ML16232A618: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:August 19, 2016  
                              NUCLEAR REGULATORY COMMISSION
                                                REGION IV
EA-15-194  
                                            1600 E. LAMAR BLVD.
                                        ARLINGTON, TX 76011-4511
Clay Warren, Acting Site Vice President  
                                            August 19, 2016
Arkansas Nuclear One
EA-15-194
Entergy Operations, Inc.  
Clay Warren, Acting Site Vice President
1448 SR 333  
Arkansas Nuclear One
Russellville, AR 72802-0967  
Entergy Operations, Inc.
1448 SR 333
SUBJECT: ARKANSAS NUCLEAR ONE - REVISED NON-CITED VIOLATION; NRC  
Russellville, AR 72802-0967
INSPECTION REPORT 05000313/2015002 AND 05000368/2015002  
SUBJECT: ARKANSAS NUCLEAR ONE - REVISED NON-CITED VIOLATION; NRC
              INSPECTION REPORT 05000313/2015002 AND 05000368/2015002
Dear Mr. Warren:  
Dear Mr. Warren:
On August 5, 2015, the U.S. Nuclear Regulatory Commission (NRC) issued NRC Inspection
On August 5, 2015, the U.S. Nuclear Regulatory Commission (NRC) issued NRC Inspection  
Report 05000313/2015002 and 05000368/2015002 that included a non-cited violation of Title 10
Report 05000313/2015002 and 05000368/2015002 that included a non-cited violation of Title 10  
of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XI, Test Control,
of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XI, Test Control,  
documenting the failure to adequately test the emergency diesel generator fuel oil transfer piping
documenting the failure to adequately test the emergency diesel generator fuel oil transfer piping  
(Agencywide Documents Access and Management System (ADAMS) ML15218A371).
(Agencywide Documents Access and Management System (ADAMS) ML15218A371).  
In a written response dated September 3, 2015 (ML15246A591), you denied the non-cited
violation (NCV 05000313/2015002-04, 05000368/2015002-04) associated with the failure to
In a written response dated September 3, 2015 (ML15246A591), you denied the non-cited  
adequately test the emergency diesel generator fuel oil transfer piping and indicated that you
violation (NCV 05000313/2015002-04, 05000368/2015002-04) associated with the failure to  
were in compliance with regulatory requirements. On October 9, 2015, the NRC acknowledged
adequately test the emergency diesel generator fuel oil transfer piping and indicated that you  
receipt of your letter (ML15282A338) and informed you that we would review the basis for your
were in compliance with regulatory requirements. On October 9, 2015, the NRC acknowledged  
denial.
receipt of your letter (ML15282A338) and informed you that we would review the basis for your  
The NRC conducted a detailed review of your response and the applicable regulatory
denial.  
requirements, in accordance with Part I, Section 2.2.8 of the NRC Enforcement Manual.
Individuals who were not involved with the original inspection effort performed this review.
The NRC conducted a detailed review of your response and the applicable regulatory  
After consideration of the bases for your denial of the non-cited violation, the NRC has concluded
requirements, in accordance with Part I, Section 2.2.8 of the NRC Enforcement Manual.
that a violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, related to the failure
Individuals who were not involved with the original inspection effort performed this review.  
to establish an adequate testing program for the emergency diesel generator fuel oil transfer
piping for Arkansas Nuclear One, Units 1 and 2, is appropriate. However, the NRC also
After consideration of the bases for your denial of the non-cited violation, the NRC has concluded  
concluded that the original non-cited violation references to 10 CFR 50.55a(g)(1) and
that a violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, related to the failure  
10 CFR 50.55a(g)(4) should be removed. Therefore, a revision to the subject NRC inspection
to establish an adequate testing program for the emergency diesel generator fuel oil transfer  
report will be issued to remove the 10 CFR 50.55a(g)(1) and 10 CFR 50.55a(g)(4) references in
piping for Arkansas Nuclear One, Units 1 and 2, is appropriate. However, the NRC also  
the non-cited violation. The details of the NRCs evaluation are contained in the enclosure.
concluded that the original non-cited violation references to 10 CFR 50.55a(g)(1) and  
In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a
10 CFR 50.55a(g)(4) should be removed. Therefore, a revision to the subject NRC inspection  
copy of this letter and its enclosure will be made available electronically for public inspection in
report will be issued to remove the 10 CFR 50.55a(g)(1) and 10 CFR 50.55a(g)(4) references in  
the NRC Public Document Room and from ADAMS, accessible from the NRC Web site at
the non-cited violation. The details of the NRCs evaluation are contained in the enclosure.  
http://www.nrc.gov/reading-rm/adams.html.
In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a  
copy of this letter and its enclosure will be made available electronically for public inspection in  
the NRC Public Document Room and from ADAMS, accessible from the NRC Web site at  
http://www.nrc.gov/reading-rm/adams.html.  
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E. LAMAR BLVD.
ARLINGTON, TX  76011-4511


C. Warren                                       -2-
C. Warren  
If you have any questions about this matter, please contact Heather Gepford, Chief, Plant Support
- 2 -  
Branch 2, Division of Reactor Safety, at 817-200-1156.
                                              Sincerely,
                                              /RA/
                                              Kriss M. Kennedy
                                              Regional Administrator
If you have any questions about this matter, please contact Heather Gepford, Chief, Plant Support  
Dockets: 50-313; 50-368
Branch 2, Division of Reactor Safety, at 817-200-1156.  
Licenses: DPR-51; NPF-6
Enclosure:
Sincerely,  
NRC Evaluation of Licensee
   Response to Non-Cited Violation
cc w/encl.: Electronic Distribution
/RA/  
Kriss M. Kennedy  
Regional Administrator  
Dockets: 50-313; 50-368
Licenses: DPR-51; NPF-6  
Enclosure:  
NRC Evaluation of Licensee
   Response to Non-Cited Violation  
cc w/encl.: Electronic Distribution  




ML16232A618
  ML16232A618  
SUNSI Review           ADAMS              Publicly Available      Non-Sensitive    Keyword:
  SUNSI Review  
By: HJG1                 Yes  No        Non-Publicly Available  Sensitive       NRC-002
By: HJG1  
OFFICE       AEA               C:PSB2           SES:ACES         RC                 TL:ACES
ADAMS
NAME         LBerger           HGepford         JKramer           KFuller           MHay
  Yes   No
SIGNATURE /RA/                 /RA/             /RA/             /RA/               /RA/
  Publicly Available
DATE         06/16/16         06/16/16         06/22/16         06/23/16           06/24/16
  Non-Publicly Available  
OFFICE       C:DRPB           D:DRS             OE               RA
  Non-Sensitive  
NAME         NOKeefe           AVegel           GFigueroa         KKennedy
Sensitive
SIGNATURE JDixon for           /RA/             /RA/             /RA/
Keyword:
DATE         07/14/16         06/30/16         07/11/16         08/19/16
NRC-002  
                                     
