ML111190061: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
Line 2: Line 2:
| number = ML111190061
| number = ML111190061
| issue date = 04/28/2011
| issue date = 04/28/2011
| title = Summary of Public Meeting with Southern Nuclear Operating Company, Inc., to Discuss the Nrc'S Reactor Oversight Process and the Nrc'S Annual Assessment of Plant Safety Performance at Hatch for the Period of 01/01/210 - 12/31/2010
| title = Summary of Public Meeting with Southern Nuclear Operating Company, Inc., to Discuss the NRCs Reactor Oversight Process and the NRCs Annual Assessment of Plant Safety Performance at Hatch for the Period of 01/01/210 - 12/31/2010
| author name = Shaeffer S
| author name = Shaeffer S
| author affiliation = NRC/RGN-II/DRP/RPB2
| author affiliation = NRC/RGN-II/DRP/RPB2
Line 16: Line 16:
=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 28, 2011 Mr. Dennis R. Madison Vice President Southern Nuclear Operating Company, Inc.
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 28, 2011 Mr. Dennis R. Madison Vice President Southern Nuclear Operating Company, Inc.
Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513
Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513  


==SUBJECT:==
==SUBJECT:==
Line 23: Line 23:
==SUMMARY==
==SUMMARY==
  - EDWIN I. HATCH NUCLEAR PLANT -
  - EDWIN I. HATCH NUCLEAR PLANT -
DOCKET NOS. 50-321 AND 50-366
DOCKET NOS. 50-321 AND 50-366  


==Dear Mr. Madison:==
==Dear Mr. Madison:==
This refers to the meeting conducted on April 21, 2011, in Baxley, GA. The purpose of this meeting was to discuss the NRC's Reactor Oversight Process (ROP) and the NRC's annual assessment of plant safety performance for the period of January 1, 2010 - December 31, 2010.
This refers to the meeting conducted on April 21, 2011, in Baxley, GA. The purpose of this meeting was to discuss the NRC's Reactor Oversight Process (ROP) and the NRC's annual assessment of plant safety performance for the period of January 1, 2010 - December 31, 2010.
The major topics addressed were the NRC's assessment program and the results of the assessment. A listing of meeting attendees and information presented during the meeting are enclosed.
The major topics addressed were the NRC's assessment program and the results of the assessment. A listing of meeting attendees and information presented during the meeting are enclosed.
Line 32: Line 31:
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact me at (404) 997-4521.
Should you have any questions concerning this meeting, please contact me at (404) 997-4521.
Sincerely,
Sincerely,  
                                                /RA/
/RA/
Scott M. Shaeffer, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-321, 50-366 License Nos.: DRP-57, NPF-5
Scott M. Shaeffer, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-321, 50-366 License Nos.: DRP-57, NPF-5  


==Enclosures:==
==Enclosures:==
: 1. List of Attendees
: 1. List of Attendees
: 2. PowerPoint Presentation
: 2. PowerPoint Presentation
: 3. Poster Boards cc w/encl: (See page 2)
: 3. Poster Boards cc w/encl: (See page 2)  


_       ML111190061 ___                       G SUNSI REVIEW COMPLETE OFFICE           RII:DRP           RII:DRP           RII:DRP SIGNATURE         SMS /RA/         SMS /RA for/     TXL /RA/
_ ML111190061 ___
NAME             SShaeffer         SRose             TLighty DATE                 04/27/2011       04/27/2011       04/27/2011 E-MAIL COPY?       YES         NO YES           NO YES           NO YES     NO YES       NO YES     NO   YES NO
G SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE SMS /RA/
SMS /RA for/
TXL /RA/
NAME SShaeffer SRose TLighty DATE 04/27/2011 04/27/2011 04/27/2011 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO  


SNC                                     2 cc w/encl:                                 Mr. Ken Rosanski Managing Attorney and Compliance Officer   Resident Manager Southern Nuclear Operating Company, Inc. Edwin I. Hatch Electronic Mail Distribution              Oglethorpe Power Corporation Electronic Mail Distribution B. D. McKinney, Jr.
SNC 2
Regulatory Response Manager               Chris Clark Southern Nuclear Operating Company, Inc. Commissioner Electronic Mail Distribution              Georgia Department of Natural Resources Electronic Mail Distribution Jeffrey T. Gasser Executive Vice President                   Lee Foley Southern Nuclear Operating Company, Inc. Manager of Contracts Generation Electronic Mail Distribution              Oglethorpe Power Corporation Electronic Mail Distribution Mark Ajluni Licensing Manager                         Arthur H. Domby, Esq.
cc w/encl:
Southern Nuclear Operating Company, Inc. Troutman Sanders Electronic Mail Distribution              Electronic Mail Distribution T. D. Honeycutt                           James C. Hardeman Regulatory Response Supervisor             Environmental Radiation Program Manager Southern Nuclear Operating Company, Inc. Environmental Protection Division Electronic Mail Distribution              Georgia Department of Natural Resources Electronic Mail Distribution L. Mike Stinson Vice President                             Ted V. Jackson Fleet Operations Support                   Emergency Response and Radiation Southern Nuclear Operating Company, Inc. Program Manager Electronic Mail Distribution               Environmental Protection Division Georgia Department of Natural Resources Paula Marino                               Electronic Mail Distribution Vice President Engineering                               F. Allen Barnes Southern Nuclear Operating Company, Inc. Director Electronic Mail Distribution               Environmental Protection Division Georgia Department of Natural Resources Moanica Caston                             Electronic Mail Distribution Vice President and General Counsel Southern Nuclear Operating Company, Inc. Cynthia A. Sanders Electronic Mail Distribution               Radioactive Materials Program Manager Environmental Protection Division Steven B. Tipps                            Georgia Department of Natural Resources Hatch Principal Engineer - Licensing      Electronic Mail Distribution Edwin I. Hatch Nuclear Plant Electronic Mail Distribution               (cc w/encl continued next page)
Managing Attorney and Compliance Officer Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution B. D. McKinney, Jr.
Regulatory Response Manager Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Mark Ajluni Licensing Manager Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution T. D. Honeycutt Regulatory Response Supervisor Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution L. Mike Stinson Vice President Fleet Operations Support Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Paula Marino Vice President Engineering Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Moanica Caston Vice President and General Counsel Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Steven B. Tipps Hatch Principal Engineer - Licensing Edwin I. Hatch Nuclear Plant Electronic Mail Distribution Mr. Ken Rosanski Resident Manager Edwin I. Hatch Oglethorpe Power Corporation Electronic Mail Distribution Chris Clark Commissioner Georgia Department of Natural Resources Electronic Mail Distribution Lee Foley Manager of Contracts Generation Oglethorpe Power Corporation Electronic Mail Distribution Arthur H. Domby, Esq.
Troutman Sanders Electronic Mail Distribution James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Ted V. Jackson Emergency Response and Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution F. Allen Barnes Director Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution (cc w/encl continued next page)  


SNC                                     3 (cc w/encl continued)
SNC 3
James A. Sommerville Program Coordination Branch Chief Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Mr. Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia Electronic Mail Distribution Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Electronic Mail Distribution Chairman Appling County Commissioners County Courthouse 69 Tippins Street, Suite 201 Baxley, GA 31513
(cc w/encl continued)
James A. Sommerville Program Coordination Branch Chief Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Mr. Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia Electronic Mail Distribution Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Electronic Mail Distribution Chairman Appling County Commissioners County Courthouse 69 Tippins Street, Suite 201 Baxley, GA 31513  


SNC                                       4 Letter to Dennis R. Madison from Scott M. Shaeffer dated April 28, 2011
SNC 4
Letter to Dennis R. Madison from Scott M. Shaeffer dated April 28, 2011  


==SUBJECT:==
==SUBJECT:==
Line 59: Line 74:
  - EDWIN I. HATCH NUCLEAR PLANT -
  - EDWIN I. HATCH NUCLEAR PLANT -
DOCKET NOS. 50-321 AND 50-366 Distribution w/encl:
DOCKET NOS. 50-321 AND 50-366 Distribution w/encl:
C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMHatch Resource Edwin I. Hatch Nuclear Plant Annual Assessment Meeting Reactor Oversight Process - 2010 Nuclear Regulatory Commission - Region 2 Vidalia, Ga April 21, 2011 1
C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMHatch Resource  
Enclosure 2


2 Purpose of Todays Meeting
1 Edwin I. Hatch Nuclear Plant Annual Assessment Meeting Reactor Oversight Process - 2010 Nuclear Regulatory Commission - Region 2 Vidalia, Ga April 21, 2011
 
2 2
Purpose of Todays Meeting
* A public forum for discussion of the licensees performance in 2010
* A public forum for discussion of the licensees performance in 2010
* NRC will address the performance issues identified in the annual assessment letter
* NRC will address the performance issues identified in the annual assessment letter
* Licensee will be given the opportunity to respond and inform the NRC of new or existing programs to maintain or improve performance 2
* Licensee will be given the opportunity to respond and inform the NRC of new or existing programs to maintain or improve performance  
Enclosure 2


3 Agenda
3 3
Agenda
* Introduction
* Introduction
* Review of Reactor Oversight Process
* Review of Reactor Oversight Process
Line 76: Line 93:
* NRC Closing Remarks
* NRC Closing Remarks
* Break
* Break
* NRC available to address public questions 3
* NRC available to address public questions  
Enclosure 2


4 Region 2 Organization Victor McCree Regional Administrator Leonard Wert Deputy Regional Administrator Division of Reactor Projects                   Division of Reactor Safety Richard Croteau, Director                      Joel Munday, Director William Jones,                         Harold Christensen, Deputy Deputy Director                                    Director Projects Branch 2                             Regional Specialist Scott Shaeffer, Chief                             Inspectors (404)562-4521 Hatch                       Project Engineers (PE)
4 4
Resident Inspectors (RI)             Steven Rose, Senior PE Eddie Morris, Senior RI                   Tonya Lighty, PE David Hardage, RI RI Office: (912)367-9881 4
Region 2 Organization Victor McCree Regional Administrator Leonard Wert Deputy Regional Administrator Division of Reactor Projects Richard Croteau, Director William Jones, Deputy Director Projects Branch 2 Scott Shaeffer, Chief (404)562-4521 Hatch Resident Inspectors (RI)
Enclosure 2
Eddie Morris, Senior RI David Hardage, RI RI Office: (912)367-9881 Project Engineers (PE)
Steven Rose, Senior PE Tonya Lighty, PE Division of Reactor Safety Joel Munday, Director Harold Christensen, Deputy Director Regional Specialist Inspectors


5 Our Mission
5 5
Our Mission
* To license and regulate the nations civilian use of byproduct, source, and special nuclear materials to ensure adequate protection of public health and safety, promote the common defense and security, and protect the environment.
* To license and regulate the nations civilian use of byproduct, source, and special nuclear materials to ensure adequate protection of public health and safety, promote the common defense and security, and protect the environment.
5 Enclosure 2


6 Some Nuclear Facts
6 6
* 104 nuclear power plants supply about 20 percent of the electricity in the U.S.
Some Nuclear Facts 104 nuclear power plants supply about 20 percent of the electricity in the U.S.
* Nuclear materials are used in medicine for diagnosis and cancer treatment.
Nuclear materials are used in medicine for diagnosis and cancer treatment.
* Nuclear materials are widely used in industry, such as in density gauges, flow measurement devices, radiography devices, and irradiators.
Nuclear materials are widely used in industry, such as in density gauges, flow measurement devices, radiography devices, and irradiators.
6 Enclosure 2


7 The NRC Regulates
7 7
The NRC Regulates
* Nuclear reactors - commercial power reactors, research and test reactors, new reactor designs
* Nuclear reactors - commercial power reactors, research and test reactors, new reactor designs
* Nuclear materials - nuclear reactor fuel, radioactive materials for medical, industrial, and academic use
* Nuclear materials - nuclear reactor fuel, radioactive materials for medical, industrial, and academic use
* Nuclear waste - transportation, storage and disposal of nuclear material and waste, decommissioning of nuclear facilities
* Nuclear waste - transportation, storage and disposal of nuclear material and waste, decommissioning of nuclear facilities
* Nuclear security - physical security of nuclear facilities and materials from sabotage or attacks 7
* Nuclear security - physical security of nuclear facilities and materials from sabotage or attacks
Enclosure 2


8 What We Dont Do
8 8
What We Dont Do
* Regulate nuclear weapons, military reactors, or space vehicle reactors
* Regulate nuclear weapons, military reactors, or space vehicle reactors
* Own or operate nuclear power plants
* Own or operate nuclear power plants
* Regulate some radioactive materials, such as X-rays and naturally occurring radon 8
* Regulate some radioactive materials, such as X-rays and naturally occurring radon  
Enclosure 2


9 How We Regulate
9 9
How We Regulate
* Establish rules and regulations
* Establish rules and regulations
* Issue licenses
* Issue licenses
* Provide oversight through inspection, enforcement, and evaluation of operational experience
* Provide oversight through inspection, enforcement, and evaluation of operational experience
* Conduct research to provide support for regulatory decisions
* Conduct research to provide support for regulatory decisions
* Respond to events and emergencies 9
* Respond to events and emergencies
Enclosure 2


10 Assurance of Plant Safety
10 10 Assurance of Plant Safety
* Require defense-in-depth
* Require defense-in-depth
* Require long-term maintenance of equipment
* Require long-term maintenance of equipment
* Require continual training of operators
* Require continual training of operators
* Verify compliance with regulations 10 Enclosure 2
* Verify compliance with regulations


11 What We Do - Nuclear Waste
11 11 What We Do - Nuclear Waste
* The NRC regulates:
* The NRC regulates:
                  - Storage of spent reactor fuel in fuel pools or dry storage casks, and
- Storage of spent reactor fuel in fuel pools or dry storage casks, and
                  - Any national spent fuel storage site, such as the proposed Yucca Mountain site.
- Any national spent fuel storage site, such as the proposed Yucca Mountain site.
11 Enclosure 2


12 What We Do - Nuclear Security
12 12 What We Do - Nuclear Security
* NRC Requires:
* NRC Requires:
                    - Well-armed and well-trained security forces,
- Well-armed and well-trained security forces,
                    - Surveillance and perimeter patrols,
- Surveillance and perimeter patrols,
                    - State-of-the-art site access equipment and controls,
- State-of-the-art site access equipment and
                    - Physical barriers and detection zones, and
: controls,
                    - Intrusion detection systems and alarm stations.
- Physical barriers and detection zones, and
12 Enclosure 2
- Intrusion detection systems and alarm stations.


13 NRC Performance Goals
13 13 NRC Performance Goals
* Safety: Ensure adequate protection of public health and safety and the environment.
* Safety: Ensure adequate protection of public health and safety and the environment.
* Security: Ensure adequate protection in the secure use and management of radioactive materials.
* Security: Ensure adequate protection in the secure use and management of radioactive materials.
13 Enclosure 2


14 Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Performance Indicator Baseline Inspection Results Results Significance                    Significance Threshold                        Threshold Action Matrix Regulatory Response 14 Enclosure 2
14 14 Reactor Oversight Process Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas
 
15 15 Examples of Baseline Inspections
* Equipment Alignment
~80 hrs/yr
* Triennial Fire Protection
~250 hrs every 3 yrs
* Operator Response
~125 hrs/yr
* Emergency Preparedness
~80 hrs/yr
* Rad Release Controls
~110 hrs every 2 yrs
* Worker Radiation Protection
~95 hrs/yr
* Corrective Action Program
~250 hrs every 2 yrs
* Corrective Action Case Reviews
~60 hrs/yr
 
16 16 Significance Threshold Performance Indicators Green:
Only Baseline Inspection White:
Increases NRC oversight Yellow:
Increases NRC oversight Red:
Increases NRC oversight Inspection Findings Green:
Very low safety issue White:
Low to moderate safety issue Yellow:
Substantial safety issue Red:
High safety issue


15 Examples of Baseline Inspections
17 17 Action Matrix Concept Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions Licensee
* Equipment Alignment            ~80 hrs/yr
* Triennial Fire Protection      ~250 hrs every 3 yrs
* Operator Response              ~125 hrs/yr
* Emergency Preparedness        ~80 hrs/yr
* Rad Release Controls          ~110 hrs every 2 yrs
* Worker Radiation Protection    ~95 hrs/yr
* Corrective Action Program      ~250 hrs every 2 yrs
* Corrective Action Case Reviews ~60 hrs/yr 15 Enclosure 2


16 Significance Threshold Performance Indicators Green: Only Baseline Inspection White: Increases NRC oversight Yellow: Increases NRC oversight Red:    Increases NRC oversight Inspection Findings Green: Very low safety issue White: Low to moderate safety issue Yellow: Substantial safety issue Red:    High safety issue 16 Enclosure 2
===Response===
Regulatory


17 Action Matrix Concept Licensee  Regulatory Degraded   M ultiple/R ep. Unacceptable Response  Response  Cornerstone Degraded       Perform ance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions 17 Enclosure 2
===Response===
Degraded Cornerstone Multiple/Rep.
Degraded Cornerstone Unacceptable Performance


18 National Summary of Plant Performance Status as of 12/31/2010 Licensee Response                     89 Regulatory Response                   9 Degraded Cornerstone                   6 Multiple/Repetitive Deg. Cornerstone   0 Unacceptable                           0 Total                               104 18 Enclosure 2
18 18 National Summary of Plant Performance Status as of 12/31/2010 Licensee Response 89 Regulatory Response 9
Degraded Cornerstone 6
Multiple/Repetitive Deg. Cornerstone 0
Unacceptable 0
Total 104


19 National Summary
19 19 National Summary
* Performance Indicator Results for 2010*
* Performance Indicator Results for 2010*
  - Green             7009
- Green 7009
  - White             23
- White 23
  - Yellow           0
- Yellow 0
  - Red               0
- Red 0
  *PIs are counted per plant per quarter
*PIs are counted per plant per quarter
* Total Inspection Findings in 2010
* Total Inspection Findings in 2010
  - Green             816
- Green 816
  - White             9
- White 9
  - Yellow           2
- Yellow 2
  - Red               0 Finding data current as of 3/3/2011 19 Enclosure 2
- Red 0
Finding data current as of 3/3/2011


20 Hatch Unit 1 Assessment Results January 1 - December 31, 2010
20 20 Hatch Unit 1 Assessment Results January 1 - December 31, 2010
* Hatch Unit 1 was within the Licensee Response column of the NRC Action Matrix for each quarter 2010 20 Enclosure 2
* Hatch Unit 1 was within the Licensee Response column of the NRC Action Matrix for each quarter 2010


21 Hatch Unit 2 Assessment Results
21 Hatch Unit 2 Assessment Results
* Hatch Unit 2 was in the Licensee Response Column of the NRC Action Matrix at the end of the assessment period after being in the Degraded Cornerstone for the 1st-3rd quarter 2010
* Hatch Unit 2 was in the Licensee Response Column of the NRC Action Matrix at the end of the assessment period after being in the Degraded Cornerstone for the 1st-3rd quarter 2010
  - Based on a previous White finding for the 1B Emergency Diesel Generator (EDG) coupling failure(1st qtr 2009) and a White finding for failure to establish and perform preventive maintenance activities to replace aged electrolytic capacitors (4th qtr 2009) 21 Enclosure 2
- Based on a previous White finding for the 1B Emergency Diesel Generator (EDG) coupling failure(1st qtr 2009) and a White finding for failure to establish and perform preventive maintenance activities to replace aged electrolytic capacitors (4th qtr 2009) 21


22 Hatch Unit 2 Assessment Results
22 Hatch Unit 2 Assessment Results
* A supplemental 95002 inspection was completed in August 2010 and documented in inspection report 05000321,366/2010007.
* A supplemental 95002 inspection was completed in August 2010 and documented in inspection report 05000321,366/2010007.
* At the beginning of the 4th Quarter 2010, Hatch Unit 2 transitioned from the Degraded Cornerstone to the Licensee Response column of the NRC Action Matrix 22 Enclosure 2
* At the beginning of the 4th Quarter 2010, Hatch Unit 2 transitioned from the Degraded Cornerstone to the Licensee Response column of the NRC Action Matrix 22


23 Hatch Inspection Activities January 1 - December 31, 2010
23 23 Hatch Inspection Activities January 1 - December 31, 2010
* Total # of Inspection Hours:
* Total # of Inspection Hours:
Regular Hours - 7219 hours Non-Regular - 471 hours
Regular Hours - 7219 hours Non-Regular - 471 hours
* Inspection Findings 1 White violation 8 Green Non-cited violations (NCVs) 23 Enclosure 2
* Inspection Findings 1 White violation 8 Green Non-cited violations (NCVs)


24 Hatch Inspection Activities January 1 - December 31, 2010
24 24 Hatch Inspection Activities January 1 - December 31, 2010
* Inspections Completed 2010
* Inspections Completed 2010
  - 95002 Supplemental Inspection (Capacitors)
- 95002 Supplemental Inspection (Capacitors)
  - Triennial Fire Inspections
- Triennial Fire Inspections
  - ISFI Inspections
- ISFI Inspections
  - TI-180 Managing Fatigue
- TI-180 Managing Fatigue
* Unit 1 Refueling Outage - Spring 2010 24 Enclosure 2
* Unit 1 Refueling Outage - Spring 2010


25 Hatch Annual Assessment Summary January 1 - December 31, 2010
25 25 Hatch Annual Assessment Summary January 1 - December 31, 2010
* Southern Nuclear company operated Hatch Units 1 & 2 in a manner that preserved public health and safety
* Southern Nuclear company operated Hatch Units 1 & 2 in a manner that preserved public health and safety
* All cornerstone objectives were met with only Green findings identified 25 Enclosure 2
* All cornerstone objectives were met with only Green findings identified


26 Hatch Annual Assessment Summary January 1 - December 31, 2010
26 26 January 1 - December 31, 2010
* NRC plans baseline inspections at Hatch for 2011 26 Enclosure 2
* NRC plans baseline inspections at Hatch for 2011 Hatch Annual Assessment Summary


27 Licensee Response and Remarks Dennis Madison Site Vice President E. I. Hatch 27 Enclosure 2
27 27 Licensee Response and Remarks Dennis Madison Site Vice President E. I. Hatch


28 Open to the Public
28 28 Open to the Public
* The NRC places a high priority on keeping the public and stakeholders informed of its activities.
* The NRC places a high priority on keeping the public and stakeholders informed of its activities.
* At www.nrc.gov, you can:
* At www.nrc.gov, you can:
    - Find public meeting dates and transcripts;
- Find public meeting dates and transcripts;
    - Read NRC testimony, speeches, press releases, and policy decisions; and
- Read NRC testimony, speeches, press releases, and policy decisions; and  
    - Access the agencys Electronic Reading Room to find NRC publications and documents.
- Access the agencys Electronic Reading Room to find NRC publications and documents.
28 Enclosure 2


29 What Do You Think of the ROP?
29 What Do You Think of the ROP?
Line 216: Line 257:
Email ROPsurvey@nrc.gov to be notified when the ROP survey is available.
Email ROPsurvey@nrc.gov to be notified when the ROP survey is available.
For information on ROP stakeholder feedback, please visit our website at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS
For information on ROP stakeholder feedback, please visit our website at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS
/program-evaluations.html#section3 29 Enclosure 2
/program-evaluations.html#section3 29


30 Contacting the NRC
30 30 Contacting the NRC
* Report an emergency
* Report an emergency
  - (301) 816-5100 (call collect)
- (301) 816-5100 (call collect)
* Report a safety concern
* Report a safety concern  
  - (800) 695-7403
- (800) 695-7403  
  - Allegation@nrc.gov
- Allegation@nrc.gov
* General information or questions
* General information or questions
  - www.nrc.gov
- www.nrc.gov
  - Select What We Do for Public Affairs 30 Enclosure 2
- Select What We Do for Public Affairs


31 NRC Representatives
31 31 NRC Representatives Richard Croteau, Director, Division Reactor Projects  
* Richard Croteau , Director, Division Reactor Projects
- (404) 997-4500 William Jones, Deputy Division Director, DRP
  - (404) 997-4500
- (404) 997-4501 Robert Martin, Project Manager, NRR
* William Jones   , Deputy Division Director, DRP
- (301) 415-1493 Eddie Morris, Senior Resident Inspector
  - (404) 997-4501
- (912) 367-9981 David Hardage, Resident Inspector
* Robert Martin   , Project Manager, NRR
- (912) 367-9882 Steven Rose, Senior Project Engineer
  - (301) 415-1493
- (404) 997-4609 Scott Shaeffer, Branch Chief
* Eddie Morris     , Senior Resident Inspector
- (404) 997-4521
  - (912) 367-9981
* David Hardage   , Resident Inspector
  - (912) 367-9882
* Steven Rose     , Senior Project Engineer
  - (404) 997-4609
* Scott Shaeffer , Branch Chief
  - (404) 997-4521 31 Enclosure 2


32 Reference Sources
32 32 Reference Sources
* Reactor Oversight Process
* Reactor Oversight Process
  - http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/in dex.html
- http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/in dex.html Public Electronic Reading Room
* Public Electronic Reading Room
- http://www.nrc.gov/reading-rm.html Public Document Room 800-397-4209 (Toll Free)
  - http://www.nrc.gov/reading-rm.html
* Public Document Room 800-397-4209 (Toll Free) 32 Enclosure 2


NRC Strategic Plan Strategic Goals
NRC Strategic Plan Strategic Goals Safety: Ensure adequate protection of public health and safety and the environment.
* Safety: Ensure adequate protection of public health and safety and the environment.
Security: Ensure adequate protection in the secure use and management of radioactive materials.
* Security: Ensure adequate protection in the secure use and management of radioactive materials.
Strategic Objectives Openness: The NRC appropriately informs and involves stakeholders in the regulatory process.
Strategic Objectives
Effectiveness: NRC actions are high quality, efficient, timely, and realistic, to enable the safe and beneficial use of radioactive materials.
* Openness: The NRC appropriately informs and involves stakeholders in the regulatory process.
Operational Excellence: NRC operations use effective business methods and solutions to achieve excellence in accomplishing the agencys mission.
* Effectiveness: NRC actions are high quality, efficient, timely, and realistic, to enable the safe and beneficial use of radioactive materials.
* Operational Excellence: NRC operations use effective business methods and solutions to achieve excellence in accomplishing the agencys mission.
Enclosure 3


2 Nuclear Security &
2 Nuclear Security &
Physical Protection                               Safeguards Security Inspections Force-on-Force Exercises Interagency Cooperation Intrusion Detection & Assessment Response &Offsite Assistance Threat Assessment Information Security Preventing Unauthorized Disclosure Enclosure 3
Safeguards Physical Protection Security Inspections Force-on-Force Exercises Interagency Cooperation Intrusion Detection & Assessment Response &Offsite Assistance Threat Assessment Information Security Preventing Unauthorized Disclosure


3 License Renewal Safety Review of     Review of Environmental Impacts Aging Management Opportunities for Public Participation Enclosure 3
3 Safety Review of Aging Management License Renewal Review of Environmental Impacts Opportunities for Public Participation


