| issue date = 01/14/2010 | | issue date = 01/14/2010 | ||
| title = IR 07200072-09-002 (DNMS) and 05000315-09-007, 05000316-09-007 05/05/2009 (On-site) & 09/30-12/15/2009 In-office Review & Telephone Exit) - D.C. Cook Nuclear Power Plant, Units 1 & 2 | | title = IR 07200072-09-002 (DNMS) and 05000315-09-007, 05000316-09-007 05/05/2009 (On-site) & 09/30-12/15/2009 In-office Review & Telephone Exit) - D.C. Cook Nuclear Power Plant, Units 1 & 2 | ||
| author name = Lipa C | | author name = Lipa C | ||
| author affiliation = NRC/RGN-III/DNMS | | author affiliation = NRC/RGN-III/DNMS | ||
| addressee name = Jensen J | | addressee name = Jensen J | ||
| Line 19: | Line 19: | ||
=Text= | =Text= | ||
{{#Wiki_filter | {{#Wiki_filter:January 14, 2010 | ||
Mr. Joseph Jensen Senior Vice President and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place | Mr. Joseph Jensen Senior Vice President and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place | ||
Bridgman, MI 49106 | Bridgman, MI 49106 SUBJECT: NRC INSPECTION REPORTS 072-00072/09-02(DNMS) AND 050-00315/09-07; 050-00316/09-07 - D.C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 | ||
SUBJECT: NRC INSPECTION REPORTS 072-00072/09-02(DNMS) AND 050-00315/09-07; 050-00316/09-07 - D.C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 | |||
==Dear Mr. Jensen:== | ==Dear Mr. Jensen:== | ||
| Line 41: | Line 38: | ||
Based on the results of this inspection, the NRC did not identify any violations. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection. | Based on the results of this inspection, the NRC did not identify any violations. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection. | ||
Sincerely,/RA/ Christine A. Lipa, Chief Materials Control, ISFSI, and Decommissioning Branch Division of Nuclear Materials Safety Docket Nos.: 72-072; 50-315; 50-316 License Nos.: DPR-58 and DPR-74 | Sincerely, | ||
/RA/ Christine A. Lipa, Chief Materials Control, ISFSI, and Decommissioning Branch Division of Nuclear Materials Safety Docket Nos.: 72-072; 50-315; 50-316 License Nos.: DPR-58 and DPR-74 | |||
Enclosure: | |||
NRC Inspection Reports 072-00072/09-02(DNMS), | NRC Inspection Reports 072-00072/09-02(DNMS), | ||
050-00315/09-07; 050-00316/09-07 cc w/encl: Distribution via ListServ | 050-00315/09-07; 050-00316/09-07 cc w/encl: Distribution via ListServ | ||
}} | }} | ||
Revision as of 13:39, 11 July 2019
| ML100151716 | |
| Person / Time | |
|---|---|
| Site: | Cook, 07200072 |
| Issue date: | 01/14/2010 |
| From: | Christine Lipa Division of Nuclear Materials Safety III |
| To: | Jensen J Indiana Michigan Power Co |
| References | |
| FOIA/PA-2010-0209 IR-09-002, IR-09-007 | |
| Download: ML100151716 (9) | |
Text
January 14, 2010
Mr. Joseph Jensen Senior Vice President and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place
Bridgman, MI 49106 SUBJECT: NRC INSPECTION REPORTS 072-00072/09-02(DNMS) AND 050-00315/09-07; 050-00316/09-07 - D.C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2
Dear Mr. Jensen:
On December 15, 2009, the U.S. Nuclear Regulatory Commission (NRC) completed inspection activities at your D.C. Cook Nuclear Power Plant, Units 1 and 2. The purpose of the inspection was to determine whether certain activities associated with the proposed dry cask storage pad were conducted safely and in accordance with the NRC requirements. At the conclusion of the on-site inspection on May 5, 2009, the inspectors discussed the preliminary inspection results with members of your staff. At the conclusion of further in-office review on December 15, 2009, the inspectors discussed the final results of the inspection with your staff on a teleconference.
The enclosed report presents the results of this inspection.
The inspection focused on certain activities associated with the proposed dry cask storage pad as they relate to safety and compliance with the Commission's rules and regulations.
Specifically, the inspectors evaluated the design of the Upper Parking Lot area radiological
survey plan and observed and evaluated the associated soil sampling and radiation survey activities. In addition, the inspectors performed confirmatory soil sampling with evaluation by the Oak Ridge Institute for Science and Education (ORISE). Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection consisted of a selective examination of procedures and representative records, and interviews with personnel.
Based on the results of this inspection, the NRC did not identify any violations. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection.
Sincerely,
/RA/ Christine A. Lipa, Chief Materials Control, ISFSI, and Decommissioning Branch Division of Nuclear Materials Safety Docket Nos.: 72-072; 50-315; 50-316 License Nos.: DPR-58 and DPR-74
Enclosure:
NRC Inspection Reports 072-00072/09-02(DNMS),
050-00315/09-07; 050-00316/09-07 cc w/encl: Distribution via ListServ