IR 05000269/2014002: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 80: | Line 80: | ||
{{a|1R01}} | {{a|1R01}} | ||
==1R01 Adverse Weather Protection | ==1R01 Adverse Weather Protection | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
Readiness for Extreme Seasonal Weather Conditions: The inspectors reviewed the licensees preparations for adverse weather associated with the cold ambient temperatures at the site. This included field walkdowns to assess the material condition and operation of freeze protection equipment, as well as other preparations made to protect plant equipment from freezing conditions. In addition, the inspectors reviewed the licensees procedures for preparing for cold weather and conducted interviews with personnel responsible for implementing the licensees cold weather protection program to assess the licensees ability to identify and resolve deficient conditions associated with cold weather protection equipment prior to cold weather events. Documents reviewed are listed in the Attachment. | Readiness for Extreme Seasonal Weather Conditions: The inspectors reviewed the licensees preparations for adverse weather associated with the cold ambient temperatures at the site. This included field walkdowns to assess the material condition and operation of freeze protection equipment, as well as other preparations made to protect plant equipment from freezing conditions. In addition, the inspectors reviewed the licensees procedures for preparing for cold weather and conducted interviews with personnel responsible for implementing the licensees cold weather protection program to assess the licensees ability to identify and resolve deficient conditions associated with cold weather protection equipment prior to cold weather events. Documents reviewed are listed in the Attachment. | ||
| Line 91: | Line 92: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R04}} | {{a|1R04}} | ||
==1R04 Equipment Alignment | ==1R04 Equipment Alignment | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
Partial Walkdown: The inspectors performed the three partial walkdowns listed below to assess the operability of redundant or diverse trains and components when safety-related equipment was inoperable or out-of-service and to identify any discrepancies that could impact the function of the system potentially increasing overall risk. The inspectors reviewed applicable operating procedures and walked down system components, selected breakers, valves, and support equipment to determine if they were correctly aligned to support system operation. The inspectors reviewed protected equipment sheets, maintenance plans, and system drawings to determine if the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program (CAP). Documents reviewed are listed in the | Partial Walkdown: The inspectors performed the three partial walkdowns listed below to assess the operability of redundant or diverse trains and components when safety-related equipment was inoperable or out-of-service and to identify any discrepancies that could impact the function of the system potentially increasing overall risk. The inspectors reviewed applicable operating procedures and walked down system components, selected breakers, valves, and support equipment to determine if they were correctly aligned to support system operation. The inspectors reviewed protected equipment sheets, maintenance plans, and system drawings to determine if the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program (CAP). Documents reviewed are listed in the | ||
. | . | ||
| Line 103: | Line 105: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R05}} | {{a|1R05}} | ||
==1R05 Fire Protection | ==1R05 Fire Protection | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
Fire Area Tours: The inspectors walked down accessible portions of the four plant areas listed below to assess the licensees control of transient combustible material and ignition sources, fire detection and suppression capabilities, fire barriers, and any related compensatory measures. The inspectors observed the fire protection suppression and detection equipment to determine if any conditions or deficiencies existed which could impair the operability of that equipment. The inspectors selected the areas based on a review of the licensees safe shutdown analysis probabilistic risk assessment and sensitivity studies for fire-related core damage accident sequences. Documents reviewed are listed in the Attachment. | Fire Area Tours: The inspectors walked down accessible portions of the four plant areas listed below to assess the licensees control of transient combustible material and ignition sources, fire detection and suppression capabilities, fire barriers, and any related compensatory measures. The inspectors observed the fire protection suppression and detection equipment to determine if any conditions or deficiencies existed which could impair the operability of that equipment. The inspectors selected the areas based on a review of the licensees safe shutdown analysis probabilistic risk assessment and sensitivity studies for fire-related core damage accident sequences. Documents reviewed are listed in the Attachment. | ||
* Unit 2 main feedwater pump area (zone 15) | * Unit 2 main feedwater pump area (zone 15) | ||
| Line 115: | Line 118: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R07}} | {{a|1R07}} | ||
==1R07 Heat Sink Performance | ==1R07 Heat Sink Performance | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
Annual Review: The inspectors reviewed the licensees program for maintenance and testing of risk-important heat exchangers in the low pressure injection system including the testing and analysis program of the Unit 3 decay heat removal heat exchanger 3A. | Annual Review: The inspectors reviewed the licensees program for maintenance and testing of risk-important heat exchangers in the low pressure injection system including the testing and analysis program of the Unit 3 decay heat removal heat exchanger 3A. | ||
| Line 125: | Line 129: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R11}} | {{a|1R11}} | ||
==1R11 Licensed Operator Requalification | ==1R11 Licensed Operator Requalification | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
Routine Operator Requalification Review: On February 26, 2014, the inspectors observed one active simulator training session to assess the performance of licensed operators during the session. The scenario involved a failed component cooling pump, two dropped control rods, a steam generator tube rupture, and a loss of main feed water. | Routine Operator Requalification Review: On February 26, 2014, the inspectors observed one active simulator training session to assess the performance of licensed operators during the session. The scenario involved a failed component cooling pump, two dropped control rods, a steam generator tube rupture, and a loss of main feed water. | ||
| Line 144: | Line 149: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R12}} | {{a|1R12}} | ||
==1R12 Maintenance Effectiveness | ==1R12 Maintenance Effectiveness | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
