ML20135E034: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 19: Line 19:
=Text=
=Text=
{{#Wiki_filter:.
{{#Wiki_filter:.
  e
e
                                                        -11-
-11-
                                                                                                        l
trained on the apparatus. The inspector also found that the system engineer had
                                                                                                        l
been present during only two of the five relief valve tests performed on-site. The
              trained on the apparatus. The inspector also found that the system engineer had
inspector was concerned that corrective actions recommended in ONE
                been present during only two of the five relief valve tests performed on-site. The
Form 96-0306 had not been implemented and that the test data could be
              inspector was concerned that corrective actions recommended in ONE
inconsistent. Licensee management stated that mechanics very carefully and
                Form 96-0306 had not been implemented and that the test data could be
slowly raised the test stand pressure to relieve entrapped air and did not cycle the
              inconsistent. Licensee management stated that mechanics very carefully and               ;
'
              slowly raised the test stand pressure to relieve entrapped air and did not cycle the     '
valve. However, the inspector found that the procedure step which directed the
              valve. However, the inspector found that the procedure step which directed the
mechanics to " cycle the valve as necessary to remove entrapped air," was not
              mechanics to " cycle the valve as necessary to remove entrapped air," was not
sufficiently detailed to ensure mechanics performed the step as described. The
              sufficiently detailed to ensure mechanics performed the step as described. The
inspector reviewed the Unit 1 sefueling outage work packages which documented
              inspector reviewed the Unit 1 sefueling outage work packages which documented
the licensee's testing of five relief valves and noted that all four of the relief valves
              the licensee's testing of five relief valves and noted that all four of the relief valves
that passed their as-found lift setpoint tests were cycled to rerr.ove entrapped air.
              that passed their as-found lift setpoint tests were cycled to rerr.ove entrapped air.
The inspector found that the procedure was not in compliance with Code
              The inspector found that the procedure was not in compliance with Code
requirements and was therefore inadequate. This was a violation of Technical
              requirements and was therefore inadequate. This was a violation of Technical             I
Specification 4.0.5 (VIO 50-445/9612-03).
              Specification 4.0.5 (VIO 50-445/9612-03).
During the review of completed work packages, the inspector noted that mechanics
              During the review of completed work packages, the inspector noted that mechanics
had identified that the setpoint pressure specified for Component Cooling Water
              had identified that the setpoint pressure specified for Component Cooling Water           l
Relief Valve 1CC-0618 was incorrectly specified at 150 psig rather than 165 psig.
              Relief Valve 1CC-0618 was incorrectly specified at 150 psig rather than 165 psig.
The problem was corrected prior to testing. In the case of Valve 1CC-0618,the
              The problem was corrected prior to testing. In the case of Valve 1CC-0618,the             .
.
              inspector found that, while the master equipment list specified the proper setpoint,     !
inspector found that, while the master equipment list specified the proper setpoint,
              it did not reference Design Change Authorization 83254/2. This change raised the
it did not reference Design Change Authorization 83254/2. This change raised the
              set pressure to 165 psig. The planner concluded that, since the master equipment
set pressure to 165 psig. The planner concluded that, since the master equipment
              list did not icterence a design change, the code data report contained the correct
list did not icterence a design change, the code data report contained the correct
              value and specified a setpoint of 150 psig in the work package. The inspector
value and specified a setpoint of 150 psig in the work package. The inspector
              reviewed the master equipment list for other relief valves affected by the design
reviewed the master equipment list for other relief valves affected by the design
              change and found that all setpoints had been changed to the new value. When
change and found that all setpoints had been changed to the new value. When
              questioned, the planners stated that they could not rely on the master equipment
questioned, the planners stated that they could not rely on the master equipment
              list because of problems they had experienced in the past. The inspector found that
list because of problems they had experienced in the past. The inspector found that
              the lack of confidence in the master equipment list was a potential program
the lack of confidence in the master equipment list was a potential program
              weakness. The inspectors planned on reviewing the licensee's control of setpo;nts
weakness. The inspectors planned on reviewing the licensee's control of setpo;nts
              in the master equipment list as an inspection followup item (IFl 50-445(446)/9612-
in the master equipment list as an inspection followup item (IFl 50-445(446)/9612-
              04).
04).
              The inspector also found that four of the relief valve work packages listed the
The inspector also found that four of the relief valve work packages listed the
              setpoint pressure tolerance as a percentage of the setpoint rather than in psig as the
setpoint pressure tolerance as a percentage of the setpoint rather than in psig as the
              procedure step required. This required the mechanics to calculate the actual
procedure step required. This required the mechanics to calculate the actual
              setraoint tolerance in the field and the inspector concluded that this practice was an
setraoint tolerance in the field and the inspector concluded that this practice was an
              unnecessary burden to mechanics.
unnecessary burden to mechanics.
l
l
(         c. Conclusions
(
c.
Conclusions
1
1
The licensee's relief valve testing procedure did not meet the ASME Code
1
1
              The licensee's relief valve testing procedure did not meet the ASME Code
requirements for relief valve testing. The master equipment list did not provide
              requirements for relief valve testing. The master equipment list did not provide
planners with the necessary information to verify the setpoint data for relief valves
              planners with the necessary information to verify the setpoint data for relief valves
modified by a design change authorization and, as a result, one work package
              modified by a design change authorization and, as a result, one work package
9612100309 961204
      9612100309 961204
I
      PDR
PDR
                                    I
ADOCK 05000445
      G    ADOCK 05000445           i
i
                        PDR       L
G
PDR
L
}}
}}