OFFICE  
          NRC EVALUATION OF LICENSEE RESPONSE TO NON-CITED VIOLATION
AEA  
Restatement of the Violation
C:PSB2  
Title 10 CFR Part 50, Appendix B, Criterion XI, Test Control, requires, in part, that a test
SES:ACES  
program shall be established to assure that all testing required to demonstrate that structures,
RC  
systems, and components will perform satisfactorily in service is identified and performed in
TL:ACES  
accordance with written test procedures, which incorporate the requirements and acceptance
NAME  
limits contained in applicable design documents.
LBerger  
For facilities with a construction permit issued prior to January 1, 1971, 10 CFR 50.55a(g)(1)
HGepford  
states, in part, that components (including supports) must meet the requirements of
JKramer  
paragraphs (g)(4) and (g)(5) of this section to the extent practical. Components that are part of
KFuller  
the reactor coolant pressure boundary and their supports must meet the requirements
MHay  
applicable to components that are classified as ASME Code Class 1. Other safety-related
SIGNATURE  
pressure vessels, piping, pumps and valves, and their supports must meet the requirements
/RA/  
applicable to components that are classified as ASME Code Class 2 or 3.
/RA/  
Title 10 CFR 50.55a(g)(4) states, in part, that components that are classified as ASME Code
/RA/  
Class 1, 2, and 3 must meet the requirements set forth in Section XI of the ASME Code. ASME
/RA/  
Code, Section XI, Table IWD-2500-1, Examination Category D-B, Item D2.10, requires a system
/RA/  
leakage test and a VT-2 visual examination for pressure retaining components. For buried
DATE  
components where a VT-2 visual examination cannot be performed, Table IWA-5244(b)(1)
06/16/16  
requires that the system pressure test for buried components that are isolable by means of
06/16/16  
valves shall consist of a test that determines the rate of pressure loss. Alternatively, the test
06/22/16  
may determine the change in flow between the ends of the buried components.
06/23/16  
Contrary to the above, from initial commercial operations to April 29, 2015, the licensee failed to
06/24/16  
establish a test program to assure that all testing required to demonstrate that the fuel oil
OFFICE  
transfer piping will perform satisfactorily in service is identified and performed in accordance
C:DRPB  
with written procedures, which incorporate the requirements and acceptance limits contained in
D:DRS  
applicable design documents.
OE  
Specifically, the licensee did not establish inservice inspection examinations and testing
RA  
required by 10 CFR 50.55a(g)(1) and (g)(4) and, as specified by ASME Code, Section XI,
Tables IWD-2500-1 and IWA- 5244(b)(1), to detect degradation of the fuel oil piping above
NAME  
ground and buried between the fuel oil storage tanks and the emergency diesel generator day
NOKeefe  
tanks. Since the violation is of very low safety significance and is documented in the licensees
AVegel  
corrective action program as Condition Report CR-ANO-2-2015-01092, it is being treated as a
GFigueroa  
non-cited violation, consistent with Section 2.3.2.a of the Enforcement Policy.
KKennedy  
(NCV 05000313/2015002-04, 05000368/2015002-04; Failure to Perform Testing of Diesel Fuel
Oil Transfer Piping)
SIGNATURE  
                                                                                          Enclosure
JDixon for  
/RA/  
/RA/  
/RA/  
DATE  
07/14/16  
06/30/16  
07/11/16  
08/19/16  


Summary of the Licensees Response
In response to NCV 05000313/2015002-04, 05000368/2015002-04, Failure to Perform Testing
of Diesel Fuel Oil Transfer Piping, the licensee provided a letter dated September 3, 2015,
which contested the non-cited violation. The letter provided the basis for disputing the non-cited
Enclosure
violation.
NRC EVALUATION OF LICENSEE RESPONSE TO NON-CITED VIOLATION
The licensee summarized its understanding of the specific points of the violation to be:
*  Arkansas Nuclear One Units 1 and 2 had not established and maintained an adequate
    testing program for the fuel oil transfer piping to meet the requirements of 10 CFR Part 50,
Restatement of the Violation
    Appendix B, Criterion XI, Test Control.
*  The failure to meet 10 CFR Part 50, Appendix B, Criterion XI, was caused by not including
Title 10 CFR Part 50, Appendix B, Criterion XI, Test Control, requires, in part, that a test
    the subject piping in the ASME, Section XI, boundaries and by not performing the
program shall be established to assure that all testing required to demonstrate that structures,
    inspections of ASME, Section XI, as required by the regulations cited by the NRC in
systems, and components will perform satisfactorily in service is identified and performed in
    Section 1R08.b.2 of the subject inspection report.
accordance with written test procedures, which incorporate the requirements and acceptance
The licensee denied that a violation of NRC requirements had occurred, in that, extending the
limits contained in applicable design documents.  
Units 1 and 2 ASME, Section XI, boundaries to include the diesel fuel oil piping is beyond the
plants licensing basis and exceeds the requirements of the regulations cited within the
For facilities with a construction permit issued prior to January 1, 1971, 10 CFR 50.55a(g)(1)
non-cited violation. In addition, the licensee believed that the non-cited violation inappropriately
states, in part, that components (including supports) must meet the requirements of
applied the same regulation to both units without distinguishing the regulatory uniqueness of the
paragraphs (g)(4) and (g)(5) of this section to the extent practical.  Components that are part of
units based on construction permit dates.
the reactor coolant pressure boundary and their supports must meet the requirements
The licensee further stated that the safety evaluation issued by the NRC for approval of the
applicable to components that are classified as ASME Code Class 1.  Other safety-related
extended operating period for both units determined that adequate actions were taken by the
pressure vessels, piping, pumps and valves, and their supports must meet the requirements
licensee for aging management of the diesel fuel oil system. Further, the aging management
applicable to components that are classified as ASME Code Class 2 or 3.
programs, combined with the surveillance testing required by the plants technical specifications,
provide adequate assurance that the fuel oil piping remains acceptable.
Title 10 CFR 50.55a(g)(4) states, in part, that components that are classified as ASME Code
NRC Independent Review
Class 1, 2, and 3 must meet the requirements set forth in Section XI of the ASME Code. ASME
The NRC performed an independent review of the documentation associated with this finding.
Code, Section XI, Table IWD-2500-1, Examination Category D-B, Item D2.10, requires a system
To evaluate the validity of the non-cited violation and address the licensees response to the
leakage test and a VT-2 visual examination for pressure retaining components.  For buried
non-cited violation, the review examined two key areas:
components where a VT-2 visual examination cannot be performed, Table IWA-5244(b)(1)
*  Reference to 10 CFR 50.55a(g)(1) in the non-cited violation
requires that the system pressure test for buried components that are isolable by means of
*  Assessment of compliance with 10 CFR Part 50, Appendix B, Criterion XI
valves shall consist of a test that determines the rate of pressure loss.  Alternatively, the test
Reference to 10 CFR 50.55a(g)(1) in the Non-Cited Violation
may determine the change in flow between the ends of the buried components.
When reviewing documentation during the inspection, the inspector noted the design
documents for both units fuel oil systems were dated 1970. Based on this, and the licensees
Contrary to the above, from initial commercial operations to April 29, 2015, the licensee failed to
lack of documentation demonstrating the Unit 2 diesel fuel oil system was designed under the
establish a test program to assure that all testing required to demonstrate that the fuel oil  
Unit 2 construction permit (December 6, 1972), the inspector concluded that the systems were
transfer piping will perform satisfactorily in service is identified and performed in accordance
both designed under the Unit 1 construction permit (December 6, 1968).
with written procedures, which incorporate the requirements and acceptance limits contained in
                                                  -2-
applicable design documents.  
Specifically, the licensee did not establish inservice inspection examinations and testing
required by 10 CFR 50.55a(g)(1) and (g)(4) and, as specified by ASME Code, Section XI,
Tables IWD-2500-1 and IWA- 5244(b)(1), to detect degradation of the fuel oil piping above
ground and buried between the fuel oil storage tanks and the emergency diesel generator day
tanks.  Since the violation is of very low safety significance and is documented in the licensees
corrective action program as Condition Report CR-ANO-2-2015-01092, it is being treated as a
non-cited violation, consistent with Section 2.3.2.a of the Enforcement Policy.
(NCV 05000313/2015002-04, 05000368/2015002-04; Failure to Perform Testing of Diesel Fuel
Oil Transfer Piping)  


However, with respect to the non-cited violation, the NRC has determined the date of the fuel oil
system design documents is not relevant. The requirements of 10 CFR 50.55a(g)(1) and (g)(2)
reference the date of the facilitys construction permit, not the date the system in question was
designed. Further, the NRC reviewed the Unit 2 Safety Evaluation Report, which stated, in part,
- 2 -
The date of the applicants [sic] construction permit (December 6, 1972) places this plant under
Summary of the Licensees Response
10 CFR 50.55a(g)(2)... As a result, the NRC agrees with the licensees contention that
10 CFR 50.55a(g)(1) does not apply to Unit 2. The NCV 05000368/2015002-04, as written, was
In response to NCV 05000313/2015002-04, 05000368/2015002-04, Failure to Perform Testing
incorrect.
of Diesel Fuel Oil Transfer Piping, the licensee provided a letter dated September 3, 2015,  
The NRC determined that all plants, regardless of construction permit date, are required to meet
which contested the non-cited violation.  The letter provided the basis for disputing the non-cited
the inservice inspection requirements of 10 CFR 50.55a(g)(4) and (g)(5). The NRC noted that
violation.  
paragraph 10 CFR 50.55a(g)(1) states that pre-1971 construction permit plants must meet
10 CFR 50.55a(g)(4) and (g)(5) to the extent practical. By use of the words to the extent
The licensee summarized its understanding of the specific points of the violation to be:
practical, this requirement acknowledges that when the plants were designed there was no
ASME, Section XI, and it may not be possible to meet all the inspection requirements of
*
Section XI. The NRC also noted that 10 CFR 50.55a(g)(4) explicitly excludes the design and
Arkansas Nuclear One Units 1 and 2 had not established and maintained an adequate
access provisions and preservice examination requirements specified in ASME, Section XI,
testing program for the fuel oil transfer piping to meet the requirements of 10 CFR Part 50,
thus, limiting the scope of Section XI requirements that must be met. Neither
Appendix B, Criterion XI, Test Control.
10 CFR 50.55a(g)(1) or (g)(2) were intended to change the design basis of the plant. However,
they are intended to ensure the scope of components tested for earlier licensed plants is similar
*
to those licensed later.
The failure to meet 10 CFR Part 50, Appendix B, Criterion XI, was caused by not including
The NRC reviewed guidance documents for insights on the classification of the diesel fuel oil
the subject piping in the ASME, Section XI, boundaries and by not performing the  
transfer system. Regulatory Guide 1.26, Quality Group Classifications and Standards for
inspections of ASME, Section XI, as required by the regulations cited by the NRC in
Water-, Steam-, and Radioactive-Waste-Containing Components, Revision 1, was issued in
Section 1R08.b.2 of the subject inspection report.  
September 1974. The NRC noted that Regulatory Guide 1.26 and its subsequent revisions
state that the guide should be applied to water-, steam-, and radioactive-waste-containing
The licensee denied that a violation of NRC requirements had occurred, in that, extending the  
components. The guidance further states, Other systems not covered by this guide, such as
Units 1 and 2 ASME, Section XI, boundaries to include the diesel fuel oil piping is beyond the
instrument and service air, diesel engines and their generators and auxiliary support systems,
plants licensing basis and exceeds the requirements of the regulations cited within the
diesel fuel, emergency and normal ventilation, fuel handling, and radioactive waste
non-cited violation. In addition, the licensee believed that the non-cited violation inappropriately
management systems, should be designed, fabricated, erected, and tested to quality standards
applied the same regulation to both units without distinguishing the regulatory uniqueness of the
commensurate with the safety function to be performed.
units based on construction permit dates.  
In contrast, Standard Review Plan, NUREG-75/087, dated November 24, 1975, Section 3.2.2,
System Quality Group Classification, III. Review Procedures, states, in part, There are also
The licensee further stated that the safety evaluation issued by the NRC for approval of the
systems of light-water-cooled reactors important to safety that are not identified in Regulatory
extended operating period for both units determined that adequate actions were taken by the  
Guide 1.26 and which the NRC considers should be classified Quality Group C. Examples of
licensee for aging management of the diesel fuel oil system. Further, the aging management
these systems are: diesel fuel oil system; diesel generator cooling This demonstrates one of
programs, combined with the surveillance testing required by the plants technical specifications,  
the inconsistencies identified in NRC guidance documents with respect to classification of the
provide adequate assurance that the fuel oil piping remains acceptable.  
diesel fuel oil system.
The NRC reviewed the units Safety Analysis Reports to determine whether the diesel fuel
NRC Independent Review
transfer piping was classified as equivalent to Class 3. The NRC determined that the Safety
Analysis Reports were inconsistent, which contributed to the difficulty of evaluating the validity
The NRC performed an independent review of the documentation associated with this finding.
of the non-cited violation as written. For example, the Unit 2 Safety Analysis Report,
To evaluate the validity of the non-cited violation and address the licensees response to the
Table 3.2-3, specifies the emergency diesel fuel transfer pump is Code Group C and classified
non-cited violation, the review examined two key areas: 
as ASME III, Class 3.
 
                                                -3-
*
Reference to 10 CFR 50.55a(g)(1) in the non-cited violation 
*
Assessment of compliance with 10 CFR Part 50, Appendix B, Criterion XI
Reference to 10 CFR 50.55a(g)(1) in the Non-Cited Violation
When reviewing documentation during the inspection, the inspector noted the design
documents for both units fuel oil systems were dated 1970. Based on this, and the licensees
lack of documentation demonstrating the Unit 2 diesel fuel oil system was designed under the  
Unit 2 construction permit (December 6, 1972), the inspector concluded that the systems were
both designed under the Unit 1 construction permit (December 6, 1968).  


The table includes a note that the Code Group applies to the process piping and components,
not to the instrument sensing lines. This seems to be consistent with Safety Guide 26, Quality
Group Classifications and Standards, published March 23, 1972, which states, The system
boundary includes those portions of the system required to accomplish the specified safety
- 3 -
function and connected piping up to and including the first valve (including a safety or relief
valve) that is either normally closed or capable of automatic closure when the safety function is
However, with respect to the non-cited violation, the NRC has determined the date of the fuel oil
required. Taken together, the NRC initially concluded that the Unit 2 diesel fuel transfer pump
system design documents is not relevant. The requirements of 10 CFR 50.55a(g)(1) and (g)(2)
piping was Code Group C and was classified by the licensee as ASME III, Class 3, in spite of it
reference the date of the facilitys construction permit, not the date the system in question was
being designed to ASME B31.1. (Note: The Safety Analysis Report for Unit 1 does not contain
designed. Further, the NRC reviewed the Unit 2 Safety Evaluation Report, which stated, in part,
this information on the Code Group and classification for the diesel fuel transfer pump.)
The date of the applicants [sic] construction permit (December 6, 1972) places this plant under
Relative to the non-cited violation in question, Unit 2 is subject to the requirements of
10 CFR 50.55a(g)(2)...  As a result, the NRC agrees with the licensees contention that
10 CFR 50.55a(g)(2) and, as previously stated, not required to comply with
10 CFR 50.55a(g)(1) does not apply to Unit 2. The NCV 05000368/2015002-04, as written, was
10 CFR 50.55a(g)(1). The NRC determined that all plants, regardless of construction permit
incorrect. 
date, are required to meet the inservice inspection requirements of 50.55a(g)(4) and (g)(5).
However, the NRC found that both units licensing basis was unclear as to whether the diesel
The NRC determined that all plants, regardless of construction permit date, are required to meet  
fuel oil transfer system is considered to be Code Class 3. In addition, industry standards and
the inservice inspection requirements of 10 CFR 50.55a(g)(4) and (g)(5). The NRC noted that  
the NRCs guidance have changed over the years for the diesel fuel oil transfer system. For
paragraph 10 CFR 50.55a(g)(1) states that pre-1971 construction permit plants must meet
these reasons, the NRC concluded that referencing 10 CFR 50.55a(g)(1) and (g)(4) in the
10 CFR 50.55a(g)(4) and (g)(5) to the extent practical.  By use of the words to the extent
non-cited violation confused the issue and detracted from the underlying performance
practical, this requirement acknowledges that when the plants were designed there was no
deficiency.
ASME, Section XI, and it may not be possible to meet all the inspection requirements of
Assessment of Compliance with 10 CFR Part 50, Appendix B, Criterion XI
Section XIThe NRC also noted that 10 CFR 50.55a(g)(4) explicitly excludes the design and
The violation was cited against 10 CFR Part 50, Appendix B, Criterion XI, Test Control,
access provisions and preservice examination requirements specified in ASME, Section XI,  
because the licensee did not have an adequate testing program for the fuel oil transfer piping.
thus, limiting the scope of Section XI requirements that must be met.  Neither
Notwithstanding ASME Code, Section XI, requirements, the failure to perform testing in
10 CFR 50.55a(g)(1) or (g)(2) were intended to change the design basis of the plant.  However,  
accordance with written procedures that incorporate the requirements and acceptance limits
they are intended to ensure the scope of components tested for earlier licensed plants is similar
contained in applicable design documents would be a nonconformance with 10 CFR Part 50,
to those licensed later.  
Appendix B, Criterion XI. The NRC noted that the fuel oil transfer piping for both units was
safety-related Seismic Class 1 piping, designed and built to ASME Code B31.1.0 requirements.
The NRC reviewed guidance documents for insights on the classification of the diesel fuel oil  
In the response letter, the licensee provided additional information on the testing of the fuel oil
transfer system.  Regulatory Guide 1.26, Quality Group Classifications and Standards for  
transfer piping that was not provided to the inspector during the inspection. This information
Water-, Steam-, and Radioactive-Waste-Containing Components, Revision 1, was issued in
included surveillance testing performed for the emergency diesel generator as defined by Unit 1
September 1974. The NRC noted that Regulatory Guide 1.26 and its subsequent revisions
Technical Specification Surveillance Requirement 3.8.1.6. Technical Specification Surveillance
state that the guide should be applied to water-, steam-, and radioactive-waste-containing
Requirement 3.8.1.6 states, Once every 31 days, verify the fuel oil transfer system operates to
components. The guidance further states, Other systems not covered by this guide, such as
transfer fuel oil from storage tanks to the day tank. This is further explained in the technical
instrument and service air, diesel engines and their generators and auxiliary support systems,
specification surveillance requirement bases, which states, This Surveillance demonstrates that
diesel fuel, emergency and normal ventilation, fuel handling, and radioactive waste
each required fuel oil transfer pump operates and transfers fuel oil from its associated storage
management systems, should be designed, fabricated, erected, and tested to quality standards
tank to its associated day tank. This is required to support continuous operation of standby
commensurate with the safety function to be performed.  
power sources. This Surveillance provides assurance that the fuel oil transfer pump is
OPERABLE, the fuel oil piping system is intact, and the fuel delivery piping is not obstructed.
In contrast, Standard Review Plan, NUREG-75/087, dated November 24, 1975, Section 3.2.2,
The licensee also referenced the equivalent Unit 2 surveillance testing performed for the
System Quality Group Classification, III. Review Procedures, states, in part, There are also
emergency diesel generator as defined by Technical Specification Surveillance
systems of light-water-cooled reactors important to safety that are not identified in Regulatory
Requirement 4.8.1.1.2.a.3 and 4.8.1.1.2.a.13. Specifically, Technical Specification Surveillance
Guide 1.26 and which the NRC considers should be classified Quality Group C.  Examples of
                                                -4-
these systems are:  diesel fuel oil system; diesel generator cooling  This demonstrates one of
the inconsistencies identified in NRC guidance documents with respect to classification of the
diesel fuel oil system. 
The NRC reviewed the units Safety Analysis Reports to determine whether the diesel fuel  
transfer piping was classified as equivalent to Class 3. The NRC determined that the Safety
Analysis Reports were inconsistent, which contributed to the difficulty of evaluating the validity
of the non-cited violation as written. For example, the Unit 2 Safety Analysis Report,
Table 3.2-3, specifies the emergency diesel fuel transfer pump is Code Group C and classified
as ASME III, Class 3. 


Requirement 4.8.1.1.2 states, Each diesel generator shall be demonstrated OPERABLE: a. At
least once per 31 days on a STAGGERED TEST BASIS by: 3. Verifying the fuel transfer pump
can be started and transfers fuel from the storage system to the day tank. Additionally,
Technical Specification Surveillance Requirement 4.8.1.1.2.c. states, Each diesel generator
- 4 -
shall be demonstrated OPERABLE: c. At least once per 18 months by: 13. Verifying that the fuel
transfer pump transfers fuel from each fuel storage tank to the day tank of each diesel via the
The table includes a note that the Code Group applies to the process piping and components,
installed cross connection lines.
not to the instrument sensing lines. This seems to be consistent with Safety Guide 26, Quality
The licensee further stated that the emergency diesel generator operating procedures for both
Group Classifications and Standards, published March 23, 1972, which states, The system
units contained specific instructions that require identification and disposition of leaks detected
boundary includes those portions of the system required to accomplish the specified safety
during or after surveillance tests. However, the NRC concluded that the described surveillances
function and connected piping up to and including the first valve (including a safety or relief
for Units 1 and 2 do not incorporate the requirements and acceptance limits contained in
valve) that is either normally closed or capable of automatic closure when the safety function is
applicable design documents for the fuel oil transfer piping. The NRC also noted that portions
required. Taken together, the NRC initially concluded that the Unit 2 diesel fuel transfer pump
of the piping are buried and leaks would not be evident.
piping was Code Group C and was classified by the licensee as ASME III, Class 3, in spite of it
The licensees response letter stated that programs and procedures had been established for
being designed to ASME B31.1. (Note:  The Safety Analysis Report for Unit 1 does not contain
the purpose of maintaining the diesel fuel oil transfer piping system commensurate with its
this information on the Code Group and classification for the diesel fuel transfer pump.)   
importance to safety. These procedures include monthly testing to verify the quality of the
diesel fuel oil is maintained according to the industry guidelines, including verifying that moisture
Relative to the non-cited violation in question, Unit 2 is subject to the requirements of  
is not present. The NRC agrees that ensuring a lack of moisture in the stored fuel minimizes
10 CFR 50.55a(g)(2) and, as previously stated, not required to comply with
the risk of internal corrosion; however, testing the fuel oil quality does not demonstrate that the
10 CFR 50.55a(g)(1). The NRC determined that all plants, regardless of construction permit
piping can meet its safety-related function.
date, are required to meet the inservice inspection requirements of 50.55a(g)(4) and (g)(5).
The licensee also stated that the buried piping program verifies that the external coating of the
However, the NRC found that both units licensing basis was unclear as to whether the diesel
buried portions of the piping is maintained to prevent degradation of the piping outer diameter,
fuel oil transfer system is considered to be Code Class 3. In addition, industry standards and
and functional testing of the relevant valves and pumps of the emergency diesel generating fuel
the NRCs guidance have changed over the years for the diesel fuel oil transfer system. For
oil system are included in the inservice testing program. The licensee stated that the safety
these reasons, the NRC concluded that referencing 10 CFR 50.55a(g)(1) and (g)(4) in the
evaluation issued by the NRC for approval of the extended operating period for both units
non-cited violation confused the issue and detracted from the underlying performance
determined that adequate actions were taken by the licensee for aging management of the
deficiency. 
diesel fuel oil system.
However, the NRC reviewed the licenses renewal application and noted that the buried piping
Assessment of Compliance with 10 CFR Part 50, Appendix B, Criterion XI
program only performs opportunistic inspections of the protective coating when plant
maintenance or modifications uncover portions of the piping. Further, the purpose of these
The violation was cited against 10 CFR Part 50, Appendix B, Criterion XI, Test Control,
inspections is to ensure that a loss of material due to external surface corrosion is adequately
because the licensee did not have an adequate testing program for the fuel oil transfer piping.
managed. Therefore, the NRC concluded that the buried piping program inspections do not
Notwithstanding ASME Code, Section XI, requirements, the failure to perform testing in
demonstrate the piping will perform satisfactorily in service. Specifically, these inspections do
accordance with written procedures that incorporate the requirements and acceptance limits
not demonstrate the structural integrity of the piping or that the piping continues to meet the
contained in applicable design documents would be a nonconformance with 10 CFR Part 50,
design criteria for Seismic Class 1 components or the design criteria of ASME B31.1.
Appendix B, Criterion XI. The NRC noted that the fuel oil transfer piping for both units was
In summary, the licensee offered that the aging management programs combined with the
safety-related Seismic Class 1 piping, designed and built to ASME Code B31.1.0 requirements.  
surveillance testing required by the plants technical specifications provided adequate
assurance that the fuel oil piping remains acceptable. The NRC determined that the licensees
In the response letter, the licensee provided additional information on the testing of the fuel oil
conclusion was incorrect and that a violation of 10 CFR Part 50, Appendix B, Criterion XI, Test
transfer piping that was not provided to the inspector during the inspection.  This information
Control, did occur.
included surveillance testing performed for the emergency diesel generator as defined by Unit 1  
                                                -5-
Technical Specification Surveillance Requirement 3.8.1.6.  Technical Specification Surveillance
Requirement 3.8.1.6 states, Once every 31 days, verify the fuel oil transfer system operates to
transfer fuel oil from storage tanks to the day tank.  This is further explained in the technical
specification surveillance requirement bases, which states, This Surveillance demonstrates that
each required fuel oil transfer pump operates and transfers fuel oil from its associated storage
tank to its associated day tank.  This is required to support continuous operation of standby
power sources.  This Surveillance provides assurance that the fuel oil transfer pump is
OPERABLE, the fuel oil piping system is intact, and the fuel delivery piping is not obstructed.  
The licensee also referenced the equivalent Unit 2 surveillance testing performed for the  
emergency diesel generator as defined by Technical Specification Surveillance
Requirement 4.8.1.1.2.a.3 and 4.8.1.1.2.a.13.  Specifically, Technical Specification Surveillance


NRC Conclusion
The violation was written to be applicable to both Units 1 and 2. The inclusion of reference to
10 CFR 50.55a(g)(1) in the violation was inappropriate as the construction permit dates for the
units are different. The NRC concluded that the appropriate requirement for Unit 2 was
- 5 -
10 CFR 50.55a(g)(2), rather than 10 CFR 50.55(g)(1), as cited. However, 10 CFR 50.55a(g)(4)
Requirement 4.8.1.1.2 states, Each diesel generator shall be demonstrated OPERABLE:  a. At
is applicable to both units.
least once per 31 days on a STAGGERED TEST BASIS by: 3. Verifying the fuel transfer pump
During review of this issue, the NRC found that the licensing basis for both units was unclear on
can be started and transfers fuel from the storage system to the day tank.  Additionally,
whether the diesel fuel oil transfer system should be considered equivalent to ASME Code
Technical Specification Surveillance Requirement 4.8.1.1.2.c. states, Each diesel generator
Class 3. In addition, industry standards and the NRCs guidance have changed over the years
shall be demonstrated OPERABLE: c. At least once per 18 months by: 13. Verifying that the fuel
for the diesel fuel oil system. For these reasons, the NRC concluded that referencing the
transfer pump transfers fuel from each fuel storage tank to the day tank of each diesel via the
testing requirements of 10 CFR 50.55a(g)(4) in the non-cited violation confused the issue and
installed cross connection lines.
detracted from the underlying performance deficiency.
The licensee stated that the aging management programs combined with the surveillance
The licensee further stated that the emergency diesel generator operating procedures for both
testing required by the plants technical specifications provided adequate assurance that the fuel
units contained specific instructions that require identification and disposition of leaks detected
oil piping remains acceptable. The NRC determined that the licensees conclusion was
during or after surveillance tests.  However, the NRC concluded that the described surveillances
incorrect and that a violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, did
for Units 1 and 2 do not incorporate the requirements and acceptance limits contained in
occur. Therefore, the non-cited violation is being upheld but revised to remove the references
applicable design documents for the fuel oil transfer piping.  The NRC also noted that portions
of the piping are buried and leaks would not be evident.
The licensees response letter stated that programs and procedures had been established for
the purpose of maintaining the diesel fuel oil transfer piping system commensurate with its
importance to safety.  These procedures include monthly testing to verify the quality of the
diesel fuel oil is maintained according to the industry guidelines, including verifying that moisture
is not present.  The NRC agrees that ensuring a lack of moisture in the stored fuel minimizes
the risk of internal corrosion; however, testing the fuel oil quality does not demonstrate that the
piping can meet its safety-related function. 
The licensee also stated that the buried piping program verifies that the external coating of the
buried portions of the piping is maintained to prevent degradation of the piping outer diameter,
and functional testing of the relevant valves and pumps of the emergency diesel generating fuel
oil system are included in the inservice testing program.  The licensee stated that the safety
evaluation issued by the NRC for approval of the extended operating period for both units
determined that adequate actions were taken by the licensee for aging management of the
diesel fuel oil system. 
However, the NRC reviewed the licenses renewal application and noted that the buried piping
program only performs opportunistic inspections of the protective coating when plant
maintenance or modifications uncover portions of the piping.  Further, the purpose of these
inspections is to ensure that a loss of material due to external surface corrosion is adequately
managed.  Therefore, the NRC concluded that the buried piping program inspections do not
demonstrate the piping will perform satisfactorily in service.  Specifically, these inspections do
not demonstrate the structural integrity of the piping or that the piping continues to meet the
design criteria for Seismic Class 1 components or the design criteria of ASME B31.1.
In summary, the licensee offered that the aging management programs combined with the
surveillance testing required by the plants technical specifications provided adequate
assurance that the fuel oil piping remains acceptable.  The NRC determined that the licensees
conclusion was incorrect and that a violation of 10 CFR Part 50, Appendix B, Criterion XI, Test
Control, did occur. 
 
- 6 -
NRC Conclusion  
The violation was written to be applicable to both Units 1 and 2. The inclusion of reference to  
10 CFR 50.55a(g)(1) in the violation was inappropriate as the construction permit dates for the  
units are different. The NRC concluded that the appropriate requirement for Unit 2 was  
10 CFR 50.55a(g)(2), rather than 10 CFR 50.55(g)(1), as cited. However, 10 CFR 50.55a(g)(4)  
is applicable to both units.  
During review of this issue, the NRC found that the licensing basis for both units was unclear on  
whether the diesel fuel oil transfer system should be considered equivalent to ASME Code  
Class 3. In addition, industry standards and the NRCs guidance have changed over the years  
for the diesel fuel oil system. For these reasons, the NRC concluded that referencing the  
testing requirements of 10 CFR 50.55a(g)(4) in the non-cited violation confused the issue and  
detracted from the underlying performance deficiency.  
The licensee stated that the aging management programs combined with the surveillance  
testing required by the plants technical specifications provided adequate assurance that the fuel  
oil piping remains acceptable. The NRC determined that the licensees conclusion was  
incorrect and that a violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, did  
occur. Therefore, the non-cited violation is being upheld but revised to remove the references  
to 10 CFR 50.55a(g)(1) and 10 CFR 50.55a(g)(4).
to 10 CFR 50.55a(g)(1) and 10 CFR 50.55a(g)(4).
                                                -6-
}}
}}

Latest revision as of 20:50, 9 January 2025

Revised Non Cited Violation; NRC Inspection Report 05000313/2015002 and 05000368/2015002
ML16232A618
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 08/19/2016
From: Kennedy K
Region 4 Administrator
To: Warren C
Entergy Operations
O'Keefe C
References
EA-15-194 IR 2015002
Download: ML16232A618 (9)


See also: IR 05000313/2015002

Text

August 19, 2016

EA-15-194

Clay Warren, Acting Site Vice President

Arkansas Nuclear One

Entergy Operations, Inc.

1448 SR 333

Russellville, AR 72802-0967

SUBJECT: ARKANSAS NUCLEAR ONE - REVISED NON-CITED VIOLATION; NRC

INSPECTION REPORT 05000313/2015002 AND 05000368/2015002

Dear Mr. Warren:

On August 5, 2015, the U.S. Nuclear Regulatory Commission (NRC) issued NRC Inspection

Report 05000313/2015002 and 05000368/2015002 that included a non-cited violation of Title 10

of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XI, Test Control,

documenting the failure to adequately test the emergency diesel generator fuel oil transfer piping

(Agencywide Documents Access and Management System (ADAMS) ML15218A371).

In a written response dated September 3, 2015 (ML15246A591), you denied the non-cited

violation (NCV 05000313/2015002-04, 05000368/2015002-04) associated with the failure to

adequately test the emergency diesel generator fuel oil transfer piping and indicated that you

were in compliance with regulatory requirements. On October 9, 2015, the NRC acknowledged

receipt of your letter (ML15282A338) and informed you that we would review the basis for your

denial.

The NRC conducted a detailed review of your response and the applicable regulatory

requirements, in accordance with Part I, Section 2.2.8 of the NRC Enforcement Manual.

Individuals who were not involved with the original inspection effort performed this review.

After consideration of the bases for your denial of the non-cited violation, the NRC has concluded

that a violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, related to the failure

to establish an adequate testing program for the emergency diesel generator fuel oil transfer

piping for Arkansas Nuclear One, Units 1 and 2, is appropriate. However, the NRC also

concluded that the original non-cited violation references to 10 CFR 50.55a(g)(1) and

10 CFR 50.55a(g)(4) should be removed. Therefore, a revision to the subject NRC inspection

report will be issued to remove the 10 CFR 50.55a(g)(1) and 10 CFR 50.55a(g)(4) references in

the non-cited violation. The details of the NRCs evaluation are contained in the enclosure.

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a

copy of this letter and its enclosure will be made available electronically for public inspection in

the NRC Public Document Room and from ADAMS, accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html.

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD.

ARLINGTON, TX 76011-4511

C. Warren

- 2 -

If you have any questions about this matter, please contact Heather Gepford, Chief, Plant Support

Branch 2, Division of Reactor Safety, at 817-200-1156.

Sincerely,

/RA/

Kriss M. Kennedy

Regional Administrator

Dockets: 50-313; 50-368

Licenses: DPR-51; NPF-6

Enclosure:

NRC Evaluation of Licensee

Response to Non-Cited Violation

cc w/encl.: Electronic Distribution

ML16232A618

SUNSI Review

By: HJG1

ADAMS

Yes No

Publicly Available

Non-Publicly Available

Non-Sensitive

Sensitive

Keyword:

NRC-002

OFFICE

AEA

C:PSB2

SES:ACES

RC

TL:ACES

NAME

LBerger

HGepford

JKramer

KFuller

MHay

SIGNATURE

/RA/

/RA/

/RA/

/RA/

/RA/

DATE

06/16/16

06/16/16

06/22/16

06/23/16

06/24/16

OFFICE

C:DRPB

D:DRS

OE

RA

NAME

NOKeefe

AVegel

GFigueroa

KKennedy

SIGNATURE

JDixon for

/RA/

/RA/

/RA/

DATE

07/14/16

06/30/16

07/11/16

08/19/16

Enclosure

NRC EVALUATION OF LICENSEE RESPONSE TO NON-CITED VIOLATION

Restatement of the Violation

Title 10 CFR Part 50, Appendix B, Criterion XI, Test Control, requires, in part, that a test

program shall be established to assure that all testing required to demonstrate that structures,

systems, and components will perform satisfactorily in service is identified and performed in

accordance with written test procedures, which incorporate the requirements and acceptance

limits contained in applicable design documents.

For facilities with a construction permit issued prior to January 1, 1971, 10 CFR 50.55a(g)(1)

states, in part, that components (including supports) must meet the requirements of

paragraphs (g)(4) and (g)(5) of this section to the extent practical. Components that are part of

the reactor coolant pressure boundary and their supports must meet the requirements

applicable to components that are classified as ASME Code Class 1. Other safety-related

pressure vessels, piping, pumps and valves, and their supports must meet the requirements

applicable to components that are classified as ASME Code Class 2 or 3.

