{{#Wiki_filter:Enclosure 7 to ET 07-0022 Nutherm International Dedication Plan WCN-9715DP, Revision 1
{{#Wiki_filter:Enclosure 7 to ET 07-0022 Nutherm International Dedication Plan WCN-9715DP, Revision 1


DEDICATION PLAN WCN-9715DP, REV 1 PAGE I OF 24 NUTHERM DEDICATION PLAN FOR REPLACEMENT MSFIS SYSTEM WOLF CREEK NUCLEAR OPERATING CORPORATION PURCHASE ORDER NO. 734527 NUTHERM DOCUMENT NUMBER WCN-9715DP, REV. 1 Prepared By:                                         Date:
DEDICATION PLAN WCN-9715DP, REV 1 PAGE I OF 24 NUTHERM DEDICATION PLAN FOR REPLACEMENT MSFIS SYSTEM WOLF CREEK NUCLEAR OPERATING CORPORATION PURCHASE ORDER NO. 734527 NUTHERM DOCUMENT NUMBER WCN-9715DP, REV. 1 Prepared By:
                                                                      -7 Project Engineering Manager Reviewed and Approved By:                                         Date: ZZe-41-6 7 Wan
Date:
* e EQ Manager 501 South 11 th Street     PHONE: 618-244-6000
-7 Project Engineering Manager Reviewed and Approved By:
~Nuthrm                            Mt. Vernon IL 62864          FAX: 618-244-6641
Wan
* e Date:
EQ Manager ZZe-41-6 7
~Nuthrm 501 South 11 th Street Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 2 OF 24 REVISIONS The revision number is indicated at the top of each page, for all revisions. To delineate the exact location of a given revision, a vertical line is used on the right margin. However, for a complete report rewrite, no vertical lines are used.
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 2 OF 24 REVISIONS The revision number is indicated at the top of each page, for all revisions. To delineate the exact location of a given revision, a vertical line is used on the right margin. However, for a complete report rewrite, no vertical lines are used.
REVISION LOG REVISION       DATE       PAGE     SECTION                        REFERENCE 1       5/31/07     5-24     Dedication Description         Complete Rewrite 501 South 11 th'Street            PHONE: 618-244-6000 f*469,tophermýýv                             Mt. Vernon IL 62864                 FAX: 618-244-6641
REVISION LOG REVISION DATE PAGE 1
5/31/07 5-24 SECTION Dedication Description REFERENCE Complete Rewrite f*469,tophermýýv 501 South 11 th'Street Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-6641


DEDICATION PLAN WCN-971 5DP, REV I PAGE 3 OF 24 TABLE OF CONTENTS
DEDICATION PLAN WCN-971 5DP, REV I PAGE 3 OF 24 TABLE OF CONTENTS
.DESCRIPTION                                                                                                               PA(~
.DESCRIPTION PA(~
PURPOSE...........................................................................................................         4 APPLICABLE STANDARDS AND DOCUMENTS..........................................................                               4 DEVICE DESCRIPTION .........................................................................................               5 DEDICATION DESCRIPTION ..................................................................................                   5 GENERAL................................................................................................................ 5 MSFIS REPLACEMENT SYSTEM ...................................................................................               6 CRITICAL CHARACTERISTIC MATRIX....................................................................                     8 PHYSICAL CHARACTERISTICS ............................................................................                 18 PERFORMANCE................................................................................................           19 DEPENDABILITY..............................................................................................         20 VERIFICATION AND) VALIDATION .......................................................................                 22 501 South 11i0 Street                               PHONE: 618-244-6000 MLTERNAflOM            4 LWL 2                      Mt. Vernon IL 62864                                      FAX: 618-244-6641
PURPOSE...........................................................................................................
4 APPLICABLE STANDARDS AND DOCUMENTS..........................................................
4 DEVICE DESCRIPTION.........................................................................................
5 DEDICATION DESCRIPTION..................................................................................
5 GENERAL................................................................................................................
5 MSFIS REPLACEMENT SYSTEM...................................................................................
6 CRITICAL CHARACTERISTIC MATRIX....................................................................
8 PHYSICAL CHARACTERISTICS............................................................................
18 PERFORMANCE................................................................................................
19 DEPENDABILITY..............................................................................................
20 VERIFICATION AND) VALIDATION.......................................................................
22 MLTERNAflOM 4 LWL 2 501 South 11i0 Street Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-6641