Latest revision as of 02:16, 12 December 2024

Errata to Insp Repts 50-445/96-12 & 50-446/96-12.Page Inadvertently Omitted
ML20135E034
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/04/1996
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20135D872 List:
References
50-445-96-12, 50-446-96-12, NUDOCS 9612100309
Download: ML20135E034 (1)


See also: IR 05000445/1996012

Text

.

e

-11-

trained on the apparatus. The inspector also found that the system engineer had

been present during only two of the five relief valve tests performed on-site. The

inspector was concerned that corrective actions recommended in ONE

Form 96-0306 had not been implemented and that the test data could be

inconsistent. Licensee management stated that mechanics very carefully and

slowly raised the test stand pressure to relieve entrapped air and did not cycle the

'

valve. However, the inspector found that the procedure step which directed the

mechanics to " cycle the valve as necessary to remove entrapped air," was not

sufficiently detailed to ensure mechanics performed the step as described. The

inspector reviewed the Unit 1 sefueling outage work packages which documented

the licensee's testing of five relief valves and noted that all four of the relief valves

that passed their as-found lift setpoint tests were cycled to rerr.ove entrapped air.

The inspector found that the procedure was not in compliance with Code

requirements and was therefore inadequate. This was a violation of Technical Specification 4.0.5 (VIO 50-445/9612-03).

During the review of completed work packages, the inspector noted that mechanics

had identified that the setpoint pressure specified for Component Cooling Water

Relief Valve 1CC-0618 was incorrectly specified at 150 psig rather than 165 psig.

The problem was corrected prior to testing. In the case of Valve 1CC-0618,the

.

inspector found that, while the master equipment list specified the proper setpoint,

it did not reference Design Change Authorization 83254/2. This change raised the

set pressure to 165 psig. The planner concluded that, since the master equipment

list did not icterence a design change, the code data report contained the correct

value and specified a setpoint of 150 psig in the work package. The inspector

reviewed the master equipment list for other relief valves affected by the design

change and found that all setpoints had been changed to the new value. When

questioned, the planners stated that they could not rely on the master equipment

list because of problems they had experienced in the past. The inspector found that

the lack of confidence in the master equipment list was a potential program

weakness. The inspectors planned on reviewing the licensee's control of setpo;nts

in the master equipment list as an inspection followup item (IFl 50-445(446)/9612-

04).

The inspector also found that four of the relief valve work packages listed the

setpoint pressure tolerance as a percentage of the setpoint rather than in psig as the

procedure step required. This required the mechanics to calculate the actual

setraoint tolerance in the field and the inspector concluded that this practice was an

unnecessary burden to mechanics.

l

(

c.

Conclusions

1

The licensee's relief valve testing procedure did not meet the ASME Code

1

requirements for relief valve testing. The master equipment list did not provide

planners with the necessary information to verify the setpoint data for relief valves

modified by a design change authorization and, as a result, one work package

9612100309 961204

I

PDR

ADOCK 05000445

i

G

PDR

L