ML20153B536: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 20: Line 20:
{{#Wiki_filter:.
{{#Wiki_filter:.
.
.
                              U.S. NUCLEAR REGULATORY COMMISSION
U.S. NUCLEAR REGULATORY COMMISSION
                                            REGION I
REGION I
    Report No.   50-333/87-25
Report No.
    Docket No.   50-333
50-333/87-25
    License No. OPR-59
Docket No.
    Licensee:   Power Authority of the State of New York
50-333
                P.O. Box 41
License No. OPR-59
                Lycoming, New York 13093
Licensee:
    Facility Name:   J. A. FitzPatrick Nuclear Power Plant
Power Authority of the State of New York
    Inspection At:     Lycoming, N.Y.
P.O. Box 41
    Inspection Conducted: November 17-19, 1937
Lycoming, New York 13093
    Inspector:         k 0 b CLtt       Cotti                       3l2 h 5'8
Facility Name:
                  S. K. Chaudhary, Sen199 Reactor Engineer           ' d a't e
J. A. FitzPatrick Nuclear Power Plant
    Approved by:         [
Inspection At:
                    . R. Strosnider, Chief, MPS, EB, DRS
Lycoming, N.Y.
                                                                      J/2[88
Inspection Conducted: November 17-19, 1937
                                                                          date
Inspector:
    Inspection Summary:     Routine unannounced inspection on November 17-19, 1987
k 0 b CLtt
    (IR 50-333/87-25)
Cotti
    Areas Inspected:     Follow-up of status of open itoms, and work in response to
3l2 h 5'8
    IE Bulletin 79-14.
S. K. Chaudhary, Sen199 Reactor Engineer
    Results: No violations or deviations were identified. However, it was
' d a't e
    determined that pipe support inspections and evaluations in response to NRC
Approved by:
    bulletin 79-14 are not complete.
[
      8803220246 880315
J/2[88
      PDR   ADOCK 05000333
. R. Strosnider, Chief, MPS, EB, DRS
      G                   PDR
date
Inspection Summary:
Routine unannounced inspection on November 17-19, 1987
(IR 50-333/87-25)
Areas Inspected:
Follow-up of status of open itoms, and work in response to
IE Bulletin 79-14.
Results: No violations or deviations were identified.
However, it was
determined that pipe support inspections and evaluations in response to NRC
bulletin 79-14 are not complete.
8803220246 880315
PDR
ADOCK 05000333
G
PDR


