{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:December 1, 2016  
                            NUCLEAR REGULATORY COMMISSION
                                                REGION IV
                                            1600 E. LAMAR BLVD
                                        ARLINGTON, TX 76011-4511
Mr. Robert S. Bement  
                                          December 1, 2016
Executive Vice President Nuclear/  
Mr. Robert S. Bement
   Chief Nuclear Officer  
Executive Vice President Nuclear/
Mail Station 7602  
   Chief Nuclear Officer
Arizona Public Service Company  
Mail Station 7602
P. O. Box 52034  
Arizona Public Service Company
Phoenix, AZ 85072-2034  
P. O. Box 52034
Phoenix, AZ 85072-2034
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -  
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -
                NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND
NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND  
                EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS
EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS  
                INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)
INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)  
                AND REQUEST FOR INFORMATION
AND REQUEST FOR INFORMATION  
Dear Mr. Bement:
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC)
Dear Mr. Bement:  
staff will conduct the baseline inspection of changes, tests, experiments, and permanent
plant modifications at your Palo Verde Nuclear Generating Station, Units 1, 2, and 3, from
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC)  
February 27, 2017, to March 3, 2017. The inspection will consist of three reactor inspectors
staff will conduct the baseline inspection of changes, tests, experiments, and permanent  
from the NRCs Region IV office for one on-site week. The inspection will be conducted in
plant modifications at your Palo Verde Nuclear Generating Station, Units 1, 2, and 3, from  
accordance with NRC Inspection Procedure 71111.17T, Evaluations of Changes, Tests, and
February 27, 2017, to March 3, 2017. The inspection will consist of three reactor inspectors  
Experiments and Permanent Plant Modifications.
from the NRCs Region IV office for one on-site week. The inspection will be conducted in  
Experience has shown that this inspection is resource intensive for both the NRC inspectors
accordance with NRC Inspection Procedure 71111.17T, Evaluations of Changes, Tests, and  
and your staff. In order to minimize the impact to your on-site resources and to ensure a
Experiments and Permanent Plant Modifications.  
productive inspection, we have enclosed a request for documents needed for this inspection.
Please note that the documents are requested to be provided by February 15, 2017. Upon
Experience has shown that this inspection is resource intensive for both the NRC inspectors  
review of these documents, the inspectors will select additional documentation for review upon
and your staff. In order to minimize the impact to your on-site resources and to ensure a  
arrival. It is important that all of these documents are up-to-date and complete in order to
productive inspection, we have enclosed a request for documents needed for this inspection.
minimize the number of additional documents requested during the preparation and/or the
Please note that the documents are requested to be provided by February 15, 2017. Upon  
on-site portions of the inspection.
review of these documents, the inspectors will select additional documentation for review upon  
We have discussed the schedule for these inspection activities with your staff. If there are any
arrival. It is important that all of these documents are up-to-date and complete in order to  
questions about this inspection or the material requested, please contact the lead inspector,
minimize the number of additional documents requested during the preparation and/or the
James Drake, by telephone at 817-200-1558 or by e-mail at James.Drake@nrc.gov.
on-site portions of the inspection.  
We have discussed the schedule for these inspection activities with your staff. If there are any  
questions about this inspection or the material requested, please contact the lead inspector,  
James Drake, by telephone at 817-200-1558 or by e-mail at James.Drake@nrc.gov.  
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E. LAMAR BLVD
ARLINGTON, TX 76011-4511


R. Bement                                         -2-
R. Bement  
This letter does not contain new or amended information collection requirements subject
- 2 -  
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, control
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
This letter does not contain new or amended information collection requirements subject  
respond to, a request for information or an information collection requirement unless the
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information  
requesting document displays a currently valid Office of Management and Budget control
collection requirements were approved by the Office of Management and Budget, control  
number.
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to  
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of
respond to, a request for information or an information collection requirement unless the  
this letter and its enclosure will be available electronically for public inspection in the NRC Public
requesting document displays a currently valid Office of Management and Budget control  
Document Room or from the Publicly Available Records (PARS) component of NRC's document
number.  
system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of  
                                                  Sincerely,
this letter and its enclosure will be available electronically for public inspection in the NRC Public  
                                                  /RA/
Document Room or from the Publicly Available Records (PARS) component of NRC's document  
                                                  Thomas R. Farnholtz, Chief
system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
                                                  Engineering Branch 1
rm/adams.html (the Public Electronic Reading Room).  
                                                  Division of Reactor Safety
Docket Nos. 50-528, 50-529, 50-530
Sincerely,  
License Nos. NPF-41, NPF-51, NPF-74
Enclosure:
Request for Information
cc: Electronic Distribution
/RA/  
Thomas R. Farnholtz, Chief  
Engineering Branch 1  
Division of Reactor Safety  
Docket Nos. 50-528, 50-529, 50-530  
License Nos. NPF-41, NPF-51, NPF-74  
Enclosure:  
Request for Information  
cc: Electronic Distribution  




