ONGOING REVIEW OF COLUMBIA GENERATING STATION - NRC | |||
INTEGRATED INSPECTION REPORT 05000397/2003007 DENIED | |||
NONCITED VIOLATION (50-397/03-07-01) | |||
Dear Mr. Parrish: | Dear Mr. Parrish: | ||
Thank you for your letter dated April 16, 2004, in response to our January 30, 2004, letter and | Thank you for your letter dated April 16, 2004, in response to our January 30, 2004, letter and | ||
integrated inspection report concerning use of nonsafety related instrument air during main | integrated inspection report concerning use of nonsafety related instrument air during main | ||
steam isolation valve local leak rate testing. A noncited violation (NCV 50-397/03-07-01) had | steam isolation valve local leak rate testing. A noncited violation (NCV 50-397/03-07-01) had | ||
been identified for inadequate local leak rate testing due to the use of the nonsafety related | been identified for inadequate local leak rate testing due to the use of the nonsafety related | ||
instrument air. | instrument air. | ||
In response to Noncited Violation 50-397/03-07-01, Energy Northwest requested that the NRC | In response to Noncited Violation 50-397/03-07-01, Energy Northwest requested that the NRC | ||
withdraw the noncited violation based on the belief that the applicable NRC regulations | withdraw the noncited violation based on the belief that the applicable NRC regulations | ||
(10 CFR Part 50 Appendix J, III.C.1) and other industry codes, that discuss closing valves for | (10 CFR Part 50 Appendix J, III.C.1) and other industry codes, that discuss closing valves for | ||
local leak rate testing, are subject to interpretation with respect to the required qualification of | local leak rate testing, are subject to interpretation with respect to the required qualification of | ||
the motive source used to close the valves. We understand that although Energy Northwest | the motive source used to close the valves. We understand that although Energy Northwest | ||
has denied the noncited violation, that Energy Northwest will perform the main steam isolation | has denied the noncited violation, that Energy Northwest will perform the main steam isolation | ||
valve local leak rate testing using the safety related air as a conservative method for ensuring | valve local leak rate testing using the safety related air as a conservative method for ensuring | ||
the main steam isolation valves are capable of performing their intended safety function. | the main steam isolation valves are capable of performing their intended safety function. | ||
The NRC is reviewing your response to Noncited Violation 50-397/03-07-01 and will inform you | The NRC is reviewing your response to Noncited Violation 50-397/03-07-01 and will inform you | ||
by a separate letter in the future of the results of our review. | by a separate letter in the future of the results of our review. | ||
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter will be | In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter will be | ||
available electronically for public inspection in the NRC Public Document Room or from the | available electronically for public inspection in the NRC Public Document Room or from the | ||
Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS | Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS | ||
is accessible from the NRC Web site at | is accessible from the NRC Web site at | ||
http://www.gov/reading-rm/adams.html (the Public Electronic Reading Room). | http://www.gov/reading-rm/adams.html (the Public Electronic Reading Room). | ||
Sincerely, | |||
/RA/ | |||
William B. Jones, Chief | |||
Project Branch E | |||
Division of Reactor Projects | |||
-2- | |||
Docket: 50-397 | Energy Northwest | ||
License: NPF-21 | Docket: 50-397 | ||
License: NPF-21 | |||
cc: | cc: | ||
Rodney Webring (Mail Drop PE04) | Rodney Webring (Mail Drop PE04) | ||
Vice President, Nuclear Generation | Vice President, Nuclear Generation | ||
Energy Northwest | Energy Northwest | ||
