ML063400561: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 20: Line 20:
{{#Wiki_filter:December 6, 2006
{{#Wiki_filter:December 6, 2006
EA-06-296
EA-06-296
James M. Levine, Executive
James M. Levine, Executive  
   Vice President, Generation
   Vice President, Generation
Mail Station 7602
Mail Station 7602
Arizona Public Service Company
Arizona Public Service Company
P.O. Box 52034
P.O. Box 52034
Phoenix, AZ 85072-2034
Phoenix, AZ 85072-2034
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, and 3 - NRC
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, and 3 - NRC
              SPECIAL INSPECTION REPORT 05000528/2006012; 05000529/2006012;
SPECIAL INSPECTION REPORT 05000528/2006012; 05000529/2006012;
              05000530/2006012
05000530/2006012
Dear Mr. Levine:
Dear Mr. Levine:
On November 30, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed a special
On November 30, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed a special
inspection at your Palo Verde Nuclear Generating Station, Units 1, 2, and 3. This inspection
inspection at your Palo Verde Nuclear Generating Station, Units 1, 2, and 3. This inspection
examined activities associated with the Unit 3 Train A emergency diesel generator (EDG)
examined activities associated with the Unit 3 Train A emergency diesel generator (EDG)
failures that occurred on July 25 and September 22, 2006. On both occasions the EDG failed
failures that occurred on July 25 and September 22, 2006. On both occasions the EDG failed
to produce an output voltage during testing. The NRC's initial evaluation satisfied the criteria in
to produce an output voltage during testing. The NRC's initial evaluation satisfied the criteria in
NRC Management Directive 8.3, NRC Incident Investigation Program, for conducting a special
NRC Management Directive 8.3, NRC Incident Investigation Program, for conducting a special
inspection. The basis for initiating this special inspection is further discussed in the Charter,
inspection. The basis for initiating this special inspection is further discussed in the Charter,
which is included as Attachment 2 to this report. The determination that the inspection would
which is included as Attachment 2 to this report. The determination that the inspection would
be conducted was made by the NRC on September 29, 2006, and the inspection started on
be conducted was made by the NRC on September 29, 2006, and the inspection started on
October 2, 2006.
October 2, 2006.
The enclosed special inspection report documents the inspection findings which were discussed
The enclosed special inspection report documents the inspection findings which were discussed
on November 9, 2006, with you, and other members of your staff, and on November 30, 2006,
on November 9, 2006, with you, and other members of your staff, and on November 30, 2006,
with Mr. David Mauldin, Vice President, Engineering, and other members of your staff.
with Mr. David Mauldin, Vice President, Engineering, and other members of your staff.  
The inspection examined activities conducted under your license as they relate to safety and
The inspection examined activities conducted under your license as they relate to safety and
compliance with the Commission's rules and regulations and with the conditions of your license.
compliance with the Commission's rules and regulations and with the conditions of your license.  
The inspectors reviewed selected procedures and records, observed activities, and interviewed
The inspectors reviewed selected procedures and records, observed activities, and interviewed
personnel.
personnel.
The attached report discusses two findings that appear to have low to moderate safety
The attached report discusses two findings that appear to have low to moderate safety
significance (White). As described in Section 3.0 of this report, the NRC concluded that the
significance (White). As described in Section 3.0 of this report, the NRC concluded that the
failure to establish appropriate instructions for performing corrective maintenance activities on a
failure to establish appropriate instructions for performing corrective maintenance activities on a
K-1 relay resulted in the Unit 3 Train A EDG being inoperable between September 4 and 22,
K-1 relay resulted in the Unit 3 Train A EDG being inoperable between September 4 and 22,
2006. Additionally, the failure to identify and correct the cause of the erratic EDG K-1 relay
2006. Additionally, the failure to identify and correct the cause of the erratic EDG K-1 relay
operation prior to installation of the relay on July 26, 2006, was identified as another
operation prior to installation of the relay on July 26, 2006, was identified as another
performance deficiency that contributed to the Unit 3 Train A EDG being inoperable for a period
performance deficiency that contributed to the Unit 3 Train A EDG being inoperable for a period


Arizona Public Service Company                   -2-
Arizona Public Service Company
greater than the Technical Specification completion time. The safety significance of these
-2-
greater than the Technical Specification completion time. The safety significance of these
findings was assessed on the basis of the best available information, including influential
findings was assessed on the basis of the best available information, including influential
assumptions, using the applicable Significance Determination Process and were preliminarily
assumptions, using the applicable Significance Determination Process and were preliminarily
determined to be White (i.e., low to moderate safety significance) findings. Preliminarily, these
determined to be White (i.e., low to moderate safety significance) findings. Preliminarily, these
findings have a low to moderate safety significance when assuming a loss of offsite power
findings have a low to moderate safety significance when assuming a loss of offsite power
initiating event and the Unit 3 Train A EDG being in an unreliable condition for approximately
initiating event and the Unit 3 Train A EDG being in an unreliable condition for approximately
40 days and a nonfunctional condition for approximately 18 days. Attachment 3 of this report
40 days and a nonfunctional condition for approximately 18 days. Attachment 3 of this report
provides a detailed description of the preliminary risk assessment. In accordance with NRC
provides a detailed description of the preliminary risk assessment. In accordance with NRC
Inspection Manual Chapter (IMC) 0609, Significance Determination Process, we intend to
Inspection Manual Chapter (IMC) 0609, Significance Determination Process, we intend to
complete our evaluation using the best available information and issue our final determination
complete our evaluation using the best available information and issue our final determination
of safety significance within 90 days of this letter.
of safety significance within 90 days of this letter.
These findings do not represent an immediate safety concern because of the corrective actions
These findings do not represent an immediate safety concern because of the corrective actions
you have taken. These actions involved inspecting, cleaning, and implementing mechanical
you have taken. These actions involved inspecting, cleaning, and implementing mechanical
adjustments, as appropriate, to the operating mechanism of the EDG K-1 relays.
adjustments, as appropriate, to the operating mechanism of the EDG K-1 relays.
Also, these findings constitute apparent violations of NRC requirements and are being
Also, these findings constitute apparent violations of NRC requirements and are being
considered for escalated enforcement action in accordance with the NRC Enforcement Policy.
considered for escalated enforcement action in accordance with the NRC Enforcement Policy.  
The current Enforcement Policy is included on the NRCs web site at
The current Enforcement Policy is included on the NRCs web site at  
http://www.nrc.gov/reading-rm/adams.html.
http://www.nrc.gov/reading-rm/adams.html.
Before we make a final decision on this matter, we are providing you an opportunity to present
Before we make a final decision on this matter, we are providing you an opportunity to present
to the NRC your perspectives on the facts and assumptions, used by the NRC to arrive at the
to the NRC your perspectives on the facts and assumptions, used by the NRC to arrive at the
findings and their significance, at a Regulatory Conference or in writing. As discussed during a
findings and their significance, at a Regulatory Conference or in writing. As discussed during a
telephone call with Mr. Scott Bauer, Department Leader, Regulatory Affairs, we understand that
telephone call with Mr. Scott Bauer, Department Leader, Regulatory Affairs, we understand that
it is your intent to discuss your perspectives during a Regulatory Conference. Accordingly, a
it is your intent to discuss your perspectives during a Regulatory Conference. Accordingly, a
Regulatory Conference is scheduled to be conducted in the NRC Region IV office in Arlington,
Regulatory Conference is scheduled to be conducted in the NRC Region IV office in Arlington,
Texas, on January 16, 2007. We encourage you to submit supporting documentation at least
Texas, on January 16, 2007. We encourage you to submit supporting documentation at least
one week prior to the conference in an effort to make the conference more efficient and
one week prior to the conference in an effort to make the conference more efficient and
effective. This Regulatory Conference will be open to public observation.
effective. This Regulatory Conference will be open to public observation.  
Since the NRC has not made a final determination in this matter, no Notice of Violation is being
Since the NRC has not made a final determination in this matter, no Notice of Violation is being
issued for these inspection findings at this time. In addition, please be advised that the number
issued for these inspection findings at this time. In addition, please be advised that the number
and characterization of apparent violations described in the enclosed inspection report may
and characterization of apparent violations described in the enclosed inspection report may
change as a result of further NRC review.
change as a result of further NRC review.  
The report also documents one finding with two examples involving inadequate implementation
The report also documents one finding with two examples involving inadequate implementation
of the operability determination process. This finding was determined to be a violation of very
of the operability determination process. This finding was determined to be a violation of very
low safety significance. Because of the very low safety significance and because it was entered
low safety significance. Because of the very low safety significance and because it was entered
into your corrective action program, the NRC is treating this finding as a noncited violation
into your corrective action program, the NRC is treating this finding as a noncited violation
consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest the noncited
consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest the noncited
violation in this report, you should provide a response within 30 days of the date of this
violation in this report, you should provide a response within 30 days of the date of this
inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission,
inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission,
ATTN.: Document Control Desk, Washington, DC 20555-0001; and the NRC Resident
ATTN.: Document Control Desk, Washington, DC 20555-0001; and the NRC Resident
Inspector at the Palo Verde Nuclear Generating Station.
Inspector at the Palo Verde Nuclear Generating Station.
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter
Line 100: Line 102:
Document Room or from the Publicly Available Records (PARS) component of NRC's
Document Room or from the Publicly Available Records (PARS) component of NRC's


Arizona Public Service Company               -3-
Arizona Public Service Company
document system (ADAMS). ADAMS is accessible from the NRC Web site at
-3-
document system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
                                          Sincerely,
Sincerely,  
                                          /RA/
/RA/
                                          Arthur T. Howell III, Director
Arthur T. Howell III, Director
                                          Division of Reactor Projects
Division of Reactor Projects
Dockets: 50-528
Dockets:   50-528
            50-529
                50-529
            50-530
                50-530
Licenses: NPF-41
Licenses: NPF-41
            NPF-51
                NPF-51
            NPF-74
                NPF-74
Enclosure:
Enclosure:
Inspection Report 05000528/2006012; 05000529/2006012; 05000530/2006012
Inspection Report 05000528/2006012; 05000529/2006012; 05000530/2006012
    w/Attachment 1: Supplemental Information
w/Attachment 1: Supplemental Information
      Attachment 2: Special Inspection Charter
  Attachment 2: Special Inspection Charter
      Attachment 3: Significance Determination Evaluation
  Attachment 3: Significance Determination Evaluation
cc w/enclosure:
cc w/enclosure:
Steve Olea
Steve Olea
Arizona Corporation Commission
Arizona Corporation Commission
1200 W. Washington Street
1200 W. Washington Street
Phoenix, AZ 85007
Phoenix, AZ 85007
Douglas K. Porter, Senior Counsel
Douglas K. Porter, Senior Counsel
Southern California Edison Company
Southern California Edison Company
Law Department, Generation Resources
Law Department, Generation Resources
P.O. Box 800
P.O. Box 800
Rosemead, CA 91770
Rosemead, CA 91770
Chairman
Chairman
Maricopa County Board of Supervisors
Maricopa County Board of Supervisors
301 W. Jefferson, 10th Floor
301 W. Jefferson, 10th Floor
Phoenix, AZ 85003
Phoenix, AZ 85003
Aubrey V. Godwin, Director
Aubrey V. Godwin, Director
Arizona Radiation Regulatory Agency
Arizona Radiation Regulatory Agency
4814 South 40 Street
4814 South 40 Street
Phoenix, AZ 85040
Phoenix, AZ 85040
Craig K. Seaman, General Manager
Craig K. Seaman, General Manager
Regulatory Affairs and
Regulatory Affairs and  
   Performance Improvement
   Performance Improvement
Palo Verde Nuclear Generating Station
Palo Verde Nuclear Generating Station


Arizona Public Service Company             -4-
Arizona Public Service Company
-4-
Mail Station 7636
Mail Station 7636
P.O. Box 52034
P.O. Box 52034
Phoenix, AZ 85072-2034
Phoenix, AZ 85072-2034
Jeffrey T. Weikert
Jeffrey T. Weikert
Assistant General Counsel
Assistant General Counsel
Line 150: Line 154:
Mail Location 167
Mail Location 167
123 W. Mills
123 W. Mills
El Paso, TX 79901
El Paso, TX 79901
John W. Schumann
John W. Schumann
Los Angeles Department of Water & Power
Los Angeles Department of Water & Power
Southern California Public Power Authority
Southern California Public Power Authority
P.O. Box 51111, Room 1255-C
P.O. Box 51111, Room 1255-C
Los Angeles, CA 90051-0100
Los Angeles, CA 90051-0100
John Taylor
John Taylor
Public Service Company of New Mexico
Public Service Company of New Mexico
2401 Aztec NE, MS Z110
2401 Aztec NE, MS Z110
Albuquerque, NM 87107-4224
Albuquerque, NM 87107-4224
Thomas D. Champ
Thomas D. Champ
Southern California Edison Company
Southern California Edison Company
5000 Pacific Coast Hwy, Bldg. D1B
5000 Pacific Coast Hwy, Bldg. D1B
San Clemente, CA 92672
San Clemente, CA 92672
Robert Henry
Robert Henry
Salt River Project
Salt River Project
6504 East Thomas Road
6504 East Thomas Road
Scottsdale, AZ 85251
Scottsdale, AZ 85251
Brian Almon
Brian Almon
Public Utility Commission
Public Utility Commission
Line 173: Line 177:
P.O. Box 13326
P.O. Box 13326
1701 North Congress Avenue
1701 North Congress Avenue
Austin, TX 78701-3326
Austin, TX 78701-3326
Karen O'Regan
Karen O'Regan
Environmental Program Manager
Environmental Program Manager
Line 179: Line 183:
Office of Environmental Programs
Office of Environmental Programs
200 West Washington Street
200 West Washington Street
Phoenix, AZ 85003
Phoenix, AZ 85003  
Matthew Benac
Matthew Benac
Assistant Vice President
Assistant Vice President
Nuclear & Generation Services
Nuclear & Generation Services


Arizona Public Service Company -5-
Arizona Public Service Company
-5-
El Paso Electric Company
El Paso Electric Company
340 East Palm Lane, Suite 310
340 East Palm Lane, Suite 310
Phoenix, AZ 85004
Phoenix, AZ 85004


Arizona Public Service Company               -6-
Arizona Public Service Company
-6-
Electronic distribution by RIV:
Electronic distribution by RIV:
Regional Administrator (BSM1)
Regional Administrator (BSM1)
Line 209: Line 215:
G. M. Vasquez (GMV)
G. M. Vasquez (GMV)
OE:EA File (RidsOeMailCenter)
OE:EA File (RidsOeMailCenter)
SUNSI Review Completed: __TWP_ ADAMS: / Yes G No                 Initials: __TWP____
SUNSI Review Completed: __TWP_   ADAMS: / Yes
/ Publicly Available      G Non-Publicly Available G Sensitive     / Non-Sensitive
G No         Initials: __TWP____  
R:\_REACTORS\_PV\2006\PV2006-12RP-MCH.wpd
/   Publicly Available      G   Non-Publicly Available     G   Sensitive
RIV:SPE:DRP/D RI:DRS/EB1           PE:DRP/D       C:DRP/D     SRA:DRS       ACES
/   Non-Sensitive
MCHay               SPRutenkroger MRBloodgood TWPruett         MFRunyan     GMVasquez
R:\\_REACTORS\\_PV\\2006\\PV2006-12RP-MCH.wpd
    /RA/               MCHay For MCHay For             /RA/         /RA/     /RA/
RIV:SPE:DRP/D RI:DRS/EB1
   11 /27/06           11/28/06         11/28/06    11/28/06    11/28/06       11/28/06
PE:DRP/D
D:DRP
C:DRP/D
ATHowell III
SRA:DRS
    /RA/
ACES
MCHay
SPRutenkroger
MRBloodgood TWPruett
MFRunyan
GMVasquez
/RA/
MCHay   For
MCHay   For
/RA/
/RA/
/RA/
   11 /27/06
    11/28/06
    11/28/06
     11/28/06
     11/28/06
    11/28/06
D:DRP
ATHowell III
/RA/
     12/06/06
     12/06/06
OFFICIAL RECORD COPY                               T=Telephone       E=E-mail     F=Fax
OFFICIAL RECORD COPY  
T=Telephone           E=E-mail       F=Fax


                U.S. NUCLEAR REGULATORY COMMISSION
U.S. NUCLEAR REGULATORY COMMISSION  
                                    REGION IV
REGION IV  
Dockets:     50-528; 50-529; 50-530
Dockets:
Licenses:   NPF-41; NPF-51; NPF-74
50-528; 50-529; 50-530
Report No.: 05000528/2006012; 05000529/2006012; 05000530/2006012
Licenses:
Licensee:   Arizona Public Service Company
NPF-41; NPF-51; NPF-74
Facility:   Palo Verde Nuclear Generating Station, Units 1, 2, and 3
Report No.:
Location:   5951 S. Wintersburg Road
05000528/2006012; 05000529/2006012; 05000530/2006012
            Tonopah, Arizona
Licensee:
Dates:       October 2 through November 30, 2006
Arizona Public Service Company
Inspectors: M. Hay, Senior Project Engineer, Team Leader
Facility:
            Dr. S. Rutenkroger, Reactor Inspector, Engineering Branch 1
Palo Verde Nuclear Generating Station, Units 1, 2, and 3
            M. Runyan, Senior Reactor Analyst
Location:
Accompanied: M. Bloodgood, Reactor Engineer, Nuclear Safety Professional Development
5951 S. Wintersburg Road  
            Program
Tonopah, Arizona
Approved By: Arthur T. Howell III, Director
Dates:
            Division of Reactor Projects
October 2 through November 30, 2006
Inspectors:
M. Hay, Senior Project Engineer, Team Leader
Dr. S. Rutenkroger, Reactor Inspector, Engineering Branch 1
M. Runyan, Senior Reactor Analyst
Accompanied:
M. Bloodgood, Reactor Engineer, Nuclear Safety Professional Development
Program  
Approved By:
Arthur T. Howell III, Director  
Division of Reactor Projects


                                    SUMMARY OF FINDINGS
Enclosure
1
SUMMARY OF FINDINGS
IR 05000528/2006012; 05000529/2006012; 05000530/2006012; 10/02/2006 - 11/09/2006; Palo
IR 05000528/2006012; 05000529/2006012; 05000530/2006012; 10/02/2006 - 11/09/2006; Palo
Verde Nuclear Generating Station, Units 1, 2, and 3: Special Inspection in response to Unit 3
Verde Nuclear Generating Station, Units 1, 2, and 3: Special Inspection in response to Unit 3
Train A EDG failures on July 25 and September 22, 2006.
Train A EDG failures on July 25 and September 22, 2006.  
The report covered a 5-day period (October 2-6, 2006) of onsite inspection, with in-office review
The report covered a 5-day period (October 2-6, 2006) of onsite inspection, with in-office review
through November 30, 2006, by a special inspection team consisting of one senior project
through November 30, 2006, by a special inspection team consisting of one senior project
engineer, one reactor inspector, one reactor engineer, and one senior reactor analyst. Three
engineer, one reactor inspector, one reactor engineer, and one senior reactor analyst. Three
findings were identified. The significance of most findings is indicated by its color (Green,
findings were identified. The significance of most findings is indicated by its color (Green,
White, Yellow, Red) using Inspection Manual Chapter 0609, Significance Determination
White, Yellow, Red) using Inspection Manual Chapter 0609, Significance Determination
Process. Findings for which the significance determination process does not apply may be
Process. Findings for which the significance determination process does not apply may be
Green or be assigned a severity level after NRC management review. The NRC's program for
Green or be assigned a severity level after NRC management review. The NRC's program for
overseeing the safe operation of commercial nuclear power reactors is described in
overseeing the safe operation of commercial nuclear power reactors is described in
NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.
NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.
Line 256: Line 295:
The NRC conducted a special inspection to better understand the circumstances surrounding
The NRC conducted a special inspection to better understand the circumstances surrounding
two failures of the Unit 3 Train A emergency diesel generator that occurred on July 25 and
two failures of the Unit 3 Train A emergency diesel generator that occurred on July 25 and
September 22, 2006. Both failures involved the emergency diesel generator failing to obtain an
September 22, 2006. Both failures involved the emergency diesel generator failing to obtain an
output voltage during surveillance testing because of faulty K-1 relay operation. In accordance
output voltage during surveillance testing because of faulty K-1 relay operation. In accordance
with NRC Management Directive 8.3, NRC Incident Investigation Program, it was determined
with NRC Management Directive 8.3, NRC Incident Investigation Program, it was determined
that this event involved repetitive failures of safety related equipment having potential adverse
that this event involved repetitive failures of safety related equipment having potential adverse
generic implications and had sufficient risk significance to warrant a special inspection.
generic implications and had sufficient risk significance to warrant a special inspection.  
A.     NRC-Identified and Self Revealing Findings
A.
        Cornerstone: Mitigating Systems
NRC-Identified and Self Revealing Findings
        *       TBD. The team identified an apparent violation of 10 CFR Part 50, Appendix B,
Cornerstone: Mitigating Systems
                Criterion V, Instructions, Procedures, and Drawings, for the failure to establish
*
                appropriate instructions for performing corrective maintenance activities on an
TBD. The team identified an apparent violation of 10 CFR Part 50, Appendix B,
                emergency diesel generator K-1 relay. As a result, following identification that a
Criterion V, Instructions, Procedures, and Drawings, for the failure to establish
                replacement emergency diesel generator K-1 relay was unreliable, the licensee
appropriate instructions for performing corrective maintenance activities on an  
                performed ineffective corrective maintenance activities on this relay. This
emergency diesel generator K-1 relay. As a result, following identification that a
                performance deficiency contributed to the Unit 3 Train A emergency diesel
replacement emergency diesel generator K-1 relay was unreliable, the licensee
                generator being inoperable between September 4 and 22, 2006, and a failure on
performed ineffective corrective maintenance activities on this relay. This
                September 22, 2006. Immediate corrective actions included inspection,
performance deficiency contributed to the Unit 3 Train A emergency diesel
                cleaning, and/or performing mechanical adjustments on all emergency diesel
generator being inoperable between September 4 and 22, 2006, and a failure on
                generator K-1 relays. This issue was entered into the licensees corrective
September 22, 2006. Immediate corrective actions included inspection,
                action program as Condition Report/Disposition Request 2926830.
cleaning, and/or performing mechanical adjustments on all emergency diesel
                The finding is greater than minor because it is associated with the equipment
generator K-1 relays. This issue was entered into the licensees corrective
                performance cornerstone objective to ensure the availability, reliability, and
action program as Condition Report/Disposition Request 2926830.
                capability of systems that respond to initiating events to prevent undesirable
The finding is greater than minor because it is associated with the equipment
                consequences. Using NRC Inspection Manual Chapter 0609, Significance
performance cornerstone objective to ensure the availability, reliability, and
                Determination Process, Phase 1 Worksheet, a Phase 2 evaluation was required
capability of systems that respond to initiating events to prevent undesirable
                                                  1                                      Enclosure
consequences. Using NRC Inspection Manual Chapter 0609, Significance
Determination Process, Phase 1 Worksheet, a Phase 2 evaluation was required


  because the finding resulted in the loss of the safety function of the Unit 3 Train
Enclosure
  A emergency diesel generator for greater than the Technical Specification
2
  completion time. The Phase 2 evaluation concluded that the finding was of low
because the finding resulted in the loss of the safety function of the Unit 3 Train
  to moderate safety significance. A Phase 3 preliminary significance
A emergency diesel generator for greater than the Technical Specification
  determination analysis also determined the finding was of low to moderate safety
completion time. The Phase 2 evaluation concluded that the finding was of low
  significance. The cause of this finding is related to the crosscutting element of
to moderate safety significance. A Phase 3 preliminary significance
  human performance associated with resources in that the licensee failed to
determination analysis also determined the finding was of low to moderate safety
  develop and implement appropriate work instructions prior to performing
significance. The cause of this finding is related to the crosscutting element of
  corrective maintenance activities on an emergency diesel generator K-1 relay
human performance associated with resources in that the licensee failed to
  (Section 3.0).
develop and implement appropriate work instructions prior to performing
* TBD. The team identified an apparent violation of 10 CFR Part 50, Appendix B,
corrective maintenance activities on an emergency diesel generator K-1 relay
  Criterion XVI, Corrective Actions, for the failure to identify and correct the
(Section 3.0).
  cause of erratic emergency diesel generator K-1 relay operation prior to
*
  installation of the relay on July 26, 2006. This performance deficiency
TBD. The team identified an apparent violation of 10 CFR Part 50, Appendix B,
  contributed to the Unit 3 Train A emergency diesel generator being inoperable
Criterion XVI, Corrective Actions, for the failure to identify and correct the
  between September 4 and 22, 2006, and a failure on September 22, 2006.
cause of erratic emergency diesel generator K-1 relay operation prior to
  Immediate corrective actions included inspection, cleaning, and performing
installation of the relay on July 26, 2006. This performance deficiency
  mechanical adjustments, as appropriate, on all emergency diesel generator K-1
contributed to the Unit 3 Train A emergency diesel generator being inoperable
  relays. This issue was entered into the licensees corrective action program as
between September 4 and 22, 2006, and a failure on September 22, 2006.  
  Condition Report/Disposition Request 2926830.
Immediate corrective actions included inspection, cleaning, and performing
  The finding is greater than minor because it is associated with the equipment
mechanical adjustments, as appropriate, on all emergency diesel generator K-1
  performance cornerstone objective to ensure the availability, reliability, and
relays. This issue was entered into the licensees corrective action program as
  capability of systems that respond to initiating events to prevent undesirable
Condition Report/Disposition Request 2926830.  
  consequences. Using NRC Inspection Manual Chapter 0609, Significance
The finding is greater than minor because it is associated with the equipment
  Determination Process, Phase 1 Worksheet, a Phase 2 evaluation was required
performance cornerstone objective to ensure the availability, reliability, and
  because the finding resulted in the loss of the safety function of the Unit 3 Train
capability of systems that respond to initiating events to prevent undesirable
  A emergency diesel generator for greater than the Technical Specification
consequences. Using NRC Inspection Manual Chapter 0609, Significance
  allowed outage time. The Phase 2 evaluation concluded that the finding was of
Determination Process, Phase 1 Worksheet, a Phase 2 evaluation was required
  low to moderate safety significance. A Phase 3 preliminary significance
because the finding resulted in the loss of the safety function of the Unit 3 Train
  determination analysis also determined the finding was of low to moderate
A emergency diesel generator for greater than the Technical Specification
  safety significance. The cause of this finding is related to the crosscutting
allowed outage time. The Phase 2 evaluation concluded that the finding was of
  element of problem identification and resolution in that the failure to fully
low to moderate safety significance. A Phase 3 preliminary significance
  evaluate and implement adequate corrective maintenance actions for the Unit 3
determination analysis also determined the finding was of low to moderate
  Train A emergency diesel generator resulted in the emergency diesel generator
safety significance. The cause of this finding is related to the crosscutting
  being inoperable for 18 days (Section 3.0).
element of problem identification and resolution in that the failure to fully
* The team identified two examples of a noncited violation of 10 CFR Part 50,
evaluate and implement adequate corrective maintenance actions for the Unit 3
  Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the failure
Train A emergency diesel generator resulted in the emergency diesel generator
  to perform operabilty determinations. In both examples, the licensee failed to
being inoperable for 18 days (Section 3.0).
  perform an operability determination following identification of a degraded
*
  condition that had the potential to adversely affect the safety function of all
The team identified two examples of a noncited violation of 10 CFR Part 50,
  emergency diesel generators. Specifically, an operability determination was not
Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the failure
  performed after identifying the failure of the Unit 3 Train A emergency diesel
to perform operabilty determinations. In both examples, the licensee failed to
  generator on July 25, 2006, was potentially the result of plastic debris affecting
perform an operability determination following identification of a degraded
  proper auxiliary contact operation of a K-1 relay. The licensee determined the
condition that had the potential to adversely affect the safety function of all
  debris most likely originated from a modification performed on all emergency
emergency diesel generators. Specifically, an operability determination was not
  diesel generator K-1 relays during initial plant startup. Following another failure
performed after identifying the failure of the Unit 3 Train A emergency diesel
                                    2                                        Enclosure
generator on July 25, 2006, was potentially the result of plastic debris affecting
proper auxiliary contact operation of a K-1 relay. The licensee determined the
debris most likely originated from a modification performed on all emergency
diesel generator K-1 relays during initial plant startup. Following another failure


          of the Unit 3 Train A emergency diesel generator on September 22, 2006, an
Enclosure
          operability determination was not performed after identifying the failure was the
3
          result of the K-1 relay actuating arm not providing adequate compression of the
of the Unit 3 Train A emergency diesel generator on September 22, 2006, an
          auxiliary contacts. The licensee determined this degraded condition most likely
operability determination was not performed after identifying the failure was the
          originated during implementation a modification done to all emergency diesel
result of the K-1 relay actuating arm not providing adequate compression of the
          generator K-1 relays during initial plant startup.
auxiliary contacts. The licensee determined this degraded condition most likely
          This finding is greater than minor because the failure to follow the operability
originated during implementation a modification done to all emergency diesel
          determination process, if left uncorrected, would become a more significant
generator K-1 relays during initial plant startup.
          safety concern in that degraded or nonconforming conditions would not be
This finding is greater than minor because the failure to follow the operability
          properly evaluated. Using the Phase 1 worksheet in NRC Inspection Manual
determination process, if left uncorrected, would become a more significant
          Chapter 0609, Significance Determination Process, the finding was determined
safety concern in that degraded or nonconforming conditions would not be
          to have very low safety significance because unreliable K-1 relay operation
properly evaluated. Using the Phase 1 worksheet in NRC Inspection Manual
          resulted in no actual loss of safety function of the other five emergency diesel
Chapter 0609, Significance Determination Process, the finding was determined
          generators prior to corrective actions being implemented, and the finding did not
to have very low safety significance because unreliable K-1 relay operation
          represent a potential risk significant condition because of a seismic, flooding, or
resulted in no actual loss of safety function of the other five emergency diesel
          severe weather event. This issue is documented in the licensees corrective
generators prior to corrective actions being implemented, and the finding did not
          action program as Condition Report/Disposition Requests 2928389 and
represent a potential risk significant condition because of a seismic, flooding, or
          2940558. The cause of this finding is related to the crosscutting element of
severe weather event. This issue is documented in the licensees corrective
          problem identification and resolution in that engineering personnel failed to
action program as Condition Report/Disposition Requests 2928389 and
          properly evaluate and perform operability determinations for identified degraded
2940558. The cause of this finding is related to the crosscutting element of
          conditions affecting the emergency diesel generators (Section 4.0).
problem identification and resolution in that engineering personnel failed to
B. Licensee-Identified Findings
properly evaluate and perform operability determinations for identified degraded
  None.
conditions affecting the emergency diesel generators (Section 4.0).
                                            3                                      Enclosure
B.
Licensee-Identified Findings
None.


                                      REPORT DETAILS
Enclosure
1.0 SPECIAL INSPECTION SCOPE
4
    The NRC conducted this special inspection to better understand the circumstances
REPORT DETAILS
    surrounding two failures of the Unit 3 Train A emergency diesel generator (EDG) that
1.0
    occurred on July 25 and September 22, 2006. Both failures involved the EDG failing to
SPECIAL INSPECTION SCOPE
    obtain an output voltage during surveillance testing because of a faulty K-1 relay
The NRC conducted this special inspection to better understand the circumstances
    operation. In accordance with NRC Management Directive 8.3, NRC Incident
surrounding two failures of the Unit 3 Train A emergency diesel generator (EDG) that
    Investigation Program, it was determined that this event met several deterministic
occurred on July 25 and September 22, 2006. Both failures involved the EDG failing to
    criteria and had sufficient risk significance to warrant a special inspection.
obtain an output voltage during surveillance testing because of a faulty K-1 relay
    The team used NRC Inspection Procedure 93812, Special Inspection Procedure, to
operation. In accordance with NRC Management Directive 8.3, NRC Incident
    conduct the inspection. The special inspection team reviewed procedures, corrective
Investigation Program, it was determined that this event met several deterministic
    action documents, and design and maintenance records for the equipment of concern.
criteria and had sufficient risk significance to warrant a special inspection.  
    The team interviewed key station personnel regarding the event, reviewed the root
The team used NRC Inspection Procedure 93812, Special Inspection Procedure, to
    cause analysis, and assessed the adequacy of corrective actions. A list of specific
conduct the inspection. The special inspection team reviewed procedures, corrective
    documents reviewed is provided in Attachment 1. The charter for the special inspection
action documents, and design and maintenance records for the equipment of concern.  
    effort is provided as Attachment 2.
The team interviewed key station personnel regarding the event, reviewed the root
2.0 EVENT DESCRIPTION
cause analysis, and assessed the adequacy of corrective actions. A list of specific
    Each unit at Palo Verde contains two safety-related 5500 Kw EDGs that provide standby
documents reviewed is provided in Attachment 1. The charter for the special inspection
    power for safe plant shutdown in the event the normal supply of power is lost. On
effort is provided as Attachment 2.  
    July 25, 2006, at 12:53 p.m., the Unit 3 Train A EDG failed to develop an output voltage
2.0
    during a routine surveillance test. When the EDGs are secured a field shorting K-1
EVENT DESCRIPTION
    relay actuates to electrically short the generator field causing the generator output
Each unit at Palo Verde contains two safety-related 5500 Kw EDGs that provide standby
    voltage to collapse. A relay latching mechanism maintains the field shorted until the
power for safe plant shutdown in the event the normal supply of power is lost. On
    EDG is started at which time the latch disengages allowing the relay to actuate and un-
July 25, 2006, at 12:53 p.m., the Unit 3 Train A EDG failed to develop an output voltage
    short the EDG field. With the field no longer shorted the voltage regulator establishes
during a routine surveillance test. When the EDGs are secured a field shorting K-1
    and controls the EDG output voltage. The licensee identified that a faulty set of auxiliary
relay actuates to electrically short the generator field causing the generator output
    contacts on a K-1 relay prevented the latch from disengaging that resulted in the
voltage to collapse. A relay latching mechanism maintains the field shorted until the
    generator field being shorted during the start of the EDG. The licensee determined the
EDG is started at which time the latch disengages allowing the relay to actuate and un-
    root cause of the auxiliary contact failure could be attributed to either plastic debris or
short the EDG field. With the field no longer shorted the voltage regulator establishes
    oxide film buildup preventing continuity across the contacts when closed. Following the
and controls the EDG output voltage. The licensee identified that a faulty set of auxiliary
    failure on July 25, 2006, the licensee replaced the failed K-1 relay with a new relay
contacts on a K-1 relay prevented the latch from disengaging that resulted in the
    obtained from the warehouse. During continuity checks of the new relay, the same
generator field being shorted during the start of the EDG. The licensee determined the
    auxiliary contacts were identified to operate unreliably. The last available relay from the
root cause of the auxiliary contact failure could be attributed to either plastic debris or
    warehouse was obtained and it also operated unreliably and it had a warped cover.
oxide film buildup preventing continuity across the contacts when closed. Following the
    Based on no other replacement K-1 relays being available, the licensee performed
failure on July 25, 2006, the licensee replaced the failed K-1 relay with a new relay
    corrective maintenance activities on the first relay obtained from the warehouse in an
obtained from the warehouse. During continuity checks of the new relay, the same
    attempt to resolve the problem. Following these corrective maintenance activities, the
auxiliary contacts were identified to operate unreliably. The last available relay from the
    relay was successfully tested several times and the Unit 3 Train A EDG was declared
warehouse was obtained and it also operated unreliably and it had a warped cover.  
    operable at 10:35 a.m. on July 26, 2006.
Based on no other replacement K-1 relays being available, the licensee performed
    On September 22, 2006, the Unit 3 Train A EDG failed to develop an output voltage
corrective maintenance activities on the first relay obtained from the warehouse in an
    following a postmaintenance surveillance test. The licensee identified that the same set
attempt to resolve the problem. Following these corrective maintenance activities, the
                                              4                                        Enclosure
relay was successfully tested several times and the Unit 3 Train A EDG was declared
operable at 10:35 a.m. on July 26, 2006.  
On September 22, 2006, the Unit 3 Train A EDG failed to develop an output voltage
following a postmaintenance surveillance test. The licensee identified that the same set


        of auxiliary contacts that previously exhibited erratic behavior during continuity checks
Enclosure
        had failed. The licensee identified that the K-1 relay actuating arm for the affected
5
        auxiliary contact module was not providing adequate compression of the auxiliary
of auxiliary contacts that previously exhibited erratic behavior during continuity checks  
        contacts. Corrective actions involved mechanical adjustments to the actuating arm to
had failed. The licensee identified that the K-1 relay actuating arm for the affected
        provide proper auxiliary contact compression. Additional corrective actions included
auxiliary contact module was not providing adequate compression of the auxiliary
        inspecting, cleaning, and making mechanical adjustments, as necessary, to all other
contacts. Corrective actions involved mechanical adjustments to the actuating arm to
        affected EDG K-1 relays.
provide proper auxiliary contact compression. Additional corrective actions included
3.0     PERFORMANCE DEFICIENCIES RESULTING IN EDG FAILURE
inspecting, cleaning, and making mechanical adjustments, as necessary, to all other
    a. Inspection Scope
affected EDG K-1 relays.
        On July 25 and September 22, 2006, the Unit 3 Train A EDG failed to produce output
3.0
        voltage during surveillance testing. The team reviewed the licensees corrective actions
PERFORMANCE DEFICIENCIES RESULTING IN EDG FAILURE  
        following failure of the Unit 3 Train A EDG on July 25, 2006, to assess their
    a.
        effectiveness with respect to preventing the subsequent failure that occurred on
Inspection Scope
        September 22, 2006.
On July 25 and September 22, 2006, the Unit 3 Train A EDG failed to produce output
    b. Observations and Findings
voltage during surveillance testing. The team reviewed the licensees corrective actions
        Introduction: The team identified two apparent violations of NRC requirements. The
following failure of the Unit 3 Train A EDG on July 25, 2006, to assess their
        team identified an apparent violation of 10 CFR Part 50, Appendix B, Criterion V,
effectiveness with respect to preventing the subsequent failure that occurred on
        Instructions, Procedures, and Drawings, for the failure to establish appropriate
September 22, 2006.
        instructions for performing corrective maintenance activities on an EDG K-1 relay. As a
      b. Observations and Findings
        result, following identification that a replacement EDG K-1 relay was unreliable, the
Introduction: The team identified two apparent violations of NRC requirements. The
        licensee performed ineffective corrective maintenance activities on this relay.
team identified an apparent violation of 10 CFR Part 50, Appendix B, Criterion V,
        Additionally, the team identified an apparent violation of 10 CFR Part 50, Appendix B,
Instructions, Procedures, and Drawings, for the failure to establish appropriate
        Criterion XVI, Corrective Action, involving the failure to identify the cause of a
instructions for performing corrective maintenance activities on an EDG K-1 relay. As a
        significant condition adverse to quality and take corrective actions to preclude repetition.
result, following identification that a replacement EDG K-1 relay was unreliable, the
        Specifically, following identification that a replacement EDG K-1 relay was unreliable,
licensee performed ineffective corrective maintenance activities on this relay.
        the licensee failed to identify the cause of this condition and implement adequate
Additionally, the team identified an apparent violation of 10 CFR Part 50, Appendix B,
        corrective actions. These performance deficiencies resulted in the Unit 3 Train A EDG
Criterion XVI, Corrective Action, involving the failure to identify the cause of a
        being inoperable between September 4 and 22, 2006, and a failure on September 22,
significant condition adverse to quality and take corrective actions to preclude repetition.  
        2006. These issues have potential low to moderate safety significance (White).
Specifically, following identification that a replacement EDG K-1 relay was unreliable,
        Description: On July 25, 2006, at 12:53 p.m., the Unit 3 Train A EDG failed to develop
the licensee failed to identify the cause of this condition and implement adequate
        an output voltage during a routine surveillance test. The licensee identified that a faulty
corrective actions. These performance deficiencies resulted in the Unit 3 Train A EDG
        set of auxiliary contacts on a K-1 relay resulted in the generator field being shorted
being inoperable between September 4 and 22, 2006, and a failure on September 22,
        during the start of the EDG. A new K-1 relay assembly was acquired from the
2006. These issues have potential low to moderate safety significance (White).
        warehouse and during functional testing the same auxiliary contacts exhibited erratic
Description:   On July 25, 2006, at 12:53 p.m., the Unit 3 Train A EDG failed to develop
        operation. The team noted that Work Order 2913004 stated, in part, that the K-1 relay
an output voltage during a routine surveillance test. The licensee identified that a faulty
        failed at first. Checked and re-attempted satisfactory. Performed several times
set of auxiliary contacts on a K-1 relay resulted in the generator field being shorted
        satisfactory. System engineering showed up and after discussing the problem they
during the start of the EDG. A new K-1 relay assembly was acquired from the
        wanted to verify repeatability. Checking contact resistance was found to be erratic.
warehouse and during functional testing the same auxiliary contacts exhibited erratic
        Unable to clean the contacts to get consistent readings. Determined not reliable and
operation. The team noted that Work Order 2913004 stated, in part, that the K-1 relay
        ordered last K-1 relay from the warehouse.
failed at first. Checked and re-attempted satisfactory. Performed several times
                                                    5                                      Enclosure
satisfactory. System engineering showed up and after discussing the problem they
wanted to verify repeatability. Checking contact resistance was found to be erratic.  
Unable to clean the contacts to get consistent readings. Determined not reliable and
ordered last K-1 relay from the warehouse.


Enclosure
6
Initial attempts, by electrical maintenance personnel, to clean the auxiliary contacts of
Initial attempts, by electrical maintenance personnel, to clean the auxiliary contacts of
the first relay obtained from the warehouse consisted of using a 9-volt battery connected
the first relay obtained from the warehouse consisted of using a 9-volt battery connected
across the contacts. By cycling the contacts, the licensee stated that an electrical arc
across the contacts. By cycling the contacts, the licensee stated that an electrical arc
could potentially clean any oxidation affecting the contacts ability to pass current. The
could potentially clean any oxidation affecting the contacts ability to pass current. The
licensee stated this practice was utilized because engineering would not allow intrusive
licensee stated this practice was utilized because engineering would not allow intrusive
actions, such as taking the relay apart, to clean the auxiliary contacts because of
actions, such as taking the relay apart, to clean the auxiliary contacts because of
concerns with maintaining critical dimensions. The team noted the licensee had no
concerns with maintaining critical dimensions. The team noted the licensee had no
maintenance instructions applicable to disassembly of the relay and no detailed vendor
maintenance instructions applicable to disassembly of the relay and no detailed vendor
specifications describing the critical attributes of the device. The licensee stated that
specifications describing the critical attributes of the device. The licensee stated that
obtaining this type of information was not possible because the equipment was
obtaining this type of information was not possible because the equipment was
obsolete, it was commercially dedicated by a vendor, and the vendor and manufacturer
obsolete, it was commercially dedicated by a vendor, and the vendor and manufacturer
of the component were no longer in business. Based on these reasons, the licensee
of the component were no longer in business. Based on these reasons, the licensee
stated that no maintenance activities were performed on the auxiliary contacts and that
stated that no maintenance activities were performed on the auxiliary contacts and that
when problems were encountered the K-1 relay was replaced as a whole unit.
when problems were encountered the K-1 relay was replaced as a whole unit.
After initial attempts to clean the K-1 relay auxiliary contacts using the 9-volt battery
After initial attempts to clean the K-1 relay auxiliary contacts using the 9-volt battery
failed, the licensee obtained the last replacement K-1 relay available onsite. Again, they
failed, the licensee obtained the last replacement K-1 relay available onsite. Again, they
found that the same set of auxiliary contacts on this relay exhibited erratic operation
found that the same set of auxiliary contacts on this relay exhibited erratic operation
when cycled. Additionally, the cover to this relay was found in a warped condition. At
when cycled. Additionally, the cover to this relay was found in a warped condition. At
this point the licensee decided to perform intrusive cleaning of the auxiliary contacts on
this point the licensee decided to perform intrusive cleaning of the auxiliary contacts on
the first device that they determined was unreliable following non-intrusive cleaning
the first device that they determined was unreliable following non-intrusive cleaning
efforts. The team noted that no detailed work instructions were established to perform
efforts. The team noted that no detailed work instructions were established to perform
this activity to improve its reliable operation. As previously stated, the licensee did not
this activity to improve its reliable operation. As previously stated, the licensee did not
possess any detailed vendor information specifically related to performing maintenance
possess any detailed vendor information specifically related to performing maintenance
activities on this device. After disassembling the auxiliary contacts, cleaning, and
activities on this device. After disassembling the auxiliary contacts, cleaning, and
reassembly, the relay was tested several times and the erratic behavior was not
reassembly, the relay was tested several times and the erratic behavior was not
observed during subsequent functional tests of the relay. A postmaintenance
observed during subsequent functional tests of the relay. A postmaintenance
surveillance test of the EDG was performed satisfactorily and the equipment was
surveillance test of the EDG was performed satisfactorily and the equipment was
declared operable at 10:35 a.m. on July 26, 2006.
declared operable at 10:35 a.m. on July 26, 2006.
On September 22, 2006, the Unit 3 Train A EDG failed to develop an output voltage
On September 22, 2006, the Unit 3 Train A EDG failed to develop an output voltage
following a postmaintenance surveillance test. The licensee identified that the same set
following a postmaintenance surveillance test. The licensee identified that the same set
of auxiliary contacts that exhibited erratic behavior on the K-1 relay had failed, resulting
of auxiliary contacts that exhibited erratic behavior on the K-1 relay had failed, resulting
in the generator field being shorted during the start of the EDG. The licensee identified
in the generator field being shorted during the start of the EDG. The licensee identified
that the auxiliary contacts were not held closed when the K-1 relay was energized
that the auxiliary contacts were not held closed when the K-1 relay was energized
because of an actuating arm that was not adequately depressing the auxiliary contact
because of an actuating arm that was not adequately depressing the auxiliary contact
switch. The team noted that this condition most likely existed during the initial testing on
switch. The team noted that this condition most likely existed during the initial testing on
July 25, 2006, and would have contributed to the erratic operation of this contact switch
July 25, 2006, and would have contributed to the erratic operation of this contact switch
assembly. Additionally, the team determined that this condition was not identified and
assembly. Additionally, the team determined that this condition was not identified and
corrected because instructions for performing corrective maintenance activities on the
corrected because instructions for performing corrective maintenance activities on the
unreliable K-1 relay were inadequate. The team noted that the last successful start of
unreliable K-1 relay were inadequate. The team noted that the last successful start of
the Unit 3 Train A EDG was on September 4, 2006.
the Unit 3 Train A EDG was on September 4, 2006.
As previously stated, the licensee initially believed the erratic behavior resulted from
As previously stated, the licensee initially believed the erratic behavior resulted from
oxidation of the contact surfaces which required an intrusive maintenance activity to
oxidation of the contact surfaces which required an intrusive maintenance activity to
clean the contact surfaces. The licensee stated that contact oxidation is a common
clean the contact surfaces. The licensee stated that contact oxidation is a common
occurrence requiring cleaning. The team reviewed all work orders associated with
occurrence requiring cleaning. The team reviewed all work orders associated with
replacement of the K-1 relay dating back to 1984 and noted that none of the work orders
replacement of the K-1 relay dating back to 1984 and noted that none of the work orders  
documented erratic auxiliary contact operation because of oxidation. During the review
documented erratic auxiliary contact operation because of oxidation. During the review
                                            6                                      Enclosure


Enclosure
7
of work orders, the team noted that Work Order 00067739, dated December 11, 1984,
of work orders, the team noted that Work Order 00067739, dated December 11, 1984,
discussed troubleshooting and repair activities for a faulty auxiliary contact on the K-1
discussed troubleshooting and repair activities for a faulty auxiliary contact on the K-1
relay affecting the Unit 1 Train B EDG. This work order contained instructions to inspect
relay affecting the Unit 1 Train B EDG. This work order contained instructions to inspect
the auxiliary contact arm on the K-1 relay and make adjustments as needed for proper
the auxiliary contact arm on the K-1 relay and make adjustments as needed for proper
contact operation per Technical Manual MO18-390. The maintenance technician
contact operation per Technical Manual MO18-390. The maintenance technician
performing the work documented, Adjusted the actuation arm for the auxiliary contacts
performing the work documented, Adjusted the actuation arm for the auxiliary contacts
on the left side of the K-1 contactor as required. Based on this work order, the team
on the left side of the K-1 contactor as required. Based on this work order, the team
determined that on this occasion the licensee had worked on the auxiliary contact
determined that on this occasion the licensee had worked on the auxiliary contact
operating mechanism to ensure reliable operation. A technician involved in this
operating mechanism to ensure reliable operation. A technician involved in this
maintenance activity did not recall the specifics of the work performed on the relay nor
maintenance activity did not recall the specifics of the work performed on the relay nor
the use of technical information contained in the technical manual. The team reviewed
the use of technical information contained in the technical manual. The team reviewed
the technical manual and found that no pertinent maintenance information for the K-1
the technical manual and found that no pertinent maintenance information for the K-1
relay existed.
relay existed.
Line 504: Line 558:
review of Technical Manual MO18-390, the team noted that detailed instructions were
review of Technical Manual MO18-390, the team noted that detailed instructions were
provided to maintenance personnel for ensuring that critical tolerances of other relays
provided to maintenance personnel for ensuring that critical tolerances of other relays
were maintained. The team noted that the voltage controlled overcurrent relay, reverse
were maintained. The team noted that the voltage controlled overcurrent relay, reverse
power relay, frequency relay, and negative-phase sequence time overcurrent relay, all
power relay, frequency relay, and negative-phase sequence time overcurrent relay, all
associated with the EDG voltage regulating system, contained specific installation,
associated with the EDG voltage regulating system, contained specific installation,
operation, and maintenance instructions. The team noted that these instructions
operation, and maintenance instructions. The team noted that these instructions
provided detailed information for activities involving contact cleaning, contact
provided detailed information for activities involving contact cleaning, contact
adjustments, operational checks, and mechanical adjustments for each particular type
adjustments, operational checks, and mechanical adjustments for each particular type
of relay to ensure reliable operation.
of relay to ensure reliable operation.
The licensee stated that the EDG K-1 relays had a history of operating reliably. Data
The licensee stated that the EDG K-1 relays had a history of operating reliably. Data
collected since 1990 indicated that the EDG K-1 relays had not failed because of
collected since 1990 indicated that the EDG K-1 relays had not failed because of  
auxiliary contact problems similar to the failures identified in July and September of
auxiliary contact problems similar to the failures identified in July and September of
2006. The team determined that this reliability data further demonstrated that, when the
2006. The team determined that this reliability data further demonstrated that, when the
erratic relay operation was identified, the licensee should have recognized that
erratic relay operation was identified, the licensee should have recognized that
corrective measures were needed that would require appropriate instructions to ensure
corrective measures were needed that would require appropriate instructions to ensure
future reliable operation.
future reliable operation.  
The team determined that the licensees problem analysis efforts were narrowly
The team determined that the licensees problem analysis efforts were narrowly
focused, which led them to conclude that the cause of the erratic relay operation was
focused, which led them to conclude that the cause of the erratic relay operation was
oxidized contacts. The erratic operation of the K-1 relay provided an indication that
oxidized contacts. The erratic operation of the K-1 relay provided an indication that
sufficient auxiliary contact continuity existed, at least intermittently, which indicated that
sufficient auxiliary contact continuity existed, at least intermittently, which indicated that
another failure mechanism was contributing to the unreliable K-1 relay operation. If the
another failure mechanism was contributing to the unreliable K-1 relay operation. If the
licensee performed an adequate cause analysis of this significant condition adverse to
licensee performed an adequate cause analysis of this significant condition adverse to
quality, then they may have identified the failure mechanism associated with the
quality, then they may have identified the failure mechanism associated with the
Line 530: Line 584:
defines a performance deficiency as an issue that is the result of a licensee not meeting
defines a performance deficiency as an issue that is the result of a licensee not meeting
a requirement or standard where the cause was reasonably within the licensees ability
a requirement or standard where the cause was reasonably within the licensees ability
to foresee and correct and that should have been prevented. The licensee determined
to foresee and correct and that should have been prevented. The licensee determined
that the K-1 relay that failed in September of 2006 was unreliable prior to placing it in
that the K-1 relay that failed in September of 2006 was unreliable prior to placing it in
service and would require corrective maintenance. The licensee stated that
service and would require corrective maintenance. The licensee stated that
                                          7                                        Enclosure


