{{#Wiki_filter:Planning Basis for Radiological Emergency Preparedness American Nuclear Society (ANS)
{{#Wiki_filter:Planning Basis for Radiological Emergency Preparedness
Risk-informed Emergency Preparedness (RIEP) Working Group February 1, 2023 Todd Smith, PhD Senior Level Advisor for Emergency Preparedness and Incident Response Office of Nuclear Security and Incident Response U.S. Nuclear Regulatory Commission


The NRC employs a graded approach to EP
American Nuclear Society (ANS)
Risk-informed Emergency Preparedness (RIEP) Working Group Februar y 1, 2023
 
Todd Smith, PhD Senior Level Advisor for Emergency Preparedness and Incident Response Office of Nuclear Security and Incident Response U.S. Nuclear Regulatory Commission The NRC employs a graded approach to EP
* A graded approach is a process by which the safety requirements and criteria are set commensurate with several factors including magnitude of hazards involved, characteristics of a facility, the balance between radiological and nonradiological hazards.
* A graded approach is a process by which the safety requirements and criteria are set commensurate with several factors including magnitude of hazards involved, characteristics of a facility, the balance between radiological and nonradiological hazards.
* EP regulations employ a graded approach, which is a risk-informed process Power reactors (low-power testing, power operations, decommissioning)
* EP regulations employ a graded approach, which is a risk-informed p ro c e s s Power reactors (low-power testing, power operations, decommissioning)
Research and test reactors Fuel Fabrication Facilities Independent Spent Fuel Storage Installations Monitored Retrievable Storage
Research and test reactors Fuel Fabrication Facilities Independent Spent Fuel Storage Installations Monitored Retrievable Storage Objective of Radiological EP
* The objective of emergency preparedness (EP) is to provide dose savings for a spectrum of accidents that could produce doses in excess of the Environment Protection Agency (EPA) protective action guides (PAG)
* Meeting NRC EP regulations provides reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency Reasonable assurance finding is made before a nuclear facility is licensed Inspected over the lifetime of that facility Reasonable assurance is not absolute assurance


Objective of Radiological EP
Our emergency planning requirements do not require that an adequate plan achieve a preset minimum radiation dose saving or a minimum evacuation time for the plume exposure pathway emergency planning zone in the event of a serious accident.
* The objective of emergency preparedness (EP) is to provide dose savings for a spectrum of accidents that could produce doses in excess of the Environment Protection Agency (EPA) protective action guides (PAG)
* Meeting NRC EP regulations provides reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency Reasonable assurance finding is made before a nuclear facility is licensed Inspected over the lifetime of that facility


Reasonable assurance is not absolute assurance Our emergency planning requirements do not require that an adequate plan achieve a preset minimum radiation dose saving or a minimum evacuation time for the plume exposure pathway emergency planning zone in the event of a serious accident.
It is implicit in this concept of adequate protective measures that a determination that a particular EPZ size will provide adequate protective measures does not in fact mean that emergency planning will eliminate, in every conceivable accident, the possibility of serious harm to the public.
It is implicit in this concept of adequate protective measures that a determination that a particular EPZ size will provide adequate protective measures does not in fact mean that emergency planning will eliminate, in every conceivable accident, the possibility of serious harm to the public.
[Shoreham CLI-86-13, 24 NRC 22, 30 (1986)]
[Shoreham CLI-86-13, 24 NRC 22, 30 (1986)]
Plans are useless, but planning is indispensable
- Dwight D. Eisenhower


Plans are useless, but planning is indispensable
Emergency Planning:
                                                - Dwight D. Eisenhower Emergency Planning:
* Reduces complex decision-making in an emergency
* Reduces complex decision-making in an emergency
* Simplifies the choice of possible responses
* Simplifies the choice of possible responses
* Allows for:
* Allows for:
      - Consistent and practiced approaches
- Consistent and practiced approaches
      - Addressing a spectrum of challenges irrespective of causes
- Addressing a spectrum of challenges irrespective of causes What should be used as a basis for EP?
 
In the 1970s, the Conference of Radiation Control Program Directors (CRCPD) asked, What is the accident we should be planning for ? What is the planning basis?


What should be used as a basis for EP?
In the 1970s, the Conference of Radiation Control Program Directors (CRCPD) asked, What is the accident we should be planning for? What is the planning basis?
A combined NRC and EPA Task Force considered different bases:
A combined NRC and EPA Task Force considered different bases:
* Risk
* Risk
    - Not used as a basis for planning for other hazards
- Not used as a basis for planning for other hazards
    - Public has subjective perception of risk (intuitive vs. quantitative)
- Public has subjective perception of risk (intuitive vs. quantitative)
    - Would require setting an acceptable level of risk (out of scope)
- Would require setting an acceptable level of risk (out of scope)
* Probability
* Probability
    - Society tolerates more probable events without specific planning
- Society tolerates more probable events without specific planning
    - However, accident probability provides perspective
- However, accident probability provides perspective
* Cost effectiveness
* Cost effectiveness NUREG-0396 Planning Basis for EP


NUREG-0396 Planning Basis for EP The consequences from a spectrum of accidents, tempered by probability considerations, should be considered to scope the planning efforts for:
The consequences from a spectrum of accidents, tempered by probability considerations, should be considered to scope the planning efforts for:
* The distance to which planning for predetermined protective actions is warranted
* The d i sta n ce to which planning for predetermined protective actions is warranted
* The time dependent characteristics of a potential release
* The time dependent characteristics of a potential release
* The type of radioactive materials The planning basis included a recommended 10 mile plume exposure path emergency planning zone (EPZ) and a 50 mile ingestion pathway zone NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978
* The type of radioactive materials
 
The planning basis included a recommended 10 mile plume exposure path emergency planning zone (EPZ) and a 50 mile ingestion pathway zone
 
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 EP EPZ Planning Distance The distance to which planning for predetermined protective actions is warranted
* The EPZ is a planning tool it was the consensus of the Task Force that emergency plans could be based upon a generic distance out to which predetermined actions would provide dose savings
 
beyond the generic distance it was concluded that actions could be taken on an ad hoc basis


EP  EPZ Planning Distance The distance to which planning for predetermined protective actions is warranted
The EPZ guidance does not change the requirements for emergency planning, it only sets bounds on the planning problem.
* The EPZ is a planning tool it was the consensus of the Task Force that emergency plans could be based upon a generic distance out to which predetermined actions would provide dose savings beyond the generic distance it was concluded that actions could be taken on an ad hoc basis The EPZ guidance does not change the requirements for emergency planning, it only sets bounds on the planning problem.
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978


EPZ simplifies decisions                       PAG for a prompt response                         PAR PAD Protective Action Guide (PAG) projected dose to an individual member of the public that warrants protective action Protective Action Recommendation (PAR)            PAG recommended protective measure from the nuclear power plant to offsite response        PAD PAR organizations (OROs)
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 EPZ simplifies decisions PA G for a prompt response PA R Protective Action Guide (PAG) PA D projected dose to an individual member of the public that warrants protective action
Protective Action Decision (PAD) measures taken in response to an actual or anticipated radiological release


The EPZ is scalable
Protective Action Recommendation (PAR) PA G recommended protective measure from the nuclear power plant to offsite response PA DPA R organizations (OROs)
 
Protective Action Decision (PAD) measures taken in response to an actual or anticipated radiological release The EPZ is scalable
* EPZ size based on the consequences from a spectrum of accidents, tempered by probability considerations.
* EPZ size based on the consequences from a spectrum of accidents, tempered by probability considerations.
* NRC regulations provide for scalable EPZs
* NRC regulations provide for scalable EPZs
* Reactors have been approved for a 5 mile EPZ in the past
* Reactors have been approved for a 5 mile EPZ in the past
* Depending on facility type, the EPZ may be at the site-boundary or have no EPZ
* Depending on facility type, the EPZ may be at the site-boundary or have no EPZ
* Considerable number of studies since the 1980s on sizing EPZs for passive and advanced reactor designs, many based on the NUREG-0396 methodology
* Considerable number of studies since the 1980s on sizing EPZs for passive and advanced reactor designs, many based on the NUREG-0396 methodology Considerations for EPZ size


Considerations for EPZ size The size of the EPZ is based on the following considerations:
The size of the EPZ is based on the following considerations:
: a. Projected doses from traditional design basis accidents would not exceed Federal PAG levels outside the EPZ
: a. Projected doses from traditional design basis accidents would not exceed Federal PAG levels outside the EPZ
: b. Projected doses from most core melt sequences would not exceed Federal PAG levels outside the EPZ
: b. Projected doses from most core melt sequences would not exceed Federal PAG levels outside the EPZ
: c. For the worst-case core melt sequences, immediate life-threatening doses would generally not occur outside the EPZ
: c. Fo r t h e wo rst-case core melt sequences, immediate life -threatening doses would generally not occur outside the EPZ
: d. Detailed planning within [the EPZ] would provide a substantial base for expansion of response efforts in the event that this proved necessary NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978
: d. Detailed planning within [the EPZ] would provide a substantial base for expansion of response efforts in the event that this proved necessary


The EPZ size is risk-informed Design Basis Accidents                                         Beyond Design Basis NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 The EPZ size is risk-informed
 
Design Basis Accidents Beyond Design Basis
 
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 EP is a matter of judgment
 
A reading of the Report [NUREG -0396] indicates clearly that the margins of safety provided by the recommended 10- mile radius were not calculated in any precise fashion but were qualitatively found adequate as a matter of judgment.


