ML19192A097: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter:Palo | {{#Wiki_filter:Palo Verde License Amendment Request for Emergency Plan July 11, 2019 | ||
-1 of NUREG-0654, Revision 2 (ML16117A427)Exelon Midwest License Amendment Request | Palo Verde LAR | ||
* Change based on the following: | |||
* NRC June 12, 2018 correspondence to NEI, Alternative Guidance for Licensee Emergency Response Organizations (ML18022A352) | |||
* Technical Basis for Section II.B, Table B-1 of NUREG-0654, Revision 2 (ML16117A427) | |||
* Exelon Midwest License Amendment Request (ML18053A159) and approved Safety Evaluation (ML19036A586) for changes to their Emergency Response Organization 2 | |||
Palo Verde LAR Critical Elements of License Amendment Request | |||
* No change to current augmentation timeframes and process | |||
* Augment at Alert for all facilities and ERO positions | |||
* Use of an All Call and duty roster process for staffing | |||
* 60 minutes during normal working hours and 120 minutes off hours | |||
* Supplemented Rev. 2 NUREG 0654 on shift ERO to support maintaining 120 minute off hours augmentation | |||
* Increase RP technicians to support onsite or offsite monitoring as needed | |||
* RP Supervision/Dose Assessment on-shift | |||
* Ensure that key ERO functions can be maintained for timeframe prior to augmented resources arrival 3 | |||
Palo Verde LAR Critical Elements of License Amendment Request (contd) | |||
* Remove on-shift Chemistry and Maintenance personnel | |||
* Increase number of augmented ERO consistent with guidance in Rev. 2 | |||
* Remove non-minimum staff positions from the emergency plan (maintain in procedures) | |||
* State of Arizona has reviewed and supports this amendment request | |||
* State and federal agencies will be invited to a once every drill cycle minimum staff drill 4 | |||
Palo Verde LAR Additional resources to support the key ERO functions remain in place on-shift: | |||
* Additional Radiation Protection support for onsite and offsite field monitoring is available if needed | |||
* The number of auxiliary operators on site (12, 4 per unit) allows for additional efforts to support operations and maintenance critical activities during the 120 minute augmentation time | |||
* Dose Assessment and Radiation Protection leadership available on shift | |||
* Offsite communications to State and Local government and the NRC 5 | |||
Palo Verde LAR Additional resources to support the key ERO functions remain in place on shift (contd): | |||
* Engineering Support in the form of the unaffected unit Shift Technical Advisor | |||
* Security Leadership to support the callout process | |||
* Augmented Command and Control assistance to the affected Unit Shift Manager in the form of two on-shift Shift Managers/Emergency Coordinators from the unaffected Units | |||
* Shift Managers, Control Room Supervisors and Shift Technical Advisors are trained to the Emergency Coordinator position qualification 6 | |||
Palo Verde LAR | |||
* Schedule for LAR submittal | |||
* 3rd Quarter 2019 | |||
* NRC review and Issuance of Safety Evaluation | |||
* 1 year | |||
* Scheduled Implementation | |||
* Six Months following approval 7 | |||
Discussion/Questions}} | Discussion/Questions}} | ||
Revision as of 15:44, 19 October 2019
| ML19192A097 | |
| Person / Time | |
|---|---|
| Site: | Palo Verde |
| Issue date: | 07/11/2019 |
| From: | Arizona Public Service Co |
| To: | Division of Operating Reactor Licensing |
| Lingam S, 301-415-1564 | |
| References | |
| Download: ML19192A097 (8) | |
Text
Palo Verde License Amendment Request for Emergency Plan July 11, 2019
Palo Verde LAR
- Change based on the following:
- NRC June 12, 2018 correspondence to NEI, Alternative Guidance for Licensee Emergency Response Organizations (ML18022A352)
- Technical Basis for Section II.B, Table B-1 of NUREG-0654, Revision 2 (ML16117A427)
- Exelon Midwest License Amendment Request (ML18053A159) and approved Safety Evaluation (ML19036A586) for changes to their Emergency Response Organization 2
Palo Verde LAR Critical Elements of License Amendment Request
- No change to current augmentation timeframes and process
- Augment at Alert for all facilities and ERO positions
- Use of an All Call and duty roster process for staffing
- 60 minutes during normal working hours and 120 minutes off hours
- Supplemented Rev. 2 NUREG 0654 on shift ERO to support maintaining 120 minute off hours augmentation
- Increase RP technicians to support onsite or offsite monitoring as needed
- RP Supervision/Dose Assessment on-shift
- Ensure that key ERO functions can be maintained for timeframe prior to augmented resources arrival 3
Palo Verde LAR Critical Elements of License Amendment Request (contd)
- Remove on-shift Chemistry and Maintenance personnel
- Increase number of augmented ERO consistent with guidance in Rev. 2
- Remove non-minimum staff positions from the emergency plan (maintain in procedures)
- State of Arizona has reviewed and supports this amendment request
- State and federal agencies will be invited to a once every drill cycle minimum staff drill 4
Palo Verde LAR Additional resources to support the key ERO functions remain in place on-shift:
- Additional Radiation Protection support for onsite and offsite field monitoring is available if needed
- The number of auxiliary operators on site (12, 4 per unit) allows for additional efforts to support operations and maintenance critical activities during the 120 minute augmentation time
- Dose Assessment and Radiation Protection leadership available on shift
- Offsite communications to State and Local government and the NRC 5
Palo Verde LAR Additional resources to support the key ERO functions remain in place on shift (contd):
- Engineering Support in the form of the unaffected unit Shift Technical Advisor
- Security Leadership to support the callout process
- Augmented Command and Control assistance to the affected Unit Shift Manager in the form of two on-shift Shift Managers/Emergency Coordinators from the unaffected Units
- Shift Managers, Control Room Supervisors and Shift Technical Advisors are trained to the Emergency Coordinator position qualification 6
Palo Verde LAR
- Schedule for LAR submittal
- 3rd Quarter 2019
- NRC review and Issuance of Safety Evaluation
- 1 year
- Scheduled Implementation
- Six Months following approval 7
Discussion/Questions