The inspectors reviewed the licensees effectiveness in performing the following four corrective maintenance activities. These reviews included an assessment of the licensees practices pertaining to the identification, scoping, and handling of degraded equipment conditions, as well as common cause failure evaluations. For each activity selected, the inspectors performed a detailed review of the problem history and surrounding circumstances, evaluated the extent of condition reviews as required, and reviewed the generic implications of the equipment and/or work practice problem. For those structures, systems and components (SSCs) scoped in the Maintenance Rule per 10 CFR 50.65, the inspectors verified that reliability and unavailability were properly monitored and that 10 CFR 50.65 (a)(1) and (a)(2) classifications were justified in light of the reviewed degraded equipment condition. Documents reviewed are listed in the | The inspectors reviewed the licensees effectiveness in performing the following four corrective maintenance activities. These reviews included an assessment of the licensees practices pertaining to the identification, scoping, and handling of degraded equipment conditions, as well as common cause failure evaluations. For each activity selected, the inspectors performed a detailed review of the problem history and surrounding circumstances, evaluated the extent of condition reviews as required, and reviewed the generic implications of the equipment and/or work practice problem. For those structures, systems and components (SSCs) scoped in the Maintenance Rule per 10 CFR 50.65, the inspectors verified that reliability and unavailability were properly monitored and that 10 CFR 50.65 (a)(1) and (a)(2) classifications were justified in light of the reviewed degraded equipment condition. Documents reviewed are listed in the | ||
. | . | ||
| Line 157: | Line 163: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R13}} | {{a|1R13}} | ||
==1R13 Maintenance Risk Assessments and Emergent Work Control | ==1R13 Maintenance Risk Assessments and Emergent Work Control | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
The inspectors evaluated the following attributes for the five activities listed below: | The inspectors evaluated the following attributes for the five activities listed below: | ||
1) the completeness of the risk assessments performed before maintenance activities were conducted; 2) the management of risk; 3) that, upon identification of an unforeseen situation, necessary steps were taken to plan and control the resulting emergent work activities; and 4) that maintenance risk assessments and emergent work problems were adequately identified and resolved. Documents reviewed are listed in the Attachment. | 1) the completeness of the risk assessments performed before maintenance activities were conducted; 2) the management of risk; 3) that, upon identification of an unforeseen situation, necessary steps were taken to plan and control the resulting emergent work activities; and 4) that maintenance risk assessments and emergent work problems were adequately identified and resolved. Documents reviewed are listed in the Attachment. | ||
| Line 171: | Line 178: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R15}} | {{a|1R15}} | ||
==1R15 Operability Evaluations and Functionality Assessments | ==1R15 Operability Evaluations and Functionality Assessments | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
The inspectors reviewed the following seven operability evaluations or functionality assessments affecting risk significant systems to assess: 1) the technical adequacy of the evaluations; 2) whether continued system operability was warranted; 3) whether other existing degraded conditions were considered; 4) if compensatory measures were involved, whether the compensatory measures were in place, would work as intended, and were appropriately controlled; and 5) where continued operability was considered unjustified, the impact on Technical Specifications (TS) limiting condition for operations. | The inspectors reviewed the following seven operability evaluations or functionality assessments affecting risk significant systems to assess: 1) the technical adequacy of the evaluations; 2) whether continued system operability was warranted; 3) whether other existing degraded conditions were considered; 4) if compensatory measures were involved, whether the compensatory measures were in place, would work as intended, and were appropriately controlled; and 5) where continued operability was considered unjustified, the impact on Technical Specifications (TS) limiting condition for operations. | ||
| Line 188: | Line 196: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R17}} | {{a|1R17}} | ||
==1R17 Evaluation of Changes, Tests, or Experiments and Permanent Plant Modifications | ==1R17 Evaluation of Changes, Tests, or Experiments and Permanent Plant Modifications | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
Evaluations of Changes, Tests, and Experiments: The inspector reviewed screening for EC 91856, PSW Support Equipment Installation and Testing, Rev. 051, where the licensee had determined that a 10 CFR 50.59 evaluation was not necessary. The inspectors performed this review to determine if: | Evaluations of Changes, Tests, and Experiments: The inspector reviewed screening for EC 91856, PSW Support Equipment Installation and Testing, Rev. 051, where the licensee had determined that a 10 CFR 50.59 evaluation was not necessary. The inspectors performed this review to determine if: | ||
* the changes, tests, or experiments performed were evaluated in accordance with 10 CFR 50.59 and that sufficient documentation existed to confirm that a license amendment was not required; | * the changes, tests, or experiments performed were evaluated in accordance with 10 CFR 50.59 and that sufficient documentation existed to confirm that a license amendment was not required; | ||
| Line 206: | Line 216: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R18}} | {{a|1R18}} | ||
==1R18 Plant Modifications | ==1R18 Plant Modifications | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
The inspectors reviewed the following plant modification to verify the adequacy of the modification package and the 10 CFR 50.59 screenings and to evaluate the modification for adverse effects on system availability, reliability, and functional capability. | The inspectors reviewed the following plant modification to verify the adequacy of the modification package and the 10 CFR 50.59 screenings and to evaluate the modification for adverse effects on system availability, reliability, and functional capability. | ||
| Line 219: | Line 230: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R19}} | {{a|1R19}} | ||
==1R19 Post-Maintenance Testing | ==1R19 Post-Maintenance Testing | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