Title 10 CFR 50.55a(g)(4) states, in part, that components that are classified as ASME Code

Class 1, 2, and 3 must meet the requirements set forth in Section XI of the ASME Code. ASME

Code,Section XI, Table IWD-2500-1, Examination Category D-B, Item D2.10, requires a system

leakage test and a VT-2 visual examination for pressure retaining components. For buried

components where a VT-2 visual examination cannot be performed, Table IWA-5244(b)(1)

requires that the system pressure test for buried components that are isolable by means of

valves shall consist of a test that determines the rate of pressure loss. Alternatively, the test

may determine the change in flow between the ends of the buried components.

Contrary to the above, from initial commercial operations to April 29, 2015, the licensee failed to

establish a test program to assure that all testing required to demonstrate that the fuel oil

transfer piping will perform satisfactorily in service is identified and performed in accordance

with written procedures, which incorporate the requirements and acceptance limits contained in

applicable design documents.

Specifically, the licensee did not establish inservice inspection examinations and testing

required by 10 CFR 50.55a(g)(1) and (g)(4) and, as specified by ASME Code,Section XI,

Tables IWD-2500-1 and IWA- 5244(b)(1), to detect degradation of the fuel oil piping above

ground and buried between the fuel oil storage tanks and the emergency diesel generator day

tanks. Since the violation is of very low safety significance and is documented in the licensees

corrective action program as Condition Report CR-ANO-2-2015-01092, it is being treated as a

non-cited violation, consistent with Section 2.3.2.a of the Enforcement Policy.

(NCV 05000313/2015002-04, 05000368/2015002-04; Failure to Perform Testing of Diesel Fuel

Oil Transfer Piping)

- 2 -

Summary of the Licensees Response

In response to NCV 05000313/2015002-04, 05000368/2015002-04, Failure to Perform Testing

of Diesel Fuel Oil Transfer Piping, the licensee provided a letter dated September 3, 2015,

which contested the non-cited violation. The letter provided the basis for disputing the non-cited

violation.

The licensee summarized its understanding of the specific points of the violation to be:

Arkansas Nuclear One Units 1 and 2 had not established and maintained an adequate

testing program for the fuel oil transfer piping to meet the requirements of 10 CFR Part 50,

Appendix B, Criterion XI, Test Control.

The failure to meet 10 CFR Part 50, Appendix B, Criterion XI, was caused by not including

the subject piping in the ASME,Section XI, boundaries and by not performing the

inspections of ASME,Section XI, as required by the regulations cited by the NRC in

Section 1R08.b.2 of the subject inspection report.

The licensee denied that a violation of NRC requirements had occurred, in that, extending the

Units 1 and 2 ASME,Section XI, boundaries to include the diesel fuel oil piping is beyond the

plants licensing basis and exceeds the requirements of the regulations cited within the

non-cited violation. In addition, the licensee believed that the non-cited violation inappropriately

applied the same regulation to both units without distinguishing the regulatory uniqueness of the

units based on construction permit dates.

The licensee further stated that the safety evaluation issued by the NRC for approval of the

extended operating period for both units determined that adequate actions were taken by the

licensee for aging management of the diesel fuel oil system. Further, the aging management

programs, combined with the surveillance testing required by the plants technical specifications,

provide adequate assurance that the fuel oil piping remains acceptable.

NRC Independent Review

The NRC performed an independent review of the documentation associated with this finding.

To evaluate the validity of the non-cited violation and address the licensees response to the

non-cited violation, the review examined two key areas:

Reference to 10 CFR 50.55a(g)(1) in the non-cited violation

Assessment of compliance with 10 CFR Part 50, Appendix B, Criterion XI

Reference to 10 CFR 50.55a(g)(1) in the Non-Cited Violation

When reviewing documentation during the inspection, the inspector noted the design

documents for both units fuel oil systems were dated 1970. Based on this, and the licensees

lack of documentation demonstrating the Unit 2 diesel fuel oil system was designed under the

Unit 2 construction permit (December 6, 1972), the inspector concluded that the systems were

both designed under the Unit 1 construction permit (December 6, 1968).

- 3 -

However, with respect to the non-cited violation, the NRC has determined the date of the fuel oil

system design documents is not relevant. The requirements of 10 CFR 50.55a(g)(1) and (g)(2)

reference the date of the facilitys construction permit, not the date the system in question was

designed. Further, the NRC reviewed the Unit 2 Safety Evaluation Report, which stated, in part,

The date of the applicants [sic] construction permit (December 6, 1972) places this plant under

10 CFR 50.55a(g)(2)... As a result, the NRC agrees with the licensees contention that

10 CFR 50.55a(g)(1) does not apply to Unit 2. The NCV 05000368/2015002-04, as written, was

incorrect.

The NRC determined that all plants, regardless of construction permit date, are required to meet

the inservice inspection requirements of 10 CFR 50.55a(g)(4) and (g)(5). The NRC noted that

paragraph 10 CFR 50.55a(g)(1) states that pre-1971 construction permit plants must meet

10 CFR 50.55a(g)(4) and (g)(5) to the extent practical. By use of the words to the extent

practical, this requirement acknowledges that when the plants were designed there was no

ASME,Section XI, and it may not be possible to meet all the inspection requirements of

Section XI. The NRC also noted that 10 CFR 50.55a(g)(4) explicitly excludes the design and

access provisions and preservice examination requirements specified in ASME,Section XI,

thus, limiting the scope of Section XI requirements that must be met. Neither

10 CFR 50.55a(g)(1) or (g)(2) were intended to change the design basis of the plant. However,

they are intended to ensure the scope of components tested for earlier licensed plants is similar

to those licensed later.

The NRC reviewed guidance documents for insights on the classification of the diesel fuel oil

transfer system. Regulatory Guide 1.26, Quality Group Classifications and Standards for

Water-, Steam-, and Radioactive-Waste-Containing Components, Revision 1, was issued in

September 1974. The NRC noted that Regulatory Guide 1.26 and its subsequent revisions

state that the guide should be applied to water-, steam-, and radioactive-waste-containing

components. The guidance further states, Other systems not covered by this guide, such as

instrument and service air, diesel engines and their generators and auxiliary support systems,

diesel fuel, emergency and normal ventilation, fuel handling, and radioactive waste

management systems, should be designed, fabricated, erected, and tested to quality standards

commensurate with the safety function to be performed.

In contrast, Standard Review Plan, NUREG-75/087, dated November 24, 1975, Section 3.2.2,

System Quality Group Classification, III. Review Procedures, states, in part, There are also

systems of light-water-cooled reactors important to safety that are not identified in Regulatory

Guide 1.26 and which the NRC considers should be classified Quality Group C. Examples of

these systems are: diesel fuel oil system; diesel generator cooling This demonstrates one of

the inconsistencies identified in NRC guidance documents with respect to classification of the

diesel fuel oil system.

The NRC reviewed the units Safety Analysis Reports to determine whether the diesel fuel

transfer piping was classified as equivalent to Class 3. The NRC determined that the Safety

Analysis Reports were inconsistent, which contributed to the difficulty of evaluating the validity

of the non-cited violation as written. For example, the Unit 2 Safety Analysis Report,

Table 3.2-3, specifies the emergency diesel fuel transfer pump is Code Group C and classified

as ASME III, Class 3.

