NRC 2009-0082, Background Information to Support License Amendment Request 261, ATC Lnterim Operation and Impacts Re-Study, Appendixes B - J: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 20: Line 20:


=Text=
=Text=
{{#Wiki_filter:G83314-J022/J023 Interim Operation and Impacts Re-Study Report-ROl Appendix B: Stability Analysis Results American Transmission Company Page 49 of 102 G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Nomenclature K or KEW: P or POB: S or SEC: F or FOX: NAP: GVL: CYP: ADN: FJT TH: L111: L121: Q303: L151: R304: NAPL71: CYP31: 6832: TIO: SEC3I: H: KWH: KWL: POBxy: Y311 CCT: Kewaunee Point Beach (PI and P2) Sheboygan Energy Center Fox Energy North Appleton Granville Cypress Arcadian Forest Junction Thilmany Point Beach-Sheboygan Energy Center 345 kV line Point Beach-Forest Junction 345 kV line Point Beach-Kewaunee 345 kV line Point Beach-Fox Energy 345 kV line Kewaunee-North Appleton 345 kV line North Appleton-Werner West 345 kV line CypressArcadian 345 kV line North Appleton-Fox Energy Center 345 kV line Kewaunee TI0 3451138 kV transformer Sheboygan Energy Center-Granville 345 kV line High side KewauneeT10 High side Kewaunee TI0 Low side Point Beach bus tie xy Nora Appleton-Fitzgerald 345 kV line Critical Clearing Time Note: The simulated clearing times and critical clearing times (CCT) noted in Appendix B contains planning margin described in Section 3.2 American Transmission Company Page 50 of 102 G83314-Jo22tJo23 Interim Ope I ation and Impacts Re-study Report-Ro1 Tab1 B.1- Stability Results for Faults Clearing in Primary Time under Intact System Conditions I Tntorim 7 /with G8?4/11073 with ~ri.rtin~ Kcrwnlinc!~? .ruh.rtntinn) -- -- .- - - - - Intact System Fault Cleared in Primary Time - Interim Period 1 (May 2010-April 2011) I Faulted End Breakers 111 121,123 151 Q-303 Q-303,1099,2450 R-304,3451 2-3,34 1-2,6-1 4-5,5-6 1-2,16 1-2,3-6 1-2,5-6 Q-303,1099,3450 Remote Location SEC FJT FOX KEW PO0 NAP POB NAP FJT POB GVL ADN KWL Remote End Event I Simulated I I I I Breakers Notes Clearing* I High 1-2.16 NO SPS 4.514.5 1-2,23 4.514.5 2-3.3-1 NO SPS 4.514.5 Q-303,1099,2450 KEW SPS In 4.516.5 Q-303 KEW SPS In 6.514.5 R-304 6.516.5 Generation I Low Generation I 151 4.514.5 1 243,344,45467-6 4.514.5 5-6,7-1 4.514.5 Ill 4.514.5 L-SEC31 4.516.5 L-CYP31 4.514.5 American Transmission compbY Page 51 of 102 G83314-J022lJO23 Interim ~Aeration and Impacts Re-Study Report-RO1 Intact System Fault Cleared in Primary Time - Interim Period 2A (~iril2011 and beyond, with existing Kewaunee) I 1 Interim 2A (with G834/J023 and G833/J022. with existing Kewau tee substation) Simulated I iigh Generation 1 Interim 2B (with G834/J023 and G833/J022, with new Kewmrnee substation) Element Fault Faulted End Remote Remote End Event Simulated File Faulted Location FltPOBSEC L111 POB 111 SEC 1-2,16 NO SPS 4.514.5 FltPOBFJT L121 POB 121,123 FJT 1-2,2-3 FltPOBFOX L151 POB 151 FOX 2-3,3-4 NO SPS 4.514.5 No FltPOBKEW Q-303 POB 4303 KEW Q-303 New 1 and 2 SPSs 4.514.5 No American Transmission ~om$an~ Page 52 of 102 07/14/2009 G833/4-J022/JO23 Interim 0~4ration and Impacts Re-Study Report-RO1 Table B.2- Stabilify Results for Double Circuit Single Line-to-Ground Faults Cleared in Primary Time under Intact System Conditions Interim 1 (with G834/J023, with existing Kewaunee substation) 1 I I I I I I I File Event I Fiyk Fault #I Acceptable Fault #2 Fault R Location American Transmission comP/any Simulated Clearing time DC3-111-971K51-I DC3-Ill-971K51-2 DC3-111-HOLG21-1 DC3-111-HOLG21-2 DC3-121-971K51-1 DC3-121-971K51-2 DC3-SEC31-3431-1 DC3-SEC31-3431-2 DC3SEC31-8231-1 DC3-SEC31-8231-2 DC3-9932-2642-1 DC~-9932-2642-2 DC3-9932-2661-1 DC3-9932-2661-2 DC3-9932-9911-1 DC3-9932-9911-2 Page 53 of 102 Interim Pel (May 2010-Apr 201 1) mm L1 l1 L1ll Ll 1 I Llll L121.R. L121.R L-SE(31- L- L- L- L- - BeachSheboygan 345 kV -Point 345 kV - Point BeachSheboygan 345 kV -Point Beach-Sheboygan 345 kV Beach-Forest Junction 345 kV Beach-Forest Junction 345kV Sheboygan-Granville 345 kV L-SEC31-Sheb0ygan-Granvi11e 345 kV LSEC31Sheb0ygan-Granvi'le 345 kV L-SE231Sheb0~!3an-Granville 345 kV CYP3l- Cypress-Arcadian 345 kV CYP31 - 345 kV CyP31 - 345 kV CyP31 - Cypress-Arcadian 345 kV CyP31 - Cypress-Arcadian 345 kV CyP31- Cypress-Arcadian 345 kV 38.5% frorn POB 16.3% from SEC SEC ' ,5.70m from SEC FJT 42.3% from FJT GVL 26.7% from GVL 43.5% from GVL 48.3% frorn GVL 32.00/0 from ADN 16.6% from ADN 10.8% from ADN 16.6% from ADN 10.8% from ADN ADN 5.515.5 5.515.5 5.515,5 5.515.5 5.515.5 5.515.5 7.517.5 7.517.5 7.517.5 7.517.5 5.515.5 5.515.5 5.55.5 5.515.5 5.515.5 5.515.5 971 K51 - Forest Junction-Howard's Grove 138 kV 971K51 -Forest Junction-Howard's Grove 138 kV HOGL21 -Howard's Grove-Holland 138 kV HOGL21- Howard's GroveHolland 138 kV Grove 138 kV 971 K51- Forest Junction-Howard's 971K51- Forest Junction-Howard's Grove 138 kV 3431 - Granville-Saukville 345 kV 3431 - Granville-Saukville 345 kV 8231 - Saukville-Barton 138 kV 8231 - Saukville-Barton 138 kV 2642 - Saukville-Gemantown 138 kV 2642 - Saukville-Gemantown 138 kV 2661 - Germantown-Bark River 138 kV 2661 - Germantown-Bark River 138 kV 991 1 - Granville-Arcadian 345 kV 991 1 - Granville-Arcadian 345 kV 33.g9/0 from NT 6.3% from HOG 76.9% from HOL 314X from HOG FJT 33.9% from FJT GVL 25.3% from SAU 36.4% from BRT 36.4% from SAU 34.2% from SAU GER 31.5% from GER GER 45.4% from GVL ADN 6.516.5 6.516.5 6.516.5 6.516.5 6.516.5 6.516.5 7.517.5 7.517.5 7.517.5 7.517.5 7.517.5 7.517.5 8.518.5 8.518.5 7.517.5 7.517.5 G83314-J022lJ023 Interim opetiation and Impacts Re-Study Report-RO1 Event File American Transmission comPby Dm-111-971 K51-I DC3-111-971K51-2 DC3-111-HOLG21-1 DC3-111-HOLG21-2 DC3-121-971 K51-1 DC3-121-971K51-2 DCSEC31-3431-1 DC3SEC31-3431-2 DC3-SEC31-8231-1 DC3SEC31-8231-2 DC3-9932-2642-1 DC3-9932-2642-2 DC3-9932-2661-1 DC3-9932-2661-2 DC3-9932-9911-1 DC3-9932-9911-2 Page 54 of 102 Interim 2A (with G834/J023 and G833/J022, with existing Kewaunee substation) Fault #1 L111 - Lll I - Llll - Llll - L121-fk L121-%. L-SECSl L- L- L- L- L- L- Point BeachSheboygan 345 kV Point BeachSheboygan 345 kV Point Beach-Sheboygan 345 kV Point BeachSheboygan 345 kV Beach-Forest Junction 345 kV Beach-Forest Jundon 345 kV - Sheboygan-Granville 345 kV LSEI.>31Sheboygan-Granville 345 kV LSEC>31Sheboygan-Granville 345 kV L-SEC>31-Sheboygan-Granville 345 kV C\rbP31 - Cypress-Arcadian 345 kV CYf"fJ1- Cypress-Arcadian 345 kV CtkP31 - Cypress-Arcadian 345 kV C"P31- Cypress4wdian 345 kV C"P31 - Cypress-Arcadian 345 kV Cbp31 - Cypress-Arcadian 345 kV Fauit#2 Location Fault #1 Location 38.5% from POB 16.3% from SEC SEC 15.7% from SEC FJT 42.3% from FJT GVL 26.7% from GVL 43.5% from GVL 48.3% from GVL 32.0% from ADN 16.6% from ADN 10.8% from ADN 16.6% from ADN 10.8% from ADN ADN Acceptable CCT" Fault #2 5.515.5 5.515.5 5.515.5 5.515.5 5.515.5 5.515.5 7.5R.5 7.517.5 7.517.5 7.5R.5 5.515.5 5.515.5 5.515.5 5.515.5 5.515.5 5.515.5 971K51- Forest Junction-Howard's Grove 138 kV 971K51- Forest Junction-Howard's Gmve 138 kV HOGL21- Howard's GroveHolland 138 kV HOGL21 - Howard's Grove-Holland 138 kV 971K51- Forest Junction-Howard's Grove 138 kV 97101 - Forest Junction-Howard's Grove 138 kV 3431 - Granvile-Saukville 345 kV 3431 - GranvilleSaukville 345 kV 8231 - Saukville-Barton 138 kV 8231 - Saukville-Barton 138 kV 2642 - Saukville-Germantown 138 kV 2642 - Saukville-Germantown 138 kV 2661 - Germantown-Bark River 138 kV 2661 - Germantown-Bark River 138 kV 9911 - Granville-Arcadian 345 kV 991 1 - Granville-Arcadian 345 kV 33.9% from FJT 6.3% from HOG 76.9% from HOL 31.4% from HOG FJT 33.9% from FJT GVL 25.3X from SAU 36.4% from BRT 36.4% from SAU 34,2% from SAU GER 31.5% from GER GER 45.40/0 from GVL ADN 6.516.5 6.516.5 OK OK 6.516.5 6.516.5 - 6.516.5 6.516.5 7.517.5 7.517.5 7.517.5 7.517.5 7.5175 7.517.5 8.518.5 8.518.5 7.517.5 I I - 7.5R.5 G83314-J022lJO23 ~nterim operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation) I I I I I I I I I Event 1 Fault Fault #I Fault Fault #2 File #I I Location #2 I Location Interim Period 2B (May 2011 -), WI new Ke American Transmission c~mPany Page 55 of 102 DC3-111-971 K51-1 DC3-111-971 K51-2 DC3-111-HOLG21-1 DC3-111MOLG21-2 DC3-121-971 K51-1 DC3-121-971 K51-2 DC3SEC31-3431-1 DC3SEC31-3431-2 DC3SEC31-8231-1 DC3SEC31-8231-2 DC3-9932-2642-1 DC3-9932-2642-2 DC3-9932-2661-1 DC3-9932-2661-2 DC3-9932-99111 DC3-9932-9911-2 L111- L111.. Ll I I -1 Ll I 1 . L121-~3. L121-3. LSEC31- L- L- L- L- L- L- Point BeachSheboygan 345 kV Point BeachSheboygan 345 kV Point BeachSheboygan 345 kV Point BeachSheboygan 345 kV Beach-Forest Junction 345 kV Beach-Forest Junction 345 kV Sheboygan-Granville 345 kV L-SEC31-Sheboygan-Granville 345 kV L-SEC31Sheboygan-Granville 345 kV LSEC31Sheboygan-Granville 345 kV C"P31- Cypress-Arcadian 345kV C'P31- Cypress-Arcadian 345 kV C\?31- Cypress-Arcadian 345 kv C\?31 - Cypress-Arcadian 345 kV C\'P31 - Cypress-Arcadian 345 kV C'931- Cypress-Arcadian 345 kV 38.5% from POB 16.3% from SEC SEC 15.7% from SEC FJT 42.3% from FJT GVL 26.7% from GVL 43.5% from GVL 48.3% from GVL 32.0% from ADN 16.6% from ADN 10.8% from ADN 16.6% from ADN 10.8% from ADN ADN 5.515.5 5.515.5 5.515.5 5.515.5 5.515.5 5.515.5 7.5R.5 7.5R.5 7.5R.5 7.517.5 5.515.5 5.515.5 5.515.5 5.515.5 5.515.5 5.515.5 971K51 -Forest Junction-Howard's Grove 138 kV 971K51- Forest Junction-Howard's Grove 138 kV HOGL21 -Howard's GroveHolland 138 kV HOGL21- Howard's Gmve-Holland 138 kV 971K51- Forest Junction-Howard's Grove 138 kV 971K51- Forest Junction-Howard's Grove 138 kV 3431 - GranvilleSaukville 345 kV 3431 - GranvilleSaukville 345 kV 8231 - Saukhile-Barton 138 kV 8231 - Saukville-Barton 138 kV 2642 - Saukville-Germantown 138 kV 2642 - Saukville-Germantown 138 kV 2661 - Germantown-Bark River 138 kV 2661 - Germantown-Bark River 138 kV 991 1 - Granville-Arcadian 345 kV 991 1 - Granville-Arcadian 345 kV High Gen I Low Gen I 33.9% from FJT 6.516.5 6.3% from HOG 6.516.5 1 76.9% from HOL 6.516.5 31.4% from HOG 6.516.5 I FJT 6.516.5 I 33.9% from FJT 6.516.5 GVL 7.5R.5 25,3% from SAU 7.5R.5 36.4% from BRT 7.517.5 36.4% from SAU 7.5R.5 34.2K from SAU 7.5R.5 GER 7.5R.5 31.5% from GER 8.518.5 GER 8.518.5 45.4% from GVL 7.5R.5 ADN 7.517.5 G83314-J022/JO23 Interim Table B.3- Stl Note: Among various Event Elemen Faulted I FltKEWNAP I R-304 *** Stable at 5.514.5 with G1 res Event Element Faulted ** Stable at 5.514.5 -replace R-! Event Element
{{#Wiki_filter:G83314-J022/J023 Interim Operation and Impacts Re-Study Report-ROl Appendix B: Stability Analysis Results American Transmission Company                   Page 49 of 102
* For stability, G1 needs to be re ** For stability, Gl needs to be I American Transmission C Operation and Impacts Re-Study Report-RO1 lbility Results for 3-Phase Faults Cleared in Primary Time under Prior Outage Condition Units Trpping contingencies evaluated, only faults with stability issues are listed in Table B.3. Interim 1 (with G834/J023, with existing Kewaunee substation) Primary Clearing Time, Prior Outage: 6832 (FOX-NAP, 38894-39556), (POB PSSs In Service) Existing KEW Sub Fault Faulted End Remote Remote End Event Simulated High Generation I Low Generation Location Breakers Location Breakers Notes Clearing* I Primary Clearing Time, Prior Outage: SEC31 (SEC-GVL, 3986538870), (POB PSSs In Service) Existing KEW Sub Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation Location Breakers Location Breakers Notes KEW R-304.3451 NAP R-304 6.516.5 04 breaker at NAP. 4.5 is MECT for R304 fault at KEW. Existing clearing time at faulted end is 4.5 cycles without margill Primary Clearing Time, Prior Outage: PO0 2-3 (POB-B23,3889&39211), (PO0 PSSs In Service) Existing KEW Sub Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation acation Breakers Location Breakers rtricted to 580 MW gross estricted to 620 MW gross Page 56 of 102 G83314-J022lJO23 Inte ' Operation and Impacts Re-Study Report-RO1 Interim 2A (with G834/J023 and G833/J022, with existing Kewaunee substation) Primary Clearing Time, Prior Outage: Llll (POB-SEC, 39433-39865), 'POB PSSs In Sewice) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation Fle Faulted Location Breakers Location Breakers Notes Clearing' Base Base FIWWNAP R-304 KEW R-304,3451 NAP R-304 6.516.5 "* Stable at 5.514.5, Replace R-304 breaker at North Appleton. Note: MECT of R304 at Kew is 4.5 Primary Clearing Time, Prior Outage: L121 (POB-FJT, 38898-39304), (POB PSSs In Service) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation File Faulted Location Breakers Location Breakers Notes Clearing* Base Base I FltKEWNAP I R-304 I KEW I R-304,3451 I NAP I R-304 I 1 6.516.5 A Stable at 5.014.5 or Stable at 5.514 5 with G2 reduced to 620 MW-replace R304 breaker at NAP. Existing clearing time at faulted end is 4.5  cycle^  cy out margin Primary Clearing Time, Prior Outage: L151 (POB-FJT, 38898-39304), (POB PSSs In Sewice) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation I Low Generation I File Faulted Location Breakers Location Breakers Note: Without G2 reduction, Vsag uAl trip P with 5.514.5 (PI 1.513sfor 19KV, P2 1.521sfor I9KV , BIB5 1st 1.083s, BIB5 2nd 1.575s). Thus, if time delay can be readjusted to avoid violation, only thing to be done is replacing R-304 breaker at NAP Primary Clearing Time, Prior Outage: R-304 (KEW-NAP, 39630-39359), (POB PSSs In Sewice) Existing KEW Sub Event 1 Element 1 Fault 1 Faulted End Remote Remote End Event I Simulated I High Generation I Low Generation I I File I Faulted I lrocation I Breakers ( ~ocation I Breakers Notes I Clearing* I FltFOXNAP 1 L6832 1 FOX I 1-2,6-1 1 NAP 1 34-3,344,454.67-6 1 1 4.5145
* Stable at 4.014.5 OR Stable at 4.5'4.5 with G2 reduced to 600 MW gmss. At 4.514.5 with G2 at 620 MW, 345 kV 2nd criteria is violated: 81: 1.583s and 82: 1.583s. Primary Clearing Time, Prior Outage: 6832 (FOX-NAP, 38894-39556), (POB PSSs In Sewice) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation File Faulted Location Breakers Location Breakers Notes Clearing* Base Base American Transmission Gmpany FIKEWNAP I R-304 1 KEW 1 R-304,3451 I NAP I R-304 ( 6.516.5 FLTKEWXFH2ROl I TI0 I KWH 1 Q-303,1099,3450 1 KWL I 1066E, 1066W I Open Q-303 at KEW 1 6.518.5 Page 57 of 102 "*Stable at 6.018.5 with G2 reduced Stable at 5.514.5 with G2 at 580 to 580 MW gmss. 5.0 cyde is the existing dearing time at the high side of TI0 transformer. MW (replace R-304 breaker at NAP and reduce G2 to 580 MW gross). Existing clearing time at faulted end is 4.5 cycles without margin AM Stable at 5.514.5 with both GI a11d 62 at 540 MW (replace R-304 breaker at NAP and reduce both GI and G2 to 540 MW). Existing clearing time at faulted end is 4.5 cycles without margin G83314-J022/J023 ~nterim  erati ti on and Impacts Re-Study Report-RO1 Event File FltKEWNAP FLTKEWXFHPROI I TI0 A Stable at 6.018.5 with G2 at 620 (02 Stable at 5.518.5 or Stable at 6.018.5 *Stable at 5.514.5 with G2 580 MW Primary Clearing Time, Prior Outage: SEC31 (SEGGVL, 398638870), (POB PSSs In Service) Existing KEW Sub Element Faulted R-304 KWH 1 Q-303,1099,3450 1 KWL I 1066E, 1066W I Open Q-303 at KEW 1 6.518.5 reduction to 620 gross). 5.0 cycle without margin is the existing clearing time at the high side of TI0 transformer. with G2 at 580 MW (62 reduction to 580 gross). 5.0 cycle without margin is the existing clearing time at the high side of TI0 transformer. - Replace R-304 breaker at NAP and 62 at 580 MW gross. Existing clearing time at faulted end is 4.5 cycles without margin 1 - Stable at 5.514.5 with G2 at 620 f#W gross. Existing clearing time at faulted end is 4.5 cycles without margin American Transmission chmPany Event Simulated High Generation Low Generation Notes Clearine Base Base 6.516.5 Event File FIWWNAP - I Page 58 of 102 Remote End Breakers R-304 Primary Clearing Time, Prior Outage: POB 1-2 (POB-Bl2,39433-38898), (POB PSSs In Service) Existing KEW Sub Element Faulted R-304 Primary Clearing Time, Prior Outage: POB 2-3 (POB-B23,38898-39211), (POB PSSs In Service) Existing KEW Sub Event File Remote Location NAP Fault Location KEW Fault Lpcation KEW "'Stable at 5.514.5. Replace R-304 Element Faulted Event Ae FltKEWNAP Faulted End Breakers R-304,3451 Event Simulated High Generation I Low Generation Notes Clearing' Rscn Rscn 4.514.5 Primary Clearing Time, Prior Outage: POB 4-5 (POB-B45,38900-38901), (POB PSSs In Senrice) Existing KEW Sub Element Faulted R-304 ~reaker at NAP. Existing clearing time at faulted end is 4.5 cycles without margin
* For stabili, GI needs to be resbi ed to 580 MW gmss Remote End Breakers 1-2,2-3 Pault Loption Fault Lpcation KEW "'Stable at 5.514.5 with G2 at 620 k Event Simulated High Generation I Low Generation Notes Clearing* - I Base Faulted End Breakers R-304,3451 FltPOBFJT YOB Faulted End Breakers L121 JV (replace R-304 breaker at NAP and reduce G2 to 620 MW). Existing clearing time at faulted end is 4.5 cycles without margin Remote Location NAP Remote Location Event Simulated High Generation Low Generation Notes Clearing* Base Base 6.516.5 Remote End Breakers R-304 121,123 Remote End Breakers R-304 Faulted End Breakers R304,3451 FJT Remote Location NAP G83314-502215023 Interim Event Element I FltKEWNAP I R-304 1 ' Stable at 4.514.5 with G2 restricted Event Element File Faulted To be stable at 4.514.5, GI needs 1 "To be stable at 4.514.5, GI needs American Transmission C Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation) Primary Clearing Time, Prior Outage: 6832 (FOX-NAP, 38894-39556), (POB PSSs In Service) New KEW Sub Page 59 of 102 Low Generation Base Primary Clearing Time, Prior Outage: POB 2-3 (POBB23,38898-39211!, High Generation Base J be restricted to 580 MW gmss to be restricted to 620 MW gross (POB PSSs In Sewice) New KEW Sub Simulated Clearing* Event Notes Remote End Breakers 1-2,23 4.516.5 Event Notes Simulated High Generation Low Generation Clearing* Base Base 4.514.5 Remote Location FJT Fault acation POB to 600 MW gmss (G2 restriction 600 MW gross with R-304 breaker at NAP replaced) R-304 Remote End Breakers Faulted End Breakers 121,123 NAP Remote Location KEW Fault )cation R-304,3451 Faulted End Breakers G83314-J022tJ023 Interim Operation dd Impacts Re-Study Report-RO1 Table B. - Stability Results for 3-Phase Faults Cleared in Delayed (Breaker Failure) Time under Intact Conditions, Units Tripping 1 Interim I (with G834/J023, with existing Kewaunee substation) re Events - lnter~m Per~od 1 (May 2010-Aprll 2011) I American Transmission Company 1 Page 60 of 102 Page 61 of 102 G833/4-JO22/JO23 Interim Operation Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation) I Event I Element I I File 1 Faulted I I BFIFOXPOBZ I L151 I FOX BFIFOXNAR 1 L6832 1 FOX 1 BFIFOWJT;! 1 971171 1 FOX BFlSECPOBl I Llll I SEC BFISECGVLl I LSEC31 I SEC BFICYPADN I LGYP~I I cn BFICYPFJT 1 971L51 1 CYI -. I I 'Relay upgrades or lnstalllng a series breaker desa " Relav uoarades described in Section 1.1 wlll addn ad el; ibrades described in Section 1 .I will add, American Transmission Company Event I Simulated I High Gen I LOW tien I I 1 !din Section 1.1 will address the issue. ;the issue she issue Page 62 of 102 G833/4-J022IJ023 Interim Operation and Impacts Re-Study Report-RO1 Table B.5- Stability Results for Point Beach Bus Single Line-to-Ground Faults Cleared in Delayed Time under Intact Conditions Kewaunee substation) Fault Location Element Clearing 1 I I i- Interim 1 tripped POB Bus 1 POBSEC 4.75124.5 POB BUS 1 POB Bus 1-2 4,75112.5 2A wl Ex~st~na KEW Fault Failure Simulated Location Element Clearing ( tripped 1 POB Bus I I POBSEC 1 4.75124.5 POB Bus 1 I POB Bus 1-2 1 4.75112.5 POB Bus 2 I POB Bus 2-1 1 4,75112.5 POB Bus 2 I POB Bus 2-3 1 4.75112.5 POB Bus 3 I POB Bus 3-2 ( 4.75112.5 POB Bus 3 ( POB-KEW 1 4,75124.5 POB Bus 3 POB Bus 4 POB Bus 5 I POB BUs5-4 ( 4.751128 POB Bus 5 I POB-FOX 1 4.7~~5 ** Stable at 4,75112.0. As described in Section 1.1, Change Relay senlug (w~mnout areaKer ral~ure relay lcpraccucur, LUL rarrruo ur I oint Beach Bus Tie 2-3 to no more than 11 cycle total breaker failure clearing time for bus faults American Transmission Company Page 63 of 102 G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation) 1 ~oGion I Elementhipped I Clearing 1 Ul-h pal I -.., can IOB Bus 1 I PoB-sEc 1 4.75124.5 1 POB Bus 1 POB Bus 2 I POB Bus2-1 I ~75113 5 POB Bus 2 POB Bus 2-3 4.75112.5 POB Bus 3 POB Bus 3-2 4.75112.5 POB Bus 3 POB-KEW 4.75112.5 POB Bus 3 I POB Bus 3-4 1 4.75112.5 POB Bus 4 I POB Bus 4-3 1 4.75112.5 POB Bus 4 I POB BUS 4-5 1 4.75112.5 POB Bus 5 POB Bus 5 American Transmission Company Page 64 of 102 G83314-J022/5023 Interim Operation and Impacts Re-Study Report-RO1 Table B.6- Stability Results for GSU Single Line-to-Ground Faults Cleared in Delayed Time under Intact Conditions, Units Tripping Interim 1 (with G834/J023, with existing Kewaunee substation) Breaker Fault 1 Failure I Simulated 1 Location Element Clearing POB GSU BF Faults Interim 2A (with G834/J023 and G833/J022, POB GSU BF Faults w' Breaker Fault I Failure I Simulated Location Element Clearing Interim 2B (with G834/J023 and G833/JO POB GSU BF Faults Breaker Fault 1 Failure 1 Simulated 1 Location Element Clearing American Transmission Company Page 65 of 102 G833/4-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table B. 7- Stability Results for Auxiliary Transformer High Side Single Line-to-Ground Faults Cleared in Delayed Time under Intact Conditions, Units Tripping Interim I 1 (with G834/J023, I with existing I Kewaunee substation) I POB AUXl HS POB-SEC @ SFC Interim 1 I Faulted Element Element Tripped Faulted Element Failure POB AUXl HS I POB Bus2" POB AUX2 HS I POB Bus4"' I -The Stability Model Time Step is 0.25 cycles, so a 13.3 cycle fault actually clears in 13.5 cycles. " - POB-Forest Junction 345 kV line Tri~s. POB Generator 1 is Isolated. "* - POB  ene era to; 2 'is isolated taulreo Element Interim 2A (with G834/J023 and G833/J02 I Failure - .. . Breaker POB AUXl HS POB AUX2 HS Faulted Breaker Element Failure POB-SEC @ Faulted Element I POB AUX2 HS POB-FOX @ FOX Breaker Failure Element Tripped - A 'a- -& Faulted Breaker Element Failure Element Tripped 5.1113.3' 5.1113.3' mms -The Stability Model Time Step is 0.25 cycles, so a 13.3 cycle fault actually clears in 13.5 cycles. - POB-Forest  unction 345-kV line Trips, POB Generator 1 is Isolated. "** - POB Generator 2 is isolated American Transmission Company Page 66 of 102 POB AUXl HS I POBBus2" I OK I _.. POB AUX2 HS I POB Bus4"' 1 OK I OK * -The Stability Model Time Step is 0.25 cycles, so a 13.3 cycle fault actually clears in 13.5 cycles. " - POB-Forest Junction 345 kV line Trips, POB Generator 1 is Isolated. "* - POB Generator 2 is isolated Interim 2B (with G834/J023 and G833/J02L" "' ee substation)
G83314-J022lJ023 ~nterimlo~eration and Impacts Re-Study Report-RO1 Table B.8- Stability R for GSU Three Phase 345 kVFaults Cleared in Primary (5.5 cycles, including I cycle margia) Time under Intact and Prior Outage Conditions, Units Tripping Interim 1 (with G834/J023, with existing Kewaunee substation) Interim 1 Interim 1 American Transmission c/omPany Page 67 of 102 G833/4-J022/J023 1nte4 Operation and Impacts Re-Study Report-RO1 Interim 2A (with G834/J023 and G833/J022, with existing Kewaunee substation) American Transmission dompany Page 68 of 102 G833/4-J022IJ023 Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation) 5.5 cyles di-cycle margin). American Transmission C/ompany Page 69 of 102 G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Table B.9- Stability Results for Auxiliary Transformer High Side 3-Phase Faults Cleared in Primary Time (6.1 cycles, including 1 cycle margin) under Intact and Prior Outage Conditions Interim 1 (with G834/J023, with existing Kewaunee substation) I I I H~igh Generatian Low Generation -. Interim 1 ' I&< ' 5.75B.1 ' 5.75 -- I "SEC Gens Isolated 7 Prior Outage I Low Generation I Interim 1 - ..- ,- . American Transmission Company "POB GEN 2 Isolated Page 70 of 102 G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Interim 2A (with G834/J023 and G833/J022, with existing Kewaunee substation) I I Uinh Canardinn I I nw Generation I Prior Fault FltPOBAXl - - Inlerlm 2A wl exlstlng lnlerlm 2A wl ex~sllng KEW 5 7516 1 5 7516 1 FltPOBAXl L-CYP31 tiEi?Tm FltPOBAXl NAPL7l FltPOBAXl 971L51 FltPOBAXl Y-311 I FItPOBAX1 1 :ii FltPOBAXl I FltPOBAXl 1 845 'SEC Gens Isolated . . . . - . . . - .. I Prior Fault "POB GEN 2 Isolated American Transmission Company nlerini 2A 1.~1 exisl~ng lnlerini 2A wl existing KE!I\! KE\N 5 7516 1 5 7516.1 ' I G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Prior Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation FltPOBAXl FltPOBAXl FltPOBAXl Hinh Ganaratinn FltPOBAXl 6832 FltPOBAXl 971L71 FltPOBAXl LSEC31 FltPOBAXl L-CYP31 FltPOBAXl TI 0 FltPOBAXl NAPL71 FltPOBAXl 971L51 FltPOBAXl Y-311 FltPOBAXl 812 FltPOBAXl 823 FltPOBAXl 834 FltPOBAXl 845 Low Generation 'SEC Gens Isolated High Generalon I Low Generation Prior Fault Outage FltPOBAX2 None "POB GEN 2 isolated I OK" OK merican Transmission Company Page 72 of 102 G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table B.10- Stability Results for Kewaunee and Point Beach Generation Outage under Intact Conditions Interim 1 (with G834/J023, with existing Kewaunee substation) I Interim I UNlT TRlP Trip time UNITTRIP POBGltn' POBG2tri POBGlGStri KEWGl tri I Low Gen i Interim 2A (with G834/J023 and G833/m77 with ~ri.vtinc Kewaunee substation) I I Interim 2A (wl existing . . - . . . . UNlT TRlP POBGltri POBG2tri POBGlG2tri Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation) American Transmission Company Page 73 of 102 G83314-J022lJO23 ~nteriml operation and Impacts Re-Study Report-RO1 1 A~nendix C: Cornnetin9 Wind Generators 1 99 1 TBD (suspended) I Kewaunee-Mishimt 138 kV line I -- 31-2011 Elkhart Lake-Forest Junction 138 kV line C 12-01-2012 Forest Junction-Lost Dauphin 138 kV line American Transmission qmpany 427 G590 Page 74 of 102 WEC WEC 98 98 TBD (suspended) TBD (suspended) Cypress 345 kV Substation Tecumseh Rd 138 kV Substation G833/4-J022/J023 Interim Operation and Impacts Re-Study Report-RO1 Appendix D: Operating Restrictions American Transmission Company Page 75 of 102 G833/4-J022/J023 Interim Operation and Impacts Re-Study Report-RO1 With all stability upgrades assumed in-service and the Minimum Excitation Limiter settings for Point Beach and Kewaunee units modified, generation restrictions identified for each interim period are: During Interim 1 period (2010 after G834lJ023 - 201 1 before G8331J022) iii. G1 at 560 MW (gross) under prior outage condition of 6832 (North Appleton-Fox River 345 kV line) iv. GI at 580 MW (gross) under prior outage condition of Point Beach Bus Tie 2-3 During Interim 2A period (Without Kewaunee project, 201 1 after G833lJ022 - beyond ) viii. G2 at 620 MW (gross) under prior outage of 121 (Point Beach-Forest Junction 345 kV line) ix. G2 at 620 MW (gross) under prior outage of 15 1 (Point Beach-Fox River 345 kV line) x. G2 at 600 MW (gross) under prior outage of R304 (Kewaunee-North Appleton 345 kV line) xi. Both GI and G2 at 540 MW (gross) under prior outage of 6832 (North Appleton- Fox River 345 kV line) xii. G2 at 580 MW (gross) under prior outage of SEC3 1 (Sheboygan Energy Center- Granville 345 kV line) xiii. GI at 580 MW (gross) under prior outage of Point Beach Bus Tie 2-3 xiv. G2 at 620 MW (gross) under prior outage of Point Beach Bus Tie 4-5 During Interim 2B period (With Kewaunee project, 201 1 after G83315022 - beyond) i. G2 at 600 MW (gross) under prior outage condition of 6832 (North Appleton-Fox River 345 kV line) ii. G1 at 580 MW (gross) under prior outage condition of Point Beach Bus Tie 2-3 American Transmission Company Page 76 of 102 683314-J022lJO23 Interim Operation and Impacts Re-Study Report-RO1 Appendix E: Short Circuit / Breaker Duty Analysis Results \, I sub with line conversion 26615.1 23988.7 10915.9 13402.2
* POB GI and G2 ofline and Q-303 out of service ** Scenario 6 and 7 were also studied to provide maximum and minimum fault duties that may appear due to potential future bansmission reinforcement. Scenario 1 = Existing system Scenario 2 = Existing with new GSU of POB G2 (Fall 2009-May 2010) Scenario 3 =With G834 (J023) and new GSU of POB GI (May 2010-May 2011) I Scenario 4 = With G83314 (J02.213) with existing Kewaunee (May 201 1-beyond) Scenario 5 =With G83314 (J02213) with new Kewaunee (May 201 1-beyond) **Scenario 6 =With G83314 (J02213) with new Kewaunee and potential East sub **Scenario 7 =With G83314 (~02d3) with new Kewaunee and ~otential EasffNorth Table E.2 - Thevenin Equivalent Impedances in Ohms corresponding to Maximum Fault Duty 23293.9 23878.5 24516 24660.4 24801.6 25448.4 Pos Seq. American Transmission Company 21 160.4 21419.7 21758.5 21927.2 22017 22749.3 Scenario 1 = Existing system Scenario 2 = Existing with new GSU of POB G2 (Fall 2009-May 2010) I Scenario 3 = With G834 (J023) and new GSU of POB GI (May 2010-May 201 1) Scenario 4 =With G83314 (J02213) with existing Kewaunee (May 201 $-beyond) I Scenario 5 =With G83314 (J02213) with new Kewaunee (May 2011-beyond) ** Scenario 6 = With G83314 (J02213) with new Kewaunee and potential East sub **Scenario 7 =With G83314 (J02213) with new Kewaunee and potential EastlNorth sub with line conversion Page 77 of 102 Neg. Seq. 9288 9288 9288 9288 9288.2 9786.8 Zero Seq. ** These scenarios were also studied to provide maximum and minimum fault duties that may appear due to potential future transmission reinforcement. 0.492146+ j 9.400272 0.47915+ j 9.28685 0.476195+ j 9.141977 0.480694+ j 9.071247 0.500629+ j 9.033035 0.483549 + j 8.742337 0.455713 + j 8.290790 11100.6 11 100.6 11100.6 11100.6 11 100.7 11 954.8 0.563439t j 9.4053 0.547887+ j 9.291845 0.648689+ j 9.140315 0.754597+ j 9.060422 0.774579+ j 9.021229 0.734901 + j 8.732362 0.685388 + j 8.282391 0.589203+ j 6.794582 0.530596+ j 6.397666 0.480063+ j 6.038944 0.480063t j 6.038944 0.483616+ j 5.974935 0.491449 + j 5.944132 0.496780 + j 5.818807 G83314-J022/1023 Interim Operation and Impacts Re-Study Report-RO1 American Transmission Company Page 78 of 102 G83314-J022N023 Interim Operation and Impacts Re-Study Report-RO1 Page 79 Of 102 G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Appendix P: Study Criteria American Transmission Company Page 80 of 102 G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Study Criteria F. 1 Contingencies For stability analysis, a set of branches in the vicinity of the generatorlpower plant of concern is selected as contingencies, based on engineering judgment. Fault analysis is performed for the following six categories of contingency conditions: 1. Three-phase fault cleared in primary time with an otherwise intact system. 2. Three-phase fault cleared in delayed clearing time (i.e. breaker failure conditions) with an otherwise intact system. 3. Three-phase fault cleared in primary clearing time with a pre-existing outage of any other transmission element. 4. Single Line Ground (SLG) bus section fault cleared in primary clearing time with an otherwise intact system. 5. SLG internal breaker fault cleared in primary clearing time with an otherwise intact system. 6. SLG fault of double circuits on common tower cleared in primary time with an otherwise intact system. For power flow analysis, contingencies include: 1. N-1 contingencies - all lines and transformers operated at 69kV and above in the following control areaslzones: ATC Planning Zones 1-5 and ties to those zones and all branches of voltage level 69kV and above in the Dairyland Power Cooperative, Northern States Power Control Area, Commonwealth Edison, and Alliant Energy West control areas. 2. Selected N-2 and multiple contingencies that ATCLLC has determined to be significant. F.2 Monitored Elements F.2.1 Intact System, N-1, N-2 and Special Multiple Contingency Evaluation Using Linear Transfer Analysis Methods All load carrying elements operated at 69kV and above in the following control areaslzones were studied: ATCLLC Planning Zones 1-5 and ties to those zones, and all branches of voltage level 69kV and above in the Dairyland Power Cooperative, Northern States Power Control Area, Commonwealth Edison, and Alliant Energy West control areas. A Transmission Reliability Margin (TRM) of 5% must be applied to the MVA ratings of each monitored ATCLLC element. Violations reported will be based upon the adjusted MVA rating. American Transmission Company Page 81 of 102 G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 F.3 Thermal Loading Criteria F. 3.1 Injection Violations Generation injection violations include: 1) thermal violations of the transmission elements that connect the Generator to the rest of the transmission network (outlet congestion); 2) thermal violations of the transmission elements that have a transfer distribution factor (TDF) 2 5% for NERC Category A (system intact) conditions and TDF 2 20% for NERC Category B contingencies anywhere in the studied system in relation to real power injected at the Point of Interconnection (POI) when delivered to all of MISO; or 3) thermal violations created by the loss of a transmission element connected to the generator interconnection substation. F.3.2 Operating Restriction Calculation Allowable Output = TDF F.4 Steady State Under Voltage Criteria F.4.1 Intact System, N-1 and Special Multiple Contingency Evaluation Using ACCC Under intact system conditions, the voltage magnitude of all transmission system buses with a decrease of 0.01 per unit due to the Generator must not be lower than 0.95 per unit. Under contingency conditions, the voltage magnitude of all transmission system buses with a decrease of 0.01 per unit, due to the Generator, must not be lower than 0.90 per unit. F. 4.2 N-2 Contingency Evaluation Power flow solutions must converge for a selected number of N-2 contingencies in the electrical proximity of the studied Generator. Divergence of a power flow solution indicates potential voltage collapse. A "fix" must be identified for any non-converging power flow simulation and may include generator operating restrictions. vote: Non-convergence may be due to solution settings such as switched shunt operation andlor LTC action.] F.5 Anwlar Stability Criteria Critical Clearing Time (CCT) is a period relative to the start of a fault, within which all generators in the system remain stable (synchronized). CCT is obtained from simulation. fault using the existing system facilities. MECT is dictated by the existing system facilities. In any contingency, if the computed CCT is less than the MECT plus a margin determined by ATC (1.0 cycle for studies using estimated generator data and 0.5 cycles for studies using confirmed generator data), it is considered an unstable situation and is unacceptable. Otherwise, it is considered acceptable transient stability performance. American Transmission Company Page 82 of 102 G833/4-J022/J023 Interim Operation and Impacts Re-Study Report-RO1 Longer time-domain simulations must be performed on faults cleared at the CCT to examine dynamic stability. Simulations will typically cover 20 seconds of system dynamics and machine angle oscillations must meet the damping criteria in the ATC Planning Criteria. Note that ATC stability criteria and NERC stability criteria differ on the study assumptions used for breaker failure analysis. ATC study criterion models breaker failure by modeling a three- phase fault during the primary time, reduced to SLG fault if the failed breaker is an Independent Pole Operated (IPO) breaker during delayed clearing and cleared at the end of the delayed clearing time. On the other hand, NERC study criterion assumes a single line-to-ground fault for the entire breaker failure analysis. Hence, the CCT computed from ATC stability criteria is always less than or equal to the value computed using the NERC study criteria. This report assumes ATC stability criteria unless otherwise stated. The time-domain simulations must also be reviewed for compliance with the transient and dynamic voltage standards in the ATC Planning Criteria. Voltages of all transmission system buses must recover to be at least 70% of the nominal system voltages immediately after fault removal and 80% of the nominal system voltages in 2.0 second after fault removal. American Transmission Company Page 83 of 102 G83314-J022/JO23 ~ntermj Operation and Impacts Re-Study Report-RO1 I cypress-Arcadian 345-k" line I 968 I P0intBeach-shebo~ginEnerg~Center345~ kV line 98.7 1 519.3 119.80% 1 546.61 Appendix 6: Point Beach-Sheboygan ~nerg~ 1311 CypressArcadian 345-kV line 516.2 540.5 23.37% 568.94 Center 345-kV line 1076 Point Beach-Sheboygan Energy Center 345- 498.7 CypressArcadian 345kV line 519.3 19.80% 546.61 kV line Estimated Allowable MW Output from 6834 or 6833 under SpringIFall or Winter Emergency Ratings 1. The Pre and Post MV flow were re-estimated fiom the previous interim operations study report in order to calculate new required ratings and new allowable MW output. The old valu s in the previous study report was obtained fiom Table A.5 9 New Pre MVA - old Pre MVA -L New Post MVA ,- old Post MVA + 6 MW x DF American Transmission Qompany Page 84 of 102 G83314-J022/JO23 1nte4 Operation and Impacts Re-Study Report-RO1 2. The Pre MVA flow w re-estimated fiom the previous interim operations study report in order to calculate new required ratings and new allowable MW output. The old values in e previous study report was obtained fiom Table A.5 S New Pre MVA old Pre MVA + 6 MW x DF 1 3. The Post MVA flow re-estimated fiom the previous interim operations study report in order to calculate new required ratings and new allowable MW output. The old value previous study report was fiom the case (Scenario 5 with G8331834 and all wind loo%, with 201 1 Kewaunee modeled) old Post MVA + 12 MW x DF Note: The results shown 4 the above tables are based on 50% peak load cases. American Transmission ompany Ci Page 85 of 102 


G833/4-J02ZNOW Interim Operation and Impacts Restudy Report-RO1 I I Il Open bustie during I I I I I I I I I I - I I I I I - now I KP 1 62620 1 zFE:z 1 5.W4.5 1 11 I I I I I No~.5l)cvdek I I I I I I American Transmission Company KP CCT - 5.W.O KP CCT - 5.546.0 &P,F CCT - 51V6.0 KP.F CCT - 51116.0 KP.F CCT - 5Y6.0 KP,F CCT -5516.0 KP CCT-5.016.0 KP CCT - 5.016.0 KPS CCT -5.016.0 Page 88 bf 102 KP.F CCT- 5.D16.0 KP,F CCT - 5Y6.0 KP,F M-5.56.0 A15.75B.1 tasted deariw 6rne - UV bip P (IS!+/ l.52ls, 345kV 1st 1.C&, 315kV md 1.5625) CCT-5.5B.O CCT - 5.016.0 KP CCT - 5.W.O KP,S CCT- 5.016.0 KP CCT - 5516.0 
G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Nomenclature K or KEW:  Kewaunee P or POB:  Point Beach (PI and P2)
S or SEC:  Sheboygan Energy Center F or FOX:  Fox Energy NAP:  North Appleton GVL:  Granville CYP:  Cypress ADN:  Arcadian FJT Forest Junction TH: Thilmany Point Beach-Sheboygan Energy Center 345 kV L111:
line L121: Point Beach-ForestJunction 345 kV line Q303: Point Beach-Kewaunee345 kV line L151: Point Beach-Fox Energy 345 kV line R304: Kewaunee-North Appleton 345 kV line NAPL71:  North Appleton-WernerWest 345 kV line CYP31:  CypressArcadian 345 kV line 6832: North Appleton-Fox Energy Center 345 kV line TIO: KewauneeTI0 3451138 kV transformer SEC3I:  Sheboygan Energy Center-Granville 345 kV line H: High side KWH:  KewauneeT10High side KWL:  Kewaunee TI0 Low side POBxy:  Point Beach bus tie xy Y311 Nora Appleton-Fitzgerald 345 kV line CCT: Critical Clearing Time Note: The simulated clearing times and critical clearing times (CCT) noted in Appendix B contains planning margin described in Section 3.2 American Transmission Company                      Page 50 of 102