DEDICATION PLAN WCN-971 5DP, REV I PAGE 4 OF 24 PURPOSE The purpose of this dedication plan is to present and define the critical characteristics and the applicable processes and standards which will be used to dedicate the commercial grade items described in the "Device Descriptions" section of this document.
DEDICATION PLAN WCN-971 5DP, REV I PAGE 4 OF 24 PURPOSE The purpose of this dedication plan is to present and define the critical characteristics and the applicable processes and standards which will be used to dedicate the commercial grade items described in the "Device Descriptions" section of this document.
This dedication plan addresses critical characteristics primarily. Additional testing and verification, beyond that required for dedication of the units described in the "Device Descriptions" section of this document, will be performed (as applicable) to ensure items purchased through Nuthermn International are the items described in the customers specification sheets and/or Purchase Order.
This dedication plan addresses critical characteristics primarily. Additional testing and verification, beyond that required for dedication of the units described in the "Device Descriptions" section of this document, will be performed (as applicable) to ensure items purchased through Nuthermn International are the items described in the customers specification sheets and/or Purchase Order.
All qualification work is accomplished in accordance with customer purchase order and specification requirements, Nuclear Regulatory Commission Guidelines, and applicable Institute of Electrical and Electronic Engineers Standards.
All qualification work is accomplished in accordance with customer purchase order and specification requirements, Nuclear Regulatory Commission Guidelines, and applicable Institute of Electrical and Electronic Engineers Standards.
APPLICABLE STANDARDS AND DOCUMENTS
APPLICABLE STANDARDS AND DOCUMENTS IEEE 344-1975 -"ýRecommended Practices for Seismic Qualification of Class 1 E Equipment for Nuclear Power Generating Stations."
* IEEE 344-1975 -"ýRecommended Practices for Seismic Qualification of Class 1E Equipment for Nuclear Power Generating Stations."
IEEE 323 -1974 - "Standard for Qualifying Class IlE Equipment for Nuclear Power Generating Stations" 0
* IEEE 323 -1974 - "Standard for Qualifying Class IlE Equipment for Nuclear Power Generating Stations" 0   1lOCFR5O, Appendix B. -"Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants"
1lOCFR5O, Appendix B. -"Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants" Nutherm. International, Inc. Quality Assurance Manual No.: QA-N-10179-5.
* Nutherm. International, Inc. Quality Assurance Manual No.: QA-N-10179-5.
EPRI NP-5652-"Guideline for the Utilization of Commercial Grade Items in Nuclear Safety Related Applications"
* EPRI NP-5652-"Guideline for the Utilization of Commercial Grade Items in Nuclear Safety Related Applications"
*EPRI TR-I02260-"Supplemental Guidance for the Application of EPRI NP-5652 on the Utilization of Commercial Grade Items" EPRI TR-1 02323-112-1997 - "Guidelines for Electromagnetic Interference Testing in Power Plants" Regulatory Guide 1. 180-RI -"Guidelines for Evaluating Electromagnetic and Radio-Frequency Interference in Safety-Related Instrumentation and Control Systems" IEEE 649-1991 - "Standard for Qualifying Class IlE Motor Control Centers for Nuclear Power Generating Stations" Wolf Creek Generating Station Specification J-1 OSA(Q), Rev. 2 501 South 11 tli Street PHONE: 618-244-6000 INTRNAIONL, NC.Mt.
      *EPRI TR- I02260-"Supplemental Guidance for the Application of EPRI NP-5652 on the Utilization of Commercial Grade Items"
Vernon IL 62864 FAX: 618-244-6641
* EPRI TR- 102323-112- 1997 - "Guidelines for Electromagnetic Interference Testing in Power Plants"
* Regulatory Guide 1.180-RI -"Guidelines for Evaluating Electromagnetic and Radio-Frequency Interference in Safety-Related Instrumentation and Control Systems"
* IEEE 649-1991 - "Standard for Qualifying Class IlE Motor Control Centers for Nuclear Power Generating Stations"
    "    Wolf Creek Generating Station Specification J-1OSA(Q), Rev. 2 501 South 11 tli Street           PHONE: 618-244-6000 INTRNAIONL, NC.Mt.         Vernon IL 62864                 FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV I PAGE 5 OF 24
DEDICATION PLAN WCN-9715DP, REV I PAGE 5 OF 24
      *EPRI TR- 106439 - "Guideline on Evaluation and Acceptance of Commercial Grade Digital Equipment of Nuclear Safety Applications" DEVICE DESCRIPTION The Main Steam and Feedwater Isolation System (MSFIS) has two distinct functions:
*EPRI TR-106439 - "Guideline on Evaluation and Acceptance of Commercial Grade Digital Equipment of Nuclear Safety Applications" DEVICE DESCRIPTION The Main Steam and Feedwater Isolation System (MSFIS) has two distinct functions:
* Steam Line Isolation System (SLIS) - Main Steam Line Isolation minimizes the uncontrolled cool down of the Reactor Coolant System (RCS) that would result from a main steam line rupture. Input signals pass from the detectors through the Solid State Protection System (SSPS) to the MSFIS cabinet where the output signal is generated.
* Steam Line Isolation System (SLIS) - Main Steam Line Isolation minimizes the uncontrolled cool down of the Reactor Coolant System (RCS) that would result from a main steam line rupture. Input signals pass from the detectors through the Solid State Protection System (SSPS) to the MSFIS cabinet where the output signal is generated.
        " Feedwater Isolation System (EWIS) - Feedwater isolation minimizes the potential for excessive post-trip cool down of the RCS due to overfilling the steam generators. It also prevents moisture carryover caused by high steam generator levels, and isolates normal Feedwater in the event of a high Energy Line Break inside containment.
" Feedwater Isolation System (EWIS) - Feedwater isolation minimizes the potential for excessive post-trip cool down of the RCS due to overfilling the steam generators. It also prevents moisture carryover caused by high steam generator levels, and isolates normal Feedwater in the event of a high Energy Line Break inside containment.
MSFIS will include a safety-related logic-controller-based system to performn the control functions of the Main Steam Isolation Valves (MSIVs) and Main Feedwater Isolation Valves (MFIVs) with system-medium actuators. The MSFIS System has two redundant subsystems located in separate cabinets:
MSFIS will include a safety-related logic-controller-based system to performn the control functions of the Main Steam Isolation Valves (MSIVs) and Main Feedwater Isolation Valves (MFIVs) with system-medium actuators. The MSFIS System has two redundant subsystems located in separate cabinets:
MSFIS Channel 1(1) located in MSFIS Cabinet SA075A (Train A)
MSFIS Channel 1 (1) located in MSFIS Cabinet SA075A (Train A)
MSFIS Channel IV (4) located in MSFIS Cabinet SA075B (Train B)
MSFIS Channel IV (4) located in MSFIS Cabinet SA075B (Train B)
Each MSFIS cabinet is capable of supplying the control logic outputs required for operating each of the 4 Main Steam Isolation Valves and 4 Main Feedwater Isolation Valves.
Each MSFIS cabinet is capable of supplying the control logic outputs required for operating each of the 4 Main Steam Isolation Valves and 4 Main Feedwater Isolation Valves.
Dedication activities will be performed by Nutherm International Inc. on the control system ALS Racks and Assembly Panels for Channels I and IV.
Dedication activities will be performed by Nutherm International Inc. on the control system ALS Racks and Assembly Panels for Channels I and IV.
DEDICATION DESCRIPTION GENERAL The dedication process, per EPRI Report 5652, assumes that "the design requirements of the item have been satisfactorily translated into specification requirements as reflected in the procurement document." The guideline goes on to describe three fundamental issues which, once addressed, provide a foundation for the acceptance process of a particular item. The three fundamental issues as described in EPRI Report 5652 are as follows:
DEDICATION DESCRIPTION GENERAL The dedication process, per EPRI Report 5652, assumes that "the design requirements of the item have been satisfactorily translated into specification requirements as reflected in the procurement document." The guideline goes on to describe three fundamental issues which, once addressed, provide a foundation for the acceptance process of a particular item. The three fundamental issues as described in EPRI Report 5652 are as follows:
501 South I Ph Street             PHONE: 618-244-6000 INTRNAIONL, NC.Mt.       Vernon IL 62864                 FAX: 618-244-6641
501 South I Ph Street PHONE: 618-244-6000 INTRNAIONL, NC.Mt.
Vernon IL 62864 FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 6 OF 24
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 6 OF 24
      " Determine the safety function of the item
" Determine the safety function of the item
* Confirm the item is commercial grade
* Confirm the item is commercial grade
* Identify critical characteristics.
* Identify critical characteristics.
These three fundamental issues are addressed during the technical review process and a Component Dedication Planner (CDP) is generated for each item to be dedicated. In the case of more complex systems such as the MSFIS system a Critical Characteristic Matrix is used to quantify Critical Characteristics and the Verification methods used. The Critical Characteristic Matrix for the replacement MSFIS system has been incorporated into this Dedication Plan.
These three fundamental issues are addressed during the technical review process and a Component Dedication Planner (CDP) is generated for each item to be dedicated. In the case of more complex systems such as the MSFIS system a Critical Characteristic Matrix is used to quantify Critical Characteristics and the Verification methods used. The Critical Characteristic Matrix for the replacement MSFIS system has been incorporated into this Dedication Plan.
EPRI NP-5 652 is used as a guideline for the dedication process of commercial grade items. As stated in section 1.3.4, 'the methods in the guideline are in conformance with existing regulatory requirements. The methods for accepting commercial grade items are consistent with the provisions of Criterion VII of Appendix B to I OCFR50 which states:
EPRI NP-5 652 is used as a guideline for the dedication process of commercial grade items. As stated in section 1.3.4, 'the methods in the guideline are in conformance with existing regulatory requirements. The methods for accepting commercial grade items are consistent with the provisions of Criterion VII of Appendix B to I OCFR50 which states:
            "Measures shall be established to assure that purchased material, equipment, and services, whether purchased. directly or through contractors and subcontractors, conform to the procurement documents.
"Measures shall be established to assure that purchased material, equipment, and services, whether purchased. directly or through contractors and subcontractors, conform to the procurement documents.
These measures shall include provisions, as appropriate, for source evaluation and selection, objective evidence of quality fturnished by the contractor or subcontractor, inspection at the contractor or subcontractor, inspection at the contractor or subcontractor source, and examination of products upon delivery."
These measures shall include provisions, as appropriate, for source evaluation and selection, objective evidence of quality fturnished by the contractor or subcontractor, inspection at the contractor or subcontractor, inspection at the contractor or subcontractor source, and examination of products upon delivery."
Nutherm International has incorporated the guideline into its QA program and in-place procedures for the dedication of commercial grade items. See Figure 1 for a block diagram of the generic dedication process. The methods referred to (Method 1 thru 4) are described in detail in EPRI NP-5652. Nutherm International employs a combination of method 1 and other acceptance methods. Figure 2 is a schematic logic diagram for employing method 1, taken from EPRI NP-S 652. Though not all inclusive, the diagram provides a general feel for the dedication process using this method.
Nutherm International has incorporated the guideline into its QA program and in-place procedures for the dedication of commercial grade items. See Figure 1 for a block diagram of the generic dedication process. The methods referred to (Method 1 thru 4) are described in detail in EPRI NP-5652. Nutherm International employs a combination of method 1 and other acceptance methods. Figure 2 is a schematic logic diagram for employing method 1, taken from EPRI NP-S 652. Though not all inclusive, the diagram provides a general feel for the dedication process using this method.
MSFIS REPLACEMENT SYSTEM The critical characteristics are divided into three general categories; Product Information, Physical Attributes, and Performance. EPRI TR-106439 incorporated Product Information in the Physical Attributes categories and added Dependability. Though the MSFIS system is not software based, many of the critical characteristics and dedication activities described in EPRI TR- 106439 are applicable and have been incorporated into this Dedication Plan. The critical characteristics of this system are varied enough that all four acceptance methods will be used to verify acceptability. For newer, more complex systems this is not unusual. System and other experts will be used, as applicable, to provide any necessary technical expertise throughout the dedication process. 1IOCFR21 states:
MSFIS REPLACEMENT SYSTEM The critical characteristics are divided into three general categories; Product Information, Physical Attributes, and Performance. EPRI TR-106439 incorporated Product Information in the Physical Attributes categories and added Dependability. Though the MSFIS system is not software based, many of the critical characteristics and dedication activities described in EPRI TR-106439 are applicable and have been incorporated into this Dedication Plan. The critical characteristics of this system are varied enough that all four acceptance methods will be used to verify acceptability. For newer, more complex systems this is not unusual. System and other experts will be used, as applicable, to provide any necessary technical expertise throughout the dedication process. 1IOCFR21 states:
501 South 11th Street               PHONE: 618-244-6000 INTERNTIONA,     INC           Mt. Vernon IL 62864                     FAX: 618-244-6641
501 South 1 1th Street PHONE: 618-244-6000 INTERNTIONA, INC Mt. Vernon IL 62864 FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 7 OF 24 "dedication is an acceptance process undertaken to provide reasonable assurance that a commercial grade item to be used as a basic component will perform its intended safety function and, in this respect, is deemed equivalent to an item designed and manufactured under a 10 CFR Part 50, appendix B, quality assurance program. This assurance is achieved by identifying the critical characteristics of the item and verifying their acceptability by inspections, tests, or analyses" As previously stated, a Critical Characteristics Matrix was developed as part of the dedication process. This matrix lists each Critical Characteristic along with its Acceptance Criteria. For each characteristic the matrix also lists the Validation Document(s) and Validation Method(s) which will be used in the dedication process.
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 7 OF 24 "dedication is an acceptance process undertaken to provide reasonable assurance that a commercial grade item to be used as a basic component will perform its intended safety function and, in this respect, is deemed equivalent to an item designed and manufactured under a 10 CFR Part 50, appendix B, quality assurance program. This assurance is achieved by identifying the critical characteristics of the item and verifying their acceptability by inspections, tests, or analyses" As previously stated, a Critical Characteristics Matrix was developed as part of the dedication process. This matrix lists each Critical Characteristic along with its Acceptance Criteria. For each characteristic the matrix also lists the Validation Document(s) and Validation Method(s) which will be used in the dedication process.
Following the matrix a more detailed explanation of each characteristic category and applicable characteristics is included. EPRI TR- 106439, 1996, "Guideline on Evaluation and Acceptance of Commercial Grade Digital Equipment for Nuclear Safety Applications", section 4.2 "Guidance on Defining and Verifying Critical Characteristics",
Following the matrix a more detailed explanation of each characteristic category and applicable characteristics is included. EPRI TR-106439, 1996, "Guideline on Evaluation and Acceptance of Commercial Grade Digital Equipment for Nuclear Safety Applications", section 4.2 "Guidance on Defining and Verifying Critical Characteristics",
states:
states:
            "Translation of design requirements into critical characteristics for a commercial grade item is a key element in the dedication process. It is the link between the technical evaluation, which defines requirements, including hardware, software, human-machine interface, quality and reliability requirements, is an important prerequisite for dedication of a commercial grade item."
"Translation of design requirements into critical characteristics for a commercial grade item is a key element in the dedication process. It is the link between the technical evaluation, which defines requirements, including hardware, software, human-machine interface, quality and reliability requirements, is an important prerequisite for dedication of a commercial grade item."
A thorough review of Wolf Creek Generating Station Specification J-1 05A(Q), was performed to generate the Critical Characteristics Matrix, with Acceptance Criteria directly linked to Specification requirements, as applicable.
A thorough review of Wolf Creek Generating Station Specification J-1 05A(Q), was performed to generate the Critical Characteristics Matrix, with Acceptance Criteria directly linked to Specification requirements, as applicable.
501 South 11 th Street               PHONE: 618-244-6000 JWE          KqwV Mt. Vernon IL 62864                      .FAX: 618-244-6641
JWE KqwV 501 South 11 th Street Mt. Vernon IL 62864 PHONE: 618-244-6000
.FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV I PAGE 8 OF 24 CRITICAL CHARACTERISTIC MATRIX CRITICAL               ACCEPTANCE CRITERIA                         VALIDATION           VALIDATION CHARACTERISTICS                                                             DOCUMENT                 METHOD Physical Characteristics:
DEDICATION PLAN WCN-9715DP, REV I PAGE 8 OF 24 CRITICAL CHARACTERISTIC MATRIX CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Physical Characteristics:
Configuration-Model Number             Manufacturer Model No.                         Nutherm Quality     Visual Inspection Assurance Procedure QAP 7.1.00 FPGA Flash Version       Manufacturer FPGA Flash                       Nutherm             Visual Inspection Revision Number           Version Revision No.                           Procedure, ALS Rack Component Verification,
Configuration-Model Number Manufacturer Model No.
_______________________TPS-9062,             Rev. 0   ________
Nutherm Quality Visual Inspection Assurance Procedure QAP 7.1.00 FPGA Flash Version Manufacturer FPGA Flash Nutherm Visual Inspection Revision Number Version Revision No.
Quality of               Quality equivalent to qualified               NTL-NQI             Visual Inspection Workmanship               unit                                           Comparison, Nutherm Form 58050-13-7, Nutherm Procedure, ALS Rack Component Verification, TPS-9062, Rev. 0 General Configuration     Enclosure same as qualified unit               NTL-NQI             Visual Inspection Comparison, Nutherm. Form 58050-13-7 Nuthermn Dedication Plan,
Procedure, ALS Rack Component Verification,
___________ _________________WCN-971                                 5DP Mounting                 Mounting same as qualified unit               Nutherm             Visual Inspection Qualification Report WCN-9715R           ______
_______________________TPS-9062, Rev. 0 Quality of Quality equivalent to qualified NTL-NQI Visual Inspection Workmanship unit Comparison, Nutherm Form 58050-13-7, Nutherm Procedure, ALS Rack Component Verification, TPS-9062, Rev. 0 General Configuration Enclosure same as qualified unit NTL-NQI Visual Inspection Comparison, Nutherm. Form 58050-13-7 Nuthermn Dedication Plan,
501 South 11th Stree~t             PHONE: 618-244-6000
_________________WCN-971 5DP Mounting Mounting same as qualified unit Nutherm Visual Inspection Qualification Report WCN-9715R  
~Nather                                            Mt. Vernon IL 628 .64                .FAX: 618-244-6641
~Nather 501 South 11 th Stree~t Mt. Vernon IL 628.64 PHONE: 618-244-6000
.FAX:
618-244-6641


DEDICATION PLAN WCN-9715DP, REV I PAGE 9 OF 24 CRITICAL                     ACCEPTANCE CRITERIA                 VALIDATION           VALIDATION CHARACTERISTICS                                                       DOCUMENT               METHOD Component                       Components same as qualified         NTL-NQI           Visual Inspection Configuration                   unit                                 Comparison, Nutherm Form 58050-13-7 Nutherm Dedication Plan,
DEDICATION PLAN WCN-9715DP, REV I PAGE 9 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Component Components same as qualified NTL-NQI Visual Inspection Configuration unit Comparison, Nutherm Form 58050-13-7 Nutherm Dedication Plan,
_____________WCN-97                                           15DP Subcomponent                   Subcomponents same as qualified NTL-NQI                 Visual Inspection Configuration                   unit                                 Comparison, Nutherm. Form 58050-13-7 Nutherm Dedication Plan, WCN-9715DP Interfaces Power                           125 Vdc                             Nutherin           Direct Test and Dedication Plan,     Inspection WCN-971 5DP, Nuthenn Test Procedure TPS-9064 MSFIS Final
_____________WCN-97 15DP Subcomponent Subcomponents same as qualified NTL-NQI Visual Inspection Configuration unit Comparison, Nutherm. Form 58050-13-7 Nutherm Dedication Plan, WCN-9715DP Interfaces Power 125 Vdc Nutherin Direct Test and Dedication Plan, Inspection WCN-971 5DP, Nuthenn Test Procedure TPS-9064 MSFIS Final
________________ ________________________Acceptance Test Point to Point                 Wiring matches wiring diagram       Nuthermn           Direct Test and Continuity Check and                                                 Procedure,         Inspection Wiring Verification                                                   CI1..30_________
________________ ________________________Acceptance Test Point to Point Wiring matches wiring diagram Nuthermn Direct Test and Continuity Check and Procedure, Inspection Wiring Verification CI1..30_________
Proper                         Switches operate smoothly, see       Nutherm. Test       Direct Test and Bypass/Operate switch Functional section for operational Procedure                       Inspection operation                       tests and Acceptance Criteria       TPS-9064 MSFIS Final Acceptance Test   _________
Proper Switches operate smoothly, see Nutherm. Test Direct Test and Bypass/Operate switch Functional section for operational Procedure Inspection operation tests and Acceptance Criteria TPS-9064 MSFIS Final Acceptance Test Performance Characteristics:
Performance Characteristics:
Functional 125 Vdc outputs to Wolf Creek Specification J-105A, Nutherm. Test Direct Test and control solenoids to Section 5.2.1 a, b, e Procedure Inspection operate valves, verify TPS-9064 output logic MSFIS Final Acceptance Test iNthrmlxwj~
Functional 125 Vdc outputs to             Wolf Creek Specification J-105A,     Nutherm. Test       Direct Test and control solenoids to           Section 5.2.1 a, b, e               Procedure           Inspection operate valves, verify                                               TPS-9064 output logic                                                         MSFIS Final Acceptance Test 501 South 11'hStreet           PHONE: 618-244-6000 iNthrmlxwj~                                      .Mt. Vernon IL 62864                FAX: 618-244-6641
501 South 1 1'hStreet
.Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV I PAGE 10 OF 24 CRITICAL                       ACCEPTANCE CRITERIA               VALIDATION           VALIDATION CHARACTERISTICS                                                         DOCUMENT                 METHOD Interchangeability of           Wolf Creek.Specification J-105A, Nutherm. Test           Direct Test and components/modules               Section 5.2.2                         Procedure         Inspection TPS-9064 MSFIS Final Acceptance Test Hot swap capability             Wolf Creek Specification*J-lIO0A,     Nutherm Test       Direct Test and Section 5.2.2                         Procedure         Inspection TPS -9064 MSFIS Final
DEDICATION PLAN WCN-9715DP, REV I PAGE 10 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Interchangeability of Wolf Creek.Specification J-105A, Nutherm. Test Direct Test and components/modules Section 5.2.2 Procedure Inspection TPS-9064 MSFIS Final Acceptance Test Hot swap capability Wolf Creek Specification* J-l IO0A, Nutherm Test Direct Test and Section 5.2.2 Procedure Inspection TPS -9064 MSFIS Final
__________________Acceptance                                     Test Hot swap will not               Wolf Creek Specification J-105A,     Nuthermi Test     Direct Test and cause plant transient           Section 5.2.2                         Procedure         Inspection TPS-9064 MSFIS Final
__________________Acceptance Test Hot swap will not Wolf Creek Specification J-1 05A, Nuthermi Test Direct Test and cause plant transient Section 5.2.2 Procedure Inspection TPS-9064 MSFIS Final
_________________Acceptance                                       Test Response <1 00 ins               Wolf Creek Specification J-105A,     Nutherm Test       Direct Test and from input step change           Section 5.2.3                         Procedure           Inspection to output response                                                     TPS-9064 MSFIS Final
_________________Acceptance Test Response <1 00 ins Wolf Creek Specification J-105A, Nutherm Test Direct Test and from input step change Section 5.2.3 Procedure Inspection to output response TPS-9064 MSFIS Final
__________________Acceptance                                       Test Momentary input                 Wolf Creek Specification J-1I05A,     Nutherm. Test       Direct Test and signal, >100 ms will             Section 5.2.4.a 2)                   Procedure           Inspection cause system response                                                 TPS-9064 MSFIS Final
__________________Acceptance Test Momentary input Wolf Creek Specification J-1I05A, Nutherm. Test Direct Test and signal, >100 ms will Section 5.2.4.a 2)
_________________Acceptance                                       Test ESFAS contacts NC,               Wolf Creek Specification J-1I05A     Nutherm, Test       Direct Test and open for response. All           Section 5.2.4.a 3)                   Procedure           Inspection other inputs NO, close                                                 TPS-9064 for response                                                           MSFIS Final Acceptance Test   _________
Procedure Inspection cause system response TPS-9064 MSFIS Final
Output signals:                 Wolf Creek Specification J-105A      Nutherm Test       Direct Test and voltage and current             Section 5.2.4.c 1)                   Procedure           Inspection capability, system                                                     TPS-9064 capable of sourcing                                                   MSFIS Final adequate current at                                                   Acceptance Test min and max voltage 501 South 1IthiiStreet           PHONE: 618-244-6000
_________________Acceptance Test ESFAS contacts NC, Wolf Creek Specification J-1I05A Nutherm, Test Direct Test and open for response. All Section 5.2.4.a 3)
~NL'7thqerm                                      Mt. Vernon IL 62864                  FAX: 618-244-76641
Procedure Inspection other inputs NO, close TPS-9064 for response MSFIS Final Acceptance Test Output signals:
Wolf Creek Specification J-1 05A Nutherm Test Direct Test and voltage and current Section 5.2.4.c 1)
Procedure Inspection capability, system TPS-9064 capable of sourcing MSFIS Final adequate current at Acceptance Test min and max voltage
~NL'7thqerm 501 South 1IthiiStreet Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-76641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 11 OF 24 CRITICAL               ACCEPTANCE CRITERIA                 VALIDATION           VALIDATION CHARACTERISTICS         ____            _______                  DOCUMIENT             METHOD Output signal:           Wolf Creek Specification J-105A         Nutherm Test       Direct Test and switching 40-60 Henry Section 5.2.4.c 1)                         Procedure           inspection loads at 1.28A                                                   TPS-9064 nominal                                                         MSFIS Final Acceptance Test Status outputs:         Wolf Creek Specification J-1I05A       Nutherm Test       Direct Test and Outputs per Appendix     Section 5.2.4.c 2)                     Procedure           Inspection B                                                               TPS-9064 Output at 125 Vdc if                                             MSFIS Final
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 11 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMIENT METHOD Output signal:
[supply fuses for                                               Acceptance Test MV5(6) sat] & [no test in system logic]
Wolf Creek Specification J-105A Nutherm Test Direct Test and switching 40-60 Henry Section 5.2.4.c 1)
Procedure inspection loads at 1.28A TPS-9064 nominal MSFIS Final Acceptance Test Status outputs:
Wolf Creek Specification J-1I05A Nutherm Test Direct Test and Outputs per Appendix Section 5.2.4.c 2)
Procedure Inspection B
TPS-9064 Output at 125 Vdc if MSFIS Final
[supply fuses for Acceptance Test MV5(6) sat] & [no test in system logic]
Output to status panel capable of 125 Vdc,
Output to status panel capable of 125 Vdc,
  <25 mA load Output states: table for Wolf Creek Specification J-105SA       Nutherm Test         Direct Test and each condition           Section 5.2.5.a 1)                     Procedure           Inspection TPS-9064 MSFIS Final Acceptance Test Four Commands:           Wolf Creek Specification J-1I05A       Nutherm Test         Direct Test and All Close; Close         Section 5.2.5.a 2)                     Procedure           Inspection output state for 60 sec,                                         TPS-9064 all 4 valves, then Keep                                           MSFIS Final Closed                                                           Acceptance Test ESFAS; 2 of 4, same output as All Close Close; Close output state for associated valve, 60 sec delay then Keep Close Open; open output state for associated valve ffq'7,ftJNuther                           50 1 South 11 thiStreet
<25 mA load Output states: table for Wolf Creek Specification J-105SA Nutherm Test Direct Test and each condition Section 5.2.5.a 1)
                                          .Mt. Vernon IL 62864 PHONE: 618-244-6000 1FAX: '618-244-6641
Procedure Inspection TPS-9064 MSFIS Final Acceptance Test Four Commands:
Wolf Creek Specification J-1I05A Nutherm Test Direct Test and All Close; Close Section 5.2.5.a 2)
Procedure Inspection output state for 60 sec, TPS-9064 all 4 valves, then Keep MSFIS Final Closed Acceptance Test ESFAS; 2 of 4, same output as All Close Close; Close output state for associated valve, 60 sec delay then Keep Close Open; open output state for associated valve ffq'7,ftJNuther 50 1 South 11 thiStreet
.Mt. Vernon I L 62864 PHONE: 618-244-6000 1FAX: '618-244-6641


DEDICATION PLAN WCN-9715DP, REV I PAGE 12 OF 24 CRITICAL             ACCEPTANCE CRITERIA                   VALIDATION         VALIDATION CHARACTERISTICS                                                   DOCUMENT             METHOD Command priorities in Wolf Creek Specification J-105A           Nutherm Test     Direct Test and OPERARE: All Close, Section 5.2.5.b 1)                         Procedure         Inspection ESFAS, Close same                                               TPS-9064 priority, Open ignored                                         MSFIS Final while above and time                                           Acceptance Test delay not timed out   _______________
DEDICATION PLAN WCN-9715DP, REV I PAGE 12 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Command priorities in Wolf Creek Specification J-105A Nutherm Test Direct Test and OPERARE: All Close, Section 5.2.5.b 1)
Command priorities in Wolf Creek Specification J-105A         Nutherm Test     Direct Test and BYPASS: All Close,     Section 5.2.5.b 2)                       Procedure         Inspection Close, ESFAS, Open                                             TPS-9064 do not cause state                                             MSFIS Final change while in                                                 Acceptance Test
Procedure Inspection ESFAS, Close same TPS-9064 priority, Open ignored MSFIS Final while above and time Acceptance Test delay not timed out Command priorities in Wolf Creek Specification J-105A Nutherm Test Direct Test and BYPASS: All Close, Section 5.2.5.b 2)
: BYPASS, BYPASS/OPERATE         Wolf Creek Specification J-105A         Nutherm Test     Direct Test and mode selection:         Section 5.2.6.a 1)                       Procedure         inspection Independent selection                                           TPS-9064 for each valve                                                   MSFIS Final Acceptance Test Positive action to switch modes In BYPASS no output state change Output state Close, time delay not timed out, will not go to BYPASS Indicating light for   Wolf Creek Specification J-1I05A         Nutherm Test       Direct Test and BYPASS                 Section 5.2.6.a 2)                       Procedure         Inspection TPS-9064 MSFIS Final Acceptance Test 501 South 11'h Street           .PHONE: 618-244-6000
Procedure Inspection Close, ESFAS, Open TPS-9064 do not cause state MSFIS Final change while in Acceptance Test
  .          NTRNATONA, q'NC.v                    Mt. Vernon IL 62864                FAX: 618-244-6641
: BYPASS, BYPASS/OPERATE Wolf Creek Specification J-105A Nutherm Test Direct Test and mode selection:
Section 5.2.6.a 1)
Procedure inspection Independent selection TPS-9064 for each valve MSFIS Final Acceptance Test Positive action to switch modes In BYPASS no output state change Output state Close, time delay not timed out, will not go to BYPASS Indicating light for Wolf Creek Specification J-1I05A Nutherm Test Direct Test and BYPASS Section 5.2.6.a 2)
Procedure Inspection TPS-9064 MSFIS Final Acceptance Test NTRNATONA, q'NC.v 501 South 1 1'h Street Mt. Vernon IL 62864
.PHONE: 618-244-6000 FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 13 OF 24 CRITICAL           ACCEPTANCE CRITERIA                 VALIDATION         VALIDATION CHARACTERISTICS                                               DOCUMENT             METHOD BYPASS initiation       Wolf Creek Specification J- 105A    Nutherm Test       Direct Test and a) Latch outputs       Section 5.2.6.a 3)                 Procedure         Inspection b) De-energize status                                       TPS-9064 output                                                     MSFIS Final c) Light BYPASS                                             Acceptance Test mode indication d) Close test contacts described in 5.2.6 Return to OPERATE;     Wolf Creek Specification J-1I05A   Nutherm Test       Direct Test and open test contacts,     Section 5.2.6 .a 4)                 Procedure         Inspection unlatch outputs,                                           TPS-9064 extinguish BYPASS                                           MSFIS Final indication, release                                         Acceptance Test status output MSFIS power supplies   Wolf Creek Specification J-I05A    Nutherm Test       Direct Test and will operate on 140-   Section 5.6.3.a                     Procedure           Inspection 105 Vdc input power                                         TPS-9064.
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 13 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD BYPASS initiation Wolf Creek Specification J-1 05A Nutherm Test Direct Test and a) Latch outputs Section 5.2.6.a 3)
Procedure Inspection b) De-energize status TPS-9064 output MSFIS Final c) Light BYPASS Acceptance Test mode indication d) Close test contacts described in 5.2.6 Return to OPERATE; Wolf Creek Specification J-1I05A Nutherm Test Direct Test and open test contacts, Section 5.2.6.a 4)
Procedure Inspection unlatch outputs, TPS-9064 extinguish BYPASS MSFIS Final indication, release Acceptance Test status output MSFIS power supplies Wolf Creek Specification J-I 05A Nutherm Test Direct Test and will operate on 140-Section 5.6.3.a Procedure Inspection 105 Vdc input power TPS-9064.
MSFIS Final
MSFIS Final
________________________Accept ne Test 105-140 Vdc power       Wolf Creek Specification J-I05A Nutherm Test           Direct Test and supplies, can source   Section 5.6.3.b                     Procedure           Inspection sufficient current for                                     TPS-9064 loads                                                       MSFIS Final Acceptance Test Hot swap replacement, two redundant power supplies per rack, one can carry the load Load sharing capability Trouble alarm on loss of a power supply, low "health" Proper operation in all Wolf Creek Specification J-105SA   Nutherm Test       Direct Test and power supply           Section 5.6.3.d                     Procedure           Inspection configurations w/o,                                         TPS-9064 spurious trips or loss                                     MSFIS Final of control                                                 Acceptance Test j~Nutherm                               501 South 11tStreet Mt. Vernon IL 62864
________________________Accept ne Test 105-140 Vdc power Wolf Creek Specification J-I 05A Nutherm Test Direct Test and supplies, can source Section 5.6.3.b Procedure Inspection sufficient current for TPS-9064 loads MSFIS Final Acceptance Test Hot swap replacement, two redundant power supplies per rack, one can carry the load Load sharing capability Trouble alarm on loss of a power supply, low "health" Proper operation in all Wolf Creek Specification J-105SA Nutherm Test Direct Test and power supply Section 5.6.3.d Procedure Inspection configurations w/o, TPS-9064 spurious trips or loss MSFIS Final of control Acceptance Test j~Nutherm 501 South 1 1 tStreet Mt. Vernon IL 62864
                                                                        .PHONE: 618-244-6000 FAX: 618-244-6641
.PHONE: 618-244-6000 FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 14 OF 24 CRITICAL                   ACCEPTANCE CRITERIA                   VALIDATION             VALIDATION CHARACTERISTICS                                                           DOCUMENT                 METHOD Provide wiring harness           Wolf Creek Specification J-105A       Nuthermn Test         Direct Test and Section 5.6.4                         Procedure             Inspection TPS-9064 MSFIS Final Acceptance Test, Point to point continuity check and wiring verification QCI 10.3.30 Summary trouble                   Wolf Creek Specification J-1I05A       Nutherm Test           Direct Test and alarm, NO contact,               Section 5.6.7.a                       Procedure             Inspection open to alarm                                                           TPS-9064 MSFIS Final Acceptance Test Alarm conditions                 Wolf Creek Specification J-l1 05A     Nutherm Test           Direct Test and
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 14 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Provide wiring harness Wolf Creek Specification J-105A Nuthermn Test Direct Test and Section 5.6.4 Procedure Inspection TPS-9064 MSFIS Final Acceptance Test, Point to point continuity check and wiring verification QCI 10.3.30 Summary trouble Wolf Creek Specification J-1I05A Nutherm Test Direct Test and alarm, NO contact, Section 5.6.7.a Procedure Inspection open to alarm TPS-9064 MSFIS Final Acceptance Test Alarm conditions Wolf Creek Specification J-l1 05A Nutherm Test Direct Test and
: 1. loss DC pwr supply           Section 5.6.7.b                       Procedure             Inspection
: 1. loss DC pwr supply Section 5.6.7.b Procedure Inspection
: 2. card removed                                                         TPS-9064
: 2. card removed TPS-9064
: 3. external test equip                                                   MSFIS Final installed                                                               Acceptance Test
: 3. external test equip MSFIS Final installed Acceptance Test
: 4. output sequence incomplete_________________________
: 4. output sequence incomplete_________________________
Indication of trouble             Wolf Creek Specification J-105A       Nutherm Test           Direct Test and alarm cause                       Section 5.6.7.c                       Procedure             Inspection TPS-9064 MSFIS Final Acceptance Test Dielectric test on wire           Wolf Creek Specification J- 105A      Nutherm. Test         Direct Test and Section 10.3.2                         Procedure             Inspection TPS -9064 MSFIS Final Acceptance Test Apply all possible               Wolf Creek Specification J-I05A        Nutherm Test           Direct Test and input combinations in             Section 10.4.3                         Procedure             Inspection all states                                                               TPS-9064 MSFIS Final
Indication of trouble Wolf Creek Specification J-105A Nutherm Test Direct Test and alarm cause Section 5.6.7.c Procedure Inspection TPS-9064 MSFIS Final Acceptance Test Dielectric test on wire Wolf Creek Specification J-1 05A Nutherm. Test Direct Test and Section 10.3.2 Procedure Inspection TPS -9064 MSFIS Final Acceptance Test Apply all possible Wolf Creek Specification J-I 05A Nutherm Test Direct Test and input combinations in Section 10.4.3 Procedure Inspection all states TPS-9064 MSFIS Final
________________________________________Acceptance Test 501 South 11 t' Street              .PHONE: 618-244-6000 wTigN,                         INC.&#xfd;T       Mt. Vernon IL 62864                   .FAX: 618-244-6641
________________ ________________________Acceptance Test
: wTigN, INC.&#xfd;T 501 South 11 t' Street Mt. Vernon IL 62864
.PHONE: 618-244-6000
.FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 15 OF 24 CRITICAL                           ACCEPTANCE CRITERIA                     VALIDATION           VALIDATION CHARACTERISTICS                     ____________                                DOCUMENT               METHOD Apply manual inputs                   Wolf Creek Specification J- I05A         Nutherm Test         Direct Test and Section 10.4.4                           Procedure             Inspection TPS-9064 MSFIS Final Accepane Test Reset                                 Demonstrate the Ability to Reset         Nuthenn Test         Direct Test and Procedure             Inspection TPS-9064 MSFIS Final
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 15 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Apply manual inputs Wolf Creek Specification J-I05A Nutherm Test Direct Test and Section 10.4.4 Procedure Inspection TPS-9064 MSFIS Final Accepane Test Reset Demonstrate the Ability to Reset Nuthenn Test Direct Test and Procedure Inspection TPS-9064 MSFIS Final
_________________Acceptance                                           Test Performance Characteristics:
_________________Acceptance Test Performance Characteristics:
Environmental EM~IRFI                               EPRI Document TR-102323-R2               Nutherm               Direct Test and and U.S. Nuclear Regulatory             EMIIRFI Report       Inspection Commission Regulatory Guide             WCN-97 15ER
Environmental EM~IRFI EPRI Document TR-102323-R2 Nutherm Direct Test and and U.S. Nuclear Regulatory EMIIRFI Report Inspection Commission Regulatory Guide WCN-97 15ER 1.180 Seismic IEEE 344-1987. TRS shall meet Nutherm Direct Test and or exceed the RRS of S4000-RP-Qualification Inspection 20 with at minimum a 10%
__________________              1.180 Seismic                               IEEE 344-1987. TRS shall meet           Nutherm               Direct Test and or exceed the RRS of S4000-RP-           Qualification         Inspection 20 with at minimum a 10%                 Report margin. Meters shall exhibit             WCN-97 15R proper operation as outlined in
Report margin. Meters shall exhibit WCN-97 15R proper operation as outlined in
________________S4000-RP-20.                                             ________
________________S4000-RP-20.
Mild Environment                     IEEE 323-1974. 650 F to 840 F at a       Nutherm               Direct Test and Conditions                           Relative Humidity of 20% to             Qualification         Inspection 70%. System shall exhibit proper         Report operation as outlined in Wolf           WCN-9715R
Mild Environment IEEE 323-1974. 6 50F to 840F at a Nutherm Direct Test and Conditions Relative Humidity of 20% to Qualification Inspection 70%. System shall exhibit proper Report operation as outlined in Wolf WCN-9715R
_________________Creek                     Specification J- 105A.
_________________Creek Specification J-1 05A.
Abnormal Conditions & Events (ACEs)
Abnormal Conditions & Events (ACEs)
Loss and Return of                   No Loss of Configuration                 Nuthenrm Test         Direct Test and Power                                                                         Procedure             Inspection TPS-9064 MSFIS Final Acceptace Test Power Over/Under                       105-140 Vdc                             Nutherm Test           Direct Test and Voltage                                                                         Procedure             Inspection TPS-9064 MSFIS Final
Loss and Return of No Loss of Configuration Nuthenrm Test Direct Test and Power Procedure Inspection TPS-9064 MSFIS Final Acceptace Test Power Over/Under 105-140 Vdc Nutherm Test Direct Test and Voltage Procedure Inspection TPS-9064 MSFIS Final
________________   _____________________1 Acceptance Test                     f 501 South 11'tS~treet             PHONE: 618-244-6000, HdM4ERPOftLONAlN                                          Mt. Vernon IL 62864                .FAX: 618-244-66i41
________________ _____________________1 Acceptance Test f
HdM4ERPOftLONAlN 501 South 11' tS~treet Mt. Vernon IL 62864 PHONE: 618-244-6000,
.FAX: 618-244-66i41


DEDICATION PLAN WCN-9715DP, REV I PAGE 16 OF 24 CRITICAL                       ACCEPTANCE CRITERIA                 VALIDATION           VALIDATION CHARACTERISTICS                                                         DOCUMENT                 METHOD Loss and Return of             Correct operation as described in Nutherm Test             Direct Test and Input Signals                   Wolf Creek Specification J- I 05A Procedure                 Inspection (1 or more)                                                           TPS-9064 MSFIS Final
DEDICATION PLAN WCN-9715DP, REV I PAGE 16 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Loss and Return of Correct operation as described in Nutherm Test Direct Test and Input Signals Wolf Creek Specification J-I 05A Procedure Inspection (1 or more)
__________________Acceptance                                       Test Input Signal                   Correct operation as described in Nutherm Test             Direct Test and Over/Under Range               Wolf Creek Specification J- 105A Procedure                 Inspection (1 or more)                                                           TPS-9064 MSFIS Final
TPS-9064 MSFIS Final
__________________Acceptance                                       Test Communication                   No Loss of Configuration or           Nuthermn Test       Direct Test and Interface Connection           Effect on System Operation             Procedure           Inspection Fault                                                                 TPS-9064 MSFIS Final
__________________Acceptance Test Input Signal Correct operation as described in Nutherm Test Direct Test and Over/Under Range Wolf Creek Specification J-1 05A Procedure Inspection (1 or more)
_________________Acceptance                                         Test Input Fault/Abnormal           No Loss of Configuration or           Nutherm Test         Direct Test and Input                           Effect on System Operation             Procedure             Inspection TPS-9064 MSFIS Final Acceptance Test Dependability Characteristics:
TPS-9064 MSFIS Final
Built-In Quality Quality of Design and           Manufacturer maintains a QA           Nutherm               Commercial Grade Manufacture                     program that is generally in           Dedication Report     Survey and/or compliance with a recognized           (NI Commercial       Source Inspection standard, including as a               Grade Survey of minimum: QA                           CSI). Nutherm Staff/Organization, QA Plans and       Quality Plan.
__________________Acceptance Test Communication No Loss of Configuration or Nuthermn Test Direct Test and Interface Connection Effect on System Operation Procedure Inspection Fault TPS-9064 MSFIS Final
_________________Acceptance Test Input Fault/Abnormal No Loss of Configuration or Nutherm Test Direct Test and Input Effect on System Operation Procedure Inspection TPS-9064 MSFIS Final Acceptance Test Dependability Characteristics:
Built-In Quality Quality of Design and Manufacturer maintains a QA Nutherm Commercial Grade Manufacture program that is generally in Dedication Report Survey and/or compliance with a recognized (NI Commercial Source Inspection standard, including as a Grade Survey of minimum: QA CSI). Nutherm Staff/Organization, QA Plans and Quality Plan.
Procedures. Evidence the QA program was applied in the production of the procured items.
Procedures. Evidence the QA program was applied in the production of the procured items.
System Reliability             Wolf Creek Specification J-1 05A       WC/Baseline           Analysis Analysis                                                               Engineering SRA Report, Nutherm
System Reliability Wolf Creek Specification J-1 05A WC/Baseline Analysis Analysis Engineering SRA Report, Nutherm Dedication Report fL 7, 501 South 11 tStreet Mt. Vernon IL 62864 PHONE: 618-244-6000
_    _____  ____    ____  ____  ____  Dedication Report   _  _ _  _  _ _ _  _
...FAX: 618-244-6641
501 South 11 tStreet             PHONE: 618-244-6000 fL 7,                                              Mt. Vernon IL 62864              ...FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV I PAGE 17 OF 24 CRITICAL                         ACCEPTANCE CRITERIA                   VALIDATION             VALIDATION CHARACTERISTICS                                                               DOCUMENT                   METHOD Hardware Design                     Evidence the QA program (DO-           Nutherm                 Commercial Grade Process'                           254) was applied in the hardware       Dedication Report       Survey and/or design                                 (NI Commercial         Source Inspection Grade Survey of
DEDICATION PLAN WCN-9715DP, REV I PAGE 17 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Hardware Design Evidence the QA program (DO-Nutherm Commercial Grade Process' 254) was applied in the hardware Dedication Report Survey and/or design (NI Commercial Source Inspection Grade Survey of
_________CSI)       ____
____CSI)
Configuration Control               Configuration control program         Nutherm                 Commercial Grade that includes:                         Dedication Report       Survey and/or
Configuration Control Configuration control program Nutherm Commercial Grade that includes:
                                            *Version control of FPGA       (NI Commercial         Source Inspection design files                 Grade Survey of
Dedication Report Survey and/or
                                            *Version control of FPGA       CSI) design tools Documented Plan & Procedures           Nutherm                 Commercial Grade Dedication Report       Survey and/or (NI Commercial         Source Inspection Grade Survey of CSD Baseline Maintenance                   Nutherm                 Commercial Grade Dedication Report       Survey and/or (NI Commercial         Source Inspection Grade Survey of CSI                     _______
*Version control of FPGA (NI Commercial Source Inspection design files Grade Survey of
Change Control                         Nutherm                 Commercial Grade Dedication Report       Survey and/or (NI Commercial         Source Inspection Grade Survey of CSI)
*Version control of FPGA CSI) design tools Documented Plan & Procedures Nutherm Commercial Grade Dedication Report Survey and/or (NI Commercial Source Inspection Grade Survey of CSD Baseline Maintenance Nutherm Commercial Grade Dedication Report Survey and/or (NI Commercial Source Inspection Grade Survey of CSI Change Control Nutherm Commercial Grade Dedication Report Survey and/or (NI Commercial Source Inspection Grade Survey of CSI)
Error-Reporting Process               Nutherm                 Commercial Grade Dedication Report       Survey and/or (NI Commercial         Source Inspection Grade Survey of CSI)______                                   _
Error-Reporting Process Nutherm Commercial Grade Dedication Report Survey and/or (NI Commercial Source Inspection Grade Survey of CSI)______
Failure Modes/Failure               A Failure Modes and Effects           WC/Baseline             Analysis Analysis                           Analysis (FMEA) is prepared as         Engineering part of the WC Engineering             FMEA Report, Package (EP) process.                 Nutherm Dedication Report Problem Reporting                   Established error-reporting           Nutherm Quality         Commercial Grade procedures. Seller will also           Manual                 Survey and/or
Failure Modes/Failure A Failure Modes and Effects WC/Baseline Analysis Analysis Analysis (FMEA) is prepared as Engineering part of the WC Engineering FMEA Report, Package (EP) process.
_______________provide                   reporting to Purchaser. _________Source                   Inspection 501 South I ItStreet                 PHONE: 618-244-6000 f*49LId,                                              Mt. Vernon IL.62864                    FAX: 618-244-6641
Nutherm Dedication Report Problem Reporting Established error-reporting Nutherm Quality Commercial Grade procedures. Seller will also Manual Survey and/or
_______________provide reporting to Purchaser.
_________Source Inspection f*49LId, 501 South I ItStreet Mt. Vernon IL.62864 PHONE: 618-244-6000 FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 18 OF 24 PHYSICAL CHARACTERISTICS Physical characteristics are those characteristics of the item that deal with its construction, materials, shape, form and fit, etc. The critical characteristics classified as physical attributes are determined during the Technical Review and listed on the Critical Characteristics Matrix. The Project Manager evaluates critical physical attributes based on the item's safety function and determines the best method to verify them. Typically, for dedication, these characteristics are compared with a tested item in the Nutherm International, Inc. Test Specimen Library. The comparison is documented, then reviewed and evaluated by the Nutherm Engineering department. Any differences between the tested item and the dedicated item are evaluated with respect to the level that the item is being dedicated to (e.g. Seismic, Mild Environment) and documented either on the Comparison sheet or a Record of Dedication. Through the comparison process, reasonable assurance is gained of the physical similarity between the item to be dedicated and the item previously tested.
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 18 OF 24 PHYSICAL CHARACTERISTICS Physical characteristics are those characteristics of the item that deal with its construction, materials, shape, form and fit, etc. The critical characteristics classified as physical attributes are determined during the Technical Review and listed on the Critical Characteristics Matrix. The Project Manager evaluates critical physical attributes based on the item's safety function and determines the best method to verify them. Typically, for dedication, these characteristics are compared with a tested item in the Nutherm International, Inc. Test Specimen Library. The comparison is documented, then reviewed and evaluated by the Nutherm Engineering department. Any differences between the tested item and the dedicated item are evaluated with respect to the level that the item is being dedicated to (e.g. Seismic, Mild Environment) and documented either on the Comparison sheet or a Record of Dedication. Through the comparison process, reasonable assurance is gained of the physical similarity between the item to be dedicated and the item previously tested.
MSFIS System critical physical characteristics are listed above. Similarity will be established to the qualified part as well as design documents during the dedication process, with any differences noted and evaluated for impact on qualification by Nutherm Engineering Department.
MSFIS System critical physical characteristics are listed above. Similarity will be established to the qualified part as well as design documents during the dedication process, with any differences noted and evaluated for impact on qualification by Nutherm Engineering Department.
Product information verification is required to provide reasonable assurance that the item ordered is in fact the item received, as is part of the Physical Characteristic category of Critical Characteristic. This portion of the dedication process includes, but is not limited to, Part Number/Model Number verification and Manufacturer verification. Product information verification is performed and documented at receipt inspection in accordance with Nutherm International, Inc. Quality Assurance Manual No.: QA-N-1 0179-5 and the applicable approved procedures. Section 1.3.3 of EPRI NP-5 652 states; "Part number verification is an integral step in the acceptance of commercial grade items and is included in each of the four acceptance methods. Verification of a part number and the utilization of the acceptance methods in this guideline provide assurance of acceptability.
Product information verification is required to provide reasonable assurance that the item ordered is in fact the item received, as is part of the Physical Characteristic category of Critical Characteristic. This portion of the dedication process includes, but is not limited to, Part Number/Model Number verification and Manufacturer verification. Product information verification is performed and documented at receipt inspection in accordance with Nutherm International, Inc. Quality Assurance Manual No.: QA-N-1 0179-5 and the applicable approved procedures. Section 1.3.3 of EPRI NP-5 652 states; "Part number verification is an integral step in the acceptance of commercial grade items and is included in each of the four acceptance methods.
Verification of a part number and the utilization of the acceptance methods in this guideline provide assurance of acceptability.
Since suppliers furnish commercial grade items for general industrial use, they may change the product design or the manufacturing process, and not the part number. These actions are taken without concern for the nuclear end user's design requirements. The methods described in this guideline provide various means to accept a commercial grade item without sole reliance upon part number verification."
Since suppliers furnish commercial grade items for general industrial use, they may change the product design or the manufacturing process, and not the part number. These actions are taken without concern for the nuclear end user's design requirements. The methods described in this guideline provide various means to accept a commercial grade item without sole reliance upon part number verification."
Because of possible changes by the manufacturer, Product Information alone is an insufficient basis for acceptance of commercial grade items for nuclear safety related applications. This is especially true of complex digital equipment. By combining Product Information verification with the applicable testing, comparisons, etc. of an item's Physical Attributes, Performance characteristics, and Dependability characteristics reasonable assurance of acceptability can be achieved.
Because of possible changes by the manufacturer, Product Information alone is an insufficient basis for acceptance of commercial grade items for nuclear safety related applications. This is especially true of complex digital equipment. By combining Product Information verification with the applicable testing, comparisons, etc. of an item's Physical Attributes, Performance characteristics, and Dependability characteristics reasonable assurance of acceptability can be achieved.
501 South 11 thStreet            PHONE: 618-244-6000 INTRNTINA,         NC           Mt. Vernon IL 62864                 1FAX: 618-244-6641
501 South 11 th Street PHONE: 618-244-6000 INTRNTINA, NC Mt. Vernon IL 62864 1FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 19 OF 24 Each cabinet of the MSFIS System contains the following which will be verified during the dedication process:
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 19 OF 24 Each cabinet of the MSFIS System contains the following which will be verified during the dedication process:
* 2 ALS Control System Racks; one Main Steam (MS) rack and one identical Feed Water (FW) rack. Each Rack contains the following boards:
* 2 ALS Control System Racks; one Main Steam (MS) rack and one identical Feed Water (FW) rack. Each Rack contains the following boards:
o 1 Core Logic board (CLB) o 2 Digital Input boards (IPB) o   1 Solid-State Output board (SOB) o 3 Solid State FET & Sensor Output boards (FSB) o   1 Service & Test board (STB) o 2 Redundant Power Supply Modules (PSU)
o 1 Core Logic board (CLB) o 2 Digital Input boards (IPB) o 1 Solid-State Output board (SOB) o 3 Solid State FET & Sensor Output boards (FSB) o 1 Service & Test board (STB) o 2 Redundant Power Supply Modules (PSU)
* 1 Assembly panel, with MS and FW components as follows:
* 1 Assembly panel, with MS and FW components as follows:
o   125V Terminal and Distribution Block o   125V Fuse Blocks for Solenoid Outputs o   125V Fuse Block and Suppression Filter to Power Supplies In addition to Nutherm's normal receipt and visual inspection procedures, each board of each rack will be subject to visual inspection in accordance with Nutherm Procedure TPS-9062, Rev. 0 "ALS Rack Component Verification"'. Each board revision and part number will be recorded along with any other distinguishing marks such as lot numbers, date codes, etc. Software Revision Number for the FPGA logic will be recorded and verified against design documents. Each component on every board will be compared to the manufacturer Bill of Materials (BOM) and Board Layout drawings, as applicable, with any discrepancies noted and addressed in the Dedication Report. Quality of workmanship, such as soldering and overall construction, will be compared with the quality of the qualification unit with any discrepancies noted and addressed in the Dedication Report.
o 125V Terminal and Distribution Block o
125V Fuse Blocks for Solenoid Outputs o
125V Fuse Block and Suppression Filter to Power Supplies In addition to Nutherm's normal receipt and visual inspection procedures, each board of each rack will be subject to visual inspection in accordance with Nutherm Procedure TPS-9062, Rev. 0 "ALS Rack Component Verification"'. Each board revision and part number will be recorded along with any other distinguishing marks such as lot numbers, date codes, etc. Software Revision Number for the FPGA logic will be recorded and verified against design documents. Each component on every board will be compared to the manufacturer Bill of Materials (BOM) and Board Layout drawings, as applicable, with any discrepancies noted and addressed in the Dedication Report. Quality of workmanship, such as soldering and overall construction, will be compared with the quality of the qualification unit with any discrepancies noted and addressed in the Dedication Report.
Component verification against design documents, BOM, and Board Layout drawings provides objective evidence that design control by the manufacturer has been implemented.
Component verification against design documents, BOM, and Board Layout drawings provides objective evidence that design control by the manufacturer has been implemented.
PERFORMANCE The Performance section of the dedication plan lists the operational critical characteristics determined during the technical evaluation. Performance characteristics are verified through testing, analysis, or, in the case of UL listings, comparison with 501 South 11Wt Street             PHONE: 618-244-6000 INUtERAINAIC                 Mt. Vernon IL 62864                   FAX: 618-244-6641
PERFORMANCE The Performance section of the dedication plan lists the operational cri tical characteristics determined during the technical evaluation. Performance characteristics are verified through testing, analysis, or, in the case of UL listings, comparison with 501 South 11Wt Street PHONE: 618-244-6000 INUtERAINAIC Mt. Vernon IL 62864 FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 20 OF 24 manufacturer cutsheets. Performance testing is typically performed at the Nuthermn Testing Facility, in accordance with approved procedures. Test results are documented, evaluated by the Nutherm Engineering Department for acceptability, and reviewed by Nuthermn QA.
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 20 OF 24 manufacturer cutsheets. Performance testing is typically performed at the Nuthermn Testing Facility, in accordance with approved procedures. Test results are documented, evaluated by the Nutherm Engineering Department for acceptability, and reviewed by Nuthermn QA.
Line 176: Line 220:
DEPENDABILITY The Dependability category of critical characteristics is described in detail in EPRI TR-106439. These characteristics are difficult to verify through testing and inspection alone.
DEPENDABILITY The Dependability category of critical characteristics is described in detail in EPRI TR-106439. These characteristics are difficult to verify through testing and inspection alone.
Because built-in features can have a significant impact on the robustness of electronic devices, dedication activities will continue throughout the design and prototype phases following the life cycle approach. Various verification and validation steps with appropriate documentation will be performed at the different phases of the life cycle as described in the Critical Characteristics Matrix. To gain reasonable assurance in the dependability of the MSFIS system, a combination of inspections, vendor process reviews, verification and validation steps, and product development and documentation review will be used to verify the critical characteristics listed in this plan.
Because built-in features can have a significant impact on the robustness of electronic devices, dedication activities will continue throughout the design and prototype phases following the life cycle approach. Various verification and validation steps with appropriate documentation will be performed at the different phases of the life cycle as described in the Critical Characteristics Matrix. To gain reasonable assurance in the dependability of the MSFIS system, a combination of inspections, vendor process reviews, verification and validation steps, and product development and documentation review will be used to verify the critical characteristics listed in this plan.
W~Idu her77501 I*1NJU11ftERN meInA, INC South 11"' Street Mt. Vernon IL 62864 PHONE:  618-244-6000 FAX: 618-244-6641
W~Idu her77501 South 1 1"' Street PHONE: 618-244-6000 I*1NJU11ftERN
: meInA, INC Mt. Vernon IL 62864 FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV I PAGE 21 OF 24 The following steps will be taken to verify the built-in quality critical characteristics:
DEDICATION PLAN WCN-9715DP, REV I PAGE 21 OF 24 The following steps will be taken to verify the built-in quality critical characteristics:
  " An initial Commercial Grade Survey was performed at CS Innovations (CSI).
" An initial Commercial Grade Survey was performed at CS Innovations (CSI).
Follow-up surveys and source inspections will be performed to verify continued compliance with the CSI QA program.
Follow-up surveys and source inspections will be performed to verify continued compliance with the CSI QA program.
* A source inspection will be performed to provide objective evidence that the CSI QA program was applied to the production of the dedicated items.
* A source inspection will be performed to provide objective evidence that the CSI QA program was applied to the production of the dedicated items.
  " A System Reliability Analysis (SKA) was performed under the Wolf Creek (WC)
" A System Reliability Analysis (SKA) was performed under the Wolf Creek (WC)
Quality Assurance program. The SRA report will be reviewed and approved by qualified WC personnel and included in the final Dedication Package. WC will provide documentation and attestation that the SRA critical characteristic has been adequately verified.
Quality Assurance program. The SRA report will be reviewed and approved by qualified WC personnel and included in the final Dedication Package. WC will provide documentation and attestation that the SRA critical characteristic has been adequately verified.
* Surveys and source inspections, as required, will be performed to verify that CSI QA program was applied to the hardware design. The CSI process follows the recommendations of DO-254, "Design Assurance Guidance for Airborne Electronic Hardware". DO-254 describes in detail the Hardware Design Life Cycle and the data which will be developed as evidence of compliance. The surveys and inspections will provide assurance that this process was followed and the appropriate data is available.
* Surveys and source inspections, as required, will be performed to verify that CSI QA program was applied to the hardware design. The CSI process follows the recommendations of DO-254, "Design Assurance Guidance for Airborne Electronic Hardware". DO-254 describes in detail the Hardware Design Life Cycle and the data which will be developed as evidence of compliance. The surveys and inspections will provide assurance that this process was followed and the appropriate data is available.
  " Surveys and source inspections, as required, will be performed to verify that CSI implements appropriate configuration control. The processes and procedures used by the manufacturer will be evaluated. In particular, version control of FPGA design files and design tools will be verified. Design documents will be verified against delivered equipment as fur-ther objective evidence that design control was implemented. The other aspects of configuration control which will be verified include; documented plans and procedures, baseline maintenance, change control, and error reporting processes.
" Surveys and source inspections, as required, will be performed to verify that CSI implements appropriate configuration control. The processes and procedures used by the manufacturer will be evaluated. In particular, version control of FPGA design files and design tools will be verified. Design documents will be verified against delivered equipment as fur-ther objective evidence that design control was implemented. The other aspects of configuration control which will be verified include; documented plans and procedures, baseline maintenance, change control, and error reporting processes.
* Selection of the FPGA and design tools was documented. Said documentation will be included in the final Dedication Report.
* Selection of the FPGA and design tools was documented. Said documentation will be included in the final Dedication Report.
  " A Failure Modes and Effects (FMEA) analysis was performed under the WC QA program. The FMEA report will be reviewed and approved by qualified WC personnel and included in the final Dedication Package. WC will provide documentation and attestation that the FMEA critical characteristic has been adequately verified.
" A Failure Modes and Effects (FMEA) analysis was performed under the WC QA program. The FMEA report will be reviewed and approved by qualified WC personnel and included in the final Dedication Package. WC will provide documentation and attestation that the FMEA critical characteristic has been adequately verified.
* Problem reporting is incorporated in the Nutherm Quality Assurance Manual.
* Problem reporting is incorporated in the Nutherm Quality Assurance Manual.
Surveys and source inspections, as required, will be performed to verify that CSI has error-reporting procedures. Conformance to such procedures will be verified.
Surveys and source inspections, as required, will be performed to verify that CSI has error-reporting procedures. Conformance to such procedures will be verified.
50 1 South I11th Street           PHONE: 618-244-6000 INTRNTINAL IC.         Mt. Vernon IL 62864                 .FAX:   618-244-6641
50 1 South I11th Street PHONE: 618-244-6000 INTRNTINAL IC.
Mt. Vernon IL 62864  
.FAX:
618-244-6641