4 Spent Nuclear Fuel Safe and Secure Storage & Transport Assured By Comprehensive Regulations Detailed NRC Review Robust Cask & Package Designs Significant Experience Base Continued Oversight U.S. Independent Spent Fuel Storage Installations Trojan      Columbia 1
4 Spent Nuclear Fuel Safe and Secure Storage & Transport Assured By Comprehensive Regulations Detailed NRC Review Robust Cask & Package Designs Significant Experience Base Continued Oversight U.S. Independent Spent Fuel Storage Installations U.S. Independent Spent Fuel Storage Installations LEGEND Interstate Highways Railroads As of August 2007:
Big Rock Monticello                        Point Nine Mile Pt         2 Kewaunee                                                3 DOE TMI-2 Storage                                                        Prairie Island                                                Fitzpatrick 4 Point                                Ginna DOE Idaho Spent Fuel Facility                                                                Beach                                                            5 Humboldt Bay                                                                                                              LaCross                                                                6 e                                                                        7 Zion Palisade                                        8 Fermi  Perry s                                      9 6        5            Cook        Davis Besse 7      1                                                          Northeast:
Disclaimer: This map provides only general information regarding the current and potential ISFSI licensees, based on various information sources that may be inexact and may change.
Private Fuel Storage                                        Ft. Calhoun                  4 2                                            10 11 13      1. Maine Yankee Beaver Valley 3                                              12 14      2. Seabrook 15      3. Vermont Yankee Rancho Seco                                                  Ft Saint Vrain (vault storage)
Browns Ferry Hatch Farley Grand Gulf River Bend Sequoyah Oconee Catawba McGuire Brunswick Robinson Surry North Anna Shearon Harris Vogtle Summer Crystal River Waterford Turkey Point St. Lucie Watts Bar Beaver Valley Fitzpatrick Nine Mile Pt Ginna 1
Cooper                      8    Midwest:                                                 4. Yankee Rowe
2 5
: 1. Dresden                                  16          5. Pilgrim
6 7 8
: 2. GE Morris (wet)                                      6. Haddam Neck North Anna
9 10 11 12 13 Northeast:
: 3. Braidwood                                            7. Millstone Callaway        4. Lasalle                                              8. Indian Point Surry
: 1. Maine Yankee
: 5. Byron                                                9. Susquehanna Wolf Creek
: 2. Seabrook
: 6. Duane Arnold                                          10.Three Mile Island Diablo Canyon                                                                                                                        7. Quad Cities                                          11. Limerick
: 3. Vermont Yankee
: 8. Clinton                                              12. Peach Bottom Shearon Harris    13. Oyster Creek McGuire                    14. Hope Creek Watts Bar
: 4. Yankee Rowe
: 15. Salem Sequoyah        Catawba Robinson              16. Calvert Cliffs San Onofre                                                                                          Arkansas Nuclear                           Oconee Browns Ferry          Summer        Brunswick One Palo Verde Vogtle Hatch Comanche Peak                Grand Gulf Farley LEGEND As of August 2007:                                                                                                                  River Bend 31 Operating General Licensed ISFSIs at Reactor Sites                                                                               Waterford Crystal River 18 Reactor Sites Pursuing a General licensed ISFSI South Texas Project 15 Specific Licensed ISFSIs (At or Away from Reactor Sites)                                                                                                                         St. Lucie
: 5. Pilgrim
: 6. Haddam Neck
: 7. Millstone
: 8. Indian Point
: 9. Susquehanna 10.Three Mile Island
: 11. Limerick
: 12. Peach Bottom
: 13. Oyster Creek
: 14. Hope Creek
: 15. Salem
: 16. Calvert Cliffs 16 Big Rock Point Davis Besse Perry Fermi Point Beach Kewaunee Monticello Prairie Island LaCross e
Zion Cook Palisade s
1 2
3 4
Midwest:
: 1. Dresden
: 2. GE Morris (wet)
: 3. Braidwood
: 4. Lasalle
: 5. Byron
: 6. Duane Arnold
: 7. Quad Cities
: 8. Clinton 5
6 7
8 Ft. Calhoun Cooper Callaway Wolf Creek Arkansas Nuclear One South Texas Project Comanche Peak DOE TMI-2 Storage DOE Idaho Spent Fuel Facility Private Fuel Storage Ft Saint Vrain (vault storage)
Humboldt Bay Trojan Columbia Rancho Seco Diablo Canyon San Onofre Palo Verde 31 Operating General Licensed ISFSIs at Reactor Sites 18 Reactor Sites Pursuing a General licensed ISFSI 15 Specific Licensed ISFSIs (At or Away from Reactor Sites)
[No known sites are pursuing a future Specific Licensed ISFSI]
[No known sites are pursuing a future Specific Licensed ISFSI]
19 reactor sites have not announced intentions regarding ISFSI Turkey Point 30 States have at least one ISFSI Railroads              Interstate Highways Disclaimer: This map provides only general information regarding the current and potential ISFSI licensees, based on various information sources that may be inexact and may change.
19 reactor sites have not announced intentions regarding ISFSI 30 States have at least one ISFSI 15 14 4
Enclosure 3}}
3}}

Latest revision as of 06:42, 13 January 2025

Summary of Public Meeting with Southern Nuclear Operating Company, Inc., to Discuss the NRCs Reactor Oversight Process and the NRCs Annual Assessment of Plant Safety Performance at Hatch for the Period of 01/01/210 - 12/31/2010
ML111190061
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 04/28/2011
From: Scott Shaeffer
NRC/RGN-II/DRP/RPB2
To: Madison D
Southern Nuclear Operating Co
References
Download: ML111190061 (42)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 28, 2011 Mr. Dennis R. Madison Vice President Southern Nuclear Operating Company, Inc.

Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513

SUBJECT:

PUBLIC MEETING

SUMMARY

- EDWIN I. HATCH NUCLEAR PLANT -

DOCKET NOS. 50-321 AND 50-366

Dear Mr. Madison:

This refers to the meeting conducted on April 21, 2011, in Baxley, GA. The purpose of this meeting was to discuss the NRC's Reactor Oversight Process (ROP) and the NRC's annual assessment of plant safety performance for the period of January 1, 2010 - December 31, 2010.

The major topics addressed were the NRC's assessment program and the results of the assessment. A listing of meeting attendees and information presented during the meeting are enclosed.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at (404) 997-4521.

Sincerely,

/RA/

Scott M. Shaeffer, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-321, 50-366 License Nos.: DRP-57, NPF-5

Enclosures:

1. List of Attendees
2. PowerPoint Presentation
3. Poster Boards cc w/encl: (See page 2)

_ ML111190061 ___

G SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE SMS /RA/

SMS /RA for/

TXL /RA/

NAME SShaeffer SRose TLighty DATE 04/27/2011 04/27/2011 04/27/2011 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO

SNC 2

cc w/encl:

Managing Attorney and Compliance Officer Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution B. D. McKinney, Jr.

Regulatory Response Manager Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Mark Ajluni Licensing Manager Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution T. D. Honeycutt Regulatory Response Supervisor Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution L. Mike Stinson Vice President Fleet Operations Support Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Paula Marino Vice President Engineering Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Moanica Caston Vice President and General Counsel Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Steven B. Tipps Hatch Principal Engineer - Licensing Edwin I. Hatch Nuclear Plant Electronic Mail Distribution Mr. Ken Rosanski Resident Manager Edwin I. Hatch Oglethorpe Power Corporation Electronic Mail Distribution Chris Clark Commissioner Georgia Department of Natural Resources Electronic Mail Distribution Lee Foley Manager of Contracts Generation Oglethorpe Power Corporation Electronic Mail Distribution Arthur H. Domby, Esq.