G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Appendix I: Minimum Excitation Limits at Point Beach and Kewaunee during Interim Periods American Transmission Company Page 90 of 102 G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Minimum Excitation Limits at Point Beach and Kewaunee during Interim Periods As noted in this G833lJ022-G834lJ023 Interim Operations Re-Study Report, Point Beach and Kewaunee units need to maintain certain reactive power output in anticipation of critical contingency conditions. Reactive power output from a synchronous machine has an impact on the transient stability of the unit. Typically, when a unit produces relatively small reactive power output or absorbs reactive power from transmission system (under- excitation), the unit tends to be less stable under a fault condition. The results of the interim operation study indicate that a certain level of reactive power output (over- excitation) needs to be maintained to ensure generation stability in anticipation of critical fault conditions. This is primarily due to too many generators with few outlets out of Fox Valley area. The minimum excitation limiter, which may also be referred to as the under-excited reactive ampere limit or under-excitation limiter, settings are an effective mechanism to ensure a minimum level of unit excitation. However, limiting the amount of under- excited operation can negatively affect the ability to control system and plant voltages under lighter system load conditions where transmission line charging may result in higher system voltages. Therefore, any minimum excitation limits need to be coordinated with voltage control requirements. The "interim" solutions described in the Interim Operations Re-Study Report would be followed by the completion of the necessary Network Upgrades identified in the G833lJ022-G834lJ023 System Impact Re-Study Report, which has yet to be posted. The Network Upgrades would be the long-term solutions which ensure a wider operating envelope for the local transmission system and the interconnected generators by permitting generating unit operation at near unity or leading power factor, or at least provide a foundation to achieve the wider operating envelop through additional transmission reinforcement in the area that may be needed in the future. Transient Stability Studies To estimate minimum excitation limits (MVAR output levels), it is assumed that the stability upgrades identified for each interim period are in-service (see G833lJ022- G834lJ023 Interim Operation Re-Study Report). Various MVAR output levels at Point Beach and Kewaunee 345 kV buses were evaluated using two different generation dispatch scenarios during the three interim periods. Critical faults under system intact condition identified in the interim operation study were applied, which are: Fault on Q-303 with breaker failure at Point Beach (post-May 2010 until May 201 1 only since a series breaker is proposed to be installed by May 201 1) Fault on R-304 with breaker failure at Kewaunee (post Kewaunee bus reconfiguration project period only) American Transmission Company Page 91 of 102 G83314-J022IJO23 Interim Operation and Impacts Re-Study Report-RO1 With stabilitv upmades for each interim period in-service and based on the studv results shown in Table 1.1 through 1.4, the Point Beach and Kewaunee units would need to maintain the following minimum excitation levels to ensure synchronism of these and nearby generators: For May 2010 - May 201 1 (With Point Beach Unit #1 up~aded and with the existing Kewaunee bus confirnation) o Point Beach G1 and G2: 48 MVAR or higher per unit o Kewaunee GI: 41 MVAR or higher For May 2011 until completion of the Kewaunee bus reconfiguration proiect with both Point Beach Units #1 and #2 upgraded), o Point Beach Gl and G2: 70 MVAR or higher per unit o Kewaunee GI: 58 MVAR or higher Post completion of the Kewaunee bus reconfiguration proiect (With both Point Beach Units #1 and #2 upgraded] o Point Beach Gl and G2: 68 MVAR or higher per unit o Kewaunee GI: 49 MVAR or higher These minimum excitation limits were estimated by testing the critical system faults. Additional study for all other relevant system faults was not performed because of the following reasons: For Interim 1 period (see Table I.1), the critical faults under system intact conditions are more severe at the low generation scenario, and the estimated minimum excitation limits of Kewaunee and Point Beach units are either same or higher than their WAR outputs at the 352 kV voltage schedule where all other faults under system intact conditions were proven to be stable in the interim operation study. Therefore, additional study for all other relevant system faults under system intact conditions was not performed. For prior outage conditions, it is recommended to maintain at least 354 kV at the Point Beach and Kewaunee 345 kV buses (note: 354 kV is high-end of the preferred voltage range at Point Beach) in anticipation of critical faults. This is to ensure stable system even with faults under prior outage conditions which appear to be more severe at high generation scenario and were proven to be stable at the 352 kV voltage level with interim upgrades and operating restrictions implemented. As mentioned above, the critical faults under system intact conditions appear to be more severe at the low generation scenario according to the results of the interim operation study, and the estimated minimum excitation limits of Kewaunee and Point Beach units are higher than their MVAR outputs at the 352 kV voltage schedule of low generation scenario (see Table 2.4.1) where all other faults under system intact conditions were proven to be stable in the interim operation report. 'l'herefore, additional study for an other relevant system taults under system intact conditions was not performed. For prior outage conditions, it is also recommended to maintain at least 354 kV (high-end of the preferred voltage range at Point Beach) in anticipation of critical faults. This is to ensure stable system even with faults under prior outage condition which appear to be more severe at high generation scenario and were proven to be stable at 352 kV. American Transmission Company Page 92 of 102 G83314-J0221J023 Interim Operation and Impacts Re-Study Report-RO1 Steady State Voltage Control Studies at Minimum System Load Conditions Using a minimum load case with 40% of 2010 summer peak load condition, three scenarios were built and studied to confii if any high voltages occur at Point Beach 345 kV and Kewaunee 3451138 kV buses under various conditions. The scenarios are: Scenario 1 : Minimum load case with G834-J023 added = Scenario 2: Minimum load case with G834/J023-G833/J022 added Scenario 3: Minimum load case with Scenario 2 and with Point Beach G2 and Kewaunee G1 offline. The minimum reactive power outputs of Point Beach and Kewaunee units in each case were adjusted to match with the estimated minimum excitation limits as follows: For Scenario 1 : o Point Beach G1 and G2: 48 MVAR o Kewaunee GI: 41 MVAR For Scenario 2: o Point Beach Gl and G2: 70 MVAR o Kewaunee GI: 58 MVAR No study was performed using the minimum excitation limits of Interim 2B period since no significant impact is expected due to the Kewaunee bus reconfiguration project. For the study, the following critical contingencies were tested. System Intact Open Line-end i. Open North Appleton end of R-304 ii. Open Granville end of L-SEC3 1 iii. Open Arcadian end of L-CYP3 1 iv. Open Forest Junction end of L121 v. Open Fox River end of L15 1 N-1 or multiple contingency analyses are not performed since these conditions will lower voltages due to increased system impedances. Monitored elements are Point Beach 19 kV and 345 kV, and Kewaunee 345 kV and 138 kV bus voltages. The following criteria are assumed for the monitored elements. Point Beach 19 kV bus voltage: 95 percent to 105 percent of nominal voltage Point Beach 345 kV bus voltage: Not exceed 358 kV (high end of normal voltage range) under system intact condition. Not exceed 360 kV (slightly lower than high end of absolute voltage range) under a line end open Kewaunee 345 kV bus voltage: 95 percent to 105 percent of nominal voltage -- a **-.TI
I G83314-Jo22tJo23 Interim Ope ation andImpacts Re-study Report-Ro1 I
* Kewaunee 138 KV bus voltage: 14U KV --. 1 ana 143 KV unaer system mmct ana contingency conditions In conclusion, no high voltage conditions were found as shown in Table 1.4. Sensitivity analysis was performed by turning on some of the capacitor banks in the area such as New Holstein, Glenview, Howard and Shoto. As a result, high voltage at Kewaunee 138 kV bus is identified with the Granville end of L-SEC3 1 open. However, the voltage issue American Transmission Company Page 93 of 102 G83314-J022IJ023 Interim Operation and Impacts Re-Study Report-RO1 can be addressed by remedial actions such as turning off some of the capacitor banks in the area as described in Table 1.5. American Transmission Company Page 94 of 102 G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table 1.1. Minimum Excitation Limit Study Results for Interim 1 (May 2010 - May 2011) / Interim 1 (KV and MVAR level at POB and KEW for stable system under critical faults) I Critical Fault under Intact (tested clearing times) Llll BF @ POB (3.5/10.0/4.5) Ll5l BF @ POB (3.5/10.0/4.5) Thus, minimum excitation limits are: POB Gl: 47.4 POB G2: 47.4 KEW GI: 40.9 High Gen scenario' Q303 BF @ POB (3.5/10.0/6.5) Table 1.2. Minimum Excitation Limit Study Results for Interim 2A (May 2011 until Kewaunee Reconfiguration Complete) I 350 kV or higher (POB Gl : 43.4 POB G2: 43.4 KEW GI: 40.9) 348 kV or higher (POB Gl: 12.0 POB G2: 12.0 KEW GI : 20.1) I Interim 2A (KV level at POB and KEW for stable system under critical faults) I Low Gen scenario' 35 1 kV or higher (POB GI: 42.7 POB G2: 42.7 KEW Gl: 26.1) 349 kV or higher (POB Gl: 33.3 POB G2: 33.3 KEW Gl: 17.5) 350 kV or higher (POB G1: 43.4 POB G2: 43.4 KEW GI: 40.9) Critical Fault under Intact High Gen scenario' (tested clearing times) Llll BF @ 35 1 kV or higher POB (POB Gl: 69.6 POB G2: 69.6 (3'519'014'5) KEW GI: 57.5) Ll5l BF @ 350 kV or higher POB (POB Gl: 53.7 POB G2: 53.7 (3'5'Y'5'4'5) KEW GI: 46.9) Comment 352 kV or higher (POB G1: 47.4 POB G2: 47.4 KEW Gl : 30.4) Low Gen scenario' 352 kV or higher (POB Gl: 60.1 POB G2: 60.1 KEW Gl: 35.8) 352 kV or higher (POB Gl: 60.1 POB G2: 60.1 KEW Gl: 35.8) Comment Thus, minimum excitation limits are: POB Gl: 69.6 POB G2: 69.6 KEW GI: 57.5 American Transmission Company Page 95 of 102 G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table 1.3. Minimum Excitation Limit Study Results for Interim 2B (Post Kewaunee Reconfiguration) I Interim 2B (KV level at POB and KEW for stable system under critical faults) I I Critical Fault I I I under Intact 1 (tested clearing I High Gen scenario1 I Low Gen scenario1 / I times) - I I I Comment L111 BF @ POB (3+5".014.5) Q303 BF @ POB Ll5l BF @ POB (3.519.514.51 POB G2: 67.2 KEW GI: 48.9 35 1 kV or higher (POB Gl: 67.2 POB G2: 67.2 KEW ~1: 48.9) 352 kV or higher (POB GI: 58.6 POB G2: 58.6 KEW Gl: 27.3) 349 kV or higher (POB Gl: 35.6 POB G2: 35.6 KEW G1 27.1) 1. Approximate MVAR change at Point Beach and Kewaunee: High generation scenario: o 1kV change at Point Beach for every 16 MVAR change o 1 kV change at Kewaunee for every 1 1 MVAR change Low generation scenario: o 1kV change at Point Beach for every 5 MVAR change o 1kV change at Kewaunee for every 4.5 MVAR change R304 BF @ KEW (3'519'5/4'5) American Transmission Company POB GI: 67.2 3 52 kV or higher (POB GI: 58.6 POB G2: 58.6 KEW : 27.3) Page 96 of 102 Thus, minimum excitation limits are: 348 kV or higher (POB G1: 20.1 POB G2: 20.1 KEW GI: 16.4) 3 5 1 kV or higher (POB GI: 53.4 POB G2: 53.4 KEW Gl: 22.9) 
            --
Tab1 B.1- Stability Results for Faults Clearing in Primary Time under Intact System Conditions Tntorim 7 /with G8?4/11073                        -
                                                              - - . - w i t h ~- r -i . r t i Kcrwnlinc!~?
n- ~          .ruh.rtntinn)
Intact System Fault Cleared in Primary Time - Interim Period 1 (May 2010-April 2011)                                       I Faulted End Breakers Remote Location Remote End Breakers I
Event Notes I Simulated I
Clearing*
I                I I High Generation I Low Generation I 111        SEC          1-2.16              NOSPS          4.514.5 121,123        FJT          1-2,23                              4.514.5 151        FOX          2-3.3-1             NOSPS          4.514.5 Q-303        KEW      Q-303,1099,2450        KEW SPS In        4.516.5 Q-303,1099,2450    PO0            Q-303            KEW SPS In        6.514.5 R-304,3451      NAP            R-304                              6.516.5 2-3,34        POB             151                                4.514.5 1 1-2,6-1       NAP    243,344,45467-6                            4.514.5 4-5,5-6       FJT        5-6,7-1                               4.514.5 1-2,16        POB             Ill                                4.514.5 1-2,3-6       GVL          L-SEC31                              4.516.5 1-2,5-6      ADN          L-CYP31                              4.514.5 Q-303,1099,3450    KWL American Transmission compbY                  Page 51 of 102


683314-J022IJ023 Interim Operation and Impacts Re-Study Report-RO1 American Transmission Company Page 98 of 102 683314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table 1.5. Voltages at Point Beach and Kewaunee Under System Intact and Contingencies Bus I Open North Appleton end Open Granville end of Open Forest Junction Open Fox River end of of Kewaunee-North I Granville-Shebovgan end of Point Beach- I Point Beach-Fox River American Transmission Company Page 99 of 102 
G83314-J022lJO23 Interim ~Aerationand Impacts Re-Study Report-RO1 1    Interim 2A (with G834/J023 and G833/J022.with existing Kewau tee substation)
@33&302%J0;53 En- Page 100 of 102 G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Appendix J: Unit Restriction Due to Stability under Prior Outage Conditions in Table ES-3 during One of Point Beach Units offline American Transmission Company Page 101 of 102 G833/4-.JO22N023 Infer& Operation and Impacts Re-Study Report-RO1 existing Kewa~ nee) L121 at POB POB Bus tie 2-3 4.514.5 OK R304 at KEW L121 5.514.5 OK OK OK OK R304 at KEW L151 5.514.5 OK OK OK OK 6832 at FOX R-304 4.514.5 OK OK OK OK Interim 2A (With G83314J022r3, With R-304 at KEW 6832 5.514.5 OK OK OK OK existing Kewau lee) R-304 at KEW LSEC31 5.514.5 OK OK OK OK LIZ1 at POB POB Bus tie 2-3 4.514.5 OK OK R-304 at KEW POB Bus tie 4-5 5.514.5 OK OK OK OK - - Interim 28 R-304 at KEW 6832 4.514.5 OK OK OK OK (Wi G833/4J022/3, With - new Kewaune?) L121 at POB POB Bus tie 2-3 45/45 OK OK 1 of Point Beach Bus tie 2-3 followed by L121 fault isolates Point Beach GI to the remaining line L111. Therefore, taking the Point Beach Bus tie 2-3 out of senrice g outage window does not eliminate the POB GI stability issue for L121 fault under Point Beach Bus tie 23 out of se~ce. Thus, follow the operating restriction for the G833/4J022/3 Interim Operation Re-study Report American Transmission C mpany 4 Page 102 of 102}}
                                                                      -
Intact System Fault Cleared in Primary Time Interim Period 2A ( ~ i r i l 2 0 1 1and beyond, with existing Kewaunee)        I Simulated I iigh Generation 1      Interim 2B (with G834/J023 and G833/J022,with new Kewmrnee substation)
Element    Fault      Faulted End    Remote      Remote End              Event  Simulated File      Faulted  Location FltPOBSEC      L111    POB            111        SEC          1-2,16              NOSPS    4.514.5 FltPOBFJT      L121    POB          121,123      FJT          1-2,2-3 FltPOBFOX      L151    POB            151        FOX          2-3,3-4              NOSPS    4.514.5 No FltPOBKEW        Q-303    POB          4303        KEW      Q-303 New 1 and 2          SPSs    4.514.5 No American Transmission ~ o m $ a n ~                Page 52 of 102                                              07/14/2009
 
G833/4-J022/JO23 Interim 0~4rationand Impacts Re-Study Report-RO1 Table B.2- Stabilify Results for Double Circuit Single Line-to-Ground Faults Cleared in Primary Time under Intact System Conditions Interim 1 (with G834/J023,with existing Kewaunee substation) 1                    I          I                              I                  I            I                                    I                I                Interim Pel File Event DC3-111-971K51-I I L1l1        -
Fyik BeachSheboygan Fault # I 38.5% frorn POB Acceptable 5.515.5 Fault
                                                                                                                      #2 971K51 - Forest Junction-Howard's Fault R Location 33.g9/0from NT Simulated Clearingtime 6.516.5 (May 2010-Apr mm 2011) 345 kV                                                        Grove 138 kV L1ll -Point                                                                  971K51 -Forest Junction-Howard's    6.3% from HOG      6.516.5 DC3-Ill-971K51-2                                              16.3% from SEC      5.515.5 345 kV                                                        Grove 138 kV DC3-111-HOLG21-1
                                    -
L l 1I Point BeachSheboygan                      SEC          5.515,5 HOGL21 -Howard's Grove-Holland      76.9% from HOL      6.516.5 345 kV                                                            138 kV L l l l -Point Beach-Sheboygan                                              HOGL21- Howard's GroveHolland      314X from HOG      6.516.5 DC3-111-HOLG21-2                                            ' ,5.70mfrom SEC      5.515.5 345 kV                                                            138 kV L121.R. Beach-Forest Junction                                                971K51- Forest Junction-Howard's          FJT          6.516.5 DC3-121-971K51-1                                                    FJT          5.515.5 345 kV                                                        Grove 138 kV L121.R Beach-Forest Junction                                                971K51- Forest Junction-Howard's                        6.516.5 DC3-121-971K51-2                                              42.3% from FJT      5.515.5                                          33.9% from FJT 345kV                                                          Grove 138 kV L-SE(31- Sheboygan-Granville                      GVL          7.517.5      3431 - Granville-Saukville345 kV        GVL            7.517.5 DC3-SEC31-3431-1 345 kV L-SEC31-Sheb0ygan-Granvi11e                26.7% from GVL      7.517.5      3431 - Granville-Saukville345 kV  25.3% from SAU      7.517.5 DC3-SEC31-3431-2 345 kV LSEC31Sheb0ygan-Granvi'le                  43.5% from GVL      7.517.5        8231 - Saukville-Barton138 kV    36.4% from BRT      7.517.5 DC3SEC31-8231-1 345 kV DC3-SEC31-8231-2 L-SE231Sheb0~!3an-Granville 345 kV 48.3% frorn GVL    7.517.5            -
8231 Saukville-Barton138 kV      36.4% from SAU      7.517.5 L- CYP3l- Cypress-Arcadian                32.00/0from ADN    5.515.5    2642 - Saukville-Gemantown 138 kV    34.2% from SAU      7.517.5 DC3-9932-2642-1 345 kV CYP31 -                              16.6% from ADN      5.515.5          -
2642 Saukville-Gemantown 138 kV          GER            7.517.5 DC~-9932-2642-2 345 kV L- CyP31 -                                10.8% from ADN      5.55.5    2661 - Germantown-Bark River 138 kV  31.5% from GER      8.518.5 DC3-9932-2661-1 345 kV L- CyP31 - Cypress-Arcadian              16.6% from ADN      5.515.5    2661 - Germantown-BarkRiver 138 kV        GER            8.518.5 DC3-9932-2661-2 345 kV DC3-9932-9911-1
                                              -
CyP31 Cypress-Arcadian                10.8% from ADN      5.515.5      9911 - Granville-Arcadian 345 kV  45.4% from GVL      7.517.5 345 kV DC3-9932-9911-2 L- CyP31- Cypress-Arcadian                      ADN          5.515.5      9911 - Granville-Arcadian 345 kV        ADN            7.517.5 345 kV American Transmission comP/any                                    Page 53 of 102
 
G83314-J022lJ023Interim opetiation and Impacts Re-Study Report-RO1 Interim 2A (with G834/J023 and G833/J022,with existing Kewaunee substation)
Event                        Fault                Fault #1  Acceptable                  Fault                  Fauit#2 File                          #1                  Location      CCT"                      #2                    Location
                                -
L111 Point BeachSheboygan                                  971K51- Forest Junction-Howard's Dm-111-971K51-I                    345 kV            38.5% from POB  5.515.5            Grove 138 kV            33.9% from FJT  6.516.5 L l l I- Point BeachSheboygan                              971K51- Forest Junction-Howard's DC3-111-971K51-2                  345 kV            16.3% from SEC  5.515.5            Gmve 138 kV              6.3% from HOG  6.516.5  OK OK
                                -
L l l l Point Beach-Sheboygan                              HOGL21- Howard's GroveHolland DC3-111-HOLG21-1                  345 kV                SEC        5.515.5                  138 kV            76.9% from HOL  6.516.5 L l l l - Point BeachSheboygan                              HOGL21 - Howard's Grove-Holland DC3-111-HOLG21-2                  345 kV            15.7% from SEC  5.515.5                  138 kV            31.4% from HOG  6.516.5 -
L121-fk Beach-Forest Junction                                971K51- Forest Junction-Howard's DC3-121-971K51-1                  345 kV                  FJT        5.515.5            Grove 138 kV                  FJT      6.516.5 L121-%. Beach-Forest Jundon                                  97101 - Forest Junction-Howard's DC3-121-971K51-2                  345 kV            42.3% from FJT  5.515.5            Grove 138 kV            33.9% from FJT  6.516.5 L-SECSl - Sheboygan-Granville DCSEC31-3431-1                    345 kV                GVL        7.5R.5
                                                                                          -
3431 Granvile-Saukville 345 kV GVL        7.517.5 LSEI.>31Sheboygan-Granville 3431 - GranvilleSaukville345 kV DC3SEC31-3431-2                    345 kV            26.7% from GVL  7.517.5                                    25.3X from SAU  7.517.5 DC3-SEC31-8231-1 LSEC>31Sheboygan-Granville 345 kV            43.5% from GVL  7.517.5
                                                                                            -
8231 Saukville-Barton138 kV 36.4% from BRT  7.517.5 L-SEC>31-Sheboygan-Granville 8231 - Saukville-Barton138 kV DC3SEC31-8231-2                    345 kV            48.3% from GVL  7.5R.5                                      36.4% from SAU  7.517.5 L- C\rbP31- Cypress-Arcadian                                  -
2642 Saukville-Germantown 138 kV DC3-9932-2642-1                  345 kV            32.0% from ADN  5.515.5                                      34,2% from SAU  7.5175 L- CYf"fJ1- Cypress-Arcadian 2642 - Saukville-Germantown 138 kV DC3-9932-2642-2                  345 kV            16.6% from ADN  5.515.5                                            GER        7.517.5
                                    -
L- CtkP31 Cypress-Arcadian                                  2661 - Germantown-BarkRiver 138 DC3-9932-2661-1                  345 kV            10.8% from ADN  5.515.5                    kV              31.5% from GER  8.518.5 L- C"P31- Cypress4wdian                                    2661 - Germantown-Bark River 138 DC3-9932-2661-2                  345 kV            16.6% from ADN  5.515.5                    kV                    GER        8.518.5
                                    -
L- C"P31 Cypress-Arcadian 9911 - Granville-Arcadian 345 kV DC3-9932-9911-1                  345 kV            10.8% from ADN  5.515.5                                      45.40/0from GVL  7.517.5        I
                                    -
L- Cbp31 Cypress-Arcadian                                    9911 - Granville-Arcadian345 kV I
DC3-9932-9911-2                  345 kV                  ADN        5.515.5                                            ADN      -7.5R.5 American Transmission comPby                          Page 54 of 102
 
G83314-J022lJO23 ~nterim    operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation)
I I
Event      1 I        I Fault I
I    Fault # I I        I Fault I
I      Fault #2 I            Interim Period 2B (May 2011 -), WI new Ke File                        #I                  Location                                  #2                      Location High Gen    I  Low Gen I L111- Point BeachSheboygan                                  971K51 -Forest Junction-Howard's DC3-111-971K51-1                345 kV            38.5% from POB  5.515.5              Grove 138 kV              33.9% from FJT  6.516.5 L111.. Point BeachSheboygan                                  971K51- Forest Junction-Howard's DC3-111-971K51-2                345 kV            16.3% from SEC  5.515.5              Grove 138 kV              6.3% from HOG    6.516.5 L l II-1 Point BeachSheboygan                                HOGL21-Howard's GroveHolland                                                            1 DC3-111-HOLG21-1                345 kV                  SEC        5.515.5                  138 kV                76.9% from HOL    6.516.5 L l I1 . Point BeachSheboygan                                HOGL21- Howard's Gmve-Holland DC3-111MOLG21-2                345 kV            15.7% from SEC  5.515.5                  138 kV                31.4% from HOG    6.516.5                          I L121-~3.Beach-Forest Junction                                971K51- Forest Junction-Howard's I
DC3-121-971K51-1                345 kV                  FJT        5.515.5              Grove 138 kV                    FJT        6.516.5 L121-3. Beach-Forest Junction                                971K51- Forest Junction-Howard's DC3-121-971K51-2                345 kV            42.3% from FJT  5.515.5              Grove 138 kV              33.9% from FJT  6.516.5 LSEC31- Sheboygan-Granville                                  3431 - GranvilleSaukville345 kV DC3SEC31-3431-1                345 kV                  GVL        7.5R.5                                                GVL        7.5R.5 L-SEC31-Sheboygan-Granville                                  3431 - GranvilleSaukville345 kV DC3SEC31-3431-2                345 kV            26.7% from GVL  7.5R.5                                          25,3% from SAU    7.5R.5 DC3SEC31-8231-1 L-SEC31Sheboygan-Granville 345 kV            43.5% from GVL  7.5R.5
                                                                                          -
8231 Saukhile-Barton 138 kV      36.4% from BRT    7.517.5 LSEC31Sheboygan-Granville                                      8231 - Saukville-Barton 138 kV    36.4% from SAU    7.5R.5 DC3SEC31-8231-2                345 kV            48.3% from GVL  7.517.5 L- C"P31- Cypress-Arcadian                                2642 - Saukville-Germantown 138 kV DC3-9932-2642-1                345kV            32.0% from ADN  5.515.5                                        34.2Kfrom SAU    7.5R.5 L- C'P31- Cypress-Arcadian                                2642 - Saukville-Germantown 138 kV DC3-9932-2642-2                345 kV            16.6% from ADN  5.515.5                                              GER        7.5R.5 L- C\?31- Cypress-Arcadian                                2661 - Germantown-Bark River 138 kV DC3-9932-2661-1                345 k v          10.8% from ADN  5.515.5                                        31.5% from GER    8.518.5 L- C\?31 - Cypress-Arcadian                              2661 - Germantown-Bark River 138 kV DC3-9932-2661-2                345 kV            16.6% from ADN  5.515.5                                                GER        8.518.5 L- C\'P31 - Cypress-Arcadian                                9911 - Granville-Arcadian345 kV DC3-9932-99111                  345 kV            10.8% from ADN  5.515.5                                        45.4% from GVL    7.5R.5 L- C'931- Cypress-Arcadian                                  9911 - Granville-Arcadian345 kV DC3-9932-9911-2                345 kV                ADN        5.515.5                                              ADN        7.517.5 American Transmission c~mPany                          Page 55 of 102
 
G83314-J022/JO23 Interim Operation and Impacts Re-Study Report-RO1 Table B.3- Stl lbility Results for 3-Phase Faults Cleared in Primary Time under Prior Outage Condition Units Trpping Note: Among various contingencies evaluated, only faults with stability issues are listed in Table B.3.
Interim 1 (with G834/J023, with existing Kewaunee substation)
Primary Clearing Time, Prior Outage: 6832 (FOX-NAP, 38894-39556), (POB PSSs In Service) Existing KEW Sub Event            Elemen        Fault          Faulted End        Remote          Remote End                Event              Simulated      High Generation  II  Low Generation Faulted    Location          Breakers          Location        Breakers                  Notes              Clearing*
I*** Stable FltKEWNAP          I R-304 at 5.514.5 with G1 res Primary Clearing Time, Prior Outage: SEC31 (SEC-GVL, 3986538870), (POB PSSs In Service) Existing KEW Sub Event          Element      Fault          Faulted End        Remote          Remote End                    Event                Simulated      High Generation      Low Generation Faulted    Location          Breakers        Location          Breakers                    Notes KEW            R-304.3451            NAP              R-304                                            6.516.5
** Stable at 5.514.5 -replace R-!04 breaker at NAP.4.5 is MECT for R304 fault at KEW. Existing clearing time at faulted end is 4.5 cycles without margill Primary Clearing Time, Prior Outage: PO0 2-3 (POB-B23,3889&39211), (PO0 PSSs In Service) Existing KEW Sub Event          Element        Fault        Faulted End      Remote              Remote End                Event          Simulated          High Generation          Low Generation acation        Breakers        Location            Breakers
* For stability, G1 needs to be re rtricted to 580 MW gross
** For stability, Gl needs to be I estricted to 620 M W gross American Transmission C                                            Page 56 of 102
 
G83314-J022lJO23 Inte ' Operation and Impacts Re-Study Report-RO1 Interim 2A (with G834/J023 and G833/J022, with existing Kewaunee substation)
Primary ClearingTime, Prior Outage: L l l l (POB-SEC, 39433-39865), 'POB PSSs In Sewice) Existing KEW Sub Event            Element        Fault        Faulted End        Remote            Remote End                    Event              Simulated High Generation        Low Generation Fle              Faulted      Location        Breakers          Location          Breakers                      Notes              Clearing'            Base                Base FIWWNAP              R-304        KEW          R-304,3451          NAP                R-304                                            6.516.5
"* Stable at 5.514.5, Replace R-304 breakerat North Appleton. Note: MECT of R304 at Kew is 4.5 Primary ClearingTime, Prior Outage: L121 (POB-FJT, 38898-39304), (POB PSSs In Service) Existing KEW Sub Event          Element        Fault          Faulted End        Remote              Remote End                  Event        Simulated        High Generation      Low Generation File          Faulted      Location          Breakers          Location            Breakers                  Notes        Clearing*              Base                Base I    FltKEWNAP        I  R-304    I  KEW    I      R-304,3451        I NAP I                  R-304            I                  1 6.516.5 A Stable at 5.014.5 or Stable at 5.514 5 with G2 reduced to 620 MW-replace R304 breaker at NAP. Existing clearing time at faulted end is 4.5 cycle^      cy out margin Primary Clearing Time, Prior Outage: L151(POB-FJT, 38898-39304), (POB PSSs In Sewice) Existing KEW Sub Event          Element        Fault          Faulted End        Remote              Remote End                  Event        Simulated        High Generation    I I
Low Generation File          Faulted      Location          Breakers          Location            Breakers Note: Without G2 reduction, Vsag uAl trip P with 5.514.5 (PI 1.513sfor 19KV, P2 1.521sfor I9KV , BIB5 1st 1.083s, BIB5 2nd 1.575s). Thus, if time delay can be readjustedto avoid violation, only thing to be done is replacing R-304 breaker at NAP Primary ClearingTime, Prior Outage: R-304(KEW-NAP, 39630-39359), (POB PSSs In Sewice) Existing KEW Sub Event        1 Element 1      Fault  1      Faulted End        Remote              Remote End                  Event      I Simulated I  I High Generation    I I
Low Generation File        I  Faulted    I lrocation I      Breakers        ( ~ocation  I          Breakers                  Notes      I  Clearing* I FltFOXNAP        1  L6832    1    FOX    I        1-2,6-1        1  NAP    1    34-3,344,454.67-6        1                  1  4.5145
* Stable at 4.014.5 OR Stable at 4.5'4.5 with G2 reducedto 600 MW gmss. At 4.514.5 with G2 at 620 MW, 345 kV 2nd criteria is violated: 81: 1.583s and 82: 1.583s.
Primary ClearingTime, Prior Outage: 6832 (FOX-NAP, 38894-39556), (POB PSSs In Sewice) Existing KEW Sub Event            Element        Fault        Faulted End        Remote          Remote End                    Event            Simulated      High Generation    Low Generation File            Faulted      Location          Breakers        Location            Breakers                    Notes            Clearing*            Base                Base FIKEWNAP          I  R-304    1  KEW    1    R-304,3451      I  NAP    I          R-304                                      ( 6.516.5 FLTKEWXFH2ROl          I  TI0      I  KWH    1  Q-303,1099,3450    1  KWL    I      1066E, 1066W        I  Open Q-303 at KEW      1  6.518.5
"*Stable at 6.018.5 with G2 reduced to 580 MW gmss. 5.0 cyde is the existing dearing time at the high side of TI0 transformer.
Stable at 5.514.5 with G2 at 580 MW (replace R-304 breaker at NAP and reduce G2 to 580 MW gross). Existing clearing time at faulted end is 4.5 cycles without margin AM Stable at 5.514.5 with both GI a11d 6 2 at 540 MW (replace R-304 breaker at NAP and reduce both GI and G2 to 540 MW). Existing clearing time at faulted end is 4.5 cycles without margin American Transmission Gmpany                                          Page 57 of 102
 
G83314-J022/J023 ~nterim                  erati ti on and Impacts Re-Study Report-RO1 Primary ClearingTime, Prior Outage: SEC31 (SEGGVL, 398638870), (POB PSSs In Service) Existing KEW Sub Event            Element        Fault        Faulted End        Remote            Remote End                        Event                  Simulated High Generation        Low Generation File            Faulted      Location        Breakers          Location          Breakers                          Notes                  Clearine          Base              Base FltKEWNAP              R-304          KEW          R-304,3451            NAP                R-304                                                  6.516.5 FLTKEWXFHPROI          I  TI0          KWH    1  Q-303,1099,3450    1  KWL    I      1066E, 1066W          I      Open Q-303 at KEW          1  6.518.5 A Stable at 6.018.5 with G2 at 620 (02 reduction to 620 gross). 5.0 cycle without margin is the existing clearing time at the high side of TI0 transformer.
-
Stable at 5.518.5 or Stable at 6.018.5 with G2 at 580 MW (62 reductionto 580 gross). 5.0 cycle without margin is the existing clearing time at the high side of TI0 transformer.
*Stable at 5.514.5 with G2 580 MW - Replace R-304 breaker at NAP and 6 2 at 580 MW gross. Existing clearing time at faulted end is 4.5 cycles without margin Stable at 5.514.5 with G2 at 620 f#W gross. Existing clearing time at faulted end is 4.5 cycles without margin 1
Primary ClearingTime, Prior Outage: POB 1-2 (POB-Bl2,39433-38898), (POB PSSs In Service) Existing KEW Sub Event          Element          Fault        Faulted End          Remote            Remote End                      Event          Simulated          High Generation  I  Low Generation I      Base File          Faulted Lpcation                Breakers          Location            Breakers                      Notes          Clearing*    -
FIWWNAP              R-304          KEW          R-304,3451            NAP                  R-304
"'Stable at 5.514.5. Replace R-304 ~reakerat NAP. Existing clearing time at faulted end is 4.5 cycles without margin
-
Primary ClearingTime, Prior Outage: POB 2-3 (POB-B23,38898-39211), (POB PSSs In Service) Existing KEW Sub Event          Element        Pault        Faulted End      Remote            Remote End                        Event            Simulated          High Generation    I  Low Generation File          Faulted      Loption          Breakers      Location              Breakers                        Notes            Clearing'                Rscn                  Rscn FltPOBFJT          L121          YOB            121,123          FJT                  1-2,2-3                                          4.514.5
* For stabili, GI needs to be resbi ed to 580 MW gmss I
Primary ClearingTime, Prior Outage: POB 4-5 (POB-B45,38900-38901), (POB PSSs In Senrice) Existing KEW Sub Event          Element          Fault        Faulted End          Remote            Remote End                      Event          Simulated          High Generation      Low Generation Ae            Faulted      Lpcation            Breakers          Location            Breakers                      Notes          Clearing*              Base                Base FltKEWNAP            R-304          KEW          R304,3451            NAP                  R-304                                        6.516.5
"'Stable at 5.514.5 with G2 at 620 k JV (replace R-304 breaker at NAP and reduce G2 to 620 MW). Existing clearing time at faulted end is 4.5 cycles without margin American Transmission chmPany                                          Page 58 of 102
 
G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation)
Primary ClearingTime, Prior Outage: 6832 (FOX-NAP, 38894-39556), (POB PSSs In Service) New KEW Sub Event          Element        Fault              Faulted End        Remote            Remote End              Event    Simulated    High Generation  Low Generation
                                      )cation            Breakers        Location            Breakers              Notes    Clearing*        Base            Base I  FltKEWNAP        I  R-304  1    KEW                R-304,3451          NAP                R-304                            4.516.5
'Stable at 4.514.5 with G2 restricted to 600 MW gmss (G2 restriction 600 MW gross with R-304 breaker at NAP replaced)
Primary Clearing Time, Prior Outage: POB 2-3 (POBB23,38898-39211!, (POB PSSs In Sewice) New KEW Sub Event          Element        Fault        Faulted End    Remote              Remote End                Event    Simulated    High Generation  Low Generation File          Faulted      acation          Breakers      Location              Breakers                Notes    Clearing*          Base              Base POB            121,123        FJT                1-2,23                            4.514.5 To be stable at 4.514.5, GI needs 1 J be restricted to 580 MW gmss "To be stable at 4.514.5, GI needs to be restricted to 620 MW gross American Transmission C                                              Page 59 of 102
 
G83314-J022tJ023 Interim Operation d d Impacts Re-Study Report-RO1 Table B.
1 - Stability Resultsfor 3-Phase Faults Cleared in Delayed (Breaker Failure) Time under Intact Conditions, Units Tripping Interim I (with G834/J023, with existing Kewaunee substation) re Events - lnter~mPer~od1 (May 2010-Aprll 2011)              I American Transmission Company      1          Page 60 of 102
 
Page 61 of 102 G833/4-JO22/JO23 Interim Operation                    Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation)
I        Event          I Element        I                                                  Event              I  Simulated I      High Gen  I        LOW tien I
I        File          1    Faulted    I  I    I 1
BFIFOXPOBZ        I      L151      I    FOX BFIFOXNAR        1    L6832      1    FOX 1    BFIFOWJT;!        1    971171      1    FOX BFlSECPOBl        I      Llll      I    SEC BFISECGVLl        I    LSEC31      I    SEC BFICYPADN        I    LGYP~I      I    cn BFICYPFJT
      -  .            1I    971L51      1I    CYI
'Relay upgradesor lnstalllng a series breaker desa !din Section 1.1 will address the issue.
" Relav uoarades described in Section 1.1 wlll addn ;the issue ad el;ibrades described in Section 1.Iwill add, she issue American Transmission Company                                      Page 62 of 102
 
G833/4-J022IJ023Interim Operation and Impacts Re-Study Report-RO1 Table B.5- Stability Resultsfor Point Beach Bus Single Line-to-Ground Faults Cleared in Delayed Time under Intact Conditions Kewaunee substation)
Fault                                            i-        Interim 1 Location            Element tripped Clearing    1              I              I POB Bus 1          POBSEC              4.75124.5 POB BUS1          POB Bus 1-2          4,75112.5 2A wl E x ~ s t ~ nKEW a
Fault              Failure        Simulated Location          Element          Clearing
(    tripped    1 POB Bus I      I  POBSEC        1  4.75124.5 POB Bus 1      I POB Bus 1-2 1      4.75112.5 POB Bus 2      I POB Bus 2-1 1      4,75112.5 POB Bus 2      I POB Bus 2-3 1      4.75112.5 POB Bus 3      I POB Bus 3-2    (  4.75112.5 POB Bus 3      (  POB-KEW      1  4,75124.5 POB Bus 3 POB Bus 4 POB Bus 5        I POB BUs5-4 ( 4.751128 POB Bus 5      I  POB-FOX      1 4 . 7 ~ ~ 5
** Stable at 4,75112.0.As described in Section 1.1, Change Relay senlug (w~mnoutareaKerral~urerelay lcpraccucur, LUL rarrruo ur I oint Beach Bus Tie 2-3 to no more than 11 cycle total breaker failure clearing time for bus faults American Transmission Company                                    Page 63 of 102
 
G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation) 1        ~oGion      I Elementhipped I Clearing 1  Ul-h pal I -.., can I          Bus 1O    I PoB-sEc 1 4.75124.5 1                B POB Bus 1 POB Bus 2    I  POB Bus2-1  I  ~ 7 5 1 153 POB Bus 2        POB Bus 2-3    4.75112.5 POB Bus 3        POB Bus 3-2    4.75112.5 POB Bus 3        POB-KEW        4.75112.5 POB Bus 3    I  POB Bus 3-4  1  4.75112.5 POB Bus 4    I  POB Bus 4-3  1  4.75112.5 POB Bus 4    I  POB BUS 4-5  1  4.75112.5 POB Bus 5 POB Bus 5 American Transmission Company                  Page 64 of 102
 
G83314-J022/5023 Interim Operation and Impacts Re-Study Report-RO1 Table B.6- Stability Results for GSU Single Line-to-Ground Faults Cleared in Delayed Time under Intact Conditions, Units Tripping Interim 1 (with G834/J023, with existing Kewaunee substation) w' 1            I            1 POB GSU BF Faults Breaker Fault        Failure      Simulated Location      Element        Clearing Interim 2A (with G834/J023 and G833/J022, I            I POB GSU BF Faults Breaker Fault          Failure      Simulated Location        Element        Clearing Interim 2B (with G834/J023 and G833/JO 1              1            1 POB GSU BF Faults Breaker Fault        Failure      Simulated Location      Element        Clearing American Transmission Company                        Page 65 of 102
 
G833/4-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table B. 7- Stability Results for Auxiliary Transformer High Side Single Line-to-Ground Faults Cleared in Delayed Time under Intact Conditions, Units Tripping InterimI 1 (with G834/J023, with existing I                    I      Kewaunee substation)
Faulted Interim 1 I
Element              Element Tripped I
POB-SEC @
POB AUXl HS                    SFC Faulted Failure Element POB AUXl HS            I    POB Bus2" I
POB AUX2 HS            I POB Bus4"'
                      -The Stability Model Time Step is 0.25 cycles, so a 13.3 cycle fault actually clears in 13.5 cycles.
                                  "- POB-Forest Junction 345 kV line Tri~s.POB Generator 1 is Isolated.
                                                          -
                                                    "* POB ene era to; 2 'is isolated Interim 2A (with G834/J023 and G833/J02
                                        -taulreo
                                              .. .                Breaker Element I      Failure POB-SEC @
POB AUXl HS POB AUX2 HS Breaker Faulted Element Failure Element Tripped
                                                                                    -  A 'a- -&
POB AUXl HS            I  POBBus2"        I        OK        I      _..
POB AUX2 HS            I  POB Bus4"'      1        OK        I      OK
                      * -The Stability Model Time Step is 0.25 cycles, so a 13.3 cycle fault actually clears in 13.5 cycles.
                                      -
                                  " POB-Forest Junction 345 kV line Trips, POB Generator 1 is Isolated.
                                                          -
                                                      "* POB Generator 2 is isolated
                                                                                      "'                          ee substation)
Interim 2B (with G834/J023 and G833/J02L" Breaker Faulted                Failure Element I
POB-FOX @
POB AUX2 HS                    FOX Breaker Faulted Failure Element              Element Tripped      5.1113.3'          5.1113.3' m      m    s
                        -The Stability ModelTime Step is 0.25 cycles, so a 13.3 cycle fault actually clears in 13.5 cycles.
                                      - POB-Forest unction 345-kV line Trips, POB Generator 1 is Isolated.
                                                            -
                                                      "** POB Generator 2 is isolated American Transmission Company                                Page 66 of 102
 