DEDICATION PLAN WCN-9715DP, REV I PAGE 22 OF 24 VERIFICATION AND VALIDATION Verification and Validation performed by Nuthermn will involve several steps-and processes. Quality Control Inspections (QCI) in accordance with Nutherm procedures will be performed on the production items. These inspections will include Visual Inspections, Point to Point Continuity Verification, Verification of Specified Parts, as well as a detailed inspection and comparison of board components, BOM's, and board layout drawings. A Final Acceptance Test will be performed in accordance with an approved procedure to verify' conformance to purchase order and specification requirements. The Critical Characteristics Matrix lists the performance characteristics which will be verified through testing.
DEDICATION PLAN WCN-9715DP, REV I PAGE 22 OF 24 VERIFICATION AND VALIDATION Verification and Validation performed by Nuthermn will involve several steps-and processes. Quality Control Inspections (QCI) in accordance with Nutherm procedures will be performed on the production items. These inspections will include Visual Inspections, Point to Point Continuity Verification, Verification of Specified Parts, as well as a detailed inspection and comparison of board components, BOM's, and board layout drawings. A Final Acceptance Test will be performed in accordance with an approved procedure to verify' conformance to purchase order and specification requirements. The Critical Characteristics Matrix lists the performance characteristics which will be verified through testing.
DO-254, "Design Assurance Guidance for Airborne Electronic Hardware", contains detailed requirements for Verification and Validation. Surveys and source inspections will be performed, as required, to verify that the CSI V&V processes, plans, and implementation conform with the requirements of DO-254.
DO-254, "Design Assurance Guidance for Airborne Electronic Hardware", contains detailed requirements for Verification and Validation. Surveys and source inspections will be performed, as required, to verify that the CSI V&V processes, plans, and implementation conform with the requirements of DO-254.
501 South 11imStreet              .PHONE: 618-244-6000
~tPR~LONJN 501 South 11 im Street Mt. Vernon IL 62864
~tPR~LONJN                              Mt. Vernon IL 62864                %FAX: 618-244-6641
.PHONE: 618-244-6000
%FAX: 618-244-6641