The inspectors reviewed the following five post-maintenance test procedures and/or test activities to assess if: 1) the effect of testing on the plant had been adequately addressed by control room and/or engineering personnel; 2) testing was adequate for the maintenance performed; 3) acceptance criteria were clear and demonstrated operational readiness consistent with design and licensing basis documents; 4) test instrumentation had current calibrations, range, and accuracy consistent with the application; 5) tests were performed as written with applicable prerequisites satisfied; 6) jumpers installed or leads lifted were properly controlled; 7) test equipment was removed following testing; and 8) equipment was returned to the status required to perform its safety function. Documents reviewed are listed in the Attachment. | The inspectors reviewed the following five post-maintenance test procedures and/or test activities to assess if: 1) the effect of testing on the plant had been adequately addressed by control room and/or engineering personnel; 2) testing was adequate for the maintenance performed; 3) acceptance criteria were clear and demonstrated operational readiness consistent with design and licensing basis documents; 4) test instrumentation had current calibrations, range, and accuracy consistent with the application; 5) tests were performed as written with applicable prerequisites satisfied; 6) jumpers installed or leads lifted were properly controlled; 7) test equipment was removed following testing; and 8) equipment was returned to the status required to perform its safety function. Documents reviewed are listed in the Attachment. | ||
* IP/0/A/0203/001 E, Low Pressure Injection System RB Emergency Sump Pump Instrumentation Calibration following replacement of 3B LPI emergency sump pump instrumentation | * IP/0/A/0203/001 E, Low Pressure Injection System RB Emergency Sump Pump Instrumentation Calibration following replacement of 3B LPI emergency sump pump instrumentation | ||
| Line 232: | Line 244: | ||
No findings were identified. | No findings were identified. | ||
{{a|1R22}} | {{a|1R22}} | ||
==1R22 Surveillance Testing | ==1R22 Surveillance Testing | ||
====a. Inspection Scope==== | ====a. Inspection Scope==== | ||
== | |||
The inspectors either witnessed and/or reviewed test data for the five surveillance tests listed below to assess if the SSCs met TS, Updated Final Safety Analysis Report (UFSAR), and licensee procedure requirements. In addition, the inspectors determined if the testing effectively demonstrated that the SSCs were ready and capable of performing their intended safety functions. Documents reviewed are listed in the | The inspectors either witnessed and/or reviewed test data for the five surveillance tests listed below to assess if the SSCs met TS, Updated Final Safety Analysis Report (UFSAR), and licensee procedure requirements. In addition, the inspectors determined if the testing effectively demonstrated that the SSCs were ready and capable of performing their intended safety functions. Documents reviewed are listed in the | ||
. | . | ||
Revision as of 05:43, 17 November 2019
| ML14132A203 | |
| Person / Time | |
|---|---|
| Site: | Oconee |
| Issue date: | 05/12/2014 |
| From: | Gerald Mccoy NRC/RGN-II/DRP/RPB1 |
| To: | Batson S Duke Energy Carolinas |
| References | |
| IR-14-002 | |
| Download: ML14132A203 (27) | |
Text
UNITED STATES May 12, 2014
SUBJECT:
OCONEE NUCLEAR STATION - NRC INTEGRATED INSPECTION REPORT 05000269/2014002, 05000270/2014002, 05000287/2014002
Dear Mr. Batson:
On March 31, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Oconee Nuclear Station Units 1, 2, and 3. On April 10, 2014, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The inspectors documented the inspection results in the enclosed inspection report.
The enclosed inspection report discusses a finding for which the NRC has not yet reached a preliminary significance determination. As described in Section 4OA3 of the enclosed report, the procedure for performing ultrasonic examinations of piping welds did not contain the necessary steps to achieve acceptable coverage when limitations were encountered. This prevented the detection of a crack that subsequently resulted reactor coolant system pressure boundary leakage and a forced shutdown of Unit 1. The finding did not present an immediate safety concern because the leakage has been repaired. The NRC will inform you in a separate correspondence when the preliminary significance has been determined. This finding is also an apparent violation of NRC requirements and is being considered for escalated enforcement action in accordance with the Enforcement Policy. However, because the NRC has not made a final determination in this matter, no notice of violation is being issued for this inspection finding at this time.
We intend to complete and issue our final safety significance determination within 90 days from the date of this letter. The NRCs significance determination process (SDP) is designed to encourage an open dialogue between your staff and the NRC; however, the dialogue should not affect the timeliness of our final determination. Additionally, as we informed you in the fourth quarter 2013 integrated inspection report, cross-cutting aspects identified in the last six months of 2013 using the previous terminology were being converted in accordance with the cross-reference in Inspection Manual Chapter 0310.
Section 4OA5 of the enclosed report documents the conversion of these cross-cutting aspects which will be evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305 starting with the 2014 mid-cycle assessment review. If you disagree with the cross cutting aspect reassignment, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region II, and the NRC Resident Inspector at the Oconee Nuclear Station.
In accordance with 10 Code of Federal Regulations 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Gerald McCoy, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos.: 50-269, 50-270, 50-287 License Nos.: DPR-38, DPR-47, DPR-55
Enclosure:
NRC Integrated Inspection Report 05000269/2014002, 05000270/2014002, 05000287/2014002 w/Attachment: Supplementary Information
REGION II==
Docket Nos: 50-269, 50-270, 50-287 License Nos: DPR-38, DPR-47, DPR-55 Report Nos: 05000269/2014002, 05000270/2014002, 05000287/2014002 Licensee: Duke Energy Carolinas, LLC Facility: Oconee Nuclear Station, Units 1, 2 and 3 Location: Seneca, SC 29672 Dates: January 1, 2014, through March 31, 2014 Inspectors: E. Crowe, Senior Resident Inspector G. Croon, Resident Inspector N. Childs, Resident Inspector J. Dymek, Reactor Inspector (Section 1R17)
M. Riley, Reactor Inspector (Section 1R17)
R. Williams, Reactor Inspector (Section 4OA3)
D. Bollock, Reactor Operations Engineer (Section 4OA5)
J. Jacobson, Senior Reactor Operations Engineer (Section 4OA5)
B. Clarke, Reactor Operations Engineer (Section 4OA5)
R. Cureton, Resident Inspector - Catawba Nuclear Station (Section 4OA5)
Approved by: Gerald McCoy, Chief Reactor Projects Branch 1 Division of Reactor Projects Enclosure
SUMMARY OF FINDINGS
IR 05000269/2014-002, 05000270/2014-002, 05000287/2014-002; 01/01/2014 - 03/31/2014;
Oconee Nuclear Station Units 1, 2 and 3; Follow-up of Events and Notices of Enforcement Discretion (NOED)
The report covered a three-month period of inspection by the Oconee resident inspectors, two Region-based inspectors, three Headquarters-based inspectors, and one Catawba resident inspector. One Apparent Violation was identified. The significance of inspection findings are indicated by their color (i.e., greater than Green, or Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP) dated June 2, 2011.
