ML102980287: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 2: | Line 2: | ||
| number = ML102980287 | | number = ML102980287 | ||
| issue date = 04/13/2010 | | issue date = 04/13/2010 | ||
| title = Email from Cline, Leonard to Lew, David, Et Al, Salem Unit 1 AFW Piping Update | | title = Email from Cline, Leonard to Lew, David, Et Al, Salem Unit 1 AFW Piping Update | ||
| author name = Cline L | | author name = Cline L | ||
| author affiliation = NRC/RGN-I/DRP/PB3 | | author affiliation = NRC/RGN-I/DRP/PB3 | ||
| Line 16: | Line 16: | ||
=Text= | =Text= | ||
{{#Wiki_filter:Ziev, Tracey From: | {{#Wiki_filter:Ziev, Tracey From: | ||
Cline, Leonard Sent: | |||
Tuesday, April 13, 2010 3:50 PM To: | |||
Lew, David Cc: | |||
Burritt, Arthur; Schroeder, Daniel; Welling, Blake; Cline, Leonard; OHara, Timothy; Conte, Richard; Ennis, Rick | |||
==Subject:== | ==Subject:== | ||
Latest revision as of 02:19, 14 January 2025
| ML102980287 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 04/13/2010 |
| From: | Leonard Cline Reactor Projects Branch 3 |
| To: | David Lew Division Reactor Projects I |
| References | |
| FOIA/PA-2010-0334 | |
| Download: ML102980287 (1) | |
Text
Ziev, Tracey From:
Cline, Leonard Sent:
Tuesday, April 13, 2010 3:50 PM To:
Lew, David Cc:
Burritt, Arthur; Schroeder, Daniel; Welling, Blake; Cline, Leonard; OHara, Timothy; Conte, Richard; Ennis, Rick
Subject:
Salem Unit 1 AFW piping Update Progress on the UTs of the Salem Unit 1 AFW piping has been slowed by the rain. They will probably not complete the UTs until tomorrow, but may still be able to complete the FEA before the end of the day tomorrow (4/14). At the latest PSEG expects to complete the FEA for the Unit 1 piping by Thursday (4/15).
There are no other significant updates for this issue at this time.
1/5