ML21132A095: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot change) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter:May 12, 2021 | {{#Wiki_filter:May 12, 2021 | ||
Mr. Rod L. Penfield | |||
Site Vice President | Mr. Rod L. Penfield | ||
Energy Harbor Nuclear Corp. | Site Vice President | ||
Perry Nuclear Power Plant | Energy Harbor Nuclear Corp. | ||
10 Center Road | Perry Nuclear Power Plant | ||
Perry, OH 44081 | 10 Center Road | ||
SUBJECT: | Perry, OH 44081 | ||
Dear Mr. Penfield: | SUBJECT: | ||
On March 31, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection | PERRY NUCLEAR POWER PLANT - INTEGRATED INSPECTION REPORT | ||
at Perry Nuclear Power Plant. On April 28, 2021, the NRC inspectors discussed the results of | 05000440/2021001 | ||
this inspection with you and other members of your staff. The results of this inspection are | |||
documented in the enclosed report. | Dear Mr. Penfield: | ||
One finding of very low safety significance (Green) is documented in this report. This finding | |||
involved a violation of NRC requirements. We are treating this violation as a non-cited violation | On March 31, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection | ||
(NCV) consistent with Section 2.3.2 of the Enforcement Policy. | at Perry Nuclear Power Plant. On April 28, 2021, the NRC inspectors discussed the results of | ||
If you contest the violation or the significance or severity of the violation documented in this | this inspection with you and other members of your staff. The results of this inspection are | ||
inspection report, you should provide a response within 30 days of the date of this inspection | documented in the enclosed report. | ||
report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: | |||
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional | One finding of very low safety significance (Green) is documented in this report. This finding | ||
Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector | involved a violation of NRC requirements. We are treating this violation as a non-cited violation | ||
at Perry Nuclear Power Plant. | (NCV) consistent with Section 2.3.2 of the Enforcement Policy. | ||
If you disagree with a cross-cutting aspect assignment in this report, you should provide a | |||
response within 30 days of the date of this inspection report, with the basis for your | If you contest the violation or the significance or severity of the violation documented in this | ||
disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, | inspection report, you should provide a response within 30 days of the date of this inspection | ||
Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the | report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: | ||
NRC Resident Inspector at Perry Nuclear Power Plant. | Document Control Desk, Washington, DC 20555-0001; with copies to the Regional | ||
Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector | |||
at Perry Nuclear Power Plant. | |||
If you disagree with a cross-cutting aspect assignment in this report, you should provide a | |||
response within 30 days of the date of this inspection report, with the basis for your | |||
disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, | |||
Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the | |||
NRC Resident Inspector at Perry Nuclear Power Plant. | |||
R. Penfield | R. Penfield | ||
This letter, its enclosure, and your response (if any) will be made available for public inspection | 2 | ||
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document | |||
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public | This letter, its enclosure, and your response (if any) will be made available for public inspection | ||
Inspections, Exemptions, Requests for Withholding. | and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document | ||
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public | |||
Inspections, Exemptions, Requests for Withholding. | |||
Sincerely, | |||
Docket No. 05000440 | /RA/ | ||
License No. NPF-58 | |||
Enclosure: | |||
As stated | Billy C. Dickson, Jr., Chief | ||
cc w/ encl: Distribution via LISTSERV | Branch 2 | ||
Division of Reactor Projects | |||
Docket No. 05000440 | |||
License No. NPF-58 | |||
Enclosure: | |||
As stated | |||
cc w/ encl: Distribution via LISTSERV | |||
ML21132A095 | ML21132A095 | ||
SUNSI Review | |||
OFFICE RIII | Non-Sensitive | ||
NAME | Sensitive | ||
DATE | |||
Publicly Available | |||
Non-Publicly Available | |||
OFFICE RIII | |||
RIII | |||
NAME | |||
RRiuz:ve via email | |||
BDickson via email | |||
DATE | |||
5/11/2021 | |||
5/12/2021 | |||
Enclosure | |||
U.S. NUCLEAR REGULATORY COMMISSION | |||
Inspection Report | |||
Docket Number: | |||
05000440 | |||
License Number: | |||
NPF-58 | |||
Report Number: | |||
05000440/2021001 | |||
Enterprise Identifier: I-2021-001-0045 | |||
Licensee: | |||
Energy Harbor Nuclear Corp. | |||
Facility: | |||
Perry Nuclear Power Plant | |||
Location: | |||
Perry, Ohio | |||
Inspection Dates: | |||
January 01, 2021 to March 31, 2021 | |||
Inspectors: | |||
S. Bell, Health Physicist | |||
V. Myers, Senior Health Physicist | |||
J. Neurauter, Senior Reactor Inspector | |||
T. Ospino, Resident Inspector | |||
J. Steffes, Senior Resident Inspector | |||
T. Taylor, Fermi Resident Inspector | |||
Approved By: | |||
Billy C. Dickson, Jr., Chief | |||
Branch 2 | |||
Division of Reactor Projects | |||
PLANT STATUS | |||
Perry Nuclear Power Plant began the inspection period at 97 percent of rated thermal power in | 2 | ||
coastdown operations before a refueling outage. On January 10, 2021, the 1B feedwater heater | |||
isolated. The isolation resulted in a power perturbation. In response to the power perturbation | SUMMARY | ||
and feedwater heater isolation, the operators lowered reactor power to 79 percent to maintain | |||
margin to thermal limits per abnormal operating procedures. High water level conditions caused | The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees | ||
the heater isolation. The high-water level condition resulted from a failed circuit card in the level | performance by conducting an integrated inspection at Perry Nuclear Power Plant, in | ||
transmitter for the alternate level controller. Operators restored level using the normal level | accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs | ||
controller. The operators returned the unit to maximum attainable power and continued | program for overseeing the safe operation of commercial nuclear power reactors. Refer to | ||
coastdown operations on January 11, 2021. On March 6, 2021, operators shutdown the | https://www.nrc.gov/reactors/operating/oversight.html for more information. | ||
reactor to commence refueling outage 1R18. The reactor remained shut down in the refueling | |||
outage for the remainder of the inspection period. | List of Findings and Violations | ||
INSPECTION SCOPES | |||
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in | Human Performance Error Resulted in Unplanned RCIC Unavailability | ||
effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with | Cornerstone | ||
Significance | |||
Cross-Cutting | |||
Aspect | |||
Report | |||
Section | |||
Mitigating | |||
Systems | |||
Green | |||
NCV 05000440/2021001-01 | |||
Open/Closed | |||
[H.12] - Avoid | |||
Complacency | |||
71111.22 | |||
A finding of very low safety significance (Green) and associated non-cited violation of | |||
TS 5.4.1, "Procedures," was self-revealed on January 19, 2021, when an unexpected isolation | |||
of the RCIC steam supply occurred. Specifically, during performance of SVI-E31-T5395A, | |||
"RCIC Steam Line Flow High Channel Functional for E31-N684A," Revision 8, the licensee | |||
failed to lift the lead from terminal B4 for relay 1E51-K24, resulting in the closure of the RCIC | |||
steam supply outboard valve and an unplanned limiting condition for operation (LCO) entry | |||
and unavailability of the RCIC system. | |||
Additional Tracking Items | |||
None. | |||
3 | |||
PLANT STATUS | |||
Perry Nuclear Power Plant began the inspection period at 97 percent of rated thermal power in | |||
coastdown operations before a refueling outage. On January 10, 2021, the 1B feedwater heater | |||
isolated. The isolation resulted in a power perturbation. In response to the power perturbation | |||
and feedwater heater isolation, the operators lowered reactor power to 79 percent to maintain | |||
margin to thermal limits per abnormal operating procedures. High water level conditions caused | |||
the heater isolation. The high-water level condition resulted from a failed circuit card in the level | |||
transmitter for the alternate level controller. Operators restored level using the normal level | |||
controller. The operators returned the unit to maximum attainable power and continued | |||
coastdown operations on January 11, 2021. On March 6, 2021, operators shutdown the | |||
reactor to commence refueling outage 1R18. The reactor remained shut down in the refueling | |||
outage for the remainder of the inspection period. | |||
INSPECTION SCOPES | |||
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in | |||
effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with | |||
their attached revision histories are located on the public website at http://www.nrc.gov/reading- | their attached revision histories are located on the public website at http://www.nrc.gov/reading- | ||
rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared | rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared | ||
complete when the IP requirements most appropriate to the inspection activity were met | complete when the IP requirements most appropriate to the inspection activity were met | ||
consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection | consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection | ||
Program - Operations Phase. The inspectors reviewed selected procedures and records, | Program - Operations Phase. The inspectors reviewed selected procedures and records, | ||
observed activities, and interviewed personnel to assess licensee performance and compliance | observed activities, and interviewed personnel to assess licensee performance and compliance | ||
with Commission rules and regulations, license conditions, site procedures, and standards. | with Commission rules and regulations, license conditions, site procedures, and standards. | ||
Starting on March 20, 2020, in response to the National Emergency declared by the President | |||
of the United States on the public health risks of the Coronavirus Disease 2019 | Starting on March 20, 2020, in response to the National Emergency declared by the President | ||
(COVID-19), resident inspectors were directed to begin telework and to remotely access | of the United States on the public health risks of the Coronavirus Disease 2019 | ||
licensee information using available technology. During this time, the resident inspectors | (COVID-19), resident inspectors were directed to begin telework and to remotely access | ||
performed periodic site visits each week; conducted plant status activities as described in | licensee information using available technology. During this time, the resident inspectors | ||
IMC 2515, Appendix D, Plant Status; observed risk-significant activities; and completed on-site | performed periodic site visits each week; conducted plant status activities as described in | ||
portions of IPs. In addition, resident and regional baseline inspections were evaluated to | IMC 2515, Appendix D, Plant Status; observed risk-significant activities; and completed on-site | ||
determine if all or portions of the objectives and requirements stated in the IP could be | portions of IPs. In addition, resident and regional baseline inspections were evaluated to | ||
performed remotely. If the inspections could be performed remotely, they were conducted per | determine if all or portions of the objectives and requirements stated in the IP could be | ||
the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The | performed remotely. If the inspections could be performed remotely, they were conducted per | ||
inspections documented below met the objectives and requirements for completion of the IP. | the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The | ||
inspections documented below met the objectives and requirements for completion of the IP. | |||
REACTOR SAFETY | |||
71111.04 - Equipment Alignment | 4 | ||
Partial Walkdown Sample (IP Section 03.01) (4 Samples) | |||
REACTOR SAFETY | |||
71111.04 - Equipment Alignment | |||
Partial Walkdown Sample (IP Section 03.01) (4 Samples) | |||
The inspectors evaluated system configurations during partial walkdowns of the following | |||
systems/trains: | |||
71111.05 - Fire Protection | |||
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (1 Sample) | (1) | ||
High pressure core spray (HPCS) system on February 9, 2021 | |||
(2) | |||
Division 2 diesel generator while division 1 vital bus was removed from service for | |||
modification on March 13, 2021 | |||
Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample) | (3) | ||
Residual heat removal (RHR) B partial alignment due to outage configuration on | |||
71111.08G - Inservice Inspection Activities (BWR) | March 14, 2021 | ||
BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding | (4) | ||
Activities (IP Section 03.01) (1 Sample) | Electrical bus and load alignment due to outage configuration on March 15, 2021 | ||
71111.05 - Fire Protection | |||
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (1 Sample) | |||
The inspectors evaluated the implementation of the fire protection program by conducting a | |||
walkdown and performing a review to verify program compliance, equipment functionality, | |||
material condition, and operational readiness of the following fire areas: | |||
(1) | |||
Quarterly fire protection alarm test on January 14, 2021 | |||
Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample) | |||
(1) | |||
Fire protection drill on January 27, 2021 | |||
71111.08G - Inservice Inspection Activities (BWR) | |||
BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding | |||
Activities (IP Section 03.01) (1 Sample) | |||
(1) | |||
The inspectors verified that the reactor coolant system boundary, reactor vessel | |||
internals, risk-significant piping system boundaries, and containment boundary were | |||
appropriately monitored for degradation and that repairs and replacements were | |||
appropriately fabricated, examined and accepted by reviewing the documentation of | |||
the following activities from March 8, 2021 to March 18, 2021: | |||
03.01.a - Nondestructive Examination and Welding Activities. | |||
1. Ultrasonic Examination (UT) of Main Steam System 26 Inch Elbow to Pipe | |||
Weld, American Society of Mechanical Engineers (ASME) Category R-A, | |||
Component 1B21-0006 | |||
2. UT of Reactor Vessel Top Head Meridional Weld, ASME Category B-A, | |||
Component 1B13-DM | |||
3. UT of Reactor Vessel Feedwater Nozzle Weld, ASME Category R-A, | |||
Component 1B13-N4E-KB | |||
5 | |||
4. Liquid Penetrant Examination (PT) of Control Rod Drive System Piping | |||
Support Welded Attachment, ASME Category C-C, Component | |||
1C11-H0040-WA | |||
5. Magnetic Particle Examination (MT) of Reactor Vessel Top Head to Top Head | |||
Flange Meridional Weld, ASME Category B-A, Component 1B13-AG | |||
6. MT of Main Steam System Flued Head Fitting to Process Pipe Attachment | |||
Weld, ASME Category B-K, Component 1B21-P124-WA | |||
7. Visual Examination (VT-3) of High-Pressure Core Spray System Pipe | |||
Restraint, ASME Category F-A, Component 1E22-H0034 | |||
8. Visual Examinations of Chilled Water System: VT-3 of Pipe Anchor, ASME | |||
Category F-A, Component 1P47-H0219 and VT-1 of Pipe Anchor Integral | |||
Attachment Weld, ASME Category D-A, Component 1P47-H0219-WA | |||
9. AVR-R17-01, ASME Section XI Flaw Evaluation, Weld ID 1B13-AE | |||
10. Pipe Replacement of Essential Service Water System B Piping between | |||
Valve 1P45F0541B and Heat Exchanger 1P42B0001B and between | |||
Valve 1P45F0541B and Second Downstream Elbow; Weld Numbers | |||
200726587-01, -02, -03, -04, -05, -06 and -07 (WO 200726587) | |||
11. Pipe Replacement of Reactor Water Clean Up System; Spool Piece between | |||
Heat Exchangers 1G33B0001C and 1G33B0002A; Weld Numbers | |||
200724734-01, -02, -03, -04, -05, -06, and -07 (WO 200724734) | |||
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance | |||
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) | The above volumetric (UT) and surface (PT and MT) examination records were | ||
(1 Sample) | selected from the previous outage in 2019 (1R17), since there were no ISI exams or | ||
aging management related exams performed during this outage (1R18). | |||
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance | |||
71111.12 - Maintenance Effectiveness | |||
Maintenance Effectiveness (IP Section 03.01) (4 Samples) | Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) | ||
(1 Sample) | |||
(1) | |||
The inspectors observed and evaluated licensed operator performance in the | |||
Control Room during plant shutdown and cooldown activities for the 1R18 refueling | |||
outage on March 6 to 7, 2021. | |||
71111.12 - Maintenance Effectiveness | |||
Maintenance Effectiveness (IP Section 03.01) (4 Samples) | |||
The inspectors evaluated the effectiveness of maintenance to ensure the following | |||
structures, systems, and components (SSCs) remain capable of performing their intended | |||
function: | |||
(1) | |||
Combustible gas mixing system A failure on December 22, 2020 | |||
(2) | |||
Containment radiation monitor outboard isolation loss of indication on | |||
January 15, 2021 | |||
(3) | |||
Inclined fuel transfer system failure on March 16, 2021 | |||
(4) | |||
Division 1 emergency core cooling systems (ECCS) integrated test failures and | |||
resolution on March 22 to 24, 2021 | |||
71111.13 - Maintenance Risk Assessments and Emergent Work Control | |||
Risk Assessment and Management Sample (IP Section 03.01) (5 Samples) | 6 | ||
71111.13 - Maintenance Risk Assessments and Emergent Work Control | |||
Risk Assessment and Management Sample (IP Section 03.01) (5 Samples) | |||
The inspectors evaluated the accuracy and completeness of risk assessments for the | |||
following planned and emergent work activities to ensure configuration changes and | |||
appropriate work controls were addressed: | |||
(1) | |||
Plant risk assessment related to D1A electrical bus emergent work started on | |||
71111.15 - Operability Determinations and Functionality Assessments | November 30, 2020 | ||
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples) | (2) | ||
Emergent work for annunciator system ground alarms on January 7, 2021 | |||
(3) | |||
Emergent work related to electro-hydraulic pump A leak and spill on | |||
January 25, 2021 | |||
(4) | |||
Reactor feed pump turbine "B" emergent work on February 22 to 24, 2021 | |||
(5) | |||
Plant risk assessment during the Division 1 ECCS integrated test between | |||
March 22 to 24, 2021 | |||
71111.15 - Operability Determinations and Functionality Assessments | |||
71111.18 - Plant Modifications | |||
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) | Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples) | ||
(3 Samples) | |||
The inspectors evaluated the licensee's justifications and actions associated with the | |||
following operability determinations and functionality assessments: | |||
(1) | |||
Combustible gas mixing system A (CR 2020-09635) failure and common cause | |||
review on December 22, 2020 | |||
(2) | |||
Operability review based on CR 2020-09501 related to the Technical Support Center | |||
radiation monitor on January 4, 2021 | |||
(3) | |||
Reactor core isolation cooling (RCIC) system operability verification based on | |||
CR 2021-00338 on January 19, 2021 | |||
(4) | |||
Operability review for SCRAM insertion times after shutdown on March 6, 2021 | |||
(5) | |||
Operability review for safety relief valves (SRV) after set pressure testing on | |||
March 29, 2021 | |||
71111.18 - Plant Modifications | |||
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) | |||
(3 Samples) | |||
The inspectors evaluated the following temporary or permanent modifications: | |||
(1) | |||
Dedicated open phase control room annunciator modification on December 17, 2020 | |||
(2) | |||
Installation of temporary jumpers to bypass the rod block as part of outage emergent | |||
activities on March 17, 2021 | |||
(3) | |||
Breaker EH1114 relay modification associated with Engineering Change 11-0559-002 | |||
on March 16, 2021 | |||
71111.19 - Post-Maintenance Testing | |||
Post-Maintenance Test Sample (IP Section 03.01) (8 Samples) | 7 | ||
71111.19 - Post-Maintenance Testing | |||
Post-Maintenance Test Sample (IP Section 03.01) (8 Samples) | |||
The inspectors evaluated the following post-maintenance test activities to verify system | |||
operability and functionality: | |||
(1) | |||
Technical support center testing following radiation monitor repair work on | |||
December 16, 2020, to January 4, 2021 | |||
(2) | |||
Division 3 emergency service water testing following packing adjustment on | |||
January 5, 2021 | |||
(3) | |||
71111.20 - Refueling and Other Outage Activities | Testing of the containment radiation monitor outboard isolation valve following blown | ||
Refueling/Other Outage Sample (IP Section 03.01) (1 Partial) | fuse replacement on January 15, 2021 | ||
(4) | |||
Testing following average power range monitor A and B power supply replacement | |||
on January 19, 2021 | |||
(5) | |||
"B" reactor protection system trip channel Potter-Brumfield relay replacement for | |||
1C71A-K012B, work order 200391663 | |||
71111.22 - Surveillance Testing | (6) | ||
The inspectors evaluated the following surveillance tests: | Testing following replacement of control rod drive mechanisms on March 17, 2021 | ||
Surveillance Tests (other) (IP Section 03.01) (6 Samples) | (7) | ||
Testing following replacement of "A" RHR relays on March 22 to 24, 2021 | |||
(8) | |||
SRV test following replacement on March 29, 2021 | |||
71111.20 - Refueling and Other Outage Activities | |||
Inservice Testing (IP Section 03.01) (1 Sample) | Refueling/Other Outage Sample (IP Section 03.01) (1 Partial) | ||
(1) | |||
(Partial) | |||
The inspectors evaluated refueling outage 1R18 activities from March 6 to | |||
March 31, 2021. Activities evaluated by the inspectors included, but were not limited | |||
to, shutdown and cooldown operations, reduced inventory control, containment | |||
walkdown, reactor vessel disassembly for heavy load controls, refueling operations, | |||
reactor coolant system instrumentation, outage plan and shutdown risk. | |||
71111.22 - Surveillance Testing | |||
The inspectors evaluated the following surveillance tests: | |||
Surveillance Tests (other) (IP Section 03.01) (6 Samples) | |||
(1) | |||
SRV pressure actuation channel A test on January 20, 2021 | |||
(2) | |||
HPCS pump test on February 1, 2021 | |||
(3) | |||
Fuel pool cooling and cleanup system surveillance on February 3, 2021 | |||
(4) | |||
Control rod maximum scram-based insertion time on March 6, 2021 | |||
(5) | |||
Division 1 standby diesel generator load rejection test on March 8, 2021 | |||
(6) | |||
Division 1 ECCS integrated test between March 22 to 24, 2021 | |||
Inservice Testing (IP Section 03.01) (1 Sample) | |||
(1) | |||
"C" RHR system pump and valve operability test, work order 200792521. | |||
Containment Isolation Valve Testing (IP Section 03.01) (1 Sample) | |||
8 | |||
FLEX Testing (IP Section 03.02) (1 Sample) | Containment Isolation Valve Testing (IP Section 03.01) (1 Sample) | ||
RADIATION SAFETY | (1) | ||
71124.01 - Radiological Hazard Assessment and Exposure Controls | Leak rate test for the shutdown cooling A to the feedwater shutdown isolation valve | ||
Radiological Hazard Assessment (IP Section 03.01) (1 Sample) | 1E12-F050A on March 22, 2021 | ||
FLEX Testing (IP Section 03.02) (1 Sample) | |||
Instructions to Workers (IP Section 03.02) (1 Sample) | (1) | ||
Calibration check of FLEX fuel pool level transmitter on January 27, 2021 | |||
RADIATION SAFETY | |||
Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples) | 71124.01 - Radiological Hazard Assessment and Exposure Controls | ||
Radiological Hazard Assessment (IP Section 03.01) (1 Sample) | |||
(1) | |||
The inspectors evaluated how the licensee identifies the magnitude and extent of | |||
Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples) | radiation levels and the concentrations and quantities of radioactive materials and | ||
how the licensee assesses radiological hazards. | |||
Instructions to Workers (IP Section 03.02) (1 Sample) | |||
The inspectors evaluated instructions to workers including radiation work permits used to | |||
access high radiation areas. | |||
(1) | |||
The inspectors evaluated radiological protection related instructions to plant workers | |||
for emergent diving activities on the inclined fuel transfer system. | |||
Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples) | |||
The inspectors evaluated licensee processes for monitoring and controlling contamination | |||
and radioactive material. | |||
(1) | |||
The inspectors observed workers exiting the radiologically controlled area (RCA). | |||
(2) | |||
The inspectors observed licensee surveys of potentially contaminated material | |||
leaving the radiologically controlled area. | |||
Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples) | |||
The inspectors evaluated in-plant radiological conditions during facility walkdowns and | |||
observation of the following radiological work activities. | |||
(1) | |||
Inclined fuel transfer system diving activities under RWP 210910 | |||
(2) | |||
Flow accelerated corrosion exams in the reactor water cleanup heat exchanger and | |||
pump room under RWP 210602 | |||
(3) | |||
Control rod drive mechanism exchange under RWP 210518 | |||
High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples) | |||
9 | |||
High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples) | |||
The inspectors evaluated licensee controls of the following High Radiation Areas and Very | |||
High Radiation Areas: | |||
Radiation Worker Performance and Radiation Protection Technician Proficiency | (1) | ||
(IP Section 03.06) (1 Sample) | Locked high radiation area for reactor water clean-up pump repair in the auxiliary | ||
building 599' | |||
(2) | |||
71124.02 - Occupational ALARA Planning and Controls | Locked high radiation area for the fuel pool cooling pump room in the intermediate | ||
Implementation of ALARA and Radiological Work Controls (IP Section 03.03) (3 Samples) | building 574' | ||
(3) | |||
Locked high radiation area established for fuel moves in containment 620' | |||
Radiation Worker Performance and Radiation Protection Technician Proficiency | |||
(IP Section 03.06) (1 Sample) | |||
Radiation Worker Performance (IP Section 03.04) (1 Sample) | (1) | ||
The inspectors evaluated radiation worker and radiation protection technician | |||
performance as it pertains to radiation protection requirements. | |||
71124.05 - Radiation Monitoring Instrumentation | 71124.02 - Occupational ALARA Planning and Controls | ||
Walkdowns and Observations (IP Section 03.01) (5 Samples) | |||
Implementation of ALARA and Radiological Work Controls (IP Section 03.03) (3 Samples) | |||
The inspectors reviewed as low as reasonably achievable practices and radiological work | |||
controls for the following work activities. | |||
(1) | |||
Inclined fuel transfer system diving activities under RWP 210910 | |||
(2) | |||
Flow accelerated corrosion exams in the reactor water cleanup heat exchanger and | |||
pump room under RWP 210602 | |||
(3) | |||
Control rod drive mechanism exchange under RWP 210518 | |||
Radiation Worker Performance (IP Section 03.04) (1 Sample) | |||
The inspectors evaluated radiation worker and radiation protection technician performance | |||
during: | |||
(1) | |||
Inclined fuel transfer system diving activities under RWP 210910 | |||
71124.05 - Radiation Monitoring Instrumentation | |||
Walkdowns and Observations (IP Section 03.01) (5 Samples) | |||
The inspectors evaluated the following radiation detection instrumentation during plant | |||
walkdowns: | |||
(1) | |||
Radiation monitors (portal monitor, personnel contamination monitor and small article | |||
monitor) located at the RCA exit. | |||
(2) | |||
Portable radiation survey instrumentation located at the RCA exit and the | |||
Instrumentation Calibration Facility (Geiger Mueller contamination monitoring | |||
instruments and dose rate survey instruments including ion chambers, pressurized | |||
ion chambers and Telepoles). | |||
(3) | |||
Gamma spectroscopy systems and liquid scintillation instrumentation located within | |||
the Chemistry Counting Room. | |||
10 | |||
Calibration and Testing Program (IP Section 03.02) (1 Sample) | |||
(4) | |||
JL Shepherd Model 89 instrumentation calibrator. | |||
(5) | |||
71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, | Area Radiation Monitors and Continuous Air Monitors in the Fuel Handling Building | ||
& Transportation | |||
Radioactive Material Storage (IP Section 03.01) (2 Samples) | Calibration and Testing Program (IP Section 03.02) (1 Sample) | ||
The inspectors evaluated the calibration and testing of the following radiation detection | |||
instruments: | |||
(1) | |||
Radioactive Waste System Walkdown (IP Section 03.02 (1 Sample) | Canberra Argos Personal Contamination Monitor, SN L70L004V | ||
71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, | |||
& Transportation | |||
Waste Characterization and Classification (IP Section 03.03) (2 Samples) | |||
Radioactive Material Storage (IP Section 03.01) (2 Samples) | |||
The inspectors evaluated the licensee's performance in controlling, labelling and securing | |||
radioactive materials in the following locations. | |||
Shipment Preparation (IP Section 03.04) (1 Sample) | |||
(1) | |||
Outside radioactive material storage locations | |||
Shipping Records (IP Section 03.05) (5 Samples) | (2) | ||
Radiation protection radioactive source storage locations (calibration facility and RCA | |||
exit) | |||
Radioactive Waste System Walkdown (IP Section 03.02 (1 Sample) | |||
(1) | |||
Inspectors walked down accessible portions of the solid radioactive waste systems | |||
located in the radioactive waste handling building and evaluated system configuration | |||
and functionality. | |||
Waste Characterization and Classification (IP Section 03.03) (2 Samples) | |||
(1) | |||
The inspectors evaluated the licensees characterization and classification of | |||
shipment 19-1030 consisting of reactor water cleanup resin radioactive waste | |||
(2) | |||
The inspectors evaluated the licensees characterization and classification of | |||
shipment 20-1026 consisting of spent resin radioactive waste | |||
Shipment Preparation (IP Section 03.04) (1 Sample) | |||
(1) | |||
The inspectors observed shipment number 21-008, containing radioactive | |||
contaminated laundry. | |||
Shipping Records (IP Section 03.05) (5 Samples) | |||
The inspectors evaluated the following non-excepted radioactive material shipments through | |||
a record review: | |||
(1) | |||
Radioactive waste shipment 19-1030 consisting of reactor water cleanup resin | |||
transported in a Type B package | |||
(2) | |||
Radioactive waste shipment 20-1026 consisting of dewatered resin transported in | |||
a general design package | |||
(3) | |||
Radioactive waste shipment 19-1025 consisting of reactor water cleanup resin | |||
transported in a Type B package | |||
11 | |||
OTHER ACTIVITIES - BASELINE | |||
71153 - Follow-up of Events and Notices of Enforcement Discretion | (4) | ||
Event Report (IP Section 03.02) (1 Sample) | Radioactive material shipment 19-3033 consisting of control rod drive mechanisms | ||
transported in a Type A package | |||
OTHER ACTIVITIES - BASELINE | |||
71153 - Follow-up of Events and Notices of Enforcement Discretion | |||
INSPECTION RESULTS | |||
Event Report (IP Section 03.02) (1 Sample) | |||
The inspectors evaluated the following licensee event reports (LERs): | |||
(1) | |||
LER 2020-002-00, Standby Liquid Control System Rendered Inoperable due to Valve | |||
Misposition (ADAMS Accession No. ML20293A204). The inspection conclusions | |||
associated with this LER are documented in this report under Inspection Results | |||
Section 71153. | |||
INSPECTION RESULTS | |||
Human Performance Error Resulted in Unplanned RCIC Unavailability | |||
Cornerstone | |||
Significance | |||
Cross-Cutting | |||
Aspect | |||
Report | |||
Section | |||
Mitigating | |||
Systems | |||
Green | |||
NCV 05000440/2021001-01 | |||
Corrective Actions: Immediate corrective actions included securing from the surveillance, | Open/Closed | ||
Corrective Action References: CR 2021-00338, Wrong Lead lifted during Surveillance | [H.12] - Avoid | ||
Complacency | |||
71111.22 | |||
A finding of very low safety significance (Green) and associated non-cited violation of | |||
TS 5.4.1, "Procedures," was self-revealed on January 19, 2021, when an unexpected | |||
isolation of the RCIC steam supply occurred. Specifically, during performance of | |||
SVI-E31-T5395A, "RCIC Steam Line Flow High Channel Functional for E31-N684A," | |||
Revision 8, the licensee failed to lift the lead from terminal B4 for relay 1E51-K24, resulting in | |||
the closure of the RCIC steam supply outboard valve and an unplanned limiting condition for | |||
operation (LCO) entry and unavailability of the RCIC system. | |||
Description: | |||
On January 19, 2021, during the performance of SVI-E31-T5395A, RCIC Steam Line Flow | |||
High Channel Functional for E31-N684A, Revision 8, the licensee received several control | |||
room alarms and identified that the RCIC steam supply outboard valve was closed. The | |||
licensee determined that an inadvertent isolation of the RCIC system and an unplanned | |||
inoperability had occurred. The inspectors determined that procedural steps were not | |||
implemented during the surveillance test, as written. Specifically, the licensee failed to | |||
perform Section 5.1 appropriately, steps 72a and 72b, and complete the independent | |||
verification to ensure the correct lead was lifted from terminal B4 associated with relay | |||
1E51-K24. This failure resulted in the closure of the RCIC steam supply outboard valve and | |||
the RCIC system unavailability. | |||
Corrective Actions: Immediate corrective actions included securing from the surveillance, | |||
restoration of the RCIC steam supply flow path and RCIC system operability. | |||
Corrective Action References: CR 2021-00338, Wrong Lead lifted during Surveillance | |||
Performance 1/19/2021. | |||
Performance Assessment: | |||
Performance Deficiency: The resident inspectors determined that the licensees failure to | 12 | ||
implement Section 5.1, Steps 72a and 72b of SVI-E31-T5395A, RCIC steam line flow high | |||
channel functional for E31-N684A, Revision 8, was a performance deficiency. Specifically, | Performance Assessment: | ||
the failure to ensure the correct lead was lifted from terminal B4 of the relay 1E51-K24 in | |||
accordance with the procedure directly led to the inoperability and unavailability of the RCIC | Performance Deficiency: The resident inspectors determined that the licensees failure to | ||
system. | implement Section 5.1, Steps 72a and 72b of SVI-E31-T5395A, RCIC steam line flow high | ||
Screening: The inspectors determined the performance deficiency was more than minor | channel functional for E31-N684A, Revision 8, was a performance deficiency. Specifically, | ||
because it was associated with the Human Performance attribute of the Mitigating Systems | the failure to ensure the correct lead was lifted from terminal B4 of the relay 1E51-K24 in | ||
cornerstone and adversely affected the cornerstone objective to ensure the availability, | accordance with the procedure directly led to the inoperability and unavailability of the RCIC | ||
reliability, and capability of systems that respond to initiating events to prevent undesirable | system. | ||
consequences. The resident inspectors determined the performance deficiency was more | |||
than minor because it was associated with the Human Performance attribute of the Mitigating | Screening: The inspectors determined the performance deficiency was more than minor | ||
Systems cornerstone and adversely affected the cornerstone objective to ensure the | because it was associated with the Human Performance attribute of the Mitigating Systems | ||
availability, reliability, and capability of systems that respond to initiating events to prevent | cornerstone and adversely affected the cornerstone objective to ensure the availability, | ||
undesirable consequences. Specifically, the licensee failed to lift the correct lead from | reliability, and capability of systems that respond to initiating events to prevent undesirable | ||
terminal B4 of relay 1E51-K24, which directly led to the closure of the RCIC steam supply | consequences. The resident inspectors determined the performance deficiency was more | ||
outboard valve and steam flow path isolation, thus negatively impacting the availability of the | than minor because it was associated with the Human Performance attribute of the Mitigating | ||
RCIC system. | Systems cornerstone and adversely affected the cornerstone objective to ensure the | ||
Significance: The inspectors assessed the significance of the finding using Appendix A, The | availability, reliability, and capability of systems that respond to initiating events to prevent | ||
Significance Determination Process (SDP) for Findings At-Power. The inspectors screened | undesirable consequences. Specifically, the licensee failed to lift the correct lead from | ||
the finding against the Mitigating Systems screening questions in Exhibit 2 and answered | terminal B4 of relay 1E51-K24, which directly led to the closure of the RCIC steam supply | ||
"NO" to all screening questions. Therefore, the finding screened to very low safety | outboard valve and steam flow path isolation, thus negatively impacting the availability of the | ||
significance (Green). | RCIC system. | ||
Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the | |||
possibility of mistakes, latent issues, and inherent risk, even while expecting successful | Significance: The inspectors assessed the significance of the finding using Appendix A, The | ||
outcomes. Individuals implement appropriate error reduction tools. Specifically, the licensee | Significance Determination Process (SDP) for Findings At-Power. The inspectors screened | ||
failed to implement error reduction tools from Section 4.2.5.3 of NOBP-LP-2601, "Human | the finding against the Mitigating Systems screening questions in Exhibit 2 and answered | ||
Performance Program," Revision 13, independent verification which resulted in the failure to | "NO" to all screening questions. Therefore, the finding screened to very low safety | ||
implement the procedure as written. | significance (Green). | ||
Enforcement: | |||
Violation: Technical Specification 5.4.1, "Procedures," requires, in part, that written | Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the | ||
procedures/instructions be established, implemented, and maintained covering the following | possibility of mistakes, latent issues, and inherent risk, even while expecting successful | ||
activities: the applicable procedures recommended in Regulatory Guide (RG) 1.33, | outcomes. Individuals implement appropriate error reduction tools. Specifically, the licensee | ||
Revision 2, Appendix A, dated February 1978. RG 1.33, Revision 2, Appendix A, | failed to implement error reduction tools from Section 4.2.5.3 of NOBP-LP-2601, "Human | ||
Section 8b(2)(r), states, in part, that for the reactor core isolation system "Specific procedures | Performance Program," Revision 13, independent verification which resulted in the failure to | ||
for surveillance tests, inspections, and calibrations should be written (implementing | implement the procedure as written. | ||
procedures are required for each surveillance test, inspection, or calibration listed in the | Enforcement: | ||
technical specifications." | |||
Contrary to the above, on January 19, 2020, while performing an activity affecting quality, the | Violation: Technical Specification 5.4.1, "Procedures," requires, in part, that written | ||
licensee did not accomplish a surveillance test in accordance with the procedure and | procedures/instructions be established, implemented, and maintained covering the following | ||
incorrectly performed a step in surveillance procedure SVI-E31-T5395A, and failed to lift the | activities: the applicable procedures recommended in Regulatory Guide (RG) 1.33, | ||
proper lead. Specifically, the licensee failed to lift the lead from terminal B4 from relay | Revision 2, Appendix A, dated February 1978. RG 1.33, Revision 2, Appendix A, | ||
1E51A-K24 resulting in an unplanned entry into Technical Specification 3.5.3, Condition A, | Section 8b(2)(r), states, in part, that for the reactor core isolation system "Specific procedures | ||
and adversely affected the availability of the RCIC system. | for surveillance tests, inspections, and calibrations should be written (implementing | ||
procedures are required for each surveillance test, inspection, or calibration listed in the | |||
technical specifications." | |||
Contrary to the above, on January 19, 2020, while performing an activity affecting quality, the | |||
licensee did not accomplish a surveillance test in accordance with the procedure and | |||
incorrectly performed a step in surveillance procedure SVI-E31-T5395A, and failed to lift the | |||
proper lead. Specifically, the licensee failed to lift the lead from terminal B4 from relay | |||
1E51A-K24 resulting in an unplanned entry into Technical Specification 3.5.3, Condition A, | |||
and adversely affected the availability of the RCIC system. | |||
Enforcement Action: This violation is being treated as a non-cited violation, consistent with | |||
Section 2.3.2 of the Enforcement Policy. | 13 | ||
Minor Violation | |||
Minor Violation: Licensee Event Report (LER) 05000440/2020-002 documented a condition | |||
where the standby liquid control (SLC) system was rendered inoperable due to a valve | Enforcement Action: This violation is being treated as a non-cited violation, consistent with | ||
alignment issue. The event occurred on August 21, 2020, from 0953 to 1307 hours | Section 2.3.2 of the Enforcement Policy. | ||
(approximately 3 hours). The licensee submitted the LER to the NRC according to | |||
10 CFR 50.73 (a)(2)(v)(A) and 50.73 (a)(2)(v)(D) for a condition that could have prevented | Minor Violation | ||
the fulfillment of the safety function of a system needed to shut down the reactor and mitigate | 71153 | ||
the consequences of an accident. | Minor Violation: Licensee Event Report (LER) 05000440/2020-002 documented a condition | ||
The LER stated that on August 20, 2020, Periodic Test Instruction, PTI-C41-P0001, Standby | where the standby liquid control (SLC) system was rendered inoperable due to a valve | ||
Liquid Control Transfer System Pump, and Valve Operability Test, was being performed on | alignment issue. The event occurred on August 21, 2020, from 0953 to 1307 hours | ||
the SLC system. During the test on August 20, 2020, at 1248 hours, a valve misposition | (approximately 3 hours). The licensee submitted the LER to the NRC according to | ||
resulted in the inadvertent addition of 226 gallons of water to the SLC storage tank, causing | 10 CFR 50.73 (a)(2)(v)(A) and 50.73 (a)(2)(v)(D) for a condition that could have prevented | ||
an unintended dilution of the boron solution. On August 21, 2020, at 0953 hours, the SLC | the fulfillment of the safety function of a system needed to shut down the reactor and mitigate | ||
system was declared inoperable when the sample results for the SLC storage tank confirmed | the consequences of an accident. | ||
the boron solution concentration did not meet Technical Specification (TS) 3.1.7 criteria. The | |||
licensee restored operability on August 21, 2020, at 1307 hours. | The LER stated that on August 20, 2020, Periodic Test Instruction, PTI-C41-P0001, Standby | ||
While reviewing LER 05000440/2020-002, the inspectors identified that the diluted boron | Liquid Control Transfer System Pump, and Valve Operability Test, was being performed on | ||
solution concentration existed for a time longer than permitted by TS 3.1.7. Following the | the SLC system. During the test on August 20, 2020, at 1248 hours, a valve misposition | ||
guidance in NUREG-1022 Revision 3 "Event Report Guidelines 10 CFR 50.72 and 50.73, the | resulted in the inadvertent addition of 226 gallons of water to the SLC storage tank, causing | ||
inspectors determined that the licensee should have reported the diluted boron solution | an unintended dilution of the boron solution. On August 21, 2020, at 0953 hours, the SLC | ||
concentration to the NRC as a condition which was prohibited by the plant's Technical | system was declared inoperable when the sample results for the SLC storage tank confirmed | ||
Specifications, pursuant to 10 CFR 50.73 (a)(2)(i)(B). Specifically, the diluted boron solution | the boron solution concentration did not meet Technical Specification (TS) 3.1.7 criteria. The | ||
concentration existed for longer (approximately 24 hours) than the total 20 hours allowed for | licensee restored operability on August 21, 2020, at 1307 hours. | ||
restoration and shutdown outage time per Technical Specifications. The licensee plans on | |||
submitting a revised LER in response to the minor violation. | While reviewing LER 05000440/2020-002, the inspectors identified that the diluted boron | ||
Screening: The inspectors determined the performance deficiency was minor. Specifically, | solution concentration existed for a time longer than permitted by TS 3.1.7. Following the | ||
the failure to identify 10 CFR 50.73 (a)(2)(i)(B) on a Licensee Event Report did not impact the | guidance in NUREG-1022 Revision 3 "Event Report Guidelines 10 CFR 50.72 and 50.73, the | ||
completeness or accuracy of performance indicator data or other information provided to the | inspectors determined that the licensee should have reported the diluted boron solution | ||
agency, as is provided in Enforcement Policy Example 6.9(d)(10). | concentration to the NRC as a condition which was prohibited by the plant's Technical | ||
Enforcement: This failure to comply with 10 CFR 50.73 (a)(2)(i)(B) constitutes a minor | Specifications, pursuant to 10 CFR 50.73 (a)(2)(i)(B). Specifically, the diluted boron solution | ||
violation that is not subject to enforcement action in accordance with the NRCs Enforcement | concentration existed for longer (approximately 24 hours) than the total 20 hours allowed for | ||
Policy. | restoration and shutdown outage time per Technical Specifications. The licensee plans on | ||
submitting a revised LER in response to the minor violation. | |||
Screening: The inspectors determined the performance deficiency was minor. Specifically, | |||
the failure to identify 10 CFR 50.73 (a)(2)(i)(B) on a Licensee Event Report did not impact the | |||
completeness or accuracy of performance indicator data or other information provided to the | |||
agency, as is provided in Enforcement Policy Example 6.9(d)(10). | |||
Enforcement: This failure to comply with 10 CFR 50.73 (a)(2)(i)(B) constitutes a minor | |||
violation that is not subject to enforcement action in accordance with the NRCs Enforcement | |||
Policy. | |||
EXIT MEETINGS AND DEBRIEFS | |||
The inspectors verified no proprietary information was retained or documented in this report. | 14 | ||
EXIT MEETINGS AND DEBRIEFS | |||
The inspectors verified no proprietary information was retained or documented in this report. | |||
* | |||
On April 28, 2021, the inspectors presented the integrated inspection results to | |||
Mr. R. Penfield, Site Vice President, and other members of the licensee staff. | |||
* | |||
On February 5, 2021, the inspectors presented the radiation protection baseline | |||
inspection results to Mr. R. Penfield, Site Vice President, and other members of the | |||
licensee staff. | |||
* | |||
On March 18, 2021, the inspectors presented the Inservice Inspection results to | |||
Mr. C. Elliott, Plant General Manager, and other members of the licensee staff. | |||
* | |||
On March 25, 2021, the inspectors presented the radiation protection baseline | |||
inspection results to Mr. R. Penfield, Site Vice President, and other members of the | |||
licensee staff. | |||
* | |||
On April 28, 2021, the inspectors presented the integrated inspection results inspection | |||
results to Mr. R. Penfield, Site Vice President, and other members of the licensee staff. | |||
DOCUMENTS REVIEWED | |||
Inspection Type | 15 | ||
DOCUMENTS REVIEWED | |||
Inspection | |||
Procedure | |||
Type | |||
Designation | |||
Description or Title | |||
Revision or | |||
Date | |||
71111.04 | |||
Drawings | |||
302-0351-00000 | |||
Standby Diesel Generator Starting Air | |||
GG | |||
302-0352-00000 | |||
Standby Diesel Generator Fuel Oil System | |||
LL | |||
302-0353-00000 | |||
Standby Diesel Generator Lube Oil | |||
T | |||
Procedures | |||
ELI-R22 | |||
15KV and 5KV Metal Clad Switchgear | |||
3/15/2021 | |||
VLI-E12 | |||
Residual Heat Removal System | |||
3/14/2021 | |||
VLI-E22A | |||
High Pressure Core Spray | |||
10 | |||
VLI-R44 | |||
Division 1 and 2 Diesel Generator Starting Air System | |||
6 | |||
VLI-R45 | |||
Division 1 and 2 Diesel Generator Fuel Oil System (Unit 1) | |||
5 | |||
VLI-R47 | |||
Division 1 and 2 Diesel Generator Lube Oil | |||
7 | |||
71111.05 | |||
Procedures | |||
FPI-A-B02 | |||
Fire Brigade Drills | |||
01/27/2021 | |||
Work Orders | |||
200750956 | |||
Quarterly Fire Alarm | |||
01/14/2021 | |||
71111.08G Corrective Action | |||
Documents | |||
CR-2019-02185 | |||
Foreign Material Head Tensioner Lock Washer Dropped in | |||
Cavity | |||
03/19/2019 | |||
CR-2019-02328 | |||
Relevant Indication Identified During Containment Surface | |||
Exams | |||
03/14/2019 | |||
CR-2019-02523 | |||
1C22D0012B Found with Internal Parts Missing - Potential | |||
Foreign Material | |||
03/19/2019 | |||
CR-2019-02677 | |||
During IVVI Piece of Foreign Material Identified Between Jet | |||
Pumps 16 and 17 | |||
03/22/2019 | |||
CR-2019-02704 | |||
During IVVI Piece of Foreign Material Identified at Jet Pump | |||
17 | |||
03/23/2019 | |||
CR-2019-02893 | |||
Foreign Material Found Inside Reactor Vessel During Core | |||
Verification | |||
03/28/2019 | |||
CR-2019-02956 | |||
Legacy Foreign Material Discovered in Inner Bellows | |||
03/29/2019 | |||
CR-2019-02990 | |||
Foreign Material - Piece of Rope Found in Inner Bellows | |||
After Draindown | |||
03/30/2019 | |||
CR-2019-03147 | |||
Leakage Identified During Reactor Pressure Vessel Test | |||
04/03/2019 | |||
CR-2019-03157 | |||
Documentation of Identified Mechanical Joint Leakage | |||
Identified During Reactor Pressure Vessel Leak Test (1R17) | |||
04/04/2019 | |||
CR-2019-03358 | |||
Roll-Up Condition Report Following 1R17 Refuel - Foreign | |||
Material Focused Observations | |||
04/09/2019 | |||
CR-2019-04170 | |||
Additional Pitting Discovered in Piping Downstream of | |||
05/07/2019 | |||
Inspection Type | |||
16 | |||
Inspection | |||
Procedure | |||
Type | |||
Designation | |||
Description or Title | |||
Revision or | |||
Date | |||
Emergency Service Water | |||
CR-2020-02539 | |||
Mechanical Leakage Identified During ISI-P2-T2200-3 | |||
03/23/2020 | |||
CR-2020-06809 | |||
1R16 Snubber As-Built Discrepancy | |||
08/31/2020 | |||
Corrective Action | |||
Documents | |||
Resulting from | |||
Inspection | |||
ATA-2021-4926 | |||
Remove "Snubbers" from Definition of VT-3 in NQI-1042, | |||
Paragraph 3.15 to Align with Language Contained in ASME | |||
Section XI (2013 Edition), IWA-2213 | |||
03/12/2021 | |||
Drawings | |||
304-672-105 | |||
Piping Isometric, Reactor Water Clean-Up System, Reactor | |||
Building | |||
D | |||
305-002-113 | |||
ISI Piping Isometric, System P47 Chilled Water System Loop | |||
B | |||
A | |||
305-006-103 | |||
Reactor Vessel Closure Head, Circumferential and | |||
Meridional Weld Arrangement | |||
A | |||
305-006-108 | |||
ISI, System 1B13, Reactor Vessel Feedwater Nozzle Weld | |||
Arrangement | |||
D | |||
305-605-103 | |||
ISI Piping Isometric, System B21, Main Steam Loop C | |||
C | |||
305-605-107 | |||
ISI Piping Isometric, System B21, Main Steam Loop A, | |||
Steam Tunnel Elevation 620-6 | |||
D | |||
305-701-102 | |||
ISI Piping Isometric, High Pressure Core Spray | |||
D | |||
305-871-104 | |||
System C11, Control Rod Drive, Loop B, Reactor Building | |||
Elevation 620-6 | |||
C | |||
92-701-0034 | |||
Pipe Support Mark Number 1E22-H0034 | |||
A | |||
92-871-0040 | |||
Pipe Support Mark 1C11-H0040 | |||
2 | |||
B-312-641 | |||
Containment Penetration Detail, Type K | |||
F | |||
Miscellaneous | |||
RRP 200724734 | |||
Repair Replacement Plan: Remove and Replace Reactor | |||
Water Clean Up Heat Exchanger 4 Spool Piece Between | |||
Heat Exchangers 1G33B0001C and 1G33B0002A | |||
0 | |||
RRP 200726587 | |||
Repair Replacement Plan: Remove 3" Bypass | |||
Piping/Components and Replace 14" Spool Piece Between | |||
Valve 1 P45F0541 B and Heat Exchanger 1 P4280001 B. | |||
Also Replace Portion of Spool Piece Between Valve | |||
1 P45F0541 B and Second Elbow Downstream of the Valve. | |||
Reference ECP 18-0162-002 | |||
0 | |||
WPS 1.1.2-001 | |||
Welding Procedure Specification: P1 Gr. 1 & 2 to P1 Gr, | |||
13 | |||
Inspection Type | |||
17 | |||
Inspection | |||
Procedure | |||
Type | |||
Designation | |||
Description or Title | |||
Revision or | |||
Date | |||
1 & 2 | |||
NDE Reports | |||
0941-19A-003 | |||
Liquid Penetrant Examination (PT): Piping Support Welded | |||
Attachment: Component 1C11-H0040-WA | |||
03/13/2019 | |||
0942-19A-008 | |||
Magnetic Particle Examination (MT): Top Head to Top Head | |||
Flange: Component 1B13-AG | |||
03/21/2019 | |||
0942-19A-010 | |||
Magnetic Particle Examination (MT): P124 Flued Head | |||
Fitting to Process Pipe Attachment Weld: Component | |||
1B21-P124-WA | |||
03/25/2019 | |||
0942-19B-009 | |||
Magnetic Particle Examination (MT): 14 Pipe to 14 Elbow | |||
03/13/2019 | |||
0942-19B-014 | |||
Magnetic Particle Examination (MT): Flange to Pipe | |||
03/13/2019 | |||
0942-19B-015 | |||
Magnetic Particle Examination (MT): Pipe to Elbow Butt | |||
Welds | |||
03/13/2019 | |||
0942-19B-016 | |||
Magnetic Particle Examination (MT): (2) Half Coupling to | |||
Pipe and Flange to Pipe Welds | |||
03/13/2019 | |||
0942-19B-017 | |||
Magnetic Particle Examination (MT): 14 Flange to 14 Elbow | |||
Butt Weld (Repair) | |||
03/13/2019 | |||
0942-19B-025 | |||
Magnetic Particle Examination (MT): 14 Pipe to 14 Elbow | |||
FW-07 | |||
03/25/2019 | |||
0942-19B-031 | |||
Magnetic Particle Examination (MT): 4 Spool Piping | |||
03/07/2019 | |||
1042-19B-018 | |||
Visual Examination System Leakage (VT-2): Order | |||
200726587 Piping Replacement | |||
03/27/2019 | |||
1042-21-023 | |||
Visual Examination of Pipe Hanger, Support, or Restraint | |||
(VT-3): Chilled Water System, Pipe Anchor, Component | |||
1P47-H0219 Located on ISI Drawing 305-002-113 | |||
03/04/2021 | |||
1042-21-024 | |||
Visual Examination of Welds (VT-1): Chilled Water System | |||
Pipe Anchor Integral Attachment, Component | |||
1P47-H0219-WA Located on ISI Drawing 305-002-113 | |||
03/08/2021 | |||
1042-21-029 | |||