Cross-cutting aspects are determined using IMC 0310, Aspects Within Cross-Cutting Areas dated December 19, 2013. All violations of NRC requirements are dispositioned in accordance with the NRCs Enforcement Policy dated July 9, 2013. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 5.
Cornerstone: Initiating Events
- TBD. A NRC-identified potentially Greater than Green Apparent Violation (AV) of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, was identified when the licensee failed to ensure that procedure NDE-995, Ultrasonic Examination of Small Diameter Piping Butt Welds and Base Material for Thermal Fatigue Damage, was adequate to achieve acceptable coverage for the ultrasonic (UT) examination of weld 1-RC-201-205. NDE-995 did not contain the necessary steps to achieve acceptable coverage for UT examinations when limitations were encountered. The licensee entered this finding into their corrective action program as PIP O-13-13168.
The failure to ensure that station procedure NDE-995 was adequate to achieve acceptable coverage for the UT examination of weld 1-RC-201-205 was more than minor because it affected the Design Control attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective in that an undetected crack resulted in reactor coolant system pressure boundary leakage and a forced shutdown of Unit 1. The inspectors determined that detailed risk analysis was required. There was no immediate safety concern because the crack was repaired. The inspectors determined this finding has a cross-cutting aspect of H.7 in the Documentation component of the Human Performance area because the licensee did not create and maintain complete, accurate, and up-to-date documentation in procedure NDE-995 to ensure acceptable coverage for UT examinations.
(Section 4OA3)
REPORT DETAILS
Summary of Plant Status
Unit 1 operated at approximately 100 percent rated thermal power (RTP) for the inspection period.
Unit 2 operated at approximately 100 percent RTP for the inspection period.
Unit 3 operated at approximately 100 percent RTP for the inspection period.
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity
==1R01 Adverse Weather Protection
a. Inspection Scope
==
Readiness for Extreme Seasonal Weather Conditions: The inspectors reviewed the licensees preparations for adverse weather associated with the cold ambient temperatures at the site. This included field walkdowns to assess the material condition and operation of freeze protection equipment, as well as other preparations made to protect plant equipment from freezing conditions. In addition, the inspectors reviewed the licensees procedures for preparing for cold weather and conducted interviews with personnel responsible for implementing the licensees cold weather protection program to assess the licensees ability to identify and resolve deficient conditions associated with cold weather protection equipment prior to cold weather events. Documents reviewed are listed in the Attachment.
Impending Adverse Weather Conditions: The inspectors evaluated implementation of adverse weather preparation procedures and compensatory measures for the following adverse weather condition. The inspectors walked-down portions of the emergency feedwater systems, safe shutdown facility, low pressure service water, and portions of the auxiliary building. These systems and areas were selected because their safety-related functions could be affected by freezing weather.
- Projected freezing temperatures for February 11 - 12, 2014 External Flooding: The inspectors reviewed the licensees compensatory measures identified in CAL 2-10-003, Confirmatory Action Letter - Oconee Nuclear Station Units 1, 2, and 3 Commitments to Address External Flooding Concerns to ensure the measures were available and properly maintained. This review included field walkdowns of temporary equipment to assess its material condition and operability. In addition, the inspectors reviewed the licensees procedures for external flood mitigation and conducted interviews with personnel responsible for implementing the licensees program to assess the licensees ability to respond to potential events.
b. Findings
No findings were identified.
==1R04 Equipment Alignment
a. Inspection Scope
==
Partial Walkdown: The inspectors performed the three partial walkdowns listed below to assess the operability of redundant or diverse trains and components when safety-related equipment was inoperable or out-of-service and to identify any discrepancies that could impact the function of the system potentially increasing overall risk. The inspectors reviewed applicable operating procedures and walked down system components, selected breakers, valves, and support equipment to determine if they were correctly aligned to support system operation. The inspectors reviewed protected equipment sheets, maintenance plans, and system drawings to determine if the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program (CAP). Documents reviewed are listed in the
.
- Keowee Underground Path during KHU-2 Pole Outage
- 4160 volt Electrical Bus SL-1 Alignment during KHU Dual Unit Outage
- Lee Combustion Turbine Alignment during KHU-2 Pole Outage
b. Findings
No findings were identified.
==1R05 Fire Protection
a. Inspection Scope
==
Fire Area Tours: The inspectors walked down accessible portions of the four plant areas listed below to assess the licensees control of transient combustible material and ignition sources, fire detection and suppression capabilities, fire barriers, and any related compensatory measures. The inspectors observed the fire protection suppression and detection equipment to determine if any conditions or deficiencies existed which could impair the operability of that equipment. The inspectors selected the areas based on a review of the licensees safe shutdown analysis probabilistic risk assessment and sensitivity studies for fire-related core damage accident sequences. Documents reviewed are listed in the Attachment.