Troutman Sanders Electronic Mail Distribution James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Ted V. Jackson Emergency Response and Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution F. Allen Barnes Director Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution (cc w/encl continued next page)

SNC 3

(cc w/encl continued)

James A. Sommerville Program Coordination Branch Chief Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Mr. Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia Electronic Mail Distribution Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Electronic Mail Distribution Chairman Appling County Commissioners County Courthouse 69 Tippins Street, Suite 201 Baxley, GA 31513

SNC 4

Letter to Dennis R. Madison from Scott M. Shaeffer dated April 28, 2011

SUBJECT:

PUBLIC MEETING

SUMMARY

- EDWIN I. HATCH NUCLEAR PLANT -

DOCKET NOS. 50-321 AND 50-366 Distribution w/encl:

C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMHatch Resource

1 Edwin I. Hatch Nuclear Plant Annual Assessment Meeting Reactor Oversight Process - 2010 Nuclear Regulatory Commission - Region 2 Vidalia, Ga April 21, 2011

2 2

Purpose of Todays Meeting

  • A public forum for discussion of the licensees performance in 2010
  • NRC will address the performance issues identified in the annual assessment letter
  • Licensee will be given the opportunity to respond and inform the NRC of new or existing programs to maintain or improve performance

3 3

Agenda

  • Introduction
  • Review of Reactor Oversight Process
  • National Summary of Plant Performance
  • Discussion of Plant Performance Results
  • Licensee Response and Remarks
  • NRC Closing Remarks
  • Break
  • NRC available to address public questions

4 4

Region 2 Organization Victor McCree Regional Administrator Leonard Wert Deputy Regional Administrator Division of Reactor Projects Richard Croteau, Director William Jones, Deputy Director Projects Branch 2 Scott Shaeffer, Chief (404)562-4521 Hatch Resident Inspectors (RI)

Eddie Morris, Senior RI David Hardage, RI RI Office: (912)367-9881 Project Engineers (PE)

Steven Rose, Senior PE Tonya Lighty, PE Division of Reactor Safety Joel Munday, Director Harold Christensen, Deputy Director Regional Specialist Inspectors

5 5

Our Mission

  • To license and regulate the nations civilian use of byproduct, source, and special nuclear materials to ensure adequate protection of public health and safety, promote the common defense and security, and protect the environment.

6 6

Some Nuclear Facts 104 nuclear power plants supply about 20 percent of the electricity in the U.S.

Nuclear materials are used in medicine for diagnosis and cancer treatment.

Nuclear materials are widely used in industry, such as in density gauges, flow measurement devices, radiography devices, and irradiators.

7 7

The NRC Regulates

  • Nuclear reactors - commercial power reactors, research and test reactors, new reactor designs
  • Nuclear materials - nuclear reactor fuel, radioactive materials for medical, industrial, and academic use
  • Nuclear waste - transportation, storage and disposal of nuclear material and waste, decommissioning of nuclear facilities
  • Nuclear security - physical security of nuclear facilities and materials from sabotage or attacks

8 8

What We Dont Do

  • Regulate nuclear weapons, military reactors, or space vehicle reactors
  • Own or operate nuclear power plants
  • Regulate some radioactive materials, such as X-rays and naturally occurring radon

9 9

How We Regulate

  • Establish rules and regulations
  • Issue licenses
  • Provide oversight through inspection, enforcement, and evaluation of operational experience
  • Conduct research to provide support for regulatory decisions
  • Respond to events and emergencies

10 10 Assurance of Plant Safety

  • Require defense-in-depth
  • Require long-term maintenance of equipment
  • Require continual training of operators
  • Verify compliance with regulations

11 11 What We Do - Nuclear Waste

  • The NRC regulates:

- Storage of spent reactor fuel in fuel pools or dry storage casks, and

- Any national spent fuel storage site, such as the proposed Yucca Mountain site.

12 12 What We Do - Nuclear Security

  • NRC Requires:

- Well-armed and well-trained security forces,

- Surveillance and perimeter patrols,

- State-of-the-art site access equipment and

controls,

- Physical barriers and detection zones, and

- Intrusion detection systems and alarm stations.

13 13 NRC Performance Goals

  • Safety: Ensure adequate protection of public health and safety and the environment.
  • Security: Ensure adequate protection in the secure use and management of radioactive materials.

14 14 Reactor Oversight Process Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas

15 15 Examples of Baseline Inspections

  • Equipment Alignment

~80 hrs/yr

  • Triennial Fire Protection

~250 hrs every 3 yrs

  • Operator Response

~125 hrs/yr

~80 hrs/yr

  • Rad Release Controls

~110 hrs every 2 yrs

  • Worker Radiation Protection

~95 hrs/yr

  • Corrective Action Program

~250 hrs every 2 yrs

  • Corrective Action Case Reviews

~60 hrs/yr

16 16 Significance Threshold Performance Indicators Green:

Only Baseline Inspection White:

Increases NRC oversight Yellow:

Increases NRC oversight Red:

Increases NRC oversight Inspection Findings Green:

Very low safety issue White:

Low to moderate safety issue Yellow:

Substantial safety issue Red:

High safety issue

17 17 Action Matrix Concept Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions Licensee

Response

Regulatory

Response

Degraded Cornerstone Multiple/Rep.

Degraded Cornerstone Unacceptable Performance

18 18 National Summary of Plant Performance Status as of 12/31/2010 Licensee Response 89 Regulatory Response 9

Degraded Cornerstone 6

Multiple/Repetitive Deg. Cornerstone 0

Unacceptable 0

Total 104

19 19 National Summary

  • Performance Indicator Results for 2010*

- Green 7009

- White 23

- Yellow 0

- Red 0

  • PIs are counted per plant per quarter
  • Total Inspection Findings in 2010

- Green 816

- White 9

- Yellow 2

- Red 0

Finding data current as of 3/3/2011

20 20 Hatch Unit 1 Assessment Results January 1 - December 31, 2010

  • Hatch Unit 1 was within the Licensee Response column of the NRC Action Matrix for each quarter 2010

21 Hatch Unit 2 Assessment Results

  • Hatch Unit 2 was in the Licensee Response Column of the NRC Action Matrix at the end of the assessment period after being in the Degraded Cornerstone for the 1st-3rd quarter 2010

- Based on a previous White finding for the 1B Emergency Diesel Generator (EDG) coupling failure(1st qtr 2009) and a White finding for failure to establish and perform preventive maintenance activities to replace aged electrolytic capacitors (4th qtr 2009) 21

22 Hatch Unit 2 Assessment Results

  • A supplemental 95002 inspection was completed in August 2010 and documented in inspection report 05000321,366/2010007.
  • At the beginning of the 4th Quarter 2010, Hatch Unit 2 transitioned from the Degraded Cornerstone to the Licensee Response column of the NRC Action Matrix 22

23 23 Hatch Inspection Activities January 1 - December 31, 2010

  • Total # of Inspection Hours:

Regular Hours - 7219 hours0.0836 days <br />2.005 hours <br />0.0119 weeks <br />0.00275 months <br /> Non-Regular - 471 hours0.00545 days <br />0.131 hours <br />7.787698e-4 weeks <br />1.792155e-4 months <br />

  • Inspection Findings 1 White violation 8 Green Non-cited violations (NCVs)

24 24 Hatch Inspection Activities January 1 - December 31, 2010

  • Inspections Completed 2010

- 95002 Supplemental Inspection (Capacitors)

- Triennial Fire Inspections

- ISFI Inspections

- TI-180 Managing Fatigue

  • Unit 1 Refueling Outage - Spring 2010

25 25 Hatch Annual Assessment Summary January 1 - December 31, 2010

  • Southern Nuclear company operated Hatch Units 1 & 2 in a manner that preserved public health and safety
  • All cornerstone objectives were met with only Green findings identified

26 26 January 1 - December 31, 2010

  • NRC plans baseline inspections at Hatch for 2011 Hatch Annual Assessment Summary

27 27 Licensee Response and Remarks Dennis Madison Site Vice President E. I. Hatch

28 28 Open to the Public

  • The NRC places a high priority on keeping the public and stakeholders informed of its activities.
  • At www.nrc.gov, you can:

- Find public meeting dates and transcripts;

- Read NRC testimony, speeches, press releases, and policy decisions; and

- Access the agencys Electronic Reading Room to find NRC publications and documents.

29 What Do You Think of the ROP?

The biennial ROP external survey is coming 3rd Quarter 2011, and we want to hear from you!

Email ROPsurvey@nrc.gov to be notified when the ROP survey is available.

For information on ROP stakeholder feedback, please visit our website at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS

/program-evaluations.html#section3 29

30 30 Contacting the NRC

  • Report an emergency

- (301) 816-5100 (call collect)

  • Report a safety concern

- (800) 695-7403

- Allegation@nrc.gov

  • General information or questions

- www.nrc.gov

- Select What We Do for Public Affairs

31 31 NRC Representatives Richard Croteau, Director, Division Reactor Projects

- (404) 997-4500 William Jones, Deputy Division Director, DRP

- (404) 997-4501 Robert Martin, Project Manager, NRR

- (301) 415-1493 Eddie Morris, Senior Resident Inspector

- (912) 367-9981 David Hardage, Resident Inspector

- (912) 367-9882 Steven Rose, Senior Project Engineer

- (404) 997-4609 Scott Shaeffer, Branch Chief

- (404) 997-4521

32 32 Reference Sources

  • Reactor Oversight Process

- http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/in dex.html Public Electronic Reading Room

- http://www.nrc.gov/reading-rm.html Public Document Room 800-397-4209 (Toll Free)

NRC Strategic Plan Strategic Goals Safety: Ensure adequate protection of public health and safety and the environment.

Security: Ensure adequate protection in the secure use and management of radioactive materials.

Strategic Objectives Openness: The NRC appropriately informs and involves stakeholders in the regulatory process.

Effectiveness: NRC actions are high quality, efficient, timely, and realistic, to enable the safe and beneficial use of radioactive materials.

Operational Excellence: NRC operations use effective business methods and solutions to achieve excellence in accomplishing the agencys mission.

2 Nuclear Security &

Safeguards Physical Protection Security Inspections Force-on-Force Exercises Interagency Cooperation Intrusion Detection & Assessment Response &Offsite Assistance Threat Assessment Information Security Preventing Unauthorized Disclosure

3 Safety Review of Aging Management License Renewal Review of Environmental Impacts Opportunities for Public Participation

4 Spent Nuclear Fuel Safe and Secure Storage & Transport Assured By Comprehensive Regulations Detailed NRC Review Robust Cask & Package Designs Significant Experience Base Continued Oversight U.S. Independent Spent Fuel Storage Installations U.S. Independent Spent Fuel Storage Installations LEGEND Interstate Highways Railroads As of August 2007:

Disclaimer: This map provides only general information regarding the current and potential ISFSI licensees, based on various information sources that may be inexact and may change.

Browns Ferry Hatch Farley Grand Gulf River Bend Sequoyah Oconee Catawba McGuire Brunswick Robinson Surry North Anna Shearon Harris Vogtle Summer Crystal River Waterford Turkey Point St. Lucie Watts Bar Beaver Valley Fitzpatrick Nine Mile Pt Ginna 1

2 5

6 7 8

9 10 11 12 13 Northeast:

1. Maine Yankee
2. Seabrook
3. Vermont Yankee
4. Yankee Rowe
5. Pilgrim
6. Haddam Neck
7. Millstone
8. Indian Point
9. Susquehanna 10.Three Mile Island
11. Limerick
12. Peach Bottom
13. Oyster Creek
14. Hope Creek
15. Salem
16. Calvert Cliffs 16 Big Rock Point Davis Besse Perry Fermi Point Beach Kewaunee Monticello Prairie Island LaCross e

Zion Cook Palisade s

1 2

3 4

Midwest:

1. Dresden
2. GE Morris (wet)
3. Braidwood
4. Lasalle
5. Byron
6. Duane Arnold
7. Quad Cities
8. Clinton 5

6 7

8 Ft. Calhoun Cooper Callaway Wolf Creek Arkansas Nuclear One South Texas Project Comanche Peak DOE TMI-2 Storage DOE Idaho Spent Fuel Facility Private Fuel Storage Ft Saint Vrain (vault storage)

Humboldt Bay Trojan Columbia Rancho Seco Diablo Canyon San Onofre Palo Verde 31 Operating General Licensed ISFSIs at Reactor Sites 18 Reactor Sites Pursuing a General licensed ISFSI 15 Specific Licensed ISFSIs (At or Away from Reactor Sites)

[No known sites are pursuing a future Specific Licensed ISFSI]

19 reactor sites have not announced intentions regarding ISFSI 30 States have at least one ISFSI 15 14 4

3