ML19344E796: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 20: Line 20:


==Reference:==
==Reference:==
: 1. Docket.No. 50-443 and 50-444
1.
: 2. NRC letter dated April 4, 1980
Docket.No. 50-443 and 50-444 2.
: 3. IE Bulletin No. 79-03A
NRC {{letter dated|date=April 4, 1980|text=letter dated April 4, 1980}} 3.
IE Bulletin No. 79-03A


==Subject:==
==Subject:==
Line 28: Line 29:


==Dear Sir:==
==Dear Sir:==
 
We have reviewed all of the SA-312 Type 304 fusion welded stainless steel pipe specified for use in safety related system for the Seabrook Project, and have performed pipe wall thickness calculations using the 85% of the maximum allowable stress criteria defined in IE Bulletin 79-03A.
We have reviewed all of the SA-312 Type 304 fusion welded stainless steel pipe specified for use in safety related system for the Seabrook Project, and have performed pipe wall thickness calculations using the 85% of the maximum allowable stress criteria defined in IE Bulletin 79-03A. Results                               of our review indicate that we have sufficient minimum pipe wall thickness.
Results of our review indicate that we have sufficient minimum pipe wall thickness.
W6 contacted the Commission for clarification of the IE Bulletin 79-03A criteria. We were informed that if the 85% of maximum allowable stress criteria is met, examination of the piping in the field by etching is not required.
W6 contacted the Commission for clarification of the IE Bulletin 79-03A criteria. We were informed that if the 85% of maximum allowable stress criteria is met, examination of the piping in the field by etching is not required.
I If you require further information, please do not hesitate to contact us.
If you require further information, please do not hesitate to contact us.
l ery truly yours, John DeVincentis Project Manager                 k HEWatan cc: NRC Office of Inspection and Enforcement Divisien of Reactor Construction Inspection Washindton,D.C. 20555
I l
* m 8009110 d ? 8
ery truly yours, John DeVincentis Project Manager k
_. . ,_ . - - - .            - -. __    ,        .      .}}
HEWatan cc: NRC Office of Inspection and Enforcement Divisien of Reactor Construction Inspection Washindton,D.C.
20555 m
8009110 d ? 8
.}}

Latest revision as of 10:59, 24 December 2024

Responds to IE Bulletin 79-03A.Results of Review of SA-312, Type 304 fusion-welded Stainless Steel Pipe Indicate Sufficient Min Pipe Wall Thickness
ML19344E796
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 08/04/1980
From: Devincentis J
PUBLIC SERVICE CO. OF NEW HAMPSHIRE
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I), NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
IEB-79-03A, IEB-79-3A, SBN-130, NUDOCS 8009110478
Download: ML19344E796 (1)


Text

T&s-AUBLIC SERVICE Companyof New Hampshere SEAsROOK STATION Engineering Office:

20 Turnpike Road Wootborough, MA 01541 August 4, 1980 SBN-130 Ref SBU-37748 SBU-38001 T.F. B 4.2.5 U.S. Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, Pennsylvania 19406 Attention: Office of Inspection and Enforcement

Reference:

1.

Docket.No. 50-443 and 50-444 2.

NRC letter dated April 4, 1980 3.

IE Bulletin No.79-03A

Subject:

Longitudinal Weld Defects in ASME SA-312 Type 304 Stainless Steel Pipe

Dear Sir:

We have reviewed all of the SA-312 Type 304 fusion welded stainless steel pipe specified for use in safety related system for the Seabrook Project, and have performed pipe wall thickness calculations using the 85% of the maximum allowable stress criteria defined in IE Bulletin 79-03A.

Results of our review indicate that we have sufficient minimum pipe wall thickness.

W6 contacted the Commission for clarification of the IE Bulletin 79-03A criteria. We were informed that if the 85% of maximum allowable stress criteria is met, examination of the piping in the field by etching is not required.

If you require further information, please do not hesitate to contact us.

I l

ery truly yours, John DeVincentis Project Manager k