{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL | {{#Wiki_filter:UNITED STATES | ||
P. Fessler -2- Experience with previous baseline design inspections of similar depth and length has shown that this type of inspection is extremely resource intensive, both for the NRC inspectors and the licensee staff. | NUCLEAR REGULATORY COMMISSION | ||
P. Fessler -3- inspection in the | REGION III | ||
REQUEST FOR INFORAMTION | 2443 WARRENVILLE RD. SUITE 210 | ||
REQUEST FOR INFORAMTION | LISLE, IL 60532-4352 | ||
REQUEST FOR INFORAMTION | April 8, 2016 | ||
REQUEST FOR INFORAMTION | Mr. Paul Fessler | ||
Chief Nuclear Officer | |||
DTE Energy Company | |||
Fermi 2 - 210 NOC | |||
6400 North Dixie Highway | |||
Newport, MI 48166 | |||
SUBJECT: FERMI POWER PLANT, UNIT 2 - REQUEST FOR INFORMATION FOR AN | |||
NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION; | |||
INSPECTION REPORT 05000341/2016007 | |||
Dear Mr. Fessler: | |||
On August 1, 2016, the U. S. Nuclear Regulatory Commission (NRC) will begin a triennial | |||
baseline Component Design Bases Inspection at Fermi Power Plant, Unit 2. This inspection | |||
will be performed in accordance with NRC Baseline Inspection Procedure 71111.21. | |||
The Component Design Bases Inspection focuses on the design, maintenance, and operation | |||
of risk-significant components associated with one or more accident scenario or systems. The | |||
components to be reviewed during this baseline inspection will be identified during the in-office | |||
preparation week that occurs prior to the first onsite inspection week. In addition, operating | |||
experience issues, associated with the component samples, will also be selected for review. | |||
The inspection team may request scenarios to be performed on the simulator. This request | |||
would require support from your simulator staff to validate scenarios, simulator time, and a crew | |||
to perform the actions which would most likely occur during the second onsite week. The team | |||
will work closely with your staff early on during the inspection process to ensure this activity can | |||
be accomplished with minimal impact. | |||
The inspection will include 3 weeks onsite. The inspection team will consist of 6 NRC | |||
inspectors, of which 5 will focus on engineering/maintenance and 1 on operations. The | |||
current inspection schedule is as follows: | |||
Onsite weeks: August 1 - 5, 2016; | |||
August 15 - 19, 2016; and | |||
August 29 - September 2, 2016. | |||
The team will be preparing for the inspection, mainly during the week of July 25 - 29, 2016, | |||
as discussed in the enclosure. | |||
P. Fessler -2- | |||
Experience with previous baseline design inspections of similar depth and length has shown | |||
that this type of inspection is extremely resource intensive, both for the NRC inspectors and the | |||
licensee staff. In order to minimize the inspection impact on the site and to ensure a productive | |||
inspection for both parties, we have enclosed a request for information needed for the | |||
inspection. | |||
It is important that all of these documents are up-to-date and complete in order to minimize the | |||
number of additional documents requested during the preparation and/or the onsite portions of | |||
the inspection. Insofar as possible, this information should be provided electronically to the lead | |||
inspector. The information request has been divided into three groups: | |||
The first group lists information necessary for our initial inspection scoping activities. | |||
This information should be provided to the lead inspector no later than June 13, 2016. | |||
By June 24, 2016, the lead inspector will communicate the initial selected set of | |||
approximately 20 components. | |||
The second group of documents requested is those items needed to support our | |||
in-office preparation activities. This set of documents, including the calculations | |||
associated with the initial selected components, should be provided to the lead | |||
inspector at the Regional Office no later than July 18, 2016. During the in-office | |||
preparation activities, the team may identify additional information needed to support | |||
the inspection. | |||
The last group includes the additional information above as well as plant specific | |||
reference material. This information should be available to the team onsite on | |||
August 1, 2016. It is also requested that corrective action documents and/or | |||
questions developed during the inspection be provided to the lead inspector as | |||
the documents are generated. | |||
The lead inspector for this inspection is Mr. Néstor J. Féliz Adorno. We understand that our | |||
licensing contact for this inspection is Mr. Jason Haas of your organization. If there are any | |||
questions about the inspection or the material requested in the enclosure, please contact the | |||
lead inspector at 630-829-9739 or via e-mail at Nestor.Feliz-Adorno@nrc.gov. | |||
This letter does not contain new or amended information collection requirements subject | |||
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information | |||