G83314-J022lJ023 ~nterimlo~eration and Impacts Re-Study Report-RO1 Table B.8- Stability R      for GSU Three Phase 345 kVFaults Cleared in Primary (5.5 cycles, including I cycle margia) Time under Intact and Prior Outage Conditions, Units Tripping Interim 1 (with G834/J023,with existing Kewaunee substation)
Interim 1                                              Interim 1 American Transmission c/omPany              Page 67 of 102
 
G833/4-J022/J023 1 n t e 4 Operation and Impacts Re-Study Report-RO1 Interim 2A (with G834/J023 and G833/J022,with existing Kewaunee substation)
American Transmission dompany                    Page 68 of 102
 
G833/4-J022IJ023            Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022,with new Kewaunee substation) 5.5 cyles di-cycle margin).
American Transmission C/ompany                    Page 69 of 102
 
G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Table B.9- Stability Resultsfor Auxiliary Transformer High Side 3-Phase Faults Cleared in Primary Time (6.1 cycles, including 1 cycle margin) under Intact and Prior Outage Conditions InterimI 1 (with G834/J023, with existing Kewaunee substation)
I                                  I I
H~ighGeneratian-. Low Generation
                                                                                          '
Interim 1    '  I&<
5.75B.1
                                                                    --
                                                                            '    5.75 "SECGens Isolated 7                                                    Low Generation  I Prior Outage I                        - ..-,- .
Interim 1 "POB GEN 2 Isolated American Transmission Company                      Page 70 of 102
 
G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Prior I-Interim 2A (with G834/J023 and G833/J022, with existing Kewaunee substation)
I                              Uinh Canardinn
                                                                -
Inlerlm 2A wl exlstlng KEW I    I nw Generation lnlerlm 2A wl ex~sllng I
Fault                          5 7516 1                      5 7516 1 FltPOBAXl FltPOBAXl      L-CYP31 tiEi?Tm FltPOBAXl      NAPL7l FltPOBAXl      971L51 FltPOBAXl        Y-311 I FItPOBAX1 FltPOBAXl 1    :ii I FltPOBAXl 1      845
                                'SEC Gens Isolated
                                                          ... . -          ..          . - ' ..              I Fault Prior nlerini 2A 1 . ~ 1exisl~ng KE!I\!
5 7516 1 lnlerini 2A wl existing KE\N 5 7516.1          I "POB GEN 2 Isolated American Transmission Company
 
G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation Hinh Ganaratinn        Low Generation Prior FltPOBAXl FltPOBAXl FltPOBAXl FltPOBAXl          6832 FltPOBAXl        971L71 FltPOBAXl      LSEC31 FltPOBAXl      L-CYP31 FltPOBAXl          T I0 FltPOBAXl        NAPL71 FltPOBAXl        971L51 FltPOBAXl        Y-311 FltPOBAXl          812 FltPOBAXl          823 FltPOBAXl          834 8  FltPOBAXl                4                      5
                  'SEC Gens Isolated High Generalon    I  Low Generation Prior Fault        Outage FltPOBAX2          None I      OK" OK "POB GEN 2 isolated merican Transmission Company                    Page 72 of 102
 
G83314-J022lJ023Interim Operation and Impacts Re-Study Report-RO1 Table B.10- Stability Results for Kewaunee and Point Beach Generation Outage under Intact Conditions Interim 1 (with G834/J023, with existing Kewaunee substation)
UNlT TRlP          I        Interim I I
i Trip time UNITTRIP                                      Low Gen POBGltn' POBG2tri POBGlGStri KEWGltri Interim 2A (with G834/J023 and G833/m77                  w i t h ~ r i . v t i n cKewaunee substation)
I Interim 2A (wl existing
                                                                      ..-. ...          I UNlT TRlP POBGltri POBG2tri POBGlG2tri Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation)
American Transmission Company                      Page 73 of 102
 
G83314-J022lJO23 ~nterimloperation and Impacts Re-Study Report-RO1 1                A~nendixC: Cornnetin9 Wind Generators 1  99  1            TBD (suspended) I    Kewaunee-Mishimt 138 kV line I
C 427        WEC        98                TBD (suspended)          Cypress 345 kV Substation G590        WEC        98                TBD (suspended)      Tecumseh Rd 138 kV Substation
                                                                          -- -
12-31-2011      Elkhart Lake-Forest Junction 138 kV line 12-01-2012      Forest Junction-Lost Dauphin 138 kV line American Transmission qmpany                  Page 74 of 102
 
G833/4-J022/J023 Interim Operation and Impacts Re-Study Report-RO1 Appendix D: Operating Restrictions American Transmission Company                  Page 75 of 102
 
G833/4-J022/J023 Interim Operation and Impacts Re-Study Report-RO1 With all stability upgrades assumed in-service and the Minimum Excitation Limiter settings for Point Beach and Kewaunee units modified, generation restrictions identified for each interim period are:
During Interim 1 period (2010 after G834lJ023 - 201 1 before G8331J022) iii. G1 at 560 MW (gross) under prior outage condition of 6832 (North Appleton-Fox River 345 kV line) iv. GI at 580 MW (gross) under prior outage condition of Point Beach Bus Tie 2-3 During Interim 2A period (Without Kewaunee project, 201 1 after G833lJ022 - beyond )
viii. G2 at 620 MW (gross) under prior outage of 121 (Point Beach-Forest Junction 345 kV line) ix. G2 at 620 MW (gross) under prior outage of 151 (Point Beach-Fox River 345 kV line)
: x. G2 at 600 MW (gross) under prior outage of R304 (Kewaunee-North Appleton 345 kV line) xi. Both GI and G2 at 540 MW (gross) under prior outage of 6832 (North Appleton-Fox River 345 kV line) xii. G2 at 580 MW (gross) under prior outage of SEC31 (Sheboygan Energy Center-Granville 345 kV line) xiii. GI at 580 MW (gross) under prior outage of Point Beach Bus Tie 2-3 xiv. G2 at 620 MW (gross) under prior outage of Point Beach Bus Tie 4-5 During Interim 2B period (With Kewaunee project, 201 1 after G83315022 - beyond)
: i. G2 at 600 MW (gross) under prior outage condition of 6832 (North Appleton-Fox River 345 kV line) ii. G1 at 580 MW (gross) under prior outage condition of Point Beach Bus Tie 2-3 American Transmission Company                  Page 76 of 102
 
683314-J022lJO23 Interim Operation and Impacts Re-Study Report-RO1 Appendix E: Short Circuit / Breaker Duty Analysis Results Scenario 1 = Existing system                                                                  23293.9                      21160.4                    9288              11100.6 Scenario 2 = Existingwith new GSU of POB G2 (Fall 2009-May 2010)                              23878.5                      21419.7                    9288              11100.6 Scenario 3 =With G834 (J023) and new GSU of POB GI (May 2010-May 2011)                        24516                      21758.5                    9288              11100.6 I
Scenario4 = With G83314 (J02.213) with existing Kewaunee (May 2011-beyond)                    24660.4                      21927.2                    9288              11100.6 Scenario 5 =With G83314 (J02213) with new Kewaunee (May 2011-beyond)                          24801.6                      22017                    9288.2              11100.7
  **Scenario 6 =With G83314 (J02213) with new Kewaunee and potential East sub                  25448.4                      22749.3                    9786.8              11954.8
  **Scenario 7 =With G83314 (~02d3)with new Kewaunee and ~otentialEasffNorth I sub with line conversion
                              \        ,
26615.1                      23988.7                    10915.9            13402.2
* POB G I and G2 ofline and Q-303 out of service
  ** Scenario 6 and 7 were also studied to provide maximum and minimum fault duties that may appear due to potentialfuture bansmission reinforcement.
Table E.2 - Thevenin Equivalent Impedances in Ohms corresponding to Maximum Fault Duty Pos Seq.                      Neg. Seq.            Zero Seq.
Scenario 1 = Existing system                                                                                        0.492146+ j 9.400272            0.563439t j 9.4053  0.589203+ j 6.794582 Scenario 2 = Existingwith new GSU of POB G2 (Fall 2009-May 2010)                                                      0.47915+ j 9.28685          0.547887+ j 9.291845  0.530596+ j 6.397666 I
Scenario 3 = With G834 (J023) and new GSU of POB G I (May 2010-May 2011)                                            0.476195+ j 9.141977          0.648689+ j 9.140315  0.480063+ j 6.038944 Scenario 4 =With G83314 (J02213) with existing Kewaunee (May 201$-beyond)                                            0.480694+ j 9.071247          0.754597+ j 9.060422  0.480063t j 6.038944 I
Scenario 5 =With G83314 (J02213) with new Kewaunee (May 2011-beyond)                                                0.500629+ j 9.033035          0.774579+ j 9.021229  0.483616+ j 5.974935
  ** Scenario 6 = With G83314 (J02213) with new Kewaunee and potential East sub                                        0.483549 + j 8.742337          0.734901 + j 8.732362 0.491449 + j 5.944132
  **Scenario 7 =With G83314 (J02213) with new Kewaunee and potential EastlNorth sub with line conversion              0.455713 + j 8.290790          0.685388 + j 8.282391 0.496780 + j 5.818807
** These scenarios were also studied to provide maximum and minimum fault duties that may appear due to potential future transmission reinforcement.
American Transmission Company                                      Page 77 of 102
 
G83314-J022/1023 Interim Operation and Impacts Re-Study Report-RO1 American Transmission Company                  Page 78 of 102
 
G83314-J022N023 Interim Operation and Impacts Re-StudyReport-RO1 Page 79 Of 102
 
G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Appendix P: Study Criteria American Transmission Company                  Page 80 of 102
 
G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Study Criteria F. 1 Contingencies For stability analysis, a set of branches in the vicinity of the generatorlpower plant of concern is selected as contingencies, based on engineering judgment. Fault analysis is performed for the following six categories of contingency conditions:
: 1. Three-phase fault cleared in primary time with an otherwise intact system.
: 2. Three-phase fault cleared in delayed clearing time (i.e. breaker failure conditions) with an otherwise intact system.
: 3. Three-phase fault cleared in primary clearing time with a pre-existing outage of any other transmission element.
: 4. Single Line Ground (SLG) bus section fault cleared in primary clearing time with an otherwise intact system.
: 5. SLG internal breaker fault cleared in primary clearing time with an otherwise intact system.
: 6. SLG fault of double circuits on common tower cleared in primary time with an otherwise intact system.
For power flow analysis, contingencies include:
: 1. N-1 contingencies - all lines and transformers operated at 69kV and above in the following control areaslzones: ATC Planning Zones 1-5 and ties to those zones and all branches of voltage level 69kV and above in the Dairyland Power Cooperative, Northern States Power Control Area, Commonwealth Edison, and Alliant Energy West control areas.
: 2. Selected N-2 and multiple contingencies that ATCLLC has determined to be significant.
F.2 Monitored Elements F.2.1 Intact System, N-1, N-2 and Special Multiple Contingency Evaluation Using Linear Transfer Analysis Methods All load carrying elements operated at 69kV and above in the following control areaslzones were studied: ATCLLC Planning Zones 1-5 and ties to those zones, and all branches of voltage level 69kV and above in the Dairyland Power Cooperative, Northern States Power Control Area, Commonwealth Edison, and Alliant Energy West control areas.
A Transmission Reliability Margin (TRM) of 5% must be applied to the MVA ratings of each monitored ATCLLC element. Violations reported will be based upon the adjusted MVA rating.
American Transmission Company                  Page 81 of 102
 
G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 F.3 Thermal Loading Criteria F.3.1 Injection Violations Generation injection violations include: 1) thermal violations of the transmission elements that connect the Generator to the rest of the transmission network (outlet congestion); 2) thermal violations of the transmission elements that have a transfer distribution factor (TDF) 2 5% for NERC Category A (system intact) conditions and TDF 2 20% for NERC Category B contingencies anywhere in the studied system in relation to real power injected at the Point of Interconnection (POI) when delivered to all of MISO; or 3) thermal violations created by the loss of a transmission element connected to the generator interconnection substation.
F.3.2 Operating Restriction Calculation Allowable Output =
TDF F.4 Steady State Under Voltage Criteria F.4.1Intact System, N-1 and Special Multiple Contingency Evaluation Using ACCC Under intact system conditions, the voltage magnitude of all transmission system buses with a decrease of 0.01 per unit due to the Generator must not be lower than 0.95 per unit. Under contingency conditions, the voltage magnitude of all transmission system buses with a decrease of 0.01 per unit, due to the Generator, must not be lower than 0.90 per unit.
F.4.2N-2 Contingency Evaluation Power flow solutions must converge for a selected number of N-2 contingencies in the electrical proximity of the studied Generator. Divergence of a power flow solution indicates potential voltage collapse. A "fix" must be identified for any non-converging power flow simulation and may include generator operating restrictions. v o t e : Non-convergence may be due to solution settings such as switched shunt operation andlor LTC action.]
F.5 Anwlar Stability Criteria Critical Clearing Time (CCT) is a period relative to the start of a fault, within which all generators in the system remain stable (synchronized). CCT is obtained from simulation.
fault using the existing system facilities. MECT is dictated by the existing system facilities. In any contingency, if the computed CCT is less than the MECT plus a margin determined by ATC (1.0 cycle for studies using estimated generator data and 0.5 cycles for studies using confirmed generator data), it is considered an unstable situation and is unacceptable. Otherwise, it is considered acceptable transient stability performance.
American Transmission Company                  Page 82 of 102
 
G833/4-J022/J023 Interim Operation and Impacts Re-Study Report-RO1 Longer time-domain simulations must be performed on faults cleared at the CCT to examine dynamic stability. Simulations will typically cover 20 seconds of system dynamics and machine angle oscillations must meet the damping criteria in the ATC Planning Criteria.
Note that ATC stability criteria and NERC stability criteria differ on the study assumptions used for breaker failure analysis. ATC study criterion models breaker failure by modeling a three-phase fault during the primary time, reduced to SLG fault if the failed breaker is an Independent Pole Operated (IPO) breaker during delayed clearing and cleared at the end of the delayed clearing time. On the other hand, NERC study criterion assumes a single line-to-ground fault for the entire breaker failure analysis. Hence, the CCT computed from ATC stability criteria is always less than or equal to the value computed using the NERC study criteria. This report assumes ATC stability criteria unless otherwise stated.
The time-domain simulations must also be reviewed for compliance with the transient and dynamic voltage standards in the ATC Planning Criteria. Voltages of all transmission system buses must recover to be at least 70% of the nominal system voltages immediately after fault removal and 80% of the nominal system voltages in 2.0 second after fault removal.
American Transmission Company                  Page 83 of 102
 
G83314-J022/JO23 ~ntermjOperation and Impacts Re-Study Report-RO1 Appendix 6 : Estimated Allowable MW Output from 6834 or 6833 under SpringIFall or Winter Emergency Ratings I    cypress-Arcadian 345-k" line      I      968        I                kV line P0intBeach-shebo~ginEnerg~Center345~    98.7      1    519.3    119.80%  1    546.61 Point Beach-Sheboygan~ n e r g ~
1311                CypressArcadian 345-kV line      516.2          540.5      23.37%      568.94 Center 345-kV line Point Beach-SheboyganEnergy Center 345-CypressArcadian 345kV line                1076                                                  498.7          519.3      19.80%      546.61 kV line
: 1. The Pre and Post MV MW output. The old valu New Pre MVA New Post MVA 9--L flow were re-estimated fiom the previous interim operations study report in order to calculate new required ratings and new allowable s in the previous study report was obtained fiom Table A.5
                                ,-
old Pre MVA old Post MVA + 6 MW x DF American Transmission Qompany                              Page 84 of 102
 
G83314-J022/JO23 1 n t e 4 Operation and Impacts Re-Study Report-RO1 S
: 2. The Pre MVA flow w re-estimated fiom the previous interim operations study report in order to calculate new required ratings and new allowable MW output. The old values in e previous study report was obtained fiom Table A.5 New Pre MVA old Pre MVA + 6 MW x DF
: 3. The Post MVA flow 1
re-estimated fiom the previous interim operations study report in order to calculate new required ratings and new allowable MW output. The old value      previous study report was fiom the case (Scenario 5 with G8331834 and all wind loo%, with 201 1 Kewaunee modeled) old Post MVA + 12 MW x DF Note: The results shown  4the above tables are based on 50% peak load cases.
Ci American Transmission ompany                      Page 85 of 102
 
G833/4-J02ZNOW InterimOperation and Impacts Restudy Report-RO1 I          I              Il            Open bustie during
                                                                                                                                  -          I                  -
I              1 zFEz: 1              1 I                                                            I              I      I 1
I              II          I                          I      I              I                                I I I now                                                        KP    62620                  5.W4.5 11        I I                    I      I      I No~.5l)cvdek I        I                        I I I KP                                    CCT - 5.W.O KP                                        -
CCT 5.546.0
                                                                                        &P,F                                      -
CCT 51V6.0 KP.F                                  CCT - 51116.0  KP.F        CCT- 5.D16.0 KP.F                                  CCT - 5Y6.0    KP,F              -
CCT 5Y6.0 KP,F                                  CCT -5516.0    KP,F        M-5.56.0 A15.75B.1 tasted deariw 6rne  -
UV bip P (IS!+/ l.52ls, 345kV 1st 1.C&, 315kV md 1.5625)
CCT-5.5B.O KP                                    CCT-5.016.0                      -
CCT 5.016.0 KP                                        -
CCT 5.016.0      KP              -
CCT 5.W.O KPS                                    CCT -5.016.0    KP,S        CCT- 5.016.0 KP              -
CCT 5516.0 I
American Transmission Company              Page 88 bf 102
 
G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Appendix I: Minimum Excitation Limits at Point Beach and Kewaunee during Interim Periods American Transmission Company                  Page 90 of 102
 
G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Minimum Excitation Limits at Point Beach and Kewaunee during Interim Periods As noted in this G833lJ022-G834lJ023 Interim Operations Re-Study Report, Point Beach and Kewaunee units need to maintain certain reactive power output in anticipation of critical contingency conditions. Reactive power output from a synchronous machine has an impact on the transient stability of the unit. Typically, when a unit produces relatively small reactive power output or absorbs reactive power from transmission system (under-excitation), the unit tends to be less stable under a fault condition. The results of the interim operation study indicate that a certain level of reactive power output (over-excitation) needs to be maintained to ensure generation stability in anticipation of critical fault conditions. This is primarily due to too many generators with few outlets out of Fox Valley area.
The minimum excitation limiter, which may also be referred to as the under-excited reactive ampere limit or under-excitation limiter, settings are an effective mechanism to ensure a minimum level of unit excitation. However, limiting the amount of under-excited operation can negatively affect the ability to control system and plant voltages under lighter system load conditions where transmission line charging may result in higher system voltages. Therefore, any minimum excitation limits need to be coordinated with voltage control requirements.
The "interim" solutions described in the Interim Operations Re-Study Report would be followed by the completion of the necessary Network Upgrades identified in the G833lJ022-G834lJ023 System Impact Re-Study Report, which has yet to be posted. The Network Upgrades would be the long-term solutions which ensure a wider operating envelope for the local transmission system and the interconnected generators by permitting generating unit operation at near unity or leading power factor, or at least provide a foundation to achieve the wider operating envelop through additional transmission reinforcement in the area that may be needed in the future.
Transient Stability Studies To estimate minimum excitation limits (MVAR output levels), it is assumed that the stability upgrades identified for each interim period are in-service (see G833lJ022-G834lJ023 Interim Operation Re-Study Report). Various MVAR output levels at Point Beach and Kewaunee 345 kV buses were evaluated using two different generation dispatch scenarios during the three interim periods. Critical faults under system intact condition identified in the interim operation study were applied, which are:
Fault on Q-303 with breaker failure at Point Beach (post-May 2010 until May 201 1 only since a series breaker is proposed to be installed by May 201 1)
Fault on R-304 with breaker failure at Kewaunee (post Kewaunee bus reconfiguration project period only)
American Transmission Company                  Page 91 of 102
 
G83314-J022IJO23 Interim Operation and Impacts Re-Study Report-RO1 With stabilitv upmades for each interim period in-service and based on the studv results shown in Table 1.1 through 1.4, the Point Beach and Kewaunee units would need to maintain the following minimum excitation levels to ensure synchronism of these and nearby generators:
For May 2010 - May 201 1 (With Point Beach Unit #1 u p ~ a d e dand with the existing Kewaunee bus confirnation) o Point Beach G1 and G2: 48 MVAR or higher per unit o Kewaunee GI: 41 MVAR or higher For May 2011 until completion of the Kewaunee bus reconfiguration proiect w i t h both Point Beach Units #1 and #2 upgraded),
o Point Beach Gl and G2: 70 MVAR or higher per unit o Kewaunee GI: 58 MVAR or higher Post completion of the Kewaunee bus reconfiguration proiect (With both Point Beach Units #1 and #2 upgraded]
o Point Beach Gl and G2: 68 MVAR or higher per unit o Kewaunee GI: 49 MVAR or higher These minimum excitation limits were estimated by testing the critical system faults.
Additional study for all other relevant system faults was not performed because of the following reasons:
For Interim 1 period (see Table I.1), the critical faults under system intact conditions are more severe at the low generation scenario, and the estimated minimum excitation limits of Kewaunee and Point Beach units are either same or higher than their W A R outputs at the 352 kV voltage schedule where all other faults under system intact conditions were proven to be stable in the interim operation study. Therefore, additional study for all other relevant system faults under system intact conditions was not performed. For prior outage conditions, it is recommended to maintain at least 354 kV at the Point Beach and Kewaunee 345 kV buses (note: 354 kV is high-end of the preferred voltage range at Point Beach) in anticipation of critical faults. This is to ensure stable system even with faults under prior outage conditions which appear to be more severe at high generation scenario and were proven to be stable at the 352 kV voltage level with interim upgrades and operating restrictions implemented.
As mentioned above, the critical faults under system intact conditions appear to be more severe at the low generation scenario according to the results of the interim operation study, and the estimated minimum excitation limits of Kewaunee and Point Beach units are higher than their MVAR outputs at the 352 kV voltage schedule of low generation scenario (see Table 2.4.1) where all other faults under system intact conditions were proven to be stable in the interim operation report. 'l'herefore, additional study for an other relevant system taults under system intact conditions was not performed. For prior outage conditions, it is also recommended to maintain at least 354 kV (high-end of the preferred voltage range at Point Beach) in anticipation of critical faults. This is to ensure stable system even with faults under prior outage condition which appear to be more severe at high generation scenario and were proven to be stable at 352 kV.
American Transmission Company                  Page 92 of 102
 
