIDS: Completed 1106.0006, Supplement 11.

ADMINISTRATIVE JOB PERFORMANCE MEASURE TUOI: A1JPM-SRO-SURV4 Page 4 of 4 INITIATING CUE:



The SM requests that you conduct a peer review of the test since he has found some errors.



Identify at least 2 errors in the test.

CRITICAL ELEMENTS (C) 2 (C)

PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT

1. Review 1106.006, Supplement 11.

Examinee reviewed 1106.006, Supplement 11.

(C)

2. Identify at least 2 administrative errors.

Examinee identified at least 2 of the following administrative errors:



Independent verification initials missing in step 1.2.1.



Entry into T.S. time clock step was N/Ad at step 2.1.4.



Acceptance Criteria Table 4, EFW Test Recirc Flow FI-2888 recorded as 532 gpm and YES circled when this value is greater than Limiting Range for Operability.



Stopwatch cal due date has expired in step 3.2.1.

END

TUOI NUMBER:

A1JPM-SRO-XX Page 1 of 4 JOB PERFORMANCE MEASURE Unit:

1 Rev #

1 Date:

1/12/2004 TUOI NUMBER:

A1JPM-SRO-XX System/Duty Area:

Administrative Topic-Emergency Procedures/Plan Task:

Determine Emergency Action Level after Scenario #3 of OP test.

JA#

KA Value RO SRO 4.1 KA Reference G 2.4.41 Approved For Administration To: RO SRO Task Location: Inside CR:

Outside CR:

Both:

Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:

Simulator:

Perform Lab:

Position Evaluated: RO:

SRO:

X Actual Testing Environment: Simulator:

Plant Site:

Lab Testing Method: Simulate:

Perform:

Approximate Completion Time In Minutes:

5 Minutes Reference(S):

1903.010 Emergency Action Level Classification, 1903.011, Emergency Response Notifications Examinee's Name:

SSN:

Evaluator's Name:

The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:

Satisfactory:

Unsatisfactory:

Performance Checklist Comments:

Start Time Stop Time Total Time Signed Date:

Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.

TUOI NUMBER:

A1JPM-SRO-XX Page 2 of 4 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:

The following conditions existed at the end of Scenario 3:

Unit 1 Reactor was tripped due to SB LOCA with SCM lost and it will not be restored. All appropriate ESAS channels had actuated and Full HPI was injecting water into the RCS with pressure stable and being controlled close to the saturation line (may even be on it) but within the limits of Figure 3 of EOP (RT14). No fuel clad failure was indicated.

TASK STANDARD:

Examinee correctly classifies this event as an Site Area Emergency per EAL 2.4 and makes notifications to plant personnel per 1903.011M.

TASK PERFORMANCE AIDS:

1903.010 Attachments 1 and 3, 1903.011 Attachment 2, and 1903.011M SIMULATOR SETUP:

N/A

TUOI NUMBER:

A1JPM-SRO-XX Page 3 of 4 INITIATING CUE: For the given plant conditions, determine the applicable EAL classification and initiate notifications per the applicable Shift Manager Emergency Direction and Control Checklist in 1903.011.

CRITICAL ELEMENTS (c): 3and 6 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT

1. Compare event conditions with the Index of EALs, of 1903.010, Emergency Action Level Classification.

Turned to Attachment 1 of 1903.010, Index of EALs.

2. Turn to appropriate EAL and compare EAL criteria with event conditions.

Turned to a specific EAL in Safety System Function, Attachment 3 of 1903.010.

C

3. Declare the emergency classification.

Declared or stated the event is an SAE per EAL 2.4, based on RCS leakage greater than normal makeup capacity (not required to be stated), no fuel clad damage, and SCM not restored.

4. Initiate immediate notifications.

Referred to 1903.011 and turned to Attachment 2.

NOTE: Cue the examinee that the Unit 2 Shift Engineer is performing the initial notifications per 1903.011 after the examinee has stated that Unit 2 Shift Engineer (or control room communicator) has been requested.

5. Begin completion of form 1903.011M, Alert Emergency Direction and Control Checklist for Shift Manager.

Began completion of form 1903.011M Alert Emergency Direction and Control Checklist for Shift Manager.

Examinee should fill in the data on items 1 and 2.

Examinee should simulate (or state) direction of the SE to complete the initial notification.

C

6. (Simulate) Announce emergency on plant paging system.

Used plant-paging system to (simulate) make announcement per step 4 of form 1903.011M.

EXAMINERS CUE: This concludes the JPM.

END

TUOI NUMBER:

A1JPM-SRO-XX Page 4 of 4 EXAMINEES COPY INITIAL CONDITIONS:

The initial conditions for this jpm are the plant conditions when scenario #3 was terminated.

INITIATING CUE:

For the given plant conditions, determine the applicable EAL classification and initiate notifications per the applicable Shift Manager Emergency Direction and Control Checklist in 1903.011.

TUOI NUMBER:

Page 1 of 5 A1JPM-RO-CRD02 JOB PERFORMANCE MEASURE Unit:

1 Rev #

4 Date:

TUOI NUMBER:

A1JPM-RO-CRD02 System/Duty Area:

CONTROL ROD DRIVE SYSTEM Task:

Perform Transfer To Auxiliary Supply JA#

ANO1-RO-CRD-NORM-12 KA Value RO 3.4 SRO 3.4 KA Reference 001 A4.03 Approved For Administration To: RO SRO Task Location: Inside CR:

Outside CR:

Both:

Suggested Testing Environment And Method (Perform Or Simulate):

Plant Site:

Simulator:

Perform Lab:

Position Evaluated: RO:

SRO:

Actual Testing Environment: Simulator:

Plant Site:

Lab Testing Method: Simulate:

Perform:

Approximate Completion Time In Minutes:

15 Minutes Reference(S):

1105.009 Examinee's Name:

SSN:

Evaluator's Name:

The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:

Satisfactory:

Unsatisfactory:

Performance Checklist Comments:

Start Time Stop Time Total Time Signed Date:

Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.

TUOI NUMBER:

Page 2 of 5 A1JPM-RO-CRD02 TUOI NUMBER:

ANO-1-JPM-RO-CRD02 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:

Rx demand and diamond stations are in manual. Preparation to exercise rods per Supplement 2, 1105.009, is in progress.

TASK STANDARD:

Group 1 Rods have been transferred to the Auxiliary Power Supply and are enabled for being moved on that power supply in run speed.

TASK PERFORMANCE AIDS:

1105.009, Section 8.0

TUOI NUMBER:

Page 3 of 5 A1JPM-RO-CRD02 TUOI NUMBER:

ANO-1-JPM-RO-CRD02 INITIATING CUE:

The CRS/SM directs you to transfer Group 1 Rods to the Auxiliary Power Supply for movement of Group 1 at run speed. IAW 1105.009, Section 8.0 CRITICAL ELEMENTS (c): 2, 3, 5, 6, 7, 8, 9, 10, 11 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT INSTRUCTOR NOTE:

Verify the Reactor Demand and Diamond are in manual.

1. Verify transfer reset lamp is ON and TR CF is OFF.

On CRD Diamond Panel, condition of both lights was checked. Transfer reset lamp was ON and TR CF lamp was OFF.

C

2. Place Group select switch to Group 1.

On CRD Diamond Panel, Group Select Switch was placed in Group 1 position.

C

3. Select Single Select Switch to ALL.

On CRD Diamond Panel, Single select switch was selected to ALL.

4. Set Auto/Manual Switch to Manual, verify Manual Lamp is ON.

On CRD Diamond Panel, verified manual lamp ON or Auto/Manual pushbutton depressed to select MANUAL.

C

5. Set SEQ.- SEQ OR. switch to SEQ. OR position.

On CRD Diamond Panel, SEQ.-

SEQ OR. switch was selected to SEQ. OR position.

TUOI NUMBER:

Page 4 of 5 A1JPM-RO-CRD02 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT C

6. Set Group/Auxiliary Switch to Auxiliary. Aux PB.

On CRD Diamond Panel, Group/Aux. PB was selected to Aux.

C

7. Set Speed Select Switch to "JOG".

On CRD Diamond Panel, Speed Select Switch was selected to JOG position.

C

8. Set Clamp/Clamp Release Switch to CLAMP.

On CRD Diamond Panel, selected Clamp/Clamp Release Switch to CLAMP.

C

9. Press Manual Transfer Switch.

On CRD Diamond Panel, manual transfer PB was depressed.

C

10. Set Clamp/Clamp Release Switch to Clamp Release.

On CRD Diamond Panel, depressed Clamp/Clamp Release Switch.

C

11. Set Group/ AUX switch to Group.

On CRD Diamond Panel, Group/Aux PB was selected to Group.

12. If movement at RUN speed is desired, set speed switch to RUN.

On CRD Diamond Panel, Speed Select Switch was selected to RUN position.

END

TUOI NUMBER:

A1JPM-RO-CRD02 Page 5 of 5 EXAMINEES COPY INITIAL CONDITIONS:

 Preparation to exercise rods per Supplement 2, 1105.009, is in progress.

 Rx Demand and Diamond stations are in manual.

INITIATING CUE:

The CRS/SM directs you to transfer Group 1 Rods to the Auxiliary Power Supply for movement of Group 1 at run speed. IAW 1105.009, Section 8.0.

TUOI NUMBER:

A1JPM-RO-Page 1 of 6 JOB PERFORMANCE MEASURE Unit:

1 Rev #

1 Date:

TUOI NUMBER:

A1JPM-RO-System/Duty Area:

002 Reactor Coolant System Task:

Restart a Make-up Pump following an RCS leak isolation JA#

ANO1-RO-KA Value RO 4.3 SRO 4.4 KA Reference 002.A2.01 Approved For Administration To: RO SRO Task Location: Inside CR:

Outside CR:

Both:

Suggested Testing Environment And Method (Perform Or Simulate):

Plant Site:

Simulator:

Perform X Lab:

Position Evaluated: RO:

X SRO:

X Actual Testing Environment: Simulator:

Plant Site:

Lab Testing Method: Simulate:

Perform:

Approximate Completion Time In Minutes:

20 Minutes Reference(S):

AOP 1203.026 Examinee's Name:

SSN:

Evaluator's Name:

The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:

Satisfactory:

Unsatisfactory:

Performance Checklist Comments:

Start Time Stop Time Total Time Signed Date:

Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.

TUOI NUMBER:

A1JPM-RO-Page 2 of 6 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:

You are the CBOR and section 2 of AOP 1202.026 was entered because of a small leak in the Makeup system on the discharge side of the pumps. The reactor was tripped and the plant is stable in Mode 3 conditions. All Makeup pumps had to be stopped to repair the leak. The leak has been repaired. Make up pump line up: P-36A is ES, P-36B is OP, P-36C is STBY. RCP seal bleedoff temperature is 1600F.

TASK STANDARD:

Restart a Makeup pump following RCS leak isolation per section 2 of Procedure 1203.026, starting with step 3.6.6.

TASK PERFORMANCE AIDS:

Radio (may be simulated), copy of section 2 AOP 1203.026, steps 3.6.6 - 3.7.

SIMULATOR SETUP:

1. Trip reactor
2. Perform 1202.001 rx trip, with enclosures as appropriate
3. Allow plant to stabilize (OTSG on LLL, DFT stable)
4. Lower PZR level SP to 100
5. Allow PZR level to reach 100
6. Initialize MUT at 80
7. When PZR level reaches 100 close all Make up valves
8. Shutdown all running Makeup pumps
9. Store IC

TUOI NUMBER:

A1JPM-RO-Page 3 of 6 INITIATING CUE:

The CRS/SM directs you to restart Makeup Pump P-36C (STBY pump) IAW section 2 of AOP 1203.026, starting with step 3.6.6 CRITICAL ELEMENTS (c): 3, 8, 9 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT INSTRUCTOR NOTE: Examinee may review the AOP 1203.0126 prior to starting the JPM.

1. Verify Makeup Tank outlet (CV-1275) is open (step 3.6.6A of procedure)

Operator verifies CV-1275 open.

2. Add to Makeup tank as necessary to maintain level

> 55 using current RCS boron concentration.

(step 3.6.6B of procedure)

Operator verifies MUT level is

> 55.

C

3. Start Aux Lube Oil pump for STBY HPI pump (P-36C). (step 3.6.7 of procedure is conditional on STBY HPI pump being available which was given as the initial condition).

Operator rotates control handle for P-36C aux lube oil pump and verifies that red light is on, green light is off.

4. Review SPDS data for HPI pump suction pressure history, leak location, and lowest suction pressure achieved. (This is the BOXED NOTE prior to step 3.6.10 in the procedure).

See Cue below NOTE: Operator should skip step 3.6.10 since pump venting is not required.

Operator should review the SPDS data and determine that no pump venting is required.

See Cue below INSTRUCTOR NOTE: Examinee must review the SPDS.

INSTRUCTOR CUE: The lowest suction pressure for the STBY pump should be around 25psig. If the SPDS is not available, then instructor must cue this value. No loss of pump suction occurred therefore candidate should NOT try to vent pump.

5. Verify HPI suction pressure >10psig.

(step 3.6.11)

Operator verifies suction pressure

>10psig.

TUOI NUMBER:

A1JPM-RO-Page 4 of 6 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT

6. Verify the following valves in HAND and CLOSED:

CV-1207 (seal injection supply)

CV-1235 (normal makeup supply)

(step 3.6.12)

NOTE: Operator should skip step 3.6.13 since ES pump is not used.

7. Operator verifies white light for HAND is on and red light for AUTO is off for both CV-1207 (seal injection supply) and CV-1235 (normal makeup supply) and valves both indicate CLOSED with corresponding valve position indicator green lights ON and red lights OFF.

C

8. After AUX lube oil pump has run for > 1 minute, start the STBY HPI pump.

(step 3.6.14)

Operator verifies red light is lit for AUX lube oil pump and places hand control switch for STBY HPI pump P-36C to start.