P.O. Box 968 | P.O. Box 968 | ||
Richland, WA 99352-0968 | Richland, WA 99352-0968 | ||
Albert E. Mouncer (Mail Drop PE01) | Albert E. Mouncer (Mail Drop PE01) | ||
Vice President, Corporate Services/ | Vice President, Corporate Services/ | ||
General Counsel/CFO | |||
Energy Northwest | Energy Northwest | ||
P.O. Box 968 | P.O. Box 968 | ||
Richland, WA 99352-0968 | Richland, WA 99352-0968 | ||
Chairman | Chairman | ||
Energy Facility Site Evaluation Council | Energy Facility Site Evaluation Council | ||
P.O. Box 43172 | P.O. Box 43172 | ||
Olympia, WA 98504-3172 | Olympia, WA 98504-3172 | ||
Douglas W. Coleman (Mail Drop PE20) | Douglas W. Coleman (Mail Drop PE20) | ||
Manager, Performance Assessment | Manager, Performance Assessment | ||
and Regulatory Programs | |||
Energy Northwest | Energy Northwest | ||
P.O. Box 968 | P.O. Box 968 | ||
Richland, WA 99352-0968 | Richland, WA 99352-0968 | ||
Christina L. Perino (Mail Drop PE20) | Christina L. Perino (Mail Drop PE20) | ||
Manager, Licensing | Manager, Licensing | ||
Energy Northwest | Energy Northwest | ||
P.O. Box 968 | P.O. Box 968 | ||
Richland, WA 99352-0968 | Richland, WA 99352-0968 | ||
Max Benitz, Chairman | Max Benitz, Chairman | ||
Benton County Board of Commissioners | Benton County Board of Commissioners | ||
P.O. Box 190 | P.O. Box 190 | ||
Prosser, WA 99350-0190 | Prosser, WA 99350-0190 | ||
Dale K. Atkinson (Mail Drop PE08) | Dale K. Atkinson (Mail Drop PE08) | ||
Vice President, Technical Services | Vice President, Technical Services | ||
Energy Northwest | Energy Northwest | ||
P.O. Box 968 | P.O. Box 968 | ||
Richland, WA 99352-0968 | Richland, WA 99352-0968 | ||
-3- | |||
Energy Northwest | |||
Thomas C. Poindexter, Esq. | Thomas C. Poindexter, Esq. | ||
Winston & Strawn | Winston & Strawn | ||
1400 L Street, N.W. | 1400 L Street, N.W. | ||
Washington, DC 20005-3502 | Washington, DC 20005-3502 | ||
Bob Nichols | Bob Nichols | ||
Executive Policy Division | Executive Policy Division | ||
Office of the Governor | Office of the Governor | ||
P.O. Box 43113 | P.O. Box 43113 | ||
Olympia, WA 98504-3113 | Olympia, WA 98504-3113 | ||
Lynn Albin, Radiation Physicist | Lynn Albin, Radiation Physicist | ||
Washington State Department of Health | Washington State Department of Health | ||
P.O. Box 47827 | P.O. Box 47827 | ||
Olympia, WA 98504-7827 | Olympia, WA 98504-7827 | ||
-4- | |||
Energy Northwest | |||
Electronic distribution by RIV: | Electronic distribution by RIV: | ||
Regional Administrator (BSM1) | Regional Administrator (BSM1) | ||
| Line 130: | Line 134: | ||
Victor Dricks | Victor Dricks | ||
Bill Maier | Bill Maier | ||
ADAMS: | ADAMS: Yes | ||
No Initials: __WBJ__ | |||
R:\_COL\2004\EA04-101.wpd | Publicly Available Non-Publicly Available | ||
Sensitive | |||
Non-Sensitive | |||
R:\\_COL\\2004\\EA04-101.wpd | |||
RIV:C:DRP/E | |||
OFFICIAL RECORD COPY | WBJones | ||
/RA/ | |||
05/21/04 | |||
OFFICIAL RECORD COPY | |||
T=Telephone E=E-mail F=Fax | |||
}} | }} | ||
Latest revision as of 02:54, 16 January 2025
| ML041420517 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 05/21/2004 |
| From: | William Jones NRC/RGN-IV/DRP/RPB-E |
| To: | Parrish J Energy Northwest |
| References | |
| EA-04-101, IR-03-007 | |
| Download: ML041420517 (4) | |
See also: IR 05000397/2003007
Text
May 21, 2004
EA 04-101
Mr. J. V. Parrish
Chief Executive Officer
Energy Northwest
P.O. Box 968; MD 1023
Richland, Washington 99352-0968
SUBJECT:
ONGOING REVIEW OF COLUMBIA GENERATING STATION - NRC
INTEGRATED INSPECTION REPORT 05000397/2003007 DENIED
NONCITED VIOLATION (50-397/03-07-01)
Dear Mr. Parrish:
Thank you for your letter dated April 16, 2004, in response to our January 30, 2004, letter and
integrated inspection report concerning use of nonsafety related instrument air during main
steam isolation valve local leak rate testing. A noncited violation (NCV 50-397/03-07-01) had
been identified for inadequate local leak rate testing due to the use of the nonsafety related
instrument air.
In response to Noncited Violation 50-397/03-07-01, Energy Northwest requested that the NRC
withdraw the noncited violation based on the belief that the applicable NRC regulations
(10 CFR Part 50 Appendix J, III.C.1) and other industry codes, that discuss closing valves for
local leak rate testing, are subject to interpretation with respect to the required qualification of
the motive source used to close the valves. We understand that although Energy Northwest
has denied the noncited violation, that Energy Northwest will perform the main steam isolation
valve local leak rate testing using the safety related air as a conservative method for ensuring
the main steam isolation valves are capable of performing their intended safety function.
The NRC is reviewing your response to Noncited Violation 50-397/03-07-01 and will inform you
by a separate letter in the future of the results of our review.
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the
Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS
is accessible from the NRC Web site at
http://www.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
William B. Jones, Chief
Project Branch E
Division of Reactor Projects
-2-
Energy Northwest
Docket: 50-397
License: NPF-21
cc:
Rodney Webring (Mail Drop PE04)
Vice President, Nuclear Generation
Energy Northwest
P.O. Box 968
Richland, WA 99352-0968
Albert E. Mouncer (Mail Drop PE01)
Vice President, Corporate Services/
General Counsel/CFO
Energy Northwest
P.O. Box 968
Richland, WA 99352-0968
Chairman
Energy Facility Site Evaluation Council
P.O. Box 43172
Olympia, WA 98504-3172
Douglas W. Coleman (Mail Drop PE20)
Manager, Performance Assessment
and Regulatory Programs
Energy Northwest
P.O. Box 968
Richland, WA 99352-0968
Christina L. Perino (Mail Drop PE20)
Manager, Licensing
Energy Northwest
P.O. Box 968
Richland, WA 99352-0968
Max Benitz, Chairman
Benton County Board of Commissioners
P.O. Box 190
Prosser, WA 99350-0190
Dale K. Atkinson (Mail Drop PE08)
Vice President, Technical Services
Energy Northwest
P.O. Box 968
Richland, WA 99352-0968
-3-
Energy Northwest
Thomas C. Poindexter, Esq.
Winston & Strawn
1400 L Street, N.W.
Washington, DC 20005-3502
Bob Nichols
Executive Policy Division
Office of the Governor
P.O. Box 43113
Olympia, WA 98504-3113
Lynn Albin, Radiation Physicist
Washington State Department of Health
P.O. Box 47827
Olympia, WA 98504-7827
-4-
Energy Northwest
Electronic distribution by RIV:
Regional Administrator (BSM1)
DRP Director (ATH)
DRS Director (DDC)
Senior Resident Inspector (GDR)
Branch Chief, DRP/E (WBJ)
Senior Project Engineer, DRP/E (VGG)
Staff Chief, DRP/TSS (PHH)
RITS Coordinator (KEG)
Rebecca Tadesse, OEDO RIV Coordinator (RXT)
Columbia Site Secretary (LEF1)
Dan Merzke, Pilot Plant Program (DXM2)
RidsNrrDipmLipb
OEMAIL
OEWEB
Gary Sanborn
ADAMS: Yes
No Initials: __WBJ__
Publicly Available Non-Publicly Available
Sensitive
Non-Sensitive
R:\\_COL\\2004\\EA04-101.wpd
RIV:C:DRP/E
WBJones
/RA/
05/21/04
OFFICIAL RECORD COPY
T=Telephone E=E-mail F=Fax