                                      _ _ _ _ _ _ _ _ _ _
_ _ _ _ _ _ _ _ _ _
  .
.
.
                                                          Details
.
    1.0 Persons Contacted
Details
        New York Power Authority
1.0 Persons Contacted
        *R. Converse, Resident Manager
New York Power Authority
        *W. Fernandez, Superintendent of Power
*R. Converse, Resident Manager
          D. Howe, Plant Engineer
*W. Fernandez, Superintendent of Power
          R. Liseno, Planning Superintendent
D. Howe, Plant Engineer
          T. Moskalyk, Technical Services Plant Engineer
R. Liseno, Planning Superintendent
          R. Patch, QA Superintendent
T. Moskalyk, Technical Services Plant Engineer
          V. Walz, Technical Services Superintendent
R. Patch, QA Superintendent
          U.S. Nuclear Regulatory Commission
V. Walz, Technical Services Superintendent
        *A. Luptak, Senior Resident Inspector
U.S. Nuclear Regulatory Commission
        In addition to the above, the inspector also contacted other engineering,
*A. Luptak, Senior Resident Inspector
        technical, and administrative personnel during the inspection.
In addition to the above, the inspector also contacted other engineering,
        * Persons attending exit interview.
technical, and administrative personnel during the inspection.
    2.0 Inspection Scope
* Persons attending exit interview.
        This inspection covered the activities associated with the inspection and
2.0 Inspection Scope
        evaluation program for pipe supports. This program was developed in re-
This inspection covered the activities associated with the inspection and
        sponse to the IEB 79-14.
evaluation program for pipe supports. This program was developed in re-
        2.1 Follow-up on Previously Identified Items
sponse to the IEB 79-14.
              (Closed) 83-18-05, Unresolved Item: This item pertains to                                 potential
2.1 Follow-up on Previously Identified Items
              non-conformance in the re-analysis of pipe suppor t design.                                 These
(Closed) 83-18-05, Unresolved Item:
              potential inadequacies were identified by the licensee's consultant
This item pertains to potential
              in this area, Target Technology Limited. (TTL).
non-conformance in the re-analysis of pipe suppor t design.
              The consultant indicated that in the design of pipe support modifica-
These
              tions, the stresses resulting from normal loads were not verified to
potential inadequacies were identified by the licensee's consultant
              be within the code allowable. The design of the supports for seismic
in this area, Target Technology Limited. (TTL).
              loads was completed in accordance with the applicable code and there-
The consultant indicated that in the design of pipe support modifica-
              fore not in question.             Targot Technology Ltd. also identified 20
tions, the stresses resulting from normal loads were not verified to
              additional supports engineered by Stone and Webster Engineering
be within the code allowable.
              Corporation (SWEC) which had the potential for not meeting the code
The design of the supports for seismic
              allowable limit for the normal loading condition.             For the 348 pipe
loads was completed in accordance with the applicable code and there-
              supports identified by TTL as having incomplete calculation packages,
fore not in question.
              the licensee's Design and Analysis Group reanalyzed 342 of these
Targot Technology Ltd. also identified 20
              supports (6 were recently modified and reanalyzed). Based on this
additional supports engineered by Stone and Webster Engineering
                                                                              - _ _ - _ _ _ _ _ _ _ _ _
Corporation (SWEC) which had the potential for not meeting the code
allowable limit for the normal loading condition.
For the 348 pipe
supports identified by TTL as having incomplete calculation packages,
the licensee's Design and Analysis Group reanalyzed 342 of these
supports (6 were recently modified and reanalyzed).
Based on this
- _ _ - _ _ _ _ _ _ _ _ _


_
_
    .
.
                                                                                                  3
3
  .
.
      reanalysis, all 342 pipe supports were found to be satisfactory under
reanalysis, all 342 pipe supports were found to be satisfactory under
      normal operating loads and did not need any structural modifications
normal operating loads and did not need any structural modifications
      to meet the FSAR or Code requirements. For the 20 supports engineered
to meet the FSAR or Code requirements.
      by SWEC, a review by SWEC indicated that all necessary verification
For the 20 supports engineered
      calculations were made and that the supports were in compliance with
by SWEC, a review by SWEC indicated that all necessary verification
      the committed criteria.
calculations were made and that the supports were in compliance with
      To evaluate the extent of non-conformaace, the licensee visually
the committed criteria.
      examined 18 of the 20 supports identified by TTL; and re-analyzed 342
To evaluate the extent of non-conformaace, the licensee visually
      of 348 supports designed by TTL to assure the adequacy of supports to
examined 18 of the 20 supports identified by TTL; and re-analyzed 342
      withstand design loads. The licensee also retained another con-
of 348 supports designed by TTL to assure the adequacy of supports to
      sultant, United Engineers and Constructors (UE), as a third party
withstand design loads.
      reviewer of this effort.                                             The third party reviewer was to provide an
The licensee also retained another con-
      independent inspection, analysis, and evaluation of the identified
sultant, United Engineers and Constructors (UE), as a third party
      pipe supports for their adequacy of design.                                                   The inspector reviewed
reviewer of this effort.
      UEs final report (UJ-0078), dated November 11, 1983, and transmitted
The third party reviewer was to provide an
      to the licensee on August 30, 1985. This third narty review did not
independent inspection, analysis, and evaluation of the identified
      result in the identification of any safety concern in areas original-
pipe supports for their adequacy of design.
      ly identified by TTL.         This item is closed.
The inspector reviewed
      (Closed) 83-21-02, Unresolved Item: This item also is related to
UEs final report (UJ-0078), dated November 11, 1983, and transmitted
      the potential inadequacy of pipe supports identified by TTL.                                                   Inspec-
to the licensee on August 30, 1985.
      tion report 83-21 identified that the licensee's 10 CFR 21 evaluations
This third narty review did not
      were not complete and were held open for the results of the third
result in the identification of any safety concern in areas original-
      party review; also, the adequacy of the licensee's original part-21
ly identified by TTL.
      evaluation was suspect. However, subsequent NRC review as documented
This item is closed.
      in NRC memoranda, Starostecki to Eisenhut, dated December 5, 1983,
(Closed) 83-21-02, Unresolved Item:
      and December 19, 1983, determined that the licensee's evaluations
This item also is related to
      were adequate. The above conclusion also was supported by the third
the potential inadequacy of pipe supports identified by TTL.
      party (UE) review.         This item is closed.
Inspec-
      (Closed) 83-21-03, Unresolved Item: This item pertains to the
tion report 83-21 identified that the licensee's 10 CFR 21 evaluations
      adequacy of licensee action in response to a TTL letter dated
were not complete and were held open for the results of the third
      September 3, 1980, questioning the validity of pipe support design
party review; also, the adequacy of the licensee's original part-21
      by Stone and Webster Engineering Corporation (SWEC). TTL indicated
evaluation was suspect.
      in their December 20, 1982 letter that the fact that calculations
However, subsequent NRC review as documented
      had not been done to demonstrate ability to meet normal loading
in NRC memoranda, Starostecki to Eisenhut, dated December 5, 1983,
      stresses for the subject supports, had been previously brought to
and December 19, 1983, determined that the licensee's evaluations
      PASNY'S attention in a letter dated September 3, 1980 (a copy of
were adequate.
      this letter was attached). A search of licensee records did not
The above conclusion also was supported by the third
      indicate that this letter had been received or evaluated. A
party (UE) review.
      subsequent search of individual files located the original of the
This item is closed.
      September 3,1980 letter, indicating that it had in fact been
(Closed) 83-21-03, Unresolved Item:
      received. The inspector interviewed the engineer who had received
This item pertains to the
      the letter and reviewed a memo written by this engineer dated
adequacy of licensee action in response to a TTL letter dated
      October 24, 1980, indicating that an answer was required from Stone
September 3, 1980, questioning the validity of pipe support design
      and Webster to determine if their design covered the work in
by Stone and Webster Engineering Corporation (SWEC).
                        - . - - -     - - - - - - - - - - - - - - - - - - - - . _ _ _ _ _ _ _ _ _         _                   J
TTL indicated
in their December 20, 1982 letter that the fact that calculations
had not been done to demonstrate ability to meet normal loading
stresses for the subject supports, had been previously brought to
PASNY'S attention in a letter dated September 3, 1980 (a copy of
this letter was attached). A search of licensee records did not
indicate that this letter had been received or evaluated. A
subsequent search of individual files located the original of the
September 3,1980 letter, indicating that it had in fact been
received.
The inspector interviewed the engineer who had received
the letter and reviewed a memo written by this engineer dated
October 24, 1980, indicating that an answer was required from Stone
and Webster to determine if their design covered the work in
- . - - -
- - - - - - - - - - - - - - - - - - - - . _ _ _ _ _ _ _ _ _
_
J


c
c
    0
0
                                      4
4
  o
o
      question. The licensee has been unable to confirm if Stone and
question.
      Webster was contacted to evaluate and respond to the September 3,
The licensee has been unable to confirm if Stone and
      1980 letter. The adequacy of the licensee's evaluation concerning
Webster was contacted to evaluate and respond to the September 3,
      the information in this September 3, 1980 letter was unresolved
1980 letter.
      pending response from Stone and Webster.
The adequacy of the licensee's evaluation concerning
      The inspector reviewed SWEC response (PAS-26077) and determined that
the information in this September 3, 1980 letter was unresolved
      the design for the pipe supports was adequate.     This item is closed.
pending response from Stone and Webster.
      (0 pen) 84-04-05, Unresolved Item:   This item pertains to inaccuracies
The inspector reviewed SWEC response (PAS-26077) and determined that
      in "as-built" drawings used for verifying installed piping and sup-
the design for the pipe supports was adequate.
      ports in response to IE Bulletin 79-14.
This item is closed.
      During the review of the licensee's actions with respect to IEB
(0 pen) 84-04-05, Unresolved Item:
      79-14, the NRC staff identified that the licensee did not have a
This item pertains to inaccuracies
      formal written procedure documenting inspection elements used in
in "as-built" drawings used for verifying installed piping and sup-
      verifying the "as-built" condition of piping and supports.     This
ports in response to IE Bulletin 79-14.
      inadequacy of procedure had previously been identified by the
During the review of the licensee's actions with respect to IEB
      licensee's consultant, United Engineers and Constructors (UE).
79-14, the NRC staff identified that the licensee did not have a
      In November 1983, during a detailed field verification of support
formal written procedure documenting inspection elements used in
      member sizes, weld sizes and length, and bolts, UE&C identified
verifying the "as-built" condition of piping and supports.
      dimensional discrepancies in thirteen (13) out of eighteen (18)
This
      supports examined. These discrepancies included undersized welds,
inadequacy of procedure had previously been identified by the
      missing welds, and difference in steel member sizes. The licensee
licensee's consultant, United Engineers and Constructors (UE).
      forwarded these discrepancies to Stone and Webster Engineering Cor-
In November 1983, during a detailed field verification of support
      poration (SWEC) for evaluation. SWEC determined that the as-instal-
member sizes, weld sizes and length, and bolts, UE&C identified
      led piping system was acceptable for all normal and seismic loading
dimensional discrepancies in thirteen (13) out of eighteen (18)
      despite these deficiencies, and no safety concern existed.
supports examined.
      As a result of the above findings the licensee developed a program
These discrepancies included undersized welds,
      to inspect all safety-related pipe supports.     The program description
missing welds, and difference in steel member sizes.
      for the above was submitted to the NRC in May 1985. The program con-
The licensee
      sisted of two phases.     Phase I consisted of inspection and evaluation
forwarded these discrepancies to Stone and Webster Engineering Cor-
      of one hundred (100) supports, the results of which would be the
poration (SWEC) for evaluation.
      basis of the second phase effort for the remaining supports.       The
SWEC determined that the as-instal-
      proposed program covered a period of three years. In October of 1985,
led piping system was acceptable for all normal and seismic loading
      the licensee informed the NRC that phase I had been completed and
despite these deficiencies, and no safety concern existed.
      phase II of the program had been started. The rate of progress was
As a result of the above findings the licensee developed a program
      approximately 10 supports per week for the balance of 1650 supports
to inspect all safety-related pipe supports.
      included in the phase II program.
The program description
      The licensee, however, had completed only 35% of the scheduled phase
for the above was submitted to the NRC in May 1985.
      II inspection and evaluation of pipe supports by September 1987. In
The program con-
      view of the conclusion reached by the plant staff (Memo Gray to
sisted of two phases.
      Converse, September 9, 1987) that many supports with problems which
Phase I consisted of inspection and evaluation
      meet the relaxed operability criteria for the short term, might not
of one hundred (100) supports, the results of which would be the
      have met the original design code requirements, it is a concern of
basis of the second phase effort for the remaining supports.
      the NRC that pipe support evaluations have been further delayed.
The
proposed program covered a period of three years.
In October of 1985,
the licensee informed the NRC that phase I had been completed and
phase II of the program had been started.
The rate of progress was
approximately 10 supports per week for the balance of 1650 supports
included in the phase II program.
The licensee, however, had completed only 35% of the scheduled phase
II inspection and evaluation of pipe supports by September 1987.
In
view of the conclusion reached by the plant staff (Memo Gray to
Converse, September 9, 1987) that many supports with problems which
meet the relaxed operability criteria for the short term, might not
have met the original design code requirements, it is a concern of
the NRC that pipe support evaluations have been further delayed.


  O
O
.                                                       5
5
.
.
The inspector reviewed the following documents to determine the
status of the above program:
Letters, memoranda, & Office Correspondence:
-
NYPA to NRC, JPN-83-65, dated 7/7/83
A.C. Pal to L. Gusquil, dated 8/16/83
-
-
NYPA to NRC, JPN-83-79, dated 9/1/83
-
United Engineers to NYPA, UJ-0049, dated 11/11/83
-
NYPA to NRC, JPN-83-100, dated 12/19/83
-
NYPA to NRC, JPN-84-02, dated 1/20/84
-
NYPA to NRC, JPN-85-38, dated 5/2/85
-
NRC to NYPA, (Vassallo to Brons), dated 7/22/85
-
L. Guaquil to J. Gray, JAF-85-253, dated 9/3/85
-
NYPA to NRC, JPN-85-68, dated 10/1/85
-
R. Converse to J. Gray, JAFP-87-0716, dated 9/9/87
Pipe Support Task Force, Project Plan. Rev. 1.
Pipe Support Evaluation-Phase 2, Work Tracking Log.
Based on the above review, discussion, and personal observation, the
inspector determined that this item has not been resolved.
This
item therefore remains open.
3.0 Exit Interview
The inspector met with the licensee at the conclusion of the inspection
on 11/19/87, at which time the inspector summarized the scope and the
findings of this inspection.
At no time during this inspection did the inspector provide any written
material to the licensee.
The licensee did not indicate that proprietary
information was included in the scope of this inspection.
_ . _ . . . . .
.
.
                          The inspector reviewed the following documents to determine the
-
                          status of the above program:
                          Letters, memoranda, & Office Correspondence:
                          -
                                NYPA to NRC, JPN-83-65, dated 7/7/83
                          -
                                A.C. Pal to L. Gusquil, dated 8/16/83
                          -
                                NYPA to NRC, JPN-83-79, dated 9/1/83
                          -
                                United Engineers to NYPA, UJ-0049, dated 11/11/83
                          -
                                NYPA to NRC, JPN-83-100, dated 12/19/83
                          -
                                NYPA to NRC, JPN-84-02, dated 1/20/84
                          -
                                NYPA to NRC, JPN-85-38, dated 5/2/85
                          -
                                NRC to NYPA, (Vassallo to Brons), dated 7/22/85
                          -
                                L. Guaquil to J. Gray, JAF-85-253, dated 9/3/85
                          -
                                NYPA to NRC, JPN-85-68, dated 10/1/85
                          -
                                R. Converse to J. Gray, JAFP-87-0716, dated 9/9/87
                          Pipe Support Task Force, Project Plan. Rev. 1.
                          Pipe Support Evaluation-Phase 2, Work Tracking Log.
                          Based on the above review, discussion, and personal observation, the
                          inspector determined that this item has not been resolved.      This
                          item therefore remains open.
    3.0 Exit Interview
                    The inspector met with the licensee at the conclusion of the inspection
                    on 11/19/87, at which time the inspector summarized the scope and the
                    findings of this inspection.
                    At no time during this inspection did the inspector provide any written
                    material to the licensee. The licensee did not indicate that proprietary
                    information was included in the scope of this inspection.
    _ . _ . . . . .              .
                                                                                              -
}}
}}

Latest revision as of 03:16, 11 December 2024

Insp Rept 50-333/87-25 on 871117-19.No Violations Noted. Major Areas Inspected:Followup of Status of Open Items & Work in Response to IE Bulletin 79-14
ML20153B536
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 03/02/1988
From: Chaudhary S, Strosnider J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20153B534 List:
References
50-333-87-25, IEB-79-14, NUDOCS 8803220246
Download: ML20153B536 (5)


See also: IR 05000333/1987025

Text

.

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

50-333/87-25

Docket No.

50-333

License No. OPR-59

Licensee:

Power Authority of the State of New York

P.O. Box 41

Lycoming, New York 13093

Facility Name:

J. A. FitzPatrick Nuclear Power Plant

Inspection At:

Lycoming, N.Y.

Inspection Conducted: November 17-19, 1937

Inspector:

k 0 b CLtt

Cotti

3l2 h 5'8

S. K. Chaudhary, Sen199 Reactor Engineer

' d a't e

Approved by:

[

J/2[88

. R. Strosnider, Chief, MPS, EB, DRS

date

Inspection Summary:

Routine unannounced inspection on November 17-19, 1987

(IR 50-333/87-25)

Areas Inspected:

Follow-up of status of open itoms, and work in response to

IE Bulletin 79-14.

Results: No violations or deviations were identified.

However, it was

determined that pipe support inspections and evaluations in response to NRC

bulletin 79-14 are not complete.