Verifies the red light ON and green light OFF for P-36C.

C

9. Stop the AUX lube oil pump for the STBY HPI pump (P-36C).

(step 3.6.15)

Operator places the hand control switch for the AUX lube oil pump (for P-36C) to the OFF position and verifies green light ON and red light OFF.

10. Place CV-1206 pushbutton to OVRD. Open CV-1206 (seal injection isolation valve).

(steps 3.6.16 and 3.6.17)

Operator pushes CV-1206 button, observes OVRD light is ON, and places the valve hand switch to open position and observes red light ON and green light OFF.

11. Slowly open CV-1207 (seal injection control valve) and adjust seal flow to 30-40gpm and place valve in AUTO.

(step 3.6.18B)

NOTE: step B is used because RCP bleedoff temperature should be 160 0F or less.

Operator slowly turns hand switch CCW for CV-1207 in order to open it enough to get 30-40gpm flow and place mode switch for the valve in AUTO and observe red light is ON, white light is OFF.

12. When RCP seals total flow is above setpoint (CV-1206 FLOW light ON), return CV-1206 OVRD pushbutton to normal (OVRD light off).

(step 3.6.19)

Operator should observe CV-1206 FLOW light is ON and then push the OVRD pushbutton in to return it to normal and observe the OVRD light is OFF.

TUOI NUMBER:

A1JPM-RO-Page 5 of 6 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT C

13. Slowly open CV-1235 until makeup flow indication is on-scale and adjust CV-1235 setpoint to desired value and place in AUTO.

(steps 3.6.20 and 3.6.21)

Operator should SLOWLY turn CV-1235 position switch CCW to open the valve and watch for flow indications on scale. Operator should then adjust the SP to a nominal value, place valve hand station in AUTO and observe white light OFF and RED light ON.

C

14. Re-establish letdown.

(step 3.7)

JPM is complete Operator places hand station for letdown isolation valve CV-1221 to CCW position to initiate letdown and observes letdown flow rate and red light ON and green light OFF (for valve open indication).

END

TUOI NUMBER:

A1JPM-RO-Page 6 of 6 EXAMINEES COPY INITIAL CONDITIONS:

You are the CBOR and AOP 1202.026 was entered because of a small leak in the Makeup system on the discharge side of the pumps. The reactor was tripped and the plant is stable in Mode 3 conditions. All Makeup pumps had to be stopped to repair the leak. The leak has been repaired. Make up pump line up: P-36A is ES, P-36B is OP, P-36C is STBY. RCP seal bleedoff temperature is 1600F.

INITIATING CUE:

The CRS/SM directs you to restart Makeup Pump P-36C (STBY pump) IAW AOP 1203.026, starting with step 3.6.6.

PROC./WORK PLAN NO. PROCEDURE/WORK PLAN TITLE: PAGE: 8 of 1203.026 11 LOSS OF REACTOR COOLANT MAKEUP CHANGE: 009-04-0 SECTION 2 -- LARGE MAKEUP AND PURIFICATION SYSTEM LEAK (continued)

NOTE The SPDS Safety System Diagnostic Inst. display contains the previous 20 minutes of data.

3.6.4 Select Safety System Diagnostic Inst. display on SPDS for OP HPI pump and evaluate suction pressure and flow stability prior to event.

3.6.5 If radiation levels prohibit leak isolation, perform the following:

A. Open BWST Outlet (CV-1407 or CV-1408) to ES HPI pump.

B. Operate ES HPI pump and associated HPI Block valve (CV-1220 or CV-1285) only as necessary to maintain RCS inventory.

C. GO TO step 3.7.

3.6.6 When system leakage has been isolated, perform the following:

A. Verify Makeup Tank Outlet (CV-1275) open.

B. Add to MU tank as necessary to maintain level 55" using current RCS boron concentration.

3.6.7 If STBY HPI pump is available, perform the following:

A. Start AUX lube oil pump for STBY HPI pump.

B. GO TO step 3.6.10 to place STBY HPI pump in service.

3.6.8 If STBY HPI pump is not available, and OP HPI pump damage is not suspected, perform the following:

A. Start AUX lube oil pump for OP HPI pump.

B. GO TO step 3.6.10 to place OP HPI pump in service.

3.6.9 If both OP and STBY HPI pumps are not available, perform the following:

A. Start AUX lube oil pump for ES HPI pump.

B. Place ES standby HPI pump in service per step 3.6.10.

PROC./WORK PLAN NO. PROCEDURE/WORK PLAN TITLE: PAGE: 8 of 1203.026 11 LOSS OF REACTOR COOLANT MAKEUP CHANGE: 009-04-0 SECTION 2 -- LARGE MAKEUP AND PURIFICATION SYSTEM LEAK (continued)

NOTE Decision to vent HPI pump should be based on suction pressure from SPDS history as well as leak location and lowest suction pressure achieved.

3.6.10 If loss of pump suction was indicated, perform the following:

A. If ES HPI pump is being re-aligned per Attachment A, verify associated P-36 Makeup Pump Suction Cross-Over open prior to venting.

B. Vent pump using applicable Makeup Pump P-36 Vent to ABV Header:

P-36A P-36B P-36C ABV-9A ABV-9B ABV-9C 3.6.11 Verify HPI pump suction pressure >10 psig.

3.6.12 Verify the following valves in HAND and closed:

  • CV-1207
  • CV-1235 3.6.13 If ES HPI pump will be used, verify Attachment A steps 1 through 6 complete.

CAUTION Operation of Aux Lube Oil Pump with HPI/MU Pump running should be minimized.

3.6.14 After AUX lube oil pump has run for 1 minute, start HPI pump.

3.6.15 Stop AUX lube oil pump for HPI pump.

3.6.16 Place CV-1206 pushbutton in OVRD (OVRD light on).

3.6.17 Open CV-1206.

3.6.18 Slowly open CV-1207 as follows:

A. If seal bleedoff temperature is >180°F, establish and maintain 8 to 12 gpm RCP Seal Total INJ Flow until <180°F.

PROC./WORK PLAN NO.

1203.026 PROCEDURE/WORK PLAN TITLE: PAGE: 8 of 11 LOSS OF REACTOR COOLANT MAKEUP CHANGE: 009-04-0 B. When seal bleedoff temperature is <180°F, adjust CV-1207 for 30-40 gpm and place in AUTO.

SECTION 2 -- LARGE MAKEUP AND PURIFICATION SYSTEM LEAK (continued) 3.6.19 When RCP Seals Total INJ Flow is above setpoint (CV-1206 FLOW light on),

return CV-1206 OVRD pushbutton to normal (OVRD light off).

3.6.20 Slowly open CV-1235 until makeup flow indication is on-scale.

3.6.21 Adjust CV-1235 setpoint to desired value and place in AUTO.

3.7 If normal makeup is in service, reestablish letdown.

TUOI NUMBER:

Page 1 of 6 A1JPM-RO-JOB PERFORMANCE MEASURE Unit:

1 Rev #

1 Date:

TUOI NUMBER:

A1JPM-RO-System/Duty Area:

Task:

Perform ERV (PSV-1000) Exercise Test JA#

ANO1-RO-KA Value RO 3.0 SRO 3.2 KA Reference 010.A3.01 Approved For Administration To: RO SRO Task Location: Inside CR:

Outside CR:

Both:

Suggested Testing Environment And Method (Perform Or Simulate):

Plant Site:

Simulator:

Perform X Lab:

Position Evaluated: RO:

X SRO:

X Actual Testing Environment: Simulator:

Plant Site:

Lab Testing Method: Simulate:

Perform:

Approximate Completion Time In Minutes:

10 Minutes Reference(S):

OP 1103.005 Supplement 1 (change 030-02-0), 1203.012H (change 031-03-0),

and AOP 1203.015 (change 011-00-0)

Examinee's Name:

SSN:

Evaluator's Name:

The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:

Satisfactory:

Unsatisfactory:

Performance Checklist Comments:

Start Time Stop Time Total Time Signed Date:

Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.

TUOI NUMBER:

Page 2 of 6 A1JPM-RO-THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:

You are the CBOR and you are directed by the CRS to perform OP 1103.005, Supplement 1, Exercising of the Pressurizer Electromatic Relief Valve (PSV-1000) in order to meet the regularly scheduled 18 month test. The plant conditions are as follows:

RC Temperature = 1200F RC Pressure = 55 psig TASK STANDARD:

Perform the ERV exercise test per OP 1103.005, Supplement 1 (change 030-02-0).

TASK PERFORMANCE AIDS:

Stopwatch, Radio (may be simulated), copy of OP 1103.005, Supplement 1 (change 030-02-0).

SIMULATOR SETUP:

1. Reactor tripped, in Mode 5
2. RC Temperature = 1200F, RC Pressure = 55 psig
3. When step 2.2.4 is reached, ERV (PSV-1000) sticks open and will not close
4. When ERV Isolation valve is closed (CV-1000), the leak stops

TUOI NUMBER:

Page 3 of 6 A1JPM-RO-INITIATING CUE:

The CRS/SM directs you to perform the ERV exercise test per OP 1103.005, Supplement 1 (change 030-02-0) in order to meet the regularly scheduled 18 month test.

CRITICAL ELEMENTS (c): 5, 6, 8 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT INSTRUCTOR NOTE: Examinee may review the OP 1103.005, Supplement 1 prior to starting the JPM. Also, the Examinee should initial each step on the procedure forms although it is not written into the JPM.

1. Check purpose of test (step 1.1 of procedure)

Operator checks B for regularly scheduled 18 month test.

2. Records stop watch M & TE # and cal date in section 3.0 of procedure.

Checks RC Temp > 100oF Checks RC Pressure < 70 psig Checks ERV Isolation (CV-1000) open (steps 1.2 thru 1.5 of procedure)

Operator enters stopwatch cal data, initials for correct RCS temp/pressure, and checks ERV isolation valve light RED is ON and GREEN is OFF.

3. If elevated airborne activity is expected as a result of ERV operations, personnel hatch interlock enabled or.

Instructor Cue here NOTE: No elevated airborne activity is expected See Instructor Cue below Operator should ask CRS about expected airborne activity.

Instructor cues as given below.

Operator should N/A the step after the cue.

INSTRUCTOR CUE: CRS reports that there is no elevated airborne activity expected. N/A the step on the form.

4. Verify no one is at the vicinity of the ERV.

(step 2.1)

Instructor Cue: when operator calls on radio or asks CRS, reply back that no one is in the vicinity of ERV See Instructor Cue at left.

Operator asks CRS to determine or uses radio to call and determine that no one is near the ERV.

TUOI NUMBER:

Page 4 of 6 A1JPM-RO-C PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT C

5. Perform the following steps while ensuring RCS pressure remains > 30psig:

-Place ERV Acoustic Monitor Full Scale Range selector to 1 g position.

-Open and measure stroke time of ERV (Record in Section 3.0).

(steps 2.2.1 - 2.2.2)

Operator selects 1 g position for ERV Acoustic Monitor with Acoustic selector switch.

Operator places hand switch for ERV to open position and verifies ERV open by using all three parameter indications listed here:



Acoustic Monitor indicating light on panel C04



Dropping RCS pressure (Operator should not let pressure drop below 30psig)



Rising Quench Tank Pressure Operator then enters the stroke time in Section 3.0.

C

6. Close and measure the stroke time of ERV (Record in Section 3.0).

(step 2.2.4)

NOTE: This is the alternate path portion of the JPM.

The ERV will stick completely open and will not move under any conditions. The block valve (CV-1000) should be closed to stop the release.

Operator places hand switch for ERV to close position and should attempt to verify that the ERV is closed by using all three parameter indications listed here:



Acoustic Monitor indicating light on panel C04 (displays open)



Stable RCS pressure (It should continue to drop)



Stable Quench Tank Pressure (It should continue to rise)

NOTE: This is the alternate path portion of the JPM. The ERV will stick completely open and will not move under any conditions. The block valve (CV-1000) should be closed to stop the release per Alarm procedure OP 1203.012H for alarm K09-A1, Relief Valve Open, page 2.

TUOI NUMBER:

Page 5 of 6 A1JPM-RO-C PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT

7. Operator should enter the Annunciator Response OP 1203.012H for alarm K09-A1, Relief Valve Open, page 2.

s Failure s

Failure.

Operator is directed by OP1203.012H to refer to procedure AOP 1203.015 for Pressurizer System

. Operator should refer to section 1.0 of this procedure for ERV Failure or Leak.

Operator acknowledges alarm and enters Alarm procedure OP 1203.012H for alarm K09-A1, Relief Valve Open, page 2.

This procedure directs Operator to AOP 1203.015 for Pressurizer System Operator should refer to section 1.0 of this procedure for ERV failure or Leak.

C

8. Operator should commence follow-up actions for section 1.0, which include:
a. Close the ERV Isolation valve (CV-1000).
b. Trip reactor if cant maintain pressure (N/A in this JPM)

(steps 3.1-3.2)

Operator closes the isolation valve with hand switch for CV-1000 and observes the following:



Acoustic Monitor indicating light on panel C04 (displays closed)



Stable RCS pressure



Stable Quench Tank Pressure NOTE: Closing the ERV block or isolation valve CV-1000 will stop the leak.

9. If closing CV-1000 stops the leak, perform the following:
a. Continue power operations with ERV isolated (N/A for this JPM)
b. Notify OPS manager
c. Log in station log and on plant status board (step 3.3)

END of JPM Operator notifies the OPS manager of the stuck open ERV, block valve has contained the leak, and logs the entry in the station log and PSB.

INSTRUCTOR CUE: This concludes the JPM.

END

TUOI NUMBER:

Page 6 of 6 A1JPM-RO-EXAMINEES COPY INITIAL CONDITIONS:

You are the CBOR and you are directed by the CRS to perform OP 1103.005, Supplement 1, Exercising of the Pressurizer Electromatic Relief Valve (PSV-1000) in order to meet the regularly scheduled 18 month test. The plant conditions are as follows:

RC Temperature = 1200F RC Pressure = 55 psig INITIATING CUE:

The CRS/SM directs you to perform the ERV exercise test per OP 1103.005, Supplement 1 (change 030-02-0) in order to meet the regularly scheduled 18-month test.

