| number = ML20038D072 | | number = ML20038D072 | ||
| issue date = 12/09/1981 | | issue date = 12/09/1981 | ||
| title = Forwards Nine-Month Response to Generic Ltr 81-07,Control of Heavy Loads, in Response to NRC | | title = Forwards Nine-Month Response to Generic Ltr 81-07,Control of Heavy Loads, in Response to NRC ,Sections 2.2, 2.3 & 2.4.Special Lifting Devices & Turbine Bldg Crane Not Resolved.Completion Expected 820131 & 0701 | ||
| author name = Mayer L | | author name = Mayer L | ||
| author affiliation = NORTHERN STATES POWER CO. | | author affiliation = NORTHERN STATES POWER CO. | ||
| Line 12: | Line 12: | ||
| case reference number = REF-GTECI-A-36, REF-GTECI-SF, RTR-NUREG-0612, RTR-NUREG-612, TASK-A-36, TASK-OR | | case reference number = REF-GTECI-A-36, REF-GTECI-SF, RTR-NUREG-0612, RTR-NUREG-612, TASK-A-36, TASK-OR | ||
| document report number = GL-81-07, GL-81-7, NUDOCS 8112160039 | | document report number = GL-81-07, GL-81-7, NUDOCS 8112160039 | ||
| title reference date = 12-22-1980 | |||
| package number = ML20038D073 | | package number = ML20038D073 | ||
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE, UTILITY TO NRC | | document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE, UTILITY TO NRC | ||
| Line 19: | Line 20: | ||
=Text= | =Text= | ||
{{#Wiki_filter:- | {{#Wiki_filter:- | ||
1 q~ | 1 q~ | ||
O Northern States Power Company 4t4 Nmow Man | |||
%nneapcas unnescia r4ul Teechone 16121 330 5500 d | |||
g n | |||
V, c.' | |||
Dec embe r 9, 19 81 o [ v[.4 q | |||
* jg / | v, f | ||
Offica of Nuclear Reactor Regulation | V!/ | ||
;2; | |||
Atta: Document Control Desk | % ()4., * ((/s | ||
U S Nuc. ear Regulatory Commission | ~c A | ||
q g | |||
* jg | |||
ug b[/ | / | ||
PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 | Di rect or Q 'tig% | ||
Attached are the responses to Sections 2.2, 2.3 and 2.4 of Enclosure 3 of Mr Eisenhut's letter dated December 22, 1980, titled " Control of Heavy Loads." | Offica of Nuclear Reactor Regulation | ||
,-[ | |||
k% | |||
Atta: Document Control Desk U S Nuc. ear Regulatory Commission | |||
// | |||
J f/'j ug b[/ | |||
Washington, DC 20555 Ne_.. | |||
PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 Control of Heavy Loads (nine month submittal) | |||
Attached are the responses to Sections 2.2, 2.3 and 2.4 of Enclosure 3 of Mr Eisenhut's {{letter dated|date=December 22, 1980|text=letter dated December 22, 1980}}, titled " Control of Heavy Loads." | |||
This was first requested to be submitted nine months following the date of the above mentioned letter. NSP's letters dated April 2, 1981, July 15, 1981, and August 31, 1981 identified delays in making this submittal. | This was first requested to be submitted nine months following the date of the above mentioned letter. NSP's letters dated April 2, 1981, July 15, 1981, and August 31, 1981 identified delays in making this submittal. | ||
Two items are not resolved to date. The additional investigat ion concerning the Special Lifting Devices (see the six month submittal, August 31, 1981, page 12) has not been completed. The new target date for this investigation is January 31, 1982. The other item is the Turbine Building Crane response to Item 2.4.2(b) of the attached report. The target date for this investi-j | Two items are not resolved to date. | ||
The additional investigat ion concerning the Special Lifting Devices (see the six month submittal, August 31, 1981, page 12) has not been completed. The new target date for this investigation is January 31, 1982. The other item is the Turbine Building Crane response to Item 2.4.2(b) of the attached report. The target date for this investi-j gation is July 1, 1982. | |||
L 0 Mayer, PE Manager of Nuclear Support Services LOM/TMP/bd l | Should there be any changes in these target dates we l | ||
will notify you. | |||
O. | |||
L 0 Mayer, PE Manager of Nuclear Support Services LOM/TMP/bd l | |||
Attachment cc: Director IE-III, USNRC NRR Project Manager, NRC y | |||
O Resident Inspector, NRC G Charnoff | |||
' 3 ib 8112160039 811209 PDR ADOCK 05000282 P | |||
pyg | |||
..}} | |||
Latest revision as of 00:48, 20 December 2024
| ML20038D072 | |
| Person / Time | |
|---|---|
| Site: | Prairie Island |
| Issue date: | 12/09/1981 |
| From: | Mayer L NORTHERN STATES POWER CO. |
| To: | Office of Nuclear Reactor Regulation |
| Shared Package | |
| ML20038D073 | List: |
| References | |
| REF-GTECI-A-36, REF-GTECI-SF, RTR-NUREG-0612, RTR-NUREG-612, TASK-A-36, TASK-OR GL-81-07, GL-81-7, NUDOCS 8112160039 | |
| Download: ML20038D072 (1) | |
Text
-
1 q~
O Northern States Power Company 4t4 Nmow Man
%nneapcas unnescia r4ul Teechone 16121 330 5500 d
g n
V, c.'
Dec embe r 9, 19 81 o [ v[.4 q
v, f
V!/
- 2;
% ()4., * ((/s
~c A
q g
- jg
/
Di rect or Q 'tig%
Offica of Nuclear Reactor Regulation
,-[
k%
Atta: Document Control Desk U S Nuc. ear Regulatory Commission
//
J f/'j ug b[/
Washington, DC 20555 Ne_..
PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 Control of Heavy Loads (nine month submittal)
Attached are the responses to Sections 2.2, 2.3 and 2.4 of Enclosure 3 of Mr Eisenhut's letter dated December 22, 1980, titled " Control of Heavy Loads."
This was first requested to be submitted nine months following the date of the above mentioned letter. NSP's letters dated April 2, 1981, July 15, 1981, and August 31, 1981 identified delays in making this submittal.
Two items are not resolved to date.
The additional investigat ion concerning the Special Lifting Devices (see the six month submittal, August 31, 1981, page 12) has not been completed. The new target date for this investigation is January 31, 1982. The other item is the Turbine Building Crane response to Item 2.4.2(b) of the attached report. The target date for this investi-j gation is July 1, 1982.
Should there be any changes in these target dates we l
will notify you.
O.
L 0 Mayer, PE Manager of Nuclear Support Services LOM/TMP/bd l
Attachment cc: Director IE-III, USNRC NRR Project Manager, NRC y
O Resident Inspector, NRC G Charnoff
' 3 ib 8112160039 811209 PDR ADOCK 05000282 P