{{#Wiki_filter:John T. Carlin | {{#Wiki_filter:John T. Carlin R.E. Ginna Nuclear Power Plant, LLC Site Vice President 1503 Lake Road Ontario, New York 14519-9364 585.771.5200 585.771.3943 Fax John.carlin @constellation.com uConstellation Group Energy Generation August 16, 2007 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION: Document Control Desk | ||
@constellation.com uConstellation Energy Generation | |||
==SUBJECT:== | ==SUBJECT:== | ||
R.E. Ginna Nuclear Power Plant Docket No. 50-244 Fitness for Duty Program Performance Data Report In accordance with the requirements set forth in 10 CFR 26.71(d), R.E. Ginna Nuclear Power Plant, LLC has compiled and is submitting the enclosed semi-annual Fitness for Duty (FFD) Program Performance Data Report covering the period January 1, 2007 through June 30, 2007 Very truly yours, Enclosure cc: S. J. Collins, NRC D. V. Pickett, NRC Resident Inspector, NRC 0A | |||
Henderson, Fitness fr, Duty Specialist" : (585) 771-5585 Contacit Na'me."Poe CUTOFFS: Screen/Confirmation (ng/ml) [X] Appendix A to 10 CFR Part 26 Marijuana 50/15 Amphetamines Cocaine Phencyclidine Opiates Alcohol (% BAC)Annual (Jan-Dec) | |||
Random testing rates: Employees | FRtness for Duty Program Performance Data Personnel Subject to 10 CFR Part 26 C?.,; | ||
& Contractors by 50%.Long-term Short-term Testing Results Licensee Employees Contractor Personnel* | ONSTELLATION ENERGY GROUP0:5 06/30/2007 | ||
Contractor Personnel Average Number with 460 0 272 Unescorted Access Categories Tested Positive Tested Positive Tested Positive Pre-Access 2 0 0 0 118 0 For Cause Post-accident 1 0 0 0 0 0 Observed Behavior 2 0 0 0 1- 0 Random 131 0 0 0 76 0 Follow-up 11 0 0 0 11 0 Other 2** 0 0 0 1*... 0'TOTAL ~ Z1,49 .i207*f,~R.E. Ginna Nuclear Power Plant does not differentiate between long-term and short-term contractors. | -Coma'' 6 Mthds Ending4 I:.R.'E._GinnaNuclear PoWer Plant Tamm-y"H. Henderson, Fitness fr, Duty Specialist" : (585) 771-5585 Contacit Na'me."Poe CUTOFFS: Screen/Confirmation (ng/ml) [X] Appendix A to 10 CFR Part 26 Marijuana 50/15 Amphetamines Cocaine Phencyclidine Opiates Alcohol (% BAC) | ||
All contractors who have obtained unescorted access are considered short-term. | Annual (Jan-Dec) Random testing rates: Employees & Contractors by 50%. | ||
** 1 employee "other" was a recollection of a dilute random sample.1 employee "other" was a test conducted at the request of the Medical Review Officer during an adjudication of the employee.*** As a contractor was being escorted to the testing facility for a test requested for observed behavior, the contractor informed his escort he chose to return home rather than have the drug and alcohol test conducted. | Long-term Short-term Testing Results Licensee Employees Contractor Personnel* Contractor Personnel Average Number with 460 0 272 Unescorted Access Categories Tested Positive Tested Positive Tested Positive Pre-Access 2 0 0 0 118 0 For Cause Post-accident 1 0 0 0 0 0 Observed Behavior 2 0 0 0 1- 0 Random 131 0 0 0 76 0 Follow-up 11 0 0 0 11 0 Other 2** 0 0 0 1*... 0 | ||
The test was logged as a refusal, and the contractor's unescorted access was permanently denied.**** A member of the MRO staff had a drug and alcohol test conducted prior to being placed in the FFD pool. Since Unescorted Access was not being granted, the category of the test was marked as "other" rather than pre-access. | 'TOTAL ~ Z1,49 .i207*f,~ | ||
Breakdown of Confirmed Positive Tests for Specific Substances Marijuana Cocaine Opiates Amphe- Phency- Alcohol Refusal Total tamines lidinetoesTta to test Licensee Employees 0 0 0 0 0 0 0 0 Long-Term Contractors* | R.E. Ginna Nuclear Power Plant does not differentiate between long-term and short-term contractors. All contractors who have obtained unescorted access are considered short-term. | ||
0 0 0 0 0 0 0 0 Short-Term Contractors 0 0 0 0 0 1** 1.. | ** 1 employee "other" was a recollection of a dilute random sample. | ||
All contractors who have obtained unescorted access are considered short-term. | 1 employee "other" was a test conducted at the request of the Medical Review Officer during an adjudication of the employee. | ||