ML16336A832
  ML16336A832  
  SUNSI Review               ADAMS            Publicly Available      Non-Sensitive    Keyword:
SUNSI Review  
By: JDrake                   Yes  No      Non-Publicly Available   Sensitive         NRC-002
By: JDrake  
OFFICE         SRI/DRS       C/DRP/D         C/EB1
ADAMS
  NAME           JDrake       GMiller         TFarnholtz
Yes   No
  SIGNATURE /RA/               /RA/           /RA/
Publicly Available
  DATE           11/30/16     12/1/16         12/1/16
  Non-Publicly Available  
                                       
Non-Sensitive
Letter to Robert S. Bement from Thomas R. Farnholtz, dated December 1, 2016
Sensitive  
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -
Keyword:
              NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND
NRC-002  
              EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS
OFFICE  
              INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)
SRI/DRS  
              AND REQUEST FOR INFORMATION
C/DRP/D  
Electronic distribution by RIV:
C/EB1  
Regional Administrator (Kriss.Kennedy@nrc.gov)
   
Deputy Regional Administrator (Scott.Morris@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
DRP Deputy Director (Ryan.Lantz@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
NAME  
DRS Deputy Director (Jeff.Clark@nrc.gov)
JDrake  
Senior Resident Inspector (Charles.Peabody@nrc.gov)
GMiller  
Resident Inspector (David.You@nrc.gov)
TFarnholtz  
Resident Inspector (Dustin.Reinert@nrc.gov)
   
PV Administrative Assistant (Yvonne.Dubay@nrc.gov)
Branch Chief, DRP/D (Geoffrey.Miller@nrc.gov)
Senior Project Engineer, DRP/D (John.Dixon@nrc.gov)
Project Engineer, DRP/D (Brian.Parks@nrc.gov)
SIGNATURE  
Project Engineer, DRP/D (Jan.Tice@nrc.gov)
/RA/  
Public Affairs Officer (Victor.Dricks@nrc.gov)
/RA/  
Project Manager (Siva.Lingam@nrc.gov)
/RA/  
Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)
   
RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Project Engineer, DRS/IPAT (Eduardo.Uribe@nrc.gov)
DATE  
Senior Congressional Affairs Officer (Jenny.Weil@nrc.gov)
11/30/16  
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
12/1/16  
RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)
12/1/16  
RIV RSLO (Bill.Maier@nrc.gov)


                                      Request for Information
  Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications
Letter to Robert S. Bement from Thomas R. Farnholtz, dated December 1, 2016
                                              Inspection
                    Palo Verde Nuclear Generating Station, Units 1, 2, and 3
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -
Inspection Report:              05000528/2017007, 05000529/2017007, and 05000530/2017007
Inspection Dates:              February 27, 2017 to March 3, 2017
NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND
Inspection Procedure:          IP 71111.17T, Evaluations of Changes, Tests, and Experiments
EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS
                                and Permanent Plant Modifications
INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)
Lead Inspector:                 James Drake, Senior Reactor Inspector
AND REQUEST FOR INFORMATION
Information Requested for the In-Office Preparation Week
The following information should be provided to the Region IV office in hard copy or electronic
Electronic distribution by RIV:  
format or via CERTREC (preferred) by February 15, 2017, to the attention of Jim Drake. We
Regional Administrator (Kriss.Kennedy@nrc.gov)
request that you categorize the documents in your response with the numbered list below. If
Deputy Regional Administrator (Scott.Morris@nrc.gov)
only hard copies of the requested documents are available or if the electronic format is too
DRP Director (Troy.Pruett@nrc.gov)  
large, please inform the lead inspector and provide the documents on the first day of the on-site
DRP Deputy Director (Ryan.Lantz@nrc.gov)
inspection. Also, the inspectors will select specific items from the information requested below
DRS Director (Anton.Vegel@nrc.gov)
and request from your staff additional documents needed during the on-site inspection week.
DRS Deputy Director (Jeff.Clark@nrc.gov) 
We ask that the specific items requested be available and ready for review on the first day of
Senior Resident Inspector (Charles.Peabody@nrc.gov)
inspection. If you have any questions regarding this information request, please contact the
Resident Inspector (David.You@nrc.gov)
lead inspector as soon as possible.
Resident Inspector (Dustin.Reinert@nrc.gov)
    1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.
PV Administrative Assistant (Yvonne.Dubay@nrc.gov)
    2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully
Branch Chief, DRP/D (Geoffrey.Miller@nrc.gov)
        implemented changes, tests, and experiments performed since the last triennial
Senior Project Engineer, DRP/D (John.Dixon@nrc.gov)
        modification inspection that did not result in an evaluation.
Project Engineer, DRP/D (Brian.Parks@nrc.gov)  
    3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes,
Project Engineer, DRP/D (Jan.Tice@nrc.gov)
        tests, and experiments performed since the last triennial modification inspection that did
Public Affairs Officer (Victor.Dricks@nrc.gov)
        not result in an application for a license amendment.
Project Manager (Siva.Lingam@nrc.gov)
    4. A list with descriptions of all corrective action documents related to 10 CFR 50.59
Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)
        screenings and evaluations since the last triennial modification inspection.
RITS Coordinator (Marisa.Herrera@nrc.gov)
    5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations,
ACES (R4Enforcement.Resource@nrc.gov)
        including qualification dates.
Regional Counsel (Karla.Fuller@nrc.gov)
    6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or
Project Engineer, DRS/IPAT (Eduardo.Uribe@nrc.gov)
        evaluations, including qualification dates.
Senior Congressional Affairs Officer (Jenny.Weil@nrc.gov)
    7. Procedure(s) for implementing permanent plant modifications.
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
                                                                                  Enclosure
RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)
RIV RSLO (Bill.Maier@nrc.gov)  


    8. A list with descriptions of all permanent plant modifications fully implemented since the
        last triennial modification inspection.
    9. A list with descriptions of all corrective action documents related to permanent plant
        modifications fully implemented since the last triennial modification inspection.
Enclosure
    10. Current revisions of the Technical Specifications and bases and the Updated Final
Request for Information
        Safety Analysis Report.
Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications
    11. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 and
Inspection
        permanent plant modification programs.
Palo Verde Nuclear Generating Station, Units 1, 2, and 3
    12. A copy of the most recent submittal of the report containing a brief description of any
        changes, tests, and experiments, including a summary of the evaluation of each,
        required by 10 CFR 50.59(d)(2).
Inspection Report: 
    13. A list of systems and system designators and a set of one-line (i.e., simplified) system
05000528/2017007, 05000529/2017007, and 05000530/2017007
        diagrams.
Note: Descriptions should be brief, but of sufficient detail to ensure that inspectors can
Inspection Dates:
      determine the safety and/or risk significance of the screenings, evaluations, and
      modifications.
February 27, 2017 to March 3, 2017
Note: For this inspection, permanent plant modifications include permanent plant changes,
      design changes, set point changes, procedure changes, equivalency evaluations,
Inspection Procedure:
      suitability analyses, calculations, and commercial grade dedications.
IP 71111.17T, Evaluations of Changes, Tests, and Experiments
Lead Inspector Contact Information:
and Permanent Plant Modifications
James Drake
Senior Reactor Inspector
Lead Inspector:
817-200-1558
James.Drake@nrc.gov
James Drake, Senior Reactor Inspector 
Mailing Address:
U.S. NRC, Region IV
Information Requested for the In-Office Preparation Week
ATTN: James Drake
1600 East Lamar Blvd.
The following information should be provided to the Region IV office in hard copy or electronic
Arlington, TX 76011-4125
format or via CERTREC (preferred) by February 15, 2017, to the attention of Jim Drake.  We
                                              -2-
request that you categorize the documents in your response with the numbered list below.  If
only hard copies of the requested documents are available or if the electronic format is too
large, please inform the lead inspector and provide the documents on the first day of the on-site
inspection.  Also, the inspectors will select specific items from the information requested below
and request from your staff additional documents needed during the on-site inspection week. 
We ask that the specific items requested be available and ready for review on the first day of
inspection.  If you have any questions regarding this information request, please contact the
lead inspector as soon as possible.
1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.
2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully
implemented changes, tests, and experiments performed since the last triennial
modification inspection that did not result in an evaluation. 
3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes,
tests, and experiments performed since the last triennial modification inspection that did
not result in an application for a license amendment. 
4. A list with descriptions of all corrective action documents related to 10 CFR 50.59
screenings and evaluations since the last triennial modification inspection. 
5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations,
including qualification dates.
6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or
evaluations, including qualification dates.
7. Procedure(s) for implementing permanent plant modifications.
 