Enclosure
8
disassembly of the relay to implement intrusive corrective actions had never been
disassembly of the relay to implement intrusive corrective actions had never been
performed because of concerns with maintaining critical dimensions for reliable relay
performed because of concerns with maintaining critical dimensions for reliable relay
operation. The licensee did not obtain, nor did they develop, detailed information
operation. The licensee did not obtain, nor did they develop, detailed information
specific to performing corrective or preventive maintenance activities for this specific
specific to performing corrective or preventive maintenance activities for this specific
relay. On the basis of these considerations, the team concluded that the licensees
relay. On the basis of these considerations, the team concluded that the licensees
failure to establish and implement adequate maintenance instructions to resolve the
failure to establish and implement adequate maintenance instructions to resolve the
unreliable K-1 relay condition was a performance deficiency resulting in the Unit 3 Train
unreliable K-1 relay condition was a performance deficiency resulting in the Unit 3 Train
A EDG being inoperable between September 4 and 22, 2006. The team determined
A EDG being inoperable between September 4 and 22, 2006. The team determined
that the EDG was inoperable for an 18-day period on the basis that when the EDG was
that the EDG was inoperable for an 18-day period on the basis that when the EDG was
shut down on September 4, 2006, the K-1 relay auxiliary contacts would have been
shut down on September 4, 2006, the K-1 relay auxiliary contacts would have been
positioned and maintained in a state that would have resulted in a subsequent failure of
positioned and maintained in a state that would have resulted in a subsequent failure of
the relay to operate properly following an EDG start signal. Additionally, the team
the relay to operate properly following an EDG start signal. Additionally, the team
determined that the failure to perform an adequate cause assessment of the erratic
determined that the failure to perform an adequate cause assessment of the erratic
relay operation contributed to the inoperability of the Unit 3 Train A EDG.
relay operation contributed to the inoperability of the Unit 3 Train A EDG.
These findings are greater than minor because they are associated with the equipment
These findings are greater than minor because they are associated with the equipment
performance cornerstone objective to ensure the availability, reliability, and capability of
performance cornerstone objective to ensure the availability, reliability, and capability of
systems that respond to initiating events to prevent undesirable consequences. Using
systems that respond to initiating events to prevent undesirable consequences. Using
NRC Inspection Manual Chapter 0609, Significance Determination Process, Phase 1
NRC Inspection Manual Chapter 0609, Significance Determination Process, Phase 1
Worksheet, a Phase 2 analysis was required because the findings resulted in the loss of
Worksheet, a Phase 2 analysis was required because the findings resulted in the loss of
the safety function of the Unit 3 Train A EDG for greater than the Technical Specification
the safety function of the Unit 3 Train A EDG for greater than the Technical Specification
completion time. The Phase 2 and 3 evaluations preliminarily concluded that the
completion time. The Phase 2 and 3 evaluations preliminarily concluded that the
findings were of low to moderate safety significance. (See Attachment 3 for Phase 2
findings were of low to moderate safety significance. (See Attachment 3 for Phase 2
and Phase 3 details.) The cause of the Criterion XVI finding is related to the
and Phase 3 details.) The cause of the Criterion XVI finding is related to the
crosscutting element of problem identification and resolution in that the failure to fully
crosscutting element of problem identification and resolution in that the failure to fully
evaluate and implement adequate corrective maintenance actions for the Unit 3 Train A
evaluate and implement adequate corrective maintenance actions for the Unit 3 Train A
EDG contributed to the EDG being inoperable for 18 days. Additionally, the cause of
EDG contributed to the EDG being inoperable for 18 days. Additionally, the cause of
the Criterion V finding is related to the crosscutting element of human performance
the Criterion V finding is related to the crosscutting element of human performance
associated with resources in that the licensee failed to develop and implement
associated with resources in that the licensee failed to develop and implement
appropriate work instructions prior to performing corrective maintenance activities on the
appropriate work instructions prior to performing corrective maintenance activities on the
subject EDG K-1 relay, which contributed to the EDG being inoperable for 18 days.
subject EDG K-1 relay, which contributed to the EDG being inoperable for 18 days.
Enforcement: 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and
Enforcement: 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and
Drawings, states, in part, that activities affecting quality shall be prescribed by
Drawings, states, in part, that activities affecting quality shall be prescribed by
documented instructions, procedures, or drawings of a type appropriate to the
documented instructions, procedures, or drawings of a type appropriate to the
circumstances and shall be accomplished in accordance with these instructions,
circumstances and shall be accomplished in accordance with these instructions,
procedures, or drawings. Contrary to this, the licensee failed to develop appropriate
procedures, or drawings. Contrary to this, the licensee failed to develop appropriate
instructions or procedures for corrective maintenance activities on the Unit 3 Train A
instructions or procedures for corrective maintenance activities on the Unit 3 Train A  
EDG K-1 relay. This failure resulted in the Unit 3 Train A EDG being inoperable
EDG K-1 relay. This failure resulted in the Unit 3 Train A EDG being inoperable
between September 4 and 22, 2006. This item has been entered into the licensees
between September 4 and 22, 2006. This item has been entered into the licensees
corrective action program as Condition Report/Disposition Request (CRDR) 2926830.
corrective action program as Condition Report/Disposition Request (CRDR) 2926830.  
Pending determination of safety significance, this finding is identified as an apparent
Pending determination of safety significance, this finding is identified as an apparent
violation (AV) 05000530/2006012-01, Failure to Establish Appropriate Instructions.
violation (AV) 05000530/2006012-01, Failure to Establish Appropriate Instructions.
Line 581: Line 636:
nonconformances are promptly identified and corrected and for significant conditions
nonconformances are promptly identified and corrected and for significant conditions
adverse to quality, measures shall assure that the cause of the condition is determined
adverse to quality, measures shall assure that the cause of the condition is determined
                                            8                                        Enclosure


      and corrective action taken to preclude repetition. Contrary to this, the licensee failed to
Enclosure
      identify and correct the cause of the erratic EDG K-1 relay operation prior to installation
9
      of the relay on July 26, 2006. This failure resulted in the Unit 3 Train A EDG being
and corrective action taken to preclude repetition. Contrary to this, the licensee failed to
      inoperable between September 4 and 22, 2006. This item has been entered into the
identify and correct the cause of the erratic EDG K-1 relay operation prior to installation
      licensees corrective action program as CRDR 2926830. Pending determination of
of the relay on July 26, 2006. This failure resulted in the Unit 3 Train A EDG being
      safety significance, this finding is identified as AV 05000530/2006012-02, Failure to
inoperable between September 4 and 22, 2006. This item has been entered into the
      Identify and Correct a Condition Adverse to Quality.
licensees corrective action program as CRDR 2926830.   Pending determination of
4.0   Failure to Implement the Operability Determination Process
safety significance, this finding is identified as AV 05000530/2006012-02, Failure to
    a. Inspection Scope
Identify and Correct a Condition Adverse to Quality.
      The team assessed the engineering and operations departments implementation of the
4.0
      operability determination (OD) process after identifying potential adverse conditions
Failure to Implement the Operability Determination Process
      involving reliable K-1 relay operation of the EDGs. This assessment was performed
    a.
      through interviews and a review of precisely logs, ODs, and related documents. In
Inspection Scope
      addition, the team conducted an independent assessment of system operability.
The team assessed the engineering and operations departments implementation of the
    b. Observations and Findings
operability determination (OD) process after identifying potential adverse conditions
      Introduction: The team identified two examples of a Green noncited violation of 10 CFR
involving reliable K-1 relay operation of the EDGs. This assessment was performed
      Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, involving the
through interviews and a review of precisely logs, ODs, and related documents. In
      failure to follow the OD procedure.
addition, the team conducted an independent assessment of system operability.
      Description:
    b.
      Example One
Observations and Findings
      Administrative Procedure 40DP-9OP26, Operability Determination and Functional
Introduction: The team identified two examples of a Green noncited violation of 10 CFR
      Assessment, Revision 17, Section 1.3, stated, in part, that the OD process is entered
Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, involving the
      when the ability of a Technical Specification system or component to perform its
failure to follow the OD procedure.
      specified safety function is called into question by the discovery of a degraded condition.
Description:
      As previously discussed, on July 25, 2006, the Unit 3 Train A EDG failed to produce
Example One
      output voltage during surveillance testing. The licensee identified that a faulty set of
Administrative Procedure 40DP-9OP26, Operability Determination and Functional
      auxiliary contacts on a K-1 relay resulted in the generator field being shorted during the
Assessment, Revision 17, Section 1.3, stated, in part, that the OD process is entered
      start of the EDG. The team noted that an engineering team was assigned to perform a
when the ability of a Technical Specification system or component to perform its
      root cause analysis for the K-1 relay auxiliary contact failure. This root cause evaluation
specified safety function is called into question by the discovery of a degraded condition.  
      was documented in CRDR 2913003. The root cause team determined the most
As previously discussed, on July 25, 2006, the Unit 3 Train A EDG failed to produce
      probable cause was due to contamination on the contact surface either from oxidation or
output voltage during surveillance testing. The licensee identified that a faulty set of
      from pieces of plastic filings found in the contact area. The plastic pieces were believed
auxiliary contacts on a K-1 relay resulted in the generator field being shorted during the
      to have resulted from a modification of the contact block actuator implemented by
start of the EDG. The team noted that an engineering team was assigned to perform a
      Design Change Package DCP X-PE-007. This design change added auxiliary contacts,
root cause analysis for the K-1 relay auxiliary contact failure. This root cause evaluation
      latching mechanisms, and spacers to all EDG K-1 relays at the facility to address
was documented in CRDR 2913003. The root cause team determined the most
      seismic concerns identified during testing of the K-1 relay during the initial plant
probable cause was due to contamination on the contact surface either from oxidation or
      construction phase.
from pieces of plastic filings found in the contact area. The plastic pieces were believed
                                                    9                                    Enclosure
to have resulted from a modification of the contact block actuator implemented by
Design Change Package DCP X-PE-007. This design change added auxiliary contacts,
latching mechanisms, and spacers to all EDG K-1 relays at the facility to address
seismic concerns identified during testing of the K-1 relay during the initial plant
construction phase.


Enclosure
10
The NRC inspection team noted that the licensees root cause assessment team
The NRC inspection team noted that the licensees root cause assessment team
concluded that only the Unit 3 Train A EDG was potentially degraded by this condition.
concluded that only the Unit 3 Train A EDG was potentially degraded by this condition.  
The evaluation stated, in part, that:
The evaluation stated, in part, that:
          The same model/type field shorting contactor is used on all six Class 1E
The same model/type field shorting contactor is used on all six Class 1E  
          EDGs. In addition, two spare K-1 relays removed from the warehouse
EDGs. In addition, two spare K-1 relays removed from the warehouse  
          exhibited the same symptoms with varying resistance across the auxiliary
exhibited the same symptoms with varying resistance across the auxiliary
          contacts. An inspection/test of the auxiliary contacts for all other EDGs
contacts. An inspection/test of the auxiliary contacts for all other EDGs  
          was performed, with no other auxiliary contact resistance problems
was performed, with no other auxiliary contact resistance problems  
          identified.
identified.
The NRC team was informed that the licensees inspection consisted of a functional
The NRC team was informed that the licensees inspection consisted of a functional
check of the relay and did not involve visually inspecting the auxiliary contact internals to
check of the relay and did not involve visually inspecting the auxiliary contact internals to
identify the presence of plastic filings. Based on this, the team determined that the
identify the presence of plastic filings. Based on this, the team determined that the
inspection and contact resistance testing alone failed to demonstrate why only the Unit 3
inspection and contact resistance testing alone failed to demonstrate why only the Unit 3
Train A EDG K-1 relay was affected since the relay had operated properly since being
Train A EDG K-1 relay was affected since the relay had operated properly since being
placed in service on August 1, 2001. Therefore, the licensee inadequately assessed the
placed in service on August 1, 2001. Therefore, the licensee inadequately assessed the
extent of condition of the unreliable relay operation relative to the other EDGs at the
extent of condition of the unreliable relay operation relative to the other EDGs at the
facility.
facility.
The NRC team noted that the root cause assessment identified a degraded condition,
The NRC team noted that the root cause assessment identified a degraded condition,
plastic filings in the contact module that likely affected all the facility EDGs. However,
plastic filings in the contact module that likely affected all the facility EDGs. However,
the licensee failed to enter the OD process after identifying this potentially degraded
the licensee failed to enter the OD process after identifying this potentially degraded
condition.
condition.  
Example Two
Example Two
As previously discussed, on September 22, 2006, at 1:18 a.m., the Unit 3 Train A EDG
As previously discussed, on September 22, 2006, at 1:18 a.m., the Unit 3 Train A EDG
failed to produce output voltage during surveillance testing. The licensee identified that
failed to produce output voltage during surveillance testing. The licensee identified that
a faulty set of auxiliary contacts on a K-1 relay resulted in the generator field being
a faulty set of auxiliary contacts on a K-1 relay resulted in the generator field being
shorted during the start of the EDG. The licensee identified that the K-1 relay actuating
shorted during the start of the EDG. The licensee identified that the K-1 relay actuating
arm for the affected auxiliary contact module was not providing adequate compression
arm for the affected auxiliary contact module was not providing adequate compression
of the auxiliary contacts. The licensee noted that part of the actuating arm consisted of
of the auxiliary contacts. The licensee noted that part of the actuating arm consisted of
a metal tab that was bent in a configuration that would result in less contact
a metal tab that was bent in a configuration that would result in less contact
compression. The licensee decided to straighten the metal tab, thereby, providing
compression. The licensee decided to straighten the metal tab, thereby, providing
additional contact compression. Five functional tests of the relay were performed and
additional contact compression.   Five functional tests of the relay were performed and
the EDG was declared operable following a postmaintenance surveillance test on
the EDG was declared operable following a postmaintenance surveillance test on
September 22, 2006, at 5:48 p.m.
September 22, 2006, at 5:48 p.m.
The team noted that CRDR 2926830 documented the licensees evaluation of this
The team noted that CRDR 2926830 documented the licensees evaluation of this
failure. The CRDR stated, in part:
failure. The CRDR stated, in part:  
          The auxiliary contacts that had failed were added to the K-1 relay by
The auxiliary contacts that had failed were added to the K-1 relay by  
          Design Change Package DCP X-PE-007 during plant startup in response
Design Change Package DCP X-PE-007 during plant startup in response  
          to electrical seismic latch failures. Engineering believes that the actuator
to electrical seismic latch failures. Engineering believes that the actuator  
          arm mounted metal tab was initially bent because originally there were no
arm mounted metal tab was initially bent because originally there were no
          auxiliary contacts on that side of the K-1 relay. Following completion of
auxiliary contacts on that side of the K-1 relay. Following completion of  
          the design change, the auxiliary contacts appeared to be working properly
the design change, the auxiliary contacts appeared to be working properly  
          so the actuator arms were left bent down. Inspection of some of the K-1
so the actuator arms were left bent down. Inspection of some of the K-1  
                                            10                                    Enclosure


          relays removed from EDGs in the past found at least one that had the
Enclosure
          actuator arm straight; however, in most cases, the actuator arm metal tab
11
          for the auxiliary contacts were found bent down. This is a repeat failure
relays removed from EDGs in the past found at least one that had the  
          of Unit 3 Train A EDG to produce output voltage. Recent verification of
actuator arm straight; however, in most cases, the actuator arm metal tab  
          acceptable K-1 relay auxiliary contact continuity on the other five EDGs
for the auxiliary contacts were found bent down. This is a repeat failure  
          provides the basis that this condition is not present on those relays.
of Unit 3 Train A EDG to produce output voltage. Recent verification of
acceptable K-1 relay auxiliary contact continuity on the other five EDGs  
provides the basis that this condition is not present on those relays.
The NRC team was informed that the licensees inspection consisted of a functional
The NRC team was informed that the licensees inspection consisted of a functional
check of the relay and did not involve visually inspecting the auxiliary contact actuating
check of the relay and did not involve visually inspecting the auxiliary contact actuating
arms to identify a bent configuration. Based on this, the team determined that the
arms to identify a bent configuration. Based on this, the team determined that the
inspection and contact resistance testing alone failed to demonstrate why only the Unit 3
inspection and contact resistance testing alone failed to demonstrate why only the Unit 3
Train A EDG K-1 relay was affected, since the relay had operated properly since being
Train A EDG K-1 relay was affected, since the relay had operated properly since being
placed in service on July 26, 2006. Therefore, the licensee inadequately assessed the
placed in service on July 26, 2006. Therefore, the licensee inadequately assessed the
extent of condition of the unreliable relay operation relative to the other EDGs at the
extent of condition of the unreliable relay operation relative to the other EDGs at the
facility.
facility.
The team noted that the engineering assessment identified a degraded condition, a bent
The team noted that the engineering assessment identified a degraded condition, a bent
K-1 relay actuating arm resulting in unreliable operation, that likely affected all the facility
K-1 relay actuating arm resulting in unreliable operation, that likely affected all the facility
EDGs. The licensee failed to enter the OD process after identifying this potentially
EDGs. The licensee failed to enter the OD process after identifying this potentially
degraded condition. Following discussions with the licensee, an OD was performed on
degraded condition. Following discussions with the licensee, an OD was performed on
September 27, 2006.
September 27, 2006.
In both of these examples the team determined that engineering failed to recognize that
In both of these examples the team determined that engineering failed to recognize that
the identified degraded conditions had the potential to adversely affect the other EDGs.
the identified degraded conditions had the potential to adversely affect the other EDGs.  
On both occasions engineering relied on continuity checks of the auxiliary contacts to
On both occasions engineering relied on continuity checks of the auxiliary contacts to
inappropriately conclude that the other EDGs were not affected. The team noted that
inappropriately conclude that the other EDGs were not affected. The team noted that
the testing results were pertinent to an OD assessment; however, the information did
the testing results were pertinent to an OD assessment; however, the information did
not provide adequate justification for not implementing the OD process ensuring
not provide adequate justification for not implementing the OD process ensuring
reasonable assurance existed supporting operability of the other EDGs.
reasonable assurance existed supporting operability of the other EDGs.
Analysis: The performance deficiency was associated with engineering personnel not
Analysis: The performance deficiency was associated with engineering personnel not
adequately implementing the provisions of the OD procedure following the identification
adequately implementing the provisions of the OD procedure following the identification
of a degraded condition. This finding was more than minor because the failure to follow
of a degraded condition. This finding was more than minor because the failure to follow
the operability determination process, if left uncorrected, would become a more
the operability determination process, if left uncorrected, would become a more
significant safety concern in that degraded or nonconforming conditions would not be
significant safety concern in that degraded or nonconforming conditions would not be
properly evaluated. Using the Phase 1 worksheet in Manual Chapter 0609,
properly evaluated. Using the Phase 1 worksheet in Manual Chapter 0609,
Significance Determination Process, the finding was determined to have very low
Significance Determination Process, the finding was determined to have very low
safety significance because, although these conditions resulted in unreliable K-1 relay
safety significance because, although these conditions resulted in unreliable K-1 relay
operation, no actual loss of safety function occurred (with respect to the other 5 EDGs)
operation, no actual loss of safety function occurred (with respect to the other 5 EDGs)
prior to corrective actions being implemented, and the finding did not represent a
prior to corrective actions being implemented, and the finding did not represent a
potential risk significant condition due to a seismic, flooding, or severe weather event.
potential risk significant condition due to a seismic, flooding, or severe weather event.  
This finding involved problem identification and resolution crosscutting aspects
This finding involved problem identification and resolution crosscutting aspects
associated with engineering personnel failing to properly evaluate and perform
associated with engineering personnel failing to properly evaluate and perform
Line 709: Line 770:
states, in part, that activities affecting quality shall be prescribed by documented
states, in part, that activities affecting quality shall be prescribed by documented
instructions, procedures, or drawings of a type appropriate to the circumstances and
instructions, procedures, or drawings of a type appropriate to the circumstances and
shall be accomplished in accordance with these instructions, procedures, or drawings.
shall be accomplished in accordance with these instructions, procedures, or drawings.  
                                            11                                      Enclosure


      Administrative Procedure 40DP-9OP26, Operability Determination and Functional
Enclosure
      Assessment, Revision 17, Section 1.3, stated, in part, that the OD process is entered
12
      when the ability of a Technical Specification system or component to perform its
Administrative Procedure 40DP-9OP26, Operability Determination and Functional
      specified safety function is called into question by the discovery of a degraded condition.
Assessment, Revision 17, Section 1.3, stated, in part, that the OD process is entered
      Contrary to the above, on two occasions the licensee failed to enter the OD process
when the ability of a Technical Specification system or component to perform its
      when the ability of a Technical Specification system or component safety function was
specified safety function is called into question by the discovery of a degraded condition.  
      called into question. On July 25, 2006, following failure of the Unit 3 Train A EDG, an
Contrary to the above, on two occasions the licensee failed to enter the OD process
      OD was not performed after identifying the failure was likely because of plastic filings
when the ability of a Technical Specification system or component safety function was
      affecting proper auxiliary contact operation of a K-1 relay. The filings were believed to
called into question. On July 25, 2006, following failure of the Unit 3 Train A EDG, an
      be from a modification that was performed on all EDG K-1 relays during initial plant
OD was not performed after identifying the failure was likely because of plastic filings
      startup. On September 22, 2006, following another failure of the Unit 3 Train A EDG, an
affecting proper auxiliary contact operation of a K-1 relay. The filings were believed to
      OD was not performed after identifying the failure was the result of the K-1 relay
be from a modification that was performed on all EDG K-1 relays during initial plant
      actuating arm not providing adequate compression of the auxiliary contacts. The
startup. On September 22, 2006, following another failure of the Unit 3 Train A EDG, an
      licensee determined this condition most likely resulted from a modification performed on
OD was not performed after identifying the failure was the result of the K-1 relay
      all EDG K-1 relays during initial plant startup. Because the finding is of very low safety
actuating arm not providing adequate compression of the auxiliary contacts. The
      significance and has been entered into the licensees corrective action program as
licensee determined this condition most likely resulted from a modification performed on
      CRDRs 2928389 and 2940558, this violation is being treated as a noncited violation
all EDG K-1 relays during initial plant startup. Because the finding is of very low safety
      consistent with Section VI.A of the Enforcement Policy: Noncited Violation
significance and has been entered into the licensees corrective action program as
      05000528;05000529;05000530/2006012-03, Failure to Implement the Operability
CRDRs 2928389 and 2940558, this violation is being treated as a noncited violation
      Determination Process.
consistent with Section VI.A of the Enforcement Policy: Noncited Violation
5.0   CORRECTIVE ACTIONS FOLLOWING EDG FAILURES
05000528;05000529;05000530/2006012-03, Failure to Implement the Operability
    a. Inspection Scope
Determination Process.
      The team assessed the licensees immediate and long-term planned corrective actions
5.0
      associated with the Unit 3 Train A EDG failures that occurred on July 25 and
CORRECTIVE ACTIONS FOLLOWING EDG FAILURES  
      September 22, 2006. This assessment was performed through interviews, review of
    a.
      operator logs, corrective action documents, work orders, and related documents.
Inspection Scope
    b. Observations and Findings
The team assessed the licensees immediate and long-term planned corrective actions
      Following the Unit 3 Train A EDG failure on July 25, 2006, the licensee identified that
associated with the Unit 3 Train A EDG failures that occurred on July 25 and
      plastic filings inside the auxiliary contact module may have resulted in the failure. The
September 22, 2006. This assessment was performed through interviews, review of
      licensee concluded this material most likely was introduced during a design change
operator logs, corrective action documents, work orders, and related documents.
      performed on all the K-1 relays and subsequently established a schedule to inspect all
    b.
      the EDG auxiliary contact modules. The team noted these inspections were scheduled
Observations and Findings
      to be performed November 2006 through March 2007. NRC Inspection Manual,
Following the Unit 3 Train A EDG failure on July 25, 2006, the licensee identified that  
      Part 9900, Technical Guidance, Operability Determination and Functionality
plastic filings inside the auxiliary contact module may have resulted in the failure. The
      Assessments for Resolution of Degraded or Nonconforming Conditions Adverse to
licensee concluded this material most likely was introduced during a design change
      Quality or Safety, Section 4.2, states, When a potential degraded or nonconforming
performed on all the K-1 relays and subsequently established a schedule to inspect all
      condition is identified, the licensee should take action without delay to confirm if a
the EDG auxiliary contact modules. The team noted these inspections were scheduled
      system, structure, or component is degraded or nonconforming. The team concluded
to be performed November 2006 through March 2007. NRC Inspection Manual,
      that waiting approximately 8 months to identify whether other EDGs were affected by
Part 9900, Technical Guidance, Operability Determination and Functionality
      this potential adverse condition was not commensurate with the safety consequences of
Assessments for Resolution of Degraded or Nonconforming Conditions Adverse to
      having a degraded EDG.
Quality or Safety, Section 4.2, states, When a potential degraded or nonconforming
                                                  12                                      Enclosure
condition is identified, the licensee should take action without delay to confirm if a
system, structure, or component is degraded or nonconforming. The team concluded
that waiting approximately 8 months to identify whether other EDGs were affected by
this potential adverse condition was not commensurate with the safety consequences of
having a degraded EDG.


    Following the September 22, 2006, Unit 3 Train A EDG failure, the licensee identified
Enclosure
    that a bent K-1 relay actuating arm resulted in unreliable auxiliary contact operation.
13
    Immediate corrective actions involved straightening the arm to provide additional contact
Following the September 22, 2006, Unit 3 Train A EDG failure, the licensee identified
    compression for the Unit 3 Train A EDG. The team noted that the licensee implemented
that a bent K-1 relay actuating arm resulted in unreliable auxiliary contact operation.  
    timely corrective actions to inspect and implement mechanical adjustments, as needed,
Immediate corrective actions involved straightening the arm to provide additional contact
    to all the EDG relays to ensure adequate contact compression during operation. These
compression for the Unit 3 Train A EDG. The team noted that the licensee implemented  
    actions were implemented September 27-30, 2006, and incorporated the inspections
timely corrective actions to inspect and implement mechanical adjustments, as needed,
    resulting from the July failure that were originally not scheduled to be completed until
to all the EDG relays to ensure adequate contact compression during operation. These
    March 2007. The licensee straightened bent K-1 relay contactor arms for the Unit 2
actions were implemented September 27-30, 2006, and incorporated the inspections
    Trains A and B EDGs, and the Unit 1 Train B EDG. The team determined that these
resulting from the July failure that were originally not scheduled to be completed until
    actions were timely and they included the inspections identified following the July failure.
March 2007. The licensee straightened bent K-1 relay contactor arms for the Unit 2
    Therefore, there were no regulatory findings associated with timeliness of these
Trains A and B EDGs, and the Unit 1 Train B EDG. The team determined that these
    corrective actions.
actions were timely and they included the inspections identified following the July failure.  
    The team noted that long-term planned corrective actions consisted of replacing all of
Therefore, there were no regulatory findings associated with timeliness of these
    the EDG automatic voltage regulators, including replacement of the K-1 relays, with a
corrective actions.
    different design. The licensee stated that they plan to have these replacement activities
The team noted that long-term planned corrective actions consisted of replacing all of
    accomplished during the next refueling outage for each unit.
the EDG automatic voltage regulators, including replacement of the K-1 relays, with a
6.0 Generic Implications
different design. The licensee stated that they plan to have these replacement activities
    The team reviewed various NRC generic communications and operating experience
accomplished during the next refueling outage for each unit.
    from other licensees relevant to the EDG relay failures identified at the Palo Verde
6.0
    Nuclear Generating Station. No relevant similar relay failures were identified. Both the
Generic Implications
    NRC and the licensee concluded that the relay problems pertaining to ensuring
The team reviewed various NRC generic communications and operating experience
    adequate contact compression is provided by the actuator arm was potentially of
from other licensees relevant to the EDG relay failures identified at the Palo Verde
    generic concern. On October 21, 2006, the licensee submitted voluntary Licensee
Nuclear Generating Station. No relevant similar relay failures were identified. Both the
    Event Report (LER) 50-530/2006-006-00 to report this concern.
NRC and the licensee concluded that the relay problems pertaining to ensuring
adequate contact compression is provided by the actuator arm was potentially of
generic concern. On October 21, 2006, the licensee submitted voluntary Licensee
Event Report (LER) 50-530/2006-006-00 to report this concern.
4OA3 Event Follow-up (71153)
4OA3 Event Follow-up (71153)
    .1       (Closed) LER 05000530/2006-006-00, Voluntary LER for Failure of Emergency
.1
              Diesel Generator to Attain Required Voltage Due to Relay Contactor
(Closed) LER 05000530/2006-006-00, Voluntary LER for Failure of Emergency
              On September 22, 2006, at 1:18 a.m., the Unit 3 Train A EDG failed to produce
Diesel Generator to Attain Required Voltage Due to Relay Contactor
              output voltage during surveillance testing. The licensee identified that a faulty
On September 22, 2006, at 1:18 a.m., the Unit 3 Train A EDG failed to produce
              set of auxiliary contacts on a K-1 relay resulted in the generator field being
output voltage during surveillance testing. The licensee identified that a faulty
              shorted during the start of the EDG. The licensee identified that the K-1 relay
set of auxiliary contacts on a K-1 relay resulted in the generator field being
              actuating arm for the affected auxiliary contact module was not providing
shorted during the start of the EDG. The licensee identified that the K-1 relay
              adequate compression of the auxiliary contacts. The licensee noted that part of
actuating arm for the affected auxiliary contact module was not providing
              the actuating arm consisted of a metal tab that was bent in a configuration that
adequate compression of the auxiliary contacts. The licensee noted that part of
              would result in less contact compression. Immediate corrective actions involved
the actuating arm consisted of a metal tab that was bent in a configuration that
              mechanical adjustments made to the actuating arm providing additional contact
would result in less contact compression. Immediate corrective actions involved
              compression for the Unit 3 Train A EDG. Additionally, the licensee implemented
mechanical adjustments made to the actuating arm providing additional contact
              corrective actions to inspect and make adjustments as needed to all the EDG
compression for the Unit 3 Train A EDG. Additionally, the licensee implemented
              relays. As discussed in section 3.0 of this report, the Unit 3 Train A EDG failure
corrective actions to inspect and make adjustments as needed to all the EDG
              on September 22, 2006, resulted from and inadequate cause assessment and
relays. As discussed in section 3.0 of this report, the Unit 3 Train A EDG failure
              the failure to establish appropriate corrective maintenance instructions which
on September 22, 2006, resulted from and inadequate cause assessment and
                                                13                                      Enclosure
the failure to establish appropriate corrective maintenance instructions which


            resulted in a violation of Technical specification 3.8.1.B since the inoperable
Enclosure
            EDG exceeded the completion time of 72 hours. The team determined that the
14
            licensee failed to identify that 10 CFR 50.73(a)(2)(B) requires the licensee to
resulted in a violation of Technical specification 3.8.1.B since the inoperable
            report any operation or condition which was prohibited by the plants Technical
EDG exceeded the completion time of 72 hours. The team determined that the
            Specifications. Based on the licensee having performed a voluntary LER
licensee failed to identify that 10 CFR 50.73(a)(2)(B) requires the licensee to
            addressing both Unit 3 Train A EDG failures that occurred on July 25, 2006, and
report any operation or condition which was prohibited by the plants Technical
            September 22, 2006, the failure to make a required report in accordance with
Specifications. Based on the licensee having performed a voluntary LER
            10 CFR 50.73 constitutes a violation of minor significance that is not subject to
addressing both Unit 3 Train A EDG failures that occurred on July 25, 2006, and
            enforcement action in accordance with Section IV of the NRCs Enforcement.
September 22, 2006, the failure to make a required report in accordance with
            This LER is closed.
10 CFR 50.73 constitutes a violation of minor significance that is not subject to
enforcement action in accordance with Section IV of the NRCs Enforcement.  
This LER is closed.
4OA6 Meetings, Including Exit
4OA6 Meetings, Including Exit
    On November 30, 2006, the inspection results were discussed with Mr. David Mauldin,
On November 30, 2006, the inspection results were discussed with Mr. David Mauldin,  
    Vice President, Engineering, and other members of the plant staff. The inspectors
Vice President, Engineering, and other members of the plant staff. The inspectors
    asked the licensee whether any of the material examined during the inspection should
asked the licensee whether any of the material examined during the inspection should
    be considered proprietary. No proprietary information was identified.
be considered proprietary. No proprietary information was identified.
ATTACHMENT 1: SUPPLEMENTAL INFORMATION
ATTACHMENT 1: SUPPLEMENTAL INFORMATION
ATTACHMENT 2: SPECIAL INSPECTION CHARTER
ATTACHMENT 2: SPECIAL INSPECTION CHARTER
ATTACHMENT 3: SIGNIFICANCE DETERMINATION EVALUATION
ATTACHMENT 3: SIGNIFICANCE DETERMINATION EVALUATION
                                              14                                    Enclosure


                                SUPPLEMENTAL INFORMATION
Attachment 1
                                  KEY POINTS OF CONTACT
A1-1
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
Licensee Personnel
S. Bauer, Department Leader, Regulatory Affairs
S. Bauer, Department Leader, Regulatory Affairs
Line 853: Line 923:
T. Vegel, Deputy Director, Division of Reactor Projects
T. Vegel, Deputy Director, Division of Reactor Projects
G. Warnick, Senior Resident Inspector, Palo Verde Nuclear Generating Station
G. Warnick, Senior Resident Inspector, Palo Verde Nuclear Generating Station
                                              A1-1                          Attachment 1


                  LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Attachment 1
  Opened
A1-2
  05000530/2006012-01           AV     Failure to Establish Appropriate Instructions
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
  05000530/2006012-02           AV     Failure to Identify and Correct aCondition Adverse
Opened
                                        to Quality
05000530/2006012-01
  05000528;05000529;             NCV     Failure to Implement the Operability Determination
AV
  05000530/2006012-03                    Process
Failure to Establish Appropriate Instructions
  Closed
05000530/2006012-02
  05000528; 05000529;           NCV     Failure to Implement the Operability Determination
AV
  05000530/2006012-03                    Process
Failure to Identify and Correct aCondition Adverse
  05000530/2006-006-00           LER     Voluntary LER for Failure of Emergency Diesel
to Quality
                                        Generator to Attain Required Voltage Due to Relay
05000528;05000529;
                                        Contactor
05000530/2006012-03
                          LIST OF DOCUMENTS REVIEWED
NCV
Failure to Implement the Operability Determination
Process
Closed
05000528; 05000529;
05000530/2006012-03
NCV
Failure to Implement the Operability Determination
Process
05000530/2006-006-00
LER
Voluntary LER for Failure of Emergency Diesel
Generator to Attain Required Voltage Due to Relay
Contactor
LIST OF DOCUMENTS REVIEWED
Drawings
Drawings
13-M018-00159
13-M018-00159
Line 890: Line 973:
Purchasing Order 10470-13-MM-018 Documentation
Purchasing Order 10470-13-MM-018 Documentation
Purchasing Order 33501265 Documentation
Purchasing Order 33501265 Documentation
                                            A1-2                                  Attachment 1


Attachment 1
A1-3
Purchasing Order 44930161 Documentation
Purchasing Order 44930161 Documentation
Purchasing Order 60113782 Documentation
Purchasing Order 60113782 Documentation
Line 917: Line 1,001:
Work Orders
Work Orders
00003495, 67521, 67550, 119715, 360726, 360944, 412917, 1040142, 1071966, 1329487,
00003495, 67521, 67550, 119715, 360726, 360944, 412917, 1040142, 1071966, 1329487,
2361781, 2410350, 2750447, 2794362, 2902642, 2913004, 2913286, 2913287, 2913295,
2361781, 2410350, 2750447, 2794362, 2902642, 2913004, 2913286, 2913287, 2913295,
2913306, 2913753, 2919666, 2919670, 2919671, 2919672, 2919673, 2919747, and 2926829
2913306, 2913753, 2919666, 2919670, 2919671, 2919672, 2919673, 2919747, and 2926829  
                                              A1-3                        Attachment 1


                                  SPECIAL INSPECTION CHARTER
Attachment 2
                                        September 29, 2006
A2-1
SPECIAL INSPECTION CHARTER
September 29, 2006
MEMORANDUM TO: Michael Hay, Senior Project Engineer,
MEMORANDUM TO: Michael Hay, Senior Project Engineer,
                        Project Branch D, Division of Reactor Projects (DRP)
Project Branch D, Division of Reactor Projects (DRP)
                        Dr. Scott Rutenkroger, Reactor Inspector,
Dr. Scott Rutenkroger, Reactor Inspector,
                        Engineering Branch 1, Division of Reactor Safety
Engineering Branch 1, Division of Reactor Safety
                        Michael Bloodgood, Reactor Engineer, Nuclear Safety Professional
Michael Bloodgood, Reactor Engineer, Nuclear Safety Professional
                        Development Program, Project Branch D, DRP
Development Program, Project Branch D, DRP  
FROM:                   Arthur T. Howell III, Director, DRP     /RA/ AVegel for
FROM:
SUBJECT:               SPECIAL INSPECTION CHARTER TO EVALUATE THE PALO VERDE
Arthur T. Howell III, Director, DRP       /RA/ AVegel for
                        NUCLEAR GENERATING STATION UNIT 3 EMERGENCY DIESEL
SUBJECT:  
                        GENERATOR FAILURE
SPECIAL INSPECTION CHARTER TO EVALUATE THE PALO VERDE
NUCLEAR GENERATING STATION UNIT 3 EMERGENCY DIESEL
GENERATOR FAILURE
A Special Inspection Team is being chartered in response to the Palo Verde Nuclear
A Special Inspection Team is being chartered in response to the Palo Verde Nuclear
Generating Station Unit 3 Emergency Diesel Generator (EDG) failure. The diesel failed to
Generating Station Unit 3 Emergency Diesel Generator (EDG) failure. The diesel failed to
develop an output voltage when started for a surveillance test. The licensee determined that a
develop an output voltage when started for a surveillance test. The licensee determined that a
modification to the field flashing relay caused the failure. You are hereby designated as the
modification to the field flashing relay caused the failure. You are hereby designated as the
Special Inspection Team members. Mr. Hay is designated as the team leader. The assigned
Special Inspection Team members. Mr. Hay is designated as the team leader. The assigned
SRA to support the team is Mike Runyan.
SRA to support the team is Mike Runyan.
A.     Basis
A.
      On July 25, 2006, Unit 3, Train A, EDG failed to develop output voltage during a
Basis
      surveillance test. The licensee's root cause determined plastic debris potentially
On July 25, 2006, Unit 3, Train A, EDG failed to develop output voltage during a
      prevented auxiliary contacts from properly functioning resulting in shorting out of the
surveillance test. The licensee's root cause determined plastic debris potentially
      generator field during startup preventing a proper field flash. Two replacement relays
prevented auxiliary contacts from properly functioning resulting in shorting out of the
      obtained from the licensee warehouse exhibited the same unreliable condition. After
generator field during startup preventing a proper field flash. Two replacement relays
      performing corrective maintenance activities on one of the relays, the diesel was
obtained from the licensee warehouse exhibited the same unreliable condition. After
      subsequently tested and declared operable on July 26, 2006.
performing corrective maintenance activities on one of the relays, the diesel was
      On September 22, 2006, Unit 3, Train A, EDG failed to develop output voltage during a
subsequently tested and declared operable on July 26, 2006.
      surveillance test. The licensee determined that the same auxiliary contact which failed
On September 22, 2006, Unit 3, Train A, EDG failed to develop output voltage during a
      in July 2006 was faulty. The licensee identified that this failure was attributed to a bent
surveillance test. The licensee determined that the same auxiliary contact which failed
      metal actuator arm that is used to actuate the auxiliary contacts associated with the field
in July 2006 was faulty. The licensee identified that this failure was attributed to a bent
      shorting circuit. Additionally, the licensee determined this bent metal actuator arm
metal actuator arm that is used to actuate the auxiliary contacts associated with the field
      potentially exits in all six EDG's at the facility. Based on previous failures it appears this
shorting circuit. Additionally, the licensee determined this bent metal actuator arm
      bent arm is the underlying root cause for the field shorting auxiliary contacts failure to
potentially exits in all six EDG's at the facility. Based on previous failures it appears this
      operate reliably, and this condition may affect all operating EDG's at the facility.
bent arm is the underlying root cause for the field shorting auxiliary contacts failure to
                                                A2-1                                    Attachment 2
operate reliably, and this condition may affect all operating EDG's at the facility.


  This Special Inspection Team is chartered to review the generic impact of the relays
Attachment 2
  bent arms on the other Palo Verde Emergency Diesel Generators as well as any
A2-2
  potential impact on other nuclear plants. The team is also to review the design change
This Special Inspection Team is chartered to review the generic impact of the relays
  method and reviews that the licensee used when making the relay modifications. The
bent arms on the other Palo Verde Emergency Diesel Generators as well as any
  team will also review the licensees operability determination and corrective action
potential impact on other nuclear plants. The team is also to review the design change
  program for determining the root cause and correction of the diesels failure.
method and reviews that the licensee used when making the relay modifications. The
B. Scope
team will also review the licensees operability determination and corrective action
  The team is expected to address the following:
program for determining the root cause and correction of the diesels failure.
  1.     Develop a complete scope of the failures of all Palo Verde Emergency Diesel
B.
          Generators to develop an output voltage.
Scope
  2.     Review the extent of condition determination for this condition (current and prior
The team is expected to address the following:
          K1 relay failures) and whether the licensees actions are comprehensive. This
1.
          should include potential for other diesel failures.
Develop a complete scope of the failures of all Palo Verde Emergency Diesel
  3.     Review the licensees determination of the cause of any design deficiencies.
Generators to develop an output voltage.
          Independently verify key assumptions and facts. If available, determine if the
2.
          licensees current and prior root cause analyses and corrective actions have
Review the extent of condition determination for this condition (current and prior
          addressed the extent of condition for problems with the emergency diesel
K1 relay failures) and whether the licensees actions are comprehensive. This
          generators K1 relays.
should include potential for other diesel failures.
  4.     Determine if the Technical Specifications were met when the diesel failed.
3.
  5.     Review and assess the corrective actions for current and past similar failures.
Review the licensees determination of the cause of any design deficiencies.  
  6.     Review the licensees EDG operability determination to evaluate the emergency
Independently verify key assumptions and facts. If available, determine if the
          diesel generators operability.
licensees current and prior root cause analyses and corrective actions have
  7.     Collect data as necessary to support a risk analysis.
addressed the extent of condition for problems with the emergency diesel
  8.     Determine if this issue has generic implications to other nuclear facilities.
generators K1 relays.
C. Guidance
4.
  Inspection Procedure 93812, Special Inspection, provides additional guidance to be
Determine if the Technical Specifications were met when the diesel failed.
  used by the Special Inspection Team. Your duties will be as described in Inspection
5.
  Procedure 93812. The inspection should emphasize fact-finding in its review of the
Review and assess the corrective actions for current and past similar failures.
  circumstances surrounding the event. It is not the responsibility of the team to examine
6.
  the regulatory process. Safety concerns identified that are not directly related to the
Review the licensees EDG operability determination to evaluate the emergency
  event should be reported to the Region IV office for appropriate action.
diesel generators operability.  
  The Team will report to the site, conduct an entrance, and begin inspection no later than
7.
  October 4, 2006. While on site, you will provide daily status briefings to Region IV
Collect data as necessary to support a risk analysis.
  management, who will coordinate with the Office of Nuclear Reactor Regulation, to
8.
  ensure that all other parties are kept informed. A report documenting the results of the
Determine if this issue has generic implications to other nuclear facilities.
  inspection should be issued within 30 days of the completion of the inspection.
C.
                                            A2-2                                Attachment 2
Guidance
Inspection Procedure 93812, Special Inspection, provides additional guidance to be
used by the Special Inspection Team. Your duties will be as described in Inspection
Procedure 93812. The inspection should emphasize fact-finding in its review of the
circumstances surrounding the event. It is not the responsibility of the team to examine
the regulatory process. Safety concerns identified that are not directly related to the
event should be reported to the Region IV office for appropriate action.
The Team will report to the site, conduct an entrance, and begin inspection no later than  
October 4, 2006. While on site, you will provide daily status briefings to Region IV
management, who will coordinate with the Office of Nuclear Reactor Regulation, to
ensure that all other parties are kept informed. A report documenting the results of the
inspection should be issued within 30 days of the completion of the inspection.


