{{#Wiki_filter:NFPA 805 Pilot License Amendment Request Review & Infrastructure Update December 4, 2008 SHEARON HARRIS (Harris) NFPA 805 License Amendment Request (LAR) REVIEW SCHEDULE (Progress Energy)
{{#Wiki_filter:NFPA 805 Pilot License Amendment Request Review
Date Available Information Harris LAR Submittal Letter from Progress Energy with Partial Enclosures 5/29/08 ML081560641 Remaining Harris LAR Enclosures 5/29/08 ML081840706 LAR Submission Ceremony 7/17/08 ML082060554 NRC LAR Acceptance Review Letter to Progress Energy 9/26/08 ML082701158 Public Meeting Summary: Clarification Call on Harris Supplement 9/29/08 ML082960153 Harris LAR Supplement (Part 1) due 11/08 ** Harris LAR Supplement (Part 2) due 12/08 Harris LAR Site Audit (tentative) 2/09* Issue LAR Request for Additional Information (RAI) to Progress Energy 3/09* Harris LAR RAI Responses due from Progress Energy 5/09* Harris Safety Evaluation Issued to Progress Energy 9/09*   OCONEE NFPA 805 LAR REVIEW SCHEDULE (Duke Energy)
                                                  & Infrastructure Update SHEARON HARRIS (Harris) NFPA 805 License Amendment Request                           Date      Available (LAR) REVIEW SCHEDULE (Progress Energy)                                                         Information Harris LAR Submittal Letter from Progress Energy with Partial Enclosures             5/29/08   ML081560641 Remaining Harris LAR Enclosures                                                       5/29/08   ML081840706 LAR Submission Ceremony                                                               7/17/08   ML082060554 NRC LAR Acceptance Review Letter to Progress Energy                                   9/26/08   ML082701158 Public Meeting Summary: Clarification Call on Harris Supplement                       9/29/08   ML082960153 Harris LAR Supplement (Part 1) due                                                   11/08     **
Date Available Information Oconee LAR Submittal Letter from Duke Energy with Partial Enclosure 5/30/08 ML081650475 Remaining Oconee LAR Enclosures 5/30/08 ML082041014 LAR Submission Ceremony 7/17/08 ML082060554 Oconee LAR Supplement due 10/31/08 ** NRC LAR Acceptance Review Letter to Duke Energy 12/08 Oconee LAR Site Visit (tentative) 2/09* Issue Oconee LAR RAIs to Duke Energy 3/09* Oconee LAR RAI Responses due from Duke Energy 5/09* LAR Safety Evaluation Issued to Duke Energy 9/09*   NFPA 805 INFRASTRUCTURE DEVELOPMENT SCHEDULE Date Available Information Received from the Nuclear Energy Institute (NEI) NEI 00-01, Revision 2 12/07 ML082050625 Received NEI 04-02, Revision 2 from NEI 4/08 ML081400332 Send NRC Comments on NEI 00-01, Rev 2 5/08 ML081640340 SRP 9.5.1.2, "Risk-Informed, Performance-Based Fire Protection"  Public Meeting Summary 10/08 ML082830934 NFPA 805 Regulatory Audit Plan Template Memo (internal memorandum; will be publicly available in ADAMS) 12/08  SRP 9.5.1.2 Published for Public Comment 1/09 Send NRC Comments on NEI 04-02, Rev 2 (unless covered in RG 1.205, Revision 1) 2/09  Publish Draft RG 1.205, Revision 1 for Public Comment 3/09 Publish RG 1.200, Revision 1 4/09
Harris LAR Supplement (Part 2) due                                                   12/08 Harris LAR Site Audit (tentative)                                                     2/09*
* These milestone dates are estimates based on a high-quality supplemental submittal. ** Waiting for a redacted version to publish in ADAMs.}}
Issue LAR Request for Additional Information (RAI) to Progress Energy                 3/09*
Harris LAR RAI Responses due from Progress Energy                                     5/09*
Harris Safety Evaluation Issued to Progress Energy                                   9/09*
OCONEE NFPA 805 LAR REVIEW SCHEDULE (Duke Energy)                                     Date     Available Information Oconee LAR Submittal Letter from Duke Energy with Partial Enclosure                   5/30/08   ML081650475 Remaining Oconee LAR Enclosures                                                       5/30/08   ML082041014 LAR Submission Ceremony                                                               7/17/08   ML082060554 Oconee LAR Supplement due                                                             10/31/08 **
NRC LAR Acceptance Review Letter to Duke Energy                                       12/08 Oconee LAR Site Visit (tentative)                                                     2/09*
Issue Oconee LAR RAIs to Duke Energy                                                 3/09*
Oconee LAR RAI Responses due from Duke Energy                                         5/09*
LAR Safety Evaluation Issued to Duke Energy                                           9/09*
NFPA 805 INFRASTRUCTURE DEVELOPMENT SCHEDULE                                         Date     Available Information Received from the Nuclear Energy Institute (NEI) NEI 00-01, Revision 2               12/07     ML082050625 Received NEI 04-02, Revision 2 from NEI                                               4/08     ML081400332 Send NRC Comments on NEI 00-01, Rev 2                                                 5/08     ML081640340 SRP 9.5.1.2, Risk-Informed, Performance-Based Fire Protection                       10/08     ML082830934 Public Meeting Summary NFPA 805 Regulatory Audit Plan Template Memo                                         12/08 (internal memorandum; will be publicly available in ADAMS)
SRP 9.5.1.2 Published for Public Comment                                             1/09 Send NRC Comments on NEI 04-02, Rev 2                                                 2/09 (unless covered in RG 1.205, Revision 1)
Publish Draft RG 1.205, Revision 1 for Public Comment                                 3/09 Publish RG 1.200, Revision 1                                                         4/09
* These milestone dates are estimates based on a high-quality supplemental submittal.
** Waiting for a redacted version to publish in ADAMs.
December 4, 2008}}