EP is a matter of judgment A reading of the Report [NUREG-0396] indicates clearly that the margins of safety provided by the recommended 10-mile radius were not calculated in any precise fashion but were qualitatively found adequate as a matter of judgment.
[55 FR 5605, Feb 16, 1990]
[55 FR 5605, Feb 16, 1990]
EPZ size methodology can be applied to any facility


EPZ size methodology can be applied to any facility EPRI TR-113509, Technical Aspects of ALWR Emergency Planning, Final Report, September 1999
EPRI TR-113509, Technical Aspects of ALWR Emergency Planning, Final Report, September 1999 Whats the likelihood of events considered?


Whats the likelihood of events considered?
NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975 down to 1 chance in 10 lifetimes of the universe
NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975


down to 1 chance in 10 lifetimes of the universe NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975
NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975 Shouldnt you be planning for the worst-case?


Shouldnt you be planning for the worst-case?
Regulation does not require dedication of resources to handle every possible accident that can be imagined. The concept of the regulation is that there should be core planning with sufficient planning flexibility to develop reasonable response to those very serious low probability accidents which could affect the public.
Regulation does not require dedication of resources to handle every possible accident that can be imagined. The concept of the regulation is that there should be core planning with sufficient planning flexibility to develop reasonable response to those very serious low probability accidents which could affect the public.
[SONGS CLI-83-10, 17 NRC 528, (1983)]
[SONGS CLI-83-10, 17 NRC 528, (1983)]
Capabilities are available at State and Federal level
The Task Force believes that it is not appropriate to develop specific plans for the most severe and most improbable Class 9 events.


Capabilities are available at State and Federal level The Task Force believes that it is not appropriate to develop specific plans for the most severe and most improbable Class 9 events.
The Task Force, however, does believe that consideration should be given to the characteristics of Class 9 events in judging whether emergency plans based primarily on smaller accidents can be expanded to cope with larger events.
The Task Force, however, does believe that consideration should be given to the characteristics of Class 9 events in judging whether emergency plans based primarily on smaller accidents can be expanded to cope with larger events.
The planning basis recommended by the Task Force therefore includes some of the key characteristics of very large releases to assure that site specific capabilities could be effectively augmented with general emergency preparedness (response) resources of the Federal government should the need arise.
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978


Response capabilities are coordinated across levels Licensee            State            Federal
The planning basis recommended by the Task Force therefore includes some of the key characteristics of very large releases to assure that site specific capabilities could be ef fectively augmented with general emergency preparedness (response) resources of the Federal government should the need arise.
 
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 Response capabilities are coordinated across levels


Planning Time The time dependent characteristics of a potential release NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978
Licensee State Federal Planning Time The time dependent characteristics of a potential release
 
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 Effectiveness of protective actions related to timing
 
The guidance cannot be very specific because of the wide range of time frames associated with the spectrum of accidents considered.


Effectiveness of protective actions related to timing The guidance cannot be very specific because of the wide range of time frames associated with the spectrum of accidents considered.
Therefore, it will be necessary for planners to consider the possible different time periods between the initiating event and arrival of the plume and possible time periods of release in relationship to time needed to implement protective actions.
Therefore, it will be necessary for planners to consider the possible different time periods between the initiating event and arrival of the plume and possible time periods of release in relationship to time needed to implement protective actions.
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978


Conservatively bounds timing of severe accidents NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 Conservatively bounds timing of severe accidents


Time basis informs functional requirements
NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975 Time basis informs functional requirements
* nuclear power reactor licensees shall establish and maintain the capability to assess, classify, and declare an emergency condition within 15 minutes after the availability of indications to plant operators that an emergency action level has been exceeded
* nuclear power reactor licensees shall establish and maintain the capability to assess, classify, and declare an emergency condition within 15 minutes after the availability of indications to plant operators that an emergency action level has been exceeded
* A licensee shall have the capability to notify responsible State and local governmental agencies within 15 minutes after declaring an emergency
* A licensee shall have the capability to notify responsible State and local governmental agencies within 15 minutes after declaring an emergency
* The design objective of the prompt public alert and notification system shall be to have the capability to essentially complete the initial alerting and initiate notification of the public within the plume exposure pathway EPZ within about 15 minutes Appendix E to 10 CFR Part 50
* The design objective of the prompt public alert and notification system shall be to have the capability to essentially complete the initial alerting and initiate notification of the public within the plume exposure pathway EPZ within about 15 minutes


Release Characteristics The type of radioactive materials NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978
Appendix E to 10 CFR Part 50 Release Characteristics The type of radioactive materials


WASH-1400 informed early understanding NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975
NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 WASH-1400 informed early understanding


Our understanding of accidents has evolved NUREG/BR-0359, Revision 3, Modeling Potential Reactor Accident ConsequencesState-of-the-Art Reactor Consequence Analyses: Using decades of research and experience to model accident progression, mitigation, emergency response, and health effects, October 2020
NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975 Our understanding of accidents has evolved
 