- 4 -

The table includes a note that the Code Group applies to the process piping and components,

not to the instrument sensing lines. This seems to be consistent with Safety Guide 26, Quality

Group Classifications and Standards, published March 23, 1972, which states, The system

boundary includes those portions of the system required to accomplish the specified safety

function and connected piping up to and including the first valve (including a safety or relief

valve) that is either normally closed or capable of automatic closure when the safety function is

required. Taken together, the NRC initially concluded that the Unit 2 diesel fuel transfer pump

piping was Code Group C and was classified by the licensee as ASME III, Class 3, in spite of it

being designed to ASME B31.1. (Note: The Safety Analysis Report for Unit 1 does not contain

this information on the Code Group and classification for the diesel fuel transfer pump.)

Relative to the non-cited violation in question, Unit 2 is subject to the requirements of

10 CFR 50.55a(g)(2) and, as previously stated, not required to comply with

10 CFR 50.55a(g)(1). The NRC determined that all plants, regardless of construction permit

date, are required to meet the inservice inspection requirements of 50.55a(g)(4) and (g)(5).

However, the NRC found that both units licensing basis was unclear as to whether the diesel

fuel oil transfer system is considered to be Code Class 3. In addition, industry standards and

the NRCs guidance have changed over the years for the diesel fuel oil transfer system. For

these reasons, the NRC concluded that referencing 10 CFR 50.55a(g)(1) and (g)(4) in the

non-cited violation confused the issue and detracted from the underlying performance

deficiency.

Assessment of Compliance with 10 CFR Part 50, Appendix B, Criterion XI

The violation was cited against 10 CFR Part 50, Appendix B, Criterion XI, Test Control,

because the licensee did not have an adequate testing program for the fuel oil transfer piping.

Notwithstanding ASME Code,Section XI, requirements, the failure to perform testing in

accordance with written procedures that incorporate the requirements and acceptance limits

contained in applicable design documents would be a nonconformance with 10 CFR Part 50,

Appendix B, Criterion XI. The NRC noted that the fuel oil transfer piping for both units was

safety-related Seismic Class 1 piping, designed and built to ASME Code B31.1.0 requirements.

In the response letter, the licensee provided additional information on the testing of the fuel oil

transfer piping that was not provided to the inspector during the inspection. This information

included surveillance testing performed for the emergency diesel generator as defined by Unit 1

Technical Specification Surveillance Requirement 3.8.1.6. Technical Specification Surveillance

Requirement 3.8.1.6 states, Once every 31 days, verify the fuel oil transfer system operates to

transfer fuel oil from storage tanks to the day tank. This is further explained in the technical

specification surveillance requirement bases, which states, This Surveillance demonstrates that

each required fuel oil transfer pump operates and transfers fuel oil from its associated storage

tank to its associated day tank. This is required to support continuous operation of standby

power sources. This Surveillance provides assurance that the fuel oil transfer pump is

OPERABLE, the fuel oil piping system is intact, and the fuel delivery piping is not obstructed.

The licensee also referenced the equivalent Unit 2 surveillance testing performed for the

emergency diesel generator as defined by Technical Specification Surveillance

Requirement 4.8.1.1.2.a.3 and 4.8.1.1.2.a.13. Specifically, Technical Specification Surveillance

- 5 -

Requirement 4.8.1.1.2 states, Each diesel generator shall be demonstrated OPERABLE: a. At

least once per 31 days on a STAGGERED TEST BASIS by: 3. Verifying the fuel transfer pump

can be started and transfers fuel from the storage system to the day tank. Additionally,

Technical Specification Surveillance Requirement 4.8.1.1.2.c. states, Each diesel generator

shall be demonstrated OPERABLE: c. At least once per 18 months by: 13. Verifying that the fuel

transfer pump transfers fuel from each fuel storage tank to the day tank of each diesel via the

installed cross connection lines.

The licensee further stated that the emergency diesel generator operating procedures for both

units contained specific instructions that require identification and disposition of leaks detected

during or after surveillance tests. However, the NRC concluded that the described surveillances

for Units 1 and 2 do not incorporate the requirements and acceptance limits contained in

applicable design documents for the fuel oil transfer piping. The NRC also noted that portions

of the piping are buried and leaks would not be evident.

The licensees response letter stated that programs and procedures had been established for

the purpose of maintaining the diesel fuel oil transfer piping system commensurate with its

importance to safety. These procedures include monthly testing to verify the quality of the

diesel fuel oil is maintained according to the industry guidelines, including verifying that moisture

is not present. The NRC agrees that ensuring a lack of moisture in the stored fuel minimizes

the risk of internal corrosion; however, testing the fuel oil quality does not demonstrate that the

piping can meet its safety-related function.

The licensee also stated that the buried piping program verifies that the external coating of the

buried portions of the piping is maintained to prevent degradation of the piping outer diameter,

and functional testing of the relevant valves and pumps of the emergency diesel generating fuel

oil system are included in the inservice testing program. The licensee stated that the safety

evaluation issued by the NRC for approval of the extended operating period for both units

determined that adequate actions were taken by the licensee for aging management of the

diesel fuel oil system.

However, the NRC reviewed the licenses renewal application and noted that the buried piping

program only performs opportunistic inspections of the protective coating when plant

maintenance or modifications uncover portions of the piping. Further, the purpose of these

inspections is to ensure that a loss of material due to external surface corrosion is adequately

managed. Therefore, the NRC concluded that the buried piping program inspections do not

demonstrate the piping will perform satisfactorily in service. Specifically, these inspections do

not demonstrate the structural integrity of the piping or that the piping continues to meet the

design criteria for Seismic Class 1 components or the design criteria of ASME B31.1.

In summary, the licensee offered that the aging management programs combined with the

surveillance testing required by the plants technical specifications provided adequate

assurance that the fuel oil piping remains acceptable. The NRC determined that the licensees

conclusion was incorrect and that a violation of 10 CFR Part 50, Appendix B, Criterion XI, Test

Control, did occur.

- 6 -

NRC Conclusion

The violation was written to be applicable to both Units 1 and 2. The inclusion of reference to

10 CFR 50.55a(g)(1) in the violation was inappropriate as the construction permit dates for the

units are different. The NRC concluded that the appropriate requirement for Unit 2 was

10 CFR 50.55a(g)(2), rather than 10 CFR 50.55(g)(1), as cited. However, 10 CFR 50.55a(g)(4)

is applicable to both units.

During review of this issue, the NRC found that the licensing basis for both units was unclear on

whether the diesel fuel oil transfer system should be considered equivalent to ASME Code

Class 3. In addition, industry standards and the NRCs guidance have changed over the years

for the diesel fuel oil system. For these reasons, the NRC concluded that referencing the

testing requirements of 10 CFR 50.55a(g)(4) in the non-cited violation confused the issue and

detracted from the underlying performance deficiency.

The licensee stated that the aging management programs combined with the surveillance

testing required by the plants technical specifications provided adequate assurance that the fuel

oil piping remains acceptable. The NRC determined that the licensees conclusion was

incorrect and that a violation of 10 CFR Part 50, Appendix B, Criterion XI, Test Control, did

occur. Therefore, the non-cited violation is being upheld but revised to remove the references

to 10 CFR 50.55a(g)(1) and 10 CFR 50.55a(g)(4).