Attachment 2
A2-3
This Charter may be modified should the team develop significant new information that
This Charter may be modified should the team develop significant new information that
warrants review. Should you have any questions concerning this Charter, contact me at
warrants review. Should you have any questions concerning this Charter, contact me at
(817) 860-8248.
(817) 860-8248.  
                                    A2-3                                Attachment 2


                        SIGNIFICANCE DETERMINATION EVALUATION
Attachment 3
A3-1
SIGNIFICANCE DETERMINATION EVALUATION
Significance determination process Phase 1:
Significance determination process Phase 1:
        In accordance with NRC Inspection Manual Chapter 0609, Appendix A, Significance
In accordance with NRC Inspection Manual Chapter 0609, Appendix A, Significance
        Determination of Reactor Inspection Findings for At-Power Situations, the inspectors
Determination of Reactor Inspection Findings for At-Power Situations, the inspectors
        conducted a significance determination Phase 1 screening and determined that the
conducted a significance determination Phase 1 screening and determined that the
        finding resulted in loss of the safety function of the Train A emergency diesel generator
finding resulted in loss of the safety function of the Train A emergency diesel generator
        for greater than the Technical Specification allowed outage time. Therefore, a
for greater than the Technical Specification allowed outage time. Therefore, a
        Significance Determination Process Phase 2 evaluation was required.
Significance Determination Process Phase 2 evaluation was required.
Significance determination process Phase 2:
Significance determination process Phase 2:
        The Risk-Informed Inspection Notebook for Palo Verde Nuclear Generating Station,
The Risk-Informed Inspection Notebook for Palo Verde Nuclear Generating Station,
        Unit 3, Revision 1, September 2, 2003, was utilized for the Phase 2 evaluation of the
Unit 3, Revision 1, September 2, 2003, was utilized for the Phase 2 evaluation of the
        inoperable Train A emergency diesel generator. The following steps and the associated
inoperable Train A emergency diesel generator. The following steps and the associated
        findings are listed below:
findings are listed below:
        *       Select or define the applicable initiating event scenarios:
*
                Table 2, Initiators and System Dependency for Palo Verde Nuclear Generating
Select or define the applicable initiating event scenarios:
                Station, Units 1, 2, and 3, was reviewed to determine that the loss of offsite
Table 2, Initiators and System Dependency for Palo Verde Nuclear Generating
                power (LOOP) initiating event scenario was the only scenario that needed to be
Station, Units 1, 2, and 3, was reviewed to determine that the loss of offsite
                analyzed due to the failure of the Train A EDG.
power (LOOP) initiating event scenario was the only scenario that needed to be
        *       Estimate the likelihood of scenario initiating events and conditions:
analyzed due to the failure of the Train A EDG.
                The performance deficiency was assumed to exist for 58 days. The Phase 2
*
                analysis assumed the EDG was nonfunctional for an 18-day period, representing
Estimate the likelihood of scenario initiating events and conditions:
                the period from its last successful start on September 4, 2006, to its failed
The performance deficiency was assumed to exist for 58 days. The Phase 2
                surveillance on September 22, 2006. Using Table 1, Categories of Initiating
analysis assumed the EDG was nonfunctional for an 18-day period, representing
                Events for Palo Verde Nuclear Generating Station Unit 3, the initiating event
the period from its last successful start on September 4, 2006, to its failed
                likelihood for loss of offsite power was determined to be valued at 3. Additional
surveillance on September 22, 2006. Using Table 1, Categories of Initiating
                risk was accrued during the first 40 days of exposure because of a higher
Events for Palo Verde Nuclear Generating Station Unit 3, the initiating event
                likelihood of failure of the K-1 relay.
likelihood for loss of offsite power was determined to be valued at 3. Additional
        *       Estimate the remaining mitigation capability:
risk was accrued during the first 40 days of exposure because of a higher
                Using the SDP worksheet for a LOOP (Table 3.7, SDP Worksheet for Palo
likelihood of failure of the K-1 relay.  
                Verde Nuclear Generating Station, Units 1, 2, and 3 - Loss of Offsite Power
*
                (LOOP)), Sequences 1, 2, 3, 4, and 5, the following results were assigned for
Estimate the remaining mitigation capability:
                each:
Using the SDP worksheet for a LOOP (Table 3.7, SDP Worksheet for Palo
                        Sequence 1:     LOOP-AFW - 6
Verde Nuclear Generating Station, Units 1, 2, and 3 - Loss of Offsite Power
                        Sequence 2:     LOOP-EAC-REC3 - 8
(LOOP)), Sequences 1, 2, 3, 4, and 5, the following results were assigned for
                        Sequence 3:     LOOP-EAC-TDAFW-REC1 - 8
each:
                        Sequence 4:     LOOP-EAC-SEAL-HPSI - 12
Sequence 1: LOOP-AFW - 6
                        Sequence 5:     LOOP-EAC-SEAL-REC1 - 10
Sequence 2: LOOP-EAC-REC3 - 8
                                                  A3-1                                Attachment 3
Sequence 3: LOOP-EAC-TDAFW-REC1 - 8
Sequence 4: LOOP-EAC-SEAL-HPSI - 12
Sequence 5: LOOP-EAC-SEAL-REC1 - 10


      *       Estimate the risk significance of the inspection finding:
Attachment 3
                NRC Inspection Manual Chapter 0609, Significance Determination Process,
A3-2
                Appendix A, Attachment 1, Counting Rule Worksheet, was utilized using one
*
                sequence that resulted in a value of 6. Since step 10 was greater than zero, the
Estimate the risk significance of the inspection finding:
                risk significance of the inspection finding was determined to be at low to
NRC Inspection Manual Chapter 0609, Significance Determination Process,
                moderate safety significance (White).
Appendix A, Attachment 1, Counting Rule Worksheet, was utilized using one
sequence that resulted in a value of 6. Since step 10 was greater than zero, the
risk significance of the inspection finding was determined to be at low to
moderate safety significance (White).
Phase 3 Analysis
Phase 3 Analysis
Description of Performance Deficiencies
Description of Performance Deficiencies
      On July 25, 2006, the Unit 3 Train A EDG failed to start because of a failed K1 relay.
On July 25, 2006, the Unit 3 Train A EDG failed to start because of a failed K1 relay.  
      The last two spare relays obtained from the warehouse were identified to operate
The last two spare relays obtained from the warehouse were identified to operate
      unreliabley. The licensee performed corrective maintenance on one of the relays and
unreliabley. The licensee performed corrective maintenance on one of the relays and
      following installation it failed on September 22, 2006. Two performance deficiencies
following installation it failed on September 22, 2006. Two performance deficiencies
      were identified that contributed to the September 22, 2006, failure. The first
were identified that contributed to the September 22, 2006, failure. The first
      performance deficiency involved the failure to establish appropriate instructions for
performance deficiency involved the failure to establish appropriate instructions for
      performing corrective maintenance activities on an emergency diesel generator K-1
performing corrective maintenance activities on an emergency diesel generator K-1
      relay. The second performance deficiency involved the failure to identify and correct the
relay. The second performance deficiency involved the failure to identify and correct the
      cause of the erratic EDG K-1 relay operation prior to installation of the relay on July 26,
cause of the erratic EDG K-1 relay operation prior to installation of the relay on July 26,
      2006.
2006.
Assumptions
Assumptions
1.     The Unit 3 Train A EDG demand record is shown in the following table. (A failed bench
1.  
      test of the new K1 relay was not credited because it may have been due to debris
The Unit 3 Train A EDG demand record is shown in the following table. (A failed bench
      buildup resulting from a long period of warehousing.)
test of the new K1 relay was not credited because it may have been due to debris
                      Date               Demand Result             K-1 Relay
buildup resulting from a long period of warehousing.)
                      7/25/06               Fail to Start               Old
Date
                      7/26/06             Successful Start               New
Demand Result
                      8/07/06             Successful Start               New
K-1 Relay  
                      8/24/06             Successful Start               New
7/25/06
                      9/04/06             Successful Start               New
Fail to Start
                      9/22/06               Fail to Start               New
Old  
      The data was analyzed using three alternate assumptions as follows:
7/26/06
                                                A3-2                                Attachment 3
Successful Start
New
8/07/06
Successful Start
New
8/24/06
Successful Start
New
9/04/06
Successful Start
New
9/22/06
Fail to Start
New
The data was analyzed using three alternate assumptions as follows:


  Deterministic Assumption
Attachment 3
          It is assumed that the as-left condition of the EDG following a run either
A3-3
          predisposes it to a guaranteed success or failure on the next demand. This
Deterministic Assumption
          assumes that the success or failure on the next attempt is a function of the
It is assumed that the as-left condition of the EDG following a run either
          as-left condition of the relay following a load run.
predisposes it to a guaranteed success or failure on the next demand. This
          Based on this assumption, the Train A EDG was guaranteed to fail to start on
assumes that the success or failure on the next attempt is a function of the
          any demand subsequent to the last successful run on September 4, 2006, but
as-left condition of the relay following a load run.
          was likewise guaranteed to succeed on any demand prior to this date.
Based on this assumption, the Train A EDG was guaranteed to fail to start on
          Therefore, the EDG is assumed to be a failed state for 18 days.
any demand subsequent to the last successful run on September 4, 2006, but
  Stochastic Assumption
was likewise guaranteed to succeed on any demand prior to this date.  
          It is assumed that the EDG success or failure is a probabilistic event on any
Therefore, the EDG is assumed to be a failed state for 18 days.
          given demand. This assumes that the relay is more or less in the same state
Stochastic Assumption
          following each run, but that the as-left tolerances are so close to critical that the
It is assumed that the EDG success or failure is a probabilistic event on any
          chance of success or failure on the next demand is purely a probabilistic event.
given demand. This assumes that the relay is more or less in the same state
          Using this assumption, the Train A EDG was vulnerable to failure on any
following each run, but that the as-left tolerances are so close to critical that the
          demand following the installation of the new K1 relay on July 26, 2006. The
chance of success or failure on the next demand is purely a probabilistic event.
          successful start on July 26, 2006, and prior bench/installed test successes and
Using this assumption, the Train A EDG was vulnerable to failure on any
          failures were excluded from the data set because of possible preconditioning
demand following the installation of the new K1 relay on July 26, 2006. The
          effects. Therefore, three demands and one failure were left. The resulting
successful start on July 26, 2006, and prior bench/installed test successes and
          assumption is that the Train A EDG would have a 0.25 chance of failing to start
failures were excluded from the data set because of possible preconditioning
          from a K1 relay failure in response to any demand during the 58-day period
effects. Therefore, three demands and one failure were left. The resulting
          between July 26, 2006, and September 22, 2006.
assumption is that the Train A EDG would have a 0.25 chance of failing to start
  Combination Assumption
from a K1 relay failure in response to any demand during the 58-day period
          It is assumed that a stochastic mechanism existed for the first 40 days, but after
between July 26, 2006, and September 22, 2006.
          the final successful start on September 4, 2006, the EDG was guaranteed to fail
Combination Assumption
          on its next demand and, therefore, was in a failed state for the final 18 days of
It is assumed that a stochastic mechanism existed for the first 40 days, but after
          the exposure period.
the final successful start on September 4, 2006, the EDG was guaranteed to fail
          Using this assumption, the Train A EDG had a 0.25 probability of failing to start
on its next demand and, therefore, was in a failed state for the final 18 days of
          because of a failed K1 relay for the first 40 days and a 1.0 probability of failure
the exposure period.
          for the final 18 days of the exposure period.
Using this assumption, the Train A EDG had a 0.25 probability of failing to start
2. The analyst discarded any risk that may have accrued from September 22, 2005, to July
because of a failed K1 relay for the first 40 days and a 1.0 probability of failure
  25, 2006, (the balance of a one-year period) because of a lack of failure history during
for the final 18 days of the exposure period.
  this period (as confirmed by a review of surveillance test results).
2.
3. The analyst modified the current Palo Verde SPAR model (Revision 3.21, October 28,
The analyst discarded any risk that may have accrued from September 22, 2005, to July
  2005) to reflect the plant-specific LOOP frequencies listed in NUREG/CR-6890,
25, 2006, (the balance of a one-year period) because of a lack of failure history during
  Reevaluation of Station Blackout Risk at Nuclear Power Plants, Volume 1, Table D-1.
this period (as confirmed by a review of surveillance test results).
  This study comprised an update based on an analysis of offsite power events during
3.
  1986-2004. This change to the Palo Verde SPAR model for this specific analysis was
The analyst modified the current Palo Verde SPAR model (Revision 3.21, October 28,
                                            A3-3                                  Attachment 3
2005) to reflect the plant-specific LOOP frequencies listed in NUREG/CR-6890,
Reevaluation of Station Blackout Risk at Nuclear Power Plants, Volume 1, Table D-1.
This study comprised an update based on an analysis of offsite power events during
1986-2004. This change to the Palo Verde SPAR model for this specific analysis was


        endorsed by a representative of the Idaho National Laboratory (INL), the NRCs
Attachment 3
        contractor for SPAR model development.
A3-4
            Category of LOOP           Current SPAR Value         Revised Value Based on
endorsed by a representative of the Idaho National Laboratory (INL), the NRCs
                                                                        NUREG/CR-6890
contractor for SPAR model development.
              Plant Centered               2.07E-3/yr.                     2.01E-3/yr.
Category of LOOP
          Switchyard Centered             1.04E-2/yr.                     9.01E-3/yr.
Current SPAR Value
                Grid Related               1.86E-2/yr.                     4.40E-2/yr.
Revised Value Based on
              Weather Related               4.83E-3/yr.                     3.83E-3/yr.
NUREG/CR-6890
4.     It is assumed that the Unit 3 Train B EDG was not vulnerable to fail from the same
Plant Centered
        cause as the Train A EDG failure for the entire 58-day exposure period. This is based
2.07E-3/yr.
        on the fact that the relay actuator arm in the K1 relay for this diesel generator was
2.01E-3/yr.
        confirmed to be in a field-straightened configuration during this period. Therefore,
Switchyard Centered
        common cause was not invoked in the analysis and a failure probability of 1.0 was used
1.04E-2/yr.
        in lieu of TRUE. This is a key assumption with respect to the risk estimate because
9.01E-3/yr.
        common cause, if presumed, would result in a large increase in the value of the
Grid Related  
        fail-to-start common cause basic event.
1.86E-2/yr.
5.     No specific recovery of the Train A EDG was assumed, and no changes were made to
4.40E-2/yr.
        the EDG recovery values in the SPAR model. That is, for this analysis, the analyst
Weather Related
        assumed that the recovery probability of the EDGs was nominal.
4.83E-3/yr.
6.     The SPAR model includes cross-connection capabilities from the other units' diesel
3.83E-3/yr.
        generators. However, the cutsets that include these basic events are very insignificant
4.
        in the analysis. Therefore, the analyst did not adjust Unit 1 and 2 EDG common cause
It is assumed that the Unit 3 Train B EDG was not vulnerable to fail from the same
        probabilities from the base case.
cause as the Train A EDG failure for the entire 58-day exposure period. This is based
on the fact that the relay actuator arm in the K1 relay for this diesel generator was
confirmed to be in a field-straightened configuration during this period. Therefore,
common cause was not invoked in the analysis and a failure probability of 1.0 was used
in lieu of TRUE. This is a key assumption with respect to the risk estimate because
common cause, if presumed, would result in a large increase in the value of the
fail-to-start common cause basic event.  
5.
No specific recovery of the Train A EDG was assumed, and no changes were made to
the EDG recovery values in the SPAR model. That is, for this analysis, the analyst
assumed that the recovery probability of the EDGs was nominal.
6.
The SPAR model includes cross-connection capabilities from the other units' diesel
generators. However, the cutsets that include these basic events are very insignificant
in the analysis. Therefore, the analyst did not adjust Unit 1 and 2 EDG common cause
probabilities from the base case.
Internal Events Analysis
Internal Events Analysis
        The Palo Verde SPAR model (Revision 3.21, October 28, 2005), modified as described
The Palo Verde SPAR model (Revision 3.21, October 28, 2005), modified as described
        above, was used at a truncation of E-12.
above, was used at a truncation of E-12.  
        Deterministic Assumption
Deterministic Assumption
        Based on this assumption, the Train A EDG was guaranteed to fail to start on any
Based on this assumption, the Train A EDG was guaranteed to fail to start on any
        demand subsequent to the last successful run on September 4, 2006, but was likewise
demand subsequent to the last successful run on September 4, 2006, but was likewise
        guaranteed to succeed on any demand prior to this date. Therefore, the EDG was
guaranteed to succeed on any demand prior to this date. Therefore, the EDG was
        assumed to be in a failed state for 18 days. The use of a "T/2" assumption is not valid
assumed to be in a failed state for 18 days. The use of a "T/2" assumption is not valid
        in this case because the normally open contact is assumed to be open following the
in this case because the normally open contact is assumed to be open following the
        previous EDG run. This would cause the K1 unlatch coil to fail to energize for any
previous EDG run. This would cause the K1 unlatch coil to fail to energize for any
        hypothetical demand during this period and result in failure of the EDG field flash.
hypothetical demand during this period and result in failure of the EDG field flash.
                                                A3-4                                    Attachment 3


Attachment 3
A3-5
In the SPAR model, the following changes were made:
In the SPAR model, the following changes were made:
        EPS-DGN-FS-DGA was set to 1.0
EPS-DGN-FS-DGA was set to 1.0
The result in SAPHIRE is 1.047E-4/yr. A review of the cutsets revealed that several
The result in SAPHIRE is 1.047E-4/yr. A review of the cutsets revealed that several
included independent failures of Train A EDG to run as well as the test and maintenance
included independent failures of Train A EDG to run as well as the test and maintenance
basic event. These cutsets were logically inconsistent:
basic event. These cutsets were logically inconsistent:
            Cutsets containing:                             Value
Cutsets containing:
            EPS-DGN-FR-DGA                             2.024E-6/yr.
Value
            EPS-DGN-TM-DGA                             4.084E-7/yr.
EPS-DGN-FR-DGA
                    Total                             2.432E-6/yr.
2.024E-6/yr.
Extracting these cutsets leaves a result of 1.047E-4 - 2.432E-6 = 1.023E-4/yr.
EPS-DGN-TM-DGA
4.084E-7/yr.
Total
2.432E-6/yr.
Extracting these cutsets leaves a result of 1.047E-4 - 2.432E-6 = 1.023E-4/yr.  
Therefore, for an 18-day exposure period, the delta-CDF of the finding is
Therefore, for an 18-day exposure period, the delta-CDF of the finding is
1.023E-4yr.(18/365) = 5.0E-6/yr.
1.023E-4yr.(18/365) = 5.0E-6/yr.
Line 1,163: Line 1,306:
Stochastic Assumption
Stochastic Assumption
Using this assumption, the Train A EDG was vulnerable to failure on any demand
Using this assumption, the Train A EDG was vulnerable to failure on any demand
following the installation of the new K1 relay on July 26, 2006. As discussed above, the
following the installation of the new K1 relay on July 26, 2006. As discussed above, the
Train A EDG had a 0.25 probability of failing to start from a K1 relay failure in response
Train A EDG had a 0.25 probability of failing to start from a K1 relay failure in response
to any demand during the 58-day period of time between July 26, 2006, and
to any demand during the 58-day period of time between July 26, 2006, and
September 22, 2006.
September 22, 2006.
In SPAR, the following changes were made:
In SPAR, the following changes were made:
        EPS-DGN-FS-DGA was set to 0.25 + 5E-3 (base case probability) = 0.255
EPS-DGN-FS-DGA was set to 0.25 + 5E-3 (base case probability) = 0.255
The result in SAPHIRE is 2.447E-5. For the 58-day exposure period, the resulting
The result in SAPHIRE is 2.447E-5. For the 58-day exposure period, the resulting
delta-CDF is 2.447E-5 (58/365) = 3.9E-6/yr.
delta-CDF is 2.447E-5 (58/365) = 3.9E-6/yr.
Combination Assumption
Combination Assumption
Line 1,175: Line 1,318:
of a failed K1 relay for the first 40 days and a 1.0 probability of the same failure for the
of a failed K1 relay for the first 40 days and a 1.0 probability of the same failure for the
final 18 days of the exposure period.
final 18 days of the exposure period.
The result from the deterministic assumption is the same in this case. The exposure
The result from the deterministic assumption is the same in this case. The exposure
time for the stochastic portion is set at 40 instead of 58 days. Using the results above,
time for the stochastic portion is set at 40 instead of 58 days. Using the results above,
the delta-CDF of the combination assumption is 5.0E-6/yr. + 40/58 (3.9.E-6/yr.) =
the delta-CDF of the combination assumption is 5.0E-6/yr. + 40/58 (3.9.E-6/yr.) =
7.7E-6/yr.
7.7E-6/yr.
                                          A3-5                                  Attachment 3


Attachment 3
A3-6
External Events
External Events
        Seismic
Seismic
        Palo Verde is located in a relatively stable seismic region for a plant located in the
Palo Verde is located in a relatively stable seismic region for a plant located in the
        Western USA. The Idaho National Laboratory conducted a study to predict the
Western USA. The Idaho National Laboratory conducted a study to predict the
        frequency of a LOOP resulting from a seismic event at all US plants, as documented in
frequency of a LOOP resulting from a seismic event at all US plants, as documented in
        Frequency of Seismically-Induced LOOP events for SPAR models, Revision 1,
Frequency of Seismically-Induced LOOP events for SPAR models, Revision 1,
        September 2005. The conclusion of this study was that the mean frequency for a
September 2005. The conclusion of this study was that the mean frequency for a
        seismically-induced LOOP at Palo Verde is 5.37E-5/yr. The study concluded that the
seismically-induced LOOP at Palo Verde is 5.37E-5/yr. The study concluded that the
        failure of ceramic insulators would be the most likely failure mode inducing a LOOP.
failure of ceramic insulators would be the most likely failure mode inducing a LOOP.
        For risk assessment purposes, a seismically-induced LOOP would have a recovery
For risk assessment purposes, a seismically-induced LOOP would have a recovery
        profile similar to a severe weather event-induced LOOP. In SPAR (as modified above
profile similar to a severe weather event-induced LOOP. In SPAR (as modified above
        for this analysis), the frequency of a weather-related LOOP (used for the internal events
for this analysis), the frequency of a weather-related LOOP (used for the internal events
        assessment) is 3.83E-3/year. Therefore, the increase in LOOP frequency from seismic
assessment) is 3.83E-3/year. Therefore, the increase in LOOP frequency from seismic
        events is not significant by itself as it relates to the risk of this finding.
events is not significant by itself as it relates to the risk of this finding.
        The analyst also considered the possibility that an earthquake that results in a LOOP
The analyst also considered the possibility that an earthquake that results in a LOOP
        could damage equipment (apart from the diesel generators) that could add non-
could damage equipment (apart from the diesel generators) that could add non-
        negligible risk to the finding. To address this issue, INL produced a document entitled,
negligible risk to the finding. To address this issue, INL produced a document entitled,
        Seismic Event Modeling and Seismic Risk Assessment Handbook, Revision 1,
Seismic Event Modeling and Seismic Risk Assessment Handbook, Revision 1,
        September 2005. In particular, a LOOP resulting from an earthquake that also involved
September 2005. In particular, a LOOP resulting from an earthquake that also involved
        loss of risk-significant equipment in Train B and/or loss of the gas turbine generators
loss of risk-significant equipment in Train B and/or loss of the gas turbine generators
        could result in significant risk despite the low frequency of seismically-induced LOOPs.
could result in significant risk despite the low frequency of seismically-induced LOOPs.
        Within this document, Table B-1, Generic SSC Seismic Fragilities, provides a list of
Within this document, Table B-1, Generic SSC Seismic Fragilities, provides a list of
        components along with the median g-force required to damage them. The following
components along with the median g-force required to damage them. The following
        table lists examples of the equipment of concern and the frequency of earthquakes at
table lists examples of the equipment of concern and the frequency of earthquakes at
        Palo Verde that exceed the threshold value:
Palo Verde that exceed the threshold value:
            Component                   High Confidence Low             Frequency of >g Earthquake
Component
                                          Probability of Failure                  at Palo Verde
High Confidence Low
                                              Capacity (g)
Probability of Failure
Electrical Equipment                0.34                               1.0E-5/yr
Capacity (g)
(function during seismic
Frequency of >g Earthquake
event)
at Palo Verde
Electrical Equipment                0.77                               1.0E-8/yr.
Electrical Equipment
(function after seismic event)
(function during seismic
Battery Chargers/Inverters         0.54                               1.0E-6/yr.
event)
Batteries/Battery Racks             1.3                                 <9.3E-10/yr.
0.34
Diesel Generator/Support           1.06                               <9.3E-10/yr.
1.0E-5/yr
Systems
Electrical Equipment
Turbine-driven pumps               0.85                               1.0E-9/yr.
(function after seismic event)
                                                  A3-6                                    Attachment 3
0.77
1.0E-8/yr.
Battery Chargers/Inverters
0.54
1.0E-6/yr.
Batteries/Battery Racks
1.3
<9.3E-10/yr.
Diesel Generator/Support
Systems
1.06
<9.3E-10/yr.
Turbine-driven pumps
0.85
1.0E-9/yr.