DEDICATION PLAN WCN-9715DP, REV I PAGE 23 OF 24 Figure 1. Generic Process for acceptance of Commercial Grade Items Used in Safety Related Applications, Per EPRI NP-5652 NO
DEDICATION PLAN WCN-9715DP, REV I PAGE 23 OF 24 Figure 1. Generic Process for acceptance of Commercial Grade Items Used in Safety Related Applications, Per EPRI NP-5652 NO
    *Deficiencyreporting responsibility accepted.
*Deficiency reporting responsibility accepted.
501 South 11itIhStreet           PHONE: 618-244-6000
~NLther 501 South 11itIhStreet Mt. Vernon IL 62864 PHONE: 618-244-6000 LFAX:. 618-244-6641
~NLther                                                  Mt. Vernon IL62864                LFAX:. 618-244-6641


DEDICATION PLAN WCN-9715DP, REV 1 PAGE 24 OF 24 FIGURE 2 Method 1 - Special Tests and Inspections 501 South 11jthStreet              PHONE: 618-244-6000 f*4L 7,               Mt. Vernon IL 62864                 FAX: 618-244-6641}}
DEDICATION PLAN WCN-9715DP, REV 1 PAGE 24 OF 24 FIGURE 2 Method 1 - Special Tests and Inspections f*4L 7, 501 South 11 jthStreet Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-6641}}

Latest revision as of 23:07, 14 January 2025

Dedication Plan WCN-9715DP, Rev. 1, for Replacement Msfis System
ML071770458
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 05/31/2007
From: Sterbis T
Nutherm International
To:
Office of Nuclear Reactor Regulation, Wolf Creek
References
ET 07-0022, Purchase Order No 734527 WCN-9715DP, Rev. 1
Download: ML071770458 (25)


Text

Enclosure 7 to ET 07-0022 Nutherm International Dedication Plan WCN-9715DP, Revision 1

DEDICATION PLAN WCN-9715DP, REV 1 PAGE I OF 24 NUTHERM DEDICATION PLAN FOR REPLACEMENT MSFIS SYSTEM WOLF CREEK NUCLEAR OPERATING CORPORATION PURCHASE ORDER NO. 734527 NUTHERM DOCUMENT NUMBER WCN-9715DP, REV. 1 Prepared By:

Date:

-7 Project Engineering Manager Reviewed and Approved By:

Wan

  • e Date:

EQ Manager ZZe-41-6 7

~Nuthrm 501 South 11 th Street Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 2 OF 24 REVISIONS The revision number is indicated at the top of each page, for all revisions. To delineate the exact location of a given revision, a vertical line is used on the right margin. However, for a complete report rewrite, no vertical lines are used.

REVISION LOG REVISION DATE PAGE 1

5/31/07 5-24 SECTION Dedication Description REFERENCE Complete Rewrite f*469,tophermýýv 501 South 11 th'Street Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-6641

DEDICATION PLAN WCN-971 5DP, REV I PAGE 3 OF 24 TABLE OF CONTENTS

.DESCRIPTION PA(~

PURPOSE...........................................................................................................

4 APPLICABLE STANDARDS AND DOCUMENTS..........................................................

4 DEVICE DESCRIPTION.........................................................................................

5 DEDICATION DESCRIPTION..................................................................................

5 GENERAL................................................................................................................

5 MSFIS REPLACEMENT SYSTEM...................................................................................

6 CRITICAL CHARACTERISTIC MATRIX....................................................................

8 PHYSICAL CHARACTERISTICS............................................................................

18 PERFORMANCE................................................................................................

19 DEPENDABILITY..............................................................................................

20 VERIFICATION AND) VALIDATION.......................................................................

22 MLTERNAflOM 4 LWL 2 501 South 11i0 Street Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-6641

DEDICATION PLAN WCN-971 5DP, REV I PAGE 4 OF 24 PURPOSE The purpose of this dedication plan is to present and define the critical characteristics and the applicable processes and standards which will be used to dedicate the commercial grade items described in the "Device Descriptions" section of this document.

This dedication plan addresses critical characteristics primarily. Additional testing and verification, beyond that required for dedication of the units described in the "Device Descriptions" section of this document, will be performed (as applicable) to ensure items purchased through Nuthermn International are the items described in the customers specification sheets and/or Purchase Order.

All qualification work is accomplished in accordance with customer purchase order and specification requirements, Nuclear Regulatory Commission Guidelines, and applicable Institute of Electrical and Electronic Engineers Standards.

APPLICABLE STANDARDS AND DOCUMENTS IEEE 344-1975 -"ýRecommended Practices for Seismic Qualification of Class 1 E Equipment for Nuclear Power Generating Stations."

IEEE 323 -1974 - "Standard for Qualifying Class IlE Equipment for Nuclear Power Generating Stations" 0

1lOCFR5O, Appendix B. -"Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants" Nutherm. International, Inc. Quality Assurance Manual No.: QA-N-10179-5.

EPRI NP-5652-"Guideline for the Utilization of Commercial Grade Items in Nuclear Safety Related Applications"

  • EPRI TR-I02260-"Supplemental Guidance for the Application of EPRI NP-5652 on the Utilization of Commercial Grade Items" EPRI TR-1 02323-112-1997 - "Guidelines for Electromagnetic Interference Testing in Power Plants" Regulatory Guide 1. 180-RI -"Guidelines for Evaluating Electromagnetic and Radio-Frequency Interference in Safety-Related Instrumentation and Control Systems" IEEE 649-1991 - "Standard for Qualifying Class IlE Motor Control Centers for Nuclear Power Generating Stations" Wolf Creek Generating Station Specification J-1 OSA(Q), Rev. 2 501 South 11 tli Street PHONE: 618-244-6000 INTRNAIONL, NC.Mt.

Vernon IL 62864 FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV I PAGE 5 OF 24

  • EPRI TR-106439 - "Guideline on Evaluation and Acceptance of Commercial Grade Digital Equipment of Nuclear Safety Applications" DEVICE DESCRIPTION The Main Steam and Feedwater Isolation System (MSFIS) has two distinct functions:
  • Steam Line Isolation System (SLIS) - Main Steam Line Isolation minimizes the uncontrolled cool down of the Reactor Coolant System (RCS) that would result from a main steam line rupture. Input signals pass from the detectors through the Solid State Protection System (SSPS) to the MSFIS cabinet where the output signal is generated.

" Feedwater Isolation System (EWIS) - Feedwater isolation minimizes the potential for excessive post-trip cool down of the RCS due to overfilling the steam generators. It also prevents moisture carryover caused by high steam generator levels, and isolates normal Feedwater in the event of a high Energy Line Break inside containment.

MSFIS will include a safety-related logic-controller-based system to performn the control functions of the Main Steam Isolation Valves (MSIVs) and Main Feedwater Isolation Valves (MFIVs) with system-medium actuators. The MSFIS System has two redundant subsystems located in separate cabinets:

MSFIS Channel 1 (1) located in MSFIS Cabinet SA075A (Train A)

MSFIS Channel IV (4) located in MSFIS Cabinet SA075B (Train B)

Each MSFIS cabinet is capable of supplying the control logic outputs required for operating each of the 4 Main Steam Isolation Valves and 4 Main Feedwater Isolation Valves.

Dedication activities will be performed by Nutherm International Inc. on the control system ALS Racks and Assembly Panels for Channels I and IV.

DEDICATION DESCRIPTION GENERAL The dedication process, per EPRI Report 5652, assumes that "the design requirements of the item have been satisfactorily translated into specification requirements as reflected in the procurement document." The guideline goes on to describe three fundamental issues which, once addressed, provide a foundation for the acceptance process of a particular item. The three fundamental issues as described in EPRI Report 5652 are as follows:

501 South I Ph Street PHONE: 618-244-6000 INTRNAIONL, NC.Mt.

Vernon IL 62864 FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 6 OF 24

" Determine the safety function of the item

  • Identify critical characteristics.

These three fundamental issues are addressed during the technical review process and a Component Dedication Planner (CDP) is generated for each item to be dedicated. In the case of more complex systems such as the MSFIS system a Critical Characteristic Matrix is used to quantify Critical Characteristics and the Verification methods used. The Critical Characteristic Matrix for the replacement MSFIS system has been incorporated into this Dedication Plan.

EPRI NP-5 652 is used as a guideline for the dedication process of commercial grade items. As stated in section 1.3.4, 'the methods in the guideline are in conformance with existing regulatory requirements. The methods for accepting commercial grade items are consistent with the provisions of Criterion VII of Appendix B to I OCFR50 which states:

"Measures shall be established to assure that purchased material, equipment, and services, whether purchased. directly or through contractors and subcontractors, conform to the procurement documents.

These measures shall include provisions, as appropriate, for source evaluation and selection, objective evidence of quality fturnished by the contractor or subcontractor, inspection at the contractor or subcontractor, inspection at the contractor or subcontractor source, and examination of products upon delivery."

Nutherm International has incorporated the guideline into its QA program and in-place procedures for the dedication of commercial grade items. See Figure 1 for a block diagram of the generic dedication process. The methods referred to (Method 1 thru 4) are described in detail in EPRI NP-5652. Nutherm International employs a combination of method 1 and other acceptance methods. Figure 2 is a schematic logic diagram for employing method 1, taken from EPRI NP-S 652. Though not all inclusive, the diagram provides a general feel for the dedication process using this method.

MSFIS REPLACEMENT SYSTEM The critical characteristics are divided into three general categories; Product Information, Physical Attributes, and Performance. EPRI TR-106439 incorporated Product Information in the Physical Attributes categories and added Dependability. Though the MSFIS system is not software based, many of the critical characteristics and dedication activities described in EPRI TR-106439 are applicable and have been incorporated into this Dedication Plan. The critical characteristics of this system are varied enough that all four acceptance methods will be used to verify acceptability. For newer, more complex systems this is not unusual. System and other experts will be used, as applicable, to provide any necessary technical expertise throughout the dedication process. 1IOCFR21 states:

501 South 1 1th Street PHONE: 618-244-6000 INTERNTIONA, INC Mt. Vernon IL 62864 FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 7 OF 24 "dedication is an acceptance process undertaken to provide reasonable assurance that a commercial grade item to be used as a basic component will perform its intended safety function and, in this respect, is deemed equivalent to an item designed and manufactured under a 10 CFR Part 50, appendix B, quality assurance program. This assurance is achieved by identifying the critical characteristics of the item and verifying their acceptability by inspections, tests, or analyses" As previously stated, a Critical Characteristics Matrix was developed as part of the dedication process. This matrix lists each Critical Characteristic along with its Acceptance Criteria. For each characteristic the matrix also lists the Validation Document(s) and Validation Method(s) which will be used in the dedication process.

Following the matrix a more detailed explanation of each characteristic category and applicable characteristics is included. EPRI TR-106439, 1996, "Guideline on Evaluation and Acceptance of Commercial Grade Digital Equipment for Nuclear Safety Applications", section 4.2 "Guidance on Defining and Verifying Critical Characteristics",

states:

"Translation of design requirements into critical characteristics for a commercial grade item is a key element in the dedication process. It is the link between the technical evaluation, which defines requirements, including hardware, software, human-machine interface, quality and reliability requirements, is an important prerequisite for dedication of a commercial grade item."

A thorough review of Wolf Creek Generating Station Specification J-1 05A(Q), was performed to generate the Critical Characteristics Matrix, with Acceptance Criteria directly linked to Specification requirements, as applicable.

JWE KqwV 501 South 11 th Street Mt. Vernon IL 62864 PHONE: 618-244-6000

.FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV I PAGE 8 OF 24 CRITICAL CHARACTERISTIC MATRIX CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Physical Characteristics:

Configuration-Model Number Manufacturer Model No.

Nutherm Quality Visual Inspection Assurance Procedure QAP 7.1.00 FPGA Flash Version Manufacturer FPGA Flash Nutherm Visual Inspection Revision Number Version Revision No.

Procedure, ALS Rack Component Verification,

_______________________TPS-9062, Rev. 0 Quality of Quality equivalent to qualified NTL-NQI Visual Inspection Workmanship unit Comparison, Nutherm Form 58050-13-7, Nutherm Procedure, ALS Rack Component Verification, TPS-9062, Rev. 0 General Configuration Enclosure same as qualified unit NTL-NQI Visual Inspection Comparison, Nutherm. Form 58050-13-7 Nuthermn Dedication Plan,

_________________WCN-971 5DP Mounting Mounting same as qualified unit Nutherm Visual Inspection Qualification Report WCN-9715R

~Nather 501 South 11 th Stree~t Mt. Vernon IL 628.64 PHONE: 618-244-6000

.FAX:

618-244-6641

DEDICATION PLAN WCN-9715DP, REV I PAGE 9 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Component Components same as qualified NTL-NQI Visual Inspection Configuration unit Comparison, Nutherm Form 58050-13-7 Nutherm Dedication Plan,

_____________WCN-97 15DP Subcomponent Subcomponents same as qualified NTL-NQI Visual Inspection Configuration unit Comparison, Nutherm. Form 58050-13-7 Nutherm Dedication Plan, WCN-9715DP Interfaces Power 125 Vdc Nutherin Direct Test and Dedication Plan, Inspection WCN-971 5DP, Nuthenn Test Procedure TPS-9064 MSFIS Final

________________ ________________________Acceptance Test Point to Point Wiring matches wiring diagram Nuthermn Direct Test and Continuity Check and Procedure, Inspection Wiring Verification CI1..30_________

Proper Switches operate smoothly, see Nutherm. Test Direct Test and Bypass/Operate switch Functional section for operational Procedure Inspection operation tests and Acceptance Criteria TPS-9064 MSFIS Final Acceptance Test Performance Characteristics:

Functional 125 Vdc outputs to Wolf Creek Specification J-105A, Nutherm. Test Direct Test and control solenoids to Section 5.2.1 a, b, e Procedure Inspection operate valves, verify TPS-9064 output logic MSFIS Final Acceptance Test iNthrmlxwj~

501 South 1 1'hStreet

.Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV I PAGE 10 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Interchangeability of Wolf Creek.Specification J-105A, Nutherm. Test Direct Test and components/modules Section 5.2.2 Procedure Inspection TPS-9064 MSFIS Final Acceptance Test Hot swap capability Wolf Creek Specification* J-l IO0A, Nutherm Test Direct Test and Section 5.2.2 Procedure Inspection TPS -9064 MSFIS Final

__________________Acceptance Test Hot swap will not Wolf Creek Specification J-1 05A, Nuthermi Test Direct Test and cause plant transient Section 5.2.2 Procedure Inspection TPS-9064 MSFIS Final

_________________Acceptance Test Response <1 00 ins Wolf Creek Specification J-105A, Nutherm Test Direct Test and from input step change Section 5.2.3 Procedure Inspection to output response TPS-9064 MSFIS Final

__________________Acceptance Test Momentary input Wolf Creek Specification J-1I05A, Nutherm. Test Direct Test and signal, >100 ms will Section 5.2.4.a 2)

Procedure Inspection cause system response TPS-9064 MSFIS Final

_________________Acceptance Test ESFAS contacts NC, Wolf Creek Specification J-1I05A Nutherm, Test Direct Test and open for response. All Section 5.2.4.a 3)

Procedure Inspection other inputs NO, close TPS-9064 for response MSFIS Final Acceptance Test Output signals:

Wolf Creek Specification J-1 05A Nutherm Test Direct Test and voltage and current Section 5.2.4.c 1)

Procedure Inspection capability, system TPS-9064 capable of sourcing MSFIS Final adequate current at Acceptance Test min and max voltage

~NL'7thqerm 501 South 1IthiiStreet Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-76641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 11 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMIENT METHOD Output signal:

Wolf Creek Specification J-105A Nutherm Test Direct Test and switching 40-60 Henry Section 5.2.4.c 1)

Procedure inspection loads at 1.28A TPS-9064 nominal MSFIS Final Acceptance Test Status outputs:

Wolf Creek Specification J-1I05A Nutherm Test Direct Test and Outputs per Appendix Section 5.2.4.c 2)

Procedure Inspection B

TPS-9064 Output at 125 Vdc if MSFIS Final

[supply fuses for Acceptance Test MV5(6) sat] & [no test in system logic]

Output to status panel capable of 125 Vdc,

<25 mA load Output states: table for Wolf Creek Specification J-105SA Nutherm Test Direct Test and each condition Section 5.2.5.a 1)

Procedure Inspection TPS-9064 MSFIS Final Acceptance Test Four Commands:

Wolf Creek Specification J-1I05A Nutherm Test Direct Test and All Close; Close Section 5.2.5.a 2)

Procedure Inspection output state for 60 sec, TPS-9064 all 4 valves, then Keep MSFIS Final Closed Acceptance Test ESFAS; 2 of 4, same output as All Close Close; Close output state for associated valve, 60 sec delay then Keep Close Open; open output state for associated valve ffq'7,ftJNuther 50 1 South 11 thiStreet

.Mt. Vernon I L 62864 PHONE: 618-244-6000 1FAX: '618-244-6641

DEDICATION PLAN WCN-9715DP, REV I PAGE 12 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Command priorities in Wolf Creek Specification J-105A Nutherm Test Direct Test and OPERARE: All Close, Section 5.2.5.b 1)

Procedure Inspection ESFAS, Close same TPS-9064 priority, Open ignored MSFIS Final while above and time Acceptance Test delay not timed out Command priorities in Wolf Creek Specification J-105A Nutherm Test Direct Test and BYPASS: All Close, Section 5.2.5.b 2)

Procedure Inspection Close, ESFAS, Open TPS-9064 do not cause state MSFIS Final change while in Acceptance Test

BYPASS, BYPASS/OPERATE Wolf Creek Specification J-105A Nutherm Test Direct Test and mode selection:

Section 5.2.6.a 1)

Procedure inspection Independent selection TPS-9064 for each valve MSFIS Final Acceptance Test Positive action to switch modes In BYPASS no output state change Output state Close, time delay not timed out, will not go to BYPASS Indicating light for Wolf Creek Specification J-1I05A Nutherm Test Direct Test and BYPASS Section 5.2.6.a 2)

Procedure Inspection TPS-9064 MSFIS Final Acceptance Test NTRNATONA, q'NC.v 501 South 1 1'h Street Mt. Vernon IL 62864

.PHONE: 618-244-6000 FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 13 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD BYPASS initiation Wolf Creek Specification J-1 05A Nutherm Test Direct Test and a) Latch outputs Section 5.2.6.a 3)

Procedure Inspection b) De-energize status TPS-9064 output MSFIS Final c) Light BYPASS Acceptance Test mode indication d) Close test contacts described in 5.2.6 Return to OPERATE; Wolf Creek Specification J-1I05A Nutherm Test Direct Test and open test contacts, Section 5.2.6.a 4)

Procedure Inspection unlatch outputs, TPS-9064 extinguish BYPASS MSFIS Final indication, release Acceptance Test status output MSFIS power supplies Wolf Creek Specification J-I 05A Nutherm Test Direct Test and will operate on 140-Section 5.6.3.a Procedure Inspection 105 Vdc input power TPS-9064.

MSFIS Final

________________________Accept ne Test 105-140 Vdc power Wolf Creek Specification J-I 05A Nutherm Test Direct Test and supplies, can source Section 5.6.3.b Procedure Inspection sufficient current for TPS-9064 loads MSFIS Final Acceptance Test Hot swap replacement, two redundant power supplies per rack, one can carry the load Load sharing capability Trouble alarm on loss of a power supply, low "health" Proper operation in all Wolf Creek Specification J-105SA Nutherm Test Direct Test and power supply Section 5.6.3.d Procedure Inspection configurations w/o, TPS-9064 spurious trips or loss MSFIS Final of control Acceptance Test j~Nutherm 501 South 1 1 tStreet Mt. Vernon IL 62864

.PHONE: 618-244-6000 FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 14 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Provide wiring harness Wolf Creek Specification J-105A Nuthermn Test Direct Test and Section 5.6.4 Procedure Inspection TPS-9064 MSFIS Final Acceptance Test, Point to point continuity check and wiring verification QCI 10.3.30 Summary trouble Wolf Creek Specification J-1I05A Nutherm Test Direct Test and alarm, NO contact, Section 5.6.7.a Procedure Inspection open to alarm TPS-9064 MSFIS Final Acceptance Test Alarm conditions Wolf Creek Specification J-l1 05A Nutherm Test Direct Test and

1. loss DC pwr supply Section 5.6.7.b Procedure Inspection
2. card removed TPS-9064
3. external test equip MSFIS Final installed Acceptance Test
4. output sequence incomplete_________________________

Indication of trouble Wolf Creek Specification J-105A Nutherm Test Direct Test and alarm cause Section 5.6.7.c Procedure Inspection TPS-9064 MSFIS Final Acceptance Test Dielectric test on wire Wolf Creek Specification J-1 05A Nutherm. Test Direct Test and Section 10.3.2 Procedure Inspection TPS -9064 MSFIS Final Acceptance Test Apply all possible Wolf Creek Specification J-I 05A Nutherm Test Direct Test and input combinations in Section 10.4.3 Procedure Inspection all states TPS-9064 MSFIS Final

________________ ________________________Acceptance Test

wTigN, INC.ýT 501 South 11 t' Street Mt. Vernon IL 62864

.PHONE: 618-244-6000

.FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 15 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Apply manual inputs Wolf Creek Specification J-I05A Nutherm Test Direct Test and Section 10.4.4 Procedure Inspection TPS-9064 MSFIS Final Accepane Test Reset Demonstrate the Ability to Reset Nuthenn Test Direct Test and Procedure Inspection TPS-9064 MSFIS Final

_________________Acceptance Test Performance Characteristics:

Environmental EM~IRFI EPRI Document TR-102323-R2 Nutherm Direct Test and and U.S. Nuclear Regulatory EMIIRFI Report Inspection Commission Regulatory Guide WCN-97 15ER 1.180 Seismic IEEE 344-1987. TRS shall meet Nutherm Direct Test and or exceed the RRS of S4000-RP-Qualification Inspection 20 with at minimum a 10%

Report margin. Meters shall exhibit WCN-97 15R proper operation as outlined in

________________S4000-RP-20.

Mild Environment IEEE 323-1974. 6 50F to 840F at a Nutherm Direct Test and Conditions Relative Humidity of 20% to Qualification Inspection 70%. System shall exhibit proper Report operation as outlined in Wolf WCN-9715R

_________________Creek Specification J-1 05A.

Abnormal Conditions & Events (ACEs)

Loss and Return of No Loss of Configuration Nuthenrm Test Direct Test and Power Procedure Inspection TPS-9064 MSFIS Final Acceptace Test Power Over/Under 105-140 Vdc Nutherm Test Direct Test and Voltage Procedure Inspection TPS-9064 MSFIS Final

________________ _____________________1 Acceptance Test f

HdM4ERPOftLONAlN 501 South 11' tS~treet Mt. Vernon IL 62864 PHONE: 618-244-6000,

.FAX: 618-244-66i41

DEDICATION PLAN WCN-9715DP, REV I PAGE 16 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Loss and Return of Correct operation as described in Nutherm Test Direct Test and Input Signals Wolf Creek Specification J-I 05A Procedure Inspection (1 or more)

TPS-9064 MSFIS Final

__________________Acceptance Test Input Signal Correct operation as described in Nutherm Test Direct Test and Over/Under Range Wolf Creek Specification J-1 05A Procedure Inspection (1 or more)

TPS-9064 MSFIS Final

__________________Acceptance Test Communication No Loss of Configuration or Nuthermn Test Direct Test and Interface Connection Effect on System Operation Procedure Inspection Fault TPS-9064 MSFIS Final

_________________Acceptance Test Input Fault/Abnormal No Loss of Configuration or Nutherm Test Direct Test and Input Effect on System Operation Procedure Inspection TPS-9064 MSFIS Final Acceptance Test Dependability Characteristics:

Built-In Quality Quality of Design and Manufacturer maintains a QA Nutherm Commercial Grade Manufacture program that is generally in Dedication Report Survey and/or compliance with a recognized (NI Commercial Source Inspection standard, including as a Grade Survey of minimum: QA CSI). Nutherm Staff/Organization, QA Plans and Quality Plan.