collection requirements were approved by the Office of Management and Budget, Control | |||
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required | |||
to respond to, a request for information or an information collection requirement unless the | |||
requesting document displays a currently valid Office of Management and Budget Control | |||
Number. | |||
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public | |||
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy | |||
of this letter, its enclosure, and your response (if any) will be available electronically for public | |||
P. Fessler -3- | |||
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) | |||
component of the NRC's Agencywide Documents Access and Management System (ADAMS). | |||
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html | |||
(the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA/ | |||
Néstor J. Féliz-Adorno, Senior Reactor Inspector | |||
Engineering Branch 2 | |||
Division of Reactor Safety | |||
Docket No. 50-341 | |||
License No. NPF-43 | |||
Enclosure: | |||
Information Request for Component Design | |||
Bases Inspection | |||
cc: Distribution via LISTSERV | |||
REQUEST FOR INFORAMTION - COMPONENT DESIGN BASES INSPECTION | |||
Inspection Report: 05000341/2016007 | |||
Inspection Dates: August 1 - 5, 2016; | |||
August 15 - 19, 2016; and | |||
August 29 - September 2, 2016. | |||
Inspection Procedure: IP 71111.21, Component Design Bases Inspection | |||
Lead Inspector: Néstor J. Féliz-Adorno, Senior Reactor Inspector, DRS | |||
630-829-9739 | |||
Nestor.Feliz-Adorno@nrc.gov | |||
I. Information Requested Prior to the Onsite Information Gathering/Inspection Week | |||
The following information is requested by June 13, 2016, or sooner, to facilitate | |||
inspection preparation. If you have any questions regarding this information, please call | |||
the team leader as soon as possible. (Please provide the information electronically in | |||
pdf files, Excel, or other searchable formats, preferably on some portable electronic | |||
media (e.g., CD-ROM, DVD). The portable electronic media should contain descriptive | |||
names, and be indexed and hyperlinked to facilitate ease of use. Information in lists | |||
should contain enough information to be easily understood by someone who has | |||
knowledge of light water reactor technology. | |||
1. Risk-ranking of top 250 components from your site specific Probabilistic Safety | |||
Analysis (PSA) sorted by Risk-Achievement Worth. Include values for Birnbaum | |||
Importance, Risk-Reduction Worth, and Fussell-Veseley (as applicable). | |||
2. Risk-ranking of top 100 containment-related components (i.e., Large Early | |||
Release Frequency) from your site specific PSA sorted by Risk-Achievement | |||
Worth. | |||
3. Provide a list of the top 200 cut-sets from your PSA. | |||
4. Provide a list of the top 100 cut-sets for each initiator modeled in the PSA that | |||
contributes more than 5 percent to the baseline plant core damage frequency. | |||
5. Copies of PSA system notebooks and latest PSA summary document. | |||
6. List of time critical operator actions. Identify those actions that do not have job | |||
performance measures. | |||
7. Provide copies of the emergency operating procedures. | |||
8. If you have an External Events or Fire PSA Model, provide the information | |||
requested in Items 1 and 2 for external events and fire. Provide narrative | |||
description of each coded event (including fire, flood zone description). | |||
Enclosure | |||
REQUEST FOR INFORAMTION - COMPONENT DESIGN BASES INSPECTION | |||
9. Electronic copy of the site Individual Plant Examination of External Events, if | |||
available. | |||
10. Any pre-existing evaluation or list of components and associated calculations | |||
with low design margins, (e.g., pumps closest to the design limit for flow or | |||
pressure, diesel generator close to design required output, heat exchangers | |||
close to rated design heat removal). | |||
11. List of available design (setup) margins in both the open and closed direction | |||
(identify safety-related direction) for valves in the Motor-Operated Valve and | |||
Air-Operated Valve Programs. Identify the basis for how the margin was | |||
determined. | |||
12. List of high-risk Maintenance Rule systems/components based on engineering | |||
or expert panel judgment (i.e., those systems/components not identified in the | |||
PSA). | |||
13. Structures, systems, and components in the Maintenance Rule (a)(1) category | |||
for the last 3 years. | |||
14. Site top ten issues list (if applicable). | |||
15. A list of operating experience evaluations for the last 3 years. | |||
16. Information of any common cause failure of components experienced in the | |||
last 5 years at your facility. | |||
17. List of Root Cause Evaluations associated with component failures or design | |||
issues initiated/completed in the last 5 years. | |||
18. List of open operability evaluations. | |||
19. List of components/systems considered operable but degraded/non-conforming. | |||