8803220246 880315

PDR

ADOCK 05000333

G

PDR

_ _ _ _ _ _ _ _ _ _

.

.

Details

1.0 Persons Contacted

New York Power Authority

  • R. Converse, Resident Manager
  • W. Fernandez, Superintendent of Power

D. Howe, Plant Engineer

R. Liseno, Planning Superintendent

T. Moskalyk, Technical Services Plant Engineer

R. Patch, QA Superintendent

V. Walz, Technical Services Superintendent

U.S. Nuclear Regulatory Commission

  • A. Luptak, Senior Resident Inspector

In addition to the above, the inspector also contacted other engineering,

technical, and administrative personnel during the inspection.

  • Persons attending exit interview.

2.0 Inspection Scope

This inspection covered the activities associated with the inspection and

evaluation program for pipe supports. This program was developed in re-

sponse to the IEB 79-14.

2.1 Follow-up on Previously Identified Items

(Closed) 83-18-05, Unresolved Item:

This item pertains to potential

non-conformance in the re-analysis of pipe suppor t design.

These

potential inadequacies were identified by the licensee's consultant

in this area, Target Technology Limited. (TTL).

The consultant indicated that in the design of pipe support modifica-

tions, the stresses resulting from normal loads were not verified to

be within the code allowable.

The design of the supports for seismic

loads was completed in accordance with the applicable code and there-

fore not in question.

Targot Technology Ltd. also identified 20

additional supports engineered by Stone and Webster Engineering

Corporation (SWEC) which had the potential for not meeting the code

allowable limit for the normal loading condition.

For the 348 pipe

supports identified by TTL as having incomplete calculation packages,

the licensee's Design and Analysis Group reanalyzed 342 of these

supports (6 were recently modified and reanalyzed).

Based on this

- _ _ - _ _ _ _ _ _ _ _ _

_

.

3

.

reanalysis, all 342 pipe supports were found to be satisfactory under

normal operating loads and did not need any structural modifications

to meet the FSAR or Code requirements.

For the 20 supports engineered

by SWEC, a review by SWEC indicated that all necessary verification

calculations were made and that the supports were in compliance with

the committed criteria.

To evaluate the extent of non-conformaace, the licensee visually

examined 18 of the 20 supports identified by TTL; and re-analyzed 342

of 348 supports designed by TTL to assure the adequacy of supports to

withstand design loads.

The licensee also retained another con-

sultant, United Engineers and Constructors (UE), as a third party

reviewer of this effort.

The third party reviewer was to provide an

independent inspection, analysis, and evaluation of the identified

pipe supports for their adequacy of design.

The inspector reviewed

UEs final report (UJ-0078), dated November 11, 1983, and transmitted

to the licensee on August 30, 1985.

This third narty review did not

result in the identification of any safety concern in areas original-

ly identified by TTL.

This item is closed.

(Closed) 83-21-02, Unresolved Item:

This item also is related to

the potential inadequacy of pipe supports identified by TTL.

Inspec-

tion report 83-21 identified that the licensee's 10 CFR 21 evaluations

were not complete and were held open for the results of the third

party review; also, the adequacy of the licensee's original part-21

evaluation was suspect.

However, subsequent NRC review as documented

in NRC memoranda, Starostecki to Eisenhut, dated December 5, 1983,

and December 19, 1983, determined that the licensee's evaluations

were adequate.

The above conclusion also was supported by the third

party (UE) review.

This item is closed.

(Closed) 83-21-03, Unresolved Item:

This item pertains to the

adequacy of licensee action in response to a TTL letter dated

September 3, 1980, questioning the validity of pipe support design

by Stone and Webster Engineering Corporation (SWEC).

TTL indicated

in their December 20, 1982 letter that the fact that calculations

had not been done to demonstrate ability to meet normal loading

stresses for the subject supports, had been previously brought to

PASNY'S attention in a letter dated September 3, 1980 (a copy of

this letter was attached). A search of licensee records did not

indicate that this letter had been received or evaluated. A

subsequent search of individual files located the original of the

September 3,1980 letter, indicating that it had in fact been

received.