PROC./WORK PLAN NO.

PROCEDURE/WORK PLAN TITLE: Page 33 of 38 1103.005 PRESSURIZER OPERATION CHANGE: 030-02-0 SUPPLEMENT 1 Page 1 of 4 EXERCISING OF THE PRESSURIZER ELECTROMATIC RELIEF VALVE (PSV-1000)

This test demonstrates operability of the pressurizer ERV by exercising the valve. This test satisfies TS 5.5.8 (ANO IST program requirements) for stroke time measurement, exercising, and fail-safe operation. This test also satisfies part of Surveillance TR 3.4.2.1 for RCS vent path operability. This test is related to SR 3.4.11.5 "Channel calibration of ERV opening circuitry".

1.0 INITIAL CONDITIONS INITIALS 1.1 Check the purpose of this test:

__A) Regularly scheduled cold shutdown test.

__B) Regularly scheduled 18 month test

__C) Operability test following significant maintenance.

__D) Other (describe in section 4.0).

1.2 Stop watch available for measuring valve stroke time.

1.2.1 Record Stopwatch M&TE# and Cal Due Date in Section 3.0.

1.3 RC temperature > 1000F.

1.4 RC pressure < 70 psig.

1.5 ERV Isolation (CV-1000) open.

1.6 If elevated airborne activity is expected as a result of ERV operations, personnel Hatch interlock enabled or Personnel Hatch watch stationed to ensure only one door opened at a time. Otherwise N/A.

2.0 TEST METHOD WARNING Opening the ERV causes a localized steam release at the pilot valve vent.

This is a radiation and safety hazard.

2.1 Verify no one is at the vicinity of the ERV.

PROC./WORK PLAN NO.

PROCEDURE/WORK PLAN TITLE: Page 34 of 38 1103.005 PRESSURIZER OPERATION CHANGE: 030-02-0 SUPPLEMENT 1 Page 2 of 4 NOTE ERV position and vent path operability are obtained using:



Acoustic Monitor indication on C04 and



dropping RCS pressure and



rising Quench Tank pressure.

2.2 Perform the following steps while ensuring RCS pressure remains < 30 psig.

2.2.1 Place ERV Acoustic Monitor Full Scale Range selector to 1 g position.

2.2.2 Open and measure stroke time of ERV (Record in Section 3.0).

2.2.3 Verify ERV open using all of the following:



Acoustic Monitor Indication on C04



Dropping RCS pressure



Rising Quench Tank pressure.

2.2.4 Close and measure stroke time of ERV (Record in Section 3.0).

2.2.5 Verify ERV closed using all of the following:



Acoustic Monitor Indication on C04



Stable RCS pressure



Stable Quench Tank pressure.

2.2.6 Place ERV Acoustic Monitor Full Scale Range selector to 10 g position.

PROC./WORK PLAN NO.

1103.005 PROCEDURE/WORK PLAN TITLE: Page 35 of 38 PRESSURIZER OPERATION CHANGE: 030-02-0 SUPPLEMENT 1 Page 3 of 4 3.0 ACCEPTANCE CRITERIA 3.1 Record stroke time measured during testing and compare with "Limiting Value For Operability".

Stopwatch M&TE#___________ Cal Due Date ________________

Valve Control Panel Test Direction Measured Stroke Time (nearest 1/10 second)

Acceptable Normal Range (Sec)

Limiting Value For Operability (Sec)

Is Measured Stroke Time Less Than "Limiting Value For Operability" Design Bases Value Open

< 2.0

< 2.0 Yes No

< 2.0 PSV-1000 C04 Closed 2.6-7.8

<10.4*

Yes No N/A

  • Valve closure verifies proper fail-safe operation.

3.2 If "No" is circled in 3.1 above, declare PSV-1000 inoperable, immediately notify the Shift Manager/CRS, write a Condition Report, initiate corrective action. Reference applicable Tech Spec for LCO.

3.3 If any measured stroke time does not fall within the "Acceptable Normal Range", immediately retest valve or declare that valve inoperable. Refer to "Operability" section of this procedure for additional guidance.

PERFORMED BY _______________________OPERATOR DATE/TIME ______/______

Page 1 of 5 TUOI: A1JPM-DHR01 JOB PERFORMANCE MEASURE UNIT: ______1_______ REV # ______8_______

DATE: ______________________________

TUOI NUMBER:_A1JPM-RO-DHR01_____________

SYSTEM/DUTY AREA:_DECAY HEAT REMOVAL______________________________________________

TASK:__ESTABLISH DECAY HEAT REMOVAL USING P-34A____________________________________

JTA#:__ANO1-RO-DHR-NORM-2__________

KA VALUE RO:___3.6____ SRO:__3.4_____ KA

REFERENCE:

__005 A4.01__________________

APPROVED FOR ADMINISTRATION TO: RO:___X____ SRO:____X____

TASK LOCATION: INSIDE CR:____X____ OUTSIDE CR:_________ BOTH:________

SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):

PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________

POSITION EVALUATED: RO:__________

SRO:___________

ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________

TESTING METHOD: SIMULATE:_________

PERFORM:___________

APPROXIMATE COMPLETION TIME IN MINUTES:___20 MINUTES_______________________________

REFERENCE(S):__1104.004 EXAMINEE'S NAME:________________________________

SSN ______-_____-____________

EVALUATOR'S NAME:__________________________________________________________________

THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:

SATISFACTORY:________________

UNSATISFACTORY:_________________

PERFORMANCE CHECKLIST COMMENTS:

____________ Start Time

____________ Stop Time

____________ Total Time SIGNED ________________________________ DATE: _______________________

SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.

Page 2 of 5 TUOI: A1JPM-DHR01 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:

 Plant shutdown and cooldown per 1102.010 is complete to step 10.8.

 Breakers B-5255/B-6255/B-5651 are closed.

 1104.004 is complete up to step 7.2.3.

INITIATING CUE:

The CRS directs that Decay Heat Pump P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.

Page 3 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER: ANO-1-JPM-RO-DHR01 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS: Plant shutdown and cooldown per 1102.010 is complete to step 10.8. Decay heat removal with P34A is to be established per 1104.004. Breakers B-5255/B-6255/B-5651 are closed.

TASK STANDARD: P-34A decay heat pump running per OP 1104.004. Flow indicated

< 3500 gpm and discharge pressure <400 psig.

TASK PERFORMANCE AIDS: 1104.004 Section 7.0

Page 4 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER: ANO-1-JPM-RO-DHR01 INITIATING CUE:

The CRS directs that P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.

INSTRUCTOR NOTE: Ensure B-5255, B-6255,and B-5651 are closed and Programmable Annunciator alarm for P34A (P1404) set at 400 psig.

CRITICAL ELEMENTS (C): 1, 2, 5, 7, 8, 9, 10, 11, 12, 15 C

PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT (C)

1. Close Decay Heat P-34A Suction from BWST (CV-1436).

CV-1436 red light off, green light on.

(C)

2. Open Decay Heat P-34A Suction from RCS (CV-1434).

CV-1434 red light on, green light off.

3. Open E-35A and E-35B sample valves SS-41A and SS-41B.

Contacted the WCO and instructed the WCO to open SS-41A and SS-41B.

NOTE: Inform examinee that Category E log entry has been made.

4. Verify white Open Permit light ON at CV-1410 handswitch on C16.

Verified white open permit light on.

(C)

5. Open CV-1410.

Opened DH suction valve CV-1410.

6.

Verify white Open Permit light ON at CV-1050 handswitch on C18.

Verified white open permit light on.

C

7.

Open DH Suction Valve CV-1050 Opened DH suction valve CV-1050.

C

8.

Open DH suction RB isolation CV-1404.

Opened CV-1404.

C

9.

Close decay heat cooler E-35A outlet valve CV-1428.

Closed CV-1428.

Page 5 of 5 TUOI: A1JPM-DHR01 C

PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT C

10.

Position E-35A Cooler Bypass (CV-1433) to ~ 50% as indicated on HIC-1433.

Positioned CV-1433 to ~

50% open.

C

11. Open Decay Heat Block Valve CV-1401 Opened CV-1401.

C

12. Start P-34A.

Started P-34A.

13.

Verify LPI/Decay Heat Pump Brg CLR E-50A Inlet (CV-3840) and Decay HT CLR Service Water E-35A Inlet (CV-3822) open.

On C-18, verified CV-3840 and CV-3822 open.

14.

Monitor pressurizer level.

Monitored pressurizer level on C04 or SPDS.

C

15.

Adjust CV-1433 to establish decay heat removal flow at < 3500 gpm from P-34A and discharge pressure

< 400 psig.

Adjusted DHR flow to

<3500 gpm and discharge pressure < 400 psig using CV-1433.

NOTE: Inform examinee that it is not necessary to perform Part 2 of Supplement 3.

16.

Verify LPI Room Cooler VUC-1A starts.

At panel C-19, verified VUC-1A started (red light on).

17.

Adjust the DECAY HEAT VORTEX WARNING SETPOINT.

Selected the U5 function of the SPDS computer and set KP34ALO just below the Decay Heat Pump motor current and adjusted KP34AHI just above the Decay Heat Pump motor current.

END

Page 1 of 5 TUOI: A1JPM-DHR01 JOB PERFORMANCE MEASURE UNIT: ______1_______ REV # ______8_______

DATE: ______________________________

TUOI NUMBER:_A1JPM-RO-DHR01_____________

SYSTEM/DUTY AREA:_DECAY HEAT REMOVAL______________________________________________

TASK:__ESTABLISH DECAY HEAT REMOVAL USING P-34A____________________________________

JTA#:__ANO1-RO-DHR-NORM-2__________

KA VALUE RO:___3.6____ SRO:__3.4_____ KA

REFERENCE:

__005 A4.01__________________

APPROVED FOR ADMINISTRATION TO: RO:___X____ SRO:____X____

TASK LOCATION: INSIDE CR:____X____ OUTSIDE CR:_________ BOTH:________

SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):

PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________

POSITION EVALUATED: RO:__________

SRO:___________

ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________

TESTING METHOD: SIMULATE:_________

PERFORM:___________

APPROXIMATE COMPLETION TIME IN MINUTES:___20 MINUTES_______________________________

REFERENCE(S):__1104.004 EXAMINEE'S NAME:________________________________

SSN ______-_____-____________

EVALUATOR'S NAME:__________________________________________________________________

THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:

SATISFACTORY:________________

UNSATISFACTORY:_________________

PERFORMANCE CHECKLIST COMMENTS:

____________ Start Time

____________ Stop Time

____________ Total Time SIGNED ________________________________ DATE: _______________________

SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.

Page 2 of 5 TUOI: A1JPM-DHR01 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:

 Plant shutdown and cooldown per 1102.010 is complete to step 10.8.

 Breakers B-5255/B-6255/B-5651 are closed.

 1104.004 is complete up to step 7.2.3.

INITIATING CUE:

The CRS directs that Decay Heat Pump P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.

Page 3 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER: ANO-1-JPM-RO-DHR01 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS: Plant shutdown and cooldown per 1102.010 is complete to step 10.8. Decay heat removal with P34A is to be established per 1104.004. Breakers B-5255/B-6255/B-5651 are closed.

TASK STANDARD: P-34A decay heat pump running per OP 1104.004. Flow indicated

< 3500 gpm and discharge pressure <400 psig.

TASK PERFORMANCE AIDS: 1104.004 Section 7.0

Page 4 of 5 TUOI: A1JPM-DHR01 TUOI NUMBER: ANO-1-JPM-RO-DHR01 INITIATING CUE:

The CRS directs that P34A be placed in service with DHR flow <3500 gpm and discharge pressure <400 psig, complete procedure through step 7.2.18.

INSTRUCTOR NOTE: Ensure B-5255, B-6255,and B-5651 are closed and Programmable Annunciator alarm for P34A (P1404) set at 400 psig.

CRITICAL ELEMENTS (C): 1, 2, 5, 7, 8, 9, 10, 11, 12, 15 C

PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT (C)

1. Close Decay Heat P-34A Suction from BWST (CV-1436).

CV-1436 red light off, green light on.

(C)

2. Open Decay Heat P-34A Suction from RCS (CV-1434).

CV-1434 red light on, green light off.

3. Open E-35A and E-35B sample valves SS-41A and SS-41B.

Contacted the WCO and instructed the WCO to open SS-41A and SS-41B.

NOTE: Inform examinee that Category E log entry has been made.

4. Verify white Open Permit light ON at CV-1410 handswitch on C16.

Verified white open permit light on.

(C)

5. Open CV-1410.

Opened DH suction valve CV-1410.

6.

Verify white Open Permit light ON at CV-1050 handswitch on C18.

Verified white open permit light on.

C

7.

Open DH Suction Valve CV-1050 Opened DH suction valve CV-1050.

C

8.

Open DH suction RB isolation CV-1404.

Opened CV-1404.

C

9.

Close decay heat cooler E-35A outlet valve CV-1428.

Closed CV-1428.

Page 5 of 5 TUOI: A1JPM-DHR01 C

PERFORMANCE CHECKLIST STANDARDS N/A SAT UNSAT C

10.

Position E-35A Cooler Bypass (CV-1433) to ~ 50% as indicated on HIC-1433.

Positioned CV-1433 to ~

50% open.

C

11. Open Decay Heat Block Valve CV-1401 Opened CV-1401.

C

12. Start P-34A.

Started P-34A.

13.

Verify LPI/Decay Heat Pump Brg CLR E-50A Inlet (CV-3840) and Decay HT CLR Service Water E-35A Inlet (CV-3822) open.

On C-18, verified CV-3840 and CV-3822 open.