20. Current management and engineering organizational chart. | |||
21. Electronic copies of Updated Final Safety Analysis Report, Technical | |||
Specifications, Technical Specifications Bases, and Technical Requirements | |||
Manual. | |||
22. Major one line electrical drawings (AC and DC) and key diagrams (electronic | |||
copies are preferred). | |||
23. Piping and Instrumentation Drawings (electronic copies are preferred). | |||
2 | |||
REQUEST FOR INFORAMTION - COMPONENT DESIGN BASES INSPECTION | |||
II. Information Requested (for the approximate 20 selected components) to be | |||
Available by July 18, 2016, (will be reviewed by the team in the Regional office | |||
during the week of July 25 - 29, 2016). | |||
This information should be separated for each selected component, especially if | |||
provided electronically (e.g., folder with component name that includes calculations, | |||
condition reports, and maintenance history). | |||
1. List of condition reports (i.e., corrective action documents) associated with each | |||
of the selected components for the last 6 years. | |||
2. The maintenance history (corrective, preventive, and elective) associated with | |||
each of the selected components for the last 10 years. Identify frequency of | |||
preventive maintenance activities. | |||
3. Copies of calculations associated with each of the selected components (if not | |||
previously provided), excluding data files. Please review the calculations and | |||
also provide copies of important referenced material (such as drawings, | |||
engineering requests, and vendor letters). [Pipe stress calculations are excluded | |||
from this request] | |||
4. System Health Reports, System Descriptions, Design Basis Documents, and/or | |||
Training Lesson Plans associated with each of the selected components. | |||
5. A list of modifications, including equivalency evaluations and setpoint changes, | |||
associated with each of the selected components. This list should include a | |||
descriptive paragraph on the purpose of the modification. Please ensure this list | |||
only includes design completed (not canceled) modifications. | |||
6. Copies of operability evaluations (open/closed for last 3 years) associated with | |||
each of the selected components and plans for restoring operability, if applicable. | |||
7. Copies of selected operator work-around evaluations associated with each of the | |||
selected components and plans for resolution, if applicable. | |||
8. Copies of any open temporary modifications associated with each of the selected | |||
components, if applicable. | |||
9. Trend data on the selected electrical/mechanical components performance for | |||
last 3 years (For example, pumps performance including in-service testing, other | |||
vibration monitoring, oil sample results, etc., for valves: stroke time and leak rate | |||
results, etc.). | |||
10. Provide copies of the normal and abnormal operating procedures associated with | |||
the selected components and selected scenarios. | |||
11. A copy of any internal/external self-assessments and associated corrective | |||
action documents generated in preparation for the inspection. | |||
12. Copy of latest completed tests and surveillances for each component, for | |||
example: | |||
3 | |||
REQUEST FOR INFORAMTION - COMPONENT DESIGN BASES INSPECTION | |||
Pumps: comprehensive test, quarterly test, flow balance, etc. | |||
Valves: stroke time testing, diagnostic testing, leak testing, interlocks, etc. | |||
Heat Exchangers/room coolers: thermal performance, clean/inspect, fan | |||
flows, etc. | |||
Acceptance criteria basis calculations should also be included. | |||
13. A copy of engineering/operations related audits completed in the last 2 years. | |||
III. Additional Information to be Provided on August 1, 2016, Onsite (for final selected | |||
components) | |||
1. During the in-office preparation activities, the team will be making final selections | |||
and may identify additional information needed to support the inspection. The | |||
lead inspector will provide a list of the additional information needed during the | |||
week of July 25 - 29, 2016. | |||
2. Schedule of any testing/maintenance activities to be conducted on the selected | |||
components during the three on-site inspection weeks. | |||
3. One complete set of Piping and Instrumentation Drawings (paper copies). | |||
4. Major one line electrical drawings (AC and DC) and key diagrams (paper copies). | |||
IV. Information Requested to be Provided Throughout the Inspection | |||
1. Copies of any corrective action documents generated as a result of the teams | |||
questions or queries during this inspection. | |||
2. Copies of the list of questions submitted by the team members and the | |||
status/resolution of the information requested (provide daily during the | |||
inspection to each team member). | |||
3. Reference materials. (make available if needed during all onsite weeks): | |||
Individual Plant Examination/Probabilistic Risk Assessment Report; | |||
Procurement documents for components selected (verify retrievable); | |||