NUREG/BR-0359, Revision 3, Modeling Potential Reactor Accident Consequences State-of-the-Art Reactor Consequence Analyses: Using decades of research and experience to model accident progression, mitigation, emergency response, and health effects, October 2020 and will continue to evolve Commission Policy Statement on Advanced Reactors
 
the Commission expects, as a minimum, at least the same degree of protection of the environment and public health and safety and the common defense and security that is required for current generation light-water reactors (LWRs)


and will continue to evolve Commission Policy Statement on Advanced Reactors the Commission expects, as a minimum, at least the same degree of protection of the environment and public health and safety and the common defense and security that is required for current generation light-water reactors (LWRs)
The Commission also expects that advanced reactor designs will comply with the Commissions safety goal policy statement.
The Commission also expects that advanced reactor designs will comply with the Commissions safety goal policy statement.
In addition, the Commission expects that the safety features of these advanced reactor designs will be complemented by the operational program for Emergency Planning (EP). This EP operational program, in turn, must be demonstrated by inspections, tests, analyses, and acceptance criteria to ensure effective implementation of established measures.
In addition, the Commission expects that the safety features of these advanced reactor designs will be complemented by the operational program for Emergency Planning (EP). This EP operational program, in turn, must be demonstrated by inspections, tests, analyses, and acceptance criteria to ensure effective implementation of established measures.
US NRC, Final Policy Statement: Policy Statement on the Regulation of Advanced Reactors, [NRC-2008-0237];
 
US NRC, Final Policy Statement: Policy Statement on the Regulation of Advanced Reactors, [NRC -2008- 0237];
73 FR 60612, October 14, 2008.
73 FR 60612, October 14, 2008.
EP is a final, independent layer of defense in depth


EP is a final, independent layer of defense in depth DID is an approach to designing and operating nuclear facilities that prevents and mitigates accidents that release radiation or hazardous materials. Defense in depth includes the use of access controls, physical barriers, redundant and diverse key safety functions, and emergency response measures.
DID is an approach to designing and operating nuclear facilities that prevents and mitigates accidents that release radiation or hazardous materials. Defense in depth includes the use of access controls, physical barriers, redundant and diverse key safety functions, and emergency response measures.
CAUTION! Some references do not clearly differentiate DID of design from siting and EP.1 NEI 18-04, Rev. 1, Risk-Informed Performance-Based Technology Inclusive Guidance for Non-Light Water Reactor Licensing Basis Development August 2019.


IAEA approach provides similar considerations IAEA. Addressing the issue of EPZ sizing for SMR, Technical Meeting on Challenges in the Application of the Design Safety Requirements for Nuclear Power Plants to Small and Medium Sized Reactors, September 4th, 2017
CAUTION! Some references do not clearly differentiate DID of design from siting and EP.1


The planning basis informs EP planning functions Ensure capabilities exist to detect, classify, notify, assess, mitigate, and effectively respond to an emergency Planning Basis           Emergency Planning Needs and Functions EPZ size, exposure pathways, protective Distance    action strategies Spectrum Timeliness of classification and notification, of              Time      protective action strategies, mitigation Accidents                    Detection and assessment capabilities, Materials    radiological protection, mitigation
NEI 18- 04, Rev. 1, Risk -Informed Performance-Based Technology Inclusive Guidance for Non-Light Water Reactor Licensing Basis Development August 2019.
IAEA approach provides similar considerations


Emergency preparedness is evidence-based Protective Action Decisionmaking in the Intermediate Phase (NUREG/CR-7248)
IAEA. Addressing the issue of EPZ sizing for SMR, Technical Meeting on Challenges in the Application of the Design Safety Requirements for Nuclear Power Plants to Small and Medium Sized Reactors, September 4th, 2017 The planning basis informs EP planning functions Ensure capabilities exist to detect, classify, notify, assess, mitigate, and effectively respond to an emergency
 
Planning Basis Emergency Planning Needs and Functions Distance EPZ size, exposure pathways, protective Spectrum action strategies of Time Timeliness of classification and notification, protective action strategies, mitigation Accidents Detection and assessment capabilities, Materials radiological protection, mitigation Emergency preparedness is evidence-based
 
Protective Action Decisionmaking in the Intermediate Phase (NUREG/CR-7248)
Evacuation Time Estimate Study (NUREG/CR-7269)
Evacuation Time Estimate Study (NUREG/CR-7269)
Emergency Planning Zone (EPZ) Size Methodology Sensitivity of Dose Projections to Weather Analysis of the Effectiveness of Sheltering-in-Place Use of Heating and Ventilation Systems while Sheltering-in-Place Dose Reduction Effectiveness of Masks Nonradiological Health Impacts of Evacuations and Relocations (NUREG/CR-7285)
Emergency Planning Zone (EPZ) Size Methodology Sensitivity of Dose Projections to Weather Analysis of the Effectiveness of Sheltering-in-Place Use of Heating and Ventilation Systems while Sheltering-in-Place Dose Reduction Effectiveness of Masks Nonradiological Health Impacts of Evacuations and Relocations (NUREG/CR-7285)
MACCS Consequence Model Improvements Impact on Protective Action Strategies
MACCS Consequence Model Improvements Impact on Protective Action Strategies Roles and Responsibilities
 
S tate / L o ca l FEMA - Technical N RC Review Hazards Division Set EP standards &
Responsible for emergency Reviews State and local reviews and approves planning and response for radiological emergency Review Findings licensee plans the community plans against planning Considers FEMA findings of Assess their own Assist standards offsite plans in reasonable capabilities and needs Can assist State & locals in assurance determinations Voluntarily participate in planning, if asked licensee planning NRC Licensee


Roles and Responsibilities FEMA - Technical                                      NRC State / Local                    Hazards Division Review                                                Set EP standards &
Develops and maintains radiological emergency plans.
Responsible for emergency                                                        reviews and approves Reviews State and local planning and response for                                        Review Findings licensee plans radiological emergency the community plans against planning                      Considers FEMA findings of Assess their own                    standards                                    offsite plans in reasonable Assist capabilities and needs                                                            assurance determinations Can assist State & locals in Voluntarily participate in          planning, if asked licensee planning NRC Licensee Develops and maintains radiological emergency plans.
(NRC review and approval)
(NRC review and approval)
Examples of Risk-Informed Approaches to EP Regulatory Basis for Decommissioning Rule


Examples of Risk-Informed Approaches to EP Regulatory Basis for Decommissioning Rule The overall objective of EP is to provide dose savings for a spectrum of accidents that could produce offsite doses in excess of PAGs EPZs are areas for which planning is needed to assure that prompt and effective actions can be taken to protect the public in the event of an accident For a facility in decommissioning:
The overall objective of EP is to provide dose savings for a spectrum of accidents that could produce offsite doses in excess of PAGs
 
EPZs are areas for which planning is needed to assure that prompt and effective actions can be taken to protect the public in the event of an accident
 
For a facility in decommissioning:
* The spectrum of accidents are significantly fewer than at an operating plant
* The spectrum of accidents are significantly fewer than at an operating plant
* Design Basis Accidents will not exceed 1 rem offsite
* Design Basis Accidents will not exceed 1 rem offsite
* At least 10 hours available to mitigate or initiate protective actions
* At least 10 hours available to mitigate or initiate protective actions Levels of Decommissioning Applying the planning basis to regulation
 
Proposed rule for power reactors based on the reduction in risk at four levels of decommissioning,
including the time when spent fuel has sufficiently decayed such that it would not reach self -ignition temperature in 10 hours under adiabatic heatup conditions
 
Initiating Event 10 hours Mitigate or (Severe Earthquake) Initiate Response
 
Time
 
Federal Register Notice Proposed Rule, Regulatory Improvements for Production and Utilization Facilities Transitioning to Decommissioning: Proposed Rule, 87 FR 12254 March 3, 2022 Conservatively assumes spent fuel pool damaged and drains instantaneously
 
NUREG-2161, Consequence Study of a Beyond -Design-Basis Earthquake Affecting the Spent Fuel Pool for a U.S.
Mark I Boiling Water Reactor, September 2014 Conservatively assumes unfavorable heat transfer
 
Transmittal of Reports to Inform Decommissioning Plant Rulemaking for User Need Request NSIR-2015- 001, dated May 31, 2016 (ADAMS Accession No. ML16110A416)
Conservatively assumes instantaneous release
 
Transmittal of Reports to Inform Decommissioning Plant Rulemaking for User Need Request NSIR-2015- 001, dated May 31, 2016 (ADAMS Accession No. ML16110A416)
Risk-informed regulations cover uncertainty


Levels of Decommissioning Applying the planning basis to regulation Proposed rule for power reactors based on the reduction in risk at four levels of decommissioning, including the time when spent fuel has sufficiently decayed such that it would not reach self-ignition temperature in 10 hours under adiabatic heatup conditions 10 hours Initiating Event                                                                                        Mitigate or (Severe Earthquake)                                                                                      Initiate Response Time Federal Register NoticeProposed Rule, Regulatory Improvements for Production and Utilization Facilities Transitioning to Decommissioning: Proposed Rule, 87 FR 12254 March 3, 2022
Proposed regulatory criteria


Conservatively assumes spent fuel pool damaged and drains instantaneously NUREG-2161, Consequence Study of a Beyond-Design-Basis Earthquake Affecting the Spent Fuel Pool for a U.S.
Minimum time margin: + 8.5 hr
Mark I Boiling Water Reactor, September 2014


Conservatively assumes unfavorable heat transfer Transmittal of Reports to Inform Decommissioning Plant Rulemaking for User Need Request NSIR-2015-001, dated May 31, 2016 (ADAMS Accession No. ML16110A416)
Median time margin: + 24 hr