Procedures. Evidence the QA program was applied in the production of the procured items.

System Reliability Wolf Creek Specification J-1 05A WC/Baseline Analysis Analysis Engineering SRA Report, Nutherm Dedication Report fL 7, 501 South 11 tStreet Mt. Vernon IL 62864 PHONE: 618-244-6000

...FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV I PAGE 17 OF 24 CRITICAL ACCEPTANCE CRITERIA VALIDATION VALIDATION CHARACTERISTICS DOCUMENT METHOD Hardware Design Evidence the QA program (DO-Nutherm Commercial Grade Process' 254) was applied in the hardware Dedication Report Survey and/or design (NI Commercial Source Inspection Grade Survey of

____CSI)

Configuration Control Configuration control program Nutherm Commercial Grade that includes:

Dedication Report Survey and/or

  • Version control of FPGA (NI Commercial Source Inspection design files Grade Survey of

Error-Reporting Process Nutherm Commercial Grade Dedication Report Survey and/or (NI Commercial Source Inspection Grade Survey of CSI)______

Failure Modes/Failure A Failure Modes and Effects WC/Baseline Analysis Analysis Analysis (FMEA) is prepared as Engineering part of the WC Engineering FMEA Report, Package (EP) process.

Nutherm Dedication Report Problem Reporting Established error-reporting Nutherm Quality Commercial Grade procedures. Seller will also Manual Survey and/or

_______________provide reporting to Purchaser.

_________Source Inspection f*49LId, 501 South I ItStreet Mt. Vernon IL.62864 PHONE: 618-244-6000 FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 18 OF 24 PHYSICAL CHARACTERISTICS Physical characteristics are those characteristics of the item that deal with its construction, materials, shape, form and fit, etc. The critical characteristics classified as physical attributes are determined during the Technical Review and listed on the Critical Characteristics Matrix. The Project Manager evaluates critical physical attributes based on the item's safety function and determines the best method to verify them. Typically, for dedication, these characteristics are compared with a tested item in the Nutherm International, Inc. Test Specimen Library. The comparison is documented, then reviewed and evaluated by the Nutherm Engineering department. Any differences between the tested item and the dedicated item are evaluated with respect to the level that the item is being dedicated to (e.g. Seismic, Mild Environment) and documented either on the Comparison sheet or a Record of Dedication. Through the comparison process, reasonable assurance is gained of the physical similarity between the item to be dedicated and the item previously tested.

MSFIS System critical physical characteristics are listed above. Similarity will be established to the qualified part as well as design documents during the dedication process, with any differences noted and evaluated for impact on qualification by Nutherm Engineering Department.

Product information verification is required to provide reasonable assurance that the item ordered is in fact the item received, as is part of the Physical Characteristic category of Critical Characteristic. This portion of the dedication process includes, but is not limited to, Part Number/Model Number verification and Manufacturer verification. Product information verification is performed and documented at receipt inspection in accordance with Nutherm International, Inc. Quality Assurance Manual No.: QA-N-1 0179-5 and the applicable approved procedures. Section 1.3.3 of EPRI NP-5 652 states; "Part number verification is an integral step in the acceptance of commercial grade items and is included in each of the four acceptance methods.

Verification of a part number and the utilization of the acceptance methods in this guideline provide assurance of acceptability.

Since suppliers furnish commercial grade items for general industrial use, they may change the product design or the manufacturing process, and not the part number. These actions are taken without concern for the nuclear end user's design requirements. The methods described in this guideline provide various means to accept a commercial grade item without sole reliance upon part number verification."

Because of possible changes by the manufacturer, Product Information alone is an insufficient basis for acceptance of commercial grade items for nuclear safety related applications. This is especially true of complex digital equipment. By combining Product Information verification with the applicable testing, comparisons, etc. of an item's Physical Attributes, Performance characteristics, and Dependability characteristics reasonable assurance of acceptability can be achieved.

501 South 11 th Street PHONE: 618-244-6000 INTRNTINA, NC Mt. Vernon IL 62864 1FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 19 OF 24 Each cabinet of the MSFIS System contains the following which will be verified during the dedication process:

  • 2 ALS Control System Racks; one Main Steam (MS) rack and one identical Feed Water (FW) rack. Each Rack contains the following boards:

o 1 Core Logic board (CLB) o 2 Digital Input boards (IPB) o 1 Solid-State Output board (SOB) o 3 Solid State FET & Sensor Output boards (FSB) o 1 Service & Test board (STB) o 2 Redundant Power Supply Modules (PSU)

  • 1 Assembly panel, with MS and FW components as follows:

o 125V Terminal and Distribution Block o

125V Fuse Blocks for Solenoid Outputs o

125V Fuse Block and Suppression Filter to Power Supplies In addition to Nutherm's normal receipt and visual inspection procedures, each board of each rack will be subject to visual inspection in accordance with Nutherm Procedure TPS-9062, Rev. 0 "ALS Rack Component Verification"'. Each board revision and part number will be recorded along with any other distinguishing marks such as lot numbers, date codes, etc. Software Revision Number for the FPGA logic will be recorded and verified against design documents. Each component on every board will be compared to the manufacturer Bill of Materials (BOM) and Board Layout drawings, as applicable, with any discrepancies noted and addressed in the Dedication Report. Quality of workmanship, such as soldering and overall construction, will be compared with the quality of the qualification unit with any discrepancies noted and addressed in the Dedication Report.

Component verification against design documents, BOM, and Board Layout drawings provides objective evidence that design control by the manufacturer has been implemented.

PERFORMANCE The Performance section of the dedication plan lists the operational cri tical characteristics determined during the technical evaluation. Performance characteristics are verified through testing, analysis, or, in the case of UL listings, comparison with 501 South 11Wt Street PHONE: 618-244-6000 INUtERAINAIC Mt. Vernon IL 62864 FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 20 OF 24 manufacturer cutsheets. Performance testing is typically performed at the Nuthermn Testing Facility, in accordance with approved procedures. Test results are documented, evaluated by the Nutherm Engineering Department for acceptability, and reviewed by Nuthermn QA.

All testing at the Nutherm Test Laboratory is performed by technicians Certified Level II (minimum) in accordance with ANSI N45.2.6 and the requirements of the Nutherm Quality Assurance Program. All quantitative data is taken using measuring and test equipment (M&TE) which is calibrated under the Nutherm Quality Assurance Program, by calibration facilities which operate under Nutherm approved 10CFR5O, Appendix B Quality Assurance programs. Standards used in performance of calibration are traceable to NIST. When no national standards exist, the basis for calibration is otherwise documented. In all cases, the accuracy of the M&TE used is equal to or greater than the accuracy requirement specified by the engineering department for the test. The description of the test equipment used is presented on the test data sheets.

Performance testing will be performed on the MSFIS systems to verify proper operation and compliance with the applicable sections of Wolf Creek specification J-105A. A Final Acceptance Test (FAT), TPS-9064, will be performed on the supplied MSFJS control system. A detailed test procedure for FAT testing has been developed by Nutherm in cooperation with CS Innovations, for approval by Wolf Creek prior to the start of testing.

The test procedure was developed based on design documents from CS Innovations as well as WC specification requirements. Actual system response to stimulus is compared to designed response as delineated in design documents through Acceptance Criteria. As part of the FAT abnormal conditions and events testing will be performed to verify proper system response to abnormal conditions.

In addition to verifying the performance critical characteristics, thorough testing of the supplied equipment provides objective evidence of design control and built-in quality, adding to the reasonable assurance that the dedicated equipment is suitable for the specified safety related application.

DEPENDABILITY The Dependability category of critical characteristics is described in detail in EPRI TR-106439. These characteristics are difficult to verify through testing and inspection alone.

Because built-in features can have a significant impact on the robustness of electronic devices, dedication activities will continue throughout the design and prototype phases following the life cycle approach. Various verification and validation steps with appropriate documentation will be performed at the different phases of the life cycle as described in the Critical Characteristics Matrix. To gain reasonable assurance in the dependability of the MSFIS system, a combination of inspections, vendor process reviews, verification and validation steps, and product development and documentation review will be used to verify the critical characteristics listed in this plan.

W~Idu her77501 South 1 1"' Street PHONE: 618-244-6000 I*1NJU11ftERN

meInA, INC Mt. Vernon IL 62864 FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV I PAGE 21 OF 24 The following steps will be taken to verify the built-in quality critical characteristics:

" An initial Commercial Grade Survey was performed at CS Innovations (CSI).

Follow-up surveys and source inspections will be performed to verify continued compliance with the CSI QA program.

  • A source inspection will be performed to provide objective evidence that the CSI QA program was applied to the production of the dedicated items.

" A System Reliability Analysis (SKA) was performed under the Wolf Creek (WC)

Quality Assurance program. The SRA report will be reviewed and approved by qualified WC personnel and included in the final Dedication Package. WC will provide documentation and attestation that the SRA critical characteristic has been adequately verified.

  • Surveys and source inspections, as required, will be performed to verify that CSI QA program was applied to the hardware design. The CSI process follows the recommendations of DO-254, "Design Assurance Guidance for Airborne Electronic Hardware". DO-254 describes in detail the Hardware Design Life Cycle and the data which will be developed as evidence of compliance. The surveys and inspections will provide assurance that this process was followed and the appropriate data is available.

" Surveys and source inspections, as required, will be performed to verify that CSI implements appropriate configuration control. The processes and procedures used by the manufacturer will be evaluated. In particular, version control of FPGA design files and design tools will be verified. Design documents will be verified against delivered equipment as fur-ther objective evidence that design control was implemented. The other aspects of configuration control which will be verified include; documented plans and procedures, baseline maintenance, change control, and error reporting processes.

  • Selection of the FPGA and design tools was documented. Said documentation will be included in the final Dedication Report.

" A Failure Modes and Effects (FMEA) analysis was performed under the WC QA program. The FMEA report will be reviewed and approved by qualified WC personnel and included in the final Dedication Package. WC will provide documentation and attestation that the FMEA critical characteristic has been adequately verified.

  • Problem reporting is incorporated in the Nutherm Quality Assurance Manual.

Surveys and source inspections, as required, will be performed to verify that CSI has error-reporting procedures. Conformance to such procedures will be verified.

50 1 South I11th Street PHONE: 618-244-6000 INTRNTINAL IC.

Mt. Vernon IL 62864

.FAX:

618-244-6641

DEDICATION PLAN WCN-9715DP, REV I PAGE 22 OF 24 VERIFICATION AND VALIDATION Verification and Validation performed by Nuthermn will involve several steps-and processes. Quality Control Inspections (QCI) in accordance with Nutherm procedures will be performed on the production items. These inspections will include Visual Inspections, Point to Point Continuity Verification, Verification of Specified Parts, as well as a detailed inspection and comparison of board components, BOM's, and board layout drawings. A Final Acceptance Test will be performed in accordance with an approved procedure to verify' conformance to purchase order and specification requirements. The Critical Characteristics Matrix lists the performance characteristics which will be verified through testing.

DO-254, "Design Assurance Guidance for Airborne Electronic Hardware", contains detailed requirements for Verification and Validation. Surveys and source inspections will be performed, as required, to verify that the CSI V&V processes, plans, and implementation conform with the requirements of DO-254.

~tPR~LONJN 501 South 11 im Street Mt. Vernon IL 62864

.PHONE: 618-244-6000

%FAX: 618-244-6641

DEDICATION PLAN WCN-9715DP, REV I PAGE 23 OF 24 Figure 1. Generic Process for acceptance of Commercial Grade Items Used in Safety Related Applications, Per EPRI NP-5652 NO

  • Deficiency reporting responsibility accepted.

~NLther 501 South 11itIhStreet Mt. Vernon IL 62864 PHONE: 618-244-6000 LFAX:. 618-244-6641

DEDICATION PLAN WCN-9715DP, REV 1 PAGE 24 OF 24 FIGURE 2 Method 1 - Special Tests and Inspections f*4L 7, 501 South 11 jthStreet Mt. Vernon IL 62864 PHONE: 618-244-6000 FAX: 618-244-6641