Plant procedures (normal, abnormal, emergency, surveillance, etc.); and | |||
Vendor manuals. | |||
If you have questions regarding the information requested, please contact the lead inspector. | |||
4 | |||
P. Fessler -3- | |||
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) | |||
component of the NRC's Agencywide Documents Access and Management System (ADAMS). | |||
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html | |||
(the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA/ | |||
Néstor J. Féliz-Adorno, Senior Reactor Inspector | |||
Engineering Branch 2 | |||
Division of Reactor Safety | |||
Docket No. 50-341 | |||
License No. NPF-43 | |||
Enclosure: | |||
Information Request for Component Design | |||
Bases Inspection | |||
cc: Distribution via LISTSERV | |||
DISTRIBUTION: | |||
Kimyata MorganButler | |||
RidsNrrDorlLpl3-1 Resource | |||
RidsNrrPMFermi2 Resource | |||
RidsNrrDirsIrib Resource | |||
Cynthia Pederson | |||
Darrell Roberts | |||
Richard Skokowski | |||
Allan Barker | |||
Carole Ariano | |||
Linda Linn | |||
DRPIII | |||
DRSIII | |||
Jim Clay | |||
Carmen Olteanu | |||
ADAMS Accession Number ML16099A305 | |||
Publicly Available Non-Publicly Available Sensitive Non-Sensitive | |||
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy | |||
OFFICE RIII RIII RIII RIII | |||
NAME NFeliz-Adorno:cl | |||
DATE 04/08/16 | |||
OFFICIAL RECORD COPY | |||
}} | }} | ||
Revision as of 21:06, 30 October 2019
| ML16099A305 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 04/08/2016 |
| From: | Nestor Feliz-Adorno NRC/RGN-III/DRS/EB2 |
| To: | Fessler P DTE Energy |
| References | |
| IR 2016007 | |
| Download: ML16099A305 (8) | |
See also: IR 05000341/2016007
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, IL 60532-4352
April 8, 2016
Mr. Paul Fessler
Chief Nuclear Officer
DTE Energy Company
Fermi 2 - 210 NOC
6400 North Dixie Highway
Newport, MI 48166
SUBJECT: FERMI POWER PLANT, UNIT 2 - REQUEST FOR INFORMATION FOR AN
NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION;
INSPECTION REPORT 05000341/2016007
Dear Mr. Fessler:
On August 1, 2016, the U. S. Nuclear Regulatory Commission (NRC) will begin a triennial
baseline Component Design Bases Inspection at Fermi Power Plant, Unit 2. This inspection
will be performed in accordance with NRC Baseline Inspection Procedure 71111.21.
The Component Design Bases Inspection focuses on the design, maintenance, and operation
of risk-significant components associated with one or more accident scenario or systems. The
components to be reviewed during this baseline inspection will be identified during the in-office
preparation week that occurs prior to the first onsite inspection week. In addition, operating
experience issues, associated with the component samples, will also be selected for review.
The inspection team may request scenarios to be performed on the simulator. This request
would require support from your simulator staff to validate scenarios, simulator time, and a crew
to perform the actions which would most likely occur during the second onsite week. The team
will work closely with your staff early on during the inspection process to ensure this activity can
be accomplished with minimal impact.
The inspection will include 3 weeks onsite. The inspection team will consist of 6 NRC
inspectors, of which 5 will focus on engineering/maintenance and 1 on operations. The
current inspection schedule is as follows:
Onsite weeks: August 1 - 5, 2016;
August 15 - 19, 2016; and
August 29 - September 2, 2016.
The team will be preparing for the inspection, mainly during the week of July 25 - 29, 2016,
as discussed in the enclosure.
P. Fessler -2-
Experience with previous baseline design inspections of similar depth and length has shown
that this type of inspection is extremely resource intensive, both for the NRC inspectors and the
licensee staff. In order to minimize the inspection impact on the site and to ensure a productive
inspection for both parties, we have enclosed a request for information needed for the
inspection.
It is important that all of these documents are up-to-date and complete in order to minimize the
number of additional documents requested during the preparation and/or the onsite portions of
the inspection. Insofar as possible, this information should be provided electronically to the lead
inspector. The information request has been divided into three groups:
The first group lists information necessary for our initial inspection scoping activities.
This information should be provided to the lead inspector no later than June 13, 2016.
By June 24, 2016, the lead inspector will communicate the initial selected set of
approximately 20 components.
The second group of documents requested is those items needed to support our
in-office preparation activities. This set of documents, including the calculations
associated with the initial selected components, should be provided to the lead
inspector at the Regional Office no later than July 18, 2016. During the in-office
preparation activities, the team may identify additional information needed to support
the inspection.
The last group includes the additional information above as well as plant specific
reference material. This information should be available to the team onsite on
August 1, 2016. It is also requested that corrective action documents and/or
questions developed during the inspection be provided to the lead inspector as
the documents are generated.
The lead inspector for this inspection is Mr. Néstor J. Féliz Adorno. We understand that our
licensing contact for this inspection is Mr. Jason Haas of your organization. If there are any
questions about the inspection or the material requested in the enclosure, please contact the
lead inspector at 630-829-9739 or via e-mail at Nestor.Feliz-Adorno@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required
to respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy
of this letter, its enclosure, and your response (if any) will be available electronically for public
P. Fessler -3-
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html
(the Public Electronic Reading Room).
Sincerely,
/RA/
Néstor J. Féliz-Adorno, Senior Reactor Inspector
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-341
License No. NPF-43
Enclosure:
Information Request for Component Design
Bases Inspection
cc: Distribution via LISTSERV
REQUEST FOR INFORAMTION - COMPONENT DESIGN BASES INSPECTION
Inspection Report: 05000341/2016007
Inspection Dates: August 1 - 5, 2016;
August 15 - 19, 2016; and
August 29 - September 2, 2016.
Inspection Procedure: IP 71111.21, Component Design Bases Inspection
Lead Inspector: Néstor J. Féliz-Adorno, Senior Reactor Inspector, DRS
630-829-9739
Nestor.Feliz-Adorno@nrc.gov
I. Information Requested Prior to the Onsite Information Gathering/Inspection Week
The following information is requested by June 13, 2016, or sooner, to facilitate
inspection preparation. If you have any questions regarding this information, please call
the team leader as soon as possible. (Please provide the information electronically in
pdf files, Excel, or other searchable formats, preferably on some portable electronic
media (e.g., CD-ROM, DVD). The portable electronic media should contain descriptive
names, and be indexed and hyperlinked to facilitate ease of use. Information in lists
should contain enough information to be easily understood by someone who has
knowledge of light water reactor technology.
1. Risk-ranking of top 250 components from your site specific Probabilistic Safety
Analysis (PSA) sorted by Risk-Achievement Worth. Include values for Birnbaum
Importance, Risk-Reduction Worth, and Fussell-Veseley (as applicable).
2. Risk-ranking of top 100 containment-related components (i.e., Large Early
Release Frequency) from your site specific PSA sorted by Risk-Achievement
Worth.
3. Provide a list of the top 200 cut-sets from your PSA.
4. Provide a list of the top 100 cut-sets for each initiator modeled in the PSA that
contributes more than 5 percent to the baseline plant core damage frequency.
5. Copies of PSA system notebooks and latest PSA summary document.
6. List of time critical operator actions. Identify those actions that do not have job
performance measures.
7. Provide copies of the emergency operating procedures.
8. If you have an External Events or Fire PSA Model, provide the information
requested in Items 1 and 2 for external events and fire. Provide narrative
description of each coded event (including fire, flood zone description).
Enclosure
REQUEST FOR INFORAMTION - COMPONENT DESIGN BASES INSPECTION
9. Electronic copy of the site Individual Plant Examination of External Events, if
available.
10. Any pre-existing evaluation or list of components and associated calculations
with low design margins, (e.g., pumps closest to the design limit for flow or
pressure, diesel generator close to design required output, heat exchangers
close to rated design heat removal).
11. List of available design (setup) margins in both the open and closed direction
(identify safety-related direction) for valves in the Motor-Operated Valve and
Air-Operated Valve Programs. Identify the basis for how the margin was
determined.
12. List of high-risk Maintenance Rule systems/components based on engineering
or expert panel judgment (i.e., those systems/components not identified in the
PSA).
13. Structures, systems, and components in the Maintenance Rule (a)(1) category
for the last 3 years.
14. Site top ten issues list (if applicable).
15. A list of operating experience evaluations for the last 3 years.
16. Information of any common cause failure of components experienced in the
last 5 years at your facility.
17. List of Root Cause Evaluations associated with component failures or design
issues initiated/completed in the last 5 years.
18. List of open operability evaluations.
19. List of components/systems considered operable but degraded/non-conforming.
20. Current management and engineering organizational chart.
21. Electronic copies of Updated Final Safety Analysis Report, Technical
Specifications, Technical Specifications Bases, and Technical Requirements
Manual.
22. Major one line electrical drawings (AC and DC) and key diagrams (electronic
copies are preferred).
23. Piping and Instrumentation Drawings (electronic copies are preferred).
2
REQUEST FOR INFORAMTION - COMPONENT DESIGN BASES INSPECTION
II. Information Requested (for the approximate 20 selected components) to be
Available by July 18, 2016, (will be reviewed by the team in the Regional office
during the week of July 25 - 29, 2016).
This information should be separated for each selected component, especially if
provided electronically (e.g., folder with component name that includes calculations,
condition reports, and maintenance history).
1. List of condition reports (i.e., corrective action documents) associated with each
of the selected components for the last 6 years.
2. The maintenance history (corrective, preventive, and elective) associated with
each of the selected components for the last 10 years. Identify frequency of
preventive maintenance activities.
3. Copies of calculations associated with each of the selected components (if not
previously provided), excluding data files. Please review the calculations and
also provide copies of important referenced material (such as drawings,
engineering requests, and vendor letters). [Pipe stress calculations are excluded
from this request]
4. System Health Reports, System Descriptions, Design Basis Documents, and/or
Training Lesson Plans associated with each of the selected components.
5. A list of modifications, including equivalency evaluations and setpoint changes,
associated with each of the selected components. This list should include a
descriptive paragraph on the purpose of the modification. Please ensure this list
only includes design completed (not canceled) modifications.
6. Copies of operability evaluations (open/closed for last 3 years) associated with
each of the selected components and plans for restoring operability, if applicable.
7. Copies of selected operator work-around evaluations associated with each of the
selected components and plans for resolution, if applicable.
8. Copies of any open temporary modifications associated with each of the selected
components, if applicable.
9. Trend data on the selected electrical/mechanical components performance for
last 3 years (For example, pumps performance including in-service testing, other
vibration monitoring, oil sample results, etc., for valves: stroke time and leak rate
results, etc.).
10. Provide copies of the normal and abnormal operating procedures associated with
the selected components and selected scenarios.
11. A copy of any internal/external self-assessments and associated corrective
action documents generated in preparation for the inspection.
12. Copy of latest completed tests and surveillances for each component, for
example:
3
REQUEST FOR INFORAMTION - COMPONENT DESIGN BASES INSPECTION
Pumps: comprehensive test, quarterly test, flow balance, etc.
Valves: stroke time testing, diagnostic testing, leak testing, interlocks, etc.
Heat Exchangers/room coolers: thermal performance, clean/inspect, fan
flows, etc.
Acceptance criteria basis calculations should also be included.
13. A copy of engineering/operations related audits completed in the last 2 years.
III. Additional Information to be Provided on August 1, 2016, Onsite (for final selected
components)
1. During the in-office preparation activities, the team will be making final selections
and may identify additional information needed to support the inspection. The
lead inspector will provide a list of the additional information needed during the
week of July 25 - 29, 2016.
2. Schedule of any testing/maintenance activities to be conducted on the selected
components during the three on-site inspection weeks.
3. One complete set of Piping and Instrumentation Drawings (paper copies).
4. Major one line electrical drawings (AC and DC) and key diagrams (paper copies).
IV. Information Requested to be Provided Throughout the Inspection
1. Copies of any corrective action documents generated as a result of the teams
questions or queries during this inspection.
2. Copies of the list of questions submitted by the team members and the
status/resolution of the information requested (provide daily during the
inspection to each team member).
3. Reference materials. (make available if needed during all onsite weeks):
Individual Plant Examination/Probabilistic Risk Assessment Report;
Procurement documents for components selected (verify retrievable);
Plant procedures (normal, abnormal, emergency, surveillance, etc.); and
Vendor manuals.
If you have questions regarding the information requested, please contact the lead inspector.
4
P. Fessler -3-
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html
(the Public Electronic Reading Room).
Sincerely,
/RA/
Néstor J. Féliz-Adorno, Senior Reactor Inspector
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-341
License No. NPF-43
Enclosure:
Information Request for Component Design
Bases Inspection
cc: Distribution via LISTSERV
DISTRIBUTION:
Kimyata MorganButler
RidsNrrDorlLpl3-1 Resource
RidsNrrPMFermi2 Resource
RidsNrrDirsIrib Resource
Cynthia Pederson
DRPIII
DRSIII
ADAMS Accession Number ML16099A305
Publicly Available Non-Publicly Available Sensitive Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE RIII RIII RIII RIII
NAME NFeliz-Adorno:cl
DATE 04/08/16
OFFICIAL RECORD COPY