- 2 -
8. A list with descriptions of all permanent plant modifications fully implemented since the  
last triennial modification inspection.
9. A list with descriptions of all corrective action documents related to permanent plant  
modifications fully implemented since the last triennial modification inspection.
10. Current revisions of the Technical Specifications and bases and the Updated Final  
Safety Analysis Report.  
11. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 and  
permanent plant modification programs.  
12. A copy of the most recent submittal of the report containing a brief description of any  
changes, tests, and experiments, including a summary of the evaluation of each,  
required by 10 CFR 50.59(d)(2).  
13. A list of systems and system designators and a set of one-line (i.e., simplified) system  
diagrams.  
Note: Descriptions should be brief, but of sufficient detail to ensure that inspectors can  
determine the safety and/or risk significance of the screenings, evaluations, and  
modifications.  
Note: For this inspection, permanent plant modifications include permanent plant changes,  
design changes, set point changes, procedure changes, equivalency evaluations,  
suitability analyses, calculations, and commercial grade dedications.  
Lead Inspector Contact Information:  
James Drake
Senior Reactor Inspector  
817-200-1558  
James.Drake@nrc.gov  
Mailing Address:  
U.S. NRC, Region IV  
ATTN: James Drake  
1600 East Lamar Blvd.  
Arlington, TX 76011-4125
}}
}}

Latest revision as of 18:53, 9 January 2025

Notification of Evaluations of Changes, Tests, and Experiments, & Permanent Plant Modifications Inspection (05000528/2017007; 05000529/2017007; and 05000530/2017007) & Request for Information
ML16336A832
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 12/01/2016
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Bement R
Arizona Public Service Co
References
IR 2017007
Download: ML16336A832 (6)


See also: IR 05000528/2017007

Text

December 1, 2016

Mr. Robert S. Bement

Executive Vice President Nuclear/

Chief Nuclear Officer

Mail Station 7602

Arizona Public Service Company

P. O. Box 52034

Phoenix, AZ 85072-2034

SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -

NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND

EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS

INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)

AND REQUEST FOR INFORMATION

Dear Mr. Bement:

The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC)

staff will conduct the baseline inspection of changes, tests, experiments, and permanent

plant modifications at your Palo Verde Nuclear Generating Station, Units 1, 2, and 3, from

February 27, 2017, to March 3, 2017. The inspection will consist of three reactor inspectors

from the NRCs Region IV office for one on-site week. The inspection will be conducted in

accordance with NRC Inspection Procedure 71111.17T, Evaluations of Changes, Tests, and

Experiments and Permanent Plant Modifications.

Experience has shown that this inspection is resource intensive for both the NRC inspectors

and your staff. In order to minimize the impact to your on-site resources and to ensure a

productive inspection, we have enclosed a request for documents needed for this inspection.

Please note that the documents are requested to be provided by February 15, 2017. Upon

review of these documents, the inspectors will select additional documentation for review upon

arrival. It is important that all of these documents are up-to-date and complete in order to

minimize the number of additional documents requested during the preparation and/or the

on-site portions of the inspection.

We have discussed the schedule for these inspection activities with your staff. If there are any

questions about this inspection or the material requested, please contact the lead inspector,

James Drake, by telephone at 817-200-1558 or by e-mail at James.Drake@nrc.gov.

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD

ARLINGTON, TX 76011-4511

R. Bement

- 2 -

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, control

number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of

this letter and its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRC's document

system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 50-528, 50-529, 50-530

License Nos. NPF-41, NPF-51, NPF-74

Enclosure:

Request for Information

cc: Electronic Distribution

ML16336A832

SUNSI Review

By: JDrake

ADAMS

Yes No

Publicly Available

Non-Publicly Available

Non-Sensitive

Sensitive

Keyword:

NRC-002

OFFICE

SRI/DRS

C/DRP/D

C/EB1

NAME

JDrake

GMiller

TFarnholtz

SIGNATURE

/RA/

/RA/

/RA/

DATE

11/30/16

12/1/16

12/1/16

Letter to Robert S. Bement from Thomas R. Farnholtz, dated December 1, 2016

SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -

NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND

EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS

INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)

AND REQUEST FOR INFORMATION

Electronic distribution by RIV:

Regional Administrator (Kriss.Kennedy@nrc.gov)

Deputy Regional Administrator (Scott.Morris@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Charles.Peabody@nrc.gov)

Resident Inspector (David.You@nrc.gov)

Resident Inspector (Dustin.Reinert@nrc.gov)

PV Administrative Assistant (Yvonne.Dubay@nrc.gov)

Branch Chief, DRP/D (Geoffrey.Miller@nrc.gov)

Senior Project Engineer, DRP/D (John.Dixon@nrc.gov)

Project Engineer, DRP/D (Brian.Parks@nrc.gov)

Project Engineer, DRP/D (Jan.Tice@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Project Manager (Siva.Lingam@nrc.gov)

Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Project Engineer, DRS/IPAT (Eduardo.Uribe@nrc.gov)

Senior Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)

RIV RSLO (Bill.Maier@nrc.gov)

Enclosure

Request for Information

Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications

Inspection

Palo Verde Nuclear Generating Station, Units 1, 2, and 3

Inspection Report: 05000528/2017007, 05000529/2017007, and 05000530/2017007

Inspection Dates:

February 27, 2017 to March 3, 2017

Inspection Procedure:

IP 71111.17T, Evaluations of Changes, Tests, and Experiments

and Permanent Plant Modifications

Lead Inspector:

James Drake, Senior Reactor Inspector

Information Requested for the In-Office Preparation Week

The following information should be provided to the Region IV office in hard copy or electronic

format or via CERTREC (preferred) by February 15, 2017, to the attention of Jim Drake. We

request that you categorize the documents in your response with the numbered list below. If

only hard copies of the requested documents are available or if the electronic format is too

large, please inform the lead inspector and provide the documents on the first day of the on-site

inspection. Also, the inspectors will select specific items from the information requested below

and request from your staff additional documents needed during the on-site inspection week.

We ask that the specific items requested be available and ready for review on the first day of

inspection. If you have any questions regarding this information request, please contact the

lead inspector as soon as possible.

1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.

2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully

implemented changes, tests, and experiments performed since the last triennial

modification inspection that did not result in an evaluation.

3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes,

tests, and experiments performed since the last triennial modification inspection that did

not result in an application for a license amendment.

4. A list with descriptions of all corrective action documents related to 10 CFR 50.59

screenings and evaluations since the last triennial modification inspection.

5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations,

including qualification dates.

6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or

evaluations, including qualification dates.

7. Procedure(s) for implementing permanent plant modifications.

- 2 -

8. A list with descriptions of all permanent plant modifications fully implemented since the

last triennial modification inspection.

9. A list with descriptions of all corrective action documents related to permanent plant

modifications fully implemented since the last triennial modification inspection.

10. Current revisions of the Technical Specifications and bases and the Updated Final

Safety Analysis Report.

11. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 and

permanent plant modification programs.

12. A copy of the most recent submittal of the report containing a brief description of any

changes, tests, and experiments, including a summary of the evaluation of each,

required by 10 CFR 50.59(d)(2).

13. A list of systems and system designators and a set of one-line (i.e., simplified) system

diagrams.

Note: Descriptions should be brief, but of sufficient detail to ensure that inspectors can

determine the safety and/or risk significance of the screenings, evaluations, and

modifications.

Note: For this inspection, permanent plant modifications include permanent plant changes,

design changes, set point changes, procedure changes, equivalency evaluations,

suitability analyses, calculations, and commercial grade dedications.

Lead Inspector Contact Information:

James Drake

Senior Reactor Inspector

817-200-1558

James.Drake@nrc.gov

Mailing Address:

U.S. NRC, Region IV

ATTN: James Drake

1600 East Lamar Blvd.

Arlington, TX 76011-4125