Equipment success at g-forces well above the HCLPF value is possible. Based on
Attachment 3
A3-7
Equipment success at g-forces well above the HCLPF value is possible. Based on
review of the information provided above and other information in the INL document, the
review of the information provided above and other information in the INL document, the
analyst concluded that earthquakes causing LOOPs and loss of other on-site equipment
analyst concluded that earthquakes causing LOOPs and loss of other on-site equipment
would add risk small in comparison to the internal events result.
would add risk small in comparison to the internal events result.
The analyst assumed (conservatively) that the gas turbine generators would be lost in a
The analyst assumed (conservatively) that the gas turbine generators would be lost in a
seismic event that also causes a LOOP. To calculate the risk of the finding in light of
seismic event that also causes a LOOP. To calculate the risk of the finding in light of
this assumption, the analyst ran two cases using the revised SPAR model. In both runs,
this assumption, the analyst ran two cases using the revised SPAR model. In both runs,
the frequency of LOOPs was set at 5.37E-5/year (frequency of seismic-induced
the frequency of LOOPs was set at 5.37E-5/year (frequency of seismic-induced
LOOPs), and nonrecoveries of offsite power for all relevant times (3 hours and less as
LOOPs), and nonrecoveries of offsite power for all relevant times (3 hours and less as
Line 1,233: Line 1,393:
truncation greater than 3 hours in the Palo Verde SPAR model except for 24 hours;
truncation greater than 3 hours in the Palo Verde SPAR model except for 24 hours;
therefore, this change set is equivalent to assuming that offsite power following an
therefore, this change set is equivalent to assuming that offsite power following an
earthquake is not recovered). Both gas turbine generator fail-to-start events were set to
earthquake is not recovered). Both gas turbine generator fail-to-start events were set to
TRUE and only LOOP sequences were quantified. In the first case, the EDGs are
TRUE and only LOOP sequences were quantified. In the first case, the EDGs are
assumed to be nominally reliable and available. This result was 1.362E-7/yr. In the
assumed to be nominally reliable and available. This result was 1.362E-7/yr. In the
second case, EDG A is assigned a failure probability of 1.0 for the fail-to-start event.
second case, EDG A is assigned a failure probability of 1.0 for the fail-to-start event.  
The result was 2.747E-6/yr. The resulting CDF of the finding attributable to a seismic
The result was 2.747E-6/yr. The resulting CDF of the finding attributable to a seismic
event that debilitates the gas turbine generators is therefore (2.747E-6 -
event that debilitates the gas turbine generators is therefore (2.747E-6 -
1.362E-7)(18/365) = 1.3E-7/yr.
1.362E-7)(18/365) = 1.3E-7/yr.
Based on disussions, the licensees PRA assigns a value of approximately 4E-7/yr
Based on disussions, the licensees PRA assigns a value of approximately 4E-7/yr
delta-CDF for seismic events for a 18-day exposure period.
delta-CDF for seismic events for a 18-day exposure period.  
Fire
Fire
The analyst reviewed the licensee's IPEEE for Severe Accident Vulnerabilities,
The analyst reviewed the licensee's IPEEE for Severe Accident Vulnerabilities,
June 30, 1995, to determine the risk attributable to the finding resulting from internal
June 30, 1995, to determine the risk attributable to the finding resulting from internal
fires.
fires.  
A fire in Room 5B (Train B ESF switchgear room) was considered to have the largest
A fire in Room 5B (Train B ESF switchgear room) was considered to have the largest
potential risk to the finding. A fire in this room would possibly cause a loss of offsite
potential risk to the finding. A fire in this room would possibly cause a loss of offsite
power to both ESF buses. In this case, with a failure of EDG A to start, a station
power to both ESF buses. In this case, with a failure of EDG A to start, a station
blackout situation would exist. In the IPEEE, the CDF result for a fire in the Train B ESF
blackout situation would exist. In the IPEEE, the CDF result for a fire in the Train B ESF
switchgear room was 9.73E-6/yr. The fire ignition frequency for this room was
switchgear room was 9.73E-6/yr. The fire ignition frequency for this room was
5.5E-3/yr.
5.5E-3/yr.
The analyst determined that the IPEEE did not contain sufficient information to quantify
The analyst determined that the IPEEE did not contain sufficient information to quantify
the risk attributable to fires pertaining to the performance deficiency. Therefore, the
the risk attributable to fires pertaining to the performance deficiency. Therefore, the
analyst requested that the licensee use its fire PRA model for this purpose. The licensee
analyst requested that the licensee use its fire PRA model for this purpose. The licensee
reported that their fire PRA calculates a delta-CDF of 3.716E-6/yr for EDG A being
reported that their fire PRA calculates a delta-CDF of 3.716E-6/yr for EDG A being
nonfunctional versus the base case condition. For this case, the EDG failure was
nonfunctional versus the base case condition. For this case, the EDG failure was
assumed to be independent in nature, the same assumption used in the SPAR analysis.
assumed to be independent in nature, the same assumption used in the SPAR analysis.
For an 18-day exposure, this would result in a delta-CDF of 1.8E-7/yr.
For an 18-day exposure, this would result in a delta-CDF of 1.8E-7/yr.
                                          A3-7                                Attachment 3


      As a comparison, the following table shows the differences in the treatment of Room 5B
Attachment 3
      between the IPEEE and the fire PRA.
A3-8
                Room 5B                       IPEEE                       Fire PRA
As a comparison, the following table shows the differences in the treatment of Room 5B
          Fire Ignition Frequency             5.5E-3/yr.                 4.16E-3/yr.
between the IPEEE and the fire PRA.
                    CDF                     9.73E-6/yr.                 1.17E-7/yr.
Room 5B
      This example shows that the CCDP of a fire in this room decreased from 1.8E-3 in the
IPEEE
      IPEEE to 2.8E-5 in the fire PRA. This difference is not surprising because the IPEEE
Fire PRA
      was basically a screening tool that assumed worst-case bounding conditions while the
Fire Ignition Frequency
      fire PRA incorporated realistic, best-estimate approximations.
5.5E-3/yr.
      Internal Flooding/High Velocity Winds/Other External Events
4.16E-3/yr.
      The analyst concluded qualitatively that no other external events would add appreciably
CDF
      to the risk of the finding. The licensee reported that the risk added from internal flooding
9.73E-6/yr.
      according to their model was in the E-8 range.
1.17E-7/yr.
This example shows that the CCDP of a fire in this room decreased from 1.8E-3 in the
IPEEE to 2.8E-5 in the fire PRA. This difference is not surprising because the IPEEE
was basically a screening tool that assumed worst-case bounding conditions while the
fire PRA incorporated realistic, best-estimate approximations.
Internal Flooding/High Velocity Winds/Other External Events
The analyst concluded qualitatively that no other external events would add appreciably
to the risk of the finding. The licensee reported that the risk added from internal flooding
according to their model was in the E-8 range.
Combined Risk
Combined Risk
      Using the licensee analysis results for seismic and fire events, the following table
Using the licensee analysis results for seismic and fire events, the following table
      indicates the total estimated risk of the finding for each of the assumed failure
indicates the total estimated risk of the finding for each of the assumed failure
      mechanisms:
mechanisms:
      Assumption         Internal       Seismic           Fire             Total Risk
Assumption
                          Events
Internal
    Deterministic        5.0E-6       4E-7/yr         1.3E-7/yr           5.5E-6/yr
Events
      Stochastic         3.9E-6       3E-7/yr1       1.0E-7/yr1           4.3E-6/yr
Seismic
      Combination         7.7E-6       6E-7/yr1       2.1E-7/yr1           8.5E-6/yr
Fire
      1. Seismic and fire CDFs were adjusted for the stochastic and combination
Total Risk
          assumptions.
Deterministic
5.0E-6
4E-7/yr
1.3E-7/yr
5.5E-6/yr
Stochastic
3.9E-6
3E-7/yr1
1.0E-7/yr1
4.3E-6/yr
Combination
7.7E-6
6E-7/yr1
2.1E-7/yr1
8.5E-6/yr
1. Seismic and fire CDFs were adjusted for the stochastic and combination                    
                assumptions.
Large Early Release Frequency
Large Early Release Frequency
      In accordance with IMC 0609, Appendix H, station blackout sequences, which
In accordance with IMC 0609, Appendix H, station blackout sequences, which
      predominate the risk of the assessed condition, are not considered significant release
predominate the risk of the assessed condition, are not considered significant release
      events for a large, dry containment. Therefore, large early release was considered
events for a large, dry containment. Therefore, large early release was considered
      unimportant in this analysis.
unimportant in this analysis.
Licensee Analysis
Licensee Analysis
      The analyst did not receive a detailed description of the licensees analysis, but was
The analyst did not receive a detailed description of the licensees analysis, but was
      informed verbally that the delta-CDF of the finding for internal events and fire, assuming
informed verbally that the delta-CDF of the finding for internal events and fire, assuming
      an 18-day exposure and no recovery of the Train A EDG, was approximately 1.6E-6/yr.
an 18-day exposure and no recovery of the Train A EDG, was approximately 1.6E-6/yr.  
                                                A3-8                                  Attachment 3


      Adding the licensees approximate seismic risk, the overall result would be
Attachment 3
      approximately 2.0E-6/yr.
A3-9
Adding the licensees approximate seismic risk, the overall result would be
approximately 2.0E-6/yr.
References
References
      Palo Verde SPAR model (Revision 3.21, October 28, 2005)
Palo Verde SPAR model (Revision 3.21, October 28, 2005)  
      NUREG/CR-6890, Reevaluation of Station Blackout Risk at Nuclear Power Plants,
NUREG/CR-6890, Reevaluation of Station Blackout Risk at Nuclear Power Plants,
      Volume 1, Table D-1
Volume 1, Table D-1
      Seismic Event Modeling and Seismic Risk Assessment Handbook, Revision 1,
Seismic Event Modeling and Seismic Risk Assessment Handbook, Revision 1,
      September 2005
September 2005
      Palo Verde IPEEE for Severe Accident Vulnerabilities, June 30, 1995
Palo Verde IPEEE for Severe Accident Vulnerabilities, June 30, 1995
      Palo Verde Fire PRA Overview and Results, 13-NS-C072
Palo Verde Fire PRA Overview and Results, 13-NS-C072
                                          A3-9                                  Attachment 3
}}
}}

Latest revision as of 04:53, 15 January 2025

IR 05000528-06-012; 05000529-06-012; 05000530-06-012; 10/02/2006 - 11/09/2006; Palo Verde Nuclear Generating Station, Units 1, 2, and 3: Special Inspection in Response to Unit 3 Train a EDG Failures on July 25 and September 22, 2006
ML063400561
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 12/06/2006
From: Howell A
NRC/RGN-IV/DRP
To: James M. Levine
Arizona Public Service Co
References
EA-06-296 IR-06-012
Download: ML063400561 (36)


See also: IR 05000528/2006012

Text

December 6, 2006

EA-06-296

James M. Levine, Executive

Vice President, Generation

Mail Station 7602

Arizona Public Service Company

P.O. Box 52034

Phoenix, AZ 85072-2034

SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, and 3 - NRC

SPECIAL INSPECTION REPORT 05000528/2006012; 05000529/2006012;

05000530/2006012

Dear Mr. Levine:

On November 30, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed a special

inspection at your Palo Verde Nuclear Generating Station, Units 1, 2, and 3. This inspection

examined activities associated with the Unit 3 Train A emergency diesel generator (EDG)

failures that occurred on July 25 and September 22, 2006. On both occasions the EDG failed

to produce an output voltage during testing. The NRC's initial evaluation satisfied the criteria in

NRC Management Directive 8.3, NRC Incident Investigation Program, for conducting a special

inspection. The basis for initiating this special inspection is further discussed in the Charter,

which is included as Attachment 2 to this report. The determination that the inspection would

be conducted was made by the NRC on September 29, 2006, and the inspection started on

October 2, 2006.

The enclosed special inspection report documents the inspection findings which were discussed

on November 9, 2006, with you, and other members of your staff, and on November 30, 2006,

with Mr. David Mauldin, Vice President, Engineering, and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commission's rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

The attached report discusses two findings that appear to have low to moderate safety

significance (White). As described in Section 3.0 of this report, the NRC concluded that the

failure to establish appropriate instructions for performing corrective maintenance activities on a

K-1 relay resulted in the Unit 3 Train A EDG being inoperable between September 4 and 22,

2006. Additionally, the failure to identify and correct the cause of the erratic EDG K-1 relay

operation prior to installation of the relay on July 26, 2006, was identified as another

performance deficiency that contributed to the Unit 3 Train A EDG being inoperable for a period

Arizona Public Service Company

-2-

greater than the Technical Specification completion time. The safety significance of these

findings was assessed on the basis of the best available information, including influential

assumptions, using the applicable Significance Determination Process and were preliminarily

determined to be White (i.e., low to moderate safety significance) findings. Preliminarily, these

findings have a low to moderate safety significance when assuming a loss of offsite power

initiating event and the Unit 3 Train A EDG being in an unreliable condition for approximately

40 days and a nonfunctional condition for approximately 18 days. Attachment 3 of this report

provides a detailed description of the preliminary risk assessment. In accordance with NRC

Inspection Manual Chapter (IMC) 0609, Significance Determination Process, we intend to

complete our evaluation using the best available information and issue our final determination

of safety significance within 90 days of this letter.

These findings do not represent an immediate safety concern because of the corrective actions

you have taken. These actions involved inspecting, cleaning, and implementing mechanical

adjustments, as appropriate, to the operating mechanism of the EDG K-1 relays.

Also, these findings constitute apparent violations of NRC requirements and are being

considered for escalated enforcement action in accordance with the NRC Enforcement Policy.

The current Enforcement Policy is included on the NRCs web site at

http://www.nrc.gov/reading-rm/adams.html.

Before we make a final decision on this matter, we are providing you an opportunity to present

to the NRC your perspectives on the facts and assumptions, used by the NRC to arrive at the

findings and their significance, at a Regulatory Conference or in writing. As discussed during a

telephone call with Mr. Scott Bauer, Department Leader, Regulatory Affairs, we understand that

it is your intent to discuss your perspectives during a Regulatory Conference. Accordingly, a

Regulatory Conference is scheduled to be conducted in the NRC Region IV office in Arlington,

Texas, on January 16, 2007. We encourage you to submit supporting documentation at least

one week prior to the conference in an effort to make the conference more efficient and

effective. This Regulatory Conference will be open to public observation.

Since the NRC has not made a final determination in this matter, no Notice of Violation is being

issued for these inspection findings at this time. In addition, please be advised that the number

and characterization of apparent violations described in the enclosed inspection report may

change as a result of further NRC review.

The report also documents one finding with two examples involving inadequate implementation

of the operability determination process. This finding was determined to be a violation of very

low safety significance. Because of the very low safety significance and because it was entered

into your corrective action program, the NRC is treating this finding as a noncited violation

consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest the noncited

violation in this report, you should provide a response within 30 days of the date of this

inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission,

ATTN.: Document Control Desk, Washington, DC 20555-0001; and the NRC Resident

Inspector at the Palo Verde Nuclear Generating Station.

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter

and its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRC's

Arizona Public Service Company

-3-

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Arthur T. Howell III, Director

Division of Reactor Projects

Dockets: 50-528

50-529

50-530

Licenses: NPF-41

NPF-51

NPF-74

Enclosure:

Inspection Report 05000528/2006012; 05000529/2006012; 05000530/2006012

w/Attachment 1: Supplemental Information

Attachment 2: Special Inspection Charter

Attachment 3: Significance Determination Evaluation

cc w/enclosure:

Steve Olea

Arizona Corporation Commission

1200 W. Washington Street

Phoenix, AZ 85007

Douglas K. Porter, Senior Counsel

Southern California Edison Company

Law Department, Generation Resources

P.O. Box 800

Rosemead, CA 91770

Chairman

Maricopa County Board of Supervisors

301 W. Jefferson, 10th Floor

Phoenix, AZ 85003

Aubrey V. Godwin, Director

Arizona Radiation Regulatory Agency

4814 South 40 Street

Phoenix, AZ 85040

Craig K. Seaman, General Manager

Regulatory Affairs and

Performance Improvement

Palo Verde Nuclear Generating Station

Arizona Public Service Company

-4-

Mail Station 7636

P.O. Box 52034

Phoenix, AZ 85072-2034

Jeffrey T. Weikert

Assistant General Counsel

El Paso Electric Company

Mail Location 167

123 W. Mills

El Paso, TX 79901

John W. Schumann

Los Angeles Department of Water & Power

Southern California Public Power Authority

P.O. Box 51111, Room 1255-C

Los Angeles, CA 90051-0100

John Taylor

Public Service Company of New Mexico

2401 Aztec NE, MS Z110

Albuquerque, NM 87107-4224

Thomas D. Champ

Southern California Edison Company

5000 Pacific Coast Hwy, Bldg. D1B

San Clemente, CA 92672

Robert Henry

Salt River Project

6504 East Thomas Road

Scottsdale, AZ 85251

Brian Almon

Public Utility Commission

William B. Travis Building

P.O. Box 13326

1701 North Congress Avenue

Austin, TX 78701-3326

Karen O'Regan

Environmental Program Manager

City of Phoenix

Office of Environmental Programs

200 West Washington Street

Phoenix, AZ 85003

Matthew Benac

Assistant Vice President

Nuclear & Generation Services

Arizona Public Service Company

-5-

El Paso Electric Company

340 East Palm Lane, Suite 310

Phoenix, AZ 85004

Arizona Public Service Company

-6-

Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

DRS Deputy Director (RJC1)

Senior Resident Inspector (GXW2)

Branch Chief, DRP/D (TWP)

Senior Project Engineer, DRP/D (GEW)

Team Leader, DRP/TSS (RVA)

RITS Coordinator (KEG)

DRS STA (DAP)

V. Dricks, PAO (VLD)

D. Cullison, OEDO RIV Coordinator (DGC)

ROPreports

PV Site Secretary (PRC)

K. S. Fuller, RC/ACES (KSF)

C. A. Carpenter, D:OE (CAC)

G. M. Vasquez (GMV)

OE:EA File (RidsOeMailCenter)

SUNSI Review Completed: __TWP_ ADAMS: / Yes

G No Initials: __TWP____

/ Publicly Available G Non-Publicly Available G Sensitive

/ Non-Sensitive

R:\\_REACTORS\\_PV\\2006\\PV2006-12RP-MCH.wpd

RIV:SPE:DRP/D RI:DRS/EB1

PE:DRP/D

C:DRP/D

SRA:DRS

ACES

MCHay

SPRutenkroger

MRBloodgood TWPruett

MFRunyan

GMVasquez

/RA/

MCHay For

MCHay For

/RA/

/RA/

/RA/

11 /27/06

11/28/06

11/28/06

11/28/06

11/28/06

11/28/06

D:DRP

ATHowell III

/RA/

12/06/06

OFFICIAL RECORD COPY

T=Telephone E=E-mail F=Fax

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Dockets:

50-528; 50-529; 50-530

Licenses:

NPF-41; NPF-51; NPF-74

Report No.:

05000528/2006012; 05000529/2006012; 05000530/2006012

Licensee:

Arizona Public Service Company

Facility:

Palo Verde Nuclear Generating Station, Units 1, 2, and 3

Location:

5951 S. Wintersburg Road

Tonopah, Arizona

Dates:

October 2 through November 30, 2006

Inspectors:

M. Hay, Senior Project Engineer, Team Leader

Dr. S. Rutenkroger, Reactor Inspector, Engineering Branch 1

M. Runyan, Senior Reactor Analyst

Accompanied:

M. Bloodgood, Reactor Engineer, Nuclear Safety Professional Development

Program

Approved By:

Arthur T. Howell III, Director

Division of Reactor Projects

Enclosure

1

SUMMARY OF FINDINGS

IR 05000528/2006012; 05000529/2006012; 05000530/2006012; 10/02/2006 - 11/09/2006; Palo

Verde Nuclear Generating Station, Units 1, 2, and 3: Special Inspection in response to Unit 3

Train A EDG failures on July 25 and September 22, 2006.

The report covered a 5-day period (October 2-6, 2006) of onsite inspection, with in-office review

through November 30, 2006, by a special inspection team consisting of one senior project

engineer, one reactor inspector, one reactor engineer, and one senior reactor analyst. Three

findings were identified. The significance of most findings is indicated by its color (Green,

White, Yellow, Red) using Inspection Manual Chapter 0609, Significance Determination

Process. Findings for which the significance determination process does not apply may be

Green or be assigned a severity level after NRC management review. The NRC's program for

overseeing the safe operation of commercial nuclear power reactors is described in

NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.

Summary of Event

The NRC conducted a special inspection to better understand the circumstances surrounding

two failures of the Unit 3 Train A emergency diesel generator that occurred on July 25 and

September 22, 2006. Both failures involved the emergency diesel generator failing to obtain an

output voltage during surveillance testing because of faulty K-1 relay operation. In accordance

with NRC Management Directive 8.3, NRC Incident Investigation Program, it was determined

that this event involved repetitive failures of safety related equipment having potential adverse

generic implications and had sufficient risk significance to warrant a special inspection.

A.

NRC-Identified and Self Revealing Findings

Cornerstone: Mitigating Systems

TBD. The team identified an apparent violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, for the failure to establish

appropriate instructions for performing corrective maintenance activities on an

emergency diesel generator K-1 relay. As a result, following identification that a

replacement emergency diesel generator K-1 relay was unreliable, the licensee

performed ineffective corrective maintenance activities on this relay. This

performance deficiency contributed to the Unit 3 Train A emergency diesel

generator being inoperable between September 4 and 22, 2006, and a failure on

September 22, 2006. Immediate corrective actions included inspection,

cleaning, and/or performing mechanical adjustments on all emergency diesel

generator K-1 relays. This issue was entered into the licensees corrective

action program as Condition Report/Disposition Request 2926830.

The finding is greater than minor because it is associated with the equipment

performance cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable

consequences. Using NRC Inspection Manual Chapter 0609, Significance

Determination Process, Phase 1 Worksheet, a Phase 2 evaluation was required

Enclosure

2

because the finding resulted in the loss of the safety function of the Unit 3 Train

A emergency diesel generator for greater than the Technical Specification

completion time. The Phase 2 evaluation concluded that the finding was of low

to moderate safety significance. A Phase 3 preliminary significance

determination analysis also determined the finding was of low to moderate safety

significance. The cause of this finding is related to the crosscutting element of

human performance associated with resources in that the licensee failed to

develop and implement appropriate work instructions prior to performing

corrective maintenance activities on an emergency diesel generator K-1 relay

(Section 3.0).

TBD. The team identified an apparent violation of 10 CFR Part 50, Appendix B,

Criterion XVI, Corrective Actions, for the failure to identify and correct the

cause of erratic emergency diesel generator K-1 relay operation prior to

installation of the relay on July 26, 2006. This performance deficiency

contributed to the Unit 3 Train A emergency diesel generator being inoperable

between September 4 and 22, 2006, and a failure on September 22, 2006.

Immediate corrective actions included inspection, cleaning, and performing

mechanical adjustments, as appropriate, on all emergency diesel generator K-1

relays. This issue was entered into the licensees corrective action program as

Condition Report/Disposition Request 2926830.

The finding is greater than minor because it is associated with the equipment

performance cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable

consequences. Using NRC Inspection Manual Chapter 0609, Significance

Determination Process, Phase 1 Worksheet, a Phase 2 evaluation was required

because the finding resulted in the loss of the safety function of the Unit 3 Train

A emergency diesel generator for greater than the Technical Specification

allowed outage time. The Phase 2 evaluation concluded that the finding was of

low to moderate safety significance. A Phase 3 preliminary significance

determination analysis also determined the finding was of low to moderate

safety significance. The cause of this finding is related to the crosscutting

element of problem identification and resolution in that the failure to fully

evaluate and implement adequate corrective maintenance actions for the Unit 3

Train A emergency diesel generator resulted in the emergency diesel generator

being inoperable for 18 days (Section 3.0).

The team identified two examples of a noncited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the failure

to perform operabilty determinations. In both examples, the licensee failed to

perform an operability determination following identification of a degraded

condition that had the potential to adversely affect the safety function of all

emergency diesel generators. Specifically, an operability determination was not

performed after identifying the failure of the Unit 3 Train A emergency diesel

generator on July 25, 2006, was potentially the result of plastic debris affecting

proper auxiliary contact operation of a K-1 relay. The licensee determined the

debris most likely originated from a modification performed on all emergency

diesel generator K-1 relays during initial plant startup. Following another failure

Enclosure

3

of the Unit 3 Train A emergency diesel generator on September 22, 2006, an

operability determination was not performed after identifying the failure was the

result of the K-1 relay actuating arm not providing adequate compression of the

auxiliary contacts. The licensee determined this degraded condition most likely

originated during implementation a modification done to all emergency diesel

generator K-1 relays during initial plant startup.

This finding is greater than minor because the failure to follow the operability

determination process, if left uncorrected, would become a more significant

safety concern in that degraded or nonconforming conditions would not be

properly evaluated. Using the Phase 1 worksheet in NRC Inspection Manual

Chapter 0609, Significance Determination Process, the finding was determined

to have very low safety significance because unreliable K-1 relay operation

resulted in no actual loss of safety function of the other five emergency diesel

generators prior to corrective actions being implemented, and the finding did not

represent a potential risk significant condition because of a seismic, flooding, or

severe weather event. This issue is documented in the licensees corrective

action program as Condition Report/Disposition Requests 2928389 and

2940558. The cause of this finding is related to the crosscutting element of

problem identification and resolution in that engineering personnel failed to

properly evaluate and perform operability determinations for identified degraded

conditions affecting the emergency diesel generators (Section 4.0).

B.

Licensee-Identified Findings

None.

Enclosure

4

REPORT DETAILS

1.0

SPECIAL INSPECTION SCOPE

The NRC conducted this special inspection to better understand the circumstances

surrounding two failures of the Unit 3 Train A emergency diesel generator (EDG) that

occurred on July 25 and September 22, 2006. Both failures involved the EDG failing to

obtain an output voltage during surveillance testing because of a faulty K-1 relay

operation. In accordance with NRC Management Directive 8.3, NRC Incident

Investigation Program, it was determined that this event met several deterministic

criteria and had sufficient risk significance to warrant a special inspection.

The team used NRC Inspection Procedure 93812, Special Inspection Procedure, to

conduct the inspection. The special inspection team reviewed procedures, corrective

action documents, and design and maintenance records for the equipment of concern.

The team interviewed key station personnel regarding the event, reviewed the root

cause analysis, and assessed the adequacy of corrective actions. A list of specific

documents reviewed is provided in Attachment 1. The charter for the special inspection

effort is provided as Attachment 2.

2.0

EVENT DESCRIPTION

Each unit at Palo Verde contains two safety-related 5500 Kw EDGs that provide standby

power for safe plant shutdown in the event the normal supply of power is lost. On

July 25, 2006, at 12:53 p.m., the Unit 3 Train A EDG failed to develop an output voltage

during a routine surveillance test. When the EDGs are secured a field shorting K-1

relay actuates to electrically short the generator field causing the generator output

voltage to collapse. A relay latching mechanism maintains the field shorted until the

EDG is started at which time the latch disengages allowing the relay to actuate and un-

short the EDG field. With the field no longer shorted the voltage regulator establishes

and controls the EDG output voltage. The licensee identified that a faulty set of auxiliary

contacts on a K-1 relay prevented the latch from disengaging that resulted in the

generator field being shorted during the start of the EDG. The licensee determined the

root cause of the auxiliary contact failure could be attributed to either plastic debris or

oxide film buildup preventing continuity across the contacts when closed. Following the

failure on July 25, 2006, the licensee replaced the failed K-1 relay with a new relay

obtained from the warehouse. During continuity checks of the new relay, the same

auxiliary contacts were identified to operate unreliably. The last available relay from the

warehouse was obtained and it also operated unreliably and it had a warped cover.

Based on no other replacement K-1 relays being available, the licensee performed

corrective maintenance activities on the first relay obtained from the warehouse in an

attempt to resolve the problem. Following these corrective maintenance activities, the

relay was successfully tested several times and the Unit 3 Train A EDG was declared

operable at 10:35 a.m. on July 26, 2006.

On September 22, 2006, the Unit 3 Train A EDG failed to develop an output voltage

following a postmaintenance surveillance test. The licensee identified that the same set

Enclosure

5

of auxiliary contacts that previously exhibited erratic behavior during continuity checks

had failed. The licensee identified that the K-1 relay actuating arm for the affected

auxiliary contact module was not providing adequate compression of the auxiliary

contacts. Corrective actions involved mechanical adjustments to the actuating arm to

provide proper auxiliary contact compression. Additional corrective actions included

inspecting, cleaning, and making mechanical adjustments, as necessary, to all other

affected EDG K-1 relays.