Revision as of 10:38, 14 November 2019

NFPA 805 Pilot License Amendment Request Review and Infrastructure Update
ML083400181
Person / Time
Site: Oconee, Harris  Duke Energy icon.png
Issue date: 12/04/2008
From:
NRC/NRR/DRA/AFPB
To:
References
Download: ML083400181 (1)


Text

NFPA 805 Pilot License Amendment Request Review

& Infrastructure Update SHEARON HARRIS (Harris) NFPA 805 License Amendment Request Date Available (LAR) REVIEW SCHEDULE (Progress Energy) Information Harris LAR Submittal Letter from Progress Energy with Partial Enclosures 5/29/08 ML081560641 Remaining Harris LAR Enclosures 5/29/08 ML081840706 LAR Submission Ceremony 7/17/08 ML082060554 NRC LAR Acceptance Review Letter to Progress Energy 9/26/08 ML082701158 Public Meeting Summary: Clarification Call on Harris Supplement 9/29/08 ML082960153 Harris LAR Supplement (Part 1) due 11/08 **

Harris LAR Supplement (Part 2) due 12/08 Harris LAR Site Audit (tentative) 2/09*

Issue LAR Request for Additional Information (RAI) to Progress Energy 3/09*

Harris LAR RAI Responses due from Progress Energy 5/09*

Harris Safety Evaluation Issued to Progress Energy 9/09*

OCONEE NFPA 805 LAR REVIEW SCHEDULE (Duke Energy) Date Available Information Oconee LAR Submittal Letter from Duke Energy with Partial Enclosure 5/30/08 ML081650475 Remaining Oconee LAR Enclosures 5/30/08 ML082041014 LAR Submission Ceremony 7/17/08 ML082060554 Oconee LAR Supplement due 10/31/08 **

NRC LAR Acceptance Review Letter to Duke Energy 12/08 Oconee LAR Site Visit (tentative) 2/09*

Issue Oconee LAR RAIs to Duke Energy 3/09*

Oconee LAR RAI Responses due from Duke Energy 5/09*

LAR Safety Evaluation Issued to Duke Energy 9/09*

NFPA 805 INFRASTRUCTURE DEVELOPMENT SCHEDULE Date Available Information Received from the Nuclear Energy Institute (NEI) NEI 00-01, Revision 2 12/07 ML082050625 Received NEI 04-02, Revision 2 from NEI 4/08 ML081400332 Send NRC Comments on NEI 00-01, Rev 2 5/08 ML081640340 SRP 9.5.1.2, Risk-Informed, Performance-Based Fire Protection 10/08 ML082830934 Public Meeting Summary NFPA 805 Regulatory Audit Plan Template Memo 12/08 (internal memorandum; will be publicly available in ADAMS)

SRP 9.5.1.2 Published for Public Comment 1/09 Send NRC Comments on NEI 04-02, Rev 2 2/09 (unless covered in RG 1.205, Revision 1)

Publish Draft RG 1.205, Revision 1 for Public Comment 3/09 Publish RG 1.200, Revision 1 4/09

  • These milestone dates are estimates based on a high-quality supplemental submittal.
    • Waiting for a redacted version to publish in ADAMs.

December 4, 2008