The inspector interviewed the engineer who had received

the letter and reviewed a memo written by this engineer dated

October 24, 1980, indicating that an answer was required from Stone

and Webster to determine if their design covered the work in

- . - - -

- - - - - - - - - - - - - - - - - - - - . _ _ _ _ _ _ _ _ _

_

J

c

0

4

o

question.

The licensee has been unable to confirm if Stone and

Webster was contacted to evaluate and respond to the September 3,

1980 letter.

The adequacy of the licensee's evaluation concerning

the information in this September 3, 1980 letter was unresolved

pending response from Stone and Webster.

The inspector reviewed SWEC response (PAS-26077) and determined that

the design for the pipe supports was adequate.

This item is closed.

(0 pen) 84-04-05, Unresolved Item:

This item pertains to inaccuracies

in "as-built" drawings used for verifying installed piping and sup-

ports in response to IE Bulletin 79-14.

During the review of the licensee's actions with respect to IEB 79-14, the NRC staff identified that the licensee did not have a

formal written procedure documenting inspection elements used in

verifying the "as-built" condition of piping and supports.

This

inadequacy of procedure had previously been identified by the

licensee's consultant, United Engineers and Constructors (UE).

In November 1983, during a detailed field verification of support

member sizes, weld sizes and length, and bolts, UE&C identified

dimensional discrepancies in thirteen (13) out of eighteen (18)

supports examined.

These discrepancies included undersized welds,

missing welds, and difference in steel member sizes.

The licensee

forwarded these discrepancies to Stone and Webster Engineering Cor-

poration (SWEC) for evaluation.

SWEC determined that the as-instal-

led piping system was acceptable for all normal and seismic loading

despite these deficiencies, and no safety concern existed.

As a result of the above findings the licensee developed a program

to inspect all safety-related pipe supports.

The program description

for the above was submitted to the NRC in May 1985.

The program con-

sisted of two phases.

Phase I consisted of inspection and evaluation

of one hundred (100) supports, the results of which would be the

basis of the second phase effort for the remaining supports.

The

proposed program covered a period of three years.

In October of 1985,

the licensee informed the NRC that phase I had been completed and

phase II of the program had been started.

The rate of progress was

approximately 10 supports per week for the balance of 1650 supports

included in the phase II program.

The licensee, however, had completed only 35% of the scheduled phase

II inspection and evaluation of pipe supports by September 1987.

In

view of the conclusion reached by the plant staff (Memo Gray to

Converse, September 9, 1987) that many supports with problems which

meet the relaxed operability criteria for the short term, might not

have met the original design code requirements, it is a concern of

the NRC that pipe support evaluations have been further delayed.

O

5

.

.

The inspector reviewed the following documents to determine the

status of the above program:

Letters, memoranda, & Office Correspondence:

-

NYPA to NRC, JPN-83-65, dated 7/7/83

A.C. Pal to L. Gusquil, dated 8/16/83

-

-

NYPA to NRC, JPN-83-79, dated 9/1/83

-

United Engineers to NYPA, UJ-0049, dated 11/11/83

-

NYPA to NRC, JPN-83-100, dated 12/19/83

-

NYPA to NRC, JPN-84-02, dated 1/20/84

-

NYPA to NRC, JPN-85-38, dated 5/2/85

-

NRC to NYPA, (Vassallo to Brons), dated 7/22/85

-

L. Guaquil to J. Gray, [[::JAF-85-253|JAF-85-253]], dated 9/3/85

-

NYPA to NRC, JPN-85-68, dated 10/1/85

-

R. Converse to J. Gray, JAFP-87-0716, dated 9/9/87

Pipe Support Task Force, Project Plan. Rev. 1.

Pipe Support Evaluation-Phase 2, Work Tracking Log.

Based on the above review, discussion, and personal observation, the

inspector determined that this item has not been resolved.

This

item therefore remains open.

3.0 Exit Interview

The inspector met with the licensee at the conclusion of the inspection

on 11/19/87, at which time the inspector summarized the scope and the

findings of this inspection.

At no time during this inspection did the inspector provide any written

material to the licensee.

The licensee did not indicate that proprietary

information was included in the scope of this inspection.

_ . _ . . . . .

.

-