- Unit 2 main feedwater pump area (zone 15)
- Unit 2 pipe room (Zone 66)
- Unit 3 6900/4160V switchgear area (zone 29)
- Unit 3 tank room (Zone 58)
b. Findings
No findings were identified.
==1R07 Heat Sink Performance
a. Inspection Scope
==
Annual Review: The inspectors reviewed the licensees program for maintenance and testing of risk-important heat exchangers in the low pressure injection system including the testing and analysis program of the Unit 3 decay heat removal heat exchanger 3A.
The inspectors review was to verify that the frequency of inspection was sufficient to detect degradation prior to loss of heat removal capability below design requirements; that the inspection results were appropriately categories against pre-established engineering acceptance criteria.
b. Findings
No findings were identified.
==1R11 Licensed Operator Requalification
a. Inspection Scope
==
Routine Operator Requalification Review: On February 26, 2014, the inspectors observed one active simulator training session to assess the performance of licensed operators during the session. The scenario involved a failed component cooling pump, two dropped control rods, a steam generator tube rupture, and a loss of main feed water.
Events progressed to a point where the crew entered an Unusual Event emergency declaration. The post-scenario critique conducted by the training instructor and the crew was also observed. Documents reviewed are listed in the Attachment.
Observation of Operator Performance: The inspectors observed operator performance in the main control room on March 6, 2014, during critical evolution to bleed and feed the 3B Bleed Hold-up Tank for reactivity control on Unit 1. Additionally on March 18, 2014, the inspectors observed operator performance in the main control room during elevated risk conditions from the SSF being out of service as well as PSW power being unavailable from the Fant line. Inspectors observed licensed operator performance to assess the following:
- Use of plant procedures
- Control board manipulations
- Communications between crew members
- Use and interpretation of instruments, indications, and alarms
- Use of human error prevention techniques
- Documentation of activities
- Management and supervision
b. Findings
No findings were identified.
==1R12 Maintenance Effectiveness
a. Inspection Scope
==
The inspectors reviewed the licensees effectiveness in performing the following four corrective maintenance activities. These reviews included an assessment of the licensees practices pertaining to the identification, scoping, and handling of degraded equipment conditions, as well as common cause failure evaluations. For each activity selected, the inspectors performed a detailed review of the problem history and surrounding circumstances, evaluated the extent of condition reviews as required, and reviewed the generic implications of the equipment and/or work practice problem. For those structures, systems and components (SSCs) scoped in the Maintenance Rule per 10 CFR 50.65, the inspectors verified that reliability and unavailability were properly monitored and that 10 CFR 50.65 (a)(1) and (a)(2) classifications were justified in light of the reviewed degraded equipment condition. Documents reviewed are listed in the
.
- PIP-O-14-00544, Switchyard battery SY-2 cell 30 discovered with low voltage of 2.06 vDC
- PIP-O-14-00755, Operations request for engineering evaluation of HPI motor oil additions
b. Findings
No findings were identified.
==1R13 Maintenance Risk Assessments and Emergent Work Control
a. Inspection Scope
==
The inspectors evaluated the following attributes for the five activities listed below:
1) the completeness of the risk assessments performed before maintenance activities were conducted; 2) the management of risk; 3) that, upon identification of an unforeseen situation, necessary steps were taken to plan and control the resulting emergent work activities; and 4) that maintenance risk assessments and emergent work problems were adequately identified and resolved. Documents reviewed are listed in the Attachment.
- Orange risk condition during KHU-1 and KHU-2 dual outage due to dewatered condition
- Orange risk condition during monthly SSF surveillance in parallel with KHU-2 pole replacement outage
- Yellow risk condition during 3A LPI DHR Cooler Eddy Current Testing
- Risk associated with maintenance on Keowee Hydro DC bus 2DA during the Keowee Unit 2 rotor pole outage
- Yellow risk condition with potential to have been an orange risk condition due to ASW maintenance during monthly SSF surveillance
b. Findings
No findings were identified.
==1R15 Operability Evaluations and Functionality Assessments
a. Inspection Scope
==
The inspectors reviewed the following seven operability evaluations or functionality assessments affecting risk significant systems to assess: 1) the technical adequacy of the evaluations; 2) whether continued system operability was warranted; 3) whether other existing degraded conditions were considered; 4) if compensatory measures were involved, whether the compensatory measures were in place, would work as intended, and were appropriately controlled; and 5) where continued operability was considered unjustified, the impact on Technical Specifications (TS) limiting condition for operations.
Operating Experience Smart Sample (OpESS) 2012/02, Technical Specification Interpretation and Operability Determination was used by the inspectors during the review.
- PIP-O-13-13443, Unit 2 containment tendons discovered below minimum lift off requirements
- PIP-O-13-13685, 2HP 4 was found in an overthrust condition during Viper testing
- PIP-O-14-00470, 230KV switchyard battery SY-1 cell 38 below minimum TS voltage of 2.13vDC
- PIP-O-14-00447, 230KV switchyard 125VDC breakers oversized
- PIP-O-14-00746, Unit 3B2 RCP lower seal cavity pressure behaving erratically
- PIP-O-14-03093, Air Leaks on ACB-3 at Keowee exceed acceptable criteria
b. Findings
No findings were identified.
==1R17 Evaluation of Changes, Tests, or Experiments and Permanent Plant Modifications
a. Inspection Scope
==
Evaluations of Changes, Tests, and Experiments: The inspector reviewed screening for EC 91856, PSW Support Equipment Installation and Testing, Rev. 051, where the licensee had determined that a 10 CFR 50.59 evaluation was not necessary. The inspectors performed this review to determine if:
- the changes, tests, or experiments performed were evaluated in accordance with 10 CFR 50.59 and that sufficient documentation existed to confirm that a license amendment was not required;
- the safety issues requiring the changes, tests, or experiments were resolved;
- the licensee conclusions for evaluations of changes, tests, or experiments were correct and consistent with 10 CFR 50.59; and
- the design and licensing basis documentation used to support the change was updated to reflect the change.