Visual Examination of Pipe Hanger, Support, or Restraint | |||
(VT-3): Mechanical Snubber, Drawing 305-701-102, | |||
Component 1E22-H0034 | |||
03/04/2021 | |||
APR-R17-02 | |||
Ultrasonic Examination Summary Sheet, System 1B13, Weld | |||
Number 1B13-N4E-KB, Safe-End to Nozzle | |||
03/282019 | |||
MVR-004 | |||
UT Report with Calibration Records C-007 and C-008: | |||
Component 1B13-DM | |||
03/23/2019 | |||
Inspection Type | |||
18 | |||
Inspection | |||
Procedure | |||
Type | |||
Designation | |||
Description or Title | |||
Revision or | |||
Date | |||
UT-19-E006 | |||
UT Calibration/Examination Report: Component 1B21-006 | |||
03/15/2019 | |||
Procedures | |||
GEH-UT-247 | |||
Procedure for Phased Array Ultrasonic Examination of | |||
Dissimilar Metal Welds | |||
4 | |||
GEH-UT-300 | |||
Procedure for Manual Examination of Reactor Vessel | |||
Assembly Welds in Accordance with PDI | |||
12 | |||
NOP-CC-5762 | |||
71111.11Q Miscellaneous | Appendix VIII Procedure for Ultrasonic Examination of | ||
Ferritic Welds | |||
3 | |||
NQI-0941 | |||
71111.12 | Liquid Penetrant Examination | ||
22 | |||
NQI-0942 | |||
Magnetic Particle Examination | |||
22 | |||
71111.13 | NQI-1042 | ||
Visual Examination | |||
20 | |||
Work Orders | |||
200718215 | |||
Reactor Vessel Top Head Meridional Weld Examination | |||
03/21/2019 | |||
200718218 | |||
Piping Weld Exams on Main Steam Lines | |||
04/17/2019 | |||
200724734 | |||
Replace 4 Piping - RWCU Piping Between Heat | |||
Exchangers 1G33B0001C and 1G33B0002A | |||
04/11/2019 | |||
200726587 | |||
Replace 14 Piping - ESW B Piping Between 1P45F0541B | |||
and Heat Exchanger 1P42B0001B and Between Valve | |||
1P45F0541B and Second Elbow Downstream of Valve | |||
04/09/2019 | |||
200728323 | |||
1B13 Reactor and Internals Non-Destructive Examination | |||
04/18/2019 | |||
200794288 | |||
System P47 Exams: Pre-1R18 | |||
03/12/2021 | |||
200794289 | |||
ISI of Piping, Supports, and Components of P42, P47, and | |||
E22 Systems | |||
03/12/2021 | |||
71111.11Q Miscellaneous | |||
Evolution Specific | |||
Reactivity Plan | |||
Perry Nuclear Power Plant End of Cycle 18 Shutdown | |||
0 | |||
Procedures | |||
IOI-3 | |||
Power Changes | |||
81 | |||
IOI-4 | |||
Shutdown | |||
26 | |||
71111.12 | |||
Corrective Action | |||
Documents | |||
2021-00266 | |||
Loss of Indication for Containment Radiation Monitor | |||
Outboard Isolation | |||
01/15/2021 | |||
2021-01834 | |||
IFT Cable Damaged During Transfer | |||
03/14/2021 | |||
Miscellaneous | |||
NOP-ER-3004-03 | |||
Maintenance Rule Failure Review Form | |||
04 | |||
NOP-SS-3001-02 | |||
Procedure Approval Form | |||
12 | |||
71111.13 | |||
Corrective Action | |||
Documents | |||
2021-00128 | |||
Multiple Alarms Received Coincident with Annunciator | |||
System Ground | |||
01/7/2021 | |||
2021-00455 | |||
EHC Pump A Leak | |||
01/25/2021 | |||
Inspection Type | |||
19 | |||
Inspection | |||
Procedure | |||
Type | |||
Designation | |||
Description or Title | |||
71111.15 | Revision or | ||
Date | |||
2021-01200 | |||
Planned Work Not Able to be Released as Scheduled Due to | |||
Leakby Aux Condenser B Air Removal Suction Valve | |||
02/23/2021 | |||
71111.18 | 2021-02121 | ||
Unplanned Division 1 DG Start During Integrated | |||
LOOP/LOCA Test | |||
03/23/2021 | |||
Work Orders | |||
71111.19 | 200840213 | ||
Determine and Correct the Cause Ground on Electrical Bus | |||
D1A CR 2020-09061 | |||
11/30/2020 | |||
71111.15 | |||
Corrective Action | |||
Documents | |||
2020-09501 | |||
Ventilation Radiation Monitor Gas Channel Reading Erratic | |||
12/16/2020 | |||
2021-00338 | |||
Wrong Lead Lifted During Surveillance Performance | |||
01/20/2021 | |||
2021-01707 | |||
71111.20 | Rod SCRAM Time Recorder Did Not Perform as Expected | ||
03/10/2021 | |||
2021-09635 | |||
Combustible Gas Mixing Compressor Suction Valve Would | |||
Not Re-Open Following Compressor Start | |||
12/22/2020 | |||
Work Orders | |||
200798943 | |||
Safety Relief Valve Removes, Replaces and Offsite Testing | |||
03/23/2021 | |||
71111.18 | |||
Engineering | |||
Changes | |||
11-0559-002 | |||
Spring Charging Motor Margin Improvement - EH 1114 | |||
0 | |||
ECP 15-0057 | |||
Installation of U1/U2 Startup Transformer | |||
02/26/2018 | |||
Engineering | |||
Evaluations | |||
ECP 19-0203-002 Dedicated Open Phase Control Room Annunciators - Unit 2 | |||
07/10/2020 | |||
Work Orders | |||
200846449 | |||
Jumper Request to Remove Rod Block | |||
03/17/2021 | |||
71111.19 | |||
Corrective Action | |||
Documents | |||
2021-00266 | |||
Loss of Indication for Containment Radiation Monitor | |||
Outboard Isolation | |||
01/15/2021 | |||
Procedures | |||
SVI-B21-T2100 | |||
Safety Relief Valve (SRV) Set Pressure Testing | |||
7 | |||
SVI-D17-T2001 | |||
Plant Radiation Monitoring Isolation Valves Operability Test | |||
8 | |||
Work Orders | |||
100841399 | |||
Technical Support Center Ventilation Radiation Monitor Gas | |||
Channel Reading Erratic Replacement | |||
01/4/2021 | |||
200391663 | |||
Replace Relay 1C17A-K0112B Reactor Protection System | |||
Trip Channel B | |||
0 | |||
200536387 | |||
Replace Relays 1E12-K18A/19A | |||
03/22/2021 | |||
200594427 | |||
Replace Power Supply PS22 | |||
01/12/2021 | |||
200727023 | |||
Install ECP-11-0559-002 74 Power Monitoring Relay in | |||
Breaker EH1114 | |||
03/14/2021 | |||
200762809 | |||
Inspect/Tighten Packing-ESW PMP Div III | |||
01/5/2021 | |||
200795982 | |||
Control Unit Hydraulic | |||
03/17/2021 | |||
71111.20 | |||
Corrective Action | |||
Documents | |||
2021-01545 | |||
Condensate Booster Pump C Tripped Following Reactor | |||
Recirculation Pump Downshift | |||
03/6/2021 | |||
Inspection Type | |||
20 | |||
Inspection | |||
Procedure | |||
Type | |||
Designation | |||
Description or Title | |||
Revision or | |||
Date | |||
2021-01557 | |||
Feedwater Heater 3A Isolated on High Level Following | |||
Recirculating Pump Downshift to Slow Speed | |||
03/6/2021 | |||
2021-01564 | |||
Control Rod 02-27 Did Not Settle at 00 | |||
03/7/2021 | |||
2021-01604 | |||
Scaffold Level Inadvertently Dropped in the Suppression | |||
Pool During Scaffold Erection | |||
03/8/2021 | |||
2021-01829 | |||
Leak in High Pressure Core Spray Room | |||
03/14/2021 | |||
71111.22 | 2021-01857 | ||
As Found Blockage of 3-Inch Fire Protection System to | |||
Emergency Service Water Pipe Connection | |||
03/15/2021 | |||
2021-01939 | |||
Fuel Assembly 18P568 Identified as Cycle 18 Fuel Defect | |||
03/17/2021 | |||
2021-02011 | |||
Design Discrepancies Contained Within the Engineering | |||
Change Package for the 1B33-F060B Side Drain Appendage | |||
03/19/2021 | |||
2021-02117 | |||
Ground Detected on DC Bus | |||
03/22/2021 | |||
2021-02159 | |||
Loose Bushing Terminal Lead Connectors Found in Unit 1 | |||
Start-Up Transformer | |||
03/24/2021 | |||
2021-02237 | |||
Issues Noted on Post Maintenance Tests for Scram | |||
Discharge Volume Vent and Drain Valves | |||
03/25/2021 | |||
2021-02312 | |||
Control Rod Drive Mechanism Temperature for Rod 34-43 | |||
Indicates Failed | |||
03/27/2021 | |||
2021-02428 | |||
Hard Ground Indicated on DC Bus D-1-B | |||
03/31/2021 | |||
Miscellaneous | |||
1R18 Shutdown Defense-In-Depth Report | |||
1 | |||
Procedures | |||
SVI-B21-T1176 | |||
Reactor Coolant System Heat Up and Cooldown | |||
Surveillance | |||
03/7/2021 | |||
71111.22 | |||
Procedures | |||
GMI-0067 | |||
Under-Vessel Maintenance Activities | |||
19 | |||
IMI-E2-47 | |||
Installation of Reactor Refuel Level Instrumentation for | |||
IOI-9 | |||
03/9/2021 | |||
SVI-B21-T2100 | |||
Safety Relief Valve (SRV) Set Pressure Testing | |||
7 | |||
SVI-E12-T2210 | |||
Leak Rate Test for RHR to FWD Injection Valves | |||
1E12-F050A and 1E12-F053A | |||
03/24/2021 | |||
SVI-G41-T2002 | |||
Fuel Pool Cooling and Cleanup System Operability Test | |||
02/3/2021 | |||
SVI-R43-T7000-A Division 1 ECCS Integrated Test | |||
12 | |||
TXI-0460 | |||
Division 1 Standby Diesel Generator Load Rejection Test | |||
03/8/2021 | |||
Work Orders | |||
200751888 | |||
SRV Pressure Actuation Channel a Functional for | |||
1B21-N668A | |||
01/20/2021 | |||
200778903 | |||
Spent Fuel Pool Level Instrument 1X13N0003 Calibration | |||
01/27/2021 | |||
Inspection Type | |||
21 | |||
Inspection | |||
Procedure | |||
Type | |||
Designation | |||
71124.01 | Description or Title | ||
Revision or | |||
Date | |||
Check | |||
200778904 | |||
Level Sensor Calibration | |||
02/3/2021 | |||
200778926 | |||
Standby Oil Pump Testing 1N27C0006A | |||
12/30/2020 | |||
200783921 | |||
Control Rod Maximum SCRAM Insertion Time | |||
03/6/2021 | |||
200792417 | |||
High Pressure Core Spray Pump and Valve Operability Test | |||
02/1/2021 | |||
71124.01 | |||
Corrective Action | |||
71124.02 | Documents | ||
CR-2021-01739 | |||
Two Unbriefed Dose Rate Alarms Received in Containment | |||
Annulus 690' Elevation | |||
03/11/2021 | |||
Corrective Action | |||
71124.05 | Documents | ||
Resulting from | |||
71124.08 | Inspection | ||
CR-2021-01952 | |||
NRC Comment During Radiological Hazards/ALARA | |||
Inspection for Loss of Telemetry | |||
03/16/2021 | |||
Radiation | |||
Surveys | |||
N/A | |||
Radiological Surveys for Lower Inclined Fuel Transfer | |||
System | |||
03/15/2021 | |||
PY-M-20210310- | |||
7 | |||
Reactor Water Cleanup Heat Exchanger Room Post Pump | |||
Failure Verification Survey for Flow Accelerated Corrosion | |||
Exam Work | |||
03/09/2021 | |||
PY-M-20210312- | |||
37 | |||
Scaffold Extension for Flow Accelerated Corrosion Exam | |||
03/12/2021 | |||
Radiation Work | |||
Permits (RWPs) | |||
210518 | |||
Undervessel Activities | |||
0 | |||
210602 | |||
Flow Accelerated Corrosion Exams in the Reactor Water | |||
Clean-Up Heat Exchanger and Pump Room | |||
0 | |||
210910 | |||
Inclined Fuel Transfer System Diving Activities and Support | |||
Work | |||
0 | |||
71124.02 | |||
ALARA Plans | |||
ALARA Plan | |||
210518 | |||
Undervessel Activities | |||
0 | |||
ALARA Plan | |||
210602 | |||
Flow Accelerated Corrosion Exams in the Reactor Water | |||
Clean-Up Heat Exchanger Room | |||
0 | |||
ALARA Plan | |||
210910 | |||
ALARA Plan for Inclined Fuel Transfer System Diving and | |||
Support Activities | |||
0 | |||
71124.05 | |||
Calibration | |||
Records | |||
Canberra Argos Personal Contamination Monitor; | |||
SN L70L004V | |||
02/17/2021 | |||
71124.08 | |||
Corrective Action | |||
Documents | |||
2019-03353 | |||
Radwaste Processing Inventory Issues | |||
04/09/2019 | |||
2019-06245 | |||
Radwaste Tanks Require Multiple Iterations of Processing in | |||
Order to Become Transfer Quality | |||
07/24/2019 | |||
Inspection Type | |||
22 | |||
Inspection | |||
Procedure | |||
Type | |||
Designation | |||
Description or Title | |||
Revision or | |||
Date | |||
2020-07918 | |||
Pre NRC-Assessment ATA 2020-10589 Identified | |||
Deficiencies in Closure Packages for SVI-E31-T5190 | |||
10/13/2020 | |||
Miscellaneous | |||
20118 | |||
Radioactive Material Transportation Training Record | |||
07/09/2020 | |||
451802001 | |||
10 CFR 61 Laboratory Analysis of Reactor Water Clean-Up | |||
Resin | |||
05/25/2018 | |||
510237001 | |||
10 CFR 61 Laboratory Analysis of Spent Resin | |||
02/25/2020 | |||
Procedures | |||
NOP-OP-4502 | |||
Control of Radioactive Material | |||
7 | |||
NOP-OP-5201 | |||
Shipment of Radioactive Material-Waste | |||
10 | |||
PCP-0000 | |||
Process Control Program | |||
15 | |||
RPI-1301 | |||
Movement of Radioactive Material/Waste Outside of | |||
Radiologically Controlled Areas and Onsite Interim Storage | |||
13 | |||
Self-Assessments ATA-2020-10589 | |||
Pre NRC-Inspection - Radioactive Solid Waste Processing | |||
and Radioactive Material Handling, Storage, and | |||
Transportation | |||
11/13/2020 | |||
Shipping Records 19-1025 | |||
Radioactive Waste Shipment of Reactor Water Cleanup | |||
Resin | |||
06/05/2019 | |||
19-1030 | |||
Radioactive Waste Shipment of Reactor Water Cleanup | |||
Resin | |||
07/23/2019 | |||
19-3033 | |||
Radioactive Material Shipment of Control Rod Drive | |||
Mechanisms | |||
07/18/2019 | |||
20-1026 | |||
Radioactive Waste Shipment of Dewatered Resin | |||
11/30/2020 | |||
21-2008 | |||
Radioactive Material Shipment Containing Radiologically | |||
Contaminated Laundry | |||
03/18/2021 | |||
Work Orders | |||
200752735 | |||
Radioactive Source Inventory/Leak Test Record | |||
09/03/2020 | |||
}} | }} | ||
Latest revision as of 09:01, 29 November 2024
| ML21132A095 | |
| Person / Time | |
|---|---|
| Site: | Perry |
| Issue date: | 05/12/2021 |
| From: | Billy Dickson NRC/RGN-III/DRP/B2 |
| To: | Penfield R Energy Harbor Nuclear Corp |
| References | |
| IR 2021001 | |
| Download: ML21132A095 (25) | |
See also: IR 05000440/2021001
Text
May 12, 2021
Mr. Rod L. Penfield
Site Vice President
Energy Harbor Nuclear Corp.
Perry Nuclear Power Plant
10 Center Road
Perry, OH 44081
SUBJECT:
PERRY NUCLEAR POWER PLANT - INTEGRATED INSPECTION REPORT
Dear Mr. Penfield:
On March 31, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection
at Perry Nuclear Power Plant. On April 28, 2021, the NRC inspectors discussed the results of
this inspection with you and other members of your staff. The results of this inspection are
documented in the enclosed report.
One finding of very low safety significance (Green) is documented in this report. This finding
involved a violation of NRC requirements. We are treating this violation as a non-cited violation
(NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this
inspection report, you should provide a response within 30 days of the date of this inspection
report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional
Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector
at Perry Nuclear Power Plant.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a
response within 30 days of the date of this inspection report, with the basis for your
disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,
Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the
NRC Resident Inspector at Perry Nuclear Power Plant.
R. Penfield
2
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public
Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Billy C. Dickson, Jr., Chief
Branch 2
Division of Reactor Projects
Docket No. 05000440
License No. NPF-58
Enclosure:
As stated
cc w/ encl: Distribution via LISTSERV
SUNSI Review
Non-Sensitive
Sensitive
Publicly Available
Non-Publicly Available
OFFICE RIII
RIII
NAME
RRiuz:ve via email
BDickson via email
DATE
5/11/2021
5/12/2021
Enclosure
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Number:
05000440
License Number:
Report Number:
Enterprise Identifier: I-2021-001-0045
Licensee:
Energy Harbor Nuclear Corp.
Facility:
Perry Nuclear Power Plant
Location:
Perry, Ohio
Inspection Dates:
January 01, 2021 to March 31, 2021
Inspectors:
S. Bell, Health Physicist
V. Myers, Senior Health Physicist
J. Neurauter, Senior Reactor Inspector
T. Ospino, Resident Inspector
J. Steffes, Senior Resident Inspector
T. Taylor, Fermi Resident Inspector
Approved By:
Billy C. Dickson, Jr., Chief
Branch 2
Division of Reactor Projects
2
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees
performance by conducting an integrated inspection at Perry Nuclear Power Plant, in
accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs
program for overseeing the safe operation of commercial nuclear power reactors. Refer to
https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
Human Performance Error Resulted in Unplanned RCIC Unavailability
Cornerstone
Significance
Cross-Cutting
Aspect
Report
Section
Mitigating
Systems
Green
Open/Closed
[H.12] - Avoid
Complacency
A finding of very low safety significance (Green) and associated non-cited violation of
TS 5.4.1, "Procedures," was self-revealed on January 19, 2021, when an unexpected isolation
of the RCIC steam supply occurred. Specifically, during performance of SVI-E31-T5395A,
"RCIC Steam Line Flow High Channel Functional for E31-N684A," Revision 8, the licensee
failed to lift the lead from terminal B4 for relay 1E51-K24, resulting in the closure of the RCIC
steam supply outboard valve and an unplanned limiting condition for operation (LCO) entry
and unavailability of the RCIC system.
Additional Tracking Items
None.
3
PLANT STATUS
Perry Nuclear Power Plant began the inspection period at 97 percent of rated thermal power in
coastdown operations before a refueling outage. On January 10, 2021, the 1B feedwater heater
isolated. The isolation resulted in a power perturbation. In response to the power perturbation
and feedwater heater isolation, the operators lowered reactor power to 79 percent to maintain
margin to thermal limits per abnormal operating procedures. High water level conditions caused
the heater isolation. The high-water level condition resulted from a failed circuit card in the level
transmitter for the alternate level controller. Operators restored level using the normal level
controller. The operators returned the unit to maximum attainable power and continued
coastdown operations on January 11, 2021. On March 6, 2021, operators shutdown the
reactor to commence refueling outage 1R18. The reactor remained shut down in the refueling
outage for the remainder of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in
effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with
their attached revision histories are located on the public website at http://www.nrc.gov/reading-
rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared
complete when the IP requirements most appropriate to the inspection activity were met
consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection
Program - Operations Phase. The inspectors reviewed selected procedures and records,
observed activities, and interviewed personnel to assess licensee performance and compliance
with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President
of the United States on the public health risks of the Coronavirus Disease 2019
(COVID-19), resident inspectors were directed to begin telework and to remotely access
licensee information using available technology. During this time, the resident inspectors
performed periodic site visits each week; conducted plant status activities as described in
IMC 2515, Appendix D, Plant Status; observed risk-significant activities; and completed on-site
portions of IPs. In addition, resident and regional baseline inspections were evaluated to
determine if all or portions of the objectives and requirements stated in the IP could be
performed remotely. If the inspections could be performed remotely, they were conducted per
the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The
inspections documented below met the objectives and requirements for completion of the IP.
4
REACTOR SAFETY
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following
systems/trains:
(1)
High pressure core spray (HPCS) system on February 9, 2021
(2)
Division 2 diesel generator while division 1 vital bus was removed from service for
modification on March 13, 2021
(3)
Residual heat removal (RHR) B partial alignment due to outage configuration on
March 14, 2021
(4)
Electrical bus and load alignment due to outage configuration on March 15, 2021
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (1 Sample)
The inspectors evaluated the implementation of the fire protection program by conducting a
walkdown and performing a review to verify program compliance, equipment functionality,
material condition, and operational readiness of the following fire areas:
(1)
Quarterly fire protection alarm test on January 14, 2021
Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)
(1)
Fire protection drill on January 27, 2021
71111.08G - Inservice Inspection Activities (BWR)
BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding
Activities (IP Section 03.01) (1 Sample)
(1)
The inspectors verified that the reactor coolant system boundary, reactor vessel
internals, risk-significant piping system boundaries, and containment boundary were
appropriately monitored for degradation and that repairs and replacements were
appropriately fabricated, examined and accepted by reviewing the documentation of
the following activities from March 8, 2021 to March 18, 2021:
03.01.a - Nondestructive Examination and Welding Activities.
1. Ultrasonic Examination (UT) of Main Steam System 26 Inch Elbow to Pipe
Weld, American Society of Mechanical Engineers (ASME) Category R-A,
Component 1B21-0006
2. UT of Reactor Vessel Top Head Meridional Weld, ASME Category B-A,
Component 1B13-DM
3. UT of Reactor Vessel Feedwater Nozzle Weld, ASME Category R-A,
Component 1B13-N4E-KB
5
4. Liquid Penetrant Examination (PT) of Control Rod Drive System Piping
Support Welded Attachment, ASME Category C-C, Component
5. Magnetic Particle Examination (MT) of Reactor Vessel Top Head to Top Head
Flange Meridional Weld, ASME Category B-A, Component 1B13-AG
6. MT of Main Steam System Flued Head Fitting to Process Pipe Attachment
Weld, ASME Category B-K, Component 1B21-P124-WA
7. Visual Examination (VT-3) of High-Pressure Core Spray System Pipe
Restraint, ASME Category F-A, Component 1E22-H0034
8. Visual Examinations of Chilled Water System: VT-3 of Pipe Anchor, ASME
Category F-A, Component 1P47-H0219 and VT-1 of Pipe Anchor Integral
Attachment Weld, ASME Category D-A, Component 1P47-H0219-WA
9. AVR-R17-01, ASME Section XI Flaw Evaluation, Weld ID 1B13-AE
10. Pipe Replacement of Essential Service Water System B Piping between
Valve 1P45F0541B and Heat Exchanger 1P42B0001B and between
Valve 1P45F0541B and Second Downstream Elbow; Weld Numbers
200726587-01, -02, -03, -04, -05, -06 and -07 (WO 200726587)
11. Pipe Replacement of Reactor Water Clean Up System; Spool Piece between
Heat Exchangers 1G33B0001C and 1G33B0002A; Weld Numbers
200724734-01, -02, -03, -04, -05, -06, and -07 (WO 200724734)
The above volumetric (UT) and surface (PT and MT) examination records were
selected from the previous outage in 2019 (1R17), since there were no ISI exams or
aging management related exams performed during this outage (1R18).
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)
(1 Sample)
(1)
The inspectors observed and evaluated licensed operator performance in the
Control Room during plant shutdown and cooldown activities for the 1R18 refueling
outage on March 6 to 7, 2021.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (4 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following
structures, systems, and components (SSCs) remain capable of performing their intended
function:
(1)
Combustible gas mixing system A failure on December 22, 2020
(2)
Containment radiation monitor outboard isolation loss of indication on
January 15, 2021
(3)
Inclined fuel transfer system failure on March 16, 2021
(4)
Division 1 emergency core cooling systems (ECCS) integrated test failures and
resolution on March 22 to 24, 2021
6
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the
following planned and emergent work activities to ensure configuration changes and
appropriate work controls were addressed:
(1)
Plant risk assessment related to D1A electrical bus emergent work started on
November 30, 2020
(2)
Emergent work for annunciator system ground alarms on January 7, 2021
(3)
Emergent work related to electro-hydraulic pump A leak and spill on
January 25, 2021
(4)
Reactor feed pump turbine "B" emergent work on February 22 to 24, 2021
(5)
Plant risk assessment during the Division 1 ECCS integrated test between
March 22 to 24, 2021
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the
following operability determinations and functionality assessments:
(1)
Combustible gas mixing system A (CR 2020-09635) failure and common cause
review on December 22, 2020
(2)
Operability review based on CR 2020-09501 related to the Technical Support Center
radiation monitor on January 4, 2021
(3)
Reactor core isolation cooling (RCIC) system operability verification based on
CR 2021-00338 on January 19, 2021
(4)
Operability review for SCRAM insertion times after shutdown on March 6, 2021
(5)
Operability review for safety relief valves (SRV) after set pressure testing on
March 29, 2021
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)
(3 Samples)
The inspectors evaluated the following temporary or permanent modifications:
(1)
Dedicated open phase control room annunciator modification on December 17, 2020
(2)
Installation of temporary jumpers to bypass the rod block as part of outage emergent
activities on March 17, 2021
(3)
Breaker EH1114 relay modification associated with Engineering Change 11-0559-002
on March 16, 2021
7
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (8 Samples)
The inspectors evaluated the following post-maintenance test activities to verify system
operability and functionality:
(1)
Technical support center testing following radiation monitor repair work on
December 16, 2020, to January 4, 2021
(2)
Division 3 emergency service water testing following packing adjustment on
January 5, 2021
(3)
Testing of the containment radiation monitor outboard isolation valve following blown
fuse replacement on January 15, 2021
(4)
Testing following average power range monitor A and B power supply replacement
on January 19, 2021
(5)
"B" reactor protection system trip channel Potter-Brumfield relay replacement for
1C71A-K012B, work order 200391663
(6)
Testing following replacement of control rod drive mechanisms on March 17, 2021
(7)
Testing following replacement of "A" RHR relays on March 22 to 24, 2021
(8)
SRV test following replacement on March 29, 2021
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)
(1)
(Partial)
The inspectors evaluated refueling outage 1R18 activities from March 6 to
March 31, 2021. Activities evaluated by the inspectors included, but were not limited
to, shutdown and cooldown operations, reduced inventory control, containment
walkdown, reactor vessel disassembly for heavy load controls, refueling operations,
reactor coolant system instrumentation, outage plan and shutdown risk.
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Surveillance Tests (other) (IP Section 03.01) (6 Samples)
(1)
SRV pressure actuation channel A test on January 20, 2021
(2)
HPCS pump test on February 1, 2021
(3)
Fuel pool cooling and cleanup system surveillance on February 3, 2021
(4)
Control rod maximum scram-based insertion time on March 6, 2021
(5)
Division 1 standby diesel generator load rejection test on March 8, 2021
(6)
Division 1 ECCS integrated test between March 22 to 24, 2021
Inservice Testing (IP Section 03.01) (1 Sample)
(1)
"C" RHR system pump and valve operability test, work order 200792521.
8
Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)
(1)
Leak rate test for the shutdown cooling A to the feedwater shutdown isolation valve
1E12-F050A on March 22, 2021
FLEX Testing (IP Section 03.02) (1 Sample)
(1)
Calibration check of FLEX fuel pool level transmitter on January 27, 2021
RADIATION SAFETY
71124.01 - Radiological Hazard Assessment and Exposure Controls
Radiological Hazard Assessment (IP Section 03.01) (1 Sample)
(1)
The inspectors evaluated how the licensee identifies the magnitude and extent of
radiation levels and the concentrations and quantities of radioactive materials and
how the licensee assesses radiological hazards.
Instructions to Workers (IP Section 03.02) (1 Sample)
The inspectors evaluated instructions to workers including radiation work permits used to
access high radiation areas.
(1)
The inspectors evaluated radiological protection related instructions to plant workers
for emergent diving activities on the inclined fuel transfer system.
Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)
The inspectors evaluated licensee processes for monitoring and controlling contamination
and radioactive material.
(1)
The inspectors observed workers exiting the radiologically controlled area (RCA).
(2)
The inspectors observed licensee surveys of potentially contaminated material
leaving the radiologically controlled area.
Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)
The inspectors evaluated in-plant radiological conditions during facility walkdowns and
observation of the following radiological work activities.
(1)
Inclined fuel transfer system diving activities under RWP 210910
(2)
Flow accelerated corrosion exams in the reactor water cleanup heat exchanger and
pump room under RWP 210602
(3)
Control rod drive mechanism exchange under RWP 210518
9
High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)
The inspectors evaluated licensee controls of the following High Radiation Areas and Very
(1)
Locked high radiation area for reactor water clean-up pump repair in the auxiliary
building 599'
(2)
Locked high radiation area for the fuel pool cooling pump room in the intermediate
building 574'
(3)
Locked high radiation area established for fuel moves in containment 620'
Radiation Worker Performance and Radiation Protection Technician Proficiency
(IP Section 03.06) (1 Sample)
(1)
The inspectors evaluated radiation worker and radiation protection technician
performance as it pertains to radiation protection requirements.
71124.02 - Occupational ALARA Planning and Controls
Implementation of ALARA and Radiological Work Controls (IP Section 03.03) (3 Samples)
The inspectors reviewed as low as reasonably achievable practices and radiological work
controls for the following work activities.
(1)
Inclined fuel transfer system diving activities under RWP 210910
(2)
Flow accelerated corrosion exams in the reactor water cleanup heat exchanger and
pump room under RWP 210602
(3)
Control rod drive mechanism exchange under RWP 210518
Radiation Worker Performance (IP Section 03.04) (1 Sample)
The inspectors evaluated radiation worker and radiation protection technician performance
during:
(1)
Inclined fuel transfer system diving activities under RWP 210910
71124.05 - Radiation Monitoring Instrumentation
Walkdowns and Observations (IP Section 03.01) (5 Samples)
The inspectors evaluated the following radiation detection instrumentation during plant
walkdowns:
(1)
Radiation monitors (portal monitor, personnel contamination monitor and small article
monitor) located at the RCA exit.
