{{#Wiki_filter:1Whited, JeffreyFrom:Whited, JeffreySent:Friday, August 01, 2014 9:22 AMTo:talentz@firstenergycorp.comCc:phlashley@firstenergycorp.com
==Subject:==
DRAFT-RAIs to FENOC LICENSE RENEWAL REACTOR VESSEL INTERNALS AGING MANAGEMENT PROGRAM PLAN AT BVPS Attachments:DRAFT RVI AMP Plan RAIs.pdfMr. Lentz,  By letter dated January 27, 2014, (Agencywide Documents Access and Management System Accession No. ML14030A131) FirstEnergy Nuclear Operating Company (the licensee) submitted two reports for its License Renewal Reactor Vessel Internals Aging Management Program Plan at Beaver Valley Power Station, Units 1 and 2, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval.
The NRC staff has reviewed the information submitted by the licensee, and based on this review, determined additional information is required to complete the assessment of the submitted information. Please find attached a DRAFT Request For Additional Information. It is being sent to you to ensure that the questions are understandable, the regulatory basis for the questions is clear, and to determine if the information was previously docketed. Please respond to me by Monday, August 4, 2014, and notify me if you desire to hold a teleconference to discuss the questions. The NRC staff will request a response to the RAIs within 30 days of the formal NRC RAI transmittal letter.
Thank you, JeffreyWhitedProjectManagerBeaverValleyandSusquehannaPlantLicensingBranchI2DivisionofOperatingReactorLicensingOfficeofNuclearReactorRegulationU.S.NuclearRegulatoryCommission(301)4154090jeffrey.whited@nrc.gov}}

Revision as of 03:18, 27 June 2018

E-mail from J. Whited to T. Lentz Draft RAIs for License Renewal Aging Management Program Plan
ML14213A096
Person / Time
Site: Beaver Valley
Issue date: 08/01/2014
From: Whited J A
Plant Licensing Branch 1
To: Lentz T, Lentz T A
FirstEnergy Nuclear Operating Co
Whited J A
References
Download: ML14213A096 (1)


Text

1Whited, JeffreyFrom:Whited, JeffreySent:Friday, August 01, 2014 9:22 AMTo:talentz@firstenergycorp.comCc:phlashley@firstenergycorp.com

Subject:

DRAFT-RAIs to FENOC LICENSE RENEWAL REACTOR VESSEL INTERNALS AGING MANAGEMENT PROGRAM PLAN AT BVPS Attachments:DRAFT RVI AMP Plan RAIs.pdfMr. Lentz, By letter dated January 27, 2014, (Agencywide Documents Access and Management System Accession No. ML14030A131) FirstEnergy Nuclear Operating Company (the licensee) submitted two reports for its License Renewal Reactor Vessel Internals Aging Management Program Plan at Beaver Valley Power Station, Units 1 and 2, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval.

The NRC staff has reviewed the information submitted by the licensee, and based on this review, determined additional information is required to complete the assessment of the submitted information. Please find attached a DRAFT Request For Additional Information. It is being sent to you to ensure that the questions are understandable, the regulatory basis for the questions is clear, and to determine if the information was previously docketed. Please respond to me by Monday, August 4, 2014, and notify me if you desire to hold a teleconference to discuss the questions. The NRC staff will request a response to the RAIs within 30 days of the formal NRC RAI transmittal letter.

Thank you, JeffreyWhitedProjectManagerBeaverValleyandSusquehannaPlantLicensingBranchI2DivisionofOperatingReactorLicensingOfficeofNuclearReactorRegulationU.S.NuclearRegulatoryCommission(301)4154090jeffrey.whited@nrc.gov