** Per procedure, the contractor who refused to take a drug and alcohol test had his unescorted access permanently denied.NRC Reportable Events (Per | *** As a contractor was being escorted to the testing facility for a test requested for observed behavior, the contractor informed his escort he chose to return home rather than have the drug and alcohol test conducted. The test was logged as a refusal, and the contractor's unescorted access was permanently denied. | ||
**** A member of the MRO staff had a drug and alcohol test conducted prior to being placed in the FFD pool. Since Unescorted Access was not being granted, the category of the test was marked as "other" rather than pre-access. | |||
Breakdown of Confirmed Positive Tests for Specific Substances Marijuana Cocaine Opiates Amphe- Phency- Alcohol Refusal Total tamines lidinetoesTta to test Licensee Employees 0 0 0 0 0 0 0 0 Long-Term Contractors* 0 0 0 0 0 0 0 0 Short-Term Contractors 0 0 0 0 0 1** 1 TAL. .. 0 O'0 | |||
.0 0 0 1. 1 Management Actions: | |||
* R.E. Ginna Nuclear Power Plant does not differentiate between long-term and short-term contractors. All contractors who have obtained unescorted access are considered short-term. | |||
** Per procedure, the contractor who refused to take a drug and alcohol test had his unescorted access permanently denied. | |||
NRC Reportable Events (Per 10CFR Part 26.73) | |||
There were no reportable events during this performance data period. | |||
}} | |||
Revision as of 03:14, 23 November 2019
| ML072390206 | |
| Person / Time | |
|---|---|
| Site: | Ginna |
| Issue date: | 08/16/2007 |
| From: | John Carlin Constellation Energy Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 1001835 | |
| Download: ML072390206 (3) | |
Text
John T. Carlin R.E. Ginna Nuclear Power Plant, LLC Site Vice President 1503 Lake Road Ontario, New York 14519-9364 585.771.5200 585.771.3943 Fax John.carlin @constellation.com uConstellation Group Energy Generation August 16, 2007 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION: Document Control Desk
SUBJECT:
R.E. Ginna Nuclear Power Plant Docket No. 50-244 Fitness for Duty Program Performance Data Report In accordance with the requirements set forth in 10 CFR 26.71(d), R.E. Ginna Nuclear Power Plant, LLC has compiled and is submitting the enclosed semi-annual Fitness for Duty (FFD) Program Performance Data Report covering the period January 1, 2007 through June 30, 2007 Very truly yours, Enclosure cc: S. J. Collins, NRC D. V. Pickett, NRC Resident Inspector, NRC 0A
FRtness for Duty Program Performance Data Personnel Subject to 10 CFR Part 26 C?.,;
ONSTELLATION ENERGY GROUP0:5 06/30/2007
-Coma 6 Mthds Ending4 I:.R.'E._GinnaNuclear PoWer Plant Tamm-y"H. Henderson, Fitness fr, Duty Specialist" : (585) 771-5585 Contacit Na'me."Poe CUTOFFS: Screen/Confirmation (ng/ml) [X] Appendix A to 10 CFR Part 26 Marijuana 50/15 Amphetamines Cocaine Phencyclidine Opiates Alcohol (% BAC)
Annual (Jan-Dec) Random testing rates: Employees & Contractors by 50%.
Long-term Short-term Testing Results Licensee Employees Contractor Personnel* Contractor Personnel Average Number with 460 0 272 Unescorted Access Categories Tested Positive Tested Positive Tested Positive Pre-Access 2 0 0 0 118 0 For Cause Post-accident 1 0 0 0 0 0 Observed Behavior 2 0 0 0 1- 0 Random 131 0 0 0 76 0 Follow-up 11 0 0 0 11 0 Other 2** 0 0 0 1*... 0
'TOTAL ~ Z1,49 .i207*f,~
R.E. Ginna Nuclear Power Plant does not differentiate between long-term and short-term contractors. All contractors who have obtained unescorted access are considered short-term.
- 1 employee "other" was a recollection of a dilute random sample.
1 employee "other" was a test conducted at the request of the Medical Review Officer during an adjudication of the employee.
- As a contractor was being escorted to the testing facility for a test requested for observed behavior, the contractor informed his escort he chose to return home rather than have the drug and alcohol test conducted. The test was logged as a refusal, and the contractor's unescorted access was permanently denied.
Breakdown of Confirmed Positive Tests for Specific Substances Marijuana Cocaine Opiates Amphe- Phency- Alcohol Refusal Total tamines lidinetoesTta to test Licensee Employees 0 0 0 0 0 0 0 0 Long-Term Contractors* 0 0 0 0 0 0 0 0 Short-Term Contractors 0 0 0 0 0 1** 1 TAL. .. 0 O'0
.0 0 0 1. 1 Management Actions:
- R.E. Ginna Nuclear Power Plant does not differentiate between long-term and short-term contractors. All contractors who have obtained unescorted access are considered short-term.
- Per procedure, the contractor who refused to take a drug and alcohol test had his unescorted access permanently denied.
NRC Reportable Events (Per 10CFR Part 26.73)
There were no reportable events during this performance data period.