(2)
Portable radiation survey instrumentation located at the RCA exit and the
Instrumentation Calibration Facility (Geiger Mueller contamination monitoring
instruments and dose rate survey instruments including ion chambers, pressurized
ion chambers and Telepoles).
(3)
Gamma spectroscopy systems and liquid scintillation instrumentation located within
the Chemistry Counting Room.
10
(4)
JL Shepherd Model 89 instrumentation calibrator.
(5)
Area Radiation Monitors and Continuous Air Monitors in the Fuel Handling Building
Calibration and Testing Program (IP Section 03.02) (1 Sample)
The inspectors evaluated the calibration and testing of the following radiation detection
instruments:
(1)
Canberra Argos Personal Contamination Monitor, SN L70L004V
71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage,
& Transportation
Radioactive Material Storage (IP Section 03.01) (2 Samples)
The inspectors evaluated the licensee's performance in controlling, labelling and securing
radioactive materials in the following locations.
(1)
Outside radioactive material storage locations
(2)
Radiation protection radioactive source storage locations (calibration facility and RCA
exit)
Radioactive Waste System Walkdown (IP Section 03.02 (1 Sample)
(1)
Inspectors walked down accessible portions of the solid radioactive waste systems
located in the radioactive waste handling building and evaluated system configuration
and functionality.
Waste Characterization and Classification (IP Section 03.03) (2 Samples)
(1)
The inspectors evaluated the licensees characterization and classification of
shipment 19-1030 consisting of reactor water cleanup resin radioactive waste
(2)
The inspectors evaluated the licensees characterization and classification of
shipment 20-1026 consisting of spent resin radioactive waste
Shipment Preparation (IP Section 03.04) (1 Sample)
(1)
The inspectors observed shipment number 21-008, containing radioactive
contaminated laundry.
Shipping Records (IP Section 03.05) (5 Samples)
The inspectors evaluated the following non-excepted radioactive material shipments through
a record review:
(1)
Radioactive waste shipment 19-1030 consisting of reactor water cleanup resin
transported in a Type B package
(2)
Radioactive waste shipment 20-1026 consisting of dewatered resin transported in
a general design package
(3)
Radioactive waste shipment 19-1025 consisting of reactor water cleanup resin
transported in a Type B package
11
(4)
Radioactive material shipment 19-3033 consisting of control rod drive mechanisms
transported in a Type A package
OTHER ACTIVITIES - BASELINE
71153 - Follow-up of Events and Notices of Enforcement Discretion
Event Report (IP Section 03.02) (1 Sample)
The inspectors evaluated the following licensee event reports (LERs):
(1)
LER 2020-002-00, Standby Liquid Control System Rendered Inoperable due to Valve
Misposition (ADAMS Accession No. ML20293A204). The inspection conclusions
associated with this LER are documented in this report under Inspection Results
Section 71153.
INSPECTION RESULTS
Human Performance Error Resulted in Unplanned RCIC Unavailability
Cornerstone
Significance
Cross-Cutting
Aspect
Report
Section
Mitigating
Systems
Green
Open/Closed
[H.12] - Avoid
Complacency
A finding of very low safety significance (Green) and associated non-cited violation of
TS 5.4.1, "Procedures," was self-revealed on January 19, 2021, when an unexpected
isolation of the RCIC steam supply occurred. Specifically, during performance of
SVI-E31-T5395A, "RCIC Steam Line Flow High Channel Functional for E31-N684A,"
Revision 8, the licensee failed to lift the lead from terminal B4 for relay 1E51-K24, resulting in
the closure of the RCIC steam supply outboard valve and an unplanned limiting condition for
operation (LCO) entry and unavailability of the RCIC system.
Description:
On January 19, 2021, during the performance of SVI-E31-T5395A, RCIC Steam Line Flow
High Channel Functional for E31-N684A, Revision 8, the licensee received several control
room alarms and identified that the RCIC steam supply outboard valve was closed. The
licensee determined that an inadvertent isolation of the RCIC system and an unplanned
inoperability had occurred. The inspectors determined that procedural steps were not
implemented during the surveillance test, as written. Specifically, the licensee failed to
perform Section 5.1 appropriately, steps 72a and 72b, and complete the independent
verification to ensure the correct lead was lifted from terminal B4 associated with relay
1E51-K24. This failure resulted in the closure of the RCIC steam supply outboard valve and
the RCIC system unavailability.
Corrective Actions: Immediate corrective actions included securing from the surveillance,
restoration of the RCIC steam supply flow path and RCIC system operability.
Corrective Action References: CR 2021-00338, Wrong Lead lifted during Surveillance
Performance 1/19/2021.
12
Performance Assessment:
Performance Deficiency: The resident inspectors determined that the licensees failure to
implement Section 5.1, Steps 72a and 72b of SVI-E31-T5395A, RCIC steam line flow high
channel functional for E31-N684A, Revision 8, was a performance deficiency. Specifically,
the failure to ensure the correct lead was lifted from terminal B4 of the relay 1E51-K24 in
accordance with the procedure directly led to the inoperability and unavailability of the RCIC
system.
Screening: The inspectors determined the performance deficiency was more than minor
because it was associated with the Human Performance attribute of the Mitigating Systems
cornerstone and adversely affected the cornerstone objective to ensure the availability,
reliability, and capability of systems that respond to initiating events to prevent undesirable
consequences. The resident inspectors determined the performance deficiency was more
than minor because it was associated with the Human Performance attribute of the Mitigating
Systems cornerstone and adversely affected the cornerstone objective to ensure the
availability, reliability, and capability of systems that respond to initiating events to prevent
undesirable consequences. Specifically, the licensee failed to lift the correct lead from
terminal B4 of relay 1E51-K24, which directly led to the closure of the RCIC steam supply
outboard valve and steam flow path isolation, thus negatively impacting the availability of the
RCIC system.
Significance: The inspectors assessed the significance of the finding using Appendix A, The
Significance Determination Process (SDP) for Findings At-Power. The inspectors screened
the finding against the Mitigating Systems screening questions in Exhibit 2 and answered
"NO" to all screening questions. Therefore, the finding screened to very low safety
significance (Green).
Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the
possibility of mistakes, latent issues, and inherent risk, even while expecting successful
outcomes. Individuals implement appropriate error reduction tools. Specifically, the licensee
failed to implement error reduction tools from Section 4.2.5.3 of NOBP-LP-2601, "Human
Performance Program," Revision 13, independent verification which resulted in the failure to
implement the procedure as written.
Enforcement:
Violation: Technical Specification 5.4.1, "Procedures," requires, in part, that written
procedures/instructions be established, implemented, and maintained covering the following
activities: the applicable procedures recommended in Regulatory Guide (RG) 1.33,
Revision 2, Appendix A, dated February 1978. RG 1.33, Revision 2, Appendix A,
Section 8b(2)(r), states, in part, that for the reactor core isolation system "Specific procedures
for surveillance tests, inspections, and calibrations should be written (implementing
procedures are required for each surveillance test, inspection, or calibration listed in the
technical specifications."
Contrary to the above, on January 19, 2020, while performing an activity affecting quality, the
licensee did not accomplish a surveillance test in accordance with the procedure and
incorrectly performed a step in surveillance procedure SVI-E31-T5395A, and failed to lift the
proper lead. Specifically, the licensee failed to lift the lead from terminal B4 from relay
1E51A-K24 resulting in an unplanned entry into Technical Specification 3.5.3, Condition A,
and adversely affected the availability of the RCIC system.
13
Enforcement Action: This violation is being treated as a non-cited violation, consistent with
Section 2.3.2 of the Enforcement Policy.
Minor Violation
Minor Violation: Licensee Event Report (LER) 05000440/2020-002 documented a condition
where the standby liquid control (SLC) system was rendered inoperable due to a valve
alignment issue. The event occurred on August 21, 2020, from 0953 to 1307 hours0.0151 days <br />0.363 hours <br />0.00216 weeks <br />4.973135e-4 months <br />
(approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />). The licensee submitted the LER to the NRC according to
10 CFR 50.73 (a)(2)(v)(A) and 50.73 (a)(2)(v)(D) for a condition that could have prevented
the fulfillment of the safety function of a system needed to shut down the reactor and mitigate
the consequences of an accident.
The LER stated that on August 20, 2020, Periodic Test Instruction, PTI-C41-P0001, Standby
Liquid Control Transfer System Pump, and Valve Operability Test, was being performed on
the SLC system. During the test on August 20, 2020, at 1248 hours0.0144 days <br />0.347 hours <br />0.00206 weeks <br />4.74864e-4 months <br />, a valve misposition
resulted in the inadvertent addition of 226 gallons of water to the SLC storage tank, causing
an unintended dilution of the boron solution. On August 21, 2020, at 0953 hours0.011 days <br />0.265 hours <br />0.00158 weeks <br />3.626165e-4 months <br />, the SLC
system was declared inoperable when the sample results for the SLC storage tank confirmed
the boron solution concentration did not meet Technical Specification (TS) 3.1.7 criteria. The
licensee restored operability on August 21, 2020, at 1307 hours0.0151 days <br />0.363 hours <br />0.00216 weeks <br />4.973135e-4 months <br />.
While reviewing LER 05000440/2020-002, the inspectors identified that the diluted boron
solution concentration existed for a time longer than permitted by TS 3.1.7. Following the
guidance in NUREG-1022 Revision 3 "Event Report Guidelines 10 CFR 50.72 and 50.73, the
inspectors determined that the licensee should have reported the diluted boron solution
concentration to the NRC as a condition which was prohibited by the plant's Technical
Specifications, pursuant to 10 CFR 50.73 (a)(2)(i)(B). Specifically, the diluted boron solution
concentration existed for longer (approximately 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />) than the total 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br /> allowed for
restoration and shutdown outage time per Technical Specifications. The licensee plans on
submitting a revised LER in response to the minor violation.
Screening: The inspectors determined the performance deficiency was minor. Specifically,
the failure to identify 10 CFR 50.73 (a)(2)(i)(B) on a Licensee Event Report did not impact the
completeness or accuracy of performance indicator data or other information provided to the
agency, as is provided in Enforcement Policy Example 6.9(d)(10).
Enforcement: This failure to comply with 10 CFR 50.73 (a)(2)(i)(B) constitutes a minor
violation that is not subject to enforcement action in accordance with the NRCs Enforcement
Policy.
14
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On April 28, 2021, the inspectors presented the integrated inspection results to
Mr. R. Penfield, Site Vice President, and other members of the licensee staff.
On February 5, 2021, the inspectors presented the radiation protection baseline
inspection results to Mr. R. Penfield, Site Vice President, and other members of the
licensee staff.
On March 18, 2021, the inspectors presented the Inservice Inspection results to
Mr. C. Elliott, Plant General Manager, and other members of the licensee staff.
On March 25, 2021, the inspectors presented the radiation protection baseline
inspection results to Mr. R. Penfield, Site Vice President, and other members of the
licensee staff.
On April 28, 2021, the inspectors presented the integrated inspection results inspection
results to Mr. R. Penfield, Site Vice President, and other members of the licensee staff.
15
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Drawings
302-0351-00000
Standby Diesel Generator Starting Air
302-0352-00000
Standby Diesel Generator Fuel Oil System
302-0353-00000
Standby Diesel Generator Lube Oil
T
Procedures
ELI-R22
15KV and 5KV Metal Clad Switchgear
3/15/2021
VLI-E12
Residual Heat Removal System
3/14/2021
VLI-E22A
10
VLI-R44
Division 1 and 2 Diesel Generator Starting Air System
6
VLI-R45
Division 1 and 2 Diesel Generator Fuel Oil System (Unit 1)
5
VLI-R47
Division 1 and 2 Diesel Generator Lube Oil
7
Procedures
FPI-A-B02
Fire Brigade Drills
01/27/2021
Work Orders
200750956
Quarterly Fire Alarm
01/14/2021
71111.08G Corrective Action
Documents
CR-2019-02185
Foreign Material Head Tensioner Lock Washer Dropped in
Cavity
03/19/2019
CR-2019-02328
Relevant Indication Identified During Containment Surface
Exams
03/14/2019
CR-2019-02523
1C22D0012B Found with Internal Parts Missing - Potential
Foreign Material
03/19/2019
CR-2019-02677
During IVVI Piece of Foreign Material Identified Between Jet
Pumps 16 and 17
03/22/2019
CR-2019-02704
During IVVI Piece of Foreign Material Identified at Jet Pump
17
03/23/2019
CR-2019-02893
Foreign Material Found Inside Reactor Vessel During Core
Verification
03/28/2019
CR-2019-02956
Legacy Foreign Material Discovered in Inner Bellows
03/29/2019
CR-2019-02990
Foreign Material - Piece of Rope Found in Inner Bellows
After Draindown
03/30/2019
CR-2019-03147
Leakage Identified During Reactor Pressure Vessel Test
04/03/2019
CR-2019-03157
Documentation of Identified Mechanical Joint Leakage
Identified During Reactor Pressure Vessel Leak Test (1R17)
04/04/2019
CR-2019-03358
Roll-Up Condition Report Following 1R17 Refuel - Foreign
Material Focused Observations
04/09/2019
CR-2019-04170
Additional Pitting Discovered in Piping Downstream of
05/07/2019
16
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Emergency Service Water
CR-2020-02539
Mechanical Leakage Identified During ISI-P2-T2200-3
03/23/2020
CR-2020-06809
1R16 Snubber As-Built Discrepancy
08/31/2020
Corrective Action
Documents
Resulting from
Inspection
ATA-2021-4926
Remove "Snubbers" from Definition of VT-3 in NQI-1042,
Paragraph 3.15 to Align with Language Contained in ASME
Section XI (2013 Edition), IWA-2213
03/12/2021
Drawings
304-672-105
Piping Isometric, Reactor Water Clean-Up System, Reactor
Building
D
305-002-113
ISI Piping Isometric, System P47 Chilled Water System Loop
B
A
305-006-103
Reactor Vessel Closure Head, Circumferential and
Meridional Weld Arrangement
A
305-006-108
ISI, System 1B13, Reactor Vessel Feedwater Nozzle Weld
Arrangement
D
305-605-103
ISI Piping Isometric, System B21, Main Steam Loop C
C
305-605-107
ISI Piping Isometric, System B21, Main Steam Loop A,
Steam Tunnel Elevation 620-6
D
305-701-102
ISI Piping Isometric, High Pressure Core Spray
D
305-871-104
System C11, Control Rod Drive, Loop B, Reactor Building
Elevation 620-6
C
92-701-0034
Pipe Support Mark Number 1E22-H0034
A
92-871-0040
Pipe Support Mark 1C11-H0040
2
B-312-641
Containment Penetration Detail, Type K
F
Miscellaneous
RRP 200724734
Repair Replacement Plan: Remove and Replace Reactor
Water Clean Up Heat Exchanger 4 Spool Piece Between
Heat Exchangers 1G33B0001C and 1G33B0002A
0
RRP 200726587
Repair Replacement Plan: Remove 3" Bypass
Piping/Components and Replace 14" Spool Piece Between
Valve 1 P45F0541 B and Heat Exchanger 1 P4280001 B.