The inspector used, in part, Nuclear Energy Institute (NEI) 96-07, Guidelines for 10 CFR 50.59 Implementation, Revision 1, to determine acceptability of the completed screenings. The NEI document was endorsed by the NRC in Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments, dated November 2000. Documents reviewed are listed in the Attachment.
Permanent Plant Modifications: The inspector reviewed licensee activities associated with the following permanent plant modification.
Tornado and High Energy Line Break (HELB) Project Modification - Protected Service Water (PSW) Building Equipment Installation - The inspector reviewed EC 91856 - PSW Support Equipment Installation and Testing, to verify equipment installed in the PSW building was afforded appropriate fire detection and protection capabilities. The inspector reviewed the completed acceptance testing procedures and work orders for fire suppression hose stations and heat and smoke fire detection systems. The inspector conducted direct observations of this equipment to verify that the location and installation conformed to design specifications and installation drawings and was capable of performing the intended functions of detection and suppression of fires occurring within the PSW Building. Documents reviewed are listed in the Attachment.
b. Findings
No findings were identified.
==1R18 Plant Modifications
a. Inspection Scope
==
The inspectors reviewed the following plant modification to verify the adequacy of the modification package and the 10 CFR 50.59 screenings and to evaluate the modification for adverse effects on system availability, reliability, and functional capability.
Documents reviewed are listed in the Attachment.
Temporary Plant Modifications
- EC 102446; Unit 2 Temporary NI Modification to Support ES/RPS Project Install
b. Findings
No findings were identified.
==1R19 Post-Maintenance Testing
a. Inspection Scope
==
The inspectors reviewed the following five post-maintenance test procedures and/or test activities to assess if: 1) the effect of testing on the plant had been adequately addressed by control room and/or engineering personnel; 2) testing was adequate for the maintenance performed; 3) acceptance criteria were clear and demonstrated operational readiness consistent with design and licensing basis documents; 4) test instrumentation had current calibrations, range, and accuracy consistent with the application; 5) tests were performed as written with applicable prerequisites satisfied; 6) jumpers installed or leads lifted were properly controlled; 7) test equipment was removed following testing; and 8) equipment was returned to the status required to perform its safety function. Documents reviewed are listed in the Attachment.
- IP/0/A/0203/001 E, Low Pressure Injection System RB Emergency Sump Pump Instrumentation Calibration following replacement of 3B LPI emergency sump pump instrumentation
- PT/3/A/0204/007, Reactor Building Spray Pump Test following periodic maintenance
- PT/0/A/0610/024, Keowee Emergency Start for Troubleshooting and Post Maintenance Checkouts, after Keowee Unit 2 pole replacement outage
- IP/3/A/4980/050 A, 3B Motor Driven Emergency Feedwater Pump breaker and relay test following periodic maintenance and inspection of 3TE-0 breakers.
- PT/3/A/0600/013 B, Post Maintenance test of 3B Motor Driven Emergency Feedwater Pump following periodic maintenance
b. Findings
No findings were identified.
==1R22 Surveillance Testing
a. Inspection Scope
==
The inspectors either witnessed and/or reviewed test data for the five surveillance tests listed below to assess if the SSCs met TS, Updated Final Safety Analysis Report (UFSAR), and licensee procedure requirements. In addition, the inspectors determined if the testing effectively demonstrated that the SSCs were ready and capable of performing their intended safety functions. Documents reviewed are listed in the
.
Routine Surveillances
- PT/0/A/0600/021, Standby Shutdown Facility Diesel-Generator Operation, monthly surveillance
- PT/1/A/026/010, 1C ESV Pump Test (Train A)
- PT/3/A/0251/003, Concentrated Boric Acid Storage Tank Pump Test - Periodic testing of 3A CBAST pump In-Service Tests
- PT/1/A/0203/006 A, Low Pressure Injection Pump Test - Recirculation for periodic testing of 1A LPI pump
- PT/2/A/0203/006 A, Low Pressure Injection Pump Test - Recirculation for periodic testing of 2A LPI pump
b. Findings
No findings were identified.
Cornerstone: Emergency Preparedness
1EP6 Drill Evaluation
a. Inspection Scope
The inspectors evaluated the licensees performance in the Technical Support Center on February 11, 2014. The drill involved a steam generator tube leak and reactor coolant pump seal failures. The NRC assessment focused on the timeliness and location of classification, offsite agency notification, and the licensees expectations of response.
The performance of emergency response organization was evaluated against applicable licensee procedures and regulatory requirements. The inspectors attended the post-exercise critique for the drill to evaluate the licensees self-assessment process for identifying potential deficiencies relating to failures in classification and notification.
Documents reviewed are listed in the Attachment.
b. Findings
No findings were identified.
OTHER ACTIVITIES
4OA1 Performance Indicator (PI) Verification
a. Inspection Scope
The inspectors sampled licensee data to confirm the accuracy of reported PI data for the following nine PIs. To determine the accuracy of the report PI elements, the reviewed data was assessed against PI definitions and guidance contained in Nuclear Energy Institute 99-02, Regulatory Assessment Indicator Guideline, Revision 6. Documents reviewed are listed in the Attachment.