Conservatively assumes instantaneous release Transmittal of Reports to Inform Decommissioning Plant Rulemaking for User Need Request NSIR-2015-001, dated May 31, 2016 (ADAMS Accession No. ML16110A416)
Realistic time margin: + days


Risk-informed regulations cover uncertainty Proposed regulatory criteria Minimum time margin: + 8.5 hr Median time margin: + 24 hr Realistic time margin: + days 10 hr           Margin in 10 hr criteria                       Time
10 hr Margin in 10 hr criteria Time Key Takeaways Emergency Preparedness


Key Takeaways Emergency Preparedness EP ensures protective actions can and will be taken EP regulations are risk-informed and commensurate to the potential hazards presented by the class of facility Informed by characteristics of a spectrum of accidents Guidance and tools to support planning functions are informed by insights from PRAs EP is not based on risk or probability of an accident occurring Requires judgmentbacked by evidence}}
EP ensures protective actions can and will be taken EP regulations are risk-informed and commensurate to the potential hazards presented by the class of facility Informed by characteristics of a spectrum of accidents Guidance and tools to support planning functions are informed by insights from PRAs EP is not based on risk or probability of an accident occurring Requires judgmentbacked by evidence}}

Revision as of 09:55, 15 November 2024

ANS Riep Wg - EP Planning Basis - February 2023
ML23032A466
Person / Time
Issue date: 02/01/2023
From: Tanya Smith
NRC/NSIR/DPR
To:
References
Download: ML23032A466 (1)


Text

Planning Basis for Radiological Emergency Preparedness

American Nuclear Society (ANS)

Risk-informed Emergency Preparedness (RIEP) Working Group Februar y 1, 2023

Todd Smith, PhD Senior Level Advisor for Emergency Preparedness and Incident Response Office of Nuclear Security and Incident Response U.S. Nuclear Regulatory Commission The NRC employs a graded approach to EP

  • A graded approach is a process by which the safety requirements and criteria are set commensurate with several factors including magnitude of hazards involved, characteristics of a facility, the balance between radiological and nonradiological hazards.
  • EP regulations employ a graded approach, which is a risk-informed p ro c e s s Power reactors (low-power testing, power operations, decommissioning)

Research and test reactors Fuel Fabrication Facilities Independent Spent Fuel Storage Installations Monitored Retrievable Storage Objective of Radiological EP

  • The objective of emergency preparedness (EP) is to provide dose savings for a spectrum of accidents that could produce doses in excess of the Environment Protection Agency (EPA) protective action guides (PAG)
  • Meeting NRC EP regulations provides reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency Reasonable assurance finding is made before a nuclear facility is licensed Inspected over the lifetime of that facility Reasonable assurance is not absolute assurance

Our emergency planning requirements do not require that an adequate plan achieve a preset minimum radiation dose saving or a minimum evacuation time for the plume exposure pathway emergency planning zone in the event of a serious accident.

It is implicit in this concept of adequate protective measures that a determination that a particular EPZ size will provide adequate protective measures does not in fact mean that emergency planning will eliminate, in every conceivable accident, the possibility of serious harm to the public.

[Shoreham CLI-86-13, 24 NRC 22, 30 (1986)]

Plans are useless, but planning is indispensable

- Dwight D. Eisenhower

Emergency Planning:

  • Reduces complex decision-making in an emergency
  • Simplifies the choice of possible responses
  • Allows for:

- Consistent and practiced approaches

- Addressing a spectrum of challenges irrespective of causes What should be used as a basis for EP?

In the 1970s, the Conference of Radiation Control Program Directors (CRCPD) asked, What is the accident we should be planning for ? What is the planning basis?

A combined NRC and EPA Task Force considered different bases:

  • Risk

- Not used as a basis for planning for other hazards

- Public has subjective perception of risk (intuitive vs. quantitative)

- Would require setting an acceptable level of risk (out of scope)

  • Probability

- Society tolerates more probable events without specific planning

- However, accident probability provides perspective

The consequences from a spectrum of accidents, tempered by probability considerations, should be considered to scope the planning efforts for:

  • The d i sta n ce to which planning for predetermined protective actions is warranted
  • The time dependent characteristics of a potential release
  • The type of radioactive materials

The planning basis included a recommended 10 mile plume exposure path emergency planning zone (EPZ) and a 50 mile ingestion pathway zone

NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 EP EPZ Planning Distance The distance to which planning for predetermined protective actions is warranted

  • The EPZ is a planning tool it was the consensus of the Task Force that emergency plans could be based upon a generic distance out to which predetermined actions would provide dose savings

beyond the generic distance it was concluded that actions could be taken on an ad hoc basis

The EPZ guidance does not change the requirements for emergency planning, it only sets bounds on the planning problem.

NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 EPZ simplifies decisions PA G for a prompt response PA R Protective Action Guide (PAG) PA D projected dose to an individual member of the public that warrants protective action

Protective Action Recommendation (PAR) PA G recommended protective measure from the nuclear power plant to offsite response PA DPA R organizations (OROs)

Protective Action Decision (PAD) measures taken in response to an actual or anticipated radiological release The EPZ is scalable

  • EPZ size based on the consequences from a spectrum of accidents, tempered by probability considerations.
  • NRC regulations provide for scalable EPZs
  • Reactors have been approved for a 5 mile EPZ in the past
  • Depending on facility type, the EPZ may be at the site-boundary or have no EPZ
  • Considerable number of studies since the 1980s on sizing EPZs for passive and advanced reactor designs, many based on the NUREG-0396 methodology Considerations for EPZ size

The size of the EPZ is based on the following considerations:

a. Projected doses from traditional design basis accidents would not exceed Federal PAG levels outside the EPZ
b. Projected doses from most core melt sequences would not exceed Federal PAG levels outside the EPZ
c. Fo r t h e wo rst-case core melt sequences, immediate life -threatening doses would generally not occur outside the EPZ
d. Detailed planning within [the EPZ] would provide a substantial base for expansion of response efforts in the event that this proved necessary

NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 The EPZ size is risk-informed

Design Basis Accidents Beyond Design Basis

NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 EP is a matter of judgment

A reading of the Report [NUREG -0396] indicates clearly that the margins of safety provided by the recommended 10- mile radius were not calculated in any precise fashion but were qualitatively found adequate as a matter of judgment.

[55 FR 5605, Feb 16, 1990]

EPZ size methodology can be applied to any facility

EPRI TR-113509, Technical Aspects of ALWR Emergency Planning, Final Report, September 1999 Whats the likelihood of events considered?

NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975 down to 1 chance in 10 lifetimes of the universe

NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975 Shouldnt you be planning for the worst-case?

Regulation does not require dedication of resources to handle every possible accident that can be imagined. The concept of the regulation is that there should be core planning with sufficient planning flexibility to develop reasonable response to those very serious low probability accidents which could affect the public.

[SONGS CLI-83-10, 17 NRC 528, (1983)]

Capabilities are available at State and Federal level

The Task Force believes that it is not appropriate to develop specific plans for the most severe and most improbable Class 9 events.

The Task Force, however, does believe that consideration should be given to the characteristics of Class 9 events in judging whether emergency plans based primarily on smaller accidents can be expanded to cope with larger events.

The planning basis recommended by the Task Force therefore includes some of the key characteristics of very large releases to assure that site specific capabilities could be ef fectively augmented with general emergency preparedness (response) resources of the Federal government should the need arise.

NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 Response capabilities are coordinated across levels

Licensee State Federal Planning Time The time dependent characteristics of a potential release

NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 Effectiveness of protective actions related to timing

The guidance cannot be very specific because of the wide range of time frames associated with the spectrum of accidents considered.

Therefore, it will be necessary for planners to consider the possible different time periods between the initiating event and arrival of the plume and possible time periods of release in relationship to time needed to implement protective actions.

NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 Conservatively bounds timing of severe accidents

NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975 Time basis informs functional requirements

  • nuclear power reactor licensees shall establish and maintain the capability to assess, classify, and declare an emergency condition within 15 minutes after the availability of indications to plant operators that an emergency action level has been exceeded
  • A licensee shall have the capability to notify responsible State and local governmental agencies within 15 minutes after declaring an emergency
  • The design objective of the prompt public alert and notification system shall be to have the capability to essentially complete the initial alerting and initiate notification of the public within the plume exposure pathway EPZ within about 15 minutes

Appendix E to 10 CFR Part 50 Release Characteristics The type of radioactive materials

NUREG-0396, Planning Basis for the Development of State and Local Government Radiological Emergency Response Plans in Support of Light Water Nuclear Power Plants, November 1978 WASH-1400 informed early understanding

NUREG-075/014 (WASH-1400), Reactor Safety Study: An Assessment of Accident Risks in U.S. Commercial Nuclear Power Plants, October 1975 Our understanding of accidents has evolved

NUREG/BR-0359, Revision 3, Modeling Potential Reactor Accident Consequences State-of-the-Art Reactor Consequence Analyses: Using decades of research and experience to model accident progression, mitigation, emergency response, and health effects, October 2020 and will continue to evolve Commission Policy Statement on Advanced Reactors

the Commission expects, as a minimum, at least the same degree of protection of the environment and public health and safety and the common defense and security that is required for current generation light-water reactors (LWRs)

The Commission also expects that advanced reactor designs will comply with the Commissions safety goal policy statement.

In addition, the Commission expects that the safety features of these advanced reactor designs will be complemented by the operational program for Emergency Planning (EP). This EP operational program, in turn, must be demonstrated by inspections, tests, analyses, and acceptance criteria to ensure effective implementation of established measures.