G83314-J0221J023 Interim Operation and Impacts Re-Study Report-RO1 Steady State Voltage Control Studies at Minimum System Load Conditions Using a minimum load case with 40% of 2010 summer peak load condition, three scenarios were built and studied to c o n f i i if any high voltages occur at Point Beach 345 kV and Kewaunee 3451138 kV buses under various conditions. The scenarios are:
Scenario 1: Minimum load case with G834-J023 added
    = Scenario 2: Minimum load case with G834/J023-G833/J022 added Scenario 3: Minimum load case with Scenario 2 and with Point Beach G2 and Kewaunee G1 offline.
The minimum reactive power outputs of Point Beach and Kewaunee units in each case were adjusted to match with the estimated minimum excitation limits as follows:
For Scenario 1:
o Point Beach G1 and G2: 48 MVAR o Kewaunee GI: 41 MVAR For Scenario 2:
o Point Beach Gl and G2: 70 MVAR o Kewaunee GI: 58 MVAR No study was performed using the minimum excitation limits of Interim 2B period since no significant impact is expected due to the Kewaunee bus reconfiguration project.
For the study, the following critical contingencies were tested.
System Intact Open Line-end
: i. Open North Appleton end of R-304 ii. Open Granville end of L-SEC3 1 iii. Open Arcadian end of L-CYP31 iv. Open Forest Junction end of L121
: v. Open Fox River end of L15 1 N-1 or multiple contingency analyses are not performed since these conditions will lower voltages due to increased system impedances.
Monitored elements are Point Beach 19 kV and 345 kV, and Kewaunee 345 kV and 138 kV bus voltages. The following criteria are assumed for the monitored elements.
Point Beach 19 kV bus voltage: 95 percent to 105 percent of nominal voltage Point Beach 345 kV bus voltage: Not exceed 358 kV (high end of normal voltage range) under system intact condition. Not exceed 360 kV (slightly lower than high end of absolute voltage range) under a line end open
        --Kewaunee        --.
345 kV bus voltage: 95 percent to 105 percent of nominal voltage a
* Kewaunee 138 KV bus voltage: 14U KV ana 143 K V unaer system mmct ana
                                                        * * - . T I                  1 contingency conditions In conclusion, no high voltage conditions were found as shown in Table 1.4. Sensitivity analysis was performed by turning on some of the capacitor banks in the area such as New Holstein, Glenview, Howard and Shoto. As a result, high voltage at Kewaunee 138 kV bus is identified with the Granville end of L-SEC3 1 open. However, the voltage issue American Transmission Company                  Page 93 of 102
 
G83314-J022IJ023 Interim Operation and Impacts Re-Study Report-RO1 can be addressed by remedial actions such as turning off some of the capacitor banks in the area as described in Table 1.5.
American Transmission Company                  Page 94 of 102
 
G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table 1.1. Minimum Excitation Limit Study Results for Interim 1 (May 2010 - May 2011)
    /    Interim 1 (KV and MVAR level at POB and KEW for stable system under critical faults)
I Critical Fault under Intact High Gen scenario'    Low Gen scenario'            Comment (tested clearing times) 350 kV or higher      35 1 kV or higher L l l l BF @
(POB G l : 43.4        (POB GI: 42.7 POB POB G2: 43.4          POB G2: 42.7 (3.5/10.0/4.5)
KEW GI: 40.9)          KEW G l : 26.1) 348 kV or higher      349 kV or higher L l 5 l BF @                                                        Thus, minimum (POB G l : 12.0        (POB G l : 33.3 POB                                                          excitation limits are:
POB G2: 12.0          POB G2: 33.3 (3.5/10.0/4.5)                                                        POB G l : 47.4 KEW GI : 20.1)        KEW G l : 17.5)
POB G2: 47.4 350 kV or higher      352 kV or higher          KEW GI: 40.9 Q303 BF @
(POB G1: 43.4          (POB G1: 47.4 POB POB G2: 43.4          POB G2: 47.4 (3.5/10.0/6.5)
KEW GI: 40.9)        KEW G l : 30.4)
Table 1.2. Minimum Excitation Limit Study Results I
for Interim 2A (May 2011 until Kewaunee Reconfiguration Complete)
I          Interim 2A (KV level at POB and KEW for stable system under critical faults)
Critical Fault I
under Intact High Gen scenario'    Low Gen scenario'            Comment (tested clearing times) 35 1 kV or higher      352 kV or higher L l l l BF @
(POB G l : 69.6        (POB Gl: 60.1 POB POB G2: 69.6          POB G2: 60.1 (3'519'014'5)
KEW GI: 57.5)          KEW G l : 35.8) 350 kV or higher      352 kV or higher        Thus, minimum L l 5 l BF @
(POB G l : 53.7        (POB G l : 60.1      excitation limits are:
POB POB G2: 53.7          POB G2: 60.1            POB G l : 69.6 (3'5'Y'5'4'5)
KEW GI: 46.9)          KEW G l : 35.8)          POB G2: 69.6 KEW GI: 57.5 American Transmission Company                    Page 95 of 102
 
G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table 1.3. Minimum Excitation Limit Study Results for Interim 2B (Post Kewaunee Reconfiguration)
I          Interim 2B (KV level at POB and KEW for stable system under critical faults)
I I  Critical Fault    I                      I                      I 1I  under Intact (tested clearing I High Gen scenario1  I  Low Gen scenario1  /        Comment times) -    I                      I                      I 35 1 kV or higher        352 kV or higher L111 BF @
(POB G l : 67.2          (POB GI: 58.6 POB POB G2: 67.2            POB G2: 58.6 (3+5".014.5)
KEW ~ 148.9) :          KEW G l : 27.3) 349 kV or higher        352 kV or higher L l 5 l BF @
(POB G l : 35.6          (POB GI: 58.6 POB                                                            Thus, minimum POB G2: 35.6              POB G2: 58.6 (3.519.514.51                                                    excitation limits are:
KEW G1 27.1)            KEW      : 27.3)
POB GI: 67.2 POB G2: 67.2 Q303 BF @                                                            KEW GI: 48.9 POB 348 kV or higher        35 1 kV or higher R304 BF @
(POB G1: 20.1            (POB GI: 53.4 KEW POB G2: 20.1            POB G2: 53.4 (3'519'5/4'5)
KEW GI: 16.4)            KEW G l : 22.9)
: 1. Approximate MVAR change at Point Beach and Kewaunee:
High generation scenario:
o 1kV change at Point Beach for every 16 MVAR change o 1kV change at Kewaunee for every 11 MVAR change Low generation scenario:
o 1kV change at Point Beach for every 5 MVAR change o 1kV change at Kewaunee for every 4.5 MVAR change American Transmission Company                      Page 96 of 102
 
683314-J022IJ023 Interim Operation and Impacts Re-Study Report-RO1 American Transmission Company                  Page 98 of 102
 
683314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table 1.5. Voltages at Point Beach and Kewaunee Under System Intact and Contingencies Bus  I                    Open North Appleton end of Kewaunee-North    I Open Granville end of Granville-Shebovgan Open Forest Junction end of Point Beach-  I Open Fox River end of Point Beach-Fox River American Transmission Company                  Page 99 of 102
 
@33&302%J0;53 En-Page 100 o f 102
 
G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Appendix J: Unit Restriction Due to Stability under Prior Outage Conditions in Table ES-3 during One of Point Beach Units offline American Transmission Company                 Page 101 of 102
 
G833/4-.JO22N023Infer& Operation and Impacts Re-Study Report-RO1 existing Kewa~nee)
L121 at POB         POB Bus tie 2-3             4.514.5                 OK R304 at KEW                 L121                   5.514.5                 OK                   OK                     OK                       OK R304 at KEW                 L151                   5.514.5                 OK                     OK                     OK                       OK 6832 at FOX               R-304                   4.514.5                 OK                     OK                     OK                       OK Interim 2A (With G83314J022r3, With     R-304 at KEW               6832                   5.514.5                 OK                     OK                     OK                       OK existing Kewaulee)
R-304 at KEW             LSEC31                   5.514.5                 OK                     OK                     OK                       OK LIZ1 at POB         POB Bus tie 2-3             4.514.5                 OK                   OK R-304at KEW           POB Bus tie 4-5             5.514.5                 OK                   OK                       OK                       OK
                                                                                                                                                                            -   -
R-304 at KEW                 6832                   4.514.5                 OK                   OK                       OK                       OK Interim 28
( W i G833/4J022/3, With -
new Kewaune?)
L121 at POB         POB Bus tie 2-3               45/45                   OK                   OK           1 of Point Beach Bus tie 2-3 followed by L121 fault isolates Point Beach GI to the remainingline L111. Therefore, taking the Point Beach Bus tie 2-3 out of senrice g outage window does not eliminate the POB GI stability issue for L121 fault under Point Beach Bus tie 2 3 out of s e ~ c eThus,
                                                                                                                                                              . follow the operating restriction for the G833/4J022/3 Interim Operation Re-study Report American Transmission C mpany 4                           Page 102 of 102}}

Revision as of 02:50, 14 November 2019

Background Information to Support License Amendment Request 261, ATC Lnterim Operation and Impacts Re-Study, Appendixes B - J
ML092400528
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 07/14/2009
From:
Point Beach
To:
Office of Nuclear Reactor Regulation
Shared Package
ML092400540 List:
References
NRC 2009-0082 G833/G834-J022/J023, Rev 1
Download: ML092400528 (54)


Text

G83314-J022/J023 Interim Operation and Impacts Re-Study Report-ROl Appendix B: Stability Analysis Results American Transmission Company Page 49 of 102

G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Nomenclature K or KEW: Kewaunee P or POB: Point Beach (PI and P2)

S or SEC: Sheboygan Energy Center F or FOX: Fox Energy NAP: North Appleton GVL: Granville CYP: Cypress ADN: Arcadian FJT Forest Junction TH: Thilmany Point Beach-Sheboygan Energy Center 345 kV L111:

line L121: Point Beach-ForestJunction 345 kV line Q303: Point Beach-Kewaunee345 kV line L151: Point Beach-Fox Energy 345 kV line R304: Kewaunee-North Appleton 345 kV line NAPL71: North Appleton-WernerWest 345 kV line CYP31: CypressArcadian 345 kV line 6832: North Appleton-Fox Energy Center 345 kV line TIO: KewauneeTI0 3451138 kV transformer SEC3I: Sheboygan Energy Center-Granville 345 kV line H: High side KWH: KewauneeT10High side KWL: Kewaunee TI0 Low side POBxy: Point Beach bus tie xy Y311 Nora Appleton-Fitzgerald 345 kV line CCT: Critical Clearing Time Note: The simulated clearing times and critical clearing times (CCT) noted in Appendix B contains planning margin described in Section 3.2 American Transmission Company Page 50 of 102

I G83314-Jo22tJo23 Interim Ope ation andImpacts Re-study Report-Ro1 I

--

Tab1 B.1- Stability Results for Faults Clearing in Primary Time under Intact System Conditions Tntorim 7 /with G8?4/11073 -

- - . - w i t h ~- r -i . r t i Kcrwnlinc!~?

n- ~ .ruh.rtntinn)

Intact System Fault Cleared in Primary Time - Interim Period 1 (May 2010-April 2011) I Faulted End Breakers Remote Location Remote End Breakers I

Event Notes I Simulated I

Clearing*

I I I High Generation I Low Generation I 111 SEC 1-2.16 NOSPS 4.514.5 121,123 FJT 1-2,23 4.514.5 151 FOX 2-3.3-1 NOSPS 4.514.5 Q-303 KEW Q-303,1099,2450 KEW SPS In 4.516.5 Q-303,1099,2450 PO0 Q-303 KEW SPS In 6.514.5 R-304,3451 NAP R-304 6.516.5 2-3,34 POB 151 4.514.5 1 1-2,6-1 NAP 243,344,45467-6 4.514.5 4-5,5-6 FJT 5-6,7-1 4.514.5 1-2,16 POB Ill 4.514.5 1-2,3-6 GVL L-SEC31 4.516.5 1-2,5-6 ADN L-CYP31 4.514.5 Q-303,1099,3450 KWL American Transmission compbY Page 51 of 102

G83314-J022lJO23 Interim ~Aerationand Impacts Re-Study Report-RO1 1 Interim 2A (with G834/J023 and G833/J022.with existing Kewau tee substation)

-

Intact System Fault Cleared in Primary Time Interim Period 2A ( ~ i r i l 2 0 1 1and beyond, with existing Kewaunee) I Simulated I iigh Generation 1 Interim 2B (with G834/J023 and G833/J022,with new Kewmrnee substation)

Element Fault Faulted End Remote Remote End Event Simulated File Faulted Location FltPOBSEC L111 POB 111 SEC 1-2,16 NOSPS 4.514.5 FltPOBFJT L121 POB 121,123 FJT 1-2,2-3 FltPOBFOX L151 POB 151 FOX 2-3,3-4 NOSPS 4.514.5 No FltPOBKEW Q-303 POB 4303 KEW Q-303 New 1 and 2 SPSs 4.514.5 No American Transmission ~ o m $ a n ~ Page 52 of 102 07/14/2009

G833/4-J022/JO23 Interim 0~4rationand Impacts Re-Study Report-RO1 Table B.2- Stabilify Results for Double Circuit Single Line-to-Ground Faults Cleared in Primary Time under Intact System Conditions Interim 1 (with G834/J023,with existing Kewaunee substation) 1 I I I I I I I Interim Pel File Event DC3-111-971K51-I I L1l1 -

Fyik BeachSheboygan Fault # I 38.5% frorn POB Acceptable 5.515.5 Fault

  1. 2 971K51 - Forest Junction-Howard's Fault R Location 33.g9/0from NT Simulated Clearingtime 6.516.5 (May 2010-Apr mm 2011) 345 kV Grove 138 kV L1ll -Point 971K51 -Forest Junction-Howard's 6.3% from HOG 6.516.5 DC3-Ill-971K51-2 16.3% from SEC 5.515.5 345 kV Grove 138 kV DC3-111-HOLG21-1

-

L l 1I Point BeachSheboygan SEC 5.515,5 HOGL21 -Howard's Grove-Holland 76.9% from HOL 6.516.5 345 kV 138 kV L l l l -Point Beach-Sheboygan HOGL21- Howard's GroveHolland 314X from HOG 6.516.5 DC3-111-HOLG21-2 ' ,5.70mfrom SEC 5.515.5 345 kV 138 kV L121.R. Beach-Forest Junction 971K51- Forest Junction-Howard's FJT 6.516.5 DC3-121-971K51-1 FJT 5.515.5 345 kV Grove 138 kV L121.R Beach-Forest Junction 971K51- Forest Junction-Howard's 6.516.5 DC3-121-971K51-2 42.3% from FJT 5.515.5 33.9% from FJT 345kV Grove 138 kV L-SE(31- Sheboygan-Granville GVL 7.517.5 3431 - Granville-Saukville345 kV GVL 7.517.5 DC3-SEC31-3431-1 345 kV L-SEC31-Sheb0ygan-Granvi11e 26.7% from GVL 7.517.5 3431 - Granville-Saukville345 kV 25.3% from SAU 7.517.5 DC3-SEC31-3431-2 345 kV LSEC31Sheb0ygan-Granvi'le 43.5% from GVL 7.517.5 8231 - Saukville-Barton138 kV 36.4% from BRT 7.517.5 DC3SEC31-8231-1 345 kV DC3-SEC31-8231-2 L-SE231Sheb0~!3an-Granville 345 kV 48.3% frorn GVL 7.517.5 -

8231 Saukville-Barton138 kV 36.4% from SAU 7.517.5 L- CYP3l- Cypress-Arcadian 32.00/0from ADN 5.515.5 2642 - Saukville-Gemantown 138 kV 34.2% from SAU 7.517.5 DC3-9932-2642-1 345 kV CYP31 - 16.6% from ADN 5.515.5 -

2642 Saukville-Gemantown 138 kV GER 7.517.5 DC~-9932-2642-2 345 kV L- CyP31 - 10.8% from ADN 5.55.5 2661 - Germantown-Bark River 138 kV 31.5% from GER 8.518.5 DC3-9932-2661-1 345 kV L- CyP31 - Cypress-Arcadian 16.6% from ADN 5.515.5 2661 - Germantown-BarkRiver 138 kV GER 8.518.5 DC3-9932-2661-2 345 kV DC3-9932-9911-1

-

CyP31 Cypress-Arcadian 10.8% from ADN 5.515.5 9911 - Granville-Arcadian 345 kV 45.4% from GVL 7.517.5 345 kV DC3-9932-9911-2 L- CyP31- Cypress-Arcadian ADN 5.515.5 9911 - Granville-Arcadian 345 kV ADN 7.517.5 345 kV American Transmission comP/any Page 53 of 102

G83314-J022lJ023Interim opetiation and Impacts Re-Study Report-RO1 Interim 2A (with G834/J023 and G833/J022,with existing Kewaunee substation)

Event Fault Fault #1 Acceptable Fault Fauit#2 File #1 Location CCT" #2 Location

-

L111 Point BeachSheboygan 971K51- Forest Junction-Howard's Dm-111-971K51-I 345 kV 38.5% from POB 5.515.5 Grove 138 kV 33.9% from FJT 6.516.5 L l l I- Point BeachSheboygan 971K51- Forest Junction-Howard's DC3-111-971K51-2 345 kV 16.3% from SEC 5.515.5 Gmve 138 kV 6.3% from HOG 6.516.5 OK OK

-

L l l l Point Beach-Sheboygan HOGL21- Howard's GroveHolland DC3-111-HOLG21-1 345 kV SEC 5.515.5 138 kV 76.9% from HOL 6.516.5 L l l l - Point BeachSheboygan HOGL21 - Howard's Grove-Holland DC3-111-HOLG21-2 345 kV 15.7% from SEC 5.515.5 138 kV 31.4% from HOG 6.516.5 -

L121-fk Beach-Forest Junction 971K51- Forest Junction-Howard's DC3-121-971K51-1 345 kV FJT 5.515.5 Grove 138 kV FJT 6.516.5 L121-%. Beach-Forest Jundon 97101 - Forest Junction-Howard's DC3-121-971K51-2 345 kV 42.3% from FJT 5.515.5 Grove 138 kV 33.9% from FJT 6.516.5 L-SECSl - Sheboygan-Granville DCSEC31-3431-1 345 kV GVL 7.5R.5

-

3431 Granvile-Saukville 345 kV GVL 7.517.5 LSEI.>31Sheboygan-Granville 3431 - GranvilleSaukville345 kV DC3SEC31-3431-2 345 kV 26.7% from GVL 7.517.5 25.3X from SAU 7.517.5 DC3-SEC31-8231-1 LSEC>31Sheboygan-Granville 345 kV 43.5% from GVL 7.517.5

-

8231 Saukville-Barton138 kV 36.4% from BRT 7.517.5 L-SEC>31-Sheboygan-Granville 8231 - Saukville-Barton138 kV DC3SEC31-8231-2 345 kV 48.3% from GVL 7.5R.5 36.4% from SAU 7.517.5 L- C\rbP31- Cypress-Arcadian -

2642 Saukville-Germantown 138 kV DC3-9932-2642-1 345 kV 32.0% from ADN 5.515.5 34,2% from SAU 7.5175 L- CYf"fJ1- Cypress-Arcadian 2642 - Saukville-Germantown 138 kV DC3-9932-2642-2 345 kV 16.6% from ADN 5.515.5 GER 7.517.5

-

L- CtkP31 Cypress-Arcadian 2661 - Germantown-BarkRiver 138 DC3-9932-2661-1 345 kV 10.8% from ADN 5.515.5 kV 31.5% from GER 8.518.5 L- C"P31- Cypress4wdian 2661 - Germantown-Bark River 138 DC3-9932-2661-2 345 kV 16.6% from ADN 5.515.5 kV GER 8.518.5

-

L- C"P31 Cypress-Arcadian 9911 - Granville-Arcadian 345 kV DC3-9932-9911-1 345 kV 10.8% from ADN 5.515.5 45.40/0from GVL 7.517.5 I

-

L- Cbp31 Cypress-Arcadian 9911 - Granville-Arcadian345 kV I

DC3-9932-9911-2 345 kV ADN 5.515.5 ADN -7.5R.5 American Transmission comPby Page 54 of 102

G83314-J022lJO23 ~nterim operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation)

I I

Event 1 I I Fault I

I Fault # I I I Fault I

I Fault #2 I Interim Period 2B (May 2011 -), WI new Ke File #I Location #2 Location High Gen I Low Gen I L111- Point BeachSheboygan 971K51 -Forest Junction-Howard's DC3-111-971K51-1 345 kV 38.5% from POB 5.515.5 Grove 138 kV 33.9% from FJT 6.516.5 L111.. Point BeachSheboygan 971K51- Forest Junction-Howard's DC3-111-971K51-2 345 kV 16.3% from SEC 5.515.5 Grove 138 kV 6.3% from HOG 6.516.5 L l II-1 Point BeachSheboygan HOGL21-Howard's GroveHolland 1 DC3-111-HOLG21-1 345 kV SEC 5.515.5 138 kV 76.9% from HOL 6.516.5 L l I1 . Point BeachSheboygan HOGL21- Howard's Gmve-Holland DC3-111MOLG21-2 345 kV 15.7% from SEC 5.515.5 138 kV 31.4% from HOG 6.516.5 I L121-~3.Beach-Forest Junction 971K51- Forest Junction-Howard's I

DC3-121-971K51-1 345 kV FJT 5.515.5 Grove 138 kV FJT 6.516.5 L121-3. Beach-Forest Junction 971K51- Forest Junction-Howard's DC3-121-971K51-2 345 kV 42.3% from FJT 5.515.5 Grove 138 kV 33.9% from FJT 6.516.5 LSEC31- Sheboygan-Granville 3431 - GranvilleSaukville345 kV DC3SEC31-3431-1 345 kV GVL 7.5R.5 GVL 7.5R.5 L-SEC31-Sheboygan-Granville 3431 - GranvilleSaukville345 kV DC3SEC31-3431-2 345 kV 26.7% from GVL 7.5R.5 25,3% from SAU 7.5R.5 DC3SEC31-8231-1 L-SEC31Sheboygan-Granville 345 kV 43.5% from GVL 7.5R.5

-

8231 Saukhile-Barton 138 kV 36.4% from BRT 7.517.5 LSEC31Sheboygan-Granville 8231 - Saukville-Barton 138 kV 36.4% from SAU 7.5R.5 DC3SEC31-8231-2 345 kV 48.3% from GVL 7.517.5 L- C"P31- Cypress-Arcadian 2642 - Saukville-Germantown 138 kV DC3-9932-2642-1 345kV 32.0% from ADN 5.515.5 34.2Kfrom SAU 7.5R.5 L- C'P31- Cypress-Arcadian 2642 - Saukville-Germantown 138 kV DC3-9932-2642-2 345 kV 16.6% from ADN 5.515.5 GER 7.5R.5 L- C\?31- Cypress-Arcadian 2661 - Germantown-Bark River 138 kV DC3-9932-2661-1 345 k v 10.8% from ADN 5.515.5 31.5% from GER 8.518.5 L- C\?31 - Cypress-Arcadian 2661 - Germantown-Bark River 138 kV DC3-9932-2661-2 345 kV 16.6% from ADN 5.515.5 GER 8.518.5 L- C\'P31 - Cypress-Arcadian 9911 - Granville-Arcadian345 kV DC3-9932-99111 345 kV 10.8% from ADN 5.515.5 45.4% from GVL 7.5R.5 L- C'931- Cypress-Arcadian 9911 - Granville-Arcadian345 kV DC3-9932-9911-2 345 kV ADN 5.515.5 ADN 7.517.5 American Transmission c~mPany Page 55 of 102

G83314-J022/JO23 Interim Operation and Impacts Re-Study Report-RO1 Table B.3- Stl lbility Results for 3-Phase Faults Cleared in Primary Time under Prior Outage Condition Units Trpping Note: Among various contingencies evaluated, only faults with stability issues are listed in Table B.3.

Interim 1 (with G834/J023, with existing Kewaunee substation)

Primary Clearing Time, Prior Outage: 6832 (FOX-NAP, 38894-39556), (POB PSSs In Service) Existing KEW Sub Event Elemen Fault Faulted End Remote Remote End Event Simulated High Generation II Low Generation Faulted Location Breakers Location Breakers Notes Clearing*

I*** Stable FltKEWNAP I R-304 at 5.514.5 with G1 res Primary Clearing Time, Prior Outage: SEC31 (SEC-GVL, 3986538870), (POB PSSs In Service) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation Faulted Location Breakers Location Breakers Notes KEW R-304.3451 NAP R-304 6.516.5

    • Stable at 5.514.5 -replace R-!04 breaker at NAP.4.5 is MECT for R304 fault at KEW. Existing clearing time at faulted end is 4.5 cycles without margill Primary Clearing Time, Prior Outage: PO0 2-3 (POB-B23,3889&39211), (PO0 PSSs In Service) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation acation Breakers Location Breakers
  • For stability, G1 needs to be re rtricted to 580 MW gross
    • For stability, Gl needs to be I estricted to 620 M W gross American Transmission C Page 56 of 102

G83314-J022lJO23 Inte ' Operation and Impacts Re-Study Report-RO1 Interim 2A (with G834/J023 and G833/J022, with existing Kewaunee substation)

Primary ClearingTime, Prior Outage: L l l l (POB-SEC, 39433-39865), 'POB PSSs In Sewice) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation Fle Faulted Location Breakers Location Breakers Notes Clearing' Base Base FIWWNAP R-304 KEW R-304,3451 NAP R-304 6.516.5

"* Stable at 5.514.5, Replace R-304 breakerat North Appleton. Note: MECT of R304 at Kew is 4.5 Primary ClearingTime, Prior Outage: L121 (POB-FJT, 38898-39304), (POB PSSs In Service) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation File Faulted Location Breakers Location Breakers Notes Clearing* Base Base I FltKEWNAP I R-304 I KEW I R-304,3451 I NAP I R-304 I 1 6.516.5 A Stable at 5.014.5 or Stable at 5.514 5 with G2 reduced to 620 MW-replace R304 breaker at NAP. Existing clearing time at faulted end is 4.5 cycle^ cy out margin Primary Clearing Time, Prior Outage: L151(POB-FJT, 38898-39304), (POB PSSs In Sewice) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation I I

Low Generation File Faulted Location Breakers Location Breakers Note: Without G2 reduction, Vsag uAl trip P with 5.514.5 (PI 1.513sfor 19KV, P2 1.521sfor I9KV , BIB5 1st 1.083s, BIB5 2nd 1.575s). Thus, if time delay can be readjustedto avoid violation, only thing to be done is replacing R-304 breaker at NAP Primary ClearingTime, Prior Outage: R-304(KEW-NAP, 39630-39359), (POB PSSs In Sewice) Existing KEW Sub Event 1 Element 1 Fault 1 Faulted End Remote Remote End Event I Simulated I I High Generation I I

Low Generation File I Faulted I lrocation I Breakers ( ~ocation I Breakers Notes I Clearing* I FltFOXNAP 1 L6832 1 FOX I 1-2,6-1 1 NAP 1 34-3,344,454.67-6 1 1 4.5145

  • Stable at 4.014.5 OR Stable at 4.5'4.5 with G2 reducedto 600 MW gmss. At 4.514.5 with G2 at 620 MW, 345 kV 2nd criteria is violated: 81: 1.583s and 82: 1.583s.

Primary ClearingTime, Prior Outage: 6832 (FOX-NAP, 38894-39556), (POB PSSs In Sewice) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation File Faulted Location Breakers Location Breakers Notes Clearing* Base Base FIKEWNAP I R-304 1 KEW 1 R-304,3451 I NAP I R-304 ( 6.516.5 FLTKEWXFH2ROl I TI0 I KWH 1 Q-303,1099,3450 1 KWL I 1066E, 1066W I Open Q-303 at KEW 1 6.518.5

"*Stable at 6.018.5 with G2 reduced to 580 MW gmss. 5.0 cyde is the existing dearing time at the high side of TI0 transformer.

Stable at 5.514.5 with G2 at 580 MW (replace R-304 breaker at NAP and reduce G2 to 580 MW gross). Existing clearing time at faulted end is 4.5 cycles without margin AM Stable at 5.514.5 with both GI a11d 6 2 at 540 MW (replace R-304 breaker at NAP and reduce both GI and G2 to 540 MW). Existing clearing time at faulted end is 4.5 cycles without margin American Transmission Gmpany Page 57 of 102

G83314-J022/J023 ~nterim erati ti on and Impacts Re-Study Report-RO1 Primary ClearingTime, Prior Outage: SEC31 (SEGGVL, 398638870), (POB PSSs In Service) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation File Faulted Location Breakers Location Breakers Notes Clearine Base Base FltKEWNAP R-304 KEW R-304,3451 NAP R-304 6.516.5 FLTKEWXFHPROI I TI0 KWH 1 Q-303,1099,3450 1 KWL I 1066E, 1066W I Open Q-303 at KEW 1 6.518.5 A Stable at 6.018.5 with G2 at 620 (02 reduction to 620 gross). 5.0 cycle without margin is the existing clearing time at the high side of TI0 transformer.

-

Stable at 5.518.5 or Stable at 6.018.5 with G2 at 580 MW (62 reductionto 580 gross). 5.0 cycle without margin is the existing clearing time at the high side of TI0 transformer.

  • Stable at 5.514.5 with G2 580 MW - Replace R-304 breaker at NAP and 6 2 at 580 MW gross. Existing clearing time at faulted end is 4.5 cycles without margin Stable at 5.514.5 with G2 at 620 f#W gross. Existing clearing time at faulted end is 4.5 cycles without margin 1

Primary ClearingTime, Prior Outage: POB 1-2 (POB-Bl2,39433-38898), (POB PSSs In Service) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation I Low Generation I Base File Faulted Lpcation Breakers Location Breakers Notes Clearing* -

FIWWNAP R-304 KEW R-304,3451 NAP R-304

"'Stable at 5.514.5. Replace R-304 ~reakerat NAP. Existing clearing time at faulted end is 4.5 cycles without margin

-

Primary ClearingTime, Prior Outage: POB 2-3 (POB-B23,38898-39211), (POB PSSs In Service) Existing KEW Sub Event Element Pault Faulted End Remote Remote End Event Simulated High Generation I Low Generation File Faulted Loption Breakers Location Breakers Notes Clearing' Rscn Rscn FltPOBFJT L121 YOB 121,123 FJT 1-2,2-3 4.514.5

  • For stabili, GI needs to be resbi ed to 580 MW gmss I

Primary ClearingTime, Prior Outage: POB 4-5 (POB-B45,38900-38901), (POB PSSs In Senrice) Existing KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation Ae Faulted Lpcation Breakers Location Breakers Notes Clearing* Base Base FltKEWNAP R-304 KEW R304,3451 NAP R-304 6.516.5

"'Stable at 5.514.5 with G2 at 620 k JV (replace R-304 breaker at NAP and reduce G2 to 620 MW). Existing clearing time at faulted end is 4.5 cycles without margin American Transmission chmPany Page 58 of 102

G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation)

Primary ClearingTime, Prior Outage: 6832 (FOX-NAP, 38894-39556), (POB PSSs In Service) New KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation

)cation Breakers Location Breakers Notes Clearing* Base Base I FltKEWNAP I R-304 1 KEW R-304,3451 NAP R-304 4.516.5

'Stable at 4.514.5 with G2 restricted to 600 MW gmss (G2 restriction 600 MW gross with R-304 breaker at NAP replaced)

Primary Clearing Time, Prior Outage: POB 2-3 (POBB23,38898-39211!, (POB PSSs In Sewice) New KEW Sub Event Element Fault Faulted End Remote Remote End Event Simulated High Generation Low Generation File Faulted acation Breakers Location Breakers Notes Clearing* Base Base POB 121,123 FJT 1-2,23 4.514.5 To be stable at 4.514.5, GI needs 1 J be restricted to 580 MW gmss "To be stable at 4.514.5, GI needs to be restricted to 620 MW gross American Transmission C Page 59 of 102

G83314-J022tJ023 Interim Operation d d Impacts Re-Study Report-RO1 Table B.

1 - Stability Resultsfor 3-Phase Faults Cleared in Delayed (Breaker Failure) Time under Intact Conditions, Units Tripping Interim I (with G834/J023, with existing Kewaunee substation) re Events - lnter~mPer~od1 (May 2010-Aprll 2011) I American Transmission Company 1 Page 60 of 102

Page 61 of 102 G833/4-JO22/JO23 Interim Operation Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation)

I Event I Element I Event I Simulated I High Gen I LOW tien I

I File 1 Faulted I I I 1

BFIFOXPOBZ I L151 I FOX BFIFOXNAR 1 L6832 1 FOX 1 BFIFOWJT;! 1 971171 1 FOX BFlSECPOBl I Llll I SEC BFISECGVLl I LSEC31 I SEC BFICYPADN I LGYP~I I cn BFICYPFJT

- . 1I 971L51 1I CYI

'Relay upgradesor lnstalllng a series breaker desa !din Section 1.1 will address the issue.

" Relav uoarades described in Section 1.1 wlll addn ;the issue ad el;ibrades described in Section 1.Iwill add, she issue American Transmission Company Page 62 of 102

G833/4-J022IJ023Interim Operation and Impacts Re-Study Report-RO1 Table B.5- Stability Resultsfor Point Beach Bus Single Line-to-Ground Faults Cleared in Delayed Time under Intact Conditions Kewaunee substation)

Fault i- Interim 1 Location Element tripped Clearing 1 I I POB Bus 1 POBSEC 4.75124.5 POB BUS1 POB Bus 1-2 4,75112.5 2A wl E x ~ s t ~ nKEW a

Fault Failure Simulated Location Element Clearing

( tripped 1 POB Bus I I POBSEC 1 4.75124.5 POB Bus 1 I POB Bus 1-2 1 4.75112.5 POB Bus 2 I POB Bus 2-1 1 4,75112.5 POB Bus 2 I POB Bus 2-3 1 4.75112.5 POB Bus 3 I POB Bus 3-2 ( 4.75112.5 POB Bus 3 ( POB-KEW 1 4,75124.5 POB Bus 3 POB Bus 4 POB Bus 5 I POB BUs5-4 ( 4.751128 POB Bus 5 I POB-FOX 1 4 . 7 ~ ~ 5

    • Stable at 4,75112.0.As described in Section 1.1, Change Relay senlug (w~mnoutareaKerral~urerelay lcpraccucur, LUL rarrruo ur I oint Beach Bus Tie 2-3 to no more than 11 cycle total breaker failure clearing time for bus faults American Transmission Company Page 63 of 102

G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation) 1 ~oGion I Elementhipped I Clearing 1 Ul-h pal I -.., can I Bus 1O I PoB-sEc 1 4.75124.5 1 B POB Bus 1 POB Bus 2 I POB Bus2-1 I ~ 7 5 1 153 POB Bus 2 POB Bus 2-3 4.75112.5 POB Bus 3 POB Bus 3-2 4.75112.5 POB Bus 3 POB-KEW 4.75112.5 POB Bus 3 I POB Bus 3-4 1 4.75112.5 POB Bus 4 I POB Bus 4-3 1 4.75112.5 POB Bus 4 I POB BUS 4-5 1 4.75112.5 POB Bus 5 POB Bus 5 American Transmission Company Page 64 of 102

G83314-J022/5023 Interim Operation and Impacts Re-Study Report-RO1 Table B.6- Stability Results for GSU Single Line-to-Ground Faults Cleared in Delayed Time under Intact Conditions, Units Tripping Interim 1 (with G834/J023, with existing Kewaunee substation) w' 1 I 1 POB GSU BF Faults Breaker Fault Failure Simulated Location Element Clearing Interim 2A (with G834/J023 and G833/J022, I I POB GSU BF Faults Breaker Fault Failure Simulated Location Element Clearing Interim 2B (with G834/J023 and G833/JO 1 1 1 POB GSU BF Faults Breaker Fault Failure Simulated Location Element Clearing American Transmission Company Page 65 of 102

G833/4-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table B. 7- Stability Results for Auxiliary Transformer High Side Single Line-to-Ground Faults Cleared in Delayed Time under Intact Conditions, Units Tripping InterimI 1 (with G834/J023, with existing I I Kewaunee substation)

Faulted Interim 1 I

Element Element Tripped I

POB-SEC @

POB AUXl HS SFC Faulted Failure Element POB AUXl HS I POB Bus2" I

POB AUX2 HS I POB Bus4"'

-The Stability Model Time Step is 0.25 cycles, so a 13.3 cycle fault actually clears in 13.5 cycles.

"- POB-Forest Junction 345 kV line Tri~s.POB Generator 1 is Isolated.

-

"* POB ene era to; 2 'is isolated Interim 2A (with G834/J023 and G833/J02

-taulreo

.. . Breaker Element I Failure POB-SEC @

POB AUXl HS POB AUX2 HS Breaker Faulted Element Failure Element Tripped

- A 'a- -&

POB AUXl HS I POBBus2" I OK I _..

POB AUX2 HS I POB Bus4"' 1 OK I OK

  • -The Stability Model Time Step is 0.25 cycles, so a 13.3 cycle fault actually clears in 13.5 cycles.

-

" POB-Forest Junction 345 kV line Trips, POB Generator 1 is Isolated.

-

"* POB Generator 2 is isolated

"' ee substation)

Interim 2B (with G834/J023 and G833/J02L" Breaker Faulted Failure Element I

POB-FOX @

POB AUX2 HS FOX Breaker Faulted Failure Element Element Tripped 5.1113.3' 5.1113.3' m m s

-The Stability ModelTime Step is 0.25 cycles, so a 13.3 cycle fault actually clears in 13.5 cycles.

- POB-Forest unction 345-kV line Trips, POB Generator 1 is Isolated.

-

"** POB Generator 2 is isolated American Transmission Company Page 66 of 102

G83314-J022lJ023 ~nterimlo~eration and Impacts Re-Study Report-RO1 Table B.8- Stability R for GSU Three Phase 345 kVFaults Cleared in Primary (5.5 cycles, including I cycle margia) Time under Intact and Prior Outage Conditions, Units Tripping Interim 1 (with G834/J023,with existing Kewaunee substation)

Interim 1 Interim 1 American Transmission c/omPany Page 67 of 102

G833/4-J022/J023 1 n t e 4 Operation and Impacts Re-Study Report-RO1 Interim 2A (with G834/J023 and G833/J022,with existing Kewaunee substation)

American Transmission dompany Page 68 of 102

G833/4-J022IJ023 Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022,with new Kewaunee substation) 5.5 cyles di-cycle margin).

American Transmission C/ompany Page 69 of 102

G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Table B.9- Stability Resultsfor Auxiliary Transformer High Side 3-Phase Faults Cleared in Primary Time (6.1 cycles, including 1 cycle margin) under Intact and Prior Outage Conditions InterimI 1 (with G834/J023, with existing Kewaunee substation)

I I I

H~ighGeneratian-. Low Generation

'

Interim 1 ' I&<

5.75B.1

--

' 5.75 "SECGens Isolated 7 Low Generation I Prior Outage I - ..-,- .

Interim 1 "POB GEN 2 Isolated American Transmission Company Page 70 of 102

G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Prior I-Interim 2A (with G834/J023 and G833/J022, with existing Kewaunee substation)

I Uinh Canardinn

-

Inlerlm 2A wl exlstlng KEW I I nw Generation lnlerlm 2A wl ex~sllng I

Fault 5 7516 1 5 7516 1 FltPOBAXl FltPOBAXl L-CYP31 tiEi?Tm FltPOBAXl NAPL7l FltPOBAXl 971L51 FltPOBAXl Y-311 I FItPOBAX1 FltPOBAXl 1 :ii I FltPOBAXl 1 845

'SEC Gens Isolated

... . - .. . - ' .. I Fault Prior nlerini 2A 1 . ~ 1exisl~ng KE!I\!

5 7516 1 lnlerini 2A wl existing KE\N 5 7516.1 I "POB GEN 2 Isolated American Transmission Company

G83314-502215023 Interim Operation and Impacts Re-Study Report-RO1 Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation Hinh Ganaratinn Low Generation Prior FltPOBAXl FltPOBAXl FltPOBAXl FltPOBAXl 6832 FltPOBAXl 971L71 FltPOBAXl LSEC31 FltPOBAXl L-CYP31 FltPOBAXl T I0 FltPOBAXl NAPL71 FltPOBAXl 971L51 FltPOBAXl Y-311 FltPOBAXl 812 FltPOBAXl 823 FltPOBAXl 834 8 FltPOBAXl 4 5

'SEC Gens Isolated High Generalon I Low Generation Prior Fault Outage FltPOBAX2 None I OK" OK "POB GEN 2 isolated merican Transmission Company Page 72 of 102

G83314-J022lJ023Interim Operation and Impacts Re-Study Report-RO1 Table B.10- Stability Results for Kewaunee and Point Beach Generation Outage under Intact Conditions Interim 1 (with G834/J023, with existing Kewaunee substation)

UNlT TRlP I Interim I I

i Trip time UNITTRIP Low Gen POBGltn' POBG2tri POBGlGStri KEWGltri Interim 2A (with G834/J023 and G833/m77 w i t h ~ r i . v t i n cKewaunee substation)

I Interim 2A (wl existing

..-. ... I UNlT TRlP POBGltri POBG2tri POBGlG2tri Interim 2B (with G834/J023 and G833/J022, with new Kewaunee substation)

American Transmission Company Page 73 of 102

G83314-J022lJO23 ~nterimloperation and Impacts Re-Study Report-RO1 1 A~nendixC: Cornnetin9 Wind Generators 1 99 1 TBD (suspended) I Kewaunee-Mishimt 138 kV line I

C 427 WEC 98 TBD (suspended) Cypress 345 kV Substation G590 WEC 98 TBD (suspended) Tecumseh Rd 138 kV Substation

-- -

12-31-2011 Elkhart Lake-Forest Junction 138 kV line 12-01-2012 Forest Junction-Lost Dauphin 138 kV line American Transmission qmpany Page 74 of 102

G833/4-J022/J023 Interim Operation and Impacts Re-Study Report-RO1 Appendix D: Operating Restrictions American Transmission Company Page 75 of 102

G833/4-J022/J023 Interim Operation and Impacts Re-Study Report-RO1 With all stability upgrades assumed in-service and the Minimum Excitation Limiter settings for Point Beach and Kewaunee units modified, generation restrictions identified for each interim period are:

During Interim 1 period (2010 after G834lJ023 - 201 1 before G8331J022) iii. G1 at 560 MW (gross) under prior outage condition of 6832 (North Appleton-Fox River 345 kV line) iv. GI at 580 MW (gross) under prior outage condition of Point Beach Bus Tie 2-3 During Interim 2A period (Without Kewaunee project, 201 1 after G833lJ022 - beyond )

viii. G2 at 620 MW (gross) under prior outage of 121 (Point Beach-Forest Junction 345 kV line) ix. G2 at 620 MW (gross) under prior outage of 151 (Point Beach-Fox River 345 kV line)

x. G2 at 600 MW (gross) under prior outage of R304 (Kewaunee-North Appleton 345 kV line) xi. Both GI and G2 at 540 MW (gross) under prior outage of 6832 (North Appleton-Fox River 345 kV line) xii. G2 at 580 MW (gross) under prior outage of SEC31 (Sheboygan Energy Center-Granville 345 kV line) xiii. GI at 580 MW (gross) under prior outage of Point Beach Bus Tie 2-3 xiv. G2 at 620 MW (gross) under prior outage of Point Beach Bus Tie 4-5 During Interim 2B period (With Kewaunee project, 201 1 after G83315022 - beyond)
i. G2 at 600 MW (gross) under prior outage condition of 6832 (North Appleton-Fox River 345 kV line) ii. G1 at 580 MW (gross) under prior outage condition of Point Beach Bus Tie 2-3 American Transmission Company Page 76 of 102

683314-J022lJO23 Interim Operation and Impacts Re-Study Report-RO1 Appendix E: Short Circuit / Breaker Duty Analysis Results Scenario 1 = Existing system 23293.9 21160.4 9288 11100.6 Scenario 2 = Existingwith new GSU of POB G2 (Fall 2009-May 2010) 23878.5 21419.7 9288 11100.6 Scenario 3 =With G834 (J023) and new GSU of POB GI (May 2010-May 2011) 24516 21758.5 9288 11100.6 I

Scenario4 = With G83314 (J02.213) with existing Kewaunee (May 2011-beyond) 24660.4 21927.2 9288 11100.6 Scenario 5 =With G83314 (J02213) with new Kewaunee (May 2011-beyond) 24801.6 22017 9288.2 11100.7

    • Scenario 6 =With G83314 (J02213) with new Kewaunee and potential East sub 25448.4 22749.3 9786.8 11954.8
    • Scenario 7 =With G83314 (~02d3)with new Kewaunee and ~otentialEasffNorth I sub with line conversion

\ ,

26615.1 23988.7 10915.9 13402.2

  • POB G I and G2 ofline and Q-303 out of service
    • Scenario 6 and 7 were also studied to provide maximum and minimum fault duties that may appear due to potentialfuture bansmission reinforcement.

Table E.2 - Thevenin Equivalent Impedances in Ohms corresponding to Maximum Fault Duty Pos Seq. Neg. Seq. Zero Seq.

Scenario 1 = Existing system 0.492146+ j 9.400272 0.563439t j 9.4053 0.589203+ j 6.794582 Scenario 2 = Existingwith new GSU of POB G2 (Fall 2009-May 2010) 0.47915+ j 9.28685 0.547887+ j 9.291845 0.530596+ j 6.397666 I

Scenario 3 = With G834 (J023) and new GSU of POB G I (May 2010-May 2011) 0.476195+ j 9.141977 0.648689+ j 9.140315 0.480063+ j 6.038944 Scenario 4 =With G83314 (J02213) with existing Kewaunee (May 201$-beyond) 0.480694+ j 9.071247 0.754597+ j 9.060422 0.480063t j 6.038944 I

Scenario 5 =With G83314 (J02213) with new Kewaunee (May 2011-beyond) 0.500629+ j 9.033035 0.774579+ j 9.021229 0.483616+ j 5.974935

    • Scenario 6 = With G83314 (J02213) with new Kewaunee and potential East sub 0.483549 + j 8.742337 0.734901 + j 8.732362 0.491449 + j 5.944132
    • Scenario 7 =With G83314 (J02213) with new Kewaunee and potential EastlNorth sub with line conversion 0.455713 + j 8.290790 0.685388 + j 8.282391 0.496780 + j 5.818807
    • These scenarios were also studied to provide maximum and minimum fault duties that may appear due to potential future transmission reinforcement.

American Transmission Company Page 77 of 102

G83314-J022/1023 Interim Operation and Impacts Re-Study Report-RO1 American Transmission Company Page 78 of 102

G83314-J022N023 Interim Operation and Impacts Re-StudyReport-RO1 Page 79 Of 102

G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Appendix P: Study Criteria American Transmission Company Page 80 of 102

G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Study Criteria F. 1 Contingencies For stability analysis, a set of branches in the vicinity of the generatorlpower plant of concern is selected as contingencies, based on engineering judgment. Fault analysis is performed for the following six categories of contingency conditions:

1. Three-phase fault cleared in primary time with an otherwise intact system.
2. Three-phase fault cleared in delayed clearing time (i.e. breaker failure conditions) with an otherwise intact system.
3. Three-phase fault cleared in primary clearing time with a pre-existing outage of any other transmission element.
4. Single Line Ground (SLG) bus section fault cleared in primary clearing time with an otherwise intact system.
5. SLG internal breaker fault cleared in primary clearing time with an otherwise intact system.
6. SLG fault of double circuits on common tower cleared in primary time with an otherwise intact system.

For power flow analysis, contingencies include:

1. N-1 contingencies - all lines and transformers operated at 69kV and above in the following control areaslzones: ATC Planning Zones 1-5 and ties to those zones and all branches of voltage level 69kV and above in the Dairyland Power Cooperative, Northern States Power Control Area, Commonwealth Edison, and Alliant Energy West control areas.
2. Selected N-2 and multiple contingencies that ATCLLC has determined to be significant.

F.2 Monitored Elements F.2.1 Intact System, N-1, N-2 and Special Multiple Contingency Evaluation Using Linear Transfer Analysis Methods All load carrying elements operated at 69kV and above in the following control areaslzones were studied: ATCLLC Planning Zones 1-5 and ties to those zones, and all branches of voltage level 69kV and above in the Dairyland Power Cooperative, Northern States Power Control Area, Commonwealth Edison, and Alliant Energy West control areas.

A Transmission Reliability Margin (TRM) of 5% must be applied to the MVA ratings of each monitored ATCLLC element. Violations reported will be based upon the adjusted MVA rating.

American Transmission Company Page 81 of 102

G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 F.3 Thermal Loading Criteria F.3.1 Injection Violations Generation injection violations include: 1) thermal violations of the transmission elements that connect the Generator to the rest of the transmission network (outlet congestion); 2) thermal violations of the transmission elements that have a transfer distribution factor (TDF) 2 5% for NERC Category A (system intact) conditions and TDF 2 20% for NERC Category B contingencies anywhere in the studied system in relation to real power injected at the Point of Interconnection (POI) when delivered to all of MISO; or 3) thermal violations created by the loss of a transmission element connected to the generator interconnection substation.

F.3.2 Operating Restriction Calculation Allowable Output =

TDF F.4 Steady State Under Voltage Criteria F.4.1Intact System, N-1 and Special Multiple Contingency Evaluation Using ACCC Under intact system conditions, the voltage magnitude of all transmission system buses with a decrease of 0.01 per unit due to the Generator must not be lower than 0.95 per unit. Under contingency conditions, the voltage magnitude of all transmission system buses with a decrease of 0.01 per unit, due to the Generator, must not be lower than 0.90 per unit.

F.4.2N-2 Contingency Evaluation Power flow solutions must converge for a selected number of N-2 contingencies in the electrical proximity of the studied Generator. Divergence of a power flow solution indicates potential voltage collapse. A "fix" must be identified for any non-converging power flow simulation and may include generator operating restrictions. v o t e : Non-convergence may be due to solution settings such as switched shunt operation andlor LTC action.]

F.5 Anwlar Stability Criteria Critical Clearing Time (CCT) is a period relative to the start of a fault, within which all generators in the system remain stable (synchronized). CCT is obtained from simulation.

fault using the existing system facilities. MECT is dictated by the existing system facilities. In any contingency, if the computed CCT is less than the MECT plus a margin determined by ATC (1.0 cycle for studies using estimated generator data and 0.5 cycles for studies using confirmed generator data), it is considered an unstable situation and is unacceptable. Otherwise, it is considered acceptable transient stability performance.

American Transmission Company Page 82 of 102

G833/4-J022/J023 Interim Operation and Impacts Re-Study Report-RO1 Longer time-domain simulations must be performed on faults cleared at the CCT to examine dynamic stability. Simulations will typically cover 20 seconds of system dynamics and machine angle oscillations must meet the damping criteria in the ATC Planning Criteria.

Note that ATC stability criteria and NERC stability criteria differ on the study assumptions used for breaker failure analysis. ATC study criterion models breaker failure by modeling a three-phase fault during the primary time, reduced to SLG fault if the failed breaker is an Independent Pole Operated (IPO) breaker during delayed clearing and cleared at the end of the delayed clearing time. On the other hand, NERC study criterion assumes a single line-to-ground fault for the entire breaker failure analysis. Hence, the CCT computed from ATC stability criteria is always less than or equal to the value computed using the NERC study criteria. This report assumes ATC stability criteria unless otherwise stated.

The time-domain simulations must also be reviewed for compliance with the transient and dynamic voltage standards in the ATC Planning Criteria. Voltages of all transmission system buses must recover to be at least 70% of the nominal system voltages immediately after fault removal and 80% of the nominal system voltages in 2.0 second after fault removal.

American Transmission Company Page 83 of 102

G83314-J022/JO23 ~ntermjOperation and Impacts Re-Study Report-RO1 Appendix 6 : Estimated Allowable MW Output from 6834 or 6833 under SpringIFall or Winter Emergency Ratings I cypress-Arcadian 345-k" line I 968 I kV line P0intBeach-shebo~ginEnerg~Center345~ 98.7 1 519.3 119.80% 1 546.61 Point Beach-Sheboygan~ n e r g ~

1311 CypressArcadian 345-kV line 516.2 540.5 23.37% 568.94 Center 345-kV line Point Beach-SheboyganEnergy Center 345-CypressArcadian 345kV line 1076 498.7 519.3 19.80% 546.61 kV line

1. The Pre and Post MV MW output. The old valu New Pre MVA New Post MVA 9--L flow were re-estimated fiom the previous interim operations study report in order to calculate new required ratings and new allowable s in the previous study report was obtained fiom Table A.5

,-

old Pre MVA old Post MVA + 6 MW x DF American Transmission Qompany Page 84 of 102

G83314-J022/JO23 1 n t e 4 Operation and Impacts Re-Study Report-RO1 S

2. The Pre MVA flow w re-estimated fiom the previous interim operations study report in order to calculate new required ratings and new allowable MW output. The old values in e previous study report was obtained fiom Table A.5 New Pre MVA old Pre MVA + 6 MW x DF
3. The Post MVA flow 1

re-estimated fiom the previous interim operations study report in order to calculate new required ratings and new allowable MW output. The old value previous study report was fiom the case (Scenario 5 with G8331834 and all wind loo%, with 201 1 Kewaunee modeled) old Post MVA + 12 MW x DF Note: The results shown 4the above tables are based on 50% peak load cases.

Ci American Transmission ompany Page 85 of 102

G833/4-J02ZNOW InterimOperation and Impacts Restudy Report-RO1 I I Il Open bustie during

- I -

I 1 zFEz: 1 1 I I I I 1

I II I I I I I I I now KP 62620 5.W4.5 11 I I I I I No~.5l)cvdek I I I I I KP CCT - 5.W.O KP -

CCT 5.546.0

&P,F -

CCT 51V6.0 KP.F CCT - 51116.0 KP.F CCT- 5.D16.0 KP.F CCT - 5Y6.0 KP,F -

CCT 5Y6.0 KP,F CCT -5516.0 KP,F M-5.56.0 A15.75B.1 tasted deariw 6rne -

UV bip P (IS!+/ l.52ls, 345kV 1st 1.C&, 315kV md 1.5625)

CCT-5.5B.O KP CCT-5.016.0 -

CCT 5.016.0 KP -

CCT 5.016.0 KP -

CCT 5.W.O KPS CCT -5.016.0 KP,S CCT- 5.016.0 KP -

CCT 5516.0 I

American Transmission Company Page 88 bf 102

G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Appendix I: Minimum Excitation Limits at Point Beach and Kewaunee during Interim Periods American Transmission Company Page 90 of 102

G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Minimum Excitation Limits at Point Beach and Kewaunee during Interim Periods As noted in this G833lJ022-G834lJ023 Interim Operations Re-Study Report, Point Beach and Kewaunee units need to maintain certain reactive power output in anticipation of critical contingency conditions. Reactive power output from a synchronous machine has an impact on the transient stability of the unit. Typically, when a unit produces relatively small reactive power output or absorbs reactive power from transmission system (under-excitation), the unit tends to be less stable under a fault condition. The results of the interim operation study indicate that a certain level of reactive power output (over-excitation) needs to be maintained to ensure generation stability in anticipation of critical fault conditions. This is primarily due to too many generators with few outlets out of Fox Valley area.

The minimum excitation limiter, which may also be referred to as the under-excited reactive ampere limit or under-excitation limiter, settings are an effective mechanism to ensure a minimum level of unit excitation. However, limiting the amount of under-excited operation can negatively affect the ability to control system and plant voltages under lighter system load conditions where transmission line charging may result in higher system voltages. Therefore, any minimum excitation limits need to be coordinated with voltage control requirements.

The "interim" solutions described in the Interim Operations Re-Study Report would be followed by the completion of the necessary Network Upgrades identified in the G833lJ022-G834lJ023 System Impact Re-Study Report, which has yet to be posted. The Network Upgrades would be the long-term solutions which ensure a wider operating envelope for the local transmission system and the interconnected generators by permitting generating unit operation at near unity or leading power factor, or at least provide a foundation to achieve the wider operating envelop through additional transmission reinforcement in the area that may be needed in the future.

Transient Stability Studies To estimate minimum excitation limits (MVAR output levels), it is assumed that the stability upgrades identified for each interim period are in-service (see G833lJ022-G834lJ023 Interim Operation Re-Study Report). Various MVAR output levels at Point Beach and Kewaunee 345 kV buses were evaluated using two different generation dispatch scenarios during the three interim periods. Critical faults under system intact condition identified in the interim operation study were applied, which are:

Fault on Q-303 with breaker failure at Point Beach (post-May 2010 until May 201 1 only since a series breaker is proposed to be installed by May 201 1)

Fault on R-304 with breaker failure at Kewaunee (post Kewaunee bus reconfiguration project period only)

American Transmission Company Page 91 of 102

G83314-J022IJO23 Interim Operation and Impacts Re-Study Report-RO1 With stabilitv upmades for each interim period in-service and based on the studv results shown in Table 1.1 through 1.4, the Point Beach and Kewaunee units would need to maintain the following minimum excitation levels to ensure synchronism of these and nearby generators:

For May 2010 - May 201 1 (With Point Beach Unit #1 u p ~ a d e dand with the existing Kewaunee bus confirnation) o Point Beach G1 and G2: 48 MVAR or higher per unit o Kewaunee GI: 41 MVAR or higher For May 2011 until completion of the Kewaunee bus reconfiguration proiect w i t h both Point Beach Units #1 and #2 upgraded),

o Point Beach Gl and G2: 70 MVAR or higher per unit o Kewaunee GI: 58 MVAR or higher Post completion of the Kewaunee bus reconfiguration proiect (With both Point Beach Units #1 and #2 upgraded]

o Point Beach Gl and G2: 68 MVAR or higher per unit o Kewaunee GI: 49 MVAR or higher These minimum excitation limits were estimated by testing the critical system faults.

Additional study for all other relevant system faults was not performed because of the following reasons:

For Interim 1 period (see Table I.1), the critical faults under system intact conditions are more severe at the low generation scenario, and the estimated minimum excitation limits of Kewaunee and Point Beach units are either same or higher than their W A R outputs at the 352 kV voltage schedule where all other faults under system intact conditions were proven to be stable in the interim operation study. Therefore, additional study for all other relevant system faults under system intact conditions was not performed. For prior outage conditions, it is recommended to maintain at least 354 kV at the Point Beach and Kewaunee 345 kV buses (note: 354 kV is high-end of the preferred voltage range at Point Beach) in anticipation of critical faults. This is to ensure stable system even with faults under prior outage conditions which appear to be more severe at high generation scenario and were proven to be stable at the 352 kV voltage level with interim upgrades and operating restrictions implemented.

As mentioned above, the critical faults under system intact conditions appear to be more severe at the low generation scenario according to the results of the interim operation study, and the estimated minimum excitation limits of Kewaunee and Point Beach units are higher than their MVAR outputs at the 352 kV voltage schedule of low generation scenario (see Table 2.4.1) where all other faults under system intact conditions were proven to be stable in the interim operation report. 'l'herefore, additional study for an other relevant system taults under system intact conditions was not performed. For prior outage conditions, it is also recommended to maintain at least 354 kV (high-end of the preferred voltage range at Point Beach) in anticipation of critical faults. This is to ensure stable system even with faults under prior outage condition which appear to be more severe at high generation scenario and were proven to be stable at 352 kV.

American Transmission Company Page 92 of 102

G83314-J0221J023 Interim Operation and Impacts Re-Study Report-RO1 Steady State Voltage Control Studies at Minimum System Load Conditions Using a minimum load case with 40% of 2010 summer peak load condition, three scenarios were built and studied to c o n f i i if any high voltages occur at Point Beach 345 kV and Kewaunee 3451138 kV buses under various conditions. The scenarios are:

Scenario 1: Minimum load case with G834-J023 added

= Scenario 2: Minimum load case with G834/J023-G833/J022 added Scenario 3: Minimum load case with Scenario 2 and with Point Beach G2 and Kewaunee G1 offline.

The minimum reactive power outputs of Point Beach and Kewaunee units in each case were adjusted to match with the estimated minimum excitation limits as follows:

For Scenario 1:

o Point Beach G1 and G2: 48 MVAR o Kewaunee GI: 41 MVAR For Scenario 2:

o Point Beach Gl and G2: 70 MVAR o Kewaunee GI: 58 MVAR No study was performed using the minimum excitation limits of Interim 2B period since no significant impact is expected due to the Kewaunee bus reconfiguration project.

For the study, the following critical contingencies were tested.

System Intact Open Line-end

i. Open North Appleton end of R-304 ii. Open Granville end of L-SEC3 1 iii. Open Arcadian end of L-CYP31 iv. Open Forest Junction end of L121
v. Open Fox River end of L15 1 N-1 or multiple contingency analyses are not performed since these conditions will lower voltages due to increased system impedances.

Monitored elements are Point Beach 19 kV and 345 kV, and Kewaunee 345 kV and 138 kV bus voltages. The following criteria are assumed for the monitored elements.

Point Beach 19 kV bus voltage: 95 percent to 105 percent of nominal voltage Point Beach 345 kV bus voltage: Not exceed 358 kV (high end of normal voltage range) under system intact condition. Not exceed 360 kV (slightly lower than high end of absolute voltage range) under a line end open

--Kewaunee --.

345 kV bus voltage: 95 percent to 105 percent of nominal voltage a

  • Kewaunee 138 KV bus voltage: 14U KV ana 143 K V unaer system mmct ana
  • * - . T I 1 contingency conditions In conclusion, no high voltage conditions were found as shown in Table 1.4. Sensitivity analysis was performed by turning on some of the capacitor banks in the area such as New Holstein, Glenview, Howard and Shoto. As a result, high voltage at Kewaunee 138 kV bus is identified with the Granville end of L-SEC3 1 open. However, the voltage issue American Transmission Company Page 93 of 102

G83314-J022IJ023 Interim Operation and Impacts Re-Study Report-RO1 can be addressed by remedial actions such as turning off some of the capacitor banks in the area as described in Table 1.5.

American Transmission Company Page 94 of 102

G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table 1.1. Minimum Excitation Limit Study Results for Interim 1 (May 2010 - May 2011)

/ Interim 1 (KV and MVAR level at POB and KEW for stable system under critical faults)

I Critical Fault under Intact High Gen scenario' Low Gen scenario' Comment (tested clearing times) 350 kV or higher 35 1 kV or higher L l l l BF @

(POB G l : 43.4 (POB GI: 42.7 POB POB G2: 43.4 POB G2: 42.7 (3.5/10.0/4.5)

KEW GI: 40.9) KEW G l : 26.1) 348 kV or higher 349 kV or higher L l 5 l BF @ Thus, minimum (POB G l : 12.0 (POB G l : 33.3 POB excitation limits are:

POB G2: 12.0 POB G2: 33.3 (3.5/10.0/4.5) POB G l : 47.4 KEW GI : 20.1) KEW G l : 17.5)

POB G2: 47.4 350 kV or higher 352 kV or higher KEW GI: 40.9 Q303 BF @

(POB G1: 43.4 (POB G1: 47.4 POB POB G2: 43.4 POB G2: 47.4 (3.5/10.0/6.5)

KEW GI: 40.9) KEW G l : 30.4)

Table 1.2. Minimum Excitation Limit Study Results I

for Interim 2A (May 2011 until Kewaunee Reconfiguration Complete)

I Interim 2A (KV level at POB and KEW for stable system under critical faults)

Critical Fault I

under Intact High Gen scenario' Low Gen scenario' Comment (tested clearing times) 35 1 kV or higher 352 kV or higher L l l l BF @

(POB G l : 69.6 (POB Gl: 60.1 POB POB G2: 69.6 POB G2: 60.1 (3'519'014'5)

KEW GI: 57.5) KEW G l : 35.8) 350 kV or higher 352 kV or higher Thus, minimum L l 5 l BF @

(POB G l : 53.7 (POB G l : 60.1 excitation limits are:

POB POB G2: 53.7 POB G2: 60.1 POB G l : 69.6 (3'5'Y'5'4'5)

KEW GI: 46.9) KEW G l : 35.8) POB G2: 69.6 KEW GI: 57.5 American Transmission Company Page 95 of 102

G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table 1.3. Minimum Excitation Limit Study Results for Interim 2B (Post Kewaunee Reconfiguration)

I Interim 2B (KV level at POB and KEW for stable system under critical faults)

I I Critical Fault I I I 1I under Intact (tested clearing I High Gen scenario1 I Low Gen scenario1 / Comment times) - I I I 35 1 kV or higher 352 kV or higher L111 BF @

(POB G l : 67.2 (POB GI: 58.6 POB POB G2: 67.2 POB G2: 58.6 (3+5".014.5)

KEW ~ 148.9) : KEW G l : 27.3) 349 kV or higher 352 kV or higher L l 5 l BF @

(POB G l : 35.6 (POB GI: 58.6 POB Thus, minimum POB G2: 35.6 POB G2: 58.6 (3.519.514.51 excitation limits are:

KEW G1 27.1) KEW  : 27.3)

POB GI: 67.2 POB G2: 67.2 Q303 BF @ KEW GI: 48.9 POB 348 kV or higher 35 1 kV or higher R304 BF @

(POB G1: 20.1 (POB GI: 53.4 KEW POB G2: 20.1 POB G2: 53.4 (3'519'5/4'5)

KEW GI: 16.4) KEW G l : 22.9)

1. Approximate MVAR change at Point Beach and Kewaunee:

High generation scenario:

o 1kV change at Point Beach for every 16 MVAR change o 1kV change at Kewaunee for every 11 MVAR change Low generation scenario:

o 1kV change at Point Beach for every 5 MVAR change o 1kV change at Kewaunee for every 4.5 MVAR change American Transmission Company Page 96 of 102

683314-J022IJ023 Interim Operation and Impacts Re-Study Report-RO1 American Transmission Company Page 98 of 102

683314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Table 1.5. Voltages at Point Beach and Kewaunee Under System Intact and Contingencies Bus I Open North Appleton end of Kewaunee-North I Open Granville end of Granville-Shebovgan Open Forest Junction end of Point Beach- I Open Fox River end of Point Beach-Fox River American Transmission Company Page 99 of 102

@33&302%J0;53 En-Page 100 o f 102

G83314-J022lJ023 Interim Operation and Impacts Re-Study Report-RO1 Appendix J: Unit Restriction Due to Stability under Prior Outage Conditions in Table ES-3 during One of Point Beach Units offline American Transmission Company Page 101 of 102

G833/4-.JO22N023Infer& Operation and Impacts Re-Study Report-RO1 existing Kewa~nee)

L121 at POB POB Bus tie 2-3 4.514.5 OK R304 at KEW L121 5.514.5 OK OK OK OK R304 at KEW L151 5.514.5 OK OK OK OK 6832 at FOX R-304 4.514.5 OK OK OK OK Interim 2A (With G83314J022r3, With R-304 at KEW 6832 5.514.5 OK OK OK OK existing Kewaulee)

R-304 at KEW LSEC31 5.514.5 OK OK OK OK LIZ1 at POB POB Bus tie 2-3 4.514.5 OK OK R-304at KEW POB Bus tie 4-5 5.514.5 OK OK OK OK

- -

R-304 at KEW 6832 4.514.5 OK OK OK OK Interim 28

( W i G833/4J022/3, With -

new Kewaune?)

L121 at POB POB Bus tie 2-3 45/45 OK OK 1 of Point Beach Bus tie 2-3 followed by L121 fault isolates Point Beach GI to the remainingline L111. Therefore, taking the Point Beach Bus tie 2-3 out of senrice g outage window does not eliminate the POB GI stability issue for L121 fault under Point Beach Bus tie 2 3 out of s e ~ c eThus,

. follow the operating restriction for the G833/4J022/3 Interim Operation Re-study Report American Transmission C mpany 4 Page 102 of 102