Also Replace Portion of Spool Piece Between Valve
1 P45F0541 B and Second Elbow Downstream of the Valve.
Reference ECP 18-0162-002
0
WPS 1.1.2-001
Welding Procedure Specification: P1 Gr. 1 & 2 to P1 Gr,
13
17
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
1 & 2
NDE Reports
0941-19A-003
Liquid Penetrant Examination (PT): Piping Support Welded
Attachment: Component 1C11-H0040-WA
03/13/2019
0942-19A-008
Magnetic Particle Examination (MT): Top Head to Top Head
Flange: Component 1B13-AG
03/21/2019
0942-19A-010
Magnetic Particle Examination (MT): P124 Flued Head
Fitting to Process Pipe Attachment Weld: Component
03/25/2019
0942-19B-009
Magnetic Particle Examination (MT): 14 Pipe to 14 Elbow
03/13/2019
0942-19B-014
Magnetic Particle Examination (MT): Flange to Pipe
03/13/2019
0942-19B-015
Magnetic Particle Examination (MT): Pipe to Elbow Butt
03/13/2019
0942-19B-016
Magnetic Particle Examination (MT): (2) Half Coupling to
03/13/2019
0942-19B-017
Magnetic Particle Examination (MT): 14 Flange to 14 Elbow
Butt Weld (Repair)
03/13/2019
0942-19B-025
Magnetic Particle Examination (MT): 14 Pipe to 14 Elbow
FW-07
03/25/2019
0942-19B-031
Magnetic Particle Examination (MT): 4 Spool Piping
03/07/2019
1042-19B-018
Visual Examination System Leakage (VT-2): Order
200726587 Piping Replacement
03/27/2019
1042-21-023
Visual Examination of Pipe Hanger, Support, or Restraint
(VT-3): Chilled Water System, Pipe Anchor, Component
1P47-H0219 Located on ISI Drawing 305-002-113
03/04/2021
1042-21-024
Visual Examination of Welds (VT-1): Chilled Water System
Pipe Anchor Integral Attachment, Component
1P47-H0219-WA Located on ISI Drawing 305-002-113
03/08/2021
1042-21-029
Visual Examination of Pipe Hanger, Support, or Restraint
(VT-3): Mechanical Snubber, Drawing 305-701-102,
Component 1E22-H0034
03/04/2021
APR-R17-02
Ultrasonic Examination Summary Sheet, System 1B13, Weld
Number 1B13-N4E-KB, Safe-End to Nozzle
03/282019
MVR-004
UT Report with Calibration Records C-007 and C-008:
Component 1B13-DM
03/23/2019
18
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
UT-19-E006
UT Calibration/Examination Report: Component 1B21-006
03/15/2019
Procedures
GEH-UT-247
Procedure for Phased Array Ultrasonic Examination of
4
GEH-UT-300
Procedure for Manual Examination of Reactor Vessel
Assembly Welds in Accordance with PDI
12
NOP-CC-5762
Appendix VIII Procedure for Ultrasonic Examination of
Ferritic Welds
3
NQI-0941
Liquid Penetrant Examination
22
NQI-0942
Magnetic Particle Examination
22
NQI-1042
Visual Examination
20
Work Orders
200718215
Reactor Vessel Top Head Meridional Weld Examination
03/21/2019
200718218
Piping Weld Exams on Main Steam Lines
04/17/2019
200724734
Replace 4 Piping - RWCU Piping Between Heat
Exchangers 1G33B0001C and 1G33B0002A
04/11/2019
200726587
Replace 14 Piping - ESW B Piping Between 1P45F0541B
and Heat Exchanger 1P42B0001B and Between Valve
1P45F0541B and Second Elbow Downstream of Valve
04/09/2019
200728323
1B13 Reactor and Internals Non-Destructive Examination
04/18/2019
200794288
System P47 Exams: Pre-1R18
03/12/2021
200794289
ISI of Piping, Supports, and Components of P42, P47, and
E22 Systems
03/12/2021
71111.11Q Miscellaneous
Evolution Specific
Reactivity Plan
Perry Nuclear Power Plant End of Cycle 18 Shutdown
0
Procedures
IOI-3
81
IOI-4
Shutdown
26
Corrective Action
Documents
2021-00266
Loss of Indication for Containment Radiation Monitor
Outboard Isolation
01/15/2021
2021-01834
IFT Cable Damaged During Transfer
03/14/2021
Miscellaneous
NOP-ER-3004-03
Maintenance Rule Failure Review Form
04
NOP-SS-3001-02
Procedure Approval Form
12
Corrective Action
Documents
2021-00128
Multiple Alarms Received Coincident with Annunciator
System Ground
01/7/2021
2021-00455
EHC Pump A Leak
01/25/2021
19
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2021-01200
Planned Work Not Able to be Released as Scheduled Due to
Leakby Aux Condenser B Air Removal Suction Valve
02/23/2021
2021-02121
Unplanned Division 1 DG Start During Integrated
LOOP/LOCA Test
03/23/2021
Work Orders
200840213
Determine and Correct the Cause Ground on Electrical Bus
D1A CR 2020-09061
11/30/2020
Corrective Action
Documents
2020-09501
Ventilation Radiation Monitor Gas Channel Reading Erratic
12/16/2020
2021-00338
Wrong Lead Lifted During Surveillance Performance
01/20/2021
2021-01707
Rod SCRAM Time Recorder Did Not Perform as Expected
03/10/2021
2021-09635
Combustible Gas Mixing Compressor Suction Valve Would
Not Re-Open Following Compressor Start
12/22/2020
Work Orders
200798943
Safety Relief Valve Removes, Replaces and Offsite Testing
03/23/2021
Engineering
Changes
11-0559-002
Spring Charging Motor Margin Improvement - EH 1114
0
ECP 15-0057
Installation of U1/U2 Startup Transformer
02/26/2018
Engineering
Evaluations
ECP 19-0203-002 Dedicated Open Phase Control Room Annunciators - Unit 2
07/10/2020
Work Orders
200846449
Jumper Request to Remove Rod Block
03/17/2021
Corrective Action
Documents
2021-00266
Loss of Indication for Containment Radiation Monitor
Outboard Isolation
01/15/2021
Procedures
SVI-B21-T2100
Safety Relief Valve (SRV) Set Pressure Testing
7
SVI-D17-T2001
Plant Radiation Monitoring Isolation Valves Operability Test
8
Work Orders
100841399
Technical Support Center Ventilation Radiation Monitor Gas
Channel Reading Erratic Replacement
01/4/2021
200391663
Replace Relay 1C17A-K0112B Reactor Protection System
Trip Channel B
0
200536387
Replace Relays 1E12-K18A/19A
03/22/2021
200594427
Replace Power Supply PS22
01/12/2021
200727023
Install ECP-11-0559-002 74 Power Monitoring Relay in
Breaker EH1114
03/14/2021
200762809
Inspect/Tighten Packing-ESW PMP Div III
01/5/2021
200795982
Control Unit Hydraulic
03/17/2021
Corrective Action
Documents
2021-01545
Condensate Booster Pump C Tripped Following Reactor
Recirculation Pump Downshift
03/6/2021
20
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2021-01557
Feedwater Heater 3A Isolated on High Level Following
Recirculating Pump Downshift to Slow Speed
03/6/2021
2021-01564
Control Rod 02-27 Did Not Settle at 00
03/7/2021
2021-01604
Scaffold Level Inadvertently Dropped in the Suppression
Pool During Scaffold Erection
03/8/2021
2021-01829
Leak in High Pressure Core Spray Room
03/14/2021
2021-01857
As Found Blockage of 3-Inch Fire Protection System to
Emergency Service Water Pipe Connection
03/15/2021
2021-01939
Fuel Assembly 18P568 Identified as Cycle 18 Fuel Defect
03/17/2021
2021-02011
Design Discrepancies Contained Within the Engineering
Change Package for the 1B33-F060B Side Drain Appendage
03/19/2021
2021-02117
Ground Detected on DC Bus
03/22/2021
2021-02159
Loose Bushing Terminal Lead Connectors Found in Unit 1
Start-Up Transformer
03/24/2021
2021-02237
Issues Noted on Post Maintenance Tests for Scram
Discharge Volume Vent and Drain Valves
03/25/2021
2021-02312
Control Rod Drive Mechanism Temperature for Rod 34-43
Indicates Failed
03/27/2021
2021-02428
Hard Ground Indicated on DC Bus D-1-B
03/31/2021
Miscellaneous
1R18 Shutdown Defense-In-Depth Report
1
Procedures
SVI-B21-T1176
Reactor Coolant System Heat Up and Cooldown
Surveillance
03/7/2021
Procedures
GMI-0067
Under-Vessel Maintenance Activities
19
IMI-E2-47
Installation of Reactor Refuel Level Instrumentation for
IOI-9
03/9/2021
SVI-B21-T2100
Safety Relief Valve (SRV) Set Pressure Testing
7
SVI-E12-T2210
Leak Rate Test for RHR to FWD Injection Valves
1E12-F050A and 1E12-F053A
03/24/2021
SVI-G41-T2002
Fuel Pool Cooling and Cleanup System Operability Test
02/3/2021
SVI-R43-T7000-A Division 1 ECCS Integrated Test
12
TXI-0460
Division 1 Standby Diesel Generator Load Rejection Test
03/8/2021
Work Orders
200751888
SRV Pressure Actuation Channel a Functional for
01/20/2021
200778903
Spent Fuel Pool Level Instrument 1X13N0003 Calibration
01/27/2021
21
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Check
200778904
Level Sensor Calibration
02/3/2021
200778926
Standby Oil Pump Testing 1N27C0006A
12/30/2020
200783921
Control Rod Maximum SCRAM Insertion Time
03/6/2021
200792417
High Pressure Core Spray Pump and Valve Operability Test
02/1/2021
Corrective Action
Documents
CR-2021-01739
Two Unbriefed Dose Rate Alarms Received in Containment
Annulus 690' Elevation
03/11/2021
Corrective Action
Documents
Resulting from
Inspection
CR-2021-01952
NRC Comment During Radiological Hazards/ALARA
Inspection for Loss of Telemetry
03/16/2021
Radiation
Surveys
N/A
Radiological Surveys for Lower Inclined Fuel Transfer
System
03/15/2021
PY-M-20210310-
7
Reactor Water Cleanup Heat Exchanger Room Post Pump
Failure Verification Survey for Flow Accelerated Corrosion
Exam Work
03/09/2021
PY-M-20210312-
37
Scaffold Extension for Flow Accelerated Corrosion Exam
03/12/2021
Radiation Work
Permits (RWPs)
210518
Undervessel Activities
0
210602
Flow Accelerated Corrosion Exams in the Reactor Water
Clean-Up Heat Exchanger and Pump Room
0
210910
Inclined Fuel Transfer System Diving Activities and Support
Work
0
ALARA Plans
ALARA Plan
210518
Undervessel Activities
0
ALARA Plan
210602
Flow Accelerated Corrosion Exams in the Reactor Water
Clean-Up Heat Exchanger Room
0
ALARA Plan
210910
ALARA Plan for Inclined Fuel Transfer System Diving and
Support Activities
0
Calibration
Records
Canberra Argos Personal Contamination Monitor;
SN L70L004V
02/17/2021
Corrective Action
Documents
2019-03353
Radwaste Processing Inventory Issues
04/09/2019
2019-06245
Radwaste Tanks Require Multiple Iterations of Processing in
Order to Become Transfer Quality
07/24/2019
22
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2020-07918
Pre NRC-Assessment ATA 2020-10589 Identified
Deficiencies in Closure Packages for SVI-E31-T5190
10/13/2020
Miscellaneous
20118
Radioactive Material Transportation Training Record
07/09/2020
451802001
10 CFR 61 Laboratory Analysis of Reactor Water Clean-Up
Resin
05/25/2018
510237001
10 CFR 61 Laboratory Analysis of Spent Resin
02/25/2020
Procedures
NOP-OP-4502
Control of Radioactive Material
7
NOP-OP-5201
Shipment of Radioactive Material-Waste
10
PCP-0000
15
RPI-1301
Movement of Radioactive Material/Waste Outside of
Radiologically Controlled Areas and Onsite Interim Storage
13
Self-Assessments ATA-2020-10589
Pre NRC-Inspection - Radioactive Solid Waste Processing
and Radioactive Material Handling, Storage, and
Transportation
11/13/2020
Shipping Records 19-1025
Radioactive Waste Shipment of Reactor Water Cleanup
Resin
06/05/2019
19-1030
Radioactive Waste Shipment of Reactor Water Cleanup
Resin
07/23/2019
19-3033
Radioactive Material Shipment of Control Rod Drive
Mechanisms
07/18/2019
20-1026
Radioactive Waste Shipment of Dewatered Resin
11/30/2020
21-2008
Radioactive Material Shipment Containing Radiologically
Contaminated Laundry
03/18/2021
Work Orders
200752735
Radioactive Source Inventory/Leak Test Record
09/03/2020