14.

Monitor pressurizer level.

Monitored pressurizer level on C04 or SPDS.

C

15.

Adjust CV-1433 to establish decay heat removal flow at < 3500 gpm from P-34A and discharge pressure

< 400 psig.

Adjusted DHR flow to

<3500 gpm and discharge pressure < 400 psig using CV-1433.

NOTE: Inform examinee that it is not necessary to perform Part 2 of Supplement 3.

16.

Verify LPI Room Cooler VUC-1A starts.

At panel C-19, verified VUC-1A started (red light on).

17.

Adjust the DECAY HEAT VORTEX WARNING SETPOINT.

Selected the U5 function of the SPDS computer and set KP34ALO just below the Decay Heat Pump motor current and adjusted KP34AHI just above the Decay Heat Pump motor current.

END

TUOI NUMBER:_ANO-1-JPM-RO-RPS02_

Page 1 of 5 JOB PERFORMANCE MEASURE UNIT: ______1_______

REV # ______4________ DATE: ______________________________

TUOI NUMBER:_A1JPM-RO-RPS02 SYSTEM/DUTY AREA:_REACTOR PROTECTION SYSTEM________________________________________

TASK:_REMOVE A CHANNEL OF RPS FROM MANUAL BYPASS___________________________________

JTA#:_ANO1-RO-RPS-NORM-6___________________________

KA VALUE RO:___3.6____ SRO:__3.6_____ KA

REFERENCE:

__012 A4.03_________________

APPROVED FOR ADMINISTRATION TO: RO:____X___ SRO:___ X ___

TASK LOCATION: INSIDE CR:____X____ OUTSIDE CR:_________ BOTH:________

SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):

PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________

POSITION EVALUATED: RO:__________ SRO:___________

ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________

TESTING METHOD: SIMULATE:_________ PERFORM:___________

APPROXIMATE COMPLETION TIME IN MINUTES:___ 15 MINUTES______________________________

REFERENCE(S):__1105.001 EXAMINEE'S NAME:________________________________

SSN ______-_____-____________

EVALUATOR'S NAME:__________________________________________________________________

THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:

SATISFACTORY:________________

UNSATISFACTORY:_________________

PERFORMANCE CHECKLIST COMMENTS:

____________ Start Time

____________ Stop Time

____________ Total Time SIGNED ________________________________ DATE: _______________________

SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.

TUOI NUMBER:_ANO-1-JPM-RO-RPS02_

Page 2 of 5 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:_The plant is operating at 100% power with ICS in auto-_

_matic. The A RPS channel is in manual bypass for maintenance. The maintenance____

_has been completed.________________________________________________________________

TASK STANDARD:_The A RPS channel is removed from manual bypass.___________________

TASK PERFORMANCE AIDS:_Manual bypass key, 1105.001_________________________________

SIMULATOR SETUP: Power operations, place A RPS in manual bypass, select SASS Neutron Flux selector to the Y position.

TUOI NUMBER:_ANO-1-JPM-RO-RPS02_

Page 3 of 5 TUOI NUMBER:_ANO-1-JPM-RO-RPS02_

INITIATING CUE:

The SM/CRS directs you to remove the A RPS channel from manual bypass per section 11.0 of 1105.001, NI & RPS Operating Procedure.

CRITICAL ELEMENTS (C):__2__

(C)

PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT NOTE: Due to the uniqueness of the design in the simulator, all channel indications are located in one RPS cabinet.

1. Verify A RPS channel is reset.

Inside the RPS cabinet in the back of the control room:

a) Verified all test modules are in operate with the On Test lamps ON dim.

b) Depressed and released the Output State and Output Memory Reset switches for all bistables with Output State and/or Output Memory lamps ON bright.

c) Verified the Building Pressure contact buffer is reset (both Input State lamps OFF).

d) On the Channel A Reactor Trip Module, placed Subsystem Reset switch to down position.

e) Verified the Subsystem No. 1 lamps ON dim for Reactor Trip modules and Cabinet Indicating Panels on all RPS Channels.

(C)

2. Turn Manual Bypass key switch out of bypass position.

On the Reactor Trip Module in A RPS, turned keyswitch out of bypass position.

Reactor Trip Module did NOT trip (verifies previous step properly performed).

3. Verify Manual Bypass lamps ON dim.

On the Reactor Trip module and indicating panel, verified the Manual Bypass lamps are ON dim.

TUOI NUMBER:_ANO-1-JPM-RO-RPS02_

Page 4 of 5 (C)

PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT

4. Verify annunciator K08-D3 clear.

Verified that annunciator K08-D3 RPS CHANNEL BYPASSED is clear.

5. Verify A EFIC channel Maintenance Bypass light ON solid.

Verified A EFIC channel Maintenance Bypass light ON solid on the upper right of the A EFIC cabinet.

6. Remove Manual Bypass key from Reactor Trip module and return to Shift Mgr.

Removed Manual Bypass key from Reactor Trip module and returned to Shift Mgr.

7. Verify <1% difference between NI-5/NI-6 high and NI-7/NI-8 high.

Used panel readings on C03 or plant computer points N1I56HI and N1I78HI to determine the difference between the highest of NI5/NI6 is <1% different from the highest of NI7/NI8.

8. Return the SASS Neutron Flux selector switch to SASS Enable.

On C03, the SASS Neutron Flux switch is placed in the SASS Enable position after the signals (N1I56HI and N1I78HI) had been compared.

END

TUOI NUMBER:_ANO-1-JPM-RO-RPS02_

Page 5 of 5 EXAMINEES COPY INITIAL CONDITIONS:

 The plant is operating at 100% power with ICS in automatic.

 The A RPS channel is in manual bypass for maintenance.

 The maintenance has been completed.

INITIATING CUE:

The SM/CRS directs you to remove the A RPS channel from manual bypass per section 11.0 of 1105.001, NI & RPS Operating Procedure.

TUOI NUMBER:

Page 1 of 6 A1JPM-RO-EOP11 JOB PERFORMANCE MEASURE Unit:

1 Rev #

1 Date:

TUOI NUMBER:

A1JPM-RO-EOP11 System/Duty Area:

Emergency and Abnormal Operations Task:

Perform Actions during ESAS Actuation to swap ECCS suction to RB sump (ALTERNATE PATH JPM)

JA#

ANO1-RO-KA Value RO 4.0 SRO 3.8 KA Reference 006.A4.02 Approved For Administration To: RO SRO Task Location: Inside CR:

Outside CR:

Both:

Suggested Testing Environment And Method (Perform Or Simulate):

Plant Site:

Simulator:

Perform X Lab:

Position Evaluated: RO:

X SRO:

X Actual Testing Environment: Simulator:

Plant Site:

Lab Testing Method: Simulate:

Perform:

Approximate Completion Time In Minutes:

20 Minutes Reference(S):

Examinee's Name:

SSN:

Evaluator's Name:

The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:

Satisfactory:

Unsatisfactory:

Performance Checklist Comments:

Start Time Stop Time Total Time Signed Date:

Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.

TUOI NUMBER:

Page 2 of 6 A1JPM-RO-EOP11 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 with the examinee.

JPM INITIAL TASK CONDITIONS:

ESAS has actuated due to a LOCA. RCS pressure is  50 psig. All unnecessary people have been evacuated from the Aux Building. Aux Spray has been aligned from LPI system. BWST level is at ~

6 feet, BWST LO and LO LO annunciators are in alarm.

TASK STANDARD:

LPI and RB Spray pumps operating with their suctions aligned to the RB sump and BWST outlet valves closed (i.e. CV-1405/1406 open AND CV-1407/1408 closed).

TASK PERFORMANCE AIDS:

RT15 from 1202.012, change 004-02-0.

SIMULATOR SETUP:

IC2, then insert large RCS leak so that full ESAS actuation occurs. Trip all RCPs and go to reflux boiling setpoint for EFW. Close CV-1000 and CV-1009. Close CV-2415 and CV-2419 (CFT Outlets).Secure HPI pumps, close all HPI block valves, close CV-1206. Secure EFW-- P-7B in P-T-L, close CV-2613/CV-2663 in manual, close MFIVs and MSIVs. Throttle RB Spray to 1050-1200 gpm. Fail CV-1405 closed.

TUOI NUMBER:

Page 3 of 6 A1JPM-RO-EOP11 INITIATING CUE: The CRS/SM directs you to shift to RB sump suction using RT-15.

CRITICAL ELEMENTS (c): 9, 10, 11, 12 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT

1. Verify both LPI pumps running (P34A and B).

On C16 and C18, operator verifies RED lights ON and GREEN lights OFF for both P34A and P34B.

2. Verify LPI Room Coolers running: VUC1A or VUC1B AND VUC1C or VUC1D.

On C19, operator verifies RED lights ON and GREEN lights OFF for VU1CA and VU1CC.

3. Verify both LPI Block valves fully open (CV-1400 and CV-1401).

On C16 and C18, operator verifies valves are open with RED lights ON and GREEN lights OFF for CV-1400 and CV-1401.

4. Verify Letdown isolated by CV-1221 closed on C16 or CV-1214/CV-1216 closed on C18.

On C-16, operator verifies letdown isolated by observing CV-1221 closed with the GREEN light ON and RED light OFF or on C-18, operator verifies letdown isolated by observing CV-1214/CV-1216 closed with the GREEN lights ON and RED lights OFF.

5. Verify both Decay Heat Supply to Makeup Pump Suctions open (CV-1276 and CV-1277).

NOTE: valves will be shut when examinee gets to this step, after examinee goes to open on these valves give the POSITIVE CUE.

Operator Opens CV1276 and CV-1277 on panels C16 and C18 and observes Red lights ON, green lights OFF.

6. Verify RB Spray flow throttled to maintain 1050-1200 gpm per train.

Operator verifies that RB Spray flow is throttled to maintain 1050-1200 gpm per train (as indicated on SPDS, C16/C18 or recorder on C14, approximately 1150 gpm indicated flow on each train)

TUOI NUMBER:

Page 4 of 6 A1JPM-RO-EOP11 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT

7. If NaOH Tank T10 level is 25 ft, THEN close RB spray NaOH Addition T-10 Outlets (CV-1616 and CV-1617).

NOTE: if this JPM is being simulated, tell examinee that T10 level is 20 ft then give POSITIVE CUE after examinee goes to close on the valves.

Operator Closes CV-1616 and CV-1617 IF T-10 level is 25 ft and observes GREEN lights ON and RED lights OFF.

8. Verify RB Sump Outlets open (CV-1414 and CV 1415).

On C16 and C18, operator verifies CV-1414 and CV-1415 open with RED lights ON and GREEN lights OFF.

NOTE: This is the alternate path portion of the JPM. The RB sump outlet valve CV-1405 will fail to open.

C

9. Open RB Sump Outlets (CV-1405 and CV-1406).

On panel C16 operator attempts to open CV-1405 (it will not open) and observes the GREEN light ON and RED light OFF for it.

On panel C18, operator opens CV-1406 and observes RED light ON and GREEN light OFF for it.

See note: This is the Alternate Path step for the JPM C

10. Stop associated LPI, HPI, and RB Spray pumps, which includes:

RB Spray pump P-35A LPI pump P-34A On C-16 and C-18, operator secures LPI pump P-34A AND secures RB Spray pump P-35A.

(HPI is already secured) and observes GREEN lights ON and RED lights OFF.

C

11. Take manual control of BWST outlets CV-1407 and CV-1408.

On C16 and C18, operator depresses the manual pushbutton on each of two AUTO/MANUAL pushbuttons for CV-1407 and CV-1408 in MANUAL and observes WHITE light ON and RED light OFF for each.

C

12. Close BWST Outlets (CV-1407 and CV-1408).

On C16 and C18, operator verifies GREEN lights ON and RED lights OFF for closed valves CV-1407 and CV-1408.

TUOI NUMBER:

Page 5 of 6 A1JPM-RO-EOP11 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT

13. Check LPI/RB Spray flow is maintained.

Checked proper LPI/RB Spray flow is being maintained by observing SPDS or meters on C16/C18 or recorder on C14 with values for spray @ 1100 gpm, LPI

@ 3000 gpm.

14. Notify HP to monitor BWST suction line for indication of back-leakage from LPI suction.

POSITIVE CUE:

HP has been notified.

Notified Health Physics.

Instructor Note: INFORM EXAMINEE THAT MAKEUP TANK LEVEL IS STEADY AT 50 INCHES.

15. IF NaOH Tank T10 Level >25 ft, THEN open CV-1616 and CV-1617.

NOTE: If being simulated tell examinee that T10 level is 20 ft which will make this step (14 and 14.a) N/A.

a) WHEN T10 level is 11-25 ft, THEN close CV-1616 and CV-1617.

Opened CV-1616 and CV-1617 IF T10 level >25 ft.

a) Closed CV-1616 and CV-1617 after T10 level is in range of 11-25 ft.

INFORM EXAMINEE THAT RB LEVELS HAVE STABILIZED AND BWST REFILL HAS BEEN INITIATED.

INSTRUCTOR CUE: This concludes the JPM.

END

TUOI NUMBER:

Page 6 of 6 A1JPM-RO-EOP11 EXAMINEES COPY INITIAL CONDITIONS:

ESAS has actuated due to a LOCA. RCS pressure is  50 psig. All unnecessary people have been evacuated from the Aux Building. Aux Spray has been aligned from LPI system. BWST level is at ~ 6 feet, BWST LO and LO LO annunciators are in alarm.

INITIATING CUE:

The CRS/SM directs you to shift to RB sump suction using RT-15.

PROC./WORK PLAN NO.