Cornerstone: Initiating Events
- Unplanned Trips (3 units)
- Unplanned Trips w/ complications (3 units)
- Unplanned Power Changes (3 units)
For the period of April 1, 2013, through March 31, 2014, the inspectors reviewed Operating Logs, Train Unavailability Data, Maintenance Records, Maintenance Rule Data, PIPs, Consolidated Derivation Entry Reports, and System Health Reports to verify the accuracy of the PI data reported for each PI.
b. Findings
No findings were identified.
4OA2 Problem Identification and Resolution
Daily Screening of Corrective Action Reports: In accordance with Inspection Procedure (IP) 71152, Identification and Resolution of Problems, and in order to help identify repetitive equipment failures or specific human performance issues for follow-up, the inspectors performed daily screening of items entered into the licensees CAP. This review was accomplished by reviewing copies of PIPs, attending daily screening meetings, and accessing the licensees computerized database.
4OA3 Follow-up of Events and Notices of Enforcement Discretion (NOED)
.1 (Closed) LER 05000287/2013-001, Unit 3 Manual Reactor Trip due to Main Feedwater
Oscillations On October 24, 2013, with Unit 3 operating at 100 percent RTP (Mode 1), control room operators observed main feedwater flow indicators oscillating outside of normal parameters. Control room operators attempted to stabilize feedwater flow by taking manual control of the integrated control system (ICS). When it was recognized that feedwater flow would not stabilize, the control room supervisor made the decision to manually trip the Unit 3 reactor. The flow oscillations were caused by actuator O-ring failure resulting in air leakage past the upper and lower bushings of the Unit 3 train A main feedwater control valve (3FDW-32) actuator. The licensee determined the root cause of the event to be premature failure of the actuator o-rings due to piston shaft misalignment and insufficient preventive maintenance activities. The inspectors verified the accuracy of the LER, the appropriateness of completed and planned corrective actions, and reviewed the licensees root cause evaluation. The licensee entered this issue into their CAP as PIP O-13-11963. No findings were identified.
.2 (Closed) LER 05000269/2013-04, High Cycle Fatigue Resulted in Reactor Coolant Leak
and Unit Shutdown On November 11, 2013, the licensee determined that a leak in the 1B2 high pressure injection line was pressure boundary leakage. Unit 1 was subsequently shutdown as required by TS 3.4.13. The residents monitored the orderly shutdown of Unit 1. The resident inspectors and a regional inspector monitored the licensees repair activities.
The NRC inspectors also evaluated the licensees extent of condition review and activities associated with additional non-destructive evaluations performed on other Unit 1 high pressure injection nozzles. Unit 2 was shutdown for a refueling outage at the time of this event; therefore, the high pressure injection nozzles of this unit were accessible for non-destructive evaluations which were also reviewed by NRC inspectors. The inspectors verified the accuracy of the LER, the appropriateness of completed and planned corrective actions, and reviewed the licensees root cause evaluation. The licensee entered this issue into their corrective action program as PIP O-13-13168.
b. Findings
Introduction:
A NRC-identified potentially Greater than Green AV of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, was identified when the licensee failed to ensure that procedure NDE-995, Ultrasonic Examination of Small Diameter Piping Butt Welds and Base Material for Thermal Fatigue Damage, was adequate to achieve acceptable coverage for the ultrasonic (UT) examination of weld 1-RC-201-205. NDE-995 did not contain the necessary steps to achieve acceptable coverage for UT examinations when limitations were encountered.
Description:
In 2004, the licensee issued procedure NDE-995, This procedure limited the number and type of UT probes permitted for use (i.e. eliminated the potential to use a 70° angle probe) and omitted earlier guidance on how to address limitations encountered during the examination which result in the required examination coverage not being achieved. As a result, numerous examinations performed on HPI safe end-to-piping welds using procedure NDE-995 did not completely cover the affected area and the less than adequate coverage was not assessed.
On November 11, 2013, the licensee investigated increased unidentified leakage and discovered a circumferential crack in weld 1-RC-201-105 located on the Unit 1 HPI nozzle to cold leg interface of the 1B2 reactor coolant pump suction pipe. The crack ran along the pipe side edge of the weld root from approximately 0° to 65° (~1.2 inches in length). The licensee reviewed the results of the previous UT examination performed in 2012 using procedure NDE-995 and found no reportable indications. However, in 2011, the licensee performed a radiographic examination specifically to check the condition and position of the 1B2 thermal sleeve. The focus of the review was limited to that area; however, the safe end area containing weld 1-RC-201-105 was incidentally visible on the film. Following the current event, the licensee re-reviewed the 2011 radiographic film and a crack-like indication was identified in the side wall image of the weld at approximately the same location as corresponding to the current crack location. From the re-review of the film, this crack-like indication appeared to be approximately 50 percent through-wall.
Following the identification of the 1B2 through-wall crack, the licensee performed an extent of condition using phased-array UT on the eight HPI safe end-to-pipe welds in Unit 1 and Unit 2 (Unit 3 was still operating at the time so the inspections were not performed). The inspections showed additional recordable indications on nozzles 1B1, 2A2 and 2B2. All of these indications were analyzed and found to be acceptable for continued service.
Analysis:
The inspectors determined that the failure to ensure that station procedure NDE-995 was adequate to achieve acceptable coverage for the ultrasonic (UT)examination of weld 1-RC-201-205 was a performance deficiency. Procedure NDE-995 did not contain necessary steps to achieve acceptable examination coverage when limitations were encountered nor did it contain guidance on actions to take when acceptable examination coverage was unattainable. The inspectors determined that the finding was more than minor because it affected the Design Control attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective in that an undetected crack resulted in reactor coolant system pressure boundary leakage and a forced shutdown of Unit 1. Using the Inspection Manual Chapter 0609, Significance Determination Process, Phase 1 Worksheet, dated 6/19/2012, the finding was determined to require a detailed risk analysis because the finding could result in a leak which exceeded the RCS leak rate for a small-break LOCA. There was no immediate safety concern because the crack was repaired. The inspectors determined this finding has a cross-cutting aspect of H.7 in the Documentation component of the Human Performance area because the licensee did not create and maintain complete, accurate, and up-to-date documentation in procedure NDE-995 to ensure acceptable coverage for UT examinations.
Enforcement:
No enforcement is being issued at this time because the NRC has not made a final safety significance determination. Because the finding is potentially Greater than Green, the associated violation is being treated as an AV consistent with the NRC Enforcement Policy and is identified as AV 05000269/2014002-01: Inadequate Procedure to Ensure Adequate Piping Weld Inspections.
4OA5 Other Activities
.1 Review of Commercial Grade Dedication Process
a. Inspection Scope
The NRC inspectors reviewed Oconees program for commercial-grade dedication (CGD) of items used in safety-related applications to determine if the established controls were in compliance with the regulatory requirements of Criterion III, Design Control, of Appendix B to 10 CFR Part 50 and 10 CFR Part 21. The NRC inspection team used IP 43004, Inspection of Commercial-Grade Dedication Programs, to assess the licensees program. This assessment included a review of the procedures governing the implementation of CGD activities, interviews with Oconee personnel, a review of related documentation, and inspection of installed items. In addition, the inspectors reviewed a sample of inputs to the Oconee CGD plans such as: 1) licensee Purchase Orders (PO), 2) engineering analysis of safety function, 3) development of critical characteristics, and 4) test or methods of acceptance. The inspectors also reviewed corrective action documents related to the CGD activities and internal audits of the quality assurance and procurement activities. The inspected commercial-grade dedication packages included:
- General purpose Potter and Brumfield relays (CGD-3009.01-01-0001 and CGPA-3000.00-00-0130)
- Acopian Power Supplies (CGD-3011.09.002)
- Brown and Sharpe pumps and replacement parts (CGPA-2000.00-00-0009)
- OSECO Rupture Disks (CGD-1026.00-00-0002)
- Three different bulk oils (CGD-2012.02-02-0007)
The inspection team also verified that Oconee provided adequate oversight of third party dedicating entities by reviewing the dedication documentation and correspondence with the third party dedicating entities. The inspection team reviewed oversight of the following Third Party dedications.
- Low and medium voltage switchgear and components from AZZ/NLI (VR-29411642-9 and VP-29411642-17)
- Protected Service Water (PSW) building dampers from Scientech (EGS-DP-927701-289 and EGS-TR-927701-302)
b. Findings and Observations
No findings were identified. The inspectors observed that the licensee performed an in-depth audit of their procurement and CGD programs prior to the NRC inspection. The licensee identified weaknesses in their CGD packages noting approximately 75 percent did not contain documentation to show they meet the requirements of 10 CFR Part 21 and 10 CFR Part 50 Appendix B. However, they were able to provide documentation showing reasonable assurance that the components in question could perform their intended safety function in each of the noted weaknesses. The licensee was conducting an Apparent Cause Evaluation and, over the next three years, a review of all CGD packages to correct the packages. The NRC inspection team identified additional examples consistent with the Oconee audit findings; however, the correct actions stemming from the audit were adequate to address these examples.
.2 Reassignment of Cross Cutting Aspects
The table below provides a cross-reference from the 2013 and earlier findings and associated cross-cutting aspects to the new cross-cutting aspects resulting from the common language initiative. These aspects and any others identified since January 2014, will be evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305 starting with the 2014 mid-cycle assessment review.
Inspection Report Old Cross-Cutting Aspect New Cross-Cutting Aspect 2013004 H.4(c) H.2 2013004 H.1(b) H.13 2013005 H.2(c) H.7 2013007 H.4(b) H.8
4OA6 Management Meetings (Including Exit Meeting)
On April 10, 2014, the resident inspectors presented the inspection results to Mr. Scott Batson and other members of licensee management. The inspectors verified that no proprietary information was retained by the inspectors or documented in this report.
ATTACHMENT:
SUPPLEMENTARY INFORMATION
KEY POINTS OF CONTACT
Licensee
- S. Batson, Site Vice President
- S. Boggs, Emergency Services Coordinator
- E. Burchfield, Engineering Manager
- S. Burton, Keowee Hydro Station Plant Manager
T. Cheslak; Oconee Fire Protection Engineer
- G. Childs, Keowee Hydro Station Operations
P. Fisk; Superintendent of Operations
- R. Guy, Organization Effectiveness Manager
- M. McNeely, Security Manager
- A. Lotfi, Duke - Construction
- T. Patterson, Safety Assurance Manager
- T. Ray, Station Manager
- F. Rickenbaker, OMP Manager
- D. Robinson, Radiation Protection Manager
- J. Smith, Regulatory Compliance
- P. Street, Emergency Planning Manager
- M. Swim, Fleet Regulatory Affairs Engineer
- J. Thomas, Manager, Fleet Procurement Engineering
- C. Wasik, Regulatory Compliance Manager
- J. Yankoglu, Electrical Procurement Engineering Manager
LIST OF REPORT ITEMS
Opened
- 05000269/2014002-01 Inadequate Procedure to Ensure Adequate Piping Weld Inspections (4OA3.2)
Closed
LER
- 05000287/2013-001-00 Unit 3 Manual Reactor Trip due to Main Feedwater Oscillations (4OA3.1)
LER
- 05000269/2013-004-00 High Cycle Fatigue Resulted in Reactor Coolant Leak and Unit Shutdown (4OA3.2)