US NRC, Final Policy Statement: Policy Statement on the Regulation of Advanced Reactors, [NRC -2008- 0237];

73 FR 60612, October 14, 2008.

EP is a final, independent layer of defense in depth

DID is an approach to designing and operating nuclear facilities that prevents and mitigates accidents that release radiation or hazardous materials. Defense in depth includes the use of access controls, physical barriers, redundant and diverse key safety functions, and emergency response measures.

CAUTION! Some references do not clearly differentiate DID of design from siting and EP.1

NEI 18- 04, Rev. 1, Risk -Informed Performance-Based Technology Inclusive Guidance for Non-Light Water Reactor Licensing Basis Development August 2019.

IAEA approach provides similar considerations

IAEA. Addressing the issue of EPZ sizing for SMR, Technical Meeting on Challenges in the Application of the Design Safety Requirements for Nuclear Power Plants to Small and Medium Sized Reactors, September 4th, 2017 The planning basis informs EP planning functions Ensure capabilities exist to detect, classify, notify, assess, mitigate, and effectively respond to an emergency

Planning Basis Emergency Planning Needs and Functions Distance EPZ size, exposure pathways, protective Spectrum action strategies of Time Timeliness of classification and notification, protective action strategies, mitigation Accidents Detection and assessment capabilities, Materials radiological protection, mitigation Emergency preparedness is evidence-based

Protective Action Decisionmaking in the Intermediate Phase (NUREG/CR-7248)

Evacuation Time Estimate Study (NUREG/CR-7269)

Emergency Planning Zone (EPZ) Size Methodology Sensitivity of Dose Projections to Weather Analysis of the Effectiveness of Sheltering-in-Place Use of Heating and Ventilation Systems while Sheltering-in-Place Dose Reduction Effectiveness of Masks Nonradiological Health Impacts of Evacuations and Relocations (NUREG/CR-7285)

MACCS Consequence Model Improvements Impact on Protective Action Strategies Roles and Responsibilities

S tate / L o ca l FEMA - Technical N RC Review Hazards Division Set EP standards &

Responsible for emergency Reviews State and local reviews and approves planning and response for radiological emergency Review Findings licensee plans the community plans against planning Considers FEMA findings of Assess their own Assist standards offsite plans in reasonable capabilities and needs Can assist State & locals in assurance determinations Voluntarily participate in planning, if asked licensee planning NRC Licensee

Develops and maintains radiological emergency plans.

(NRC review and approval)

Examples of Risk-Informed Approaches to EP Regulatory Basis for Decommissioning Rule

The overall objective of EP is to provide dose savings for a spectrum of accidents that could produce offsite doses in excess of PAGs

EPZs are areas for which planning is needed to assure that prompt and effective actions can be taken to protect the public in the event of an accident

For a facility in decommissioning:

  • The spectrum of accidents are significantly fewer than at an operating plant
  • Design Basis Accidents will not exceed 1 rem offsite
  • At least 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> available to mitigate or initiate protective actions Levels of Decommissioning Applying the planning basis to regulation

Proposed rule for power reactors based on the reduction in risk at four levels of decommissioning,

including the time when spent fuel has sufficiently decayed such that it would not reach self -ignition temperature in 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> under adiabatic heatup conditions

Initiating Event 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> Mitigate or (Severe Earthquake) Initiate Response

Time

Federal Register Notice Proposed Rule, Regulatory Improvements for Production and Utilization Facilities Transitioning to Decommissioning: Proposed Rule, 87 FR 12254 March 3, 2022 Conservatively assumes spent fuel pool damaged and drains instantaneously

NUREG-2161, Consequence Study of a Beyond -Design-Basis Earthquake Affecting the Spent Fuel Pool for a U.S.

Mark I Boiling Water Reactor, September 2014 Conservatively assumes unfavorable heat transfer

Transmittal of Reports to Inform Decommissioning Plant Rulemaking for User Need Request NSIR-2015- 001, dated May 31, 2016 (ADAMS Accession No. ML16110A416)

Conservatively assumes instantaneous release

Transmittal of Reports to Inform Decommissioning Plant Rulemaking for User Need Request NSIR-2015- 001, dated May 31, 2016 (ADAMS Accession No. ML16110A416)

Risk-informed regulations cover uncertainty

Proposed regulatory criteria

Minimum time margin: + 8.5 hr

Median time margin: + 24 hr

Realistic time margin: + days

10 hr Margin in 10 hr criteria Time Key Takeaways Emergency Preparedness

EP ensures protective actions can and will be taken EP regulations are risk-informed and commensurate to the potential hazards presented by the class of facility Informed by characteristics of a spectrum of accidents Guidance and tools to support planning functions are informed by insights from PRAs EP is not based on risk or probability of an accident occurring Requires judgmentbacked by evidence