1202.012 PROCEDURE/WORK PLAN TITLE: Page 28 of 30 REPETITIVE TASKS CHANGE: 004-02-0

TUOI NUMBER:_A1JPM-RO-EDG04 Page 1 of 5 JOB PERFORMANCE MEASURE UNIT: ______1_______

REV # ______1_______

DATE: ______________________________

TUOI NUMBER:_A1JPM-RO-EDG04__

SYSTEM/DUTY AREA:_EMERGENCY DIESEL GENERATOR (EDG) SYSTEM__________________________

TASK:_LOAD EDG1____________________________________________________________________

JTA#:_ANO1-RO-EDG-NORM-10___________________________

KA VALUE RO:__3.4_____ SRO:__3.4_____ KA

REFERENCE:

__064 A4.07_________________

APPROVED FOR ADMINISTRATION TO: RO:____X___ SRO:___ X ___

TASK LOCATION: INSIDE CR:____X____ OUTSIDE CR:_________ BOTH:________

SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):

PLANT SITE:_______________ SIMULATOR:___PERFORM_______ LAB:__________________

POSITION EVALUATED: RO:__________ SRO:___________

ACTUAL TESTING ENVIRONMENT: SIMULATOR:__________ PLANT SITE:__________ LAB:________

TESTING METHOD: SIMULATE:_________ PERFORM:___________

APPROXIMATE COMPLETION TIME IN MINUTES:___ 15 MINUTES______________________________

REFERENCE(S):_1104.036 ________________________

EXAMINEE'S NAME:________________________________

SSN ______-_____-____________

EVALUATOR'S NAME:__________________________________________________________________

THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:

SATISFACTORY:________________

UNSATISFACTORY:_________________

PERFORMANCE CHECKLIST COMMENTS:

____________ Start Time

____________ Stop Time

____________ Total Time SIGNED ________________________________ DATE: _______________________

SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.

TUOI NUMBER:_A1JPM-RO-EDG04 Page 2 of 5 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:_EDG1 is running with its output breaker open and its___

_service water inlet valve (CV-3806) open._ ________________________________________

TASK STANDARD:_EDG1 tripped by examinee after its load increases without operator __

_control._This is an Alternate Success Path JPM.__________________________ ________

TASK PERFORMANCE AIDS:__1104.036 Section 7.0 NOTE: When the EDG1 output breaker is closed, insert override DI CS3-DG1_RO2; true and CS3-DG1_W02; false which will fail the governor handswitch in the raise position; this will cause the EDG load to rise without control.

TUOI NUMBER:_A1JPM-RO-EDG04 Page 3 of 5 INITIATING CUE:

The SM/CRS directs you to parallel EDG1 to the grid and load EDG1 to ~2750 KW per 1104.036 Step 7.10.

CRITICAL ELEMENTS (C):_2, 6, 7 (C)

PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT

1.

Inform dispatcher that EDG1 will be loaded and inquire about weather.

Called the dispatcher, informed him/her that EDG1 is ready for loading and asked about proper weather conditions.

(C)

2.

Turn on synchronize switch for EDG1 output breaker A-308.

On C10, placed synchronize switch for A-308 to ON position.

3.

Verify voltage control.

Verified voltage control by raising and/or lowering voltage using the EDG1 voltage regulator control switch on C10.

4.

Verify frequency control.

Verified frequency control by raising and/or lowering frequency by using the EDG1 governor control switch on C10.

5.

Match running and incoming voltages.

On C10, matched running and incoming voltages by adjusting EDG1 voltage regulator.

NOTE: Voltages may be verified matched on C10 or SPDS or on plant computer.

(C)

6.

Adjust EDG1 frequency.

On C10, adjusted EDG1 governor control to achieve

~60 hz with synchroscope rotating slowly in the FAST direction.

NOTE: IA Operator  When the EDG1 output breaker is closed, insert override DI CS3-DG1_RO2; true and DI CS3-DG1_W02; false which will fail the governor handswitch in the raise position, this will cause the EDG load to rise without control.

TUOI NUMBER:_A1JPM-RO-EDG04 Page 4 of 5 (C)

PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT (C)

7.

As synchroscope approaches 12 oclock position (~5 min. til) close EDG1 output breaker A-308.

Closed EDG1 output breaker A-308.

(C)

8.

Operator identifies increasing load and trips the EDG.

On C10, tripped EDG1.

END

TUOI NUMBER:_A1JPM-RO-EDG04 Page 5 of 5 EXAMINEES COPY INITIAL CONDITIONS:

EDG1 is running with its output breaker open and its service water inlet valve (CV-3806) open.

INITIATING CUE:

The SM/CRS directs you to parallel EDG1 to the grid and load EDG1 to ~2750 KW per 1104.036 Step 7.10.

JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030 Page 1 of 5 UNIT: 1 REV # 0 DATE: ______________________________

TUOI NUMBER: A1JPM-RO-ED030 SYSTEM/DUTY AREA: BATTERY AND 125V DC DISTRIBUTION TASK: PLACE BATTERY CHARGER D-03B IN SERVICE JTA#: ANO1-AO-125DC-NORM-12 KA VALUE RO:

3.9 SRO:

3.4 KA

REFERENCE:

2.1.30 APPROVED FOR ADMINISTRATION TO: RO: X SRO:

X TASK LOCATION: INSIDE CR:

X OUTSIDE CR:_________ BOTH:________

SUGGESTED TESTING ENVIRONMENT AND METHOD (PERFORM OR SIMULATE):

PLANT SITE:____ X_____SIMULATOR:

LAB:_________________

POSITION EVALUATED: RO:

X SRO:

X ACTUAL TESTING ENVIRONMENT: SIMULATOR:

PLANT SITE:__________ LAB:________

TESTING METHOD: SIMULATE:___X______

PERFORM:___________

APPROXIMATE COMPLETION TIME IN MINUTES:

20 MINUTES REFERENCE(S): 1107.004 EXAMINEE'S NAME:________________________________

SSN ______-_____-____________

EVALUATOR'S NAME:__________________________________________________________________

THE EXAMINEE'S PERFORMANCE WAS EVALUATED AGAINST THE STANDARDS CONTAINED IN THIS JPM AND IS DETERMINED TO BE:

SATISFACTORY:________________

UNSATISFACTORY:_________________

PERFORMANCE CHECKLIST COMMENTS:

____________ Start Time

____________ Stop Time

____________ Total Time SIGNED ________________________________ DATE: _______________________

SIGNATURE INDICATES THIS JPM HAS BEEN COMPARED TO ITS APPLICABLE PROCEDURE BY A QUALIFIED INDIVIDUAL (NOT THE EXAMINEE) AND IS CURRENT WITH THAT REVISION.

JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030 Page 2 of 5 EXAMINEES COPY JPM INITIAL TASK CONDITIONS:

 Battery Charger D-03A is in service on Bus D01.

INITIATING CUE:

The Shift Manager requests you to place Battery Charger D-03B in service on Bus D01 and remove Battery Charger D-03A from service per 1107.004, Battery and 125V DC Distribution, Attachment B.

JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030 Page 3 of 5 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the "Briefing Checklist - System Walkthrough" portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:

Battery Charger D-03A is in service on Battery D01.

TASK STANDARD: IAW 1107.004, Att. B, examinee places charger D-03B in service, removes D-03A from service, and performs actions for D-03A DC output voltage drifting to zero.

THIS IS AN ALTERNATE SUCCESS PATH JPM.

TASK PERFORMANCE AIDS: 1107.0004 Attachment B

JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030 Page 4 of 5 INITIATING CUE:

The Shift Manager requests you to place Battery Charger D-03B in service on Bus D01 and remove Battery Charger D-03A from service.

CRITICAL ELEMENTS (C) 5, 6, 8, 9, 12, 14, 16 (C)

PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT TRANSITION NOTE: Proceed to El. 372 in Auxiliary Building off Corridor 98 to Rm. 109, DC Equipment Room.

1. Verify breakers open for charger D-03B.



AC Input breaker



DC Output breaker On front of charger D-03B, verified the AC Input and DC Output breakers open (OFF).

TRANSITION NOTE: Proceed to MCC B57 in South ES Switchgear Room on the same elevation.

2. Verify AC feeder breaker to charger D-03B closed (B-5733).

Verified breaker B-5733 closed (ON).

TRANSITION NOTE: Return to DC Equipment Room.

In the following step, Caution the examinee not to break plane of cubicle door.

3. Verify charger D-03B supply to bus breaker closed (D01-42).

Inside panel D01, verified breaker D01-42 closed (ON).

4. Verify Manual Disconnect for battery D-07 closed (D-13).

At D13, verified manual disconnect for battery D07 closed (ON).

(C)

5. Close D-03B AC Input breaker.

On front of charger D-03B, closed the AC Input breaker (ON).

(C)

6. Close D-03B DC Output breaker.

On front of charger D-03B, closed the DC Output breaker (ON).

7. Wait ~1 minute for automatic load sharing to occur.

CUE:

Amps are rising on D-03B and amps are falling on D-03A.

Waited ~1 minute, observed rising amps on D-03B and falling amps on D-03A.

(C)

8. Open D-03A DC Output breaker.

On front of charger D-03A, opened the DC Output breaker (OFF).

JOB PERFORMANCE MEASURE TUOI: A1JPM-RO-ED030 Page 5 of 5 (C)

PERFORMANCE CHECKLIST STANDARD N/A SAT UNSAT (C)

9. Open D-03A AC Input breaker.

On front of charger D-03A, opened the AC Input breaker (OFF).

10. Check Charger D-03B picks up load.

CUE:



D-03B DC Out ~100 amps



AC In ~30 amps



D01 bus voltage 130V



At charger D-03B checked ammeter deflected to a nominal value, and at D01 checked bus voltage maintained at ~130 volts.

11. Reset local alarm panel for Charger D-03B.

At charger D-03B, pressed R button on RIS panel.

(C)

12. Place D-03B alarm to control room toggle switch ON.

At charger D-03B, placed control room alarm switch to ON (up).

13. Place D-03A alarm to control room toggle switch OFF.

At charger D-03A, placed control room alarm switch to OFF (down).

14. Check annunciator D01 CHARGER TROUBLE (K01-E7) clears.

Called control room and requested check for clear annunciator K01-E7.

ALTERNATE PATH CUE:

Inform examinee that D-03A DC Output Voltage drifted to zero, also inform examinee that one minute has passed since D-03A was de-energized.

(C)

15. Close D-03A AC Input breaker.

On front of charger D-03A, closed the AC Input breaker (ON).

16. Check D-03A DC output voltage and AC input voltage.

CUE:



DC Output Voltage ~90V



AC Input Voltage ~480V On charger D-03A, observed DC output voltage and AC input voltage meters.

Examinee stated that he would contact electrical maintenance for support.

(C)

17. Open D-03A AC Input breaker.

On front of charger D-03A, opened the AC Input breaker (OFF).

18. Submit condition report and WR.

Examinee stated that he would submit a condition report and Work Request or Work Order on D-03A.

END

TUOI NUMBER:

A1JPM-RO-AOP08 Page 1 of 6 JOB PERFORMANCE MEASURE Unit:

1 Rev #

4 Date:

11/04/2003 TUOI NUMBER:

A1JPM-RO-AOP08 System/Duty Area:

Emergency and Abnormal Operations Task:

RO #1 Duties for Alternate Shutdown with immediate Control Room evacuation JA#

13035210401 KA Value RO 4.3 SRO 4.2 KA Reference A06.AA1.1 Approved For Administration To: RO SRO Task Location: Inside CR:

Outside CR:

Both:

Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:

Perform Simulator:

Lab:

Position Evaluated: RO:

X SRO:

X Actual Testing Environment: Simulator:

Plant Site:

Lab Testing Method: Simulate:

X Perform:

Approximate Completion Time In Minutes:

20 Minutes Reference(S):

OP 1203.002 change 015-05-0 Examinee's Name:

SSN:

Evaluator's Name:

The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:

Satisfactory:

Unsatisfactory:

Performance Checklist Comments:

Start Time Stop Time Total Time Signed Date:

Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.

TUOI NUMBER:

A1JPM-RO-AOP08 Page 2 of 6 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:

There is a Fire in the Cable Spreading Room. An Alternate Shutdown is in progress. At the Alternate Shutdown Cabinet, you have received a copy of OP 1203.002 and Section 1C.Perform to step 3.14 of applicable section.

TASK STANDARD:

RO#1 perform actions for alternate shutdown completed through step 3.14.

TASK PERFORMANCE AIDS:

OP 1203.002 and Section 1C, change 015-05-0.

SIMULATOR SETUP:

N/A

TUOI NUMBER:

A1JPM-RO-AOP08 Page 3 of 6 INITIATING CUE: The first 3 steps of OP 1203.002 Section 1C have been completed. Perform the actions required of RO

  1. 1 through step 3.14.

CRITICAL ELEMENTS (c): 1, 7, 9, 11, 12, and 13 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT C

1.

At The MSIV's, open the instrument air vent valves for each MSIV (IA-2691B through E and IA-2692B through E).

POSITIVE CUE:

All 8 vent valves have stem full out, with each valves handwheel fully CW.

Opened instrument air vent valves IA-2691B through E and IA-2692B through E.

2.

Verify CV-2667 open.

POSITIVE CUE:

CV-2667 has stem full out, with the valve handwheel fully CW.

CV-2667 verified open by visually observing stem or valve position indicator.

3.

Verify CV-2617 open.

POSITIVE CUE:

CV-2617 has stem full out, with the valve handwheel fully CW.

CV-2617 verified open by visually observing stem or valve position indicator.

4.

Verify CV-2663 open.

POSITIVE CUE:

CV-2663 has stem full out, with the valve handwheel fully CW.

CV-2663 verified open by visually observing stem or valve position indicator.

5.

Verify CV-2613 open.

POSITIVE CUE:

CV-2613 has stem full out, with the valve handwheel fully CW.

CV-2613 verified open by visually observing stem or valve position indicator.

6.

Notify TSC of completion POSITIVE CUE:

TSC notified of completion of actions Communicated via phone or radio the Completion of Item 1.A EXAMINERS NOTE: The examinee should proceed to the Auxiliary Building 354 elevation.

C

7.

Proceed to Aux Bldg, 354. Slowly open CV-1407 manually POSITIVE CUE:

Valve has stem full out, with the valve handwheel fully CW.

Used manual lever and handwheel, fully opened CV-1407.

TUOI NUMBER:

A1JPM-RO-AOP08 Page 4 of 6 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT

8.

Check for flow noise as CV-1407 is opened.

POSITIVE CUE:

No flow noise is heard.

Checked for flow noise as CV-1407 was opened.

EXAMINERS NOTE: The examinee should proceed to the UNPPR.

C

9.

Manually open CV-1219 and CV-1220. Close CV-1206 POSITIVE CUE:

CV1219 and CV1220 have stems full out, with the valves handwheels fully CW, CV1206 has stem full in, with the valve handwheel fully CCW.

Opened CV-1219, CV-1220, closed CV-1206 with manual lever and handwheel, verified valve movement

10.

Notify TSC of completion POSITIVE CUE:

TSC notified of completion of actions Established communication with TSC telephone or radio, notified of action HPI Item 5.A, 5.B, EXAMINERS NOTE:

When TSC is notified have examinee throttle EFW P-7A to SG-A ISOL, CV-2627 to approximately 50 % open.

C

11.

Close CV-2627 to approximately 50% open.

POSITIVE CUE:

CV-2627 has stem approximately halfway out.

Moved to CV-2627, and used the manual lever and hand wheel to close CV-2627 to approximately to 50% open.

EXAMINERS NOTE:

Inform examinee that EFW flow is controlled.

C

12.

Open valves:

EFW P-7B to SG-A ISOL (CV-2670)

B HPI Block Valve (CV-1227)

A HPI Block Valve (CV1228)

POSITIVE CUE:

CV-2670, CV-1227, CV-1228 have stems full out, with each valves handwheel fully CW.

Opened EFW P-7B to SG-A ISOL (CV-2670), B HPI Block Valve (CV-1227), and A HPI Block Valve (CV1228) using manual handwheel and clutch lever.

TRANSITION NOTE: The examinee should proceed to the 354 elevation waste gas room.

C

13.

Slowly open BWST Outlet CV-1408.

POSITIVE CUE:

CV-1408 has stem full out, with the valve handwheel fully CW.

Opened CV-1408 using clutch lever and manual handwheel.

TUOI NUMBER:

A1JPM-RO-AOP08 Page 5 of 6 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT

14.

Check for flow noise as CV-1408 is opened.

POSITIVE CUE:

No flow noise is heard.

Checked for flow noise as CV1408 was opened.

TRANSITION NOTE: The examinee should proceed to the 335 elevation letdown filter area.

15.

Verify service water header pressure >40 psig.

POSITIVE CUE:

Service water pressure is 50 psig.

NEGATIVE CUE:

Service water pressure is 0 psig.

Opened RB Coolers VCC-2C &

2D PI-3813A ISOL SW-3813A and verified pressure >40 psig.

16.

Establish communications with the TSC and report completion of steps.

POSITIVE CUE:

All steps have been reported to TSC.

NOTE:

Provide the cue for steps missed.

NEGATIVE CUE:

Step 1 RCS is overcooling due to high steam flow.

Step 9. A OTSG level is going up rapidly.

Step 7, 10b or c, 11. Unable to establish HPI flow.

Operator Calls TSC via radio or telephone and reports completion of steps 2.B, 6.A, 6.B, 7.B.

INSTRUCTOR CUE: This concludes the JPM.

END

TUOI NUMBER:

A1JPM-RO-AOP08 Page 6 of 6 EXAMINEES COPY INITIAL CONDITIONS:

There is a Fire in the Cable Spreading Room. An Alternate Shutdown is in progress. At the Alternate Shutdown Cabinet, you have received a copy of OP 1203.002 and Section 1C.

INITIATING CUE:

The first 3 steps of OP 1203.002 Section 1C have been completed. Perform the actions required of RO #1 through step 3.14.

TUOI NUMBER:

Page 1 of 5 A1JPM-RO-EFW01 JOB PERFORMANCE MEASURE Unit:

1 Rev #

10 Date:

11/04/2003 TUOI NUMBER:

A1JPM-RO-EFW01 System/Duty Area:

Emergency Feedwater and EFIC Task:

Reset the Steam Driven Emergency Feedwater Pump after an overspeed trip JA#

ANO1-RO-EFW-NORM-13 KA Value RO 3.4 SRO 3.8 KA Reference 061 A2.04 Approved For Administration To: RO SRO Task Location: Inside CR:

Outside CR:

Both:

Suggested Testing Environment And Method (Perform Or Simulate): Simulate Plant Site:

Perform Simulator:

Lab:

Position Evaluated: RO:

X SRO:

X Actual Testing Environment: Simulator:

Plant Site:

Lab Testing Method: Simulate:

X Perform:

Approximate Completion Time In Minutes:

15 Minutes Reference(S):

1106.006 Exhibit A, change 063-08-0.

Examinee's Name:

SSN:

Evaluator's Name:

The Examinee's performance was evaluated against the standards contained in this JPM and is determined to be:

Satisfactory:

Unsatisfactory:

Performance Checklist Comments:

Start Time Stop Time Total Time Signed Date:

Signature indicates this JPM has been compared to its applicable procedure by a qualified individual (not the examinee) and is current with that revision.

TUOI NUMBER:

Page 2 of 5 A1JPM-RO-EFW01 THE EXAMINER SHALL REVIEW THE FOLLOWING WITH THE EXAMINEE:

The examiner shall review the Briefing Checklist - System Walkthrough portion of OP 1064.023 Attachment 6 with the examinee.

JPM INITIAL TASK CONDITIONS:

P7A Emergency Feedwater Pump has tripped on overspeed during an EFIC actuation.

TASK STANDARD:

P7A turbine has been reset per 1106.006 Exhibit A.

TASK PERFORMANCE AIDS:

OP 1106.006 Exhibit A, change 063-08-0.

SIMULATOR SETUP:

N/A

TUOI NUMBER:

Page 3 of 5 A1JPM-RO-EFW01 INITIATING CUE: The SM/CRS directs you to reset P7A overspeed trip per 1106.006, Exhibit A.

CRITICAL ELEMENTS (c): 2, 3, and 8 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT EXAMINERS NOTE: Simulate communications with the Control Room.

1. Verify the following valves are closed. If EFW initiate signal is present, manual control is required.



EFW Pump Turbine K3 Steam Admission Valves (CV-2613 and CV-2663)



EFW Pump Turbine K3 Steam Admission Valve Bypasses (SV-2613 and SV-2663)

POSITIVE CUE:

SV-2613, SV-2663, CV-2613, CV-2663 have valve stems full out with handwheels full CW.

Called control room to verify SV-2613, SV-2663, CV-2613, CV-2663 are closed.

C

2. Turn EFW Turbine K3 Trip-Throttle Valve (CV-6601A) handwheel clockwise. Observe rotation of screw raises sliding nut and latch lever to where it will engage the trip hook.

POSITIVE CUE:

Trip/ Throttle valve (CV-6601A) sliding nut raised and latch lever has engaged the trip hook.

Trip/ Throttle valve (CV-6601A) handwheel turned clockwise until sliding nut rises and latch lever engages the trip hook.

EXAMINERS NOTE: The following steps will reset the mechanical trip linkage.

C

3. Pull spring-loaded connecting rod against spring force to move head lever away from tappet and tappet nut.

POSITIVE CUE:

Head lever moved away from tappet and tappet nut.

Connecting rod pulled against spring force to move head lever away from tappet and tappet nut.

4. Lift and release tappet assembly POSITIVE CUE:

Tappet assembly lifted and released.

Tappet assembly lifted and released.

5. Verify tappet nut in trip reset position.

POSITIVE CUE:

Tappet nut in trip reset position.

Verified tappet nut in trip reset position.

TUOI NUMBER:

Page 4 of 5 A1JPM-RO-EFW01 C

PERFORMANCE CHECKLIST STANDARD N/A SAT UN SAT

6. Observe tappet returns to reset position.

POSITIVE CUE:

Tappet is in reset position.

Observed tappet returns to reset position.

7. Verify the following:





Tappet nut in trip reset position and properly aligned.

Spring tension holds connecting rod in position.

POSITIVE CUE:

Tappet nut in trip reset position and properly aligned.

Spring tension is holding connecting rod in position.

Verified tappet nut in trip reset position and properly aligned.

Verified spring tension holds connecting rod in position.

C

8. Slowly turn CV-6601A handwheel counterclockwise until valve is fully open.

POSITIVE CUE:

CV-6601A has valve stem full out with handwheel in the full CW position.

CV-6601A fully opened.

9. Close valve (CV-6601A) 3/4 turn to prevent binding on heatup.

POSITIVE CUE:

CV-6601A as you see it.

CV-6601A closed 3/4 turn.

EXAMINERS NOTE: Simulate communications with the Control Room.

10. Verify P-7A TURBINE TRIP (K12-B5) clear.

POSITIVE CUE:

P-7A TURBINE TRIP (K12-B5) clear Call Control Room and verified that P-7A TURBINE TRIP (K12-B5) is clear.

11. Notify Control Room that P-7A is ready for restart.

POSITIVE CUE:

Control Room notified that P-7A is ready for restart.

Control Room notified that P-7A is ready for restart.

EXAMINERS CUE: This concludes the JPM.

END

TUOI NUMBER:

A1JPM-RO-EFW01 Page 5 of 5 EXAMINEES COPY INITIAL CONDITIONS:

P7A Emergency Feedwater Pump has tripped on overspeed during an EFIC actuation.

INITIATING CUE:

The SM/CRS directs you to reset P7A overspeed trip per 1106.006, Exhibit A.

Appendix D Operator Actions Form ES-D-1 Facility: ANO-1 Scenario No.: 1 (NEW) Op-Test No.: 2004-1 Page 1 of 10 Examiners:

Operators:

Initial Conditions:

100% MOL; Severe Thunderstorm Warning for Pope and Conway counties.

Turnover::

National Weather service has issued a Severe Thunderstorm Warning for Pope and Conway Counties until 8:00 pm today. AOP 1203.025, Natural Emergencies, Section 2, High Winds/Tornado/Thunderstorm, steps 3.1 and 3.2 have been completed. #2 EDG OOS for fuel leak repairs. 1104.036 Supplement 11 is due right after turn-over.

Event No.

Malf. No.

Event Type*

Event Description 1

N/A N (ALL)

Perform 1104.036 Supplement 11 for EDG #1 2

TR568 I (BOR)

A OTSG operating level transmitter fails high 3

CAE RX7460 I (BOT)

RB atmosphere radioactivity monitor fails low. TS 3.4.15 determination.

4 N/A R (BOR)

Dispatcher orders down power to 650 MWe due to weather that has damaged Mablevale sub-station.

5 RX150 I (BOT)

Turbine EHC fails to respond in auto mode for ICS (manual control required) 6 CV2692 C (BOR)

One MSIV for B OTSG drifts shut-requires manual reactor trip per EOP 1202.001 7

MS131 M (ALL)

A OTSG steam leak in containment (MSLI activates). Transfer to 1202.003 overcooling if necessary.

8 ES264 CV2214 I (BOT)

Containment pressure >4psig but B train RBIC will fail to actuate automatically and an ICW isolation valve will fail open that should shut.

Operator will be required to manually initiate B RBIC and verify shut the redundant ICW valve to isolate ICW.

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Operator Actions Form ES-D-1 Page 2 of 10 Event No.

Time Malf. No.

Value/Ramp Time Event Description 8

T=0 IMF ES264 IMF CV2214 N/A 1

B Train of Reactor Bldg. Isolation and Cooling fails to auto actuate (ESAS channel 6)

ICW valve CV2214 fails to close upon ESAS actuation 1

T=0 N/A N/A Perform surveillance test of the #1 EDG for operability due to maintenance of #2 EDG.

2 T=~15 IMF TR568 292 / Ramp 3 Min.

A OTSG Operating Range Level Transmitter fails high.

3 T=20 CAE RX7460 N/A RB Sump Radiation Monitor fails low (RX7460) 4 T=25 N/A N/A The dispatcher requests an emergency power reduction to ~650 MWe to maintain system integrity.

5 T=25.5 IMF RX150 N/A Turbine EHC fails to respond.

6 T=30 IMF CV2692 0 / Ramp 1 Min.

B MSIV drifts shut requiring manual reactor trip.

7 T=35 IMF MS131

.4 / Ramp 3Min.

A OTSG Main Steam Line Leak inside containment.

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 1 Page 3 of 10 Event

Description:

Perform surveillance test of the #1 EDG for operability due to maintenance of #2 EDG.

Time Position Applicants Actions or Behavior T=0 CRS Directs the performance of the #1 EDG surveillance test per Supplement 11 of 1104.036.

CBOT Make plant announcement of the starting of #1 EDG.

CBOT Verify DG1 Volts Select switch NOT in OFF on C10.

CBOT Simultaneously depress the START pushbutton for #1 EDG and start the stopwatch.

CBOT Stop the stopwatch when DG1 voltage exceeds 3750 volts.

CBOT Record the time from start to >3750 volts in section 3.0.

CBOT Verify service water to DG1 coolers (CV3806) opens and record verification in section 3.0.

CBOT Adjust the voltage and frequency within the acceptable operating bands.

CBOT Stop DG1 by depressing the STOP pushbutton.

CBOT Verify associated critical and non-critical alarms on K01 clear.

EVENT TERMINATION CRITERIA

  1. 1 EDG is stopped or Next Event

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 2 Page 4 of 10 Event

Description:

A OTSG Operating Range Level Transmitter fails high.

Time Position Applicants Actions or Behavior T=15 CBOR Acknowledge and report annunciator K07 B4, SASS MISMATCH.

CRS Obtain Annunciator Corrective Action for K07 B4 for guidance.

CBOR Acknowledge and report annunciator K07 A2, A OTSG Hi Level Limit.

CRS Obtain Annunciator Corrective Action for K07 A2 for guidance.

CBOT Observe/verify A Operating range level on C13 level recorder.

CRS Direct the CBOR to place the A feed pump H/A station in HAND and stabilize plant.

CBOR Place the A main feed pump H/A station in HAND and balanced feed flows.

CRS Direct board operators to validate level transmitters by comparing to other (redundant) instruments.

CBOT/R Determine the A OTSG operating level transmitter is failing high.

CRS Verify plant stable and ICS in condition for instrument swap and direct the CBOR to select the other instrument.

CBOT Verify the Operating Range Level for A is indicating properly on C13.

CRS Direct placing ICS (A feed pump H/A station) back to AUTO EVENT TERMINATION CRITERIA ICS in AUTO or next event

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 3 Page 5 of 10 Event

Description:

RB atmosphere radioactivity monitor fails low.

Time Position Applicants Actions or Behavior T=20 CBOR Acknowledge and report annunciator K10 C1, Radiation Monitor Trouble.

CBOT Observe monitors at C24 and C25 and determine that RX7460 has FAILURE lights ON and BOTH monitors, RI7460 and RI7461, are reading 0 CPM.

CRS Refer to ACA 1203.012I for corrective action and guidance.

CRS Determine RB Atmosphere Gaseous Monitor is inoperable and refer to Tech Spec 3.4.15B.

CRS Initiate steps to meet requirements per Tech Specs.

CRS Initiate steps to have the failed monitor checked and repaired.

EVENT TERMINATION CRITERIA Tech Spec determination made

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 4 & 5 Page 6 of 10 Event

Description:

The Mablevale substation experiences storm damage causing the breakers in the switchyard supplying that line to open. The dispatcher requests an emergency power reduction to ~650 MWe to maintain system integrity. The Turbine fails to respond to lowering demand.

Time Position Applicants Actions or Behavior ROLE PLAY Call control room as EOC Dispatcher and direct unit to reduce power to 650 MWe as soon as possible due to transformer damage at the Mablevale substation.

If asked by control room personnel inform them that there is serious concern over grid stability due to the severe weather and substation damage.

T=25 CRS Direct CBOR to reduce unit load to 650 MWe.

CRS Direct operations per 1203.045, Rapid Plant Shutdown.

CBOR Commence reduction in unit load to 650 MWe using the ULD.

NOTE: Turbine may revert to Operator Auto mode before operator takes action.

CBOT/R Recognize and report to the CRS that the turbine is not responding during the power reduction.

NOTE: The crew may elect to place both the SG/RX master and the Turbine in the MANUAL mode. In this configuration, the CBOR controls the change in load demand and the CBOT will maintain turbine header pressure.

CRS Direct the CBOT to place the turbine in Operator Auto or Manual mode and control steam header pressure.

CBOT Take the turbine to manual or operator auto CRS Direct the CBOR to place the SG/RX Master H/A station in HAND and lower load to 650 MWe.

CBOR Place the SG/RX master in HAND and slowly toggle down.

continued

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 4 & 5 Page 7 of 10 Event

Description:

The Mablevale substation experiences storm damage causing the breakers in the switchyard supplying that line to open. The dispatcher requests an emergency power reduction to ~650 MWe to maintain system integrity. The Turbine fails to respond to lowering demand.

Time Position Applicants Actions or Behavior NOTE: In the manual mode on the SG/RX master, the operator has control of the rate the plant will change. It is expected the operator will maintain the rate of change near the directed rate by the CRS.

CBOT Verify Turbine EHC responds to lowering load and maintains header pressure at or near setpoint of 895#. (Operator Auto or Manual)

ROLE PLAY If asked about PPAS information, report ICS signal to EHC good.

CBOR Stabilize load at ~650MWe. Power should be near 65-67%.

EVENT TERMINATION CRITERIA Power reduction is complete OR the next event occurs

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 6 Page 8 of 10 Event

Description:

The B Main Steam Isolation Valve drifts shut, requiring a manual reactor trip per EOP 1202.001.

Time Position Applicants Actions or Behavior T=30 CBOR Acknowledge and report annunciator K07 C6, Main Steam Pressure Hi/Lo in alarm.

CRS Refer to ACA 1203.012I for guidance.

CBOR/T Observe the B MSIV, CV2692, closing.

CRS Direct the CBOR to TRIP the reactor and Carryout the immediate actions.

CBOR Trip the reactor by depressing the pushbutton on C03 and observing all control rods inserted and power dropping.

CBOT Manually trip the turbine by depressing the pushbutton on C01 and observing the throttle and governor valves close and output and exciter field breakers open.

CBOR/T Verify subcooling margin adequate.

CRS Provide direction to the crew per Reactor Trip EOP, 1202.001.

EVENT TERMINATION CRITERIA B MSIV closed and Reactor is tripped OR As determined by the lead examiner.

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 7 & 8 Page 9 of 10 Event

Description:

Main Steam Line rupture inside containment. Channel 6 of ESAS fails to auto actuate. ICW valve CV2214 fails to close.

Time Position Applicants Actions or Behavior T=35 CBOR Recognize A OTSG pressure dropping OR noticeably lower than B OTSG pressure.

CBOR Monitor RB pressure and temperature.

NOTE:

Due to rise in reactor building pressure and temperature, ESAS may actuate prior to the direction to trip the Reactor if CRS fails to recognize MSIV drifting shut in event 6 above.

Annunciator K12A1 will alarm due to the environmental conditions inside the Reactor Building. If panel 463 is checked for location of the alarm, instruct that module A2-5 lower, RB UNEP ZONE 32-K, in alarm.

CBOR/T Identify and announce ESAS has actuated on high RB Pressure.

CRS Transition to ESAS Procedure, EOP1202.010 and direct crew actions.

CRS Direct the verification of ESAS per RT10.

CBOR/T Recognize failure of Channel 6 of ESAS to auto actuate. Tech Spec 3.3.7A.

CT CBOR Manually actuate Channel 6 of ESAS using the button on C04.

CBOT Identify and report failure of CV2214 to close.

CRS Direct the CBOT to verify the redundant ICW valve on Channel 6, CV2215, closed.

CBOT Verify actuation of ESAS per RT 10.

CREW Recognize SG pressure < 900#

continued

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 1 Event No: 7 & 8 Page 10 of 10 Event

Description:

Main Steam Line rupture inside containment. Channel 6 of ESAS fails to auto actuate. ICW valve CV2214 fails to close.

Time Position Applicants Actions or Behavior CRS Transition to Overcooling Emergency Operating procedure (1202.003).

CT CBOT Manually override and secure HPI as directed by the CRS and the Emergency Operating Procedure.

CBOR Report A MSLI actuated.

EAL NUE 3.1 Uncontrolled OTSG Depressurization Resulting in MSLI Actuation CRS Provide RT6 to CBOR to verify proper MSLI and EFW actuation and control.

CBOR Verify proper MSLI and EFW actuation and control per RT6.

CBOR Control RCS pressure within the limits of Figure 3 per RT14 using PZR heaters EVENT AND SCENARIO TERMINATION CRITERIA RCS pressure and temperature stable with the A OTSG isolated, channel 6 of ESAS manually actuated, with the ICW flowpath isolated OR As determined by the lead examiner.

Appendix D Operator Actions Form ES-D-1 Facility: ANO-1 Scenario No.: 2 (MOD) Op-Test No.: 2004-1 Page 1 of 11 Examiners:

Operators:

Initial Conditions:

100% MOL, equilibrium Xenon, P4A and P4B in service (P4C down for maintenance).

Sluice gates SG-1, SG-2, and SG-4 open.

Turnover:

100% power, MOL, equilibrium Xenon. Expected P4C return to service and restore normal line-up within next 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.. #2 EDG is OOS to repair its governor (day 1 of 7 day LCO 3.8.1.B).

Event No.

Malf. No.

Event Type*

Event Description 1

TR625 I (BOT)

A CFT-LT LIS2416 fails low. SRO TS determination required.

2 N/A N (BOT)

Shift service water pump to P4A/P4C line-up, return P4B to standby 3

TR051 I (BOR)

Selected PZR level transmitter fails high 4

TR558 I (BOR)

B Main Feed flow transmitter drifts low slowly 5

BAT P1B_vibes C (BOR)

MFP B has excessive vibration.

6 N/A R (BOR)

Perform normal shutdown to repair MFP B.

7 ED183 DG175 M (ALL)

C (BOT)

Loss of Offsite power, Rx trip.

  1. 1 EDG fails to auto start and pushbutton on C10 fails to start it.

STATION BLACK-OUT 8

CV2645 C (BOR)

EFW valve fails open to A OTSG, resulting in level being raised higher than EFIC controlled SP.

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-1 Page 2 of 11 Event No.

Time Malf. No.

Value/Ramp Time Event Description 7&8 T=0 IMF DG175 IOR DI_DG1S ICM CV2645 N/A False 1

  1. 1 EDG fails to autostart Pushbutton on C10 fails to start the EDG.

EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.

1 T=2 IMF TR625 0 Ramp 0 A Core Flood Tank LT(LIS2416) fails low.

2 T=~10 N/A N/A Shift service water pumps to P4A/P4C line-up, return P4B to standby 3

T=20 IMF TR051 320 Ramp 2 Min.

PZR level transmitter (LT1001) fails to high 4

T=27 IMF TR558 1.0e06 Ramp 4 Min.

B Main Feed flow transmitter drifts low slowly 5

T=30 BAT P1B_vibes N/A Report that B Main Feed Pump has excessive vibration 6

T=~32 N/A N/A Perform normal shutdown to repair B MFP 7

T=40 IMF ED183 N/A Loss of offsite power occurs. Reactor trip.

STATION BLACKOUT NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 1 Page 3 of 11 Event

Description:

A CFT Level transmitter (LIS2416) fails low.

Time Position Applicants Actions or Behavior T=2 CBOR Recognize and report that annunciator K10 C5, A CFT LEVEL HI/LO, in alarm.

CRS Refer to ACA 1203.012I for corrective action.

CBOT Diagnose LIS2416 failure after comparing level indications for T2A on C16 and C18.

CRS Refer to Technical Specifications for applicability. ACA 1203.012I refers to TS 3.5.1 if actual level is high or low. Reference to the Technical Requirement Manual for instrumentation should be performed.

Technical Requirements Manual 3.3.5, Miscellaneous Instrumentation.

(Only one pressure and one level transmitter is required for operability)

EVENT TERMINATION CRITERIA Next Event

Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 2 Page 4 of 11 Event

Description:

Shift Service Water Pumps Time Position Applicants Actions or Behavior T~10 Role Play Call as work week manager and report P4C is ready for operation and rotation of pumps can proceed as anticipated.

CRS Direct shifting the service water pump configuration to P4A and P4C running and return P4B to standby status.

CBOT Notify Chemistry of pump rotation so chemical injection can be appropriately aligned.

CBOT Refer to Table 9.3 of 1104.029 to determine the service water alignment necessary for the pumps that will remain in service.

CBOT Verify sluice gates aligned to supply water to the desired SW Pumps.

CBOT Start P4C CBOT Stop P4B CBOT Notify the Outside AO to check for reverse rotation of P4B.

CBOT Align service water system per Table 9.3 CBOR/T Verify normal service water loop pressures.

CBOR/T Monitor SW bay level, CW bay level, and bay differentials for proper operation of SW bay strainiers.

EVENT TERMINATION CRITERIA Service Water Pumps rotated and system aligned OR Next Event

Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 3 Page 5 of 11 Event

Description:

PZR level transmitter (LT1001) fails to upscale Time Position Applicants Actions or Behavior T=20 CBOR Recognize and report that PZR level indications are mismatched CREW Diagnose LT1001 failure Tech. Spec. 3.3.15A CRS Direct operations per 1203.015 Pressurizer Systems Failure, section 4.0.

CRS Direct CBOR to select valid PZR level indicator for PZR level control.

CBOR Select LT1002 to control PZR level control valve (CV-1235) using hand switch on upright section of C04.

CBOR Verify CV-1235 opens to control PZR level at setpoint.

EVENT TERMINATION CRITERIA Pressurizer level control is selected to LT1002 and PZR level control valve is controlling level in auto.

Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 4 Page 6 of 11 Event

Description:

B Main Feed flow transmitter drifts low slowly Time Position Applicants Actions or Behavior T=27 CBOR Acknowledge and report annunciator K07 B4, SASS MISMATCH.

CBOR/T Determine the cause of the alarm by scanning C03, C04, and C13 for SASS ENABLE light that is not illuminated. Identify the B MFW flow SASS Enable not illuminated.

CBOR Determine that SASS did not transfer to the Y instrument for control.

CRS Refer to ACA 1203.012F for corrective action and guidance.

CRS Direct the CBOR to place both FW pump H/A stations, and control rods in MANUAL. (Reactor Demand or Diamond station to MANUAL is acceptable)

CBOR Place the BOTH MFW pump H/A stations to MANUAL and Reactor Demand or Diamond Station to MANUAL.

CRS Direct the CBOR to stabilize the plant CBOR Using the MFW pump H/A stations and control rods, balance feedwater flows and Tave to return to normal values.

CRS Direct the CBOT to compare failed instrument to the non-selected instrument using PMS.

CBOT Using PMS, verify the non-selected MFW flow is reading correctly.

CRS Direct the CBOR to select the Y MFW flow instrument for loop B.

CBOR Select the Y instrument for loop B MFW flow.

continued

Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 4 Page 7 of 11 Event

Description:

B Main Feed flow transmitter drifts low slowly Time Position Applicants Actions or Behavior NOTE: A caution placard on both C03 and C13 provides direction of selecting the associated X or Y MFW Temperature instrument when the MFW flow instrument is selected due to hard wired temperature compensation of the MFW flow instrument.

CRS Direct the CBOT to select the Y MFW temperature instrument for loop B on C13.

CBOT Select the Y MFW temperature instrument for loop B.

CBOR Place ICS in AUTO in accordance with 1105.004, ICS Operations.

EVENT TERMINATION CRITERIA B Main Feedwater Flow Y instrument selected and ICS in AUTO

Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 5 & 6 Page 8 of 11 Event

Description:

B Main Feedwater pump excessive vibration and power reduction to secure B MFW pump for repair.

Time Position Applicants Actions or Behavior T=30 CBOR Acknowledge and report annunciator K06 C3, B MFP TURB CONTROL SYS TROUBLE.

CRS Refer to ACA 1203.012E for corrective action and guidance.

CBOR/T Report vibration alarm on B MFP from OIT alarm panel OR TSI.

CRS Direct AO to verify/confirm B MFP has excessive vibration.

CRS Direct the CBOR and CBOT to perform a power reduction to approxiomately 40%

power to secure the B MFP.

CBOR Begin a power reduction to 40% power using the Unit Load Demand (ULD).

EVENT TERMINATION CRITERIA Power reduction >10%

Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 7 & 8 Page 9 of 11 Event

Description:

Loss of offsite power occurs. Reactor trip. #1 EDG fails to autostart and the pushbutton on C10 fails to start the EDG. STATION BLACKOUT. EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.

Time Position Applicants Actions or Behavior T=40 CREW Recognize loss of offsite power CRS Direct actions per the Reactor Trip Procedure, 1202.001.

CBOR Manually trip the reactor by depressing the Rx. Trip pushbutton. Verify all rods on bottom and power dropping.

CBOT Manually trip the turbine by depressing the Turbine Trip pushbutton CBOR/

CBOT Verify adequate subcooling margin.

CRS Transition to the Degraded Power Emergency Operating Procedure (1202.007).

Direct operations per 1202.007.

(Tech Spec. 3.8.1.G, AC Sources - Operating, Three or more required AC sources inoperable.)

CBOT Recognize the failure of #1 EDG to autostart CBOT Attempt to manually start #1 EDG using push-button on C10.

CRS Transition to the Blackout Emergency Operating Procedure (1202.008) and direct operations.

(Tech Spec. 3.8.1.G, AC Sources - Operating, Three or more required AC sources inoperable.)

CBOR Verify EFW actuated and perform RT5 CRS Dispatch AO to #1 EDG continued

Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 7 & 8 Page 10 of 11 Event

Description:

Loss of offsite power occurs. Reactor trip. #1 EDG fails to autostart and the pushbutton on C10 fails to start the EDG. STATION BLACKOUT. EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.

Time Position Applicants Actions or Behavior CRS Communicate with Unit 2 to make the AAC generator available for use by Unit 1.

CRS Direct manual isolation of letdown and RCP seal return.

CBOR Close CV1223 on C04.

CBOT Place RCP seal Bleedoff alternate path to quench tank valves in CLOSED position on C13.

CRS Dispatch the WCO to isolate letdown by manually closing CV1221 and isolating RCP seal return by manually closing CV1274.

CBOR Close both MSIVs (CV2691 and CV2692) on C09.

CBOR Report the EFW valve, CV2645 to the A OTSG, will not control and will not move in manual.

CT CBOR Manually throttle CV2627 on C09 to establish approximately 280 gpm.

CRS Direct the CBOT to place the AAC generator on the A3 bus utilizing O.P. 1107.002.

INSTRUCTOR NOTE: Make the AAC generator available to the crew by performing the following; RMF EDA901 TRUE Call as the Unit 2 CRS and report the AAC generator is available for loading the vital bus.

CT CBOT Place the AAC generator on the A3 bus.

continued

Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 2 Event No: 7 & 8 Page 11 of 11 Event

Description:

Loss of offsite power occurs. Reactor trip. #1 EDG fails to autostart and the pushbutton on C10 fails to start the EDG. STATION BLACKOUT. EFW valve to the A OTSG fails open resulting in level being raised higher than the EFIC controlled setpoint.

Time Position Applicants Actions or Behavior CRS Transition back to the Degraded Power procedure (1202.007).

CT CBOR Start P7B by releasing handswitch from Pull-to-lock and placing handswitch in the start position.

CRS Direct the CBOR to establish EFW to both OTSGs using P7B.

CBOR Verify EFW flow to the OTSGs.

EVENT AND SCENARIO TERMINATION CRITERIA Power restored to the A3 bus from the AAC generator and EFW re-established to both OTSGs from P7B OR as directed by the lead examiner.

Appendix D Operator Actions Form ES-D-1 Facility: ANO-1 Scenario No.: 3 (MOD) Op-Test No.: 2004-1 Page 1 of 10 Examiners:

Operators:

Initial Conditions:

90% power, equilibrium Xenon, MOL, #2 EDG SW valve fails to open on manual start.

Turnover::

90% power, MOL, equilibrium Xenon. AO routinely checking traveling screens due to mild shad run over past 24 hrs. System Engineering and Ops Management have discussed rotation of operating Makeup pumps. They will call control room when they want this evolution performed.

Event No.

Malf. No.

Event Type*

Event Description 1

IMF C5A C (BOT)

Condenser Vacuum Pump C5A trips 2

N/A N (ALL)

Shift running make up pumps from P36B to P36C to equalize run times 3

N/A R (BOR)

Load dispatcher orders power increase to 100%

due to grid loading.

4 TR458 I (BOR)

Controlling RCS pressure fails to 2280#

5 IMF CV1008 C (BOR)

PZR spray valve leaks by after cycling 6

IMF ED453 I (ALL)

SPDS failure 7

IMF RC005 M (ALL)

SB LOCA 8

IMF CV1400 C (BOR)

LPI injection valve CV1400 does not open.

9 IMF ES259 IMF ES260 C (BOR)

ESAS channels 1, 2 fail to actuate at RCS pressure set point

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-1 Page 2 of 10 Event No.

Time Malf. No.

Value/Ramp Time Event Description 8 & 9 T=0 IMF CV1400 IMF ES259 IMF ES260 IMF CV3807 0 Ramp 0 N/A 0 Ramp 0 LPI Block valve, CV1400, does not open.

ES channels 1 and 2 fail to auto actuate

  1. 2 EDG SW valve fails to open when EDG autostarts 1

T=2 IMF C5A OFF Condenser Vacuum Pump C5A trips 2

T=~10 N/A N/A Shift running Makeup Pumps 3

T=20 N/A N/A Load dispatcher orders power escalation to 100%

due to grid loading.

4 T=25 IMF TR458 2280 Ramp 2 Min.

Controlling RCS pressure fails to 2280 psig 5

T=Spray valve closure IMF CV1008

.12 PZR Spray Valve leaks through 6

T=30 IMF ED453 N/A SPDS failure 7

T=35 IMF RC005

.007 R 0 Small Break LOCA into the Containment Building NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 1 Page 3 of 10 Event

Description:

Condenser Vacuum Pump, C5A, trips.

Time Position Applicants Actions or Behavior T=2 CBOR Acknowledge and report annunciator K05 A3, Vacuum Pump Trip, alarm CRS Refer to ACA 1203.012D for corrective action and guidance.

CBOT Verify C5A has tripped by observing pump status on C02.

CBOT Manually start standby Vacuum Pump, C5B.

CRS Initiate steps to determine cause of pump trip. Call AO to investigate.

CBOT Monitor condenser vacuum for return to normal value.

CRS If condenser vacuum lowers to < 26.5 Hg, then go to Loss of Condenser Vacuum, 1203.016.

CBOT IF DESIRED, place the hand switch for C5A in normal-after-stop or Pull-To-Lock to clear the alarm.

EVENT TERMINATION CRITERIA C5B started and vacuum returned to normal OR Next Event NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 2 Page 4 of 10 Event

Description:

Shift Running Makeup pumps from P36B to P36C to equalize run times.

Time Position Applicants Actions or Behavior T=10 CRS Direct the CBOR and CBOT to shift makeup pumps by starting P36C and stopping P36B per 1104.002, Makeup and Purification System Operations Procedure.

CBOT Start P64C, Aux. Lube Oil pump for P36C.

CBOT After one minute of P64C operation, Start P36C.

CBOT Stop P64C.

CBOT Start P64B CBOT Stop P36B.

CBOR Verify proper discharge pressure on C04 and/or SPDS.

CBOT After one minute of P64B operation, Stop P64B.

CBOT Change the pump status tags for the correct alignment.

EVENT TERMINATION CRITERIA P36C running, P36B off NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 3 Page 5 of 10 Event

Description:

Power escalation to 100%.

Time Position Applicants Actions or Behavior T=20 CRS Direct the crew to continue power escalation to 100% at ~30/Hr.

CBOR Begin power escalation by verifying the rate of change set at ~.5%/min. and raising the demand with the ULD station.

CBOT Verify turbine load is rising and the turbine is maintaining header pressure at the desired setpoint.

CBOR Verify Reactor power rising and feedwater flow rising to maintain proper Tave.

EVENT TERMINATION CRITERIA Power returned to 100%

OR Next Event NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 4 & 5 Page 6 of 10 Event

Description:

Controlling RCS pressure fails and PZR Spray Valve leaks through.

Time Position Applicants Actions or Behavior T=25 CBOR Identify and report a disparity between RCS pressure indications.

NOTE: Crew may or may not identify the PZR Spray valve simultaneous with pressure indication failure.

CREW Diagnose failed RCS pressure indication using panel indications, plant computer and SPDS. (Tech. Spec. 3.3.1A)

CBOR If not identified earlier, report RCS pressure lowering and the pressurizer spray valve open.

CRS Direct operation per 1203.015, PZR Systems Failures, Section 6 CBOR Determine and report that the failed indication is controlling RCS pressure.

CBOR Manually close the pressurizer spray valve, CV1008.

CBOR Report RCS pressure continues to lower.

CRS Direct the CBOR to close the pressurizer spray isolation, CV-1009.

CT CBOR Close CV1009, Pressurizer Spray Valve Isolation.

CRS Direct the CBOR to select the alternate RCS pressure indication for control.

continued NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 4 & 5 Page 7 of 10 Event

Description:

Controlling RCS pressure fails and PZR Spray Valve leaks through.

Time Position Applicants Actions or Behavior CBOR Select PT1038 using the handswitch on panel C04.

CRS Reference 1203.015, Pressurizer Systems Failures, Pressurizer Spray Valve (CV-1008) Failure section. (Tech Spec. TRM 3.4.3.A for differential temperature of spray fluid and pressurizer temperature of >430°F)

CBOR Recognize and report that RCS pressure is recovering.

EVENT TERMINATION CRITERIA Alternate RCS pressure instrument selected and Pressurizer Spray valve closed OR Next Event NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 6 Page 8 of 10 Event

Description:

SPDS Loss of Power.

Time Position Applicants Actions or Behavior T=30 CREW Recognize and report the failure of the SPDS displays in the control room on panels C09 and C19.

CRS Contact Unit 2 or Computer Support to attempt to reboot the SPDS computers.

CRS Refer to 1105.014, SPDS Operation, to determine that there is a one hour time limit to restore operation of at least one SPDS system OR it will become a reportable item.

EVENT TERMINATION CRITERIA This event will exist for the remainder of the scenario.

NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-2 Op-Test No: 2004-1 Scenario No: 3 Event No: 7, 8, & 9 Page 9 of 10 Event

Description:

LOCA in the A RCS loop Tcold. ESAS channels 1 and 2 fail to auto actuate. #2 EDG service water valve fails to open when the EDG autostarts.

Time Position Applicants Actions or Behavior T=35 CBOR Identify pressurizer level and RCS pressure dropping.

CBOT Recognize and report RCS leakage into the Reactor Building.

(Tech Spec. 3.4.13.B RCS Operational LEAKAGE)

EAL 2.2, ALERT(RCS leakage >Normal Makeup capacity)

CRS Direct actions per the Reactor Trip Procedure, 1202.001.

CBOR Manually trip the reactor by depressing the Rx. Trip pushbutton. Verify all rods on bottom and power dropping.

CBOT Manually trip the turbine by depressing the Turbine Trip pushbutton CBOR/

CBOT Verify adequate subcooling margin.

CRS Direct initiation of HPI per RT 2.

NOTE The crew may manually initiate ESAS due to the imminent automatic actuation prior to reaching the setpoint and therefore may not identify the failure of channel 1 and 2 to auto actuate.

CREW Recognize the actuation of ESAS on low RCS pressure.

CBOR Identify the failure of channels 1 and 2 of ESAS to actuate.

CT CBOR Manually initiate channel 1 and 2 from the pushbuttons on C04 CRS Transition to ESAS procedure, 1202.010, and direct crew operations CBOR Check for adequate subcooling margin.

continued NUREG-1021, Revision 8, Supplement 1

Appendix D Operator Actions Form ES-D-2 NUREG-1021, Revision 8, Supplement 1 Op-Test No: 2004-1 Scenario No: 3 Event No: 7, 8, & 9 Page 10 of 10 Event

Description:

LOCA in the A RCS loop Tcold. ESAS channels 1 and 2 fail to auto actuate. #2 EDG service water valve fails to open when the EDG autostarts.

Time Position Applicants Actions or Behavior CBOT Verify proper ESAS actuation per RT 10.

CBOT Identify the failure of the service water valve for the #2 EDG to open when the EDG autostarts.

CBOT Attempt to open the service water valve for #2 EDG.

CRS Direct the stopping of the #2 EDG.

CBOT Stop the #2 EDG by placing the #2 EDG control switch in LOCKOUT position.

CBOR Close or verify closed the following valves; CV-1008, CV-1009, and CV-1000 CRS Transition to Loss of subcooling margin procedure, 1202.002, and direct crew actions.

CBOR Control RCS pressure within limits of Figure 3 of EOP (RT 14)

EVENT and SCENARIO TERMINATION CRITERIA All appropriate channels of ESAS actuated and HPI injecting water into RCS and RCS pressure stable.

OR As directed by the lead examiner