ML091520264: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 2: | Line 2: | ||
| number = ML091520264 | | number = ML091520264 | ||
| issue date = 07/07/2008 | | issue date = 07/07/2008 | ||
| title = NRC Region | | title = NRC Region III, Initial License Exam, Job Performance Measure, JPM: Ro/Sro Admin 1A, Title: Determine Quadrant Power Tilt Per PO-3 | ||
| author name = | | author name = | ||
| author affiliation = NRC/RGN-III | | author affiliation = NRC/RGN-III | ||
Revision as of 22:07, 11 July 2019
| ML091520264 | |
| Person / Time | |
|---|---|
| Site: | Palisades |
| Issue date: | 07/07/2008 |
| From: | NRC/RGN-III |
| To: | Entergy Nuclear Palisades |
| Shared Package | |
| ML082200311 | List: |
| References | |
| Download: ML091520264 (9) | |
Text
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE
JPM: RO/SRO ADMIN 1a TITLE: DETERMINE QUADRANT POWER TILT PER PO-3
CANDIDATE: _____________________________________________
EXAMINER: _____________________________________________
JPM RO SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 2 of 9 July 2008 JOB PERFORMANCE MEASURE DATA PAGE Task: Determine Quadrant Power Tilt PER PO-3
Alternate Path: N/A
Facility JPM #: PL-OPS-ENG-014J
K/A: G2.1.7 Importance: RO: 4.4 SRO: 4.7
K/A Statement: Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation.
Task Standard: Correctly calculate a Quadrant Power Tilt Per PO-3
Preferred Evaluation Location: Simulator __X__ In Plant _____
Preferred Evaluation Method: Perform __X__ Simulate _____
References:
PO-3, Alternate Incore and Excore Applications
Validation Time: 12 minutes Time Critical: NO
Candidate: ________________________________________________
Time Start: ________ Time Finish: ________
Performance Time: ________ minutes
Performance Rating: SAT______ UNSAT ______
Comments:
Examiner: _______________________________ Date: ______________ Signature JPM RO SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 3 of 9 July 2008 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
PO-3, Attachment 2, Rev. 2
Also see Simulator Operator Instructions (last page of this document).
READ TO CANDIDATE
DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
- Plant was at full power.
- Incores #9 and #35 are inoperable.
- CRD #11 has dropped into the core.
INITIATING CUES:
- During performance of PO-3, Alternate Incore and Excore Applications, the Control Room Supervisor directs you to calculate Excore Quadrant Power Tilt utilizing Power Range NI Channels on Panel C-06.
JPM RO SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 4 of 9 July 2008 Proc. Step TASK ELEMENT 1 STANDARD Grade n/a Correct Procedure located PO-3, Attachment 2, Excore Quadrant Power Tilt, located.
S U Comment: Notes: Evaluator provides candidate with a Working Copy.
Proc. Step TASK ELEMENT 2 STANDARD Grade5.2.1 Obtain lower and upper excore readings as required. (S AL , S BL , S CL , S DL and S AU , S BU , S CU , S DU). Lower and upper excore readings from the PPC using NI5L, NI5U, NI6L, NI6U, NI7L, NI7U, NI8L and NI8U or from the Upper and Lower NI Detector meters on EC-06 are entered on PO-3, Attachment 2, within
+/-1% (0.01) of the answer key. S U Comment:
CRITICAL STEP
Proc. Step TASK ELEMENT 3 STANDARD Grade5.2.1 Calculate the sum from the Lower + Upper excore readings (S A , S B , S C , S D Lower + Upper excore readings (S A , S B , S C , S D) summed and entered on PO-3, Attachment #2, within +/-1% (0.01) of the answer key.
S U Comment:
CRITICAL STEP
JPM RO SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 5 of 9 July 2008 Proc. Step TASK ELEMENT 4 STANDARD Grade5.2.1 1. Calculate the sum of all excore readings divided by 4: (S = all detectors/4).
Sum of all excores reading divided by 4 calculated and entered on PO-3, Attachment 2, within +/- 1% (0.01) of the answer key.
S U Comment:
CRITICAL STEP
Proc. Step TASK ELEMENT 5 STANDARD Grade5.2.1 Calculate the Quadrant Tilt.
Using the formula T EX = [(S X - S)/S], calculate the tilt for each Quadrant, within
+/-1% (0.01) of the answer key.
S U Comment: Evaluator: Acceptance criteria is all four Quadrant Tilts should add up to zero (0) +/- 0.01 CRITICAL STEP
Proc. Step TASK ELEMENT 6 STANDARD Grade5.2.1 Have calculations verified.
Have another qualified individual verify the calculations.
S U Comment: Notes: Evaluator CUE: State to operator that someone else will verify the calculation.
JPM RO SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 6 of 9 July 2008 Proc. Step TASK ELEMENT 7 STANDARD Grade n/a Notify the CRS that Excore Quadrant Power Tilt has been completed per PO-3, .
Operator notifies CRS of completion of PO-3, Attachment 2, Excore Quadrant Power Tilt S U Comment:
END OF TASK
JPM RO SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 7 of 9 July 2008 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
- Plant was at full power.
- Incores #9 and #35 are inoperable.
- CRD #11 has dropped into the core.
INITIATING CUES:
- During performance of PO-3, Alternate Incore and Excore Applications, the Control Room Supervisor directs you to calculate Excore Quadrant Power Tilt utilizing Power Range NI Channels on Panel C-06.
JPM RO SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 8 of 9 July 2008 SIMULATOR OPERATOR INSTRUCTIONS SIMULATOR SET UP:
Simulator Setup Instructions:
- Full power IC
- Drop CRD #11 fully into the core with RD-11 (Final Value = 2) on PIDRD02
- When plant has stabilized, freeze the Simulator and SNAP. ***See NOTE #1 below.
- Use PO-3, Attachment 2 and record/calculate from the Upper and Lower NI Detector meters on EC-06) and use as answer key.
- Leave the Simulator in freeze during performance of this JPM to ensure that the conditions will not change
JPM RO SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 9 of 9 July 2008 Excore Lower Reading(%)
S AL , S BL , S CL , S DL Upper Reading(%)
S AU , S BU , S CU , S DU Lower + Upper S A , S B , S C , S D S = ( All Detectors)/4 = (S A + S B + S C + S D)/4 Excore Quadrant Tilt T EA , T EB , T EC , T ED 5 (CH A) S AL = 50.5 S AU = 50 S A = S AL + SAU 100.5
95.125 T EA = [(S A-S)/S] .0565 QUAD 1 6 (CH B) S BL = 40 S BU = 39 S B = S BL + SBU 79 T EB = [(S B-S)/S] -.1695 QUAD 3 7 (CH C) S CL = 50 S CU = 50 S C = S CL + S CU 100 T EC = [(S C-S)/S] .0512 QUAD 4 8 (CH D) S DL = 52 S DU = 49 S D = S DL + S DU 101 T ED = [(S D-S)/S] .0618 QUAD 2 NOTE: The four QPTs should sum to approximately zero.
Comments:
Performed By: ____Pat Person_________________________________ Date: _____Today__________ Time: _______Now______
Calculations Verified By: _____________________________________________________ Date: _______________
After calculations are verified, forward to Reactor Engineering Supervisor or designee for final review.
Reactor Engineering Supervisor or designee: _______________________________________ Date: _______________
ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY