{{#Wiki_filter:December 13, 2013 EN 13-043 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION | {{#Wiki_filter:December 13, 2013 EN 13-043 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee: NextEra Energy Duane Arnold, LLC EA-13-182 Duane Arnold Energy Center Docket No.: 50-331 | ||
Licensee: NextEra Energy Duane Arnold, LLC | |||
==Subject:== | ==Subject:== | ||
ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that a Notice of Violation will be issued on or about December 18, 2013, to NextEra Energy Duane Arnold, LLC (NextEra) for a violation associated with a White Significance Determination Process finding identified during an inspection of the Duane Arnold Energy Center. This White finding, an issue of low to moderate safety significance, will require additional U.S. Nuclear Regulatory Commission (NRC) inspections. It involves the failure of Duane Arnold personnel to prescribe a work instruction of a type appropriate to the circumstances for the re-assembly of the | ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that a Notice of Violation will be issued on or about December 18, 2013, to NextEra Energy Duane Arnold, LLC (NextEra) for a violation associated with a White Significance Determination Process finding identified during an inspection of the Duane Arnold Energy Center. This White finding, an issue of low to moderate safety significance, will require additional U.S. Nuclear Regulatory Commission (NRC) inspections. It involves the failure of Duane Arnold personnel to prescribe a work instruction of a type appropriate to the circumstances for the re-assembly of the A standby diesel generator lube oil heat exchanger. | ||
Specifically, the work instruction did not contain sufficient detail and acceptance criteria, appropriate torque values, and operating experience information to ensure the heat exchanger gasket was properly compressed. This contributed to the catastrophic failure of the heat exchanger gasket during a maintenance run of the engine on March 8, 2013, rendering the A standby diesel generator unavailable. | |||
A Notice of Violation is included based on | A Notice of Violation is included based on NextEras failure to meet 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, which requires, in part, that activities affecting quality shall be prescribed by documented instructions of a type appropriate to the circumstances and be accomplished in accordance with these instructions. In accordance with the NRC Enforcement Policy, the NOV is considered an escalated enforcement action because it is associated with a White finding. | ||
NextEra attended a Regulatory Conference on November 5, 2013, and presented its assessment of the significance of the finding. After reviewing the information developed during the inspection, and the information provided by NextEra, the staff concluded that the finding is appropriately characterized as White. | |||
NextEra attended a Regulatory Conference on November 5, 2013, and presented its assessment of the significance of the finding. After reviewing the information developed during the inspection, and the information provided by NextEra, the staff concluded that the finding is appropriately characterized as White. | It should be noted that the licensee has not been specifically informed of the enforcement action. The schedule of issuance and notification is: | ||
Mailing of Final Significance Determination December 18, 2013 Telephone Notification of Licensee December 18, 2013 The State of Iowa will be notified. | |||
It should be noted that the licensee has not been specifically informed of the enforcement action. The schedule of issuance and notification is: | CONTACTS: Lauren Casey, OE, (301) 415-1038 Nick Hilton, OE, (301) 415-2741 | ||
The State of Iowa will be notified. | |||
CONTACTS: | |||
ADAMS ML13347B051 OFFICE OE:ES | Distribution: EN-13-043, December 13, 2013 OWFN OWFN TWFN 3WFN Regional Offices Chair. MacFarlane EDO OCFO NMSS RI RII Comm. Svinicki DEDR OIS NSIR RIII RIV Comm. Apostolakis DEDMRS FSME OP CENTER Comm. Magwood OE RES MAIL Comm. Ostendorff OGC ACRS Public SECY NRR RES OE staff OCA OI OPA OIG OIP Electronic DISTRIBUTION: | ||
R. Zimmerman, OE N. Hilton, OE L. Casey, OE OE r/f EN binder X PUBLIC X NON-SENSITIVE ADAMS ML13347B051 OFFICE OE:ES OE:BC NAME LCasey NHilton DATE 12/11/2013 12/13/2013 OFFICIAL RECORD COPY}} | |||
Revision as of 10:27, 4 November 2019
| ML13347B051 | |
| Person / Time | |
|---|---|
| Site: | Duane Arnold |
| Issue date: | 12/13/2013 |
| From: | Casey L, Nick Hilton NRC/OE |
| To: | |
| Casey L | |
| References | |
| EA-13-182 EN-13-043 | |
| Download: ML13347B051 (2) | |
Text
December 13, 2013 EN 13-043 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee: NextEra Energy Duane Arnold, LLC EA-13-182 Duane Arnold Energy Center Docket No.: 50-331
Subject:
ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that a Notice of Violation will be issued on or about December 18, 2013, to NextEra Energy Duane Arnold, LLC (NextEra) for a violation associated with a White Significance Determination Process finding identified during an inspection of the Duane Arnold Energy Center. This White finding, an issue of low to moderate safety significance, will require additional U.S. Nuclear Regulatory Commission (NRC) inspections. It involves the failure of Duane Arnold personnel to prescribe a work instruction of a type appropriate to the circumstances for the re-assembly of the A standby diesel generator lube oil heat exchanger.
Specifically, the work instruction did not contain sufficient detail and acceptance criteria, appropriate torque values, and operating experience information to ensure the heat exchanger gasket was properly compressed. This contributed to the catastrophic failure of the heat exchanger gasket during a maintenance run of the engine on March 8, 2013, rendering the A standby diesel generator unavailable.
A Notice of Violation is included based on NextEras failure to meet 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, which requires, in part, that activities affecting quality shall be prescribed by documented instructions of a type appropriate to the circumstances and be accomplished in accordance with these instructions. In accordance with the NRC Enforcement Policy, the NOV is considered an escalated enforcement action because it is associated with a White finding.
NextEra attended a Regulatory Conference on November 5, 2013, and presented its assessment of the significance of the finding. After reviewing the information developed during the inspection, and the information provided by NextEra, the staff concluded that the finding is appropriately characterized as White.
It should be noted that the licensee has not been specifically informed of the enforcement action. The schedule of issuance and notification is:
Mailing of Final Significance Determination December 18, 2013 Telephone Notification of Licensee December 18, 2013 The State of Iowa will be notified.
CONTACTS: Lauren Casey, OE, (301) 415-1038 Nick Hilton, OE, (301) 415-2741
Distribution: EN-13-043, December 13, 2013 OWFN OWFN TWFN 3WFN Regional Offices Chair. MacFarlane EDO OCFO NMSS RI RII Comm. Svinicki DEDR OIS NSIR RIII RIV Comm. Apostolakis DEDMRS FSME OP CENTER Comm. Magwood OE RES MAIL Comm. Ostendorff OGC ACRS Public SECY NRR RES OE staff OCA OI OPA OIG OIP Electronic DISTRIBUTION: