ML16349A652: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:December 21, 2016  
{{#Wiki_filter:December 21, 2016
Dr. Melinda Krahenbuhl, Director
  Dr. Melinda Krahenbuhl, Director  
Reed Reactor Facility
Reed Reactor Facility  
Reed College
3203 S.E. Woodstock Boulevard
Portland, OR 97202-8199
SUBJECT:        REED COLLEGE - U.S. NUCLEAR REGULATORY COMMISSION ROUTINE
                INSPECTION REPORT NO. 50-288/2016-202 AND NOTICE OF VIOLATION
Dear Dr. Krahenbuhl:
From October 31 to November 3, and November 28 to December 2, 2016, the U.S. Nuclear
Regulatory Commission (NRC or the Commission) completed an inspection at the TRIGA
Mark-I Reed Research Reactor facility. The enclosed report documents the inspection results,
which were discussed on November 2, 2016, with you, Dr. Nigel Nicholson, Dean of the Faculty,
and Christina Barrett, Reactor Operations Manager, and on December 1, 2016, with you and
Dr. Nicholson.
The inspection examined activities conducted under your license as they relate to safety and
compliance with the Commissions rules and regulations and with the conditions of your license.
The inspector reviewed selected procedures and records, observed activities in progress, and
interviewed various personnel.
Based on the results of this inspection, the NRC has determined that two Severity Level IV
violations of NRC requirements occurred. The violations were evaluated in accordance with the
NRC Enforcement Policy, which can be found on the NRCs Web site at www.nrc.gov by
selecting What We Do, Enforcement, and then Enforcement Policy. The violations are
cited in the enclosed Notice of Violation (Notice) and the circumstances surrounding them are
described in detail in the subject inspection report. The violations are being cited in the Notice
because they constitute the failure to meet regulatory requirements that have more than minor
safety significance and they were identified by the NRC.
You are required to respond to this letter and should follow the instructions specified in the
enclosed Notice when preparing your response. The NRC will use your response, in part, to
determine whether further enforcement action is necessary to ensure compliance with
regulatory requirements.
In addition, based on the results of this inspection, the NRC has determined that one other
Severity Level IV violation of NRC requirements occurred. This violation is being treated as a
non-cited violation (NCV), consistent with Section 2.3.2.b of the Enforcement Policy. The NCV
is described in the subject inspection report. If you contest the violation or significance of the
NCV, you should provide a response within 30 days of the date of this inspection report, with the
basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk,
Washington DC 20555-0001, with copies to the Director, Office of Enforcement, United States
Nuclear Regulatory Commission, Washington, DC 20555-0001.


Reed College
M. Krahenbuhl                                    -2-
3203 S.E. Woodstock Boulevard
In accordance with Title 10 of the Code of Federal Regulations Section 2.390, Public
inspections, exemptions, requests for withholding, a copy of this letter, its enclosure, and your
response (if any) will be available electronically for public inspection in the NRC Public
Document Room or from the NRCs document system (Agencywide Documents Access and
Management System (ADAMS)). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this inspection, please contact Craig Bassett at
301-466-4495 or by electronic mail at Craig.Bassett@nrc.gov.
                                                    Sincerely,
                                                        /RA/
                                                    Anthony J. Mendiola, Chief
                                                    Research and Test Reactors Oversight Branch
                                                    Division of Policy and Rulemaking
                                                    Office of Nuclear Reactor Regulation
Docket No. 50-288
License No. R-112
Enclosures:
1. Notice of Violation
2. NRC Inspection Report
    No. 50-288/2016-202
cc: See next page


Portland, OR 97202-8199  
Reed College                        Docket No. 50-288
SUBJECT: REED COLLEGE - U.S. NUCLEAR REGULATORY COMMISSION ROUTINE INSPECTION REPORT NO. 50-288/2016-202 AND NOTICE OF VIOLATION
cc:
 
Mayor of City of Portland
Dear Dr. Krahenbuhl:
1220 Southwest 5th Avenue
From October 31 to November 3, and November 28 to December 2, 2016, the U.S. Nuclear
Portland, OR 97204
Regulatory Commission (NRC or the Commission) completed an inspection at the TRIGA Mark-I Reed Research Reactor facility.  The enclosed report documents the inspection results,  
Dr. Nigel Nicholson, Dean of Faculty
which were discussed on November 2, 2016, with you, Dr. Nigel Nicholson, Dean of the Faculty, and Christina Barrett, Reactor Operations Manager, and on December 1, 2016, with you and Dr. Nicholson. 
Reed College
3203 S.E. Woodstock Boulevard
Portland, OR 97202-8199
Mr. John Kroger, President
Reed College
3203 S.E. Woodstock Boulevard
Portland, OR 97202-8199
Division Administrator
Nuclear Safety Division
Oregon Department of Energy
625 Marion Street, N.E.
Salem, OR 97310-3737
Program Director
Radiation Protection Services
Public Health Division
Oregon Health Authority
800 NE Oregon Street, Suite 640
Portland, OR 97232-2162
Test, Research, and Training
  Reactor Newsletter
University of Florida
202 Nuclear Sciences Center
Gainesville, FL 32611


The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license.
The inspector reviewed selected procedures and records, observed activities in progress, and interviewed various personnel. 
Based on the results of this inspection, the NRC has determined that two Severity Level IV
violations of NRC requirements occurred.  The violations were evaluated in accordance with the
NRC Enforcement Policy, which can be found on the NRC's Web site at www.nrc.gov
by selecting "What We Do," "Enforcement," and then "Enforcement Policy."  The violations are cited in the enclosed Notice of Violation (Notice) and the circumstances surrounding them are
described in detail in the subject inspection report.  The violations are being cited in the Notice
because they constitute the failure to meet regulatory requirements that have more than minor
safety significance and they were identified by the NRC. 


  You are required to respond to this letter and should follow the instructions specified in the enclosed Notice when preparing your response. The NRC will use your response, in part, to  
  ML16349A652; *concurrence via e-mail                        NRC-002
determine whether further enforcement action is necessary to ensure compliance with  
OFFICE          NRR/DPR/PROB*        NRR/DPR/PROB*              NRR/DPR/PROB
NAME            CBassett              NParker                    AMendiola
DATE            12/16/16              12/16/16                    12/21/16
                               
                                        NOTICE OF VIOLATION
Reed College                                                                      Docket No. 50-288
Reed Research Reactor                                                            License No. R-112
During a U.S. Nuclear Regulatory Commission (NRC) inspection conducted from October 31 to
November 3, 2016 and from November 28 to December 2, 2016, two violations of NRC
requirements were identified. In accordance with the NRC Enforcement Policy, the violations
are listed below:
1.      Reed Research Reactor Technical Specification (TS) Section 3.2.2 requires that the
        reactor shall not be operated unless the reactor power measuring channels in Table 2
        are operable. Table 2 lists the Percent Power Channel, the Linear Channel, and the
        Logarithmic Channel.
        Contrary to this requirement, from October 6 to October 16, 2016, the reactor was
        operated or attempted to be operated when the Logarithmic Channel was not operable.
        This has been determined to be a Severity Level IV violation (Section 6.1).
2.      Title 10 of the Code of Federal Regulations (10 CFR) 50.59, Changes, tests, and
        experiments, paragraph (c)(1) states, in part, that a licensee may make changes in the
        facility as described in the final safety analysis report without obtaining a license
        amendment pursuant to 10 CFR 50.90 only if: (i) a change to the technical
        specifications incorporated in the license is not required, and (ii) the change does not
        meet any of the criteria in 10 CFR 50.59(c)(2).
        The regulation in 10 CFR 50.59(c)(2) requires, in part, that a licensee shall obtain a
        license amendment pursuant to 10 CFR 50.90 prior to implementing a proposed change
        if the change would: (i) result in more than a minimal increase in the frequency of
        occurrence of an accident previously evaluated in the final safety analysis report;
        (ii) result in more than a minimal increase in the likelihood of occurrence of a malfunction
        of a structure, system, or component (SSC) important to safety previously evaluated in
        the final safety analysis report; (iii) result in more than a minimal increase in the
        consequences of an accident previously evaluated in the final safety analysis report;
        (iv) result in more than a minimal increase in the consequences of a malfunction of an
        SSC important to safety previously evaluated in the final safety analysis report; (v)
        create a possibility for an accident of a different type than any previously evaluated in
        the final safety analysis report; (vi) create a possibility for a malfunction of an SSC
        important to safety with a different result than any previously evaluated in the final safety
        analysis report; (vii) result in a design basis limit for a fission product barrier as
        described in the FSAR being exceeded or altered; or (viii) result in a departure from a
        method of evaluation described in the FSAR used in establishing the design bases or in
        the safety analyses.
        The regulation in 10 CFR 50.59(d)(1) requires, in part, that the licensee shall maintain
        records of changes in the facility made pursuant to 10 CFR 50.59(c). These records
                                                                                              Enclosure 1


regulatory requirements.  
                                                  -2-
        must include a written evaluation which provides the bases for the determination that the
        change does not require a license amendment pursuant to 10 CFR 50.59(c)(2).
        The Reed Research Reactor safety analysis report (SAR) states in Chapter 7,
        Section 7.2.3.3, that the Percent Power channel has an associated Uncompensated Ion
        Chamber that provides indication for that channel.
        Contrary to the above requirements, on October 5, 2016, the licensee made a change to
        the facility as described in the SAR without conducting an evaluation to determine
        whether or not the change would require a change to the TSs or should have required a
        license amendment. Specifically, the licensee replaced the detection chamber
        associated with the Percent Power channel with a fission chamber which was not as
        described in the SAR without performing an evaluation of the change using the criteria in
        10 CFR 50.59(c)(1) and (2) to determine if the change would require a change to the
        TSs or should have required a license amendment.
        This has been determined to be a Severity Level IV violation (Section 6.1).
Pursuant to the provisions of 10 CFR 2.201, Notice of violation, Reed College is hereby
required to submit a written statement or explanation to the U.S. Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington, D.C. 20555-0001, with a copy to the
responsible inspector, within 30 days of the date of the letter transmitting this Notice of Violation
(Notice). This reply should be clearly marked as a Reply to a Notice of Violation and should
include for each violation: (1) the reason for each violation, or, if contested, the basis for
disputing the violation or severity level; (2) the corrective steps that have been taken and the
results achieved; (3) the corrective steps that will be taken to avoid further violations; and (4) the
date when full compliance will be achieved. Your response may reference or include previously
docketed correspondence, if the correspondence adequately addresses the required response.
If an adequate reply is not received within the time specified in this Notice, an order or Demand
for Information may be issued as to why the license should not be modified, suspended, or
revoked, or why such other action as may be proper should not be taken. Where good cause is
shown, consideration will be given to extending the response time. If you contest this
enforcement action, you should also provide a copy of your response, with the basis for your
denial, to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission,
Washington, D.C. 20555-0001.
Because your response will be made available electronically for public inspection in the NRC
Public Document Room or from the Publicly Available Records component of the NRCs
Agencywide Documents Access and Management System (ADAMS), to the extent possible, it
should not include any personal privacy, proprietary, or safeguards information so that it can be
made available to the public without redaction. ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). If personal
privacy or proprietary information is necessary to provide an acceptable response, then please
provide a bracketed copy of your response that identifies the information that should be
protected and a redacted copy of your response that deletes such information. If you request
withholding of such material, you must specifically identify the portions of your response that
you seek to have withheld and provide in detail the bases for your claim of withholding (e.g.,
explain why the disclosure of information will create an unwarranted invasion of personal
privacy or provide the information required by 10 CFR 2.390, Public inspections, exemptions,


In addition, based on the results of this inspection, the NRC has determined that one other Severity Level IV violation of NRC requirements occurred.  This violation is being treated as a  
                                              -3-
non-cited violation (NCV), consistent with Section 2.3.2.b of the Enforcement Policy.  The NCV
requests for withholding, paragraph (b) to support a request for withholding confidential
is described in the subject inspection report.  If you contest the violation or significance of the
commercial or financial information). If safeguards information is necessary to provide an
NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to the Director, Office of Enforcement, United States
acceptable response, please provide the level of protection described in 10 CFR 73.21,
Nuclear Regulatory Commission, Washington, DC 20555-0001.  
Protection of Safeguards Information: Performance Requirements.
M. Krahenbuhl - 2 -
In accordance with 10 CFR 19.11, Posting of notices to workers, you may be required to post
  In accordance with Title 10 of the Code of Federal Regulations Section 2.390, "Public inspections, exemptions, requests for withholding," a copy of this letter, its enclosure, and your response (if any) will be available electronica
this Notice within two working days.
lly for public inspection in the NRC Public
Dated this 21st day of December
Document Room or from the NRC's document system (Agencywide Documents Access and Management System (ADAMS)).  ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).  
Should you have any questions concerning this inspection, please contact Craig Bassett at 301-466-4495 or by electronic mail at Craig.Bassett@nrc.gov.    Sincerely, 
  /RA/ 
Anthony J. Mendiola, Chief  Research and Test Reactors Oversight Branch
Division of Policy and Rulemaking Office of Nuclear Reactor Regulation 


Docket No. 50-288  
                  U. S. NUCLEAR REGULATORY COMMISSION
License No. R-112  
                OFFICE OF NUCLEAR REACTOR REGULATION
Docket No.     50-288
License No.     R-112
Report No.      50-288/2016-202
Licensee:      Reed College
Facility:      Reed Research Reactor
Location:      Portland, Oregon
Dates:          October 31, 2016 - November 3, 2016
                November 28, 2016 - December 2, 2016
Inspector:      Craig Bassett
Accompanied by: Michele DeSouza, Examiner
                John Nguyen, Examiner
                Michael Takacs, Security Specialist
Approved by:    Anthony J. Mendiola, Chief
                Research and Test Reactors Oversight Branch
                Division of Policy and Rulemaking
                Office of Nuclear Reactor Regulation
                                                            Enclosure 2


Enclosures:   1. Notice of Violation
                                    EXECUTIVE SUMMARY
                                          Reed College
                                  Reed Research Reactor Facility
                                NRC Report No. 50-288/2016-202
The primary focus of this routine, announced inspection included onsite review of selected
aspects of the Reed College (the licensee) Class II research reactor safety program. This
included a review of: (1) organization and staffing, (2) review and audit and design change
functions, (3) conduct of operations, (4) operator requalification program, (5) fuel handling,
(6) maintenance and surveillance, (7) procedures, (8) experiments, and (9) emergency
preparedness. The licensees program was acceptably directed toward the protection of public
health and safety. Two apparent Severity Level IV violations and one Severity Level IV
non-cited violation were identified.
Organization and Staffing
  The organization and staffing remain in compliance with the requirements specified in
    Technical Specification (TS) Section 6.1.
Review and Audit and Design Change Functions
  Review and oversight functions required by TS Section 6.2 were acceptably completed by
    the Reactor Operations Committee. Audits were being completed as required.
  The design change program being implemented at the facility generally satisfied Nuclear
    Regulatory Commission requirements.
Conduct of Operations
  Operations were generally being conducted in accordance with TS and procedural
    requirements.
  Two apparent violations and one non-cited violation were identified involving the nuclear
    measuring channels of the reactor.
Operator Requalification Program
  The operator requalification/training program was up-to-date and being acceptably
    implemented and documented.
  Biennial medical examinations were being completed as required.
  A one-time Alternate Requalification Plan was initiated due to the problems created by
    malfunctioning nuclear instrumentation.


2. NRC Inspection Report
                                              -2-
Fuel Handling
  Reactor fuel movements and inspections were conducted and documented in accordance
  with procedure.
  Twenty-five percent of the fuel elements were being inspected on an annual basis.
Maintenance and Surveillance
  Maintenance was being completed as needed.
  The surveillance program, including calibration of equipment, was being completed in
  accordance with TS Sections 3 and 4.
Procedures
  Facility procedures were available for the safe operation of the reactor as required by
  TS Section 6.4.
Experiments
  The program for the control of experiments satisfied TS Sections 3.6, 4.6, and 6.5 and other
  regulatory requirements.
Emergency Preparedness
  The Emergency Plan (E-Plan) and Emergency Implementation Procedures were being
  audited and reviewed annually as required.
  Letters of Agreement documenting emergency support to be provided by offsite agencies
  were being maintained and periodically updated.
  Annual drills were being held and documentation of the drills and the follow-up critiques was
  maintained. Subsequent corrective actions were taken as needed.
  Emergency preparedness training for staff and offsite personnel was being conducted as
  stipulated in the E-Plan.


      No. 50-288/2016-202  
                                          REPORT DETAILS
Summary of Facility Status
The Reed College (the licensees) 250 kilowatt TRIGA Mark I research reactor was typically
operated in support of undergraduate instruction, laboratory experiments, reactor system
testing, reactor surveillances, and operator training. During this inspection the reactor was not
operated due to nuclear instrumentation issues.
1.      Organization and Staffing
        a.      Inspection Scope (Inspection Procedure (IP) 69001)
                To verify the organization and staffing requirements specified in technical
                specifications (TSs) Section 6.1 were being met, the inspector reviewed selected
                aspects of the following:
                  Main (Reactor Console) Log - Numbers (Nos.) 86 - 89
                  Reed Research Reactor (RRR) facility organization and staffing during
                    reactor operations
                  Administrative controls and management responsibilities specified in the TS
                    and facility procedures
                  RRR Administrative Procedures, Section 1, Personnel, and Section 3,
                    Reactor Operations
                  RRR Standard Operating Procedure (SOP) 60, Logbook Entries
                  RRR Annual Report for the period from July 1, 2014, through
                    June 30, 2015, submitted to the U.S. Nuclear Regulatory Commission (NRC)
                    on August 7, 2015
                  RRR Annual Report for the period from July 1, 2015, through
                    June 30, 2016, submitted to the NRC on July 27, 2016
        b.      Observations and Findings
                Through discussions with licensee representatives, the inspector determined that
                management responsibilities and the organizational structure at the RRR facility
                had not changed since the previous NRC inspection of licensee operations in
                December 2014 (Inspection Report No. 50-288/2014-202). The inspector
                determined that the Facility Director retained direct control and overall
                responsibility for management of the facility as specified in the TS. The Facility
                Director reported to the President of Reed College through the Dean of Faculty.
                This organization was consistent with that specified in the TS.
                It was noted that since the last operations inspection in 2014, a new person had
                been hired to be the Reactor Operations Manager. Also, a new person had been
                hired to fill the position of campus Radiation Safety Officer/Director of
                Environmental Health and Safety.


cc:  See next page
                                          -2-
 
        The licensees current operational organization consisted of the Facility Director,
  Reed College Docket No. 50-288
        a Reactor Operations Manager, a Radiation Safety Officer, an Operations
cc:
        Supervisor, a Training Supervisor, an Assistant Training Supervisor, a Projects
Mayor of City of Portland
        Supervisor, and a Requalification Supervisor. The Facility Director, Reactor
        Operations Manager, and Radiation Safety Officer positions were full-time while
        the rest were part-time positions filled by students. Except for the Radiation
        Safety Officer, the aforementioned individuals, in addition to their administrative
        duties, were qualified reactor operators (ROs) or senior reactor operators
        (SROs). It was noted that there were a total of 20 SROs and 19 ROs licensed to
        operate the RRR.
  c.    Conclusion
        Organization and staffing met the requirements specified in TS Section 6.1.
2. Review, Audit, and Design Change Functions
  a.   Inspection Scope (IP 69001)
        In order to verify that the licensee had established and conducted reviews and
        audits as required, and to determine whether facility modifications and change
        reviews were consistent with Title 10 of the Code of Federal Regulations
        (10 CFR) Section 50.59, Changes, tests and experiments, and TS Section 6.2,
        the inspector reviewed selected portions of the following:
            Maintenance Log pages completed for unscheduled work
            Corrective Action Reports (CARs) for 2015 and to date in 2016
            Design changes reviewed under 10 CFR 50.59 for 2015 and 2016
            Reactor Operations Committee (ROC) meeting minutes from
            October 2014 through the present
            RRR Administrative Procedures, Section 1, Personnel; Section 2, Reactor
            Review Committee; and Section 9, Record Retention
            RRR SOP 62, Changes, Tests, and Experiments, and SOP 69, Corrective
            Action Report; and associated forms, Corrective Action Reports; last
            revised August 26, 2014
            RRR Annual Reports for the last two reporting periods
  b.    Observations and Findings
        (1)    Review and Audit Functions
                The inspector reviewed ROC meeting minutes from October 2014
                through the present. These meeting minutes showed that the committee
                was meeting at the required frequency and was considering the types of
                topics outlined by the TS.
                The inspector noted that, since the last NRC inspection, the appropriate
                audits had been completed by the ROC and an external auditor in the


1220 Southwest 5
                                              -3-
th Avenue Portland, OR  97204
                  various areas outlined in the TS. The audits were designed so that most
                  aspects of the licensees operations and safety programs were reviewed
                  every year. Various facility documents, such as the Radiation Protection
                  Program, the Emergency Plan (E-Plan), the Fire Plan, the Administrative
                  Procedures, and the Requalification Plan comprised the material that was
                  typically reviewed. The Reactor Experiments and various SOPs were
                  also reviewed. The inspector noted that the audits and the resulting
                  findings were detailed and that the licensee responded and took
                  corrective actions as needed.
          (2)    Design Changes
                  The inspector reviewed the licensees 10 CFR 50.59 screening forms
                  concerning changes or modifications that had been initiated at the facility
                  for 2015 and to date in 2016. The results indicated that none of the
                  screenings required further evaluation under 10 CFR 50.59. The
                  inspector also reviewed the Maintenance Log pages that had been
                  completed for unscheduled work associated with various systems. The
                  forms contained a section which required a 50.59 Screen to be completed
                  prior to initiating the work. None of the maintenance items reviewed
                  required any further actions, such as a 50.59 evaluation, to be completed
                  except as noted in Part 3, Section (3) below. None of the other changes
                  reviewed by the inspector met any of the criteria of 10 CFR 50.59(c)(1)
                  and (2), which would have required a TS change or a license amendment
                  from the NRC.
  c.      Conclusion
          Review and oversight functions required by TS Section 6.2 were acceptably
          completed by the ROC. Audits were being completed as required. The
          licensees design change program generally satisfied NRC requirements.
3. Conduct of Operations
  The inspector reviewed selected aspects of the following to verify operation of the
  reactor in accordance with TS Sections 3, 4, and 6.1:
  a.      Inspection Scope (IP 69001)
              Main (Reactor Console) Log Nos. 86 - 89
              Various SCRAM Response Forms for 2015 and 2016
              CARs for 2015 and to date in 2016
              Maintenance Log pages completed for unscheduled work
              Selected Startup Checklist Forms for the period from January 2015 through
              the present
              Selected Shutdown Checklist Forms for the period from January 2015
              through the present
              RRR Administrative Procedures, Section 3, Reactor Operations


Dr. Nigel Nicholson, Dean of Faculty
                                  -4-
Reed College
      Various RRR SOPs and Appendices including SOP 1, Reactor Operations;
3203 S.E. Woodstock Boulevard
      SOP 20, Startup Checklist; SOP 20, Appendix A, Startup Checklist Form;
      SOP 21, Same Day Startup Checklist; SOP 21, Appendix A, Same-Day
      Startup Checklist Form; SOP 22, Shutdown Checklist; SOP 22,
      Appendix A, Shutdown Checklist Form; SOP 23, Biweekly Checklist; SOP
      23, Appendix A, Biweekly Checklist Form; SOP 24, Bimonthly Checklist;
      SOP 24, Appendix A, Bimonthly Checklist Form; SOP 25, Semiannual
      Checklist; SOP 25, Appendix A, Reed Research Reactor Semiannual
      Checklist; SOP 26, Annual Checklist; SOP 26, Appendix A, Annual
      Checklist Form; SOP 33, Nuclear Instruments; SOP 34, Control Rods;
      SOP 60, Logbook Entries; and, SOP 69, Corrective Action Report
      RRR Annual Reports for the last two reporting periods
b. Observations and Findings
  (1)    Routine Operations
          The inspector reviewed selected reactor operating records from
          January 2015 through the present. These records included daily Startup
          Checklists, Shutdown Checklists, Experimental Startup and Shutdown
          Checklists, associated forms, Weekly Checklists, and the Main (reactor
          console) Logs. The records indicated that the activities were generally
          carried out in accordance with written procedures as required by TS
          Section 6.4, except as noted below. The checklists were completed and
          signed off by the appropriate personnel as required.
          Through interviews with operators and review of logs and records, the
          inspector confirmed that shift staffing met the minimum requirements for
          duty and on-call personnel as required by TS Section 6.1.
          Information on the operational status of the facility was generally recorded
          properly on the log sheets and/or checklists as required by procedure.
          Scrams were identified in the logs and were reported and resolved as
          required before reactor operations were allowed to continue. However, it
          was noted that the logs were not totally complete in that they did not
          indicate who authorized operations to resume. The inspector indicated
          that the complete documentation of reactor operations should include not
          only when and why a scram occurred, but who gave the authorization to
          resume operations as well. The licensee was informed that the issue of
          complete and accurate documentation of scram events and other
          operational events would be designated by the NRC as an Inspector
          Follow-up Item (IFI) and would be reviewed during future inspections
          (IFI 50-288/2016-202-01).


Portland, OR  97202-8199
                              -5-
(2) NRC-Identified Violation of TS Section 3.2.2
    TS Section 3.2.2 requires that the reactor shall not be operated unless
    the reactor power measuring channels in Table 2 are operable. Table 2
    lists the Percent Power Channel, the Linear Channel, and the Logarithmic
    Channel.
    On May 28, 2016, the licensee discovered that the facility reactor pool
    had overflowed due to a malfunction of the recently installed automatic fill
    system. On May 30, 2016, operators noticed that all reactor trips were
    illuminated. Because of this, the reactor was determined to be inoperable
    due to electronics problems. In mid-June, some of the electronic
    components of the power measuring channels, including the Logarithmic
    Channel pre-amp and the Percent Power Channel High Voltage (HV)
    power supply, were removed and taken to Oregon State University (OSU)
    by the electronics specialist from OSU where he worked to correct the
    problems. It was noted that the Linear Channel was not found to have
    been damaged.
    During August 8 and 9, the OSU electronics specialist came to Reed
    College and installed the repaired pre-amp and HV power supply for the
    Log and Percent Power channels. After the electronics were installed,
    the licensee determined that the detector chambers associated with the
    Percent Power and Logarithmic Channels were not functioning properly.
    Licensee personnel then removed the assemblies for each channel from
    the reactor pool and began the process of trying to dry out the detectors.
    On October 5, after the channel detectors were thought to be completely
    dry, the electronics specialist from OSU again came to Reed College to
    help test and reinstall the power channels. At that point the Log channel
    was determined to be functional but the Percent Power Channel shorted
    out and was not functional. Upon further investigation, the licensee found
    that the detector associated with the Percent Power Channel was not an
    UIC as stipulated in the SAR but a fission chamber operating in current
    mode. Because that fission chamber was not functioning, licensee staff
    and the OSU electronics specialist installed a spare fission chamber (one
    that Reed had on hand) with the Percent Power Channel to see if it would
    operate. The channel appeared to be functioning properly and appeared
    to be giving the expected signals.
    The following day, October 6, licensee staff attempted to adjust the
    detectors and conduct a core excess and power calibration of the reactor.
    Although the power channels appeared to be working properly, the
    Percent Power Channel had repeated HV scrams. Licensee staff found a
    loose wire and corrected that problem. During the next few days licensee
    staff adjusted the Linear Power and Percent Power detector positions to
    adjust for power calibration. However, another HV Percent Power scram
    occurred, the cause of which could not be explained.


Mr. John Kroger, President
                        -6-
Reed College
On October 13, channel testing continued and core excess
3203 S.E. Woodstock Boulevard
measurements were again attempted but to no avail and the
Percent Power Channel was determined to be non-functional. On
October 14, the OSU electronics specialist returned to Reed and installed
a spare UIC (one that OSU had received from another university) to
operate in the Percent Power Channel. On October 16, the licensee
completed core excess and reactor power calibrations. They operated up
to 150 kilowatt (kW) for training and operator requalification.
Two days later operations were conducted for requalification but the
Log channel was determined to be erratic, possibly due to electronic
noise. Because the reactor had been operated for over an hour with a
non-functional Logarithmic Channel, the reactor was scrammed. At that
point, the Reactor Operations Manager declared the problem as an event
and a report was made to the NRC (see Section (4) below). When the
licensee investigated the problem, it was believed that the problem was
due to an electronics noise problem. After disconnecting, testing, and
reconnecting the channel, they thought the problem (the noise issue) with
the Logarithmic Channel was corrected. The following day, October 19,
the Logarithmic Channel was tested and determined to be functional.
Core excess measurements were completed and the reactor was
operated for requalification of operators. An inadvertent scram occurred
but this was caused by operator error and operations were allowed to
continue.
Because most of the student operators were out of qualification
(due to the continuing problems with the nuclear instruments NI
channels), reactor operations continued and were conducted on various
occasions for requalification but problems persisted. Core excess
measurements were completed each day and other activities were
attempted such as measuring Regulating Rod worth. The licensee also
completed Shim and Safety rod worth measurements but problems kept
occurring with the Logarithmic Channel. On October 21, the licensee
determined that the Logarithmic Channel detector was apparently working
properly but the electronics were not. At that point the reactor was
declared non-operational. The reactor has not been operated since that
date.
The NRC reviewed the issues associated with the reactor power
measuring channels. From October 6-16, licensee staff operated the
reactor up to 150 kW for training and requalification. (It was noted that
after October 16, the reactor was only operated at a power level of
5 watts (W) or less.) During that period when operating at 150 kW, the
Linear Channel typically read 60 percent, the Percent Power Channel
typically read 60 percent, but the Logarithmic Channel was reading from
90 to 100 percent. The inspector reviewed the console logs for the past
two years. For that time frame, when operating at 150 kW, the Linear
Channel typically read 60 percent, the Percent Power Channel typically
read 60 percent, and the Logarithmic Channel typically read 60 percent.


Portland, OR  97202-8199
                              -7-
    Therefore, from October 6 through 16, the Logarithmic Channel was not
    reading correctly because it was reading high and over responding,
    probably indicating that the channel detector was shorted out. The NRC
    concluded that the Logarithmic Channel was not operating properly and
    thus was not operational during this period. The licensee was informed
    that failure to have an operable Logarithmic Channel during reactor
    operation was an apparent violation of TS Section 3.2.2 (violation (VIO)
    50-288/2016-202-02).
(3) NRC-Identified Violation of Regulatory Requirements
    The RRR safety analysis report (SAR) states in Chapter 7, Section
    7.2.3.3, that the Percent Power Channel has an Uncompensated Ion
    Chamber that provides indication for that channel.
    Regulation in 10 CFR 50.59 requires that licensees evaluate a change
    from what was described in the SAR to ensure that a TS change or a
    license amendment was not required in accordance with 10 CFR 50.59
    pargraphs (c)(1)(i and ii) and (c)(2)(i-viii).
    As noted above, the licensee had been experiencing various problems
    with the reactor power measuring channels. Because of these problems,
    the licensee tried repeatedly to make adjustments to the channel
    electronics and the positions of the associated detectors. On
    October 6, 2016, licensee staff attempted to adjust the detectors and
    conduct a core excess and power calibration of the reactor. Although the
    power channels appeared to be working properly, the Percent Power
    Channel had repeated HV scrams. Licensee staff found a loose wire and
    corrected that problem but other problems persisted. Finally on
    October 14, the OSU electronics specialist returned to Reed and installed
    a spare UIC (one that OSU had received from another university) into the
    Percent Power Channel. Licensee staff conducted a core excess
    measurement and performed testing of the electronics using the reactor
    at various power levels.
    The NRC reviewed this situation and the problems with the Percent
    Power Channel. As stated above, it was noted that the licensee was not
    aware that the detector associated with the Percent Power Channel was
    a fission chamber (and not a UIC as stated in the SAR) prior to
    October 5, 2016. However, following that date, the licensee was fully
    aware of the situation. Nevertheless, the decision was made to replace
    the existing fission chamber with a spare fission chamber that the
    licensee had on hand.


Division Administrator
                              -8-
Nuclear Safety Division
    A fission chamber was not what the SAR stipulated as the detector to be
Oregon Department of Energy
    operated with the Percent Power Channel. No attempt was made to
625 Marion Street, N.E.  
    conduct a 10 CFR 50.59 review as to whether or not such a detector
Salem, OR  97310-3737
    should be used with the Percent Power Channel. The licensee was
    informed that failure to conduct a review in this situation was an apparent
    violation of 10 CFR 50.59 requirements (VIO 50-288/2016-202-03).
(4) Self-Reported Violation of the Requirements of TS Section 3.2.2
    Section 3.2.2 of the RRR technical specifications requires that the reactor
    shall not be operated unless the reactor power measuring channels in
    Table 2 are operable. Table 2 lists the Percent Power Channel, the
    Linear Channel, and the Log Channel.
    On October 18, 2016, a licensed reactor operator and another person
    operating under the operators direction completed the Start Up Checklist
    had checked out properly and appeared to be functioning normally.
    They then inserted the key and began a check out of the reactor NIs prior
    to full power operation. They conducted the excess reactivity surveillance
    test at a power level below 5 W.
    About an hour after the key was inserted into the console, the Reactor
    Operations Manager entered the Control Room and noted that one of the
    NIs, the Log channel was not tracking correctly, i.e., the Log channel was
    reading a constant number and not tracking with the power level. The
    reactor was immediately scrammed and secured.
    The three individuals then began to investigate the problem and diagnose
    what had happened. Analysis showed that the Log channel pre-amp was
    picking up excessive noise due to its close proximity to other electrical
    components. Also, upon further investigation, a ground wire was found
    detached from its proper connection.
    The loose ground wire was replaced and a test of the pre-amp was
    initiated. Testing of the pre-amp on a platform away from interference
    from other electronics indicated that it was then functioning properly.
    Under these corrected conditions, the Log channel was tested and the
    reading appeared to return to normal. However, reactor operations were
    suspended until the channel could be more thoroughly tested. A CAR
    was initiated to document the issue. The NRC was notified of the event
    on October 19, 2016.
    The NRC reviewed this issue and discussed the self-identified TS
    violation with the licensee and interviewed various reactor staff personnel.
    The NRC confirmed that the licensee had, in fact, been in violation of
    TS Section 3.2.2. The circumstances of the event and the notifications
    were reviewed.


Program Director Radiation Protection Services
                              -9-
Public Health Division
    The inspector verified that the licensee had taken what they thought were
Oregon Health Authority
    appropriate corrective actions once the issue was identified. Corrective
800 NE Oregon Street, Suite 640
    actions included immediately shutting down the reactor, investigating the
Portland, OR  97232-2162
    problem and making the repairs that they thought would repair the
    channel. Following repairs and discussion of the issue with the Reactor
Test, Research, and Training
    Director, the reactor was placed back in operation.
    The licensee was informed that the failure to have all of required channels
    operable during reactor operation was a Severity Level IV violation of
    TS Section 3.2.2. However, the safety consequences were low because
    the reactor was operated at a power level less than 5 W and 2 of the 3
    required channels were operable to provide any required reactor scram.
    The inspector determined that this particular problem had been identified
    by the licensee and promptly reported to the NRC. What the licensee
    thought were adequate corrective actions had been identified and
    implemented. As a result, the licensee was informed that this issue would
    be treated as a NCV, consistent with Section VI.A.8 of the NRC
    Enforcement Policy (NCV 50-288/2016-202-04).
    This issue is considered closed.
(5) Reactor Pool Overfill Problem
    As noted above, near the end of May, the licensee found that the reactor
    pool had overflowed. Upon investigation the licensee found that the
    problem had occurred due to a malfunction of the recently installed
    automatic fill system. In the past, as part of a weekly checklist, staff
    members were tasked with checking the pool level and adding water if the
    pool level dropped below a certain mark. However, on occasion, the staff
    members forgot to shut the fill water off and the tank was nearly over
    filled. To correct that problem, under the auspices of the 10 CFR 50.59
    program, the licensee installed an automatic fill control system.
    Unfortunately, the automatic system failed on May 28, 2016, and the pool
    overfilled to the point that water entered the nuclear instrumentation tubes
    leading to the detectors. The Percent Power channel and the Log
    Channel were affected; the Linear Channel was not damaged.
    The overfill caused problems that persisted with the two affected
    channels from June through October (as noted above). The licensee was
    informed that the issue of correcting the overfill problem would be
    designated by the NRC as an IFI and would be reviewed during future
    inspections (IFI 50-288/2016-202-05).


  Reactor Newsletter
                                              - 10 -
University of Florida
    c.    Conclusion
202 Nuclear Sciences Center
            Reactor staffing, operations, and logs were generally acceptable. One apparent
Gainesville, FL  32611
            violation was identified for operating the reactor without the logarithmic channel
            being operable as required by TS Section 3.2.2. One apparent violation was
            identified for failure to conduct a 10 CFR 50.59 review. One non-cited violation
            was identified for operating the reactor without the logarithmic channel being
            operable as required by TS Section 3.2.2.
4. Operator Requalification Program
    a.    Inspection Scope (IP 69001)
            The inspector reviewed selected portions of the following regarding the RRR
            Requalification Plan to ensure that the requirements of the plan and
            10 CFR 55.59, Requalification, were being met:
              Main (Reactor Console) Log Nos. 86 - 89
              Active license status of all current operators
              Medical examination records for selected operators
              RRR Facility Requalification Program, dated July 2009
              RRR Facility Alternate Requalification Plan, dated September 2016
              Training lectures and records for the current training cycle
              NRC Form 398, Personal Qualification Statement - Licensee
              Written examinations given during 2014 and 2015 for selected operators
              RRR Facility Requalification Plan, dated July 2009
              NRC Form 396, Certification of Medical Examination - by Facility Licensee
              RRR Facility Requalification Meeting Agenda and Attendance Sheets for
                September 2014 through the present
              Requalification Hours and Reactivity Manipulation Sheets documenting
                reactivity manipulations for 2014 through the present for selected operators
              RRR Administrative Procedures, Section 9, Record Retention
              Various RRR SOPS including: SOP 63, Requalification; SOP 63 Appendix
                A, Reactor Operator Physical Exam; and SOP 63,
                Appendix B, Accelerated Requalification Form
    b.    Observations and Findings
            (1)      Routine Requalification Program - For the Period 2014 through
                    June 2015 and for July 2015 through June 2016
                    As noted previously, there are currently 20 qualified SROs and
                    19 qualified ROs at the RRR facility. The inspector reviewed selected
                    operators licenses and noted that they were current.


  ML16349A652; *concurrence via e-mail  NRC-002
                            - 11 -
OFFICE NRR/DPR/PROB* NRR/DPR/PROB* NRR/DPR/PROB NAME CBassett NParker AMendiola DATE 12/16/16 12/16/16 12/21/16 
    The inspector reviewed the requalification program for July 2014 through
     Enclosure 1 NOTICE OF VIOLATION
    June 2015, and for July 2015 through June 2016, as well as the annual
  Reed College         Docket No. 50-288
    drill scenarios and attendance sheets. It was noted that operators
Reed Research Reactor      License No. R-112
    typically made entries on the Requalification Hours and Reactivity
    Manipulation Sheet that was located in the control room. Through these
    actions the hours on duty and in what capacity (i.e., RO/SRO), as well
    as the tasks performed, were documented. The inspector also reviewed
    the Requalification Meeting Agenda and Attendance Sheets for the period
    from September 2014 through the present. The inspector reviewed
    various individual operators requalification records as well.
    The review of the various logs and records noted above showed that
    training had been conducted in accordance with the licensees
    requalification and training program until May 2016. Training reviews and
    examinations had been completed and documented as required. The
    records indicated that operators were completing the required activities,
    including reactivity manipulations and number of operating hours.
    Records indicated that annual operations tests and supervisory
    observations were being completed. Biennial written examinations were
    also being completed as required or credit was taken by the licensee for
    the exams administered by the NRC to satisfy the requalification cycle
    exam requirements when applicable. Additionally, the inspector noted
    that operators were receiving the required biennial medical examinations
    within the required time frame.
(2) Alternate Requalification Plan - For the period from July 2016 until the
    Reactor is Operational
    As noted in Section 3 of this report, the RRR has been functional and
    operational only sporadically since May 2016. Because of this problem,
    operators have not been able to complete the operational requirements to
    remain fully qualified. The licensee recognized this and proposed an
    alternate requalification plan to the NRC in September. The alternate
    plan was reviewed and subsequently approved.
    The Alternate Requalification Plan stipulated that two Reed College
    SROs would go to the OSU research reactor facility and complete two
    hours of reactor operation under direction of OSU personnel and two
    hours of supervision of the other Reed College operator. These two
    individuals would also complete one reactivity manipulation each while at
    OSU as well. This would suffice for the reactor operation requirements of
     the Reed Requalification Program and allow the two operators to return to
    Reed College and observe Reed operators to operate under their
    direction.
    For the remainder of the operators at Reed who did not go to OSU and
    were out of qualification, the alternate plan required that each operator
    complete three hours of reactor operation and two reactivity
    manipulations under direction of one of the SROs who went to OSU.


                            - 12 -
During a U.S. Nuclear Regulatory Commission (NRC) inspection conducted from October 31 to November 3, 2016 and from November 28 to December 2, 2016, two violations of NRC
    In addition, these operators would then need to meet the routine Reed
requirements were identified. In accordance with the NRC Enforcement Policy, the violations are listed below:
    Requalification Program requirements of four hours of reactor operation
    and two reactivity manipulations for the quarter. If any licensed
    individuals were not in compliance with other requirements outlined in
    10 CFR 55.59, the operators would be required to meet the requirements
    of 10 CFR 55.53, Conditions of licenses, paragraph (f)(2) of six
    additional hours of operation under direction.
    The inspector reviewed the actions of the licensee to comply with the
    requirements of the Alternative Requalification Plan. The inspector
    verified that the two SROs who went to OSU had completed the required
    hours of operation and the required reactivity manipulations. They then
    returned to Reed and began observing other operators. It was noted that
    4 SROs and 2 ROs had completed the requirements of the alternate
    requalification plan. However, it was also noted that only two SROs
    would be in compliance with the Routine Requalification Program if the
    Reed reactor remains shut down through the end of December (the end
    of the quarter). The licensee acknowledged that, if the reactor remains
    shut down through the end of the quarter, all operators who are not in
    compliance with the requalification program requirements will have to
    complete the Alternate Requalification Plan requirements as well as the
    regular Reed Requalification Program requirements before being
    considered qualified to operate the reactor.
(3) Access to the Reed Research Reactor Facility (RRRF) Controlled Access
    Area
    As noted above, the inspector reviewed the Reed Routine Requalification
    Program. During records review it was found the Reed Operations
    Manager was approving individuals access to the facility Controlled
    Access Area (CAA), i.e., signing the access forms. Only the NRC
    approved reviewing official may grant unescorted access to the facility in
    accordance with 10 CFR 73.57, Requirements for criminal history
    records checks of individuals granted unescorted access to a nuclear
    power facility, a non-power reactor, or access to Safeguards Information,
    paragraph (g). The NRC approved reviewing official is the RRRF
    Director as indicated in a letter from the NRC to the licensee. The
    licensee was informed that only the NRC approved reviewing official is
    authorized to approve individuals access. Any changes or request for
    changes must be submitted to the NRC for evaluation.
    Because the decision to grant unescorted access to the CAA of the
    facility was always discussed between, and approved by, both the
    Director and the Reactor Operations Manager, the Director subsequently
    countersigned all the access forms. The licensee agreed that only an
    approved Reviewing Official would sign the access forms in the future.


                                          - 13 -
1. Reed Research Reactor Technical Specification (TS) Section 3.2.2 requires that the reactor shall not be operated unless the reactor power measuring channels in Table 2 are operable. Table 2 lists the Percent Power Channel, the Linear Channel, and the  
  c.    Conclusion
Logarithmic Channel.  
        The requalification/training program was up-to-date and being acceptably
        maintained. Medical examinations were being completed biennially as required.
5. Fuel Handling
  a.   Inspection Scope (IP 69001)
        In order to verify adherence to fuel handling and inspection requirements
        specified in TS Section 4.1, the inspector reviewed selected aspects of the
        following:
            Fuel Element Inspection Cards
            Main (Reactor Console) Log Nos. 86 - 89
            Fuel Element Inspection sheet maintained in the appropriate Fuel Inspection
              Binder
            RRR Administrative Procedures Section 6, Fuel and Special Nuclear
              Material
            Various RRR SOPs including: RRR SOP 35, Fuel and Core; SOP 35,
              Appendix A, Core Diagram; SOP 35, Appendix B, Fuel Handling
              Checklist; SOP 35, Appendix C, Fuel Handling SRO Qualification; and
              SOP 35, Appendix D, Fuel Handling Receipt Form
  b.   Observations and Findings
        Through review of the main logs and interviews with licensee personnel, the
        inspector verified that fuel movements were conducted in compliance with
        procedure. The inspector also verified that the licensee was maintaining the
        required records of fuel movements as they were completed. The logs were
        being filled out properly to indicate which elements were moved and to what
        locations.
        Also through records review, it was noted that the reactor fuel was being
        inspected upon initial receipt and 25 percent of the fuel elements in the core were
        being inspected annually. This exceeded the percentage of fuel elements
        required to be inspected as stipulated by TS Section 4.1. The last annual fuel
        inspection was completed during January 11-27, 2016. The inspector verified
        that all fuel elements were inspected at least once every 5 years, including
        elements in storage and/or removed from service as required.
  c.    Conclusion
        Reactor fuel movements and inspections were completed and documented in
        accordance with procedure and the fuel was being inspected more frequently
        than required by TS Section 4.1.


                                          - 14 -
Contrary to this requirement, from October 6 to October 16, 2016, the reactor was
6. Maintenance and Surveillance
operated or attempted to be operated when the Logarithmic Channel was not operable.  
  a.    Inspection Scope (IP 69001)
This has been determined to be a Severity Level IV violation (Section 6.1).
        To verify that operations, surveillance activities, and calibrations were being
        completed as required by the TS, the inspector reviewed selected portions of:
2. Title 10 of the
            Main (Reactor Console) Log Nos. 86 - 89
Code of Federal Regulations (10 CFR) 50.59, "Changes, tests, and experiments," paragraph (c)(1) states, in part, that a licensee may make changes in the
            Maintenance Log pages completed for unscheduled work
facility as described in the final safety analysis report without obtaining a license amendment pursuant to 10 CFR 50.90 only if:  (i) a change to the technical specifications incorporated in the license is not required, and (ii) the change does not
            Associated surveillance and calibration data and records for 2015-2016
meet any of the criteria in 10 CFR 50.59(c)(2).  
            Other Checklists Notebook which contained calibration forms, inspection
The regulation in 10 CFR 50.59(c)(2) requires, in part, that a licensee shall obtain a license amendment pursuant to 10 CFR 50.90 prior to implementing a proposed change if the change would: (i) result in more than a minimal increase in the frequency of
            forms, and various checklists
occurrence of an accident previously evaluated in the final safety analysis report;
          Various RRR SOPs and Appendices including: SOP 23, Biweekly Checklist;
(ii) result in more than a minimal increase in the likelihood of occurrence of a malfunction
            SOP 23, Appendix A, Biweekly Checklist Form; SOP 24, Bimonthly
of a structure, system, or component (SSC) important to safety previously evaluated in the final safety analysis report; (iii) result in more than a minimal increase in the
            Checklist; SOP 24, Appendix A, Bimonthly Checklist Form; SOP 25,
consequences of an accident previously evaluated in the final safety analysis report; (iv) result in more than a minimal increase in the consequences of a malfunction of an
            Semiannual Checklist; SOP 25, Appendix A, Reed Research Reactor
SSC important to safety previously evaluated in the final safety analysis report; (v) create a possibility for an accident of a diffe
            Semiannual Checklist; SOP 26, Annual Checklist; SOP 26, Appendix A,
rent type than any previously evaluated in the final safety analysis report; (vi) create a possibility for a malfunction of an SSC
            Annual Checklist Form; SOP 34, Control Rods; SOP 34, Appendix A,
important to safety with a different result than any previously evaluated in the final safety analysis report; (vii) result in a design basis limit for a fission product barrier as
            Control Rod Calibration Form; SOP 34, Appendix B, Control Rod
described in the FSAR being exceeded or altered; or (viii) result in a departure from a
            Inspection Checklist; SOP 34, Appendix C, Control Rod Inspection Form;
method of evaluation described in the FSAR used in establishing the design bases or in
            and, SOP 60, Logbook Entries; and associated Appendix A, Maintenance
            Log forms
          RRR Annual Reports for the last two reporting periods
  b.    Observations and Findings
        The licensee conducted various maintenance and surveillance activities which
        were then documented on the appropriate forms and checklists. The inspector
        verified that these activities were conducted within the time frame required and
        according to procedure. The inspector reviewed selected biweekly, bimonthly,
        semiannual, and annual forms and checklists. All the recorded results reviewed
        were within the TS and procedurally prescribed parameters. The records and
        logs reviewed appeared to be complete and were being maintained as required.
        The inspector was not able to observe a Startup or Shutdown Checklist being
        performed during the inspection. However, previously completed Startup and
        Shutdown Checklists were reviewed. These activities appeared to have been
        conducted appropriately and in accordance with procedure.
        A review of the RRRF Main Logs and current Maintenance Logbook showed that
        these records were also being completed as required and problems, if any, were
        being documented. Through observation and records review, the inspector also
        confirmed that maintenance was being conducted as needed, consistent with the
        TS.


the safety analyses.  
                                          - 15 -
The regulation in 10 CFR 50.59(d)(1) requires, in part, that the licensee shall maintain records of changes in the facility made pursuant to 10 CFR 50.59(c). These records 
  c.   Conclusion
- 2 -  must include a written evaluation which provides the bases for the determination that the change does not require a license amendment pursuant to 10 CFR 50.59(c)(2). The Reed Research Reactor safety analysis report (SAR) states in Chapter 7,
        Maintenance was being completed as required. The program for surveillance
Section 7.2.3.3, that the Percent Power channel has an associated Uncompensated Ion
        was being carried out in accordance with TS requirements.
Chamber that provides indication for that channel.  
7. Procedures
  a.    Inspection Scope (IP 69001)
        To determine whether facility procedures met the requirements outlined in
        TS Section 6.4, the inspector reviewed portions of the following:
            Procedural reviews and updates documented in the ROC meeting minutes
            RRR Administrative Procedures, Section 8, Adoption and Revision of
            Operating Procedures, and Section 9, Record Retention
            Various RRR SOPs and Appendices including: SOP 60, Logbook
            Entries;SOP 61, Procedure Writing and Use; SOP 61, Appendix A,
            Document Structure; SOP 61, Appendix B, Document Locations; and
            SOP 61, Appendix C, Temporary Procedure Change
  b.    Observations and Findings
        Procedures were in effect for those activities specified in TS Section 6.4 as
        required. RRR Administrative Procedures and SOPs were found to be
        acceptable for the current staffing level and status of the facility. The
        Administrative Procedures and SOPs specified the responsibilities of the various
        members of the staff. Substantive changes to procedures were being reviewed
        and approved by the ROC. The procedures were being audited, reviewed, and
        updated as needed.
        The inspector reviewed the temporary procedure changes that had been
        promulgated during the past 12 months. The changes were written after minor
        problems with the procedures were noted. The temporary changes were
        typically incorporated in the referenced procedures if deemed appropriate by the
        licensee. Changes suggested as a result of the ROC and independent audits
        were also incorporated into the procedures if deemed appropriate.
  c.   Conclusion
        Facility procedures for the safe operation of the reactor were available as
        required by TS Section 6.4.


                                        - 16 -
Contrary to the above requirements, on October 5, 2016, the licensee made a change to the facility as described in the SAR without conducting an evaluation to determine whether or not the change would require a change to the TSs or should have required a  
8. Experiments
license amendment.  Specifically, the licensee replaced the detection chamber
  a.    Inspection Scope (IP 69001)
associated with the Percent Power channel with a fission chamber which was not as  
        In order to verify that experiments were being conducted within approved
described in the SAR without performing an evaluation of the change using the criteria in 10 CFR 50.59(c)(1) and (2) to determine if the change would require a change to the TSs or should have required a license amendment.  
        guidelines specified in TS Sections 3.6, 4.6, and 6.5, the inspector reviewed
        selected portions of the following:
            Experiment review and approval by the ROC
            Selected Irradiation Request Forms for 2015 and 2016
            Approved RRR Routine Experiments (REs), including: RE 1, Irradiation with
            Neutrons; RE 2, Irradiation with Gammas; RE 3, Fuel, Graphite, or Source
            Material; RE 4, Reactor Power Measurement; RE 5, Control Rod Worth
            Measurement; RE 6, Pool Parameter Measurement; RE 7, Fuel Loading;
            RE 8, Cerenkov Radiation Spectrum Acquisition; RE 9, Neutron Induced
            Auto-Radiography; and RE 10, Radial Flux Measurements
            Approved RRR Special Experiment (SE), SE 4, Core Temperature
            Measurements
            RRR Administrative Procedures, Section 4, Reactor Experiments; and
            Section 9, Record Retention
            Various RRR SOPs and Appendices including: SOP 10, Irradiation
            Preparation; SOP 10, Appendix A, Irradiation Request Form; SOP 10,
            Appendix D, Irradiation Request Log; SOP 11, Irradiation Analysis;
            SOP 12, Lazy Susan; SOP 13, Rabbit; SOP 14, Central Thimble;
            SOP 15, Beam; SOP 15, Appendix A, Beam Irradiation Request
            Form;SOP 16, Near Core; and SOP 17, Gamma Irradiations
  b.    Observations and Findings
        The inspector noted that the various experiments conducted at the facility, and
        revisions thereto, were being reviewed and approved as required. It was also
        noted that the two most recently proposed REs had been submitted by licensee
        staff and students and had been reviewed and approved by the Facility Director
        and the ROC as required.
        Through a review of console logs and various irradiation request forms, the
        inspector noted that irradiations were conducted under the cognizance of the
        Facility Director and the Reactor Supervisor as required. The irradiations were
        documented in the Main Log and the results of the experiments were
        documented on the Irradiation Request Forms as required. The resulting
        radioactive material was being transferred to an authorized user, disposed of as
        stipulated by procedure, or held for decay.


                                        - 17 -
This has been determined to be a Severity Level IV violation (Section 6.1).
  c.  Conclusion
Pursuant to the provisions of 10 CFR 2.201, "Notice of violation," Reed College is hereby
        The licenses program for the control of experiments generally satisfied
required to submit a written statement or explanation to the U.S. Nuclear Regulatory
        TS Sections 3.6, 4.6, and 6.5 and other regulatory requirements.
Commission, ATTN:  Document Control Desk, Washington, D.C. 20555-0001, with a copy to the  
9. Emergency Preparedness
responsible inspector, within 30 days of the date of the letter transmitting this Notice of Violation
  a.  Inspection Scope (IP 69001)
(Notice). This reply should be clearly marked as a "Reply to a Notice of Violation" and should
        To verify compliance with the RRRF, E-Plan, the inspector reviewed selected
include for each violation:  (1) the reason for each violation, or, if contested, the basis for disputing the violation or severity level; (2) the corrective steps that have been taken and the results achieved; (3) the corrective steps that will be taken to avoid further violations; and (4) the date when full compliance will be achieved. Your response may reference or include previously docketed correspondence, if the correspondence adequately addresses the required response.
        aspects of the following:
If an adequate reply is not received within the time specified in this Notice, an order or Demand for Information may be issued as to why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be taken. Where good cause is
          ERR E-Plan last revised August 2014
          Emergency response training records for the past 2 years
          Emergency drills and exercises held during 2015 and 2016
          Emergency response facilities, supplies, equipment and instrumentation
          ERR SOP 25, Semiannual Checklist
          ERR SOP 25, Appendix A, Reed Research Reactor Semiannual Checklist
          ERR E-Plan, Appendix a, Emergency Implementation Procedures (EIPs)
          ERR E-Plan, Appendix B, Projected Doses for Bounding Accidents
          ERR E-Plan, Appendix C, Visible and Audible Alarms
  b.   Observations and Findings
        The E-Plan in use at the reactor had been updated, reviewed, and approved by
        the ROC. The licensee had determined that there was no decrease in
        effectiveness as defined in 10 CFR 50.54, Conditions of licenses,
        paragraph (q). The licensee had submitted a letter to the NRC documenting this
        determination on August 18, 2014.
        The E-Plan and EIPs were being audited and reviewed annually as required.
        Supplies, instrumentation, and equipment staged for emergency use were being
        maintained, controlled, and inventoried semiannually as required in the E-Plan. It
        was noted that the Emergency Support Center was located in the RRRF
        Directors office in the Chemistry Building.
        Through records review and interviews with licensee personnel, emergency
        responders were determined to be knowledgeable of the proper actions to take in
        case of an emergency. The inspector reviewed the Agreement Letters that had
        been signed with various emergency support organizations. These agreements
        were being maintained and updated as needed.
        Communications capabilities were acceptable and had been tested and
        emergency information updated as stipulated in the E-Plan. It was noted that the
        Emergency Notification Call List, posted in various locations throughout the
        facility, was current and the most recent version was dated October 5, 2016.
        The inspector verified that training for staff and offsite support personnel was
        being provided annually as required.


shown, consideration will be given to extending the response time. If you contest this enforcement action, you should also provide a copy of your response, with the basis for your denial, to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission,
                                            - 18 -
Washington, D.C. 20555-0001.  
          Training for staff was typically completed through the Operator Requalification
Because your response will be made available el
          Program. Training for representatives from the Portland Fire and Rescue
ectronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRC's  Agencywide Documents Access and Management System (ADAMS), to the extent possible, it should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the public without redaction. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). If personal
          Department (PF&RD) was conducted annually. Training for representatives from
privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be
          the Portland Police Bureau was offered but the police could not always commit to
protected and a redacted copy of your response that deletes such information. If you request
          attend because of staffing level shortages.
withholding of such material, you must specifically identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g.,  
          Emergency drills had been conducted annually as required by the E-Plan.
explain why the disclosure of information will create an unwarranted invasion of personal
          Off-site support organization participation was also as required by the E-Plan.
          Critiques were held following the drills to discuss the strengths and weaknesses
          identified during the exercises and to develop possible solutions to any problems
          identified. The results of these critiques were documented and reported to the
          Radiation Safety Committee/ROC. Drills involving off-site personnel were being
          conducted annually and documented as stipulated by the E-Plan.
          The inspector and the Facility Director visited a PF&RD unit located several miles
          from the RRRF. The inspector and Director were given a tour of the facility and
          observed the equipment maintained by the unit for response to various types of
          emergencies. As a result of this visit, and following a review of the licensees
          records documenting drills and training, the inspector verified that fire department
          personnel were well trained, properly equipped, and knowledgeable of the
          actions to take in case of an emergency at the reactor facility. The inspector
          determined that the licensee communicated with the PF&RD frequently and was
          maintaining a good working relationship with this support group.
    c.   Conclusion
          The emergency preparedness program was conducted in accordance with the
          E-Plan.
10. Follow-up on Previously Identified Items
    a.   Inspection Scope (IP 92701)
          The inspector reviewed the actions taken by the licensee to address a previously
          identified IFI.
    b.   Observation and Findings
          50-288/2014-202-01 - IFI - Follow-up on the licensees actions to correct the
          inconsistencies between the E-Plan and the Implementing Procedures dealing
          with the Alert classification of various events.
          During an inspection in December 2014, the inspector reviewed of the E-Plan. It
          was noted that there were no accidents that could cause an Alert classification
          for the facility. However, certain security events would require an Alert"
          Nevertheless, it was noted that there were various EIPs which indicated that, in
          certain accident situations, the classification for the event would be Alert.


privacy or provide the information required by 10 CFR 2.390, "Public inspections, exemptions,
                                            - 19 -
- 3 -  requests for withholding," paragraph (b) to support a request for withholding confidential commercial or financial information). If safeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21,  
            The licensee acknowledged these inconsistencies and agreed to correct the
"Protection of Safeguards Information: Performance Requirements."
            problem. The licensee was informed that correcting these issues would be
            followed by the NRC as an IFI.
            During this inspection, the inspector reviewed the actions taken by the licensee
            to resolve the inconsistencies between the E-Plan and the EIPs. It was noted
            that the procedures had been revised to indicate that accidents or events
            occurring in conjunction with security events require the Alert designation.
            Otherwise these events are classified as Unusual Events. This issue is
            considered closed.
    c.      Conclusions
            One IFI was reviewed and this issue is considered closed.
11. Exit Interview
    The initial scope of the inspection were summarized on November 2, 2016, with the
    Facility Director, the Reactor Manager, and the Dean of Faculty. On November 3, 2016,
    the preliminary results were discussed with the Facility Director and the Reactor
    Manager. On December 1, 2016, the results of the inspection were discussed with the
    Facility Director and the Dean of Faculty. On December 2, 2016, the results of the
    inspection were reiterated with the Facility Director. The inspector discussed the
    findings for each area reviewed. The licensee acknowledged the findings and did not
    identify as proprietary any of the material provided to or reviewed by the inspector during
    the inspection.


                        PARTIAL LIST OF PERSONS CONTACTED
In accordance with 10 CFR 19.11, "Posting of notices to workers," you may be required to post
Licensee
this Notice within two working days.  
C. Barrett            Reactor Operations Manager
Dated this 21st day of December
S. Brodesser          Training Supervisor
 
T. Freeman            Requalification Supervisor
   Enclosure 2 U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION
A. Karr              Radiation Safety Officer and Campus Environmental Director
 
J. Koh                Operations Supervisor
Docket No. 50-288  
M. Krahenbuhl        Director, Reed Reactor Facility
M. McCarthy          Projects Supervisor
N. Nicholson          Dean of the Faculty, Reed College
M. Oxley              Training Supervisor
Other Personnel
S. Christensen        First Lieutenant, Portland Fire and Rescue, Training, Safety, and EMS
                      Division, City of Portland
B. Profit            Training Lieutenant, Portland Fire and Rescue, Training, Safety, and EMS
                      Division, City of Portland
                              INSPECTION PROCEDURE USED
IP 69001   Class II Non-Power Reactors
                        ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
50-288/2016-202-01        IFI    Follow-up on the licensees actions to maintain logs which
                                  contain the accurate and complete documentation of scram
                                  events and other operational events.
50-288/2016-202-02        VIO    Failure to have all of required channels operable during
                                  reactor operation as required by TS Section 3.2.2.
50-288/2016-202-03        VIO    Failure to complete a review prior to installing a fission
                                  chamber instead of an uncompensated ion chamber with the
                                  Percent Power Channel (as stipulated in the facility SAR) as
                                  required by 10 CFR 50.59 (c)(1)(i and ii) and (c)(2)(i-viii).
50-288/2016-202-04        NCV    Failure to have all of required channels operable during
                                  reactor operation as required by TS Section 3.2.2.
50-288/2016-202-01        IFI    Follow-up on the licensees actions to correct the reactor pool
                                  overfill problem caused by the automatic fill system installed
                                  by the licensee.


                                            -2-
Closed
License No.  R-112
50-288/2014-202-01        IFI   Follow-up on the licensees actions to correct the
 
                                inconsistencies between the E-Plan and the Implementing
Report No.  50-288/2016-202
                                Procedures dealing with the Alert classification of various
 
                                events.
50-288/2016-202-04       NCV   Failure to have all of required channels operable during
Licensee:  Reed College
                                reactor operation was a Severity Level IV violation of
                                TS Section 3.2.2.
                                LIST OF ACRONYMS USED
Facility:  Reed Research Reactor
10 CFR       Title 10 of the Code of Federal Regulations
 
CAA         Controlled Access Area
  Location:  Portland, Oregon
CAR         Corrective Action Report
 
E-Plan       Emergency Plan
EIP         Emergency Implementation Procedures
HV           High Voltage
Dates:  October 31, 2016 - November 3, 2016
IFI         Inspector Follow-up Item
  November 28, 2016 - December 2, 2016
IP           Inspection Procedure
 
kW           Kilowatt
Inspector:  Craig Bassett
NCV         Non-Cited Violation
 
No.         Number
NRC         Nuclear Regulatory Commission
Accompanied by: Michele DeSouza, Examiner    John Nguyen, Examiner
OSU         Oregon State University
  Michael Takacs, Security Specialist
PF&RD       Portland Fire and Rescue Department
 
RE           Routine Experiment
RO           Reactor Operator
ROC         Reactor Operations Committee
Approved by: Anthony J. Mendiola, Chief Research and Test Reactors Oversight Branch
RRR         Reed Research Reactor
Division of Policy and Rulemaking
RRRF         Reed Research Reactor Facility
Office of Nuclear Reactor Regulation 
SAR         Safety Analysis Report
    EXECUTIVE SUMMARY
SE           Special Experiment
Reed College Reed Research Reactor Facility NRC Report No. 50-288/2016-202
SOP         Standard Operating Procedure
The primary focus of this routine, announced inspection included onsite review of selected
SRO         Senior Reactor Operator
aspects of the Reed College (the licensee) Class II research reactor safety program.  This included a review of:  (1) organization and staffing, (2) review and audit and design change functions, (3) conduct of operations, (4) operator requalification program, (5) fuel handling,
SSC         Structure, System, or Component
(6) maintenance and surveillance, (7) procedures, (8) experiments, and (9) emergency
TS           Technical Specifications
preparedness.  The licensee's program was acceptably directed toward the protection of public
UIC         Uncompensated Ion Chamber
health and safety.  Two apparent Severity Level IV violations and one Severity Level IV non-cited violation were identified.
VIO         Violation
W           Watt
Organization and Staffing
The organization and staffing remain in compliance with the requirements specified in Technical Specification (TS) Section 6.1.
Review and Audit and Design Change Functions
Review and oversight functions required by TS Section 6.2 were acceptably completed by the Reactor Operations Committee.  Audits were being completed as required.
  The design change program being implemented at the facility generally satisfied Nuclear Regulatory Commission requirements.
Conduct of Operations
Operations were generally being conducted in accordance with TS and procedural
requirements.
Two apparent violations and one non-cited violation were identified involving the nuclear measuring channels of the reactor.
Operator Requalification Program 
The operator requalification/training program was up-to-date and being acceptably implemented and documented.
  Biennial medical examinations were being completed as required.   
A one-time Alternate Requalification Plan was initiated due to the problems created by
malfunctioning nuclear instrumentation.
 
- 2 -  Fuel Handling 
Reactor fuel movements and inspections were conducted and documented in accordance with procedure.
Twenty-five percent of the fuel elements were being inspected on an annual basis.
Maintenance and Surveillance
  Maintenance was being completed as needed.
The surveillance program, including calibration of equipment, was being completed in accordance with TS Sections 3 and 4.
Procedures
Facility procedures were available for the safe operation of the reactor as required by
TS Section 6.4.
Experiments
The program for the control of experiments satisfied TS Sections 3.6, 4.6, and 6.5 and other
regulatory requirements.
Emergency Preparedness
The Emergency Plan (E-Plan) and Emergency Implementation Procedures were being audited and reviewed annually as required.
  Letters of Agreement documenting emergency support to be provided by offsite agencies
were being maintained and periodically updated.
Annual drills were being held and documentation of the drills and the follow-up critiques was maintained.  Subsequent corrective actions were taken as needed.
  Emergency preparedness training for staff and offsite personnel was being conducted as stipulated in the E-Plan.
    REPORT DETAILS
  Summary of Facility Status
 
The Reed College (the licensee's) 250 kilowatt TRIGA Mark I research reactor was typically operated in support of undergraduate instruction, laboratory experiments, reactor system
testing, reactor surveillances, and operator training.  During this inspection the reactor was not
operated due to nuclear instrumentation issues.
1. Organization and Staffing
a. Inspection Scope (Inspection Procedure (IP) 69001)
To verify the organization and staffing requirements specified in technical specifications (TSs) Section 6.1 were being met, the inspector reviewed selected
aspects of the following:
  Main (Reactor Console) Log - Numbers (Nos.) 86 - 89  Reed Research Reactor (RRR) facility organization and staffing during reactor operations  Administrative controls and management responsibilities specified in the TS
and facility procedures  RRR Administrative Procedures, Section 1, "Personnel," and Section 3, "Reactor Operations"  RRR Standard Operating Procedure (SOP) 60, "Logbook Entries"  RRR Annual Report for the period from July 1, 2014, through  June 30, 2015, submitted to the U.S. Nuclear Regulatory Commission (NRC) on August 7, 2015  RRR Annual Report for the period from July 1, 2015, through  June 30, 2016, submitted to the NRC on July 27, 2016
b. Observations and Findings
Through discussions with licensee representatives, the inspector determined that
management responsibilities and the organizational structure at the RRR facility
had not changed since the previous NRC in
spection of licensee operations in December 2014 (Inspection Report No. 50-288/2014-202).  The inspector
determined that the Facility Director retained direct control and overall
responsibility for management of the facility as specified in the TS.  The Facility
Director reported to the President of Reed College through the Dean of Faculty.  This organization was consistent with that specified in the TS. 
It was noted that since the last operations inspection in 2014, a new person had
been hired to be the Reactor Operations Manager.  Also, a new person had been
hired to fill the position of campus Radiation Safety Officer/Director of
Environmental Health and Safety.
 
- 2 The licensee's current operational organization consisted of the Facility Director, a Reactor Operations Manager, a Radiation Safety Officer, an Operations Supervisor, a Training Supervisor, an Assistant Training Supervisor, a Projects
Supervisor, and a Requalification Supervisor.  The Facility Director, Reactor
Operations Manager, and Radiation Safety Officer positions were full-time while
 
the rest were part-time positions filled by students.  Except for the Radiation
Safety Officer, the aforementioned individuals, in addition to their administrative duties, were qualified reactor operators (ROs) or senior reactor operators (SROs).  It was noted that there were a total of 20 SROs and 19 ROs licensed to
operate the RRR.
c. Conclusion
Organization and staffing met the requirements specified in TS Section 6.1.
2. Review, Audit, and Design Change Functions 
a. Inspection Scope (IP 69001)
In order to verify that the licensee had established and conducted reviews and
audits as required, and to determine whether facility modifications and change
reviews were consistent with Title 10 of the
Code of Federal Regulations (10 CFR) Section 50.59, "Changes, tests and experiments," and TS Section 6.2, the inspector reviewed selected portions of the following:
  Maintenance Log pages completed for unscheduled work  Corrective Action Reports (CARs) for 2015 and to date in 2016  Design changes reviewed under 10 CFR 50.59 for 2015 and 2016  Reactor Operations Committee (ROC) meeting minutes from  October 2014 through the present
RRR Administrative Procedures, Section 1, "Personnel;" Section 2, "Reactor Review Committee;" and Section 9, "Record Retention"  RRR SOP 62, "Changes, Tests, and Experiments," and SOP 69, "Corrective Action Report;" and associated forms, "Corrective Action Reports;" last revised August 26, 2014  RRR Annual Reports for the last two reporting periods
b. Observations and Findings
(1) Review and Audit Functions
The inspector reviewed ROC meeting minutes from October 2014
through the present.  These meeting minutes showed that the committee
was meeting at the required frequency and was considering the types of
topics outlined by the TS.
The inspector noted that, since the last NRC inspection, the appropriate
audits had been completed by the ROC and an external auditor in the 
- 3 -  various areas outlined in the TS.  The audits were designed so that most aspects of the licensee's operations and safety programs were reviewed every year.  Various facility documents, such as the Radiation Protection
Program, the Emergency Plan (E-Plan), the Fire Plan, the Administrative
Procedures, and the Requalification Plan comprised the material that was
typically reviewed.  The Reactor Experiments and various SOPs were
also reviewed.  The inspector noted that the audits and the resulting findings were detailed and that the licensee responded and took corrective actions as needed.
 
(2) Design Changes
The inspector reviewed the licensee's 10 CFR 50.59 screening forms concerning changes or modifications that had been initiated at the facility
for 2015 and to date in 2016.  The results indicated that none of the
screenings required further evaluation under 10 CFR 50.59.  The
inspector also reviewed the Maintenance Log pages that had been completed for unscheduled work associated with various systems.  The forms contained a section which required a 50.59 Screen to be completed
prior to initiating the work.  None of the maintenance items reviewed
required any further actions, such as a 50.59 evaluation, to be completed
except as noted in Part 3, Section (3) below.  None of the other changes
reviewed by the inspector met any of the criteria of 10 CFR 50.59(c)(1) and (2), which would have required a TS change or a license amendment
from the NRC.
c. Conclusion
Review and oversight functions required by TS Section 6.2 were acceptably completed by the ROC.  Audits were being completed as required.  The
 
licensee's design change program gener
ally satisfied NRC requirements.
3. Conduct of Operations
The inspector reviewed selected aspects of the following to verify operation of the reactor in accordance with TS Sections 3, 4, and 6.1:
a. Inspection Scope (IP 69001)
  Main (Reactor Console) Log Nos. 86 - 89  Various SCRAM Response Forms for 2015 and 2016  CARs for 2015 and to date in 2016  Maintenance Log pages completed for unscheduled work  Selected Startup Checklist Forms for the period from January 2015 through
the present  Selected Shutdown Checklist Forms for the period from January 2015 through the present  RRR Administrative Procedures, Section 3, "Reactor Operations" 
- 4 -    Various RRR SOPs and Appendices including SOP 1, "Reactor Operations;" SOP 20, "Startup Checklist;" SOP 20, Appendix A, "Startup Checklist Form;" SOP 21, "Same Day Startup Checklist;" SOP 21, Appendix A, "Same-Day
 
Startup Checklist Form;" SOP 22, "Shutdown Checklist;" SOP 22,
Appendix A, "Shutdown Checklist Form;" SOP 23, "Biweekly Checklist;" SOP 23, Appendix A, "Biweekly Checklist Form;" SOP 24, "Bimonthly Checklist;"
SOP 24, Appendix A, "Bimonthly Checklist Form;" SOP 25, "Semiannual Checklist;" SOP 25, Appendix A, "Reed Research Reactor Semiannual Checklist;" SOP 26, "Annual Checklist;" SOP 26, Appendix A, "Annual
Checklist Form;" SOP 33, "Nuclear Instruments;" SOP 34, "Control Rods;"
SOP 60, "Logbook Entries;" and, SOP 69, "Corrective Action Report"  RRR Annual Reports for the last two reporting periods
b. Observations and Findings
(1) Routine Operations
 
The inspector reviewed selected reactor operating records from January 2015 through the present.  These records included daily Startup
Checklists, Shutdown Checklists, Experimental Startup and Shutdown
Checklists, associated forms, Weekly Checklists, and the Main (reactor
console) Logs.  The records indicated that the activities were generally
carried out in accordance with written procedures as required by TS Section 6.4, except as noted below.  The checklists were completed and signed off by the appropriate personnel as required.
 
Through interviews with operators and review of logs and records, the
inspector confirmed that shift staffing met the minimum requirements for duty and on-call personnel as required by TS Section 6.1.
Information on the operational status of
the facility was generally recorded properly on the log sheets and/or checklists as required by procedure. 
Scrams were identified in the logs and were reported and resolved as
required before reactor operations were allowed to continue.  However, it was noted that the logs were not totally complete in that they did not indicate who authorized operations to resume.  The inspector indicated
that the complete documentation of reactor operations should include not
 
only when and why a scram occurred, but who gave the authorization to
resume operations as well.  The licensee was informed that the issue of complete and accurate documentation of scram events and other operational events would be designated by the NRC as an Inspector
Follow-up Item (IFI) and would be reviewed during future inspections 
(IFI 50-288/2016-202-01).
 
 
- 5 -  (2) NRC-Identified Violation of TS Section 3.2.2
TS Section 3.2.2 requires that the reactor shall not be operated unless
the reactor power measuring channels in Table 2 are operable.  Table 2
lists the Percent Power Channel, the Linear Channel, and the Logarithmic
 
Channel.
On May 28, 2016, the licensee discovered that the facility reactor pool had overflowed due to a malfunction of the recently installed automatic fill
system.  On May 30, 2016, operators noticed that all reactor trips were
illuminated.  Because of this, the reactor was determined to be inoperable
due to electronics problems.  In mid-June, some of the electronic components of the power measuring channels, including the Logarithmic Channel pre-amp and the Percent Power Channel High Voltage (HV)
power supply, were removed and taken to Oregon State University (OSU)
by the electronics specialist from OSU where he worked to correct the
problems.  It was noted that the Linear Channel was not found to have
been damaged.
During August 8 and 9, the OSU electronics specialist came to Reed
College and installed the repaired pre-amp and HV power supply for the
Log and Percent Power channels.  After the electronics were installed,
the licensee determined that the detector chambers associated with the Percent Power and Logarithmic Channels were not functioning properly.  Licensee personnel then removed the assemblies for each channel from
the reactor pool and began the process of trying to dry out the detectors.
 
On October 5, after the channel detectors were thought to be completely dry, the electronics specialist from OSU again came to Reed College to help test and reinstall the power channels.  At that point the Log channel
was determined to be functional but the Percent Power Channel shorted
out and was not functional.  Upon further investigation, the licensee found
that the detector associated with the Percent Power Channel was not an UIC as stipulated in the SAR but a fission chamber operating in current mode.  Because that fission chamber was not functioning, licensee staff and the OSU electronics specialist installed a spare fission chamber (one
 
that Reed had on hand) with the Percent Power Channel to see if it would
operate.  The channel appeared to be functioning properly and appeared
to be giving the expected signals.
The following day, October 6, licensee staff attempted to adjust the
detectors and conduct a core excess and power calibration of the reactor. 
Although the power channels appeared to be working properly, the
Percent Power Channel had repeated HV scrams.  Licensee staff found a
loose wire and corrected that problem.  During the next few days licensee staff adjusted the Linear Power and Percent Power detector positions to adjust for power calibration.  However, another HV Percent Power scram
occurred, the cause of which could not be explained. 
- 6 -  On October 13, channel testing continued and core excess measurements were again attempted but to no avail and the Percent Power Channel was determined to be non-functional.  On
October 14, the OSU electronics specialist returned to Reed and installed
a spare UIC (one that OSU had received from another university) to
operate in the Percent Power Channel.  On October 16, the licensee
completed core excess and reactor power calibrations.  They operated up to 150 kilowatt (kW) for training and operator requalification. Two days later operations were conducted for requalification but the
Log channel was determined to be erratic, possibly due to electronic
noise.  Because the reactor had been operated for over an hour with a
non-functional Logarithmic Channel, the reactor was scrammed.  At that point, the Reactor Operations Manager declared the problem as an event and a report was made to the NRC (see Section (4) below).  When the
licensee investigated the problem, it was believed that the problem was
due to an electronics "noise problem."  After disconnecting, testing, and
reconnecting the channel, they thought the problem (the noise issue) with the Logarithmic Channel was corrected.  The following day, October 19, the Logarithmic Channel was tested and determined to be functional. 
Core excess measurements were completed and the reactor was
operated for requalification of operators.  An inadvertent scram occurred
but this was caused by operator error and operations were allowed to
continue. 
Because most of the student operators were out of qualification 
(due to the continuing problems with the nuclear instruments NI
channels), reactor operations continued and were conducted on various
occasions for requalification but problems persisted.  Core excess measurements were completed each day and other activities were
attempted such as measuring Regulating Rod worth.  The licensee also
completed Shim and Safety rod worth measurements but problems kept
occurring with the Logarithmic Channel.  On October 21, the licensee
determined that the Logarithmic Channel detector was apparently working
properly but the electronics were not.  At that point the reactor was declared non-operational.  The reactor has not been operated since that
date. 
The NRC reviewed the issues associated with the reactor power
measuring channels.  From October 6-16, licensee staff operated the reactor up to 150 kW for training and requalification.  (It was noted that
after October 16, the reactor was only operated at a power level of
5 watts (W) or less.)  During that period when operating at 150 kW, the
Linear Channel typically read 60 percent, the Percent Power Channel
typically read 60 percent, but the Logarithmic Channel was reading from
90 to 100 percent.  The inspector reviewed the console logs for the past two years.  For that time frame, when operating at 150 kW, the Linear Channel typically read 60 percent, the Percent Power Channel typically
read 60 percent, and the Logarithmic Channel typically read 60 percent.   
- 7 -    Therefore, from October 6 through 16, the Logarithmic Channel was not reading correctly because it was reading high and over responding,
probably indicating that the channel detector was shorted out.  The NRC
concluded that the Logarithmic Channel was not operating properly and
thus was not operational during this period.  The licensee was informed
that failure to have an operable Logarithmic Channel during reactor operation was an apparent violation of TS Section 3.2.2 (violation (VIO)
50-288/2016-202-02).
 
(3) NRC-Identified Violation of Regulatory Requirements
The RRR safety analysis report (SAR) states in Chapter 7, Section 7.2.3.3, that the Percent Power Channel has an Uncompensated Ion
Chamber that provides indication for that channel. 
 
Regulation in 10 CFR 50.59 requires that licensees evaluate a change from what was described in the SAR to ensure that a TS change or a license amendment was not required in accordance with 10 CFR 50.59
pargraphs (c)(1)(i and ii) and (c)(2)(i-viii).
 
As noted above, the licensee had been experiencing various problems
with the reactor power measuring channels.  Because of these problems, the licensee tried repeatedly to make adjustments to the channel electronics and the positions of the associated detectors.  On
October 6, 2016, licensee staff attempted to adjust the detectors and
conduct a core excess and power calibration of the reactor.  Although the
power channels appeared to be working properly, the Percent Power Channel had repeated HV scrams.  Licensee staff found a loose wire and corrected that problem but other problems persisted.  Finally on
October 14, the OSU electronics specialist returned to Reed and installed
a spare UIC (one that OSU had received from another university) into the
Percent Power Channel.  Licensee staff conducted a core excess
measurement and performed testing of the electronics using the reactor
at various power levels. 
The NRC reviewed this situation and the problems with the Percent
Power Channel.  As stated above, it was noted that the licensee was not
aware that the detector associated with the Percent Power Channel was a fission chamber (and not a UIC as stated in the SAR) prior to October 5, 2016.  However, following that date, the licensee was fully
aware of the situation.  Nevertheless, the decision was made to replace
the existing fission chamber with a spare fission chamber that the
licensee had on hand. 
 
 
- 8 -  A fission chamber was not what the SAR stipulated as the detector to be operated with the Percent Power Channel.  No attempt was made to conduct a 10 CFR 50.59 review as to whether or not such a detector
should be used with the Percent Power Channel.  The licensee was
informed that failure to conduct a review in this situation was an apparent
violation of 10 CFR 50.59 requirements (VIO 50-288/2016-202-03).
(4) Self-Reported Violation of the Requirements of TS Section 3.2.2
Section 3.2.2 of the RRR technical specifications requires that the reactor
shall not be operated unless the reactor power measuring channels in
Table 2 are operable.  Table 2 lists the Percent Power Channel, the Linear Channel, and the Log Channel.
On October 18, 2016, a licensed reactor operator and another person
operating under the operator's direction completed the Start Up Checklist
had checked out properly and appeared to be functioning normally.  They then inserted the key and began a check out of the reactor NIs prior to full power operation.  They conducted the excess reactivity surveillance
test at a power level below 5 W. 
 
About an hour after the key was inserted into the console, the Reactor
Operations Manager entered the Control Room and noted that one of the NIs, the Log channel was not tracking correctly, i.e., the Log channel was reading a constant number and not tracking with the power level.  The
reactor was immediately scrammed and secured.
 
The three individuals then began to investigate the problem and diagnose what had happened.  Analysis showed that the Log channel pre-amp was picking up excessive noise due to its close proximity to other electrical
components.  Also, upon further investigation, a ground wire was found
detached from its proper connection. 
 
The loose ground wire was replaced and a test of the pre-amp was initiated.  Testing of the pre-amp on a platform away from interference from other electronics indicated that it was then functioning properly. 
Under these corrected conditions, the Log channel was tested and the
reading appeared to return to normal.  However, reactor operations were
suspended until the channel could be more thoroughly tested.  A CAR was initiated to document the issue.  The NRC was notified of the event
on October 19, 2016.
 
The NRC reviewed this issue and discussed the self-identified TS
violation with the licensee and interviewed various reactor staff personnel. 
The NRC confirmed that the licensee had, in fact, been in violation of TS Section 3.2.2.  The circumstances of the event and the notifications were reviewed.   
- 9 -  The inspector verified that the licensee had taken what they thought were appropriate corrective actions once the issue was identified.  Corrective actions included immediately shutting down the reactor, investigating the
problem and making the repairs that they thought would repair the
channel.  Following repairs and discussion of the issue with the Reactor
Director, the reactor was placed back in operation.
 
The licensee was informed that the failure to have all of required channels operable during reactor operation was a Severity Level IV violation of
TS Section 3.2.2.  However, the safety consequences were low because
the reactor was operated at a power level less than 5 W and 2 of the 3
required channels were operable to provide any required reactor scram.  The inspector determined that this particular problem had been identified by the licensee and promptly reported to the NRC.  What the licensee
thought were adequate corrective actions had been identified and
implemented.  As a result, the licensee was informed that this issue would
be treated as a NCV, consistent with Section VI.A.8 of the NRC
Enforcement Policy (NCV 50-288/2016-202-04). 
This issue is considered closed.
 
(5) Reactor Pool Overfill Problem
 
As noted above, near the end of May, the licensee found that the reactor pool had overflowed.  Upon investigation the licensee found that the
problem had occurred due to a malfunction of the recently installed
 
automatic fill system.  In the past, as part of a weekly checklist, staff members were tasked with checking the pool level and adding water if the pool level dropped below a certain mark.  However, on occasion, the staff members forgot to shut the fill water off and the tank was nearly over
filled.  To correct that problem, under the auspices of the 10 CFR 50.59
program, the licensee installed an automatic fill control system. 
 
Unfortunately, the automatic system failed on May 28, 2016, and the pool
overfilled to the point that water entered the nuclear instrumentation tubes leading to the detectors.  The Percent Power channel and the Log Channel were affected; the Linear Channel was not damaged.
 
The overfill caused problems that persisted with the two affected
channels from June through October (as noted above).  The licensee was informed that the issue of correcting the overfill problem would be designated by the NRC as an IFI and would be reviewed during future
inspections (IFI 50-288/2016-202-05).
 
 
- 10 -  c. Conclusion
Reactor staffing, operations, and logs were generally acceptable.  One apparent
violation was identified for operating the reactor without the logarithmic channel
being operable as required by TS Section 3.2.2.  One apparent violation was
identified for failure to conduct a 10 CFR 50.59 review.  One non-cited violation
was identified for operating the reactor without the logarithmic channel being operable as required by TS Section 3.2.2.
4. Operator Requalification Program 
a. Inspection Scope (IP 69001)
The inspector reviewed selected portions of the following regarding the RRR
Requalification Plan to ensure that the requirements of the plan and
10 CFR 55.59, "Requalification," were being met:
  Main (Reactor Console) Log Nos. 86 - 89  Active license status of all current operators  Medical examination records for selected operators  RRR Facility Requalification Program, dated July 2009  RRR Facility Alternate Requalification Plan, dated September 2016  Training lectures and records for the current training cycle  NRC Form 398, "Personal Qualification Statement - Licensee"  Written examinations given during 2014 and 2015 for selected operators  RRR Facility Requalification Plan, dated July 2009  NRC Form 396, "Certification of Medica
l Examination - by Facility Licensee"  RRR Facility Requalification Meeting Agenda and Attendance Sheets for September 2014 through the present  "Requalification Hours and Reactivi
ty Manipulation" Sheets documenting reactivity manipulations for 2014 through the present for selected operators  RRR Administrative Procedures, Section 9, "Record Retention"  Various RRR SOPS including:  SOP 63, "Requalification;" SOP 63 Appendix A, "Reactor Operator Physical Exam;" and SOP 63,  Appendix B, "Accelerated Requalification Form" 
b. Observations and Findings
(1) Routine Requalification Program - For the Period 2014 through June 2015 and for July 2015 through June 2016
As noted previously, there are currently 20 qualified SROs and 
19 qualified ROs at the RRR facility.  The inspector reviewed selected
operators' licenses and noted that they were current.
 
 
- 11 -  The inspector reviewed the requalification program for July 2014 through June 2015, and for July 2015 through June 2016, as well as the annual drill scenarios and attendance sheets.  It was noted that operators
typically made entries on the "Requalification Hours and Reactivity
Manipulation Sheet" that was located in the control room.  Through these
actions the hours "on duty" and in what capacity (i.e., RO/SRO), as well
 
as the tasks performed, were documented.  The inspector also reviewed the Requalification Meeting Agenda and Attendance Sheets for the period from September 2014 through the present.  The inspector reviewed
various individual operators' requalification records as well.
 
The review of the various logs and records noted above showed that training had been conducted in accordance with the licensee's requalification and training program until May 2016.  Training reviews and
examinations had been completed and documented as required.  The
records indicated that operators were completing the required activities,
including reactivity manipulations and number of operating hours.  Records indicated that annual operations tests and supervisory observations were being completed.  Biennial written examinations were
also being completed as required or credit was taken by the licensee for
the exams administered by the NRC to satisfy the requalification cycle
exam requirements when applicable.
Additionally, the inspector noted that operators were receiving the required biennial medical examinations within the required time frame. (2) Alternate Requalification Plan - For the period from July 2016 until the
Reactor is Operational
 
As noted in Section 3 of this report, the RRR has been functional and operational only sporadically since May 2016.  Because of this problem, operators have not been able to complete the operational requirements to
remain fully qualified.  The licensee recognized this and proposed an
alternate requalification plan to the NRC in September.  The alternate
plan was reviewed and subsequently approved. 
 
The Alternate Requalification Plan stipulated that two Reed College SROs would go to the OSU research reactor facility and complete two
hours of reactor operation under direction of OSU personnel and two
hours of supervision of the other Reed College operator.  These two
individuals would also complete one reactivity manipulation each while at OSU as well.  This would suffice for the reactor operation requirements of the Reed Requalification Program and allow the two operators to return to
Reed College and observe Reed operators to operate under their
direction. 
 
For the remainder of the operators at Reed who did not go to OSU and were out of qualification, the alternate plan required that each operator complete three hours of reactor operation and two reactivity
manipulations under direction of one of the SROs who went to OSU.
- 12 -  In addition, these operators would then need to meet the routine Reed Requalification Program requirements of four hours of reactor operation and two reactivity manipulations for the quarter.  If any licensed
individuals were not in compliance with other requirements outlined in 
10 CFR 55.59, the operators would be required to meet the requirements
of 10 CFR 55.53, "Conditions of licenses," paragraph (f)(2) of six
additional hours of operation under direction.
The inspector reviewed the actions of the licensee to comply with the
requirements of the Alternative Requalification Plan.  The inspector
verified that the two SROs who went to OSU had completed the required
hours of operation and the required reactivity manipulations.  They then returned to Reed and began observing other operators.  It was noted that 4 SROs and 2 ROs had completed the requirements of the alternate
requalification plan.  However, it was also noted that only two SROs
would be in compliance with the Routine Requalification Program if the
Reed reactor remains shut down through the end of December (the end of the quarter).  The licensee acknowledged that, if the reactor remains shut down through the end of the quarter, all operators who are not in
compliance with the requalification program requirements will have to complete the Alternate Requalification Plan requirements as well as the
regular Reed Requalification Program requirements before being
considered qualified to operate the reactor.
(3) Access to the Reed Research Reactor Facility (RRRF) Controlled Access
Area
As noted above, the inspector reviewed the Reed Routine Requalification Program.  During records review it was found the Reed Operations Manager was approving individuals' access to the facility Controlled
Access Area (CAA), i.e., signing the access forms.  Only the NRC
approved reviewing official may grant unescorted access to the facility in
accordance with 10 CFR 73.57, "Requirements for criminal history
records checks of individuals granted unescorted access to a nuclear power facility, a non-power reactor, or access to Safeguards Information," paragraph (g).  The NRC approved reviewing official is the RRRF
Director as indicated in a letter from the NRC to the licensee.  The
licensee was informed that only the NRC approved reviewing official is
authorized to approve individuals access.  Any changes or request for changes must be submitted to the NRC for evaluation. 
Because the decision to grant unescorted access to the CAA of the
facility was always discussed between, and approved by, both the
 
Director and the Reactor Operations Manager, the Director subsequently
countersigned all the access forms.  The licensee agreed that only an approved Reviewing Official would sign the access forms in the future.
 
- 13 -  c. Conclusion
The requalification/training program was up-to-date and being acceptably
maintained.  Medical examinations were being completed biennially as required.
5. Fuel Handling 
a. Inspection Scope (IP 69001)
In order to verify adherence to fuel handling and inspection requirements
specified in TS Section 4.1, the inspector reviewed selected aspects of the
 
following:
  Fuel Element Inspection Cards  Main (Reactor Console) Log Nos. 86 - 89  Fuel Element Inspection sheet maintained in the appropriate Fuel Inspection
Binder  RRR Administrative Procedures Section 6, "Fuel and Special Nuclear
Material"  Various RRR SOPs including:  RRR SOP 35, "Fuel and Core;" SOP 35, Appendix A, "Core Diagram;"  SOP 35, Appendix B, "Fuel Handling
Checklist;" SOP 35, Appendix C, "Fuel Handling SRO Qualification;" and
SOP 35, Appendix D, "Fuel Handling Receipt Form"
b. Observations and Findings
Through review of the main logs and interviews with licensee personnel, the
inspector verified that fuel movements were conducted in compliance with procedure.  The inspector also verified that the licensee was maintaining the required records of fuel movements as they were completed.  The logs were
being filled out properly to indicate which elements were moved and to what
 
locations.
Also through records review, it was noted that the reactor fuel was being inspected upon initial receipt and 25 percent of the fuel elements in the core were being inspected annually.  This exceeded the percentage of fuel elements
required to be inspected as stipulated by TS Section 4.1.  The last annual fuel
inspection was completed during January 11-27, 2016.  The inspector verified
that all fuel elements were inspected at least once every 5 years, including elements in storage and/or removed from service as required.
c. Conclusion
Reactor fuel movements and inspections were completed and documented in
accordance with procedure and the fuel was being inspected more frequently than required by TS Section 4.1.
 
- 14 -  6. Maintenance and Surveillance
a. Inspection Scope (IP 69001)
To verify that operations, surveillance activities, and calibrations were being
completed as required by the TS, the inspector reviewed selected portions of:
  Main (Reactor Console) Log Nos. 86 - 89  Maintenance Log pages completed for unscheduled work  Associated surveillance and calibration data and records for 2015-2016  "Other Checklists" Notebook which contained calibration forms, inspection forms, and various checklists  Various RRR SOPs and Appendices including: SOP 23, "Biweekly Checklist;" SOP 23, Appendix A, "Biweekly Checklist Form;" SOP 24, "Bimonthly
Checklist;" SOP 24, Appendix A, "Bimonthly Checklist Form;" SOP 25,
"Semiannual Checklist;" SOP 25, Appendix A, "Reed Research Reactor
Semiannual Checklist;" SOP 26, "Annual Checklist;" SOP 26, Appendix A, "Annual Checklist Form;" SOP 34, "Control Rods;" SOP 34, Appendix A, "Control Rod Calibration Form;" SOP 34, Appendix B, "Control Rod
Inspection Checklist;" SOP 34, Appendix C, "Control Rod Inspection Form;"
and, SOP 60, "Logbook Entries;" and associated Appendix A, "Maintenance
 
Log" forms  RRR Annual Reports for the last two reporting periods b. Observations and Findings
The licensee conducted various maintenance and surveillance activities which
were then documented on the appropriate forms and checklists.  The inspector
verified that these activities were conducted within the time frame required and according to procedure.  The inspector reviewed selected biweekly, bimonthly, semiannual, and annual forms and checklists.  All the recorded results reviewed
were within the TS and procedurally prescribed parameters.  The records and
logs reviewed appeared to be complete and were being maintained as required.
The inspector was not able to observe a Startup or Shutdown Checklist being performed during the inspection.  However, previously completed Startup and Shutdown Checklists were reviewed.  These activities appeared to have been
conducted appropriately and in accordance with procedure.
A review of the RRRF Main Logs and current Maintenance Logbook showed that these records were also being completed as required and problems, if any, were being documented.  Through observation and records review, the inspector also
confirmed that maintenance was being conducted as needed, consistent with the
 
TS.   
- 15 -  c. Conclusion
Maintenance was being completed as required.  The program for surveillance
was being carried out in accordance with TS requirements.
7. Procedures
a. Inspection Scope (IP 69001)
To determine whether facility procedures met the requirements outlined in
TS Section 6.4, the inspector reviewed portions of the following:
  Procedural reviews and updates documented in the ROC meeting minutes  RRR Administrative Procedures, Section 8, "Adoption and Revision of Operating Procedures," and Section 9, "Record Retention"  Various RRR SOPs and Appendices including:  SOP 60, "Logbook Entries;"SOP 61, "Procedure Writing and Use;" SOP 61, Appendix A, "Document Structure;" SOP 61, Appendix B, "Document Locations;" and SOP 61, Appendix C, "Temporary Procedure Change"
b. Observations and Findings
Procedures were in effect for those activities specified in TS Section 6.4 as required.  RRR Administrative Procedures and SOPs were found to be acceptable for the current staffing level and status of the facility.  The
Administrative Procedures and SOPs specified the responsibilities of the various
members of the staff.  Substantive changes to procedures were being reviewed
and approved by the ROC.  The procedures were being audited, reviewed, and updated as needed.
The inspector reviewed the temporary procedure changes that had been
promulgated during the past 12 months.  The changes were written after minor
problems with the procedures were noted.  The temporary changes were
typically incorporated in the referenced procedures if deemed appropriate by the licensee.  Changes suggested as a result of the ROC and independent audits were also incorporated into the procedures if deemed appropriate.
 
c. Conclusion
Facility procedures for the safe operation of the reactor were available as
required by TS Section 6.4.
 
- 16 -  8. Experiments
a. Inspection Scope (IP 69001)
In order to verify that experiments were being conducted within approved
guidelines specified in TS Sections 3.6, 4.6, and 6.5, the inspector reviewed
selected portions of the following:
  Experiment review and approval by the ROC  Selected Irradiation Request Forms for 2015 and 2016  Approved RRR Routine Experiments (REs), including:  RE 1, "Irradiation with
Neutrons;" RE 2, "Irradiation with Gammas;" RE 3, "Fuel, Graphite, or Source Material;" RE 4, "Reactor Power Measurement;" RE 5, "Control Rod Worth Measurement"; RE 6, "Pool Parameter Measurement;"  RE 7, "Fuel Loading;"
RE 8, "Cerenkov Radiation Spectrum Acquisition;" RE 9, "Neutron Induced
Auto-Radiography;" and RE 10, "Radial Flux Measurements"  Approved RRR Special Experiment (SE), SE 4, "Core Temperature Measurements"  RRR Administrative Procedures, Section 4, "Reactor Experiments;" and Section 9, "Record Retention"  Various RRR SOPs and Appendices including:  SOP 10, "Irradiation Preparation;" SOP 10, Appendix A, "Irradiation Request Form;" SOP 10,
Appendix D, "Irradiation Request Log;" SOP 11, "Irradiation Analysis;" SOP 12, "Lazy Susan;" SOP 13, "Rabbit;" SOP 14, "Central Thimble;" SOP 15, "Beam;" SOP 15, Appendix A, "Beam Irradiation Request
Form;"SOP 16, "Near Core;" and SOP 17, "Gamma Irradiations"
b. Observations and Findings
The inspector noted that the various experiments conducted at the facility, and
revisions thereto, were being reviewed and approved as required.  It was also
noted that the two most recently proposed REs had been submitted by licensee
staff and students and had been reviewed and approved by the Facility Director
 
and the ROC as required.
Through a review of console logs and various irradiation request forms, the
inspector noted that irradiations were conducted under the cognizance of the
Facility Director and the Reactor Supervisor as required.  The irradiations were
documented in the Main Log and the results of the experiments were documented on the Irradiation Request Forms as required.  The resulting radioactive material was being transferred to an authorized user, disposed of as
stipulated by procedure, or held for decay.
 
 
- 17 -  c. Conclusion
The license's program for the control of experiments generally satisfied TS Sections 3.6, 4.6, and 6.5 and other regulatory requirements.
9. Emergency Preparedness
a. Inspection Scope (IP 69001)
To verify compliance with the RRRF, E-Plan, the inspector reviewed selected
aspects of the following:
  ERR E-Plan last revised August 2014  Emergency response training records for the past 2 years  Emergency drills and exercises held during 2015 and 2016  Emergency response facilities, supplies, equipment and instrumentation  ERR SOP 25, "Semiannual Checklist"  ERR SOP 25, Appendix A, "Reed Research Reactor Semiannual Checklist"  ERR E-Plan, Appendix a, "Emergency Implementation Procedures (EIPs)"  ERR E-Plan, Appendix B, "Projected Doses for Bounding Accidents"  ERR E-Plan, Appendix C, "Visible and Audible Alarms"
b. Observations and Findings
The E-Plan in use at the reactor had been updated, reviewed, and approved by
the ROC.  The licensee had determined that there was no decrease in
effectiveness as defined in 10 CFR 50.54, "Conditions of licenses,"
paragraph (q).  The licensee had submitted a letter to the NRC documenting this determination on August 18, 2014.
The E-Plan and EIPs were being audited and reviewed annually as required. 
Supplies, instrumentation, and equipment staged for emergency use were being
maintained, controlled, and inventoried semiannually as required in the E-Plan.  It
was noted that the Emergency Support Center was located in the RRRF Director's office in the Chemistry Building.
Through records review and interviews with licensee personnel, emergency
responders were determined to be knowledgeable of the proper actions to take in
case of an emergency.  The inspector reviewed the Agreement Letters that had been signed with various emergency support organizations.  These agreements were being maintained and updated as needed. 
 
Communications capabilities were acceptable and had been tested and
emergency information updated as stipulated in the E-Plan.  It was noted that the
Emergency Notification Call List, posted in various locations throughout the facility, was current and the most recent version was dated October 5, 2016. The inspector verified that training for staff and offsite support personnel was
being provided annually as required.   
- 18 -  Training for staff was typically completed through the Operator Requalification Program.  Training for representatives from the Portland Fire and Rescue Department (PF&RD) was conducted annually.  Training for representatives from the Portland Police Bureau was offered but the police could not always commit to
attend because of staffing level shortages.
 
Emergency drills had been conducted annually as required by the E-Plan.  Off-site support organization participation was also as required by the E-Plan.  Critiques were held following the drills to discuss the strengths and weaknesses
identified during the exercises and to develop possible solutions to any problems identified.  The results of these critiques were documented and reported to the
Radiation Safety Committee/ROC.  Drills involving off-site personnel were being conducted annually and documented as stipulated by the E-Plan.
The inspector and the Facility Director visited a PF&RD unit located several miles
from the RRRF.  The inspector and Director were given a tour of the facility and
observed the equipment maintained by the unit for response to various types of emergencies.  As a result of this visit, and following a review of the licensee's records documenting drills and training, the inspector verified that fire department
personnel were well trained, properly equipped, and knowledgeable of the
actions to take in case of an emergency at the reactor facility.  The inspector
determined that the licensee communicated with the PF&RD frequently and was
maintaining a good working relationship with this support group.
c. Conclusion
The emergency preparedness program was conducted in accordance with the
 
E-Plan.  10. Follow-up on Previously Identified Items
  a. Inspection Scope (IP 92701)
The inspector reviewed the actions taken by the licensee to address a previously identified IFI.
b. Observation and Findings
50-288/2014-202-01 - IFI - Follow-up on the licensee's actions to correct the inconsistencies between the E-Plan and the Implementing Procedures dealing with the "Alert" classification of various events. During an inspection in December 2014, the inspector reviewed of the E-Plan.  It
was noted that there were no accidents that could cause an "Alert" classification for the facility.  However, certain security events would require an "Alert" 
Nevertheless, it was noted that there were various EIPs which indicated that, in
certain accident situations, the classification for the event would be "Alert." 
- 19 -  The licensee acknowledged these inconsistencies and agreed to correct the problem.  The licensee was informed that correcting these issues would be followed by the NRC as an IFI.
 
During this inspection, the inspector reviewed the actions taken by the licensee
to resolve the inconsistencies between the E-Plan and the EIPs.  It was noted
that the procedures had been revised to indicate that accidents or events occurring in conjunction with security events require the "Alert" designation.  Otherwise these events are classified as "Unusual Events."  This issue is
considered closed.
 
c. Conclusions
One IFI was reviewed and this issue is considered closed.
11. Exit Interview
The initial scope of the inspection were summarized on November 2, 2016, with the Facility Director, the Reactor Manager, and the Dean of Faculty.  On November 3, 2016,
the preliminary results were discussed with the Facility Director and the Reactor
Manager.  On December 1, 2016, the results of the inspection were discussed with the
Facility Director and the Dean of Faculty.  On December 2, 2016, the results of the
inspection were reiterated with the Facility Director.  The inspector discussed the findings for each area reviewed.  The licensee acknowledged the findings and did not identify as proprietary any of the material provided to or reviewed by the inspector during
the inspection.
 
    PARTIAL LIST OF PERSONS CONTACTED
Licensee  C. Barrett  Reactor Operations Manager S. Brodesser  Training Supervisor
T. Freeman  Requalification Supervisor A. Karr  Radiation Safety Officer and Campus Environmental Director J. Koh  Operations Supervisor
M. Krahenbuhl  Director, Reed Reactor Facility
M. McCarthy  Projects Supervisor
N. Nicholson  Dean of the Faculty, Reed College M. Oxley  Training Supervisor
Other Personnel
S. Christensen  First Lieutenant, Portland Fire and Rescue, Training, Safety, and EMS
Division, City of Portland B. Profit  Training Lieutenant, Portland Fire and Rescue, Training, Safety, and EMS
Division, City of Portland
  INSPECTION PROCEDURE USED
IP 69001 Class II Non-Power Reactors
 
ITEMS OPENED, CLOSED, AND DISCUSSED
Opened 
50-288/2016-202-01 IFI Follow-up on the licensee's actions to maintain logs which contain the accurate and complete documentation of scram
events and other operational events.
50-288/2016-202-02 VIO Failure to have all of required channels operable during reactor operation as required by TS Section 3.2.2. 
50-288/2016-202-03 VIO Failure to complete a review prior to installing a fission chamber instead of an uncompensated ion chamber with the
Percent Power Channel (as stipulated in the facility SAR) as
required by 10 CFR 50.59 (c)(1)(i and ii) and (c)(2)(i-viii). 
50-288/2016-202-04 NCV Failure to have all of required channels operable during reactor operation as required by TS Section 3.2.2. 
50-288/2016-202-01 IFI Follow-up on the licensee's actions to correct the reactor pool overfill problem caused by the automatic fill system installed
by the licensee. 
- 2 -  Closed  50-288/2014-202-01 IFI Follow-up on the licensee's actions to correct the inconsistencies between the E-Plan and the Implementing
Procedures dealing with the "Alert" classification of various
 
events.  50-288/2016-202-04 NCV Failure to have all of required channels operable during reactor operation was a Severity Level IV violation of  
 
TS Section 3.2.2.  
LIST OF ACRONYMS USED  
10 CFR Title 10 of the  
Code of Federal Regulations CAA Controlled Access Area  
CAR Corrective Action Report E-Plan Emergency Plan EIP Emergency Implementation Procedures  
HV High Voltage  
IFI Inspector Follow-up Item IP Inspection Procedure kW Kilowatt  
NCV Non-Cited Violation  
No. Number  
NRC Nuclear Regulatory Commission OSU Oregon State University PF&RD Portland Fire and Rescue Department  
RE Routine Experiment  
RO Reactor Operator  
ROC Reactor Operations Committee RRR Reed Research Reactor RRRF Reed Research Reactor Facility  
SAR Safety Analysis Report  
SE Special Experiment SOP Standard Operating Procedure SRO Senior Reactor Operator SSC Structure, System, or Component TS Technical Specifications  
UIC Uncompensated Ion Chamber  
VIO Violation W Watt
}}
}}

Revision as of 10:18, 30 October 2019

Reed College - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 50-288/2016-202 and Notice of Violation
ML16349A652
Person / Time
Site: Reed College
Issue date: 12/21/2016
From: Anthony Mendiola
Research and Test Reactors Oversight Branch
To: Krahenbuhl M
Reed College
Bassett C
References
IR 2016202
Download: ML16349A652 (31)


See also: IR 05000288/2016202

Text

December 21, 2016

Dr. Melinda Krahenbuhl, Director

Reed Reactor Facility

Reed College

3203 S.E. Woodstock Boulevard

Portland, OR 97202-8199

SUBJECT: REED COLLEGE - U.S. NUCLEAR REGULATORY COMMISSION ROUTINE

INSPECTION REPORT NO. 50-288/2016-202 AND NOTICE OF VIOLATION

Dear Dr. Krahenbuhl:

From October 31 to November 3, and November 28 to December 2, 2016, the U.S. Nuclear

Regulatory Commission (NRC or the Commission) completed an inspection at the TRIGA

Mark-I Reed Research Reactor facility. The enclosed report documents the inspection results,

which were discussed on November 2, 2016, with you, Dr. Nigel Nicholson, Dean of the Faculty,

and Christina Barrett, Reactor Operations Manager, and on December 1, 2016, with you and

Dr. Nicholson.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities in progress, and

interviewed various personnel.

Based on the results of this inspection, the NRC has determined that two Severity Level IV

violations of NRC requirements occurred. The violations were evaluated in accordance with the

NRC Enforcement Policy, which can be found on the NRCs Web site at www.nrc.gov by

selecting What We Do, Enforcement, and then Enforcement Policy. The violations are

cited in the enclosed Notice of Violation (Notice) and the circumstances surrounding them are

described in detail in the subject inspection report. The violations are being cited in the Notice

because they constitute the failure to meet regulatory requirements that have more than minor

safety significance and they were identified by the NRC.

You are required to respond to this letter and should follow the instructions specified in the

enclosed Notice when preparing your response. The NRC will use your response, in part, to

determine whether further enforcement action is necessary to ensure compliance with

regulatory requirements.

In addition, based on the results of this inspection, the NRC has determined that one other

Severity Level IV violation of NRC requirements occurred. This violation is being treated as a

non-cited violation (NCV), consistent with Section 2.3.2.b of the Enforcement Policy. The NCV

is described in the subject inspection report. If you contest the violation or significance of the

NCV, you should provide a response within 30 days of the date of this inspection report, with the

basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington DC 20555-0001, with copies to the Director, Office of Enforcement, United States

Nuclear Regulatory Commission, Washington, DC 20555-0001.

M. Krahenbuhl -2-

In accordance with Title 10 of the Code of Federal Regulations Section 2.390, Public

inspections, exemptions, requests for withholding, a copy of this letter, its enclosure, and your

response (if any) will be available electronically for public inspection in the NRC Public

Document Room or from the NRCs document system (Agencywide Documents Access and

Management System (ADAMS)). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this inspection, please contact Craig Bassett at

301-466-4495 or by electronic mail at Craig.Bassett@nrc.gov.

Sincerely,

/RA/

Anthony J. Mendiola, Chief

Research and Test Reactors Oversight Branch

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Docket No. 50-288

License No. R-112

Enclosures:

1. Notice of Violation

2. NRC Inspection Report

No. 50-288/2016-202

cc: See next page

Reed College Docket No. 50-288

cc:

Mayor of City of Portland

1220 Southwest 5th Avenue

Portland, OR 97204

Dr. Nigel Nicholson, Dean of Faculty

Reed College

3203 S.E. Woodstock Boulevard

Portland, OR 97202-8199

Mr. John Kroger, President

Reed College

3203 S.E. Woodstock Boulevard

Portland, OR 97202-8199

Division Administrator

Nuclear Safety Division

Oregon Department of Energy

625 Marion Street, N.E.

Salem, OR 97310-3737

Program Director

Radiation Protection Services

Public Health Division

Oregon Health Authority

800 NE Oregon Street, Suite 640

Portland, OR 97232-2162

Test, Research, and Training

Reactor Newsletter

University of Florida

202 Nuclear Sciences Center

Gainesville, FL 32611

ML16349A652; *concurrence via e-mail NRC-002

OFFICE NRR/DPR/PROB* NRR/DPR/PROB* NRR/DPR/PROB

NAME CBassett NParker AMendiola

DATE 12/16/16 12/16/16 12/21/16

NOTICE OF VIOLATION

Reed College Docket No. 50-288

Reed Research Reactor License No. R-112

During a U.S. Nuclear Regulatory Commission (NRC) inspection conducted from October 31 to

November 3, 2016 and from November 28 to December 2, 2016, two violations of NRC

requirements were identified. In accordance with the NRC Enforcement Policy, the violations

are listed below:

1. Reed Research Reactor Technical Specification (TS) Section 3.2.2 requires that the

reactor shall not be operated unless the reactor power measuring channels in Table 2

are operable. Table 2 lists the Percent Power Channel, the Linear Channel, and the

Logarithmic Channel.

Contrary to this requirement, from October 6 to October 16, 2016, the reactor was

operated or attempted to be operated when the Logarithmic Channel was not operable.

This has been determined to be a Severity Level IV violation (Section 6.1).

2. Title 10 of the Code of Federal Regulations (10 CFR) 50.59, Changes, tests, and

experiments, paragraph (c)(1) states, in part, that a licensee may make changes in the

facility as described in the final safety analysis report without obtaining a license

amendment pursuant to 10 CFR 50.90 only if: (i) a change to the technical

specifications incorporated in the license is not required, and (ii) the change does not

meet any of the criteria in 10 CFR 50.59(c)(2).

The regulation in 10 CFR 50.59(c)(2) requires, in part, that a licensee shall obtain a

license amendment pursuant to 10 CFR 50.90 prior to implementing a proposed change

if the change would: (i) result in more than a minimal increase in the frequency of

occurrence of an accident previously evaluated in the final safety analysis report;

(ii) result in more than a minimal increase in the likelihood of occurrence of a malfunction

of a structure, system, or component (SSC) important to safety previously evaluated in

the final safety analysis report; (iii) result in more than a minimal increase in the

consequences of an accident previously evaluated in the final safety analysis report;

(iv) result in more than a minimal increase in the consequences of a malfunction of an

SSC important to safety previously evaluated in the final safety analysis report; (v)

create a possibility for an accident of a different type than any previously evaluated in

the final safety analysis report; (vi) create a possibility for a malfunction of an SSC

important to safety with a different result than any previously evaluated in the final safety

analysis report; (vii) result in a design basis limit for a fission product barrier as

described in the FSAR being exceeded or altered; or (viii) result in a departure from a

method of evaluation described in the FSAR used in establishing the design bases or in

the safety analyses.

The regulation in 10 CFR 50.59(d)(1) requires, in part, that the licensee shall maintain

records of changes in the facility made pursuant to 10 CFR 50.59(c). These records

Enclosure 1

-2-

must include a written evaluation which provides the bases for the determination that the

change does not require a license amendment pursuant to 10 CFR 50.59(c)(2).

The Reed Research Reactor safety analysis report (SAR) states in Chapter 7,

Section 7.2.3.3, that the Percent Power channel has an associated Uncompensated Ion

Chamber that provides indication for that channel.

Contrary to the above requirements, on October 5, 2016, the licensee made a change to

the facility as described in the SAR without conducting an evaluation to determine

whether or not the change would require a change to the TSs or should have required a

license amendment. Specifically, the licensee replaced the detection chamber

associated with the Percent Power channel with a fission chamber which was not as

described in the SAR without performing an evaluation of the change using the criteria in

10 CFR 50.59(c)(1) and (2) to determine if the change would require a change to the

TSs or should have required a license amendment.

This has been determined to be a Severity Level IV violation (Section 6.1).

Pursuant to the provisions of 10 CFR 2.201, Notice of violation, Reed College is hereby

required to submit a written statement or explanation to the U.S. Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington, D.C. 20555-0001, with a copy to the

responsible inspector, within 30 days of the date of the letter transmitting this Notice of Violation

(Notice). This reply should be clearly marked as a Reply to a Notice of Violation and should

include for each violation: (1) the reason for each violation, or, if contested, the basis for

disputing the violation or severity level; (2) the corrective steps that have been taken and the

results achieved; (3) the corrective steps that will be taken to avoid further violations; and (4) the

date when full compliance will be achieved. Your response may reference or include previously

docketed correspondence, if the correspondence adequately addresses the required response.

If an adequate reply is not received within the time specified in this Notice, an order or Demand

for Information may be issued as to why the license should not be modified, suspended, or

revoked, or why such other action as may be proper should not be taken. Where good cause is

shown, consideration will be given to extending the response time. If you contest this

enforcement action, you should also provide a copy of your response, with the basis for your

denial, to the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission,

Washington, D.C. 20555-0001.

Because your response will be made available electronically for public inspection in the NRC

Public Document Room or from the Publicly Available Records component of the NRCs

Agencywide Documents Access and Management System (ADAMS), to the extent possible, it

should not include any personal privacy, proprietary, or safeguards information so that it can be

made available to the public without redaction. ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). If personal

privacy or proprietary information is necessary to provide an acceptable response, then please

provide a bracketed copy of your response that identifies the information that should be

protected and a redacted copy of your response that deletes such information. If you request

withholding of such material, you must specifically identify the portions of your response that

you seek to have withheld and provide in detail the bases for your claim of withholding (e.g.,

explain why the disclosure of information will create an unwarranted invasion of personal

privacy or provide the information required by 10 CFR 2.390, Public inspections, exemptions,

-3-

requests for withholding, paragraph (b) to support a request for withholding confidential

commercial or financial information). If safeguards information is necessary to provide an

acceptable response, please provide the level of protection described in 10 CFR 73.21,

Protection of Safeguards Information: Performance Requirements.

In accordance with 10 CFR 19.11, Posting of notices to workers, you may be required to post

this Notice within two working days.

Dated this 21st day of December

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

Docket No. 50-288

License No. R-112

Report No. 50-288/2016-202

Licensee: Reed College

Facility: Reed Research Reactor

Location: Portland, Oregon

Dates: October 31, 2016 - November 3, 2016

November 28, 2016 - December 2, 2016

Inspector: Craig Bassett

Accompanied by: Michele DeSouza, Examiner

John Nguyen, Examiner

Michael Takacs, Security Specialist

Approved by: Anthony J. Mendiola, Chief

Research and Test Reactors Oversight Branch

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Enclosure 2

EXECUTIVE SUMMARY

Reed College

Reed Research Reactor Facility

NRC Report No. 50-288/2016-202

The primary focus of this routine, announced inspection included onsite review of selected

aspects of the Reed College (the licensee) Class II research reactor safety program. This

included a review of: (1) organization and staffing, (2) review and audit and design change

functions, (3) conduct of operations, (4) operator requalification program, (5) fuel handling,

(6) maintenance and surveillance, (7) procedures, (8) experiments, and (9) emergency

preparedness. The licensees program was acceptably directed toward the protection of public

health and safety. Two apparent Severity Level IV violations and one Severity Level IV

non-cited violation were identified.

Organization and Staffing

The organization and staffing remain in compliance with the requirements specified in

Technical Specification (TS) Section 6.1.

Review and Audit and Design Change Functions

Review and oversight functions required by TS Section 6.2 were acceptably completed by

the Reactor Operations Committee. Audits were being completed as required.

The design change program being implemented at the facility generally satisfied Nuclear

Regulatory Commission requirements.

Conduct of Operations

Operations were generally being conducted in accordance with TS and procedural

requirements.

Two apparent violations and one non-cited violation were identified involving the nuclear

measuring channels of the reactor.

Operator Requalification Program

The operator requalification/training program was up-to-date and being acceptably

implemented and documented.

Biennial medical examinations were being completed as required.

A one-time Alternate Requalification Plan was initiated due to the problems created by

malfunctioning nuclear instrumentation.

-2-

Fuel Handling

Reactor fuel movements and inspections were conducted and documented in accordance

with procedure.

Twenty-five percent of the fuel elements were being inspected on an annual basis.

Maintenance and Surveillance

Maintenance was being completed as needed.

The surveillance program, including calibration of equipment, was being completed in

accordance with TS Sections 3 and 4.

Procedures

Facility procedures were available for the safe operation of the reactor as required by

TS Section 6.4.

Experiments

The program for the control of experiments satisfied TS Sections 3.6, 4.6, and 6.5 and other

regulatory requirements.

Emergency Preparedness

The Emergency Plan (E-Plan) and Emergency Implementation Procedures were being

audited and reviewed annually as required.

Letters of Agreement documenting emergency support to be provided by offsite agencies

were being maintained and periodically updated.

Annual drills were being held and documentation of the drills and the follow-up critiques was

maintained. Subsequent corrective actions were taken as needed.

Emergency preparedness training for staff and offsite personnel was being conducted as

stipulated in the E-Plan.

REPORT DETAILS

Summary of Facility Status

The Reed College (the licensees) 250 kilowatt TRIGA Mark I research reactor was typically

operated in support of undergraduate instruction, laboratory experiments, reactor system

testing, reactor surveillances, and operator training. During this inspection the reactor was not

operated due to nuclear instrumentation issues.

1. Organization and Staffing

a. Inspection Scope (Inspection Procedure (IP) 69001)

To verify the organization and staffing requirements specified in technical

specifications (TSs) Section 6.1 were being met, the inspector reviewed selected

aspects of the following:

Main (Reactor Console) Log - Numbers (Nos.) 86 - 89

Reed Research Reactor (RRR) facility organization and staffing during

reactor operations

Administrative controls and management responsibilities specified in the TS

and facility procedures

RRR Administrative Procedures, Section 1, Personnel, and Section 3,

Reactor Operations

RRR Standard Operating Procedure (SOP) 60, Logbook Entries

RRR Annual Report for the period from July 1, 2014, through

June 30, 2015, submitted to the U.S. Nuclear Regulatory Commission (NRC)

on August 7, 2015

RRR Annual Report for the period from July 1, 2015, through

June 30, 2016, submitted to the NRC on July 27, 2016

b. Observations and Findings

Through discussions with licensee representatives, the inspector determined that

management responsibilities and the organizational structure at the RRR facility

had not changed since the previous NRC inspection of licensee operations in

December 2014 (Inspection Report No. 50-288/2014-202). The inspector

determined that the Facility Director retained direct control and overall

responsibility for management of the facility as specified in the TS. The Facility

Director reported to the President of Reed College through the Dean of Faculty.

This organization was consistent with that specified in the TS.

It was noted that since the last operations inspection in 2014, a new person had

been hired to be the Reactor Operations Manager. Also, a new person had been

hired to fill the position of campus Radiation Safety Officer/Director of

Environmental Health and Safety.

-2-

The licensees current operational organization consisted of the Facility Director,

a Reactor Operations Manager, a Radiation Safety Officer, an Operations

Supervisor, a Training Supervisor, an Assistant Training Supervisor, a Projects

Supervisor, and a Requalification Supervisor. The Facility Director, Reactor

Operations Manager, and Radiation Safety Officer positions were full-time while

the rest were part-time positions filled by students. Except for the Radiation

Safety Officer, the aforementioned individuals, in addition to their administrative

duties, were qualified reactor operators (ROs) or senior reactor operators

(SROs). It was noted that there were a total of 20 SROs and 19 ROs licensed to

operate the RRR.

c. Conclusion

Organization and staffing met the requirements specified in TS Section 6.1.

2. Review, Audit, and Design Change Functions

a. Inspection Scope (IP 69001)

In order to verify that the licensee had established and conducted reviews and

audits as required, and to determine whether facility modifications and change

reviews were consistent with Title 10 of the Code of Federal Regulations

(10 CFR) Section 50.59, Changes, tests and experiments, and TS Section 6.2,

the inspector reviewed selected portions of the following:

Maintenance Log pages completed for unscheduled work

Corrective Action Reports (CARs) for 2015 and to date in 2016

Design changes reviewed under 10 CFR 50.59 for 2015 and 2016

Reactor Operations Committee (ROC) meeting minutes from

October 2014 through the present

RRR Administrative Procedures, Section 1, Personnel; Section 2, Reactor

Review Committee; and Section 9, Record Retention

RRR SOP 62, Changes, Tests, and Experiments, and SOP 69, Corrective

Action Report; and associated forms, Corrective Action Reports; last

revised August 26, 2014

RRR Annual Reports for the last two reporting periods

b. Observations and Findings

(1) Review and Audit Functions

The inspector reviewed ROC meeting minutes from October 2014

through the present. These meeting minutes showed that the committee

was meeting at the required frequency and was considering the types of

topics outlined by the TS.

The inspector noted that, since the last NRC inspection, the appropriate

audits had been completed by the ROC and an external auditor in the

-3-

various areas outlined in the TS. The audits were designed so that most

aspects of the licensees operations and safety programs were reviewed

every year. Various facility documents, such as the Radiation Protection

Program, the Emergency Plan (E-Plan), the Fire Plan, the Administrative

Procedures, and the Requalification Plan comprised the material that was

typically reviewed. The Reactor Experiments and various SOPs were

also reviewed. The inspector noted that the audits and the resulting

findings were detailed and that the licensee responded and took

corrective actions as needed.

(2) Design Changes

The inspector reviewed the licensees 10 CFR 50.59 screening forms

concerning changes or modifications that had been initiated at the facility

for 2015 and to date in 2016. The results indicated that none of the

screenings required further evaluation under 10 CFR 50.59. The

inspector also reviewed the Maintenance Log pages that had been

completed for unscheduled work associated with various systems. The

forms contained a section which required a 50.59 Screen to be completed

prior to initiating the work. None of the maintenance items reviewed

required any further actions, such as a 50.59 evaluation, to be completed

except as noted in Part 3, Section (3) below. None of the other changes

reviewed by the inspector met any of the criteria of 10 CFR 50.59(c)(1)

and (2), which would have required a TS change or a license amendment

from the NRC.

c. Conclusion

Review and oversight functions required by TS Section 6.2 were acceptably

completed by the ROC. Audits were being completed as required. The

licensees design change program generally satisfied NRC requirements.

3. Conduct of Operations

The inspector reviewed selected aspects of the following to verify operation of the

reactor in accordance with TS Sections 3, 4, and 6.1:

a. Inspection Scope (IP 69001)

Main (Reactor Console) Log Nos. 86 - 89

Various SCRAM Response Forms for 2015 and 2016

CARs for 2015 and to date in 2016

Maintenance Log pages completed for unscheduled work

Selected Startup Checklist Forms for the period from January 2015 through

the present

Selected Shutdown Checklist Forms for the period from January 2015

through the present

RRR Administrative Procedures, Section 3, Reactor Operations

-4-

Various RRR SOPs and Appendices including SOP 1, Reactor Operations;

SOP 20, Startup Checklist; SOP 20, Appendix A, Startup Checklist Form;

SOP 21, Same Day Startup Checklist; SOP 21, Appendix A, Same-Day

Startup Checklist Form; SOP 22, Shutdown Checklist; SOP 22,

Appendix A, Shutdown Checklist Form; SOP 23, Biweekly Checklist; SOP

23, Appendix A, Biweekly Checklist Form; SOP 24, Bimonthly Checklist;

SOP 24, Appendix A, Bimonthly Checklist Form; SOP 25, Semiannual

Checklist; SOP 25, Appendix A, Reed Research Reactor Semiannual

Checklist; SOP 26, Annual Checklist; SOP 26, Appendix A, Annual

Checklist Form; SOP 33, Nuclear Instruments; SOP 34, Control Rods;

SOP 60, Logbook Entries; and, SOP 69, Corrective Action Report

RRR Annual Reports for the last two reporting periods

b. Observations and Findings

(1) Routine Operations

The inspector reviewed selected reactor operating records from

January 2015 through the present. These records included daily Startup

Checklists, Shutdown Checklists, Experimental Startup and Shutdown

Checklists, associated forms, Weekly Checklists, and the Main (reactor

console) Logs. The records indicated that the activities were generally

carried out in accordance with written procedures as required by TS Section 6.4, except as noted below. The checklists were completed and

signed off by the appropriate personnel as required.

Through interviews with operators and review of logs and records, the

inspector confirmed that shift staffing met the minimum requirements for

duty and on-call personnel as required by TS Section 6.1.

Information on the operational status of the facility was generally recorded

properly on the log sheets and/or checklists as required by procedure.

Scrams were identified in the logs and were reported and resolved as

required before reactor operations were allowed to continue. However, it

was noted that the logs were not totally complete in that they did not

indicate who authorized operations to resume. The inspector indicated

that the complete documentation of reactor operations should include not

only when and why a scram occurred, but who gave the authorization to

resume operations as well. The licensee was informed that the issue of

complete and accurate documentation of scram events and other

operational events would be designated by the NRC as an Inspector

Follow-up Item (IFI) and would be reviewed during future inspections

(IFI 50-288/2016-202-01).

-5-

(2) NRC-Identified Violation of TS Section 3.2.2

TS Section 3.2.2 requires that the reactor shall not be operated unless

the reactor power measuring channels in Table 2 are operable. Table 2

lists the Percent Power Channel, the Linear Channel, and the Logarithmic

Channel.

On May 28, 2016, the licensee discovered that the facility reactor pool

had overflowed due to a malfunction of the recently installed automatic fill

system. On May 30, 2016, operators noticed that all reactor trips were

illuminated. Because of this, the reactor was determined to be inoperable

due to electronics problems. In mid-June, some of the electronic

components of the power measuring channels, including the Logarithmic

Channel pre-amp and the Percent Power Channel High Voltage (HV)

power supply, were removed and taken to Oregon State University (OSU)

by the electronics specialist from OSU where he worked to correct the

problems. It was noted that the Linear Channel was not found to have

been damaged.

During August 8 and 9, the OSU electronics specialist came to Reed

College and installed the repaired pre-amp and HV power supply for the

Log and Percent Power channels. After the electronics were installed,

the licensee determined that the detector chambers associated with the

Percent Power and Logarithmic Channels were not functioning properly.

Licensee personnel then removed the assemblies for each channel from

the reactor pool and began the process of trying to dry out the detectors.

On October 5, after the channel detectors were thought to be completely

dry, the electronics specialist from OSU again came to Reed College to

help test and reinstall the power channels. At that point the Log channel

was determined to be functional but the Percent Power Channel shorted

out and was not functional. Upon further investigation, the licensee found

that the detector associated with the Percent Power Channel was not an

UIC as stipulated in the SAR but a fission chamber operating in current

mode. Because that fission chamber was not functioning, licensee staff

and the OSU electronics specialist installed a spare fission chamber (one

that Reed had on hand) with the Percent Power Channel to see if it would

operate. The channel appeared to be functioning properly and appeared

to be giving the expected signals.

The following day, October 6, licensee staff attempted to adjust the

detectors and conduct a core excess and power calibration of the reactor.

Although the power channels appeared to be working properly, the

Percent Power Channel had repeated HV scrams. Licensee staff found a

loose wire and corrected that problem. During the next few days licensee

staff adjusted the Linear Power and Percent Power detector positions to

adjust for power calibration. However, another HV Percent Power scram

occurred, the cause of which could not be explained.

-6-

On October 13, channel testing continued and core excess

measurements were again attempted but to no avail and the

Percent Power Channel was determined to be non-functional. On

October 14, the OSU electronics specialist returned to Reed and installed

a spare UIC (one that OSU had received from another university) to

operate in the Percent Power Channel. On October 16, the licensee

completed core excess and reactor power calibrations. They operated up

to 150 kilowatt (kW) for training and operator requalification.

Two days later operations were conducted for requalification but the

Log channel was determined to be erratic, possibly due to electronic

noise. Because the reactor had been operated for over an hour with a

non-functional Logarithmic Channel, the reactor was scrammed. At that

point, the Reactor Operations Manager declared the problem as an event

and a report was made to the NRC (see Section (4) below). When the

licensee investigated the problem, it was believed that the problem was

due to an electronics noise problem. After disconnecting, testing, and

reconnecting the channel, they thought the problem (the noise issue) with

the Logarithmic Channel was corrected. The following day, October 19,

the Logarithmic Channel was tested and determined to be functional.

Core excess measurements were completed and the reactor was

operated for requalification of operators. An inadvertent scram occurred

but this was caused by operator error and operations were allowed to

continue.

Because most of the student operators were out of qualification

(due to the continuing problems with the nuclear instruments NI

channels), reactor operations continued and were conducted on various

occasions for requalification but problems persisted. Core excess

measurements were completed each day and other activities were

attempted such as measuring Regulating Rod worth. The licensee also

completed Shim and Safety rod worth measurements but problems kept

occurring with the Logarithmic Channel. On October 21, the licensee

determined that the Logarithmic Channel detector was apparently working

properly but the electronics were not. At that point the reactor was

declared non-operational. The reactor has not been operated since that

date.

The NRC reviewed the issues associated with the reactor power

measuring channels. From October 6-16, licensee staff operated the

reactor up to 150 kW for training and requalification. (It was noted that

after October 16, the reactor was only operated at a power level of

5 watts (W) or less.) During that period when operating at 150 kW, the

Linear Channel typically read 60 percent, the Percent Power Channel

typically read 60 percent, but the Logarithmic Channel was reading from

90 to 100 percent. The inspector reviewed the console logs for the past

two years. For that time frame, when operating at 150 kW, the Linear

Channel typically read 60 percent, the Percent Power Channel typically

read 60 percent, and the Logarithmic Channel typically read 60 percent.

-7-

Therefore, from October 6 through 16, the Logarithmic Channel was not

reading correctly because it was reading high and over responding,

probably indicating that the channel detector was shorted out. The NRC

concluded that the Logarithmic Channel was not operating properly and

thus was not operational during this period. The licensee was informed

that failure to have an operable Logarithmic Channel during reactor

operation was an apparent violation of TS Section 3.2.2 (violation (VIO)

50-288/2016-202-02).

(3) NRC-Identified Violation of Regulatory Requirements

The RRR safety analysis report (SAR) states in Chapter 7, Section

7.2.3.3, that the Percent Power Channel has an Uncompensated Ion

Chamber that provides indication for that channel.

Regulation in 10 CFR 50.59 requires that licensees evaluate a change

from what was described in the SAR to ensure that a TS change or a

license amendment was not required in accordance with 10 CFR 50.59

pargraphs (c)(1)(i and ii) and (c)(2)(i-viii).

As noted above, the licensee had been experiencing various problems

with the reactor power measuring channels. Because of these problems,

the licensee tried repeatedly to make adjustments to the channel

electronics and the positions of the associated detectors. On

October 6, 2016, licensee staff attempted to adjust the detectors and

conduct a core excess and power calibration of the reactor. Although the

power channels appeared to be working properly, the Percent Power

Channel had repeated HV scrams. Licensee staff found a loose wire and

corrected that problem but other problems persisted. Finally on

October 14, the OSU electronics specialist returned to Reed and installed

a spare UIC (one that OSU had received from another university) into the

Percent Power Channel. Licensee staff conducted a core excess

measurement and performed testing of the electronics using the reactor

at various power levels.

The NRC reviewed this situation and the problems with the Percent

Power Channel. As stated above, it was noted that the licensee was not

aware that the detector associated with the Percent Power Channel was

a fission chamber (and not a UIC as stated in the SAR) prior to

October 5, 2016. However, following that date, the licensee was fully

aware of the situation. Nevertheless, the decision was made to replace

the existing fission chamber with a spare fission chamber that the

licensee had on hand.

-8-

A fission chamber was not what the SAR stipulated as the detector to be

operated with the Percent Power Channel. No attempt was made to

conduct a 10 CFR 50.59 review as to whether or not such a detector

should be used with the Percent Power Channel. The licensee was

informed that failure to conduct a review in this situation was an apparent

violation of 10 CFR 50.59 requirements (VIO 50-288/2016-202-03).

(4) Self-Reported Violation of the Requirements of TS Section 3.2.2

Section 3.2.2 of the RRR technical specifications requires that the reactor

shall not be operated unless the reactor power measuring channels in

Table 2 are operable. Table 2 lists the Percent Power Channel, the

Linear Channel, and the Log Channel.

On October 18, 2016, a licensed reactor operator and another person

operating under the operators direction completed the Start Up Checklist

had checked out properly and appeared to be functioning normally.

They then inserted the key and began a check out of the reactor NIs prior

to full power operation. They conducted the excess reactivity surveillance

test at a power level below 5 W.

About an hour after the key was inserted into the console, the Reactor

Operations Manager entered the Control Room and noted that one of the

NIs, the Log channel was not tracking correctly, i.e., the Log channel was

reading a constant number and not tracking with the power level. The

reactor was immediately scrammed and secured.

The three individuals then began to investigate the problem and diagnose

what had happened. Analysis showed that the Log channel pre-amp was

picking up excessive noise due to its close proximity to other electrical

components. Also, upon further investigation, a ground wire was found

detached from its proper connection.

The loose ground wire was replaced and a test of the pre-amp was

initiated. Testing of the pre-amp on a platform away from interference

from other electronics indicated that it was then functioning properly.

Under these corrected conditions, the Log channel was tested and the

reading appeared to return to normal. However, reactor operations were

suspended until the channel could be more thoroughly tested. A CAR

was initiated to document the issue. The NRC was notified of the event

on October 19, 2016.

The NRC reviewed this issue and discussed the self-identified TS

violation with the licensee and interviewed various reactor staff personnel.

The NRC confirmed that the licensee had, in fact, been in violation of

TS Section 3.2.2. The circumstances of the event and the notifications

were reviewed.

-9-

The inspector verified that the licensee had taken what they thought were

appropriate corrective actions once the issue was identified. Corrective

actions included immediately shutting down the reactor, investigating the

problem and making the repairs that they thought would repair the

channel. Following repairs and discussion of the issue with the Reactor

Director, the reactor was placed back in operation.

The licensee was informed that the failure to have all of required channels

operable during reactor operation was a Severity Level IV violation of

TS Section 3.2.2. However, the safety consequences were low because

the reactor was operated at a power level less than 5 W and 2 of the 3

required channels were operable to provide any required reactor scram.

The inspector determined that this particular problem had been identified

by the licensee and promptly reported to the NRC. What the licensee

thought were adequate corrective actions had been identified and

implemented. As a result, the licensee was informed that this issue would

be treated as a NCV, consistent with Section VI.A.8 of the NRC

Enforcement Policy (NCV 50-288/2016-202-04).

This issue is considered closed.

(5) Reactor Pool Overfill Problem

As noted above, near the end of May, the licensee found that the reactor

pool had overflowed. Upon investigation the licensee found that the

problem had occurred due to a malfunction of the recently installed

automatic fill system. In the past, as part of a weekly checklist, staff

members were tasked with checking the pool level and adding water if the

pool level dropped below a certain mark. However, on occasion, the staff

members forgot to shut the fill water off and the tank was nearly over

filled. To correct that problem, under the auspices of the 10 CFR 50.59

program, the licensee installed an automatic fill control system.

Unfortunately, the automatic system failed on May 28, 2016, and the pool

overfilled to the point that water entered the nuclear instrumentation tubes

leading to the detectors. The Percent Power channel and the Log

Channel were affected; the Linear Channel was not damaged.

The overfill caused problems that persisted with the two affected

channels from June through October (as noted above). The licensee was

informed that the issue of correcting the overfill problem would be

designated by the NRC as an IFI and would be reviewed during future

inspections (IFI 50-288/2016-202-05).

- 10 -

c. Conclusion

Reactor staffing, operations, and logs were generally acceptable. One apparent

violation was identified for operating the reactor without the logarithmic channel

being operable as required by TS Section 3.2.2. One apparent violation was

identified for failure to conduct a 10 CFR 50.59 review. One non-cited violation

was identified for operating the reactor without the logarithmic channel being

operable as required by TS Section 3.2.2.

4. Operator Requalification Program

a. Inspection Scope (IP 69001)

The inspector reviewed selected portions of the following regarding the RRR

Requalification Plan to ensure that the requirements of the plan and

10 CFR 55.59, Requalification, were being met:

Main (Reactor Console) Log Nos. 86 - 89

Active license status of all current operators

Medical examination records for selected operators

RRR Facility Requalification Program, dated July 2009

RRR Facility Alternate Requalification Plan, dated September 2016

Training lectures and records for the current training cycle

NRC Form 398, Personal Qualification Statement - Licensee

Written examinations given during 2014 and 2015 for selected operators

RRR Facility Requalification Plan, dated July 2009

NRC Form 396, Certification of Medical Examination - by Facility Licensee

RRR Facility Requalification Meeting Agenda and Attendance Sheets for

September 2014 through the present

Requalification Hours and Reactivity Manipulation Sheets documenting

reactivity manipulations for 2014 through the present for selected operators

RRR Administrative Procedures, Section 9, Record Retention

Various RRR SOPS including: SOP 63, Requalification; SOP 63 Appendix

A, Reactor Operator Physical Exam; and SOP 63,

Appendix B, Accelerated Requalification Form

b. Observations and Findings

(1) Routine Requalification Program - For the Period 2014 through

June 2015 and for July 2015 through June 2016

As noted previously, there are currently 20 qualified SROs and

19 qualified ROs at the RRR facility. The inspector reviewed selected

operators licenses and noted that they were current.

- 11 -

The inspector reviewed the requalification program for July 2014 through

June 2015, and for July 2015 through June 2016, as well as the annual

drill scenarios and attendance sheets. It was noted that operators

typically made entries on the Requalification Hours and Reactivity

Manipulation Sheet that was located in the control room. Through these

actions the hours on duty and in what capacity (i.e., RO/SRO), as well

as the tasks performed, were documented. The inspector also reviewed

the Requalification Meeting Agenda and Attendance Sheets for the period

from September 2014 through the present. The inspector reviewed

various individual operators requalification records as well.

The review of the various logs and records noted above showed that

training had been conducted in accordance with the licensees

requalification and training program until May 2016. Training reviews and

examinations had been completed and documented as required. The

records indicated that operators were completing the required activities,

including reactivity manipulations and number of operating hours.

Records indicated that annual operations tests and supervisory

observations were being completed. Biennial written examinations were

also being completed as required or credit was taken by the licensee for

the exams administered by the NRC to satisfy the requalification cycle

exam requirements when applicable. Additionally, the inspector noted

that operators were receiving the required biennial medical examinations

within the required time frame.

(2) Alternate Requalification Plan - For the period from July 2016 until the

Reactor is Operational

As noted in Section 3 of this report, the RRR has been functional and

operational only sporadically since May 2016. Because of this problem,

operators have not been able to complete the operational requirements to

remain fully qualified. The licensee recognized this and proposed an

alternate requalification plan to the NRC in September. The alternate

plan was reviewed and subsequently approved.

The Alternate Requalification Plan stipulated that two Reed College

SROs would go to the OSU research reactor facility and complete two

hours of reactor operation under direction of OSU personnel and two

hours of supervision of the other Reed College operator. These two

individuals would also complete one reactivity manipulation each while at

OSU as well. This would suffice for the reactor operation requirements of

the Reed Requalification Program and allow the two operators to return to

Reed College and observe Reed operators to operate under their

direction.

For the remainder of the operators at Reed who did not go to OSU and

were out of qualification, the alternate plan required that each operator

complete three hours of reactor operation and two reactivity

manipulations under direction of one of the SROs who went to OSU.

- 12 -

In addition, these operators would then need to meet the routine Reed

Requalification Program requirements of four hours of reactor operation

and two reactivity manipulations for the quarter. If any licensed

individuals were not in compliance with other requirements outlined in

10 CFR 55.59, the operators would be required to meet the requirements

of 10 CFR 55.53, Conditions of licenses, paragraph (f)(2) of six

additional hours of operation under direction.

The inspector reviewed the actions of the licensee to comply with the

requirements of the Alternative Requalification Plan. The inspector

verified that the two SROs who went to OSU had completed the required

hours of operation and the required reactivity manipulations. They then

returned to Reed and began observing other operators. It was noted that

4 SROs and 2 ROs had completed the requirements of the alternate

requalification plan. However, it was also noted that only two SROs

would be in compliance with the Routine Requalification Program if the

Reed reactor remains shut down through the end of December (the end

of the quarter). The licensee acknowledged that, if the reactor remains

shut down through the end of the quarter, all operators who are not in

compliance with the requalification program requirements will have to

complete the Alternate Requalification Plan requirements as well as the

regular Reed Requalification Program requirements before being

considered qualified to operate the reactor.

(3) Access to the Reed Research Reactor Facility (RRRF) Controlled Access

Area

As noted above, the inspector reviewed the Reed Routine Requalification

Program. During records review it was found the Reed Operations

Manager was approving individuals access to the facility Controlled

Access Area (CAA), i.e., signing the access forms. Only the NRC

approved reviewing official may grant unescorted access to the facility in

accordance with 10 CFR 73.57, Requirements for criminal history

records checks of individuals granted unescorted access to a nuclear

power facility, a non-power reactor, or access to Safeguards Information,

paragraph (g). The NRC approved reviewing official is the RRRF

Director as indicated in a letter from the NRC to the licensee. The

licensee was informed that only the NRC approved reviewing official is

authorized to approve individuals access. Any changes or request for

changes must be submitted to the NRC for evaluation.

Because the decision to grant unescorted access to the CAA of the

facility was always discussed between, and approved by, both the

Director and the Reactor Operations Manager, the Director subsequently

countersigned all the access forms. The licensee agreed that only an

approved Reviewing Official would sign the access forms in the future.

- 13 -

c. Conclusion

The requalification/training program was up-to-date and being acceptably

maintained. Medical examinations were being completed biennially as required.

5. Fuel Handling

a. Inspection Scope (IP 69001)

In order to verify adherence to fuel handling and inspection requirements

specified in TS Section 4.1, the inspector reviewed selected aspects of the

following:

Fuel Element Inspection Cards

Main (Reactor Console) Log Nos. 86 - 89

Fuel Element Inspection sheet maintained in the appropriate Fuel Inspection

Binder

RRR Administrative Procedures Section 6, Fuel and Special Nuclear

Material

Various RRR SOPs including: RRR SOP 35, Fuel and Core; SOP 35,

Appendix A, Core Diagram; SOP 35, Appendix B, Fuel Handling

Checklist; SOP 35, Appendix C, Fuel Handling SRO Qualification; and

SOP 35, Appendix D, Fuel Handling Receipt Form

b. Observations and Findings

Through review of the main logs and interviews with licensee personnel, the

inspector verified that fuel movements were conducted in compliance with

procedure. The inspector also verified that the licensee was maintaining the

required records of fuel movements as they were completed. The logs were

being filled out properly to indicate which elements were moved and to what

locations.

Also through records review, it was noted that the reactor fuel was being

inspected upon initial receipt and 25 percent of the fuel elements in the core were

being inspected annually. This exceeded the percentage of fuel elements

required to be inspected as stipulated by TS Section 4.1. The last annual fuel

inspection was completed during January 11-27, 2016. The inspector verified

that all fuel elements were inspected at least once every 5 years, including

elements in storage and/or removed from service as required.

c. Conclusion

Reactor fuel movements and inspections were completed and documented in

accordance with procedure and the fuel was being inspected more frequently

than required by TS Section 4.1.

- 14 -

6. Maintenance and Surveillance

a. Inspection Scope (IP 69001)

To verify that operations, surveillance activities, and calibrations were being

completed as required by the TS, the inspector reviewed selected portions of:

Main (Reactor Console) Log Nos. 86 - 89

Maintenance Log pages completed for unscheduled work

Associated surveillance and calibration data and records for 2015-2016

Other Checklists Notebook which contained calibration forms, inspection

forms, and various checklists

Various RRR SOPs and Appendices including: SOP 23, Biweekly Checklist;

SOP 23, Appendix A, Biweekly Checklist Form; SOP 24, Bimonthly

Checklist; SOP 24, Appendix A, Bimonthly Checklist Form; SOP 25,

Semiannual Checklist; SOP 25, Appendix A, Reed Research Reactor

Semiannual Checklist; SOP 26, Annual Checklist; SOP 26, Appendix A,

Annual Checklist Form; SOP 34, Control Rods; SOP 34, Appendix A,

Control Rod Calibration Form; SOP 34, Appendix B, Control Rod

Inspection Checklist; SOP 34, Appendix C, Control Rod Inspection Form;

and, SOP 60, Logbook Entries; and associated Appendix A, Maintenance

Log forms

RRR Annual Reports for the last two reporting periods

b. Observations and Findings

The licensee conducted various maintenance and surveillance activities which

were then documented on the appropriate forms and checklists. The inspector

verified that these activities were conducted within the time frame required and

according to procedure. The inspector reviewed selected biweekly, bimonthly,

semiannual, and annual forms and checklists. All the recorded results reviewed

were within the TS and procedurally prescribed parameters. The records and

logs reviewed appeared to be complete and were being maintained as required.

The inspector was not able to observe a Startup or Shutdown Checklist being

performed during the inspection. However, previously completed Startup and

Shutdown Checklists were reviewed. These activities appeared to have been

conducted appropriately and in accordance with procedure.

A review of the RRRF Main Logs and current Maintenance Logbook showed that

these records were also being completed as required and problems, if any, were

being documented. Through observation and records review, the inspector also

confirmed that maintenance was being conducted as needed, consistent with the

TS.

- 15 -

c. Conclusion

Maintenance was being completed as required. The program for surveillance

was being carried out in accordance with TS requirements.

7. Procedures

a. Inspection Scope (IP 69001)

To determine whether facility procedures met the requirements outlined in

TS Section 6.4, the inspector reviewed portions of the following:

Procedural reviews and updates documented in the ROC meeting minutes

RRR Administrative Procedures, Section 8, Adoption and Revision of

Operating Procedures, and Section 9, Record Retention

Various RRR SOPs and Appendices including: SOP 60, Logbook

Entries;SOP 61, Procedure Writing and Use; SOP 61, Appendix A,

Document Structure; SOP 61, Appendix B, Document Locations; and

SOP 61, Appendix C, Temporary Procedure Change

b. Observations and Findings

Procedures were in effect for those activities specified in TS Section 6.4 as

required. RRR Administrative Procedures and SOPs were found to be

acceptable for the current staffing level and status of the facility. The

Administrative Procedures and SOPs specified the responsibilities of the various

members of the staff. Substantive changes to procedures were being reviewed

and approved by the ROC. The procedures were being audited, reviewed, and

updated as needed.

The inspector reviewed the temporary procedure changes that had been

promulgated during the past 12 months. The changes were written after minor

problems with the procedures were noted. The temporary changes were

typically incorporated in the referenced procedures if deemed appropriate by the

licensee. Changes suggested as a result of the ROC and independent audits

were also incorporated into the procedures if deemed appropriate.

c. Conclusion

Facility procedures for the safe operation of the reactor were available as

required by TS Section 6.4.

- 16 -

8. Experiments

a. Inspection Scope (IP 69001)

In order to verify that experiments were being conducted within approved

guidelines specified in TS Sections 3.6, 4.6, and 6.5, the inspector reviewed

selected portions of the following:

Experiment review and approval by the ROC

Selected Irradiation Request Forms for 2015 and 2016

Approved RRR Routine Experiments (REs), including: RE 1, Irradiation with

Neutrons; RE 2, Irradiation with Gammas; RE 3, Fuel, Graphite, or Source

Material; RE 4, Reactor Power Measurement; RE 5, Control Rod Worth

Measurement; RE 6, Pool Parameter Measurement; RE 7, Fuel Loading;

RE 8, Cerenkov Radiation Spectrum Acquisition; RE 9, Neutron Induced

Auto-Radiography; and RE 10, Radial Flux Measurements

Approved RRR Special Experiment (SE), SE 4, Core Temperature

Measurements

RRR Administrative Procedures, Section 4, Reactor Experiments; and

Section 9, Record Retention

Various RRR SOPs and Appendices including: SOP 10, Irradiation

Preparation; SOP 10, Appendix A, Irradiation Request Form; SOP 10,

Appendix D, Irradiation Request Log; SOP 11, Irradiation Analysis;

SOP 12, Lazy Susan; SOP 13, Rabbit; SOP 14, Central Thimble;

SOP 15, Beam; SOP 15, Appendix A, Beam Irradiation Request

Form;SOP 16, Near Core; and SOP 17, Gamma Irradiations

b. Observations and Findings

The inspector noted that the various experiments conducted at the facility, and

revisions thereto, were being reviewed and approved as required. It was also

noted that the two most recently proposed REs had been submitted by licensee

staff and students and had been reviewed and approved by the Facility Director

and the ROC as required.

Through a review of console logs and various irradiation request forms, the

inspector noted that irradiations were conducted under the cognizance of the

Facility Director and the Reactor Supervisor as required. The irradiations were

documented in the Main Log and the results of the experiments were

documented on the Irradiation Request Forms as required. The resulting

radioactive material was being transferred to an authorized user, disposed of as

stipulated by procedure, or held for decay.

- 17 -

c. Conclusion

The licenses program for the control of experiments generally satisfied

TS Sections 3.6, 4.6, and 6.5 and other regulatory requirements.

9. Emergency Preparedness

a. Inspection Scope (IP 69001)

To verify compliance with the RRRF, E-Plan, the inspector reviewed selected

aspects of the following:

ERR E-Plan last revised August 2014

Emergency response training records for the past 2 years

Emergency drills and exercises held during 2015 and 2016

Emergency response facilities, supplies, equipment and instrumentation

ERR SOP 25, Semiannual Checklist

ERR SOP 25, Appendix A, Reed Research Reactor Semiannual Checklist

ERR E-Plan, Appendix a, Emergency Implementation Procedures (EIPs)

ERR E-Plan, Appendix B, Projected Doses for Bounding Accidents

ERR E-Plan, Appendix C, Visible and Audible Alarms

b. Observations and Findings

The E-Plan in use at the reactor had been updated, reviewed, and approved by

the ROC. The licensee had determined that there was no decrease in

effectiveness as defined in 10 CFR 50.54, Conditions of licenses,

paragraph (q). The licensee had submitted a letter to the NRC documenting this

determination on August 18, 2014.

The E-Plan and EIPs were being audited and reviewed annually as required.

Supplies, instrumentation, and equipment staged for emergency use were being

maintained, controlled, and inventoried semiannually as required in the E-Plan. It

was noted that the Emergency Support Center was located in the RRRF

Directors office in the Chemistry Building.

Through records review and interviews with licensee personnel, emergency

responders were determined to be knowledgeable of the proper actions to take in

case of an emergency. The inspector reviewed the Agreement Letters that had

been signed with various emergency support organizations. These agreements

were being maintained and updated as needed.

Communications capabilities were acceptable and had been tested and

emergency information updated as stipulated in the E-Plan. It was noted that the

Emergency Notification Call List, posted in various locations throughout the

facility, was current and the most recent version was dated October 5, 2016.

The inspector verified that training for staff and offsite support personnel was

being provided annually as required.

- 18 -

Training for staff was typically completed through the Operator Requalification

Program. Training for representatives from the Portland Fire and Rescue

Department (PF&RD) was conducted annually. Training for representatives from

the Portland Police Bureau was offered but the police could not always commit to

attend because of staffing level shortages.

Emergency drills had been conducted annually as required by the E-Plan.

Off-site support organization participation was also as required by the E-Plan.

Critiques were held following the drills to discuss the strengths and weaknesses

identified during the exercises and to develop possible solutions to any problems

identified. The results of these critiques were documented and reported to the

Radiation Safety Committee/ROC. Drills involving off-site personnel were being

conducted annually and documented as stipulated by the E-Plan.

The inspector and the Facility Director visited a PF&RD unit located several miles

from the RRRF. The inspector and Director were given a tour of the facility and

observed the equipment maintained by the unit for response to various types of

emergencies. As a result of this visit, and following a review of the licensees

records documenting drills and training, the inspector verified that fire department

personnel were well trained, properly equipped, and knowledgeable of the

actions to take in case of an emergency at the reactor facility. The inspector

determined that the licensee communicated with the PF&RD frequently and was

maintaining a good working relationship with this support group.

c. Conclusion

The emergency preparedness program was conducted in accordance with the

E-Plan.

10. Follow-up on Previously Identified Items

a. Inspection Scope (IP 92701)

The inspector reviewed the actions taken by the licensee to address a previously

identified IFI.

b. Observation and Findings

50-288/2014-202-01 - IFI - Follow-up on the licensees actions to correct the

inconsistencies between the E-Plan and the Implementing Procedures dealing

with the Alert classification of various events.

During an inspection in December 2014, the inspector reviewed of the E-Plan. It

was noted that there were no accidents that could cause an Alert classification

for the facility. However, certain security events would require an Alert"

Nevertheless, it was noted that there were various EIPs which indicated that, in

certain accident situations, the classification for the event would be Alert.

- 19 -

The licensee acknowledged these inconsistencies and agreed to correct the

problem. The licensee was informed that correcting these issues would be

followed by the NRC as an IFI.

During this inspection, the inspector reviewed the actions taken by the licensee

to resolve the inconsistencies between the E-Plan and the EIPs. It was noted

that the procedures had been revised to indicate that accidents or events

occurring in conjunction with security events require the Alert designation.

Otherwise these events are classified as Unusual Events. This issue is

considered closed.

c. Conclusions

One IFI was reviewed and this issue is considered closed.

11. Exit Interview

The initial scope of the inspection were summarized on November 2, 2016, with the

Facility Director, the Reactor Manager, and the Dean of Faculty. On November 3, 2016,

the preliminary results were discussed with the Facility Director and the Reactor

Manager. On December 1, 2016, the results of the inspection were discussed with the

Facility Director and the Dean of Faculty. On December 2, 2016, the results of the

inspection were reiterated with the Facility Director. The inspector discussed the

findings for each area reviewed. The licensee acknowledged the findings and did not

identify as proprietary any of the material provided to or reviewed by the inspector during

the inspection.

PARTIAL LIST OF PERSONS CONTACTED

Licensee

C. Barrett Reactor Operations Manager

S. Brodesser Training Supervisor

T. Freeman Requalification Supervisor

A. Karr Radiation Safety Officer and Campus Environmental Director

J. Koh Operations Supervisor

M. Krahenbuhl Director, Reed Reactor Facility

M. McCarthy Projects Supervisor

N. Nicholson Dean of the Faculty, Reed College

M. Oxley Training Supervisor

Other Personnel

S. Christensen First Lieutenant, Portland Fire and Rescue, Training, Safety, and EMS

Division, City of Portland

B. Profit Training Lieutenant, Portland Fire and Rescue, Training, Safety, and EMS

Division, City of Portland

INSPECTION PROCEDURE USED

IP 69001 Class II Non-Power Reactors

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

50-288/2016-202-01 IFI Follow-up on the licensees actions to maintain logs which

contain the accurate and complete documentation of scram

events and other operational events.

50-288/2016-202-02 VIO Failure to have all of required channels operable during

reactor operation as required by TS Section 3.2.2.

50-288/2016-202-03 VIO Failure to complete a review prior to installing a fission

chamber instead of an uncompensated ion chamber with the

Percent Power Channel (as stipulated in the facility SAR) as

required by 10 CFR 50.59 (c)(1)(i and ii) and (c)(2)(i-viii).

50-288/2016-202-04 NCV Failure to have all of required channels operable during

reactor operation as required by TS Section 3.2.2.

50-288/2016-202-01 IFI Follow-up on the licensees actions to correct the reactor pool

overfill problem caused by the automatic fill system installed

by the licensee.

-2-

Closed

50-288/2014-202-01 IFI Follow-up on the licensees actions to correct the

inconsistencies between the E-Plan and the Implementing

Procedures dealing with the Alert classification of various

events.

50-288/2016-202-04 NCV Failure to have all of required channels operable during

reactor operation was a Severity Level IV violation of

TS Section 3.2.2.

LIST OF ACRONYMS USED

10 CFR Title 10 of the Code of Federal Regulations

CAA Controlled Access Area

CAR Corrective Action Report

E-Plan Emergency Plan

EIP Emergency Implementation Procedures

HV High Voltage

IFI Inspector Follow-up Item

IP Inspection Procedure

kW Kilowatt

NCV Non-Cited Violation

No. Number

NRC Nuclear Regulatory Commission

OSU Oregon State University

PF&RD Portland Fire and Rescue Department

RE Routine Experiment

RO Reactor Operator

ROC Reactor Operations Committee

RRR Reed Research Reactor

RRRF Reed Research Reactor Facility

SAR Safety Analysis Report

SE Special Experiment

SOP Standard Operating Procedure

SRO Senior Reactor Operator

SSC Structure, System, or Component

TS Technical Specifications

UIC Uncompensated Ion Chamber

VIO Violation

W Watt