3.0

PERFORMANCE DEFICIENCIES RESULTING IN EDG FAILURE

a.

Inspection Scope

On July 25 and September 22, 2006, the Unit 3 Train A EDG failed to produce output

voltage during surveillance testing. The team reviewed the licensees corrective actions

following failure of the Unit 3 Train A EDG on July 25, 2006, to assess their

effectiveness with respect to preventing the subsequent failure that occurred on

September 22, 2006.

b. Observations and Findings

Introduction: The team identified two apparent violations of NRC requirements. The

team identified an apparent violation of 10 CFR Part 50, Appendix B, Criterion V,

Instructions, Procedures, and Drawings, for the failure to establish appropriate

instructions for performing corrective maintenance activities on an EDG K-1 relay. As a

result, following identification that a replacement EDG K-1 relay was unreliable, the

licensee performed ineffective corrective maintenance activities on this relay.

Additionally, the team identified an apparent violation of 10 CFR Part 50, Appendix B,

Criterion XVI, Corrective Action, involving the failure to identify the cause of a

significant condition adverse to quality and take corrective actions to preclude repetition.

Specifically, following identification that a replacement EDG K-1 relay was unreliable,

the licensee failed to identify the cause of this condition and implement adequate

corrective actions. These performance deficiencies resulted in the Unit 3 Train A EDG

being inoperable between September 4 and 22, 2006, and a failure on September 22,

2006. These issues have potential low to moderate safety significance (White).

Description: On July 25, 2006, at 12:53 p.m., the Unit 3 Train A EDG failed to develop

an output voltage during a routine surveillance test. The licensee identified that a faulty

set of auxiliary contacts on a K-1 relay resulted in the generator field being shorted

during the start of the EDG. A new K-1 relay assembly was acquired from the

warehouse and during functional testing the same auxiliary contacts exhibited erratic

operation. The team noted that Work Order 2913004 stated, in part, that the K-1 relay

failed at first. Checked and re-attempted satisfactory. Performed several times

satisfactory. System engineering showed up and after discussing the problem they

wanted to verify repeatability. Checking contact resistance was found to be erratic.

Unable to clean the contacts to get consistent readings. Determined not reliable and

ordered last K-1 relay from the warehouse.

Enclosure

6

Initial attempts, by electrical maintenance personnel, to clean the auxiliary contacts of

the first relay obtained from the warehouse consisted of using a 9-volt battery connected

across the contacts. By cycling the contacts, the licensee stated that an electrical arc

could potentially clean any oxidation affecting the contacts ability to pass current. The

licensee stated this practice was utilized because engineering would not allow intrusive

actions, such as taking the relay apart, to clean the auxiliary contacts because of

concerns with maintaining critical dimensions. The team noted the licensee had no

maintenance instructions applicable to disassembly of the relay and no detailed vendor

specifications describing the critical attributes of the device. The licensee stated that

obtaining this type of information was not possible because the equipment was

obsolete, it was commercially dedicated by a vendor, and the vendor and manufacturer

of the component were no longer in business. Based on these reasons, the licensee

stated that no maintenance activities were performed on the auxiliary contacts and that

when problems were encountered the K-1 relay was replaced as a whole unit.

After initial attempts to clean the K-1 relay auxiliary contacts using the 9-volt battery

failed, the licensee obtained the last replacement K-1 relay available onsite. Again, they

found that the same set of auxiliary contacts on this relay exhibited erratic operation

when cycled. Additionally, the cover to this relay was found in a warped condition. At

this point the licensee decided to perform intrusive cleaning of the auxiliary contacts on

the first device that they determined was unreliable following non-intrusive cleaning

efforts. The team noted that no detailed work instructions were established to perform

this activity to improve its reliable operation. As previously stated, the licensee did not

possess any detailed vendor information specifically related to performing maintenance

activities on this device. After disassembling the auxiliary contacts, cleaning, and

reassembly, the relay was tested several times and the erratic behavior was not

observed during subsequent functional tests of the relay. A postmaintenance

surveillance test of the EDG was performed satisfactorily and the equipment was

declared operable at 10:35 a.m. on July 26, 2006.

On September 22, 2006, the Unit 3 Train A EDG failed to develop an output voltage

following a postmaintenance surveillance test. The licensee identified that the same set

of auxiliary contacts that exhibited erratic behavior on the K-1 relay had failed, resulting

in the generator field being shorted during the start of the EDG. The licensee identified

that the auxiliary contacts were not held closed when the K-1 relay was energized

because of an actuating arm that was not adequately depressing the auxiliary contact

switch. The team noted that this condition most likely existed during the initial testing on

July 25, 2006, and would have contributed to the erratic operation of this contact switch

assembly. Additionally, the team determined that this condition was not identified and

corrected because instructions for performing corrective maintenance activities on the

unreliable K-1 relay were inadequate. The team noted that the last successful start of

the Unit 3 Train A EDG was on September 4, 2006.

As previously stated, the licensee initially believed the erratic behavior resulted from

oxidation of the contact surfaces which required an intrusive maintenance activity to

clean the contact surfaces. The licensee stated that contact oxidation is a common

occurrence requiring cleaning. The team reviewed all work orders associated with

replacement of the K-1 relay dating back to 1984 and noted that none of the work orders

documented erratic auxiliary contact operation because of oxidation. During the review

Enclosure

7

of work orders, the team noted that Work Order 00067739, dated December 11, 1984,

discussed troubleshooting and repair activities for a faulty auxiliary contact on the K-1

relay affecting the Unit 1 Train B EDG. This work order contained instructions to inspect

the auxiliary contact arm on the K-1 relay and make adjustments as needed for proper

contact operation per Technical Manual MO18-390. The maintenance technician

performing the work documented, Adjusted the actuation arm for the auxiliary contacts

on the left side of the K-1 contactor as required. Based on this work order, the team

determined that on this occasion the licensee had worked on the auxiliary contact

operating mechanism to ensure reliable operation. A technician involved in this

maintenance activity did not recall the specifics of the work performed on the relay nor

the use of technical information contained in the technical manual. The team reviewed

the technical manual and found that no pertinent maintenance information for the K-1

relay existed.

Although no pertinent maintenance information for the K-1 relay was identified during

review of Technical Manual MO18-390, the team noted that detailed instructions were

provided to maintenance personnel for ensuring that critical tolerances of other relays

were maintained. The team noted that the voltage controlled overcurrent relay, reverse

power relay, frequency relay, and negative-phase sequence time overcurrent relay, all

associated with the EDG voltage regulating system, contained specific installation,

operation, and maintenance instructions. The team noted that these instructions

provided detailed information for activities involving contact cleaning, contact

adjustments, operational checks, and mechanical adjustments for each particular type

of relay to ensure reliable operation.

The licensee stated that the EDG K-1 relays had a history of operating reliably. Data

collected since 1990 indicated that the EDG K-1 relays had not failed because of

auxiliary contact problems similar to the failures identified in July and September of

2006. The team determined that this reliability data further demonstrated that, when the

erratic relay operation was identified, the licensee should have recognized that

corrective measures were needed that would require appropriate instructions to ensure

future reliable operation.

The team determined that the licensees problem analysis efforts were narrowly

focused, which led them to conclude that the cause of the erratic relay operation was

oxidized contacts. The erratic operation of the K-1 relay provided an indication that

sufficient auxiliary contact continuity existed, at least intermittently, which indicated that

another failure mechanism was contributing to the unreliable K-1 relay operation. If the

licensee performed an adequate cause analysis of this significant condition adverse to

quality, then they may have identified the failure mechanism associated with the

actuating arm not providing adequate contact compression prior to installation of the

new relay on July 26, 2006.

Analysis: NRC Inspection Manual Chapter 0612, Power Reactor Inspection Reports,

defines a performance deficiency as an issue that is the result of a licensee not meeting

a requirement or standard where the cause was reasonably within the licensees ability

to foresee and correct and that should have been prevented. The licensee determined

that the K-1 relay that failed in September of 2006 was unreliable prior to placing it in

service and would require corrective maintenance. The licensee stated that

Enclosure

8

disassembly of the relay to implement intrusive corrective actions had never been

performed because of concerns with maintaining critical dimensions for reliable relay

operation. The licensee did not obtain, nor did they develop, detailed information

specific to performing corrective or preventive maintenance activities for this specific

relay. On the basis of these considerations, the team concluded that the licensees

failure to establish and implement adequate maintenance instructions to resolve the

unreliable K-1 relay condition was a performance deficiency resulting in the Unit 3 Train

A EDG being inoperable between September 4 and 22, 2006. The team determined

that the EDG was inoperable for an 18-day period on the basis that when the EDG was

shut down on September 4, 2006, the K-1 relay auxiliary contacts would have been

positioned and maintained in a state that would have resulted in a subsequent failure of

the relay to operate properly following an EDG start signal. Additionally, the team

determined that the failure to perform an adequate cause assessment of the erratic

relay operation contributed to the inoperability of the Unit 3 Train A EDG.

These findings are greater than minor because they are associated with the equipment

performance cornerstone objective to ensure the availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences. Using

NRC Inspection Manual Chapter 0609, Significance Determination Process, Phase 1

Worksheet, a Phase 2 analysis was required because the findings resulted in the loss of

the safety function of the Unit 3 Train A EDG for greater than the Technical Specification

completion time. The Phase 2 and 3 evaluations preliminarily concluded that the

findings were of low to moderate safety significance. (See Attachment 3 for Phase 2

and Phase 3 details.) The cause of the Criterion XVI finding is related to the

crosscutting element of problem identification and resolution in that the failure to fully

evaluate and implement adequate corrective maintenance actions for the Unit 3 Train A

EDG contributed to the EDG being inoperable for 18 days. Additionally, the cause of

the Criterion V finding is related to the crosscutting element of human performance

associated with resources in that the licensee failed to develop and implement

appropriate work instructions prior to performing corrective maintenance activities on the

subject EDG K-1 relay, which contributed to the EDG being inoperable for 18 days.

Enforcement: 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and

Drawings, states, in part, that activities affecting quality shall be prescribed by

documented instructions, procedures, or drawings of a type appropriate to the

circumstances and shall be accomplished in accordance with these instructions,

procedures, or drawings. Contrary to this, the licensee failed to develop appropriate

instructions or procedures for corrective maintenance activities on the Unit 3 Train A

EDG K-1 relay. This failure resulted in the Unit 3 Train A EDG being inoperable

between September 4 and 22, 2006. This item has been entered into the licensees

corrective action program as Condition Report/Disposition Request (CRDR) 2926830.

Pending determination of safety significance, this finding is identified as an apparent

violation (AV)05000530/2006012-01, Failure to Establish Appropriate Instructions.

10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, states, in part, that

measures shall be established to assure that conditions adverse to quality, such as

failures, malfunctions, deficiencies, deviations, defective material and equipment, and

nonconformances are promptly identified and corrected and for significant conditions

adverse to quality, measures shall assure that the cause of the condition is determined

Enclosure

9

and corrective action taken to preclude repetition. Contrary to this, the licensee failed to

identify and correct the cause of the erratic EDG K-1 relay operation prior to installation

of the relay on July 26, 2006. This failure resulted in the Unit 3 Train A EDG being

inoperable between September 4 and 22, 2006. This item has been entered into the

licensees corrective action program as CRDR 2926830. Pending determination of

safety significance, this finding is identified as AV 05000530/2006012-02, Failure to

Identify and Correct a Condition Adverse to Quality.

4.0

Failure to Implement the Operability Determination Process

a.

Inspection Scope

The team assessed the engineering and operations departments implementation of the

operability determination (OD) process after identifying potential adverse conditions

involving reliable K-1 relay operation of the EDGs. This assessment was performed

through interviews and a review of precisely logs, ODs, and related documents. In

addition, the team conducted an independent assessment of system operability.

b.

Observations and Findings

Introduction: The team identified two examples of a Green noncited violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, involving the

failure to follow the OD procedure.

Description:

Example One

Administrative Procedure 40DP-9OP26, Operability Determination and Functional

Assessment, Revision 17, Section 1.3, stated, in part, that the OD process is entered

when the ability of a Technical Specification system or component to perform its

specified safety function is called into question by the discovery of a degraded condition.

As previously discussed, on July 25, 2006, the Unit 3 Train A EDG failed to produce

output voltage during surveillance testing. The licensee identified that a faulty set of

auxiliary contacts on a K-1 relay resulted in the generator field being shorted during the

start of the EDG. The team noted that an engineering team was assigned to perform a

root cause analysis for the K-1 relay auxiliary contact failure. This root cause evaluation

was documented in CRDR 2913003. The root cause team determined the most

probable cause was due to contamination on the contact surface either from oxidation or

from pieces of plastic filings found in the contact area. The plastic pieces were believed

to have resulted from a modification of the contact block actuator implemented by

Design Change Package DCP X-PE-007. This design change added auxiliary contacts,

latching mechanisms, and spacers to all EDG K-1 relays at the facility to address

seismic concerns identified during testing of the K-1 relay during the initial plant

construction phase.

Enclosure

10

The NRC inspection team noted that the licensees root cause assessment team

concluded that only the Unit 3 Train A EDG was potentially degraded by this condition.

The evaluation stated, in part, that:

The same model/type field shorting contactor is used on all six Class 1E

EDGs. In addition, two spare K-1 relays removed from the warehouse

exhibited the same symptoms with varying resistance across the auxiliary

contacts. An inspection/test of the auxiliary contacts for all other EDGs

was performed, with no other auxiliary contact resistance problems

identified.

The NRC team was informed that the licensees inspection consisted of a functional

check of the relay and did not involve visually inspecting the auxiliary contact internals to

identify the presence of plastic filings. Based on this, the team determined that the

inspection and contact resistance testing alone failed to demonstrate why only the Unit 3

Train A EDG K-1 relay was affected since the relay had operated properly since being

placed in service on August 1, 2001. Therefore, the licensee inadequately assessed the

extent of condition of the unreliable relay operation relative to the other EDGs at the

facility.

The NRC team noted that the root cause assessment identified a degraded condition,

plastic filings in the contact module that likely affected all the facility EDGs. However,

the licensee failed to enter the OD process after identifying this potentially degraded

condition.

Example Two

As previously discussed, on September 22, 2006, at 1:18 a.m., the Unit 3 Train A EDG

failed to produce output voltage during surveillance testing. The licensee identified that

a faulty set of auxiliary contacts on a K-1 relay resulted in the generator field being

shorted during the start of the EDG. The licensee identified that the K-1 relay actuating

arm for the affected auxiliary contact module was not providing adequate compression

of the auxiliary contacts. The licensee noted that part of the actuating arm consisted of

a metal tab that was bent in a configuration that would result in less contact

compression. The licensee decided to straighten the metal tab, thereby, providing

additional contact compression. Five functional tests of the relay were performed and

the EDG was declared operable following a postmaintenance surveillance test on

September 22, 2006, at 5:48 p.m.

The team noted that CRDR 2926830 documented the licensees evaluation of this

failure. The CRDR stated, in part:

The auxiliary contacts that had failed were added to the K-1 relay by

Design Change Package DCP X-PE-007 during plant startup in response

to electrical seismic latch failures. Engineering believes that the actuator

arm mounted metal tab was initially bent because originally there were no

auxiliary contacts on that side of the K-1 relay. Following completion of

the design change, the auxiliary contacts appeared to be working properly

so the actuator arms were left bent down. Inspection of some of the K-1

Enclosure

11

relays removed from EDGs in the past found at least one that had the

actuator arm straight; however, in most cases, the actuator arm metal tab

for the auxiliary contacts were found bent down. This is a repeat failure

of Unit 3 Train A EDG to produce output voltage. Recent verification of

acceptable K-1 relay auxiliary contact continuity on the other five EDGs

provides the basis that this condition is not present on those relays.

The NRC team was informed that the licensees inspection consisted of a functional

check of the relay and did not involve visually inspecting the auxiliary contact actuating

arms to identify a bent configuration. Based on this, the team determined that the

inspection and contact resistance testing alone failed to demonstrate why only the Unit 3

Train A EDG K-1 relay was affected, since the relay had operated properly since being

placed in service on July 26, 2006. Therefore, the licensee inadequately assessed the

extent of condition of the unreliable relay operation relative to the other EDGs at the

facility.

The team noted that the engineering assessment identified a degraded condition, a bent

K-1 relay actuating arm resulting in unreliable operation, that likely affected all the facility

EDGs. The licensee failed to enter the OD process after identifying this potentially

degraded condition. Following discussions with the licensee, an OD was performed on

September 27, 2006.

In both of these examples the team determined that engineering failed to recognize that

the identified degraded conditions had the potential to adversely affect the other EDGs.

On both occasions engineering relied on continuity checks of the auxiliary contacts to

inappropriately conclude that the other EDGs were not affected. The team noted that

the testing results were pertinent to an OD assessment; however, the information did

not provide adequate justification for not implementing the OD process ensuring

reasonable assurance existed supporting operability of the other EDGs.

Analysis: The performance deficiency was associated with engineering personnel not

adequately implementing the provisions of the OD procedure following the identification

of a degraded condition. This finding was more than minor because the failure to follow

the operability determination process, if left uncorrected, would become a more

significant safety concern in that degraded or nonconforming conditions would not be

properly evaluated. Using the Phase 1 worksheet in Manual Chapter 0609,

Significance Determination Process, the finding was determined to have very low

safety significance because, although these conditions resulted in unreliable K-1 relay

operation, no actual loss of safety function occurred (with respect to the other 5 EDGs)

prior to corrective actions being implemented, and the finding did not represent a

potential risk significant condition due to a seismic, flooding, or severe weather event.

This finding involved problem identification and resolution crosscutting aspects

associated with engineering personnel failing to properly evaluate and perform

operability determinations for identified degraded conditions.

Enforcement: 10 CFR Part 50, Criterion V, Instructions, Procedures, and Drawings,

states, in part, that activities affecting quality shall be prescribed by documented

instructions, procedures, or drawings of a type appropriate to the circumstances and

shall be accomplished in accordance with these instructions, procedures, or drawings.

Enclosure

12

Administrative Procedure 40DP-9OP26, Operability Determination and Functional

Assessment, Revision 17, Section 1.3, stated, in part, that the OD process is entered

when the ability of a Technical Specification system or component to perform its

specified safety function is called into question by the discovery of a degraded condition.

Contrary to the above, on two occasions the licensee failed to enter the OD process

when the ability of a Technical Specification system or component safety function was

called into question. On July 25, 2006, following failure of the Unit 3 Train A EDG, an

OD was not performed after identifying the failure was likely because of plastic filings

affecting proper auxiliary contact operation of a K-1 relay. The filings were believed to

be from a modification that was performed on all EDG K-1 relays during initial plant

startup. On September 22, 2006, following another failure of the Unit 3 Train A EDG, an

OD was not performed after identifying the failure was the result of the K-1 relay

actuating arm not providing adequate compression of the auxiliary contacts. The

licensee determined this condition most likely resulted from a modification performed on

all EDG K-1 relays during initial plant startup. Because the finding is of very low safety

significance and has been entered into the licensees corrective action program as

CRDRs 2928389 and 2940558, this violation is being treated as a noncited violation

consistent with Section VI.A of the Enforcement Policy: Noncited Violation

05000528;05000529;05000530/2006012-03, Failure to Implement the Operability

Determination Process.

5.0

CORRECTIVE ACTIONS FOLLOWING EDG FAILURES

a.

Inspection Scope

The team assessed the licensees immediate and long-term planned corrective actions

associated with the Unit 3 Train A EDG failures that occurred on July 25 and

September 22, 2006. This assessment was performed through interviews, review of

operator logs, corrective action documents, work orders, and related documents.

b.

Observations and Findings

Following the Unit 3 Train A EDG failure on July 25, 2006, the licensee identified that

plastic filings inside the auxiliary contact module may have resulted in the failure. The

licensee concluded this material most likely was introduced during a design change

performed on all the K-1 relays and subsequently established a schedule to inspect all

the EDG auxiliary contact modules. The team noted these inspections were scheduled

to be performed November 2006 through March 2007. NRC Inspection Manual,

Part 9900, Technical Guidance, Operability Determination and Functionality

Assessments for Resolution of Degraded or Nonconforming Conditions Adverse to

Quality or Safety, Section 4.2, states, When a potential degraded or nonconforming

condition is identified, the licensee should take action without delay to confirm if a

system, structure, or component is degraded or nonconforming. The team concluded

that waiting approximately 8 months to identify whether other EDGs were affected by

this potential adverse condition was not commensurate with the safety consequences of

having a degraded EDG.

Enclosure

13

Following the September 22, 2006, Unit 3 Train A EDG failure, the licensee identified

that a bent K-1 relay actuating arm resulted in unreliable auxiliary contact operation.

Immediate corrective actions involved straightening the arm to provide additional contact

compression for the Unit 3 Train A EDG. The team noted that the licensee implemented

timely corrective actions to inspect and implement mechanical adjustments, as needed,

to all the EDG relays to ensure adequate contact compression during operation. These

actions were implemented September 27-30, 2006, and incorporated the inspections

resulting from the July failure that were originally not scheduled to be completed until

March 2007. The licensee straightened bent K-1 relay contactor arms for the Unit 2

Trains A and B EDGs, and the Unit 1 Train B EDG. The team determined that these

actions were timely and they included the inspections identified following the July failure.

Therefore, there were no regulatory findings associated with timeliness of these

corrective actions.

The team noted that long-term planned corrective actions consisted of replacing all of

the EDG automatic voltage regulators, including replacement of the K-1 relays, with a

different design. The licensee stated that they plan to have these replacement activities

accomplished during the next refueling outage for each unit.

6.0

Generic Implications

The team reviewed various NRC generic communications and operating experience

from other licensees relevant to the EDG relay failures identified at the Palo Verde

Nuclear Generating Station. No relevant similar relay failures were identified. Both the

NRC and the licensee concluded that the relay problems pertaining to ensuring

adequate contact compression is provided by the actuator arm was potentially of

generic concern. On October 21, 2006, the licensee submitted voluntary Licensee

Event Report (LER) 50-530/2006-006-00 to report this concern.

4OA3 Event Follow-up (71153)

.1

(Closed) LER 05000530/2006-006-00, Voluntary LER for Failure of Emergency

Diesel Generator to Attain Required Voltage Due to Relay Contactor

On September 22, 2006, at 1:18 a.m., the Unit 3 Train A EDG failed to produce

output voltage during surveillance testing. The licensee identified that a faulty

set of auxiliary contacts on a K-1 relay resulted in the generator field being

shorted during the start of the EDG. The licensee identified that the K-1 relay

actuating arm for the affected auxiliary contact module was not providing

adequate compression of the auxiliary contacts. The licensee noted that part of

the actuating arm consisted of a metal tab that was bent in a configuration that

would result in less contact compression. Immediate corrective actions involved

mechanical adjustments made to the actuating arm providing additional contact

compression for the Unit 3 Train A EDG. Additionally, the licensee implemented

corrective actions to inspect and make adjustments as needed to all the EDG

relays. As discussed in section 3.0 of this report, the Unit 3 Train A EDG failure

on September 22, 2006, resulted from and inadequate cause assessment and

the failure to establish appropriate corrective maintenance instructions which

Enclosure

14

resulted in a violation of Technical specification 3.8.1.B since the inoperable

EDG exceeded the completion time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The team determined that the

licensee failed to identify that 10 CFR 50.73(a)(2)(B) requires the licensee to

report any operation or condition which was prohibited by the plants Technical

Specifications. Based on the licensee having performed a voluntary LER

addressing both Unit 3 Train A EDG failures that occurred on July 25, 2006, and

September 22, 2006, the failure to make a required report in accordance with

10 CFR 50.73 constitutes a violation of minor significance that is not subject to

enforcement action in accordance with Section IV of the NRCs Enforcement.

This LER is closed.

4OA6 Meetings, Including Exit

On November 30, 2006, the inspection results were discussed with Mr. David Mauldin,

Vice President, Engineering, and other members of the plant staff. The inspectors

asked the licensee whether any of the material examined during the inspection should

be considered proprietary. No proprietary information was identified.

ATTACHMENT 1: SUPPLEMENTAL INFORMATION

ATTACHMENT 2: SPECIAL INSPECTION CHARTER

ATTACHMENT 3: SIGNIFICANCE DETERMINATION EVALUATION

Attachment 1

A1-1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

S. Bauer, Department Leader, Regulatory Affairs

P. Borchert, Director, Operations

L. Bullington, Probabilistic Risk Analysis

C. Churchman, Director, Engineering

C. Cooper, Acting Electrical Maintenance Engineering Section Leader

E. Dutton, Nuclear Assurance Department

C. Eubanks, Vice President, Nuclear Operations

M. Green, LAN Department

J. Holmes, Section Leader

R. Henry, Site Representative

D. Leech, Department Leader, Corrective Action Program

J. Levine, Executive Vice President, Generation

C. Marschall, Consultant

D. Mauldin, Vice President, Engineering

L. Nguyen, LA Power and Water

S. Peace, Owner Services Consultant

M. Perito, Plant Manager

J. Proctor, Section Leader, Regulatory Affairs - Compliance

C. Seaman, General Manager, Regulatory Affairs and Performance Improvement

D. Steen, Senior Engineer

T. Radtke, General Manager

B. Ramey, Maintenance Engineering Department Leader

R, Schwartsbeck, Enercon Services

E. Shouse, Site Representative

G. Sowers, Section Leader, Probabilistic Risk Analysis

D. Straka, Senior Consultant, Regulatory Affairs

D. Vogt, Section Leader, Operations/Shift Technical Advisor

D. Withers, Maintenance Engineering

NRC Personnel

T. Vegel, Deputy Director, Division of Reactor Projects

G. Warnick, Senior Resident Inspector, Palo Verde Nuclear Generating Station

Attachment 1

A1-2

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000530/2006012-01

AV

Failure to Establish Appropriate Instructions05000530/2006012-02

AV

Failure to Identify and Correct aCondition Adverse

to Quality

05000528;05000529;05000530/2006012-03

NCV

Failure to Implement the Operability Determination

Process

Closed

05000528; 05000529;05000530/2006012-03

NCV

Failure to Implement the Operability Determination

Process

05000530/2006-006-00

LER

Voluntary LER for Failure of Emergency Diesel

Generator to Attain Required Voltage Due to Relay

Contactor

LIST OF DOCUMENTS REVIEWED

Drawings

13-M018-00159

C72-15000-100

D72 12200 750 Rev. E

D72-12200-710 Rev. E

D72-12200-100 Rev. B

Miscellaneous

1986 Document Specification 13-MM-0018

CES 0391-45C Seismic Test Program on Unit and Diesel Generator Control Panel

Emergency Diesel Generator Pre-operational Test

Surveillance Logs

IEEE 387 (1972 Version)

Design Change Package DCP 2SE-PE-007

Design Change Package DCP 10E-PE-007

M018-00425 Seismic Qualification Report on Triaxial Shake Table Tests of Two K-1 Relays

M018-00367 Report of Witness Tests of KSV-20-T Engine-Generator Set

Miscellaneous Documents Containing Pre-operational Test Data

Miscellaneous Control Room Log Entries for K-1 Relay Failures

Plant Change Request 86-13-PE-002

Purchasing Order 10470-13-MM-018 Documentation

Purchasing Order 33501265 Documentation

Attachment 1

A1-3

Purchasing Order 44930161 Documentation

Purchasing Order 60113782 Documentation

Portec Inc. Instruction Manual for the Static Voltage Regulator System

SFR 1PE-018

TN-E-3489

Startup Work Authorizations

SWA 15805, 1 SWA 15532, 1 SWA 15795, 1 SWA 17469, 1 SWA 16047, 2 SWA 15532, 2

SWA 15795, 2 SWA 16047, 3 SWA 15532, 3 SWA 15795, U1-SWA 15188, and U1-SWA

19219

Engineering Evaluation Requests

EER 85-PE-007

EER 85-PE-008

EER 84-PE-002

Procedures

93PE-1PE01

CRAIs

2829958, 2829959, 2829960, 2829961, 2829964, 2829965, 2829967, 2829971, 2829973, and

2829974

CRDRs

43930, 51630, 51743, 53295, 53788, 55546, 58135, 59433, 90278, 115952, 160332, 2361791,

2405054, 2410347, 2432009, 2532225, 2570582, 2579229, 2582956, 2641676, 2645588,

2650009, 2660221, 2752631, 2759704, 2784750, 2847506, 2872154, 2906158, 2913003,

2926830, and 2927262

Work Orders

00003495, 67521, 67550, 119715, 360726, 360944, 412917, 1040142, 1071966, 1329487,

2361781, 2410350, 2750447, 2794362, 2902642, 2913004, 2913286, 2913287, 2913295,

2913306, 2913753, 2919666, 2919670, 2919671, 2919672, 2919673, 2919747, and 2926829

Attachment 2

A2-1

SPECIAL INSPECTION CHARTER

September 29, 2006

MEMORANDUM TO: Michael Hay, Senior Project Engineer,

Project Branch D, Division of Reactor Projects (DRP)

Dr. Scott Rutenkroger, Reactor Inspector,

Engineering Branch 1, Division of Reactor Safety

Michael Bloodgood, Reactor Engineer, Nuclear Safety Professional

Development Program, Project Branch D, DRP

FROM:

Arthur T. Howell III, Director, DRP /RA/ AVegel for

SUBJECT:

SPECIAL INSPECTION CHARTER TO EVALUATE THE PALO VERDE

NUCLEAR GENERATING STATION UNIT 3 EMERGENCY DIESEL

GENERATOR FAILURE

A Special Inspection Team is being chartered in response to the Palo Verde Nuclear

Generating Station Unit 3 Emergency Diesel Generator (EDG) failure. The diesel failed to

develop an output voltage when started for a surveillance test. The licensee determined that a

modification to the field flashing relay caused the failure. You are hereby designated as the

Special Inspection Team members. Mr. Hay is designated as the team leader. The assigned

SRA to support the team is Mike Runyan.

A.

Basis

On July 25, 2006, Unit 3, Train A, EDG failed to develop output voltage during a

surveillance test. The licensee's root cause determined plastic debris potentially

prevented auxiliary contacts from properly functioning resulting in shorting out of the

generator field during startup preventing a proper field flash. Two replacement relays

obtained from the licensee warehouse exhibited the same unreliable condition. After

performing corrective maintenance activities on one of the relays, the diesel was

subsequently tested and declared operable on July 26, 2006.

On September 22, 2006, Unit 3, Train A, EDG failed to develop output voltage during a

surveillance test. The licensee determined that the same auxiliary contact which failed

in July 2006 was faulty. The licensee identified that this failure was attributed to a bent

metal actuator arm that is used to actuate the auxiliary contacts associated with the field

shorting circuit. Additionally, the licensee determined this bent metal actuator arm

potentially exits in all six EDG's at the facility. Based on previous failures it appears this

bent arm is the underlying root cause for the field shorting auxiliary contacts failure to

operate reliably, and this condition may affect all operating EDG's at the facility.

Attachment 2

A2-2

This Special Inspection Team is chartered to review the generic impact of the relays

bent arms on the other Palo Verde Emergency Diesel Generators as well as any

potential impact on other nuclear plants. The team is also to review the design change

method and reviews that the licensee used when making the relay modifications. The

team will also review the licensees operability determination and corrective action

program for determining the root cause and correction of the diesels failure.

B.

Scope

The team is expected to address the following:

1.

Develop a complete scope of the failures of all Palo Verde Emergency Diesel

Generators to develop an output voltage.

2.

Review the extent of condition determination for this condition (current and prior

K1 relay failures) and whether the licensees actions are comprehensive. This

should include potential for other diesel failures.

3.

Review the licensees determination of the cause of any design deficiencies.

Independently verify key assumptions and facts. If available, determine if the

licensees current and prior root cause analyses and corrective actions have

addressed the extent of condition for problems with the emergency diesel

generators K1 relays.

4.

Determine if the Technical Specifications were met when the diesel failed.

5.

Review and assess the corrective actions for current and past similar failures.

6.

Review the licensees EDG operability determination to evaluate the emergency

diesel generators operability.

7.

Collect data as necessary to support a risk analysis.

8.

Determine if this issue has generic implications to other nuclear facilities.

C.

Guidance

Inspection Procedure 93812, Special Inspection, provides additional guidance to be

used by the Special Inspection Team. Your duties will be as described in Inspection

Procedure 93812. The inspection should emphasize fact-finding in its review of the

circumstances surrounding the event. It is not the responsibility of the team to examine

the regulatory process. Safety concerns identified that are not directly related to the

event should be reported to the Region IV office for appropriate action.

The Team will report to the site, conduct an entrance, and begin inspection no later than

October 4, 2006. While on site, you will provide daily status briefings to Region IV

management, who will coordinate with the Office of Nuclear Reactor Regulation, to

ensure that all other parties are kept informed. A report documenting the results of the

inspection should be issued within 30 days of the completion of the inspection.

Attachment 2

A2-3

This Charter may be modified should the team develop significant new information that

warrants review. Should you have any questions concerning this Charter, contact me at

(817) 860-8248.

Attachment 3

A3-1

SIGNIFICANCE DETERMINATION EVALUATION

Significance determination process Phase 1:

In accordance with NRC Inspection Manual Chapter 0609, Appendix A, Significance

Determination of Reactor Inspection Findings for At-Power Situations, the inspectors

conducted a significance determination Phase 1 screening and determined that the

finding resulted in loss of the safety function of the Train A emergency diesel generator

for greater than the Technical Specification allowed outage time. Therefore, a

Significance Determination Process Phase 2 evaluation was required.

Significance determination process Phase 2:

The Risk-Informed Inspection Notebook for Palo Verde Nuclear Generating Station,

Unit 3, Revision 1, September 2, 2003, was utilized for the Phase 2 evaluation of the

inoperable Train A emergency diesel generator. The following steps and the associated

findings are listed below:

Select or define the applicable initiating event scenarios:

Table 2, Initiators and System Dependency for Palo Verde Nuclear Generating

Station, Units 1, 2, and 3, was reviewed to determine that the loss of offsite

power (LOOP) initiating event scenario was the only scenario that needed to be

analyzed due to the failure of the Train A EDG.

Estimate the likelihood of scenario initiating events and conditions:

The performance deficiency was assumed to exist for 58 days. The Phase 2

analysis assumed the EDG was nonfunctional for an 18-day period, representing

the period from its last successful start on September 4, 2006, to its failed

surveillance on September 22, 2006. Using Table 1, Categories of Initiating

Events for Palo Verde Nuclear Generating Station Unit 3, the initiating event

likelihood for loss of offsite power was determined to be valued at 3. Additional

risk was accrued during the first 40 days of exposure because of a higher

likelihood of failure of the K-1 relay.

Estimate the remaining mitigation capability:

Using the SDP worksheet for a LOOP (Table 3.7, SDP Worksheet for Palo

Verde Nuclear Generating Station, Units 1, 2, and 3 - Loss of Offsite Power

(LOOP)), Sequences 1, 2, 3, 4, and 5, the following results were assigned for

each:

Sequence 1: LOOP-AFW - 6

Sequence 2: LOOP-EAC-REC3 - 8

Sequence 3: LOOP-EAC-TDAFW-REC1 - 8

Sequence 4: LOOP-EAC-SEAL-HPSI - 12

Sequence 5: LOOP-EAC-SEAL-REC1 - 10

Attachment 3

A3-2

Estimate the risk significance of the inspection finding:

NRC Inspection Manual Chapter 0609, Significance Determination Process,

Appendix A, Attachment 1, Counting Rule Worksheet, was utilized using one

sequence that resulted in a value of 6. Since step 10 was greater than zero, the

risk significance of the inspection finding was determined to be at low to

moderate safety significance (White).

Phase 3 Analysis

Description of Performance Deficiencies

On July 25, 2006, the Unit 3 Train A EDG failed to start because of a failed K1 relay.

The last two spare relays obtained from the warehouse were identified to operate

unreliabley. The licensee performed corrective maintenance on one of the relays and

following installation it failed on September 22, 2006. Two performance deficiencies

were identified that contributed to the September 22, 2006, failure. The first

performance deficiency involved the failure to establish appropriate instructions for

performing corrective maintenance activities on an emergency diesel generator K-1

relay. The second performance deficiency involved the failure to identify and correct the

cause of the erratic EDG K-1 relay operation prior to installation of the relay on July 26,

2006.

Assumptions

1.

The Unit 3 Train A EDG demand record is shown in the following table. (A failed bench

test of the new K1 relay was not credited because it may have been due to debris

buildup resulting from a long period of warehousing.)

Date

Demand Result

K-1 Relay

7/25/06

Fail to Start

Old

7/26/06

Successful Start

New

8/07/06

Successful Start

New

8/24/06

Successful Start

New

9/04/06

Successful Start

New

9/22/06

Fail to Start

New

The data was analyzed using three alternate assumptions as follows:

Attachment 3

A3-3

Deterministic Assumption

It is assumed that the as-left condition of the EDG following a run either

predisposes it to a guaranteed success or failure on the next demand. This

assumes that the success or failure on the next attempt is a function of the

as-left condition of the relay following a load run.

Based on this assumption, the Train A EDG was guaranteed to fail to start on

any demand subsequent to the last successful run on September 4, 2006, but

was likewise guaranteed to succeed on any demand prior to this date.

Therefore, the EDG is assumed to be a failed state for 18 days.

Stochastic Assumption

It is assumed that the EDG success or failure is a probabilistic event on any

given demand. This assumes that the relay is more or less in the same state

following each run, but that the as-left tolerances are so close to critical that the

chance of success or failure on the next demand is purely a probabilistic event.

Using this assumption, the Train A EDG was vulnerable to failure on any

demand following the installation of the new K1 relay on July 26, 2006. The

successful start on July 26, 2006, and prior bench/installed test successes and

failures were excluded from the data set because of possible preconditioning

effects. Therefore, three demands and one failure were left. The resulting

assumption is that the Train A EDG would have a 0.25 chance of failing to start

from a K1 relay failure in response to any demand during the 58-day period

between July 26, 2006, and September 22, 2006.

Combination Assumption

It is assumed that a stochastic mechanism existed for the first 40 days, but after

the final successful start on September 4, 2006, the EDG was guaranteed to fail

on its next demand and, therefore, was in a failed state for the final 18 days of

the exposure period.

Using this assumption, the Train A EDG had a 0.25 probability of failing to start

because of a failed K1 relay for the first 40 days and a 1.0 probability of failure

for the final 18 days of the exposure period.

2.

The analyst discarded any risk that may have accrued from September 22, 2005, to July

25, 2006, (the balance of a one-year period) because of a lack of failure history during

this period (as confirmed by a review of surveillance test results).

3.

The analyst modified the current Palo Verde SPAR model (Revision 3.21, October 28,

2005) to reflect the plant-specific LOOP frequencies listed in NUREG/CR-6890,

Reevaluation of Station Blackout Risk at Nuclear Power Plants, Volume 1, Table D-1.

This study comprised an update based on an analysis of offsite power events during

1986-2004. This change to the Palo Verde SPAR model for this specific analysis was

Attachment 3

A3-4

endorsed by a representative of the Idaho National Laboratory (INL), the NRCs

contractor for SPAR model development.

Category of LOOP

Current SPAR Value

Revised Value Based on

NUREG/CR-6890

Plant Centered

2.07E-3/yr.

2.01E-3/yr.

Switchyard Centered

1.04E-2/yr.

9.01E-3/yr.

Grid Related

1.86E-2/yr.

4.40E-2/yr.

Weather Related

4.83E-3/yr.

3.83E-3/yr.

4.

It is assumed that the Unit 3 Train B EDG was not vulnerable to fail from the same

cause as the Train A EDG failure for the entire 58-day exposure period. This is based

on the fact that the relay actuator arm in the K1 relay for this diesel generator was

confirmed to be in a field-straightened configuration during this period. Therefore,

common cause was not invoked in the analysis and a failure probability of 1.0 was used

in lieu of TRUE. This is a key assumption with respect to the risk estimate because

common cause, if presumed, would result in a large increase in the value of the

fail-to-start common cause basic event.

5.

No specific recovery of the Train A EDG was assumed, and no changes were made to

the EDG recovery values in the SPAR model. That is, for this analysis, the analyst

assumed that the recovery probability of the EDGs was nominal.

6.

The SPAR model includes cross-connection capabilities from the other units' diesel

generators. However, the cutsets that include these basic events are very insignificant

in the analysis. Therefore, the analyst did not adjust Unit 1 and 2 EDG common cause

probabilities from the base case.

Internal Events Analysis

The Palo Verde SPAR model (Revision 3.21, October 28, 2005), modified as described

above, was used at a truncation of E-12.

Deterministic Assumption

Based on this assumption, the Train A EDG was guaranteed to fail to start on any

demand subsequent to the last successful run on September 4, 2006, but was likewise

guaranteed to succeed on any demand prior to this date. Therefore, the EDG was

assumed to be in a failed state for 18 days. The use of a "T/2" assumption is not valid

in this case because the normally open contact is assumed to be open following the

previous EDG run. This would cause the K1 unlatch coil to fail to energize for any

hypothetical demand during this period and result in failure of the EDG field flash.

Attachment 3

A3-5

In the SPAR model, the following changes were made:

EPS-DGN-FS-DGA was set to 1.0

The result in SAPHIRE is 1.047E-4/yr. A review of the cutsets revealed that several

included independent failures of Train A EDG to run as well as the test and maintenance

basic event. These cutsets were logically inconsistent:

Cutsets containing:

Value

EPS-DGN-FR-DGA

2.024E-6/yr.

EPS-DGN-TM-DGA

4.084E-7/yr.

Total

2.432E-6/yr.

Extracting these cutsets leaves a result of 1.047E-4 - 2.432E-6 = 1.023E-4/yr.

Therefore, for an 18-day exposure period, the delta-CDF of the finding is

1.023E-4yr.(18/365) = 5.0E-6/yr.

Common cause events were retained in the evaluation case in order to retain the entire

probability of failure of the Train B EDG.

Stochastic Assumption

Using this assumption, the Train A EDG was vulnerable to failure on any demand

following the installation of the new K1 relay on July 26, 2006. As discussed above, the

Train A EDG had a 0.25 probability of failing to start from a K1 relay failure in response

to any demand during the 58-day period of time between July 26, 2006, and

September 22, 2006.

In SPAR, the following changes were made:

EPS-DGN-FS-DGA was set to 0.25 + 5E-3 (base case probability) = 0.255

The result in SAPHIRE is 2.447E-5. For the 58-day exposure period, the resulting

delta-CDF is 2.447E-5 (58/365) = 3.9E-6/yr.

Combination Assumption

Using this assumption, the Train A EDG had a 0.25 probability of failing to start because

of a failed K1 relay for the first 40 days and a 1.0 probability of the same failure for the

final 18 days of the exposure period.

The result from the deterministic assumption is the same in this case. The exposure

time for the stochastic portion is set at 40 instead of 58 days. Using the results above,

the delta-CDF of the combination assumption is 5.0E-6/yr. + 40/58 (3.9.E-6/yr.) =

7.7E-6/yr.

Attachment 3

A3-6

External Events

Seismic

Palo Verde is located in a relatively stable seismic region for a plant located in the

Western USA. The Idaho National Laboratory conducted a study to predict the

frequency of a LOOP resulting from a seismic event at all US plants, as documented in

Frequency of Seismically-Induced LOOP events for SPAR models, Revision 1,

September 2005. The conclusion of this study was that the mean frequency for a

seismically-induced LOOP at Palo Verde is 5.37E-5/yr. The study concluded that the

failure of ceramic insulators would be the most likely failure mode inducing a LOOP.

For risk assessment purposes, a seismically-induced LOOP would have a recovery

profile similar to a severe weather event-induced LOOP. In SPAR (as modified above

for this analysis), the frequency of a weather-related LOOP (used for the internal events

assessment) is 3.83E-3/year. Therefore, the increase in LOOP frequency from seismic

events is not significant by itself as it relates to the risk of this finding.

The analyst also considered the possibility that an earthquake that results in a LOOP

could damage equipment (apart from the diesel generators) that could add non-

negligible risk to the finding. To address this issue, INL produced a document entitled,

Seismic Event Modeling and Seismic Risk Assessment Handbook, Revision 1,

September 2005. In particular, a LOOP resulting from an earthquake that also involved

loss of risk-significant equipment in Train B and/or loss of the gas turbine generators

could result in significant risk despite the low frequency of seismically-induced LOOPs.

Within this document, Table B-1, Generic SSC Seismic Fragilities, provides a list of

components along with the median g-force required to damage them. The following

table lists examples of the equipment of concern and the frequency of earthquakes at

Palo Verde that exceed the threshold value:

Component

High Confidence Low

Probability of Failure

Capacity (g)

Frequency of >g Earthquake

at Palo Verde

Electrical Equipment

(function during seismic

event)

0.34

1.0E-5/yr

Electrical Equipment

(function after seismic event)

0.77

1.0E-8/yr.

Battery Chargers/Inverters

0.54

1.0E-6/yr.

Batteries/Battery Racks

1.3

<9.3E-10/yr.

Diesel Generator/Support

Systems

1.06

<9.3E-10/yr.

Turbine-driven pumps

0.85

1.0E-9/yr.

Attachment 3

A3-7

Equipment success at g-forces well above the HCLPF value is possible. Based on

review of the information provided above and other information in the INL document, the

analyst concluded that earthquakes causing LOOPs and loss of other on-site equipment

would add risk small in comparison to the internal events result.

The analyst assumed (conservatively) that the gas turbine generators would be lost in a

seismic event that also causes a LOOP. To calculate the risk of the finding in light of

this assumption, the analyst ran two cases using the revised SPAR model. In both runs,

the frequency of LOOPs was set at 5.37E-5/year (frequency of seismic-induced

LOOPs), and nonrecoveries of offsite power for all relevant times (3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> and less as

well as 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />) were set to TRUE (there are no offsite recovery events within the E-12

truncation greater than 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> in the Palo Verde SPAR model except for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />;

therefore, this change set is equivalent to assuming that offsite power following an

earthquake is not recovered). Both gas turbine generator fail-to-start events were set to

TRUE and only LOOP sequences were quantified. In the first case, the EDGs are

assumed to be nominally reliable and available. This result was 1.362E-7/yr. In the

second case, EDG A is assigned a failure probability of 1.0 for the fail-to-start event.

The result was 2.747E-6/yr. The resulting CDF of the finding attributable to a seismic

event that debilitates the gas turbine generators is therefore (2.747E-6 -

1.362E-7)(18/365) = 1.3E-7/yr.

Based on disussions, the licensees PRA assigns a value of approximately 4E-7/yr

delta-CDF for seismic events for a 18-day exposure period.

Fire

The analyst reviewed the licensee's IPEEE for Severe Accident Vulnerabilities,

June 30, 1995, to determine the risk attributable to the finding resulting from internal

fires.

A fire in Room 5B (Train B ESF switchgear room) was considered to have the largest

potential risk to the finding. A fire in this room would possibly cause a loss of offsite

power to both ESF buses. In this case, with a failure of EDG A to start, a station

blackout situation would exist. In the IPEEE, the CDF result for a fire in the Train B ESF

switchgear room was 9.73E-6/yr. The fire ignition frequency for this room was

5.5E-3/yr.

The analyst determined that the IPEEE did not contain sufficient information to quantify

the risk attributable to fires pertaining to the performance deficiency. Therefore, the

analyst requested that the licensee use its fire PRA model for this purpose. The licensee

reported that their fire PRA calculates a delta-CDF of 3.716E-6/yr for EDG A being

nonfunctional versus the base case condition. For this case, the EDG failure was

assumed to be independent in nature, the same assumption used in the SPAR analysis.

For an 18-day exposure, this would result in a delta-CDF of 1.8E-7/yr.

Attachment 3

A3-8

As a comparison, the following table shows the differences in the treatment of Room 5B

between the IPEEE and the fire PRA.

Room 5B

IPEEE

Fire PRA

Fire Ignition Frequency

5.5E-3/yr.

4.16E-3/yr.

CDF

9.73E-6/yr.

1.17E-7/yr.

This example shows that the CCDP of a fire in this room decreased from 1.8E-3 in the

IPEEE to 2.8E-5 in the fire PRA. This difference is not surprising because the IPEEE

was basically a screening tool that assumed worst-case bounding conditions while the

fire PRA incorporated realistic, best-estimate approximations.

Internal Flooding/High Velocity Winds/Other External Events

The analyst concluded qualitatively that no other external events would add appreciably

to the risk of the finding. The licensee reported that the risk added from internal flooding

according to their model was in the E-8 range.

Combined Risk

Using the licensee analysis results for seismic and fire events, the following table

indicates the total estimated risk of the finding for each of the assumed failure

mechanisms:

Assumption

Internal

Events

Seismic

Fire

Total Risk

Deterministic

5.0E-6

4E-7/yr

1.3E-7/yr

5.5E-6/yr

Stochastic

3.9E-6

3E-7/yr1

1.0E-7/yr1

4.3E-6/yr

Combination

7.7E-6

6E-7/yr1

2.1E-7/yr1

8.5E-6/yr

1. Seismic and fire CDFs were adjusted for the stochastic and combination

assumptions.

Large Early Release Frequency

In accordance with IMC 0609, Appendix H, station blackout sequences, which

predominate the risk of the assessed condition, are not considered significant release

events for a large, dry containment. Therefore, large early release was considered

unimportant in this analysis.

Licensee Analysis

The analyst did not receive a detailed description of the licensees analysis, but was

informed verbally that the delta-CDF of the finding for internal events and fire, assuming

an 18-day exposure and no recovery of the Train A EDG, was approximately 1.6E-6/yr.

Attachment 3

A3-9

Adding the licensees approximate seismic risk, the overall result would be

approximately 2.0E-6/yr.

References

Palo Verde SPAR model (Revision 3.21, October 28, 2005)

NUREG/CR-6890, Reevaluation of Station Blackout Risk at Nuclear Power Plants,

Volume 1, Table D-1

Seismic Event Modeling and Seismic Risk Assessment Handbook, Revision 1,

September 2005

Palo Verde IPEEE for Severe Accident Vulnerabilities, June 30, 1995

Palo Verde Fire PRA